Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan February 7, 2014. Revision of the Procurement Plan, February 8, 2017 2. Date of General Procurement Notice: Updated April 20, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year June 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 5 million All 2. NCB (Goods) Above US$ 4 million All 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 15 million All 5. ICB and LIB (Non-Consultant Services) Above US$ 5 million All 6. NCB (Non-Consultant Services) Above US$ 4 million All 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan IBRD 8353-BR was approved on January 8, 2014 and revised on December 23, 2015 by the Government of the State of Espirito Santo. Any Other Special Procurement Arrangements: Retroactive Financing - an aggregate amount not to exceed $20,000,000 equivalent may be made for payments made prior to this date but on or after October 1, 2013, for Eligible Expenditures. 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness June 5, 2017 Goods and Works Estimated Review Cost by Bank Comments US$ Description of Assignment million (Prior / Post) SEAMA-1F2 / Aquisição de Equipamentos para o Sistema de Informações Ambiental 4.9 Prior Single CESAN-2B5 / Works at Vila Velha and Cariacica 164 Prior Stage III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2 million All 2. Single Source (Firms) Above US$ 2 million All 3. Individual Above US$ 0.4 million All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $1.5 million equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule Consultant Services Estimated Review Cost by Bank Comments US$ Description of Assignment million (Prior / Post) SEAMA-1F1 / Study and Projects for the development 2.34 Prior of the Environmental Management System. QCBS CESAN-2B1 / Supervision of works and execution of socio-environmental of the sewage systems in nine 2.8 Prior municipalities of the countryside of the State of QCBS - Espirito Santo Initiated CESAN-4A1 / Management of the RMGV Works 18 Prior QCBS - Supervision Program Initiated ARSP-4B1 / Revision and Tariff Restructuring of the 1.8 Prior Sanitation Services and Regulatory Accounting QCBS June 5, 2017 June 5, 2017 PROCUREMENT Brazil : BR Espirito Santo Integrated Sustainable Water Management Project PLAN General Information Country: Brazil Banks Approval Date of the Original Procurement Plan: 2017-02-08 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-11-09 Project ID: P130682 GPN Date: 2017-04-20 Project Name: BR Espirito Santo Integrated Sustainable Water Management Project Loan / Credit No: IBRD / 83530 Executing Agency(ies): Executive Secretariat of the State of Espirito Santo WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Efficient Water Supply Services CESAN-2B6 / Contratacao Single Stage - One IBRD / 83530 and Increased Access to Prior Request for Bids Open - International 0.00 Canceled 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Obras de Cariacica Envelope Sanitation CESAN-2B3 / Execucao de obras e servicos de Implantacao, Reabilitacao e Ampliacao de Efficient Water Supply Services Single Stage - One Under Sistemas de Esgotamento IBRD / 83530 and Increased Access to Post Request for Bids Open - National 6,059,394.19 2017-04-28 2017-09-11 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2018-02-14 Envelope Implementation Sanitario de Conceicao do Sanitation Castelo, Divino de Sao Lourenco e Marechal Floriano SEAMA-3B6 / Adequacao e recuperacao de Estradas vicinais Watershed Management and Single Stage - One Pending IBRD / 83530 Post Request for Bids Open - National 0.00 2017-07-31 2017-08-05 2017-09-16 2017-10-16 2017-11-20 2018-05-19 de terra, com confeccao de Restoration of Forest Cover Envelope Implementation caixas secas CESAN-2B4 / Execucao de obras e servicos de Implantacao, Efficient Water Supply Services Reabilitacao e Ampliacao de Single Stage - One Under IBRD / 83530 and Increased Access to Post Request for Bids Open - National 0.00 2017-06-10 2017-06-15 2017-07-27 2017-08-26 2017-09-30 2018-03-29 Sistemas de Esgotamento Envelope Implementation Sanitation Sanitario de Santa Leopoldina e Santa Maria de Jetiba SEAMA-3B2 / Construcao de Watershed Management and Single Stage - One Pending equipamentos sociais a margem IBRD / 83530 Post Request for Bids Open - National 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Restoration of Forest Cover Envelope Implementation do Mangarai CESAN-3B2 / Construcao de Watershed Management and Single Stage - One equipamentos sociais a margem IBRD / 83530 Post Request for Bids Open - National 0.00 Canceled 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Restoration of Forest Cover Envelope do Mangarai CESAN-3B6 / Adequacao e recuperacao de Estradas Watershed Management and Single Stage - One IBRD / 83530 Post Request for Bids Open - National 0.00 Canceled 2017-03-15 2017-03-20 2017-05-01 2017-05-31 2017-07-05 2018-01-01 vicinais de terra, com confeccao Restoration of Forest Cover Envelope de caixas secas Efficient Water Supply Services CESAN-2B5 / Contratacao Single Stage - One IBRD / 83530 and Increased Access to Prior Request for Bids Open - International 0.00 Canceled 2017-05-30 2017-06-04 2017-07-16 2017-08-15 2017-09-19 2018-03-18 Obras de Vila Velha e Cariacica Envelope Sanitation Efficient Water Supply Services CESAN-2B7 / DBO de Vila Request for Single Stage - One Pending IBRD / 83530 and Increased Access to Prior Open - International Y 0.00 2017-12-18 2018-04-05 2018-04-05 2018-02-07 2018-05-20 2018-06-04 2018-07-09 2024-06-07 Velha. Proposals Envelope Implementation Sanitation Efficient Water Supply Services CESAN-2B8 / Contratacao de Single Stage - One Pending IBRD / 83530 and Increased Access to Prior Request for Bids Open - International 0.00 2018-01-15 2018-01-20 2018-03-03 2018-04-02 2018-05-07 2021-04-21 Obras Cariacica Envelope Implementation Sanitation GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CESAN-2A2 / Reforma ou substituicao das bombas de grande porte da CESAN, com Efficient Water Supply Services Single Stage - One Pending intuito de recuperacao do IBRD / 83530 and Increased Access to Post Request for Bids Open - National 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 Envelope Implementation rendimento eletrico dos Sanitation equipamentos (Item 6 Efic Energetica) AGERH-1C2 / Aquisicao de 03 medidores de vazao para conduto forcado, 01 medidor de vazao para pequenas Integrated Water Management Single Stage - One Pending IBRD / 83530 Post Request for Bids Open - National 0.00 2017-05-22 2017-05-27 2017-07-08 2017-08-07 2017-09-11 2018-03-10 profundidades, 01 medidor de and Disaster Risk Management Envelope Implementation vazao para medias e grandes profundidades e 04 sondas multiparametros DEFESA CIVIL-1H31 / Aquisicao de mobiliario para Integrated Water Management Request for Single Stage - One Under Coordenadorias Regionais e IBRD / 83530 Post Open - National 0.00 2017-07-20 2017-09-14 2018-03-13 and Disaster Risk Management Quotations Envelope Implementation Municipais de Protecao e Defesa Civil SEAMA-1F6 / Aquisicao de Integrated Water Management Request for Single Stage - One Pending Software para o Sistema de IBRD / 83530 Post Open - National 0.00 2017-07-09 2017-09-03 2018-03-02 and Disaster Risk Management Quotations Envelope Implementation Informacoes Ambiental SEAMA-1F7 / Aquisicao de Integrated Water Management Single Stage - One Pending Ó ica para o Sistema de Fibra t IBRD / 83530 Post Request for Bids Open - National 0.00 2017-07-04 2017-07-09 2017-08-20 2017-09-19 2017-10-24 2018-04-22 and Disaster Risk Management Envelope Implementation Informacoes Ambiental Page 1 CESAN-2A3 / Aquisicao de Motores Eletricos de Alta Efficient Water Supply Services Single Stage - One Eficiencia para substituicao de IBRD / 83530 and Increased Access to Post Request for Bids Open - National 0.00 Canceled 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 Envelope equipamentos diversos na Sanitation CESAN (Item 8 Efic Energetica) CESAN-2A6 / Aquisicao de Motores Eletricos de Alta Efficient Water Supply Services Pending Eficiencia para substituicao de IBRD / 83530 and Increased Access to Post E-Auctions Open 0.00 2017-11-28 2017-12-17 2018-01-21 2018-07-20 Implementation equipamentos diversos na Sanitation CESAN (Item 8 Efic Energética) DEFESA CIVIL-1H32 / Integrated Water Management Single Stage - One Aquisicao de equipamentos de IBRD / 83530 Post Request for Bids Open - National 0.00 Canceled 2017-04-10 2017-09-04 2017-04-15 2017-05-27 2017-06-26 2017-07-31 2018-01-27 and Disaster Risk Management Envelope comunicacao e outros DEFESA CIVIL-1H321 / Aquisicao de veiculos para Integrated Water Management Pending IBRD / 83530 Post E-Auctions Open 0.00 2017-11-20 2017-12-09 2018-01-13 2018-07-12 combate a incendio florestal e and Disaster Risk Management Implementation outros DEFESA CIVIL-1H322 / Integrated Water Management Pending Aquisicao de empilhadeira e mini IBRD / 83530 Post E-Auctions Open 0.00 2017-11-23 2017-12-18 2018-01-22 2018-07-21 and Disaster Risk Management Implementation escavadeira DEFESA CIVIL-1H323 / Aquisicao de equipamentos para Integrated Water Management Pending IBRD / 83530 Post E-Auctions Open 0.00 2017-12-15 2018-01-03 2018-02-07 2018-08-06 salvamento em enchentes e and Disaster Risk Management Implementation outros SEAMA-1F2 / Aquisicao de Integrated Water Management Single Stage - One Hardware para o Sistema de IBRD / 83530 Post Request for Bids Open - National 0.00 Canceled 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 and Disaster Risk Management Envelope Informacoes Ambiental SEAMA-1F8 / Aquisicao de Integrated Water Management Pending Hardware para o Sistema de IBRD / 83530 Post E-Auctions Open 0.00 2017-11-28 2017-12-17 2018-01-21 2018-07-20 and Disaster Risk Management Implementation Informacoes Ambiental DEFESA CIVIL-1H5 / Aquisicao Integrated Water Management Single Stage - One de estacoes moveis de IBRD / 83530 Post Request for Bids Open - National 0.00 Canceled 2017-05-20 2017-09-04 2017-05-25 2017-07-06 2017-08-05 2017-09-09 2018-03-08 and Disaster Risk Management Envelope tratamento de agua DEFESA CIVIL-1H6 / Aquisicao Integrated Water Management Pending de estacoes moveis de IBRD / 83530 Post E-Auctions Open 0.00 2017-12-05 2017-12-24 2018-01-28 2018-07-27 and Disaster Risk Management Implementation tratamento de agua NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SEAMA-3A3 / Assistencia Watershed Management and Single Stage - One Pending IBRD / 83530 Post Request for Bids Open - International 0.00 2017-09-20 2017-09-25 2017-11-06 2017-12-06 2018-01-10 2018-07-09 Tecnica Rural - ATER Restoration of Forest Cover Envelope Implementation SEAMA-1F3 / Capacitacao em Integrated Water Management Single Stage - One Pending Gestao Ambiental e de Recursos IBRD / 83530 Post Request for Bids Open - National 0.00 2018-08-17 2018-08-22 2018-10-03 2018-11-02 2018-12-07 2019-06-05 and Disaster Risk Management Envelope Implementation Hidricos DEFESA CIVIL-1H21 / Integrated Water Management Request for Single Stage - One Pending IBRD / 83530 Post Open - National 0.00 2018-08-20 2018-10-15 2019-04-13 Aquisicao de passagens aereas and Disaster Risk Management Quotations Envelope Implementation SEAMA-3A2 / Elaboracao e Implementacao do Plano de Watershed Management and Single Stage - One Pending IBRD / 83530 Post Request for Bids Open - National 0.00 2017-07-17 2017-07-22 2017-09-02 2017-10-02 2017-11-06 2018-05-05 Comunicacao Social do Restoration of Forest Cover Envelope Implementation Reflorestar SEAMA-1D2 / Servicos de levantamento de batimetria e Integrated Water Management Single Stage - One Pending IBRD / 83530 Post Request for Bids Open - National 0.00 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-04-23 medicao de ondas e correntes da and Disaster Risk Management Envelope Implementation Costa do Espirito Santo DEFESA CIVIL-1H22 / Integrated Water Management Pending IBRD / 83530 Post Direct Selection Direct 0.00 2018-08-06 2018-08-11 2018-09-15 2019-03-14 Inscricoes and Disaster Risk Management Implementation CESAN-3B1 / Elaboracao e Implementacao do Plano de Watershed Management and Single Stage - One IBRD / 83530 Post Request for Bids Open - National 0.00 Canceled 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Comunicacao Social do Restoration of Forest Cover Envelope Mangarai Project Management, CESAN-4C5 / Auditoria Externa Request for Single Stage - One Pending IBRD / 83530 Supervision and Institutional Post Open - National 0.00 2017-11-20 2018-01-15 2020-12-30 do Projeto Quotations Envelope Implementation Strengthening Project Management, CESAN-4C2 / Contratacao de Single Stage - One IBRD / 83530 Supervision and Institutional Post Request for Bids Open - National 0.00 Canceled 2017-02-10 2017-02-15 2017-03-29 2017-04-28 2017-06-02 2017-11-29 modernizacao do Sistema SAFFI Envelope Strengthening Project Management, CESAN-4C6 / Contratacao de Pending IBRD / 83530 Supervision and Institutional Post E-Auctions Open 0.00 2017-12-10 2017-12-29 2018-02-02 2020-01-23 modernizacao do Sistema SAFFI Implementation Strengthening SEAMA-3B7 / Assistencia Watershed Management and Single Stage - One IBRD / 83530 Post Request for Bids Open - International 0.00 Canceled 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 Tecnica Rural - ATER Mangarai. Restoration of Forest Cover Envelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 ARSP-4B1 / Revisao e Project Management, Reestruturacao Tarifaria dos Quality And Cost- Under IBRD / 83530 Supervision and Institutional Prior Open - International 0.00 2017-04-10 2017-05-01 2017-06-16 2017-06-14 2017-11-05 2017-07-12 2017-08-11 2017-09-15 2017-10-20 2018-10-20 Servicos de Saneamento e Based Selection Implementation Strengthening Contabilidade Regulatoria SEAMA-1F1 / Estudos e Projetos para o desenvolvimento Integrated Water Management Quality And Cost- Pending IBRD / 83530 Prior Open - International 0.00 2017-09-15 2017-10-06 2017-11-19 2017-12-17 2018-01-16 2018-02-20 2018-03-27 2019-03-27 de Sistema de Informacao de and Disaster Risk Management Based Selection Implementation Gestao Ambiental SEDURB-1G1 / Elaboracao de Estudos e Desenvolvimento Integrated Water Management Quality And Cost- Pending IBRD / 83530 Post Open - International 0.00 2017-09-20 2017-10-11 2017-11-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2019-04-01 Plano Diretor de Aguas Urbanas and Disaster Risk Management Based Selection Implementation da RMGV - Fase 1 CESAN-2B1 / Supervisao de obras e execucao de Servicos Efficient Water Supply Services Socioambientais dos Sistemas Quality And Cost- Under IBRD / 83530 and Increased Access to Prior Open - International 0.00 2017-05-22 2017-09-13 2017-06-12 2017-07-26 2017-08-23 2017-09-22 2017-10-27 2017-12-01 2018-12-01 de Esgotamento Sanitario em Based Selection Implementation Sanitation 09 (nove) municipios do interior do Espirito Santo CESAN-2A1 / 1a. Etapa do Plano Diretor de Conservacao de Efficient Water Supply Services Energia Eletrica para Sistemas Quality And Cost- Pending IBRD / 83530 and Increased Access to Post Open - National 0.00 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 de Coleta e Tratamento de Based Selection Implementation Sanitation Esgoto da CESAN no Espirito Santo (Item 10 Efic Energetica) CESAN-4A1 / Gerenciamento Project Management, Quality And Cost- Under do Programa e Supervisao de IBRD / 83530 Supervision and Institutional Prior Open - International 0.00 2017-04-15 2017-06-23 2017-05-06 2017-06-19 2017-10-16 2017-07-17 2017-08-16 2017-09-20 2017-10-25 2018-10-25 Based Selection Implementation Obras RMGV Strengthening SEAMA-3A1 / Contratacao de Servicos de Aperfeicoamento do Sistema de Gestao Tecnica e Watershed Management and Quality And Cost- Pending IBRD / 83530 Post Open - National 0.00 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-12-25 Financeira do Programa Restoration of Forest Cover Based Selection Implementation Reflorestar - PORTAL REFLORESTAR SEAMA-1D1 / Determinacao da Integrated Water Management Quality And Cost- Pending variacao temporal da linha de IBRD / 83530 Post Open - National 0.00 2017-06-16 2017-07-07 2017-08-20 2017-09-17 2017-10-17 2017-11-21 2017-12-26 2018-12-26 and Disaster Risk Management Based Selection Implementation costa do Espirito Santo AGERH-1C1 / Projeto executivo de microlocalizacao (Identificacao dos pontos e Consultant Integrated Water Management Under referenciais de niveis), Teste de IBRD / 83530 Post Qualification Open - National 0.00 2017-06-05 2017-08-26 2017-10-09 2017-11-08 2017-12-13 2018-06-11 and Disaster Risk Management Implementation Intensidade de sinais GSM, Selection anuencia de instalacao e croqui de estrutura de fixacao (50 ptos) SEAMA-1F5 / Modelagem Integrated Water Management Quality And Cost- Pending Institucional da Agencia IBRD / 83530 Post Open - National 0.00 2017-09-20 2017-10-11 2017-11-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2019-04-01 and Disaster Risk Management Based Selection Implementation Ambiental SEAMA-3B4 / Avaliacao Socioambiental da Bacia e Watershed Management and Quality And Cost- Pending IBRD / 83530 Post Open - National 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 Monitoramento de Impacto de Restoration of Forest Cover Based Selection Implementation Resultados SEAMA-3B5 / Elaboracao de Watershed Management and Quality And Cost- Pending Diagnostico Socioeconomico de IBRD / 83530 Post Open - National 0.00 2017-09-15 2017-10-06 2017-11-19 2017-12-17 2018-01-16 2018-02-20 2018-03-27 2019-03-27 Restoration of Forest Cover Based Selection Implementation 800 propriedades rurais CESAN-3B4 / Avaliacao Socioambiental da Bacia e Watershed Management and Quality And Cost- IBRD / 83530 Post Open - National 0.00 Canceled 2017-05-15 2017-06-05 2017-07-19 2017-08-16 2017-09-15 2017-10-20 2017-11-24 2018-11-24 Monitoramento de Impacto de Restoration of Forest Cover Based Selection Resultados INCAPER-3B5 / Elaboracao de Watershed Management and Quality And Cost- Diagnostico Socioeconomico de IBRD / 83530 Post Open - National 0.00 Canceled 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-12-25 Restoration of Forest Cover Based Selection 800 propriedades rurais Project Management, CESAN-4C1 / Auditoria Externa IBRD / 83530 Supervision and Institutional Post Least Cost Selection Open - National 0.00 Canceled 2017-05-22 2017-06-12 2017-07-26 2017-08-23 2017-09-22 2017-10-27 2017-12-01 2018-05-30 do Projeto Strengthening SEAMA-3B8 / Assistencia Watershed Management and Quality And Cost- Pending IBRD / 83530 Post Open - National 0.00 2017-11-14 2017-12-05 2018-01-18 2018-02-15 2018-03-17 2018-04-21 2018-05-26 2019-05-26 Tecnica Rural - ATER MangaraI Restoration of Forest Cover Based Selection Implementation INDIVIDUAL CONSULTANTS Page 3