Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: August 19, 2016; Updated Procurement Plan, April 2017 2. Date of General Procurement Notice: Dec 24, 2015 3. Period covered by this procurement plan: The procurement period of project covered from August 2016 – December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB Goods and Non-Consulting Above or equal to US$ All Services 2,000,000 2. NCB - Goods and Non-Consulting Below US$ 2,000,000 None Services 3. Shopping - Goods and Non-Consulting Below US$ 100,000 None Services 4. ICB (Works) Above US$ 10 million All 5. NCB (Works) Below US$ 10 million None 6. Shopping – (Works) Below US$ 100,000 None 2. Prequalification. Bidders for shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: N/A at this stage 5. Any Other Special Procurement Arrangements: 5 ICB works packages are eligible to be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 128.1 8 No Prior the ICB (Works) Summary of 1.8 1 No Prior the ICB (Goods) Summary of 19 3 No Post the NCB (Works) Summary of 4.8 1 No Prior the ICB (Non- Consultant Services) Summary of 0.27 1 No Post the Shopping (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) QCBS Above US$ 1,000,000 All 1. Competitive Methods (Firms) QCBS ≥ 300,000 - < 1,000,000 None 1. Competitive Methods (Firms) Below US$ 300,000 None CQS/FBS/LCS 2. Single Source (Firms) All All 3. Individual Above or equal to US$ All 200,000 4. Individual Below US$ 200,000 None 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. 3. Any Other Special Selection Arrangements: 5 QCBS works packages are eligible to be financed under retroactive financing 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 38.1 13 Prior number of contracts that will be let under QCBS Summary of 0.93 3 Prior CQS number of contracts that will be let under other methods Summary of 4.4 7 Prior number of contracts that will be let under ICS PROCUREMENT Angola : Second Water Sector Institutional Development Project PLAN General Information Country: Angola Bank’s Approval Date of the Original Procurement Plan: 2016-08-10 2019-01-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151224 GPN Date: 2017-08-07 Project Name: Second Water Sector Institutional Development Project Loan / Credit No: IBRD / 87020, / Executing Agency(ies): National Directorate of Water WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1W3/MALANJE/DNA/16 / Design and construction of Open - Single Stage - One IBRD / 87020 Prior Request for Bids 8,096,602.85 Signed 2016-09-07 2017-03-04 2017-05-27 2017-06-26 2017-02-27 2021-02-25 network and home International Envelope connections in Malanje 2W3/DUNDO/DNA/16 / Design and construction of Open - Single Stage - One IBRD / 87020 Prior Request for Bids 12,836,980.85 Signed 2016-09-27 2016-10-02 2017-02-27 2017-03-29 2017-05-04 2021-05-03 network and home International Envelope connections in Dundo 3W3/HUAMBO/DNA/16 / Design and construction of Open - Single Stage - One network and home IBRD / 87020 Prior Request for Bids 12,859,401.26 Signed 2016-10-12 2016-10-23 2017-02-19 2017-03-21 2017-05-10 2020-12-10 International Envelope connection for peri-urban areas in Huambo 4W3/LUENA/DNA/16 / Design and construction of Open - Single Stage - One IBRD / 87020 Prior Request for Bids 9,849,128.19 Signed 2016-10-15 2017-05-25 2017-09-20 2017-10-20 2017-05-15 2021-05-14 network and home International Envelope connections in Luena 5W3/UIGE/DNA/16 / Design and construction of network Open - Single Stage - One IBRD / 87020 Prior Request for Bids 10,368,081.40 Signed 2016-11-14 2016-11-19 2017-03-01 2017-03-31 2017-05-19 2021-05-18 and home connections in International Envelope Uige 6W3/NAMIBE/DNA/16 / Pending Design and construction of Open - Single Stage - One / Prior Request for Bids 0.00 Implementati 2016-11-29 2016-12-04 2017-03-19 2017-04-18 2017-05-25 2021-05-19 network and home International Envelope on connections in Namibe 7W3/KUITO/DNA/16 / Design and construction of Single Stage - One IBRD / 87020 Post Request for Bids Open - National 4,071,186.08 Signed 2017-01-16 2017-01-21 2017-03-21 2017-04-20 2017-05-31 2020-06-01 network and home Envelope connections in Kuito 9W3/NDALATANDO/DNA/16 / Design and construction for refurbishment of the WTW, Open - Single Stage - One / Prior Request for Bids 0.00 Canceled 2017-05-11 2017-05-16 2017-07-17 2017-08-16 2017-09-28 2020-09-28 construction of distribution International Envelope centers and 1.6 km trunk mains for Ndalatando 33W3-B/HUAMBO/DAS/17 / Construction of Network and IBRD / 87020 Prior Direct Selection Direct 5,827,776.58 Signed 2017-05-19 2017-05-24 2017-06-28 2019-02-18 Home Connections for the City of Huambo-Lot 2 Page 1 13W3/KUITO/DNA/17 / Supply and installation of IBRD / 87020 Post Direct Selection Direct 0.00 Canceled 2017-09-01 2017-09-06 2017-10-11 2018-04-09 valves and fittings for Kuito Water Supply System 12W3/NDALATANDO/DNA/17 / Supply and installation of Single Stage - One bulk meters and valves for IBRD / 87020 Post Request for Bids Open - National 0.00 Canceled 2017-09-12 2017-09-17 2017-10-29 2017-11-28 2018-01-02 2018-07-01 Envelope Ndalatando water supply system 6W3-R/DAS/17 / Repairs to Under the Network and Home Single Stage - One IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Connections in the City of Envelope on Ndalatando 44W3/LUBANGO/DNA/18 / Pending Design and Construction of Single Stage - One IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2019-05-28 2019-06-02 2019-07-14 2019-08-13 2019-09-17 2021-03-10 Network and Household Envelope on Connections in Lubango 45W3/MALANJE/DNA/18 / Pending Single Stage - One Repair works to connections IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2018-10-31 2018-11-05 2019-01-14 2019-02-13 2019-03-20 2020-03-14 Envelope in Malanje on 46W3/CUITO/DNA/18 / Pending Design and Construction of Single Stage - One IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2018-10-15 2018-10-20 2018-12-01 2018-12-31 2019-02-04 2020-07-28 Network and Household Envelope on Connections in Cuito-Phase 2 8W3/NDALATANDO/DNA/16 / Design and construction of a new water source, WTW, Open - Single Stage - One pumping station, raw water IBRD / 87020 Prior Request for Bids 0.00 Canceled 2018-05-28 2018-08-09 2018-08-12 2018-06-15 2018-09-03 2018-10-03 2018-11-26 2023-06-26 International Envelope pipeline, distribution centers and trunk mains for Ndalatando 9W3/LUBANGO/DNA/18 / Pending Construction of Water Single Stage - One IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2018-09-06 2018-09-11 2018-10-23 2018-11-22 2018-12-27 2019-06-25 Production Boreholes in Envelope on Lubango 11W3/LUBANGO/DNA/16 / Pending Single Stage - One Design and construction of IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2019-09-26 2019-10-01 2019-11-12 2019-12-12 2020-01-16 2021-01-15 Envelope boreholes in Lubango on 8W3A/NDALATANDO/DNA/18 / Design and construction of a new water source, WTW, Request for Open - Under pumping station, raw water IBRD / 87020 Prior Multi Stage 0.00 2018-07-10 2018-10-05 2018-10-05 2018-07-25 2018-12-24 2019-04-22 2019-05-27 2020-11-17 Proposals International Review pipeline, distribution centers and trunk mains for Ndalatando 10W3/LUBANGO/DNA/16 / Pending Open - Single Stage - One Design and Construction of IBRD / 87020 Prior Request for Bids 0.00 Implementati 2018-12-12 2018-12-17 2019-03-07 2019-04-06 2019-05-11 2021-04-30 International Envelope reservoirs in Lubango on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 1G4/DNA/16 / Education Pending Single Stage - One and laboratory equipment for / Prior Request for Bids Open - National 0.00 Implementati 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Envelope Onga Zanga training center on 4G4/DNA/16 / Implementation of a Request for Single Stage - One Financial Management / Post Limited 0.00 Canceled 2017-08-08 2017-10-03 2018-04-01 Quotations Envelope System (Primavera software) 47G1/CITIES/DNA/18 / Under Single Stage - One Water meters, pipes valves IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2018-07-20 2018-07-25 2018-09-05 2018-10-05 2018-11-09 2019-05-08 Envelope and fittings for six cities on 48/G1/CITIES/DNA/18 / Pending Single Stage - One Workshop and maintenance IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2018-06-20 2018-06-25 2018-08-06 2018-09-05 2018-10-10 2019-04-08 Envelope equipment on 53G1/CITIES/DNA/18 / Under Workstations and printers Single Stage - One IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2018-05-30 2018-06-04 2018-07-19 2018-08-18 2018-09-22 2019-03-21 for Utilities in Huila, Envelope on Malanje and Cuanza Norte 2G4/DNA/16 / Computers Pending Request for Single Stage - One and IT equipment for the IBRD / 87020 Post Limited 0.00 Implementati 2019-02-17 2019-04-14 2019-10-11 Quotations Envelope Project on Pending 3G4/DNA/16 / Furniture Request for Single Stage - One IBRD / 87020 Post Limited 0.00 Implementati 2019-03-05 2019-04-30 2019-10-27 shopping Quotations Envelope on 70CS2/INRH/18 / Purchase and installation of 15 remote Pending satellite communication Single Stage - One IBRD / 87020 Post Request for Bids Open - National 0.00 Implementati 2019-05-07 2019-05-12 2019-06-23 2019-07-23 2019-08-27 2020-02-23 equipment and Envelope on meteorological sensors for hydrometric stations 71G3/UIGE/DNA/18 / Power Pending Request for Single Stage - One Transformer for Uige Water IBRD / 87020 Post Limited 0.00 Implementati 2019-01-28 2019-03-25 2019-09-21 Quotations Envelope Supply System on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1NC1/LUENA/DNA/16 / Pending Open - Single Stage - Two Management Contract for / Prior Request for Bids 0.00 Implementati 2017-08-23 2017-08-28 2017-10-30 2018-01-12 2018-02-16 2021-03-16 International Envelope Luena on 54NC1/CUITO/DNA/18 / Pending Open - Single Stage - Two Management Support IBRD / 87020 Prior Request for Bids 0.00 Implementati 2018-05-30 2018-08-15 2018-08-15 2018-06-04 2018-10-24 2019-01-06 2019-02-10 2022-02-09 International Envelope Services Contract for Cuito on 55NC1/HUAMBO/DNA/18 / Pending Management Support Open - Single Stage - Two IBRD / 87020 Prior Request for Bids 0.00 Implementati 2018-05-31 2018-08-16 2018-08-16 2018-06-05 2018-10-25 2019-01-07 2019-02-11 2022-02-10 Services Contract for International Envelope on Huambo 56NC1/UIGE/DNA/18 / Under Open - Single Stage - Two Management Support IBRD / 87020 Prior Request for Bids 0.00 Implementati 2018-06-01 2018-08-17 2018-08-17 2018-06-06 2018-10-26 2019-01-08 2019-02-12 2022-02-11 International Envelope Services Contract for Uige on Page 3 57NC1/MALANJE/DNA/18 / Pending Management Support Open - Single Stage - Two IBRD / 87020 Prior Request for Bids 0.00 Implementati 2018-06-04 2018-08-20 2018-08-20 2018-06-09 2018-10-29 2019-01-11 2019-02-15 2022-02-14 Services Contract for International Envelope on Malanje 58NC1/NDALATANDO/DNA/1 Pending 8 / Management Support Open - Single Stage - Two IBRD / 87020 Prior Request for Bids 0.00 Implementati 2018-06-05 2018-08-21 2018-08-21 2018-06-10 2018-10-30 2019-01-12 2019-02-16 2022-02-15 Services Contract for International Envelope on Ndalatando 11CS1/DAS/18 / Operation and Management of Kuito IBRD / 87020 Prior Direct Selection Direct 874,978.20 Signed 2018-06-06 2018-06-11 2018-07-01 2018-12-28 and Kunje Water Supply System 93CS1/DAS/18 / Operation and Management of Huambo IBRD / 87020 Prior Direct Selection Direct 1,470,480.00 Signed 2018-06-06 2018-06-11 2018-07-01 2018-12-28 Water Supply System 20CS1/DAS/18 / Operation and Management of Malanje IBRD / 87020 Prior Direct Selection Direct 995,502.26 Signed 2018-06-06 2018-06-11 2018-07-01 2018-12-28 Water Supply System 94CS1/DAS/18 / Operation and Management of Uige IBRD / 87020 Prior Direct Selection Direct 894,007.00 Signed 2018-06-06 2018-06-11 2018-07-01 2018-12-28 Water Supply System 59CS1/DAS/15 / Operation and Management of Lubango IBRD / 87020 Prior Direct Selection Direct 1,826,233.00 Signed 2018-06-06 2018-06-11 2018-07-01 2018-12-28 Water Supply System 95CS1/DAS/18 / Operation and Management of IBRD / 87020 Post Direct Selection Direct 774,481.75 Signed 2018-08-20 2018-08-25 2018-09-14 2019-03-13 N´dalatando Water Supply System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1CS3/DNA/16 / Design checking and works Quality And Cost- Open - Supervision of Network and IBRD / 87020 Prior 1,934,914.78 Signed 2016-08-16 2016-09-06 2016-10-20 2016-11-17 2016-12-17 2017-01-21 2017-02-25 2020-09-25 Based Selection International Home Connections for Peirurban areas of Malanje 2CS3/DNA/16 / Design checking and works Quality And Cost- Open - IBRD / 87020 Prior 2,328,726.00 Signed 2016-08-16 2016-10-03 2016-11-10 2017-01-24 2017-02-23 2017-03-30 2017-05-04 2021-06-04 Supervision of Network and Based Selection International Home Connections for Dundo 3CS3/DNA/16 / Design checking and works Quality And Cost- Open - Supervision of Network and IBRD / 87020 Prior 2,074,255.00 Signed 2016-08-17 2016-10-04 2016-11-10 2017-01-30 2017-03-01 2017-04-05 2017-05-10 2020-12-10 Based Selection International Home Connections for Huambo (1st phase) 4CS3/DNA/16 / Design checking and works Quality And Cost- Open - IBRD / 87020 Prior 1,680,971.28 Signed 2016-08-18 2016-10-05 2016-11-18 2017-02-02 2017-03-04 2017-04-08 2017-05-13 2020-12-14 Supervision of Network and Based Selection International Home Connections for Luena Page 4 5CS3/DNA/16 / Design checking and works Quality And Cost- Open - IBRD / 87020 Prior 2,194,207.00 Signed 2016-08-19 2016-10-06 2016-11-19 2017-02-08 2017-03-10 2017-04-14 2017-05-19 2020-12-21 Supervision of Network and Based Selection International Home Connections for Uige 6CS3/DNA/16 / Design checking and works Quality And Cost- Open - Supervision of Network and IBRD / 87020 Prior 2,060,259.00 Signed 2016-08-20 2016-10-07 2016-11-20 2017-02-14 2017-03-16 2017-04-20 2017-05-25 2020-12-25 Based Selection International Home Connections for Namibe 7CS3/DNA/16 / Design checking and works Quality And Cost- Open - Supervision of Network and IBRD / 87020 Prior 994,220.00 Signed 2016-08-21 2016-10-08 2016-11-21 2017-02-20 2017-03-22 2017-04-26 2017-05-31 2020-12-28 Based Selection International Home Connections for Kuito (1st phase) 8CS3/NDALATANDO/DNA/16 / Design checking and works supervision for the Quality And Cost- Open - Under / Prior 0.00 2017-02-01 2017-02-22 2017-04-07 2017-06-05 2017-07-05 2017-08-09 2017-09-13 2020-09-14 construction of a new water Based Selection International Implementation source and pipeline in Ndalatando 10CS3/LUBANGO/DNA/16 / Design checking and works Quality And Cost- Open - Under IBRD / 87020 Prior 0.00 2017-03-03 2017-05-18 2017-07-01 2017-08-28 2017-09-27 2017-11-01 2017-12-06 2020-12-07 Supervision of Construction Based Selection International Implementation of reservoirs in Lubango 12CS2/INRH/DNA/16 / TA to develop Integrated Basin Quality And Cost- Open - / Prior 0.00 Canceled 2017-09-01 2017-11-03 2017-12-17 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2019-06-13 Management Plan for River Based Selection International Basins in Benguela 13CS2/INRH/DNA/16 / TA to develop Integrated Basin Quality And Cost- Open - / Prior 0.00 Canceled 2017-02-03 2017-04-24 2017-06-07 2017-08-06 2017-09-05 2017-10-10 2017-11-14 2018-11-14 Management Plan for Keve Based Selection International e Longa Basins 14CS4/NAMIBE/DNA/16 / Quality And Cost- Open - Salt water intrusion study / Post 0.00 Canceled 2017-06-01 2017-08-01 2017-09-14 2017-11-12 2017-12-12 2018-01-16 2018-09-20 2019-09-20 Based Selection International at Namibe 15CS1/IRSEA/DNA/16 / TA Quality And Cost- Open - Under Water and Electricity / Prior 0.00 2017-02-08 2017-04-27 2017-06-10 2017-08-09 2017-09-08 2017-10-13 2017-11-17 2020-12-17 Based Selection International Implementation Regulator (IRSEA) 16CS1/DNA/17 / External Least Cost Open - IBRD / 87020 Post 64,705.88 Signed 2017-04-17 2017-05-08 2017-05-10 2017-06-07 2017-07-07 2017-08-11 2017-09-15 2021-09-14 Audit Selection International 35CS4/DNA/17 / Project Least Cost Open - IBRD / 87020 Post 171,122.99 Signed 2017-10-18 2017-11-08 2017-12-22 2018-01-19 2018-02-18 2018-03-25 2018-04-29 2021-04-13 Internal Audit Selection International 39CS1/DNA/17 / AUDIT OF FINANCIAL STATEMENTS Least Cost Open - FOR SIX BENEFICIARY IBRD / 87020 Post 197,326.20 Signed 2018-01-24 2018-02-14 2018-04-06 2018-05-04 2018-06-03 2018-07-08 2018-08-12 2021-09-10 Selection International WATER SUPPLY AND SANITATION UTILITIES 42CS2/TA/INRH/17 / Technical Assistance to Quality And Cost- Open - Under IBRD / 87020 Prior 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-01 2018-07-31 2018-09-04 2018-10-09 2021-10-08 INRH (National Water Based Selection International Implementation Resources Institute) 52CS3/KUITO/DNA/18 / Design checking and works Quality And Cost- Open - Pending Supervision of Network and IBRD / 87020 Prior 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-12-30 Based Selection International Implementation Home Connections for Kuito (2nd phase) Page 5 50CS3/LUBANGO/DNA/18 / Design checking and works Quality And Cost- Open - Pending Supervision of Network and IBRD / 87020 Prior 0.00 2018-06-20 2018-07-20 2018-08-18 2018-09-15 2018-10-15 2018-11-19 2018-12-24 2020-06-16 Based Selection International Implementation Home Connections for Lubango (1st phase) 49CS3/UIGE/DNA/18 / Environmental and Social Quality And Cost- Under IBRD / 87020 Post Open - National 0.00 2018-07-03 2018-07-24 2018-09-06 2018-10-04 2018-11-03 2018-12-08 2019-01-12 2020-01-12 Impact Assessment for Uige Based Selection Implementation Water Supply System 51CS3/MALANJE/DNA/18 / Design Checking and Quality And Cost- Open - Pending Supervision of Repairs to IBRD / 87020 Prior 0.00 2018-07-27 2018-08-17 2018-09-30 2018-10-28 2018-11-27 2019-01-01 2019-02-05 2020-02-05 Based Selection International Implementation Household Connections at Malanje 59CS3/LUBANGO/DNA/18 / Hydrogeological survey and Quality And Cost- Open - Pending prospection of new IBRD / 87020 Post 0.00 2018-05-24 2018-06-14 2018-07-28 2018-08-25 2018-09-24 2018-10-29 2018-12-03 2019-12-03 Based Selection International Implementation production boreholes in Lubango 60CS1/DNA/18 / Review of the Legal and Institutional Quality And Cost- Open - Under IBRD / 87020 Prior 0.00 2018-05-16 2018-06-06 2018-07-20 2018-08-17 2018-09-16 2018-10-21 2018-11-25 2019-08-22 Frameworks of the Angola Based Selection International Implementation Water Sector 64CS1/IRSEA/18 / Quality And Cost- Under Consultancy for the baseline IBRD / 87020 Post Open - National 0.00 2019-05-30 2019-06-20 2019-08-03 2019-08-31 2019-09-30 2019-11-04 2019-12-09 2020-06-06 Based Selection Implementation for the sector 65CS1/IRSEA/18 / Quality And Cost- Open - Under Consultancy for beneficiary IBRD / 87020 Post 0.00 2019-04-25 2019-05-16 2019-06-29 2019-07-27 2019-08-26 2019-09-30 2019-11-04 2020-11-03 Based Selection International Implementation assessment 66CS1/IRSEA/18 / Consultancy for the design Quality And Cost- and implementation of an IBRD / 87020 Post Open - National 0.00 Under Review 2019-04-17 2019-05-08 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-04-24 Based Selection information management system 67CS2/INRH/18 / Development of National Quality And Cost- Pending IBRD / 87020 Post Open - National 0.00 2019-05-29 2019-06-19 2019-08-02 2019-08-30 2019-09-29 2019-11-03 2019-12-08 2020-06-05 Water Resources Information Based Selection Implementation and Use System 68CS2/INRH/18 / Quality And Cost- Open - Pending Development and Application IBRD / 87020 Prior 0.00 2019-05-29 2019-06-19 2019-08-02 2019-08-30 2019-09-29 2019-11-03 2019-12-08 2020-12-07 Based Selection International Implementation of Water Rights 9CS3/NDALATANDO/DNA/16 / Design checking and works supervision for the Quality And Cost- Open - refurbishment of the / Prior 0.00 Canceled 2017-02-16 2017-03-09 2017-04-22 2017-06-20 2017-07-20 2017-08-24 2017-09-28 2020-09-28 Based Selection International treatment plant and construction of distribution centers in Ndalatando 72CS4/UCP/18 / Support to Least Cost Under the recruitment process of IBRD / 87020 Post Open - National 0.00 2018-09-27 2018-10-18 2018-12-01 2018-12-29 2019-01-28 2019-03-04 2019-04-08 2019-10-05 Selection Implementation young professionals 69CS2/INRH/18 / Survey of water users and assessment Quality And Cost- Open - Pending IBRD / 87020 Prior 0.00 2019-04-25 2019-05-16 2019-06-29 2019-07-27 2019-08-26 2019-09-30 2019-11-04 2020-11-03 of volume of water demand Based Selection International Implementation in Cuanza river basin Page 6 INDIVIDUAL CONSULTANTS Page 7