P128534 Safety Nets Project Procurement Plan June 1st 2017 I. General 1. Bank’s approval Date of the procurement Plan: February 5, 2013 (initial): Revision 12 of Updated Procurement Plan, April 20, 2017 2. Date of General Procurement Notice: Nov 24, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year November 2016 to March 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. NCB (Goods) Above or equal US$ 10 million 2. NCB (Works) Above or equal US$ 10 million 3. NCB (Non-Consultant Services) Above or equal US$ 2 million 4. Individual (Goods) Above or equal Justification to be included US$ 10 million in the PP 5. Individual (Non Consultant Above or equal Justification to be included Services) US$ 2 million in the PP 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for the Safety Nets Project issued on January 2014 by Project Coordination Unit. 5. Any Other Special Procurement Arrangements: Not Applicable 1 6. Summary of the Procurement Packages planned during the 18 months of the current Procurement Plan-November 2016 to March 2018 (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) 1 Summary of 0 0 No No the ICB (Works) 2 Summary of 0 0 No No the ICB (Goods) 3 Summary of 0 0 No No the NCB (Works) 4 Summary of 1.5 18 No Post the NCB (Goods) 5 Summary of 0.74 2 No Prior the NCB (Non- Consultant Services) 6 Summary of 0.51 16 No Post the NCB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above or equal US$ 1 million 2 Competitive Methods (Individual) Above or equal US$ 0.3 million 3 Single Source (Firms) Above or equal Justification to be US$ 1 million included in the PP 4 Single Source (Individual) Above or equal Justification to be US$ 0.3 million included in the PP 2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 1.7 8 Prior LCS; SSS; number of CQS; contracts that Individual; will be let under other methods 2 Summary of 2 72 Post SSS; CQS; number of Individual contracts that will be let under other methods 3 PROCUREMENT Cameroon : Cameroon Social Safety Nets PLAN General Information Country: Cameroon Bank’s Approval Date of the Original Procurement Plan: 2017-02-14 2019-10-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128534 GPN Date: Project Name: Cameroon Social Safety Nets Loan / Credit No: IDA / 52240, IDA / 62230, IDA / D2980 Executing Agency(ies): UNITE DE GESTION DU PROJET FILETS SOCIAUX WORKS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-26069-CW- Laying the Foundations of RFQ / Aménagement des a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,300.00 7,209.40 Achevé 2018-04-01 2018-04-24 2018-05-15 bureaux de l'antenne Supporting Project Envelope régionale du Nord ouest Management GOODS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-5831-GO-RFB Laying the Foundations of / fourniture du matériel a Safety Net System and Single Stage - One informatique, de téléphonie, IDA / 52240 A posteriori Appel d'offres Open - National 253,000.00 243,616.43 Achevé 2017-01-24 2017-01-29 2017-03-12 2017-04-11 2017-05-16 2017-11-12 Supporting Project Envelope et d'équipement de bureau Management (en 3 lots distincts) CM-UGP-PFS-6172-GO-RFQ / Fourniture du matériel de la phase 3 des THIMO Single Stage - One dans 2 communes de la IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 188,000.00 159,198.65 Achevé 2017-02-18 2017-04-15 2017-05-15 Envelope région de l'Extrême Nord et 2 communes de la région de l'EST CM-UGP-PFS-6231-GO-RFQ / Fourniture des boîtes à pharmacie de la phase 3 des THIMO pour 2 Single Stage - One IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 29,000.00 31,172.51 Achevé 2017-02-20 2017-04-17 2017-05-01 communes de la région de Envelope l'Extrême Nord et 2 communes de la région de l'Est CM-UGP-PFS-6307-GO-RFQ Laying the Foundations of / Fourniture des fournitures a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 60,000.00 0.00 Annulé 2017-03-20 2017-05-15 2018-05-10 de bureau au Projet Filets Supporting Project Envelope Sociaux Management Laying the Foundations of CM-UGP-PFS-7392-GO-RFQ a Safety Net System and Single Stage - One / Fourniture des IDA / 52240 A posteriori Appel d'offres Open - National 130,000.00 0.00 Annulé 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2017-10-20 Supporting Project Envelope consommables informatiques Management CM-UGP-PFS-16931-GO- Laying the Foundations of RFQ / fourniture des pièces a Safety Net System and Single Stage - One de rechange pour véhicules IDA / 52240 A posteriori Demande de prix Open - National 37,500.00 32,502.70 Achevé 2017-06-19 2017-08-14 2017-08-28 Supporting Project Envelope et motos du Projet Filets Management Sociaux CM-UGP-PFS-23000-GO- RFQ / fourniture des boites à pharmacie pour la phase Single Stage - One 4 des THIMO dans 2 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 25,100.00 21,014.35 Achevé 2017-08-15 2017-10-13 2018-04-11 Envelope communes de la région de l'Adamaoua et 1 commune de la région du Nord CM-UGP-PFS-25708-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,300.00 6,813.69 Achevé 2017-11-09 2017-12-12 2018-01-02 mobilier de bureau de Supporting Project Envelope l'antenne du Nord-Ouest Management CM-UGP-PFS-25990-GO- RFQ / Fourniture des boites à pharmacie de la phase 5 Single Stage - One des THIMO pour 2 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 25,100.00 20,966.02 Achevé 2017-10-12 2017-11-10 2017-12-01 Envelope communes de la région de l'Est et 2 communes de la région du Nord ouest CM-UGP-PFS-26037-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - One autocollants pour voitures et IDA / 52240 A posteriori Demande de prix Limited 2,000.00 2,081.57 Achevé 2017-09-27 2017-10-16 2017-10-30 Supporting Project Envelope motos au Projet Filets Management Sociaux CM-UGP-PFS-23003-GO- RFQ / Fourniture du matériel et des matériaux Single Stage - One IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 100,000.00 90,128.08 Achevé 2017-09-11 2017-10-03 2017-10-24 de travail pour la phase 4 Envelope des THIMO dans 2 communes de la région de l'Adamaoua CM-UGP-PFS-25561-GO- Laying the Foundations of RFB / Fourniture du a Safety Net System and Single Stage - One matériel roulant autos et IDA / 52240 A posteriori Appel d'offres Open - National 162,000.00 143,614.65 Signé 2017-09-01 2017-09-01 2017-09-01 2017-09-01 2017-09-08 2017-10-08 Supporting Project Envelope motos au projet Filets Management Sociaux en deux lots distincts Cash Transfer Program CM-UGP-PFS-25477-GO- with Accompanying Single Stage - One RFQ / Fourniture des seaux IDA / 52240 A posteriori Demande de prix Limited 38,000.00 26,101.20 Achevé 2017-10-09 2017-11-06 2017-11-27 Measures to Boost Envelope au Projet Filets Sociaux Household Productivity CM-UGP-PFS-25475-GO- RFQ / Fourniture du matériel et des matériaux Single Stage - One IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 61,000.00 50,255.93 Achevé 2017-09-02 2017-09-24 2017-10-15 de travail pour la phase 4 Envelope des THIMO dans la région du nord , commune de Touboro Page 1 CM-UGP-PFS-47595-GO- RFQ / Fourniture du matériel de la phase 6 des Single Stage - One IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 80,275.00 65,428.39 Achevé 2018-06-18 2018-07-30 2018-08-29 THIMO du Projet Filets Envelope Sociaux dans les communes de Dembo et Bashéo, région du Nord CM-UGP-PFS-47606-GO- RFB / Fourniture et paramétrage d'un progiciel Cash Transfer Program de gestion intégré pour la with Accompanying Single Stage - One planification, la IDA / 52240 A posteriori Appel d'offres Open - National 167,500.00 0.00 Annulé 2018-06-21 2018-06-26 2018-07-27 2018-08-17 2018-09-14 2019-03-13 Measures to Boost Envelope programmation, la Household Productivity budgétisation, le suivi évaluation et la production des rapports et indicateurs CM-UGP-PFS-47608-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 48,400.00 0.00 Annulé 2018-03-27 2018-05-08 2018-05-29 logiciels informatiques au Measures to Boost Envelope projet Filets Sociaux Household Productivity CM-UGP-PFS-16933-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Single Stage - One seaux, Tee shirt, casquettes IDA / 52240 A posteriori Demande de prix Open - National 193,700.00 0.00 Annulé 2017-06-20 2017-08-15 2017-09-14 Measures to Boost Envelope autocollants pour véhicules Household Productivity estampillés Projet Filets Sociaux CM-UGP-PFS-25989-GO- RFQ / Fourniture du matériel et des matériaux Single Stage - One de travail pour la phase 5 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 80,275.00 72,952.92 Achevé 2018-04-06 2018-05-05 2018-06-04 Envelope des THIMO dans 2 communes de la région du Nord ouest (Oku et Ako) CM-UGP-PFS-25987-GO- RFQ / Fourniture du matériel et des matériaux Single Stage - One de travail pour la phase 5 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 80,275.00 65,815.47 Achevé 2018-04-06 2018-05-05 2018-06-04 Envelope des THIMO dans 2 communes de la région de l'EST (Bétaré OYA et Batouri) CM-UGP-PFS-25491-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2018-04-19 2018-05-24 2019-05-24 matériel de pause café au Supporting Project Envelope Projet Filets Sociaux Management CM-UGP-PFS-47578-GO- Cash Transfer Program RFQ / Fourniture des pneus with Accompanying Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 28,400.00 24,340.71 Achevé 2018-06-04 2018-07-16 2018-08-06 de recharge pour des autos Measures to Boost Envelope et motos du Projet Household Productivity CM-UGP-PFS-25476-GO- Cash Transfer Program RFQ / Fourniture des tee- with Accompanying Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 99,000.00 68,943.69 Achevé 2017-12-02 2017-12-26 2018-01-16 shirts et casquettes Measures to Boost Envelope estampillés au Projet Filets Household Productivity Sociaux CM-UGP-PFS-25488-GO- Laying the Foundations of RFQ / fourniture des encres a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 100,000.00 83,622.13 Achevé 2018-01-03 2018-02-10 2019-02-10 pour imprimantes et Supporting Project Envelope photocopieurs Management CM-UGP-PFS-25487-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 60,000.00 0.00 Annulé 2017-09-16 2017-10-11 2018-10-11 fournitures de bureau au Supporting Project Envelope Projet Filets sociaux Management CM-UGP-PFS-67485-GO- RFQ / Fourniture du Laying the Foundations of matériel informatique et de a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,250.00 6,993.13 Achevé 2018-07-15 2018-08-19 2018-09-02 bureautique de l'antenne Supporting Project Envelope régionale du projet du Nord Management Ouest CM-UGP-PFS-67490-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,250.00 3,525.35 Achevé 2018-07-10 2018-08-14 2019-08-14 polices d'assurance aux 40 Supporting Project Envelope premières motos du projet Management CM-UGP-PFS-47597-GO- RFQ / Fourniture des boîtes Single Stage - One à pharmacie de la phase 6 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 8,360.00 7,383.31 Achevé 2018-09-09 2018-09-30 2018-10-07 Envelope des THIMO du Projet Filets Sociaux CM-UGP-PFS-75801-GO- Cash Transfer Program RFQ / Fourniture du with Accompanying Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,360.00 7,144.10 Achevé 2018-09-15 2018-10-10 2018-10-17 matériel pour les crèches Measures to Boost Envelope temporaires au PFS Household Productivity CM-UGP-PFS-130190-GO- RFQ / Fourniture des licences pour la plateforme Laying the Foundations of tomate ( Licence a Safety Net System and Single Stage - One En cours IDA / 62230 A posteriori Demande de prix Limited 34,000.00 0.00 2019-10-10 2019-12-13 2020-06-10 Multiprojet, Monosite et Supporting Project Envelope d'exécution Multiposte Tom2pro, Management Tom2monitoring, Tom2paie et Tom2marché) CM-UGP-PFS-121205-GO- Laying the Foundations of RFB / Fourniture des a Safety Net System and Single Stage - One En cours IDA / 52240 A posteriori Demande de prix Limited 80,000.00 0.00 2019-10-05 2019-11-23 2020-03-22 consommables informatiques Supporting Project Envelope d'exécution au Projet Filets Sociaux Management CM-UGP-PFS-121383-GO- RFQ / Acquisition des Laying the Foundations of fournitures de bureaux et a Safety Net System and Single Stage - One En cours IDA / 62230 A posteriori Demande de prix Limited 40,000.00 0.00 2019-10-14 2019-12-16 2020-04-14 des produits d'entretien de Supporting Project Envelope d'exécution bureau en deux lots Management distincts CM-UGP-PFS-120445-GO- UN / FOURNITURE DE 756 TABLETTES BIOMETRIQUES MOBILES Laying the Foundations of Passation de et 756 BATTERIE a Safety Net System and marchés auprès En attente IDA / 62230 A posteriori Direct 660,808.00 0.00 2019-11-30 2019-12-14 2020-02-02 2020-08-20 EXTERNES TYPES Supporting Project des agences de d'exécution POWERBANK ET 756 Management l'ONU SACS PHOTOVOLTAÏQUES en deux tranches de 400 et 356 chacune NON CONSULTING SERVICES Page 2 Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6232-NC-RFQ / Recrutement des agences Single Stage - One de paiement pour les IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 60,000.00 61,263.97 Signé 2017-02-15 2017-04-12 2017-12-08 Envelope phases 3 et 4 des THIMO en lots CM-UGP-PFS-6233-NC-RFQ / Recrutement des agences de paiement pour le paiement de 19500 ménages bénéficiaires du cycle 2 des Cash Transfer Program transferts monétaires dont with Accompanying Single Stage - One IDA / 52240 A priori Demande de prix Limited 351,000.00 0.00 Annulé 2017-03-07 2017-05-05 2019-04-25 7500 dans la région de Measures to Boost Envelope l'Extrême Nord, 5500 dans Household Productivity les régions du Nord et de l'Adamaoua, et 6500 dans les régions de l'Est, du Nord Cash Transfer Program CM-UGP-PFS-6315-NC-RFQ with Accompanying Single Stage - One / Impression des documents IDA / 52240 A posteriori Demande de prix Limited 70,000.00 22,001.63 Achevé 2017-02-25 2017-04-22 2017-05-06 Measures to Boost Envelope du Projet Household Productivity Laying the Foundations of CM-UGP-PFS-6306-NC-RFQ a Safety Net System and Single Stage - One / fourniture des polices IDA / 52240 A posteriori Demande de prix Limited 123,900.00 58,410.90 Achevé 2017-03-03 2017-04-28 2018-04-23 Supporting Project Envelope d'assurance maladie Management Laying the Foundations of CM-UGP-PFS-7385-NC-RFQ a Safety Net System and Single Stage - One / Fourniture des polices IDA / 52240 A posteriori Demande de prix Limited 31,100.00 18,329.45 Achevé 2017-03-03 2017-04-28 2018-04-23 Supporting Project Envelope d'assurance automobile Management CM-UGP-PFS-14464-NC- Laying the Foundations of RFQ / Renouvellement du a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,250.00 3,553.09 Signé 2017-06-13 2017-06-19 2018-06-14 contrat d'assurance des 40 Supporting Project Envelope motos en circulation Management Laying the Foundations of CM-UGP-PFS-25608-NC- a Safety Net System and Single Stage - One RFQ / Maintenance Autos IDA / 52240 A posteriori Demande de prix Limited 8,300.00 0.00 Annulé 2017-10-04 2017-10-31 2018-10-31 Supporting Project Envelope UGP pour 1 an Management CM-UGP-PFS-25616-NC- Laying the Foundations of RFQ / Maintenance matériel a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,300.00 0.00 Annulé 2017-10-07 2017-11-07 2018-11-07 bureautique et informatique Supporting Project Envelope UGP pour 1 an Management CM-UGP-PFS-25623-NC- Laying the Foundations of RFQ / Maintenance froid et a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,300.00 0.00 Annulé 2017-10-11 2017-11-09 2018-11-09 climatisation UGP pour 1 Supporting Project Envelope an Management CM-UGP-PFS-25711-NC- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 6,000.00 8,986.03 Signé 2017-12-09 2018-01-09 2019-01-09 service de gardiennage pour Supporting Project Envelope l'antenne régionale du Nord Management Ouest CM-UGP-PFS-25729-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - One systèmes de sécurité et de IDA / 52240 A posteriori Demande de prix Limited 4,000.00 1,315.18 Achevé 2017-10-15 2017-11-15 2017-12-15 Supporting Project Envelope GPS et du service de Management tracking pour les autos CM-UGP-PFS-25892-NC- Laying the Foundations of RFQ / Confection et la pose a Safety Net System and Single Stage - One des plaques signalétiques (7 IDA / 52240 A posteriori Demande de prix Open - National 4,000.00 7,636.09 Achevé 2017-09-30 2017-11-10 2017-12-01 Supporting Project Envelope plaques directionnelles + 3 Management panneaux) CM-UGP-PFS-25980-NC- Laying the Foundations of RFQ / Avenant au contrat a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 6,000.00 14,850.36 Signé 2017-09-11 2017-09-23 2018-09-23 de l'agence de gardiennage Supporting Project Envelope de l'antenne régionale du Management Nord CM-UGP-PFS-25981-NC- Laying the Foundations of RFQ / Avenant au contrat a Safety Net System and Single Stage - One de l'agence de gardiennage IDA / 52240 A posteriori Demande de prix Limited 5,000.00 16,374.35 Signé 2017-09-11 2017-09-23 2018-09-23 Supporting Project Envelope de l'antenne régionale de Management l'Extrême Nord CM-UGP-PFS-25983-NC- RFQ / Avenant au contrat Laying the Foundations of d'assurance du personnel en a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 39,000.00 24,386.04 Achevé 2017-09-15 2017-10-16 2018-08-12 vu de la prise en compte Supporting Project Envelope du personnel nouvellement Management recruté CM-UGP-PFS-30748-NC- DIR / recrutement d'une agence de paiement chargée Cash Transfer Program d'assurer les transferts Passation de with Accompanying monétaires des bénéficiaires IDA / 52240 A posteriori marché de gré à Direct 36,000.00 30,643.76 Signé 2017-10-04 2017-10-09 2017-11-16 2018-11-16 Measures to Boost de la phase 2 des gré Household Productivity transferts monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-37510-NC- RFQ / avenant Lettre de Marché N°009/LM/MINEPAT/CTS/PF Passation de S/UGP/CAPM/2017 du 26 IDA / 52240 Public Works Program Pilot A posteriori marché de gré à Direct 6,000.00 22,354.79 Signé 2017-12-18 2017-12-25 2018-01-15 2018-05-15 mai 2017 de l'agence de gré paiement pour la réalisation des paiements des 6000 bénéficiaires des THIMO 5 dont 3000 dans le Nord- Ouest et 3000 dans l'Est CM-UGP-PFS-37511-NC- RFQ / Avenant au contrat Laying the Foundations of d'assurance véhicule Passation de a Safety Net System and LETTRE DE MARCHE IDA / 52240 A posteriori marché de gré à Direct 4,000.00 1,207.48 Signé 2017-12-18 2017-12-23 2018-01-09 2018-07-08 Supporting Project N°011/LM/MINEPAT/CTS/PF gré Management S/UGP/CAPM/2017 DU 08 JUIN 2017 Page 3 CM-UGP-PFS-25853-NC- DIR / Avenant au contrat de l'agence de paiement chargée des transferts monetaires du cycle 2 à Single Stage - One l'Est, le Nord ouest, Douala IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 23,400.00 22,232.85 Signé 2017-09-25 2017-11-20 2018-05-19 Envelope et Yaoundé pour la phase 5 des THIMO dont 3000 dans la région de l'Est et 3000 dans la région du Nord Ouest CM-UGP-PFS-47580-NC- Cash Transfer Program RFQ / Fourniture de polices with Accompanying Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 28,000.00 14,785.79 Signé 2018-03-31 2018-05-26 2019-05-26 d'assurance autos au projet Measures to Boost Envelope Filets Sociaux Household Productivity CM-UGP-PFS-47582-NC- Cash Transfer Program RFQ / Confection et pause with Accompanying Single Stage - One des plaques signalétiques IDA / 52240 A posteriori Demande de prix Limited 8,250.00 7,009.83 Achevé 2018-04-30 2018-06-11 2018-07-11 Measures to Boost Envelope des réalisations du Projet Household Productivity Filets Sociaux dans les communes CM-UGP-PFS-47593-NC- RFQ / Agence de paiement chargée d'assurer le Cash Transfer Program paiement des 3000 with Accompanying Single Stage - One bénéficiaires de la phase 3 IDA / 52240 A posteriori Demande de prix Limited 19,170.00 0.00 Annulé 2018-05-23 2018-07-18 2019-07-18 Measures to Boost Envelope des transferts monétaires Household Productivity d'urgence du du Projet Filets Sociaux dans le Nord Ouest CM-UGP-PFS-47602-NC- DIR / Avenant au contrat de l'agence de paiement chargée d'assurer les paiement des transfert Passation de monétaires du cycle 2 IDA / 52240 Public Works Program Pilot A posteriori marché de gré à Direct 11,700.00 10,227.50 Achevé 2018-06-21 2018-06-26 2018-07-31 2019-01-27 dans le Nord et l'Adamaoua gré pour les paiements de 3000 bénéficiaire de la phase 6 des THIMO dans la région du Nord, communes de Dembo et Bashéo CM-UGP-PFS-25707-NC- Laying the Foundations of RFQ / Maintenance froid et a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2017-10-09 2017-11-07 2018-11-07 climatisation EN et NO Supporting Project Envelope pour 1 an Management CM-UGP-PFS-25610-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2017-10-04 2017-10-31 2018-10-31 Autos et Motos de Supporting Project Envelope l'Extrême-Nord Management CM-UGP-PFS-25612-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2017-09-03 2017-09-30 2018-09-30 Autos et Motos du Projet Supporting Project Envelope du Nord Management CM-UGP-PFS-25618-NC- Laying the Foundations of RFQ / Maintenance matériel a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2017-10-07 2017-11-03 2018-11-03 bureautique et informatique Supporting Project Envelope EN et NO pour 1 an Management CM-UGP-PFS-47255-NC- Cash Transfer Program RFQ / Production et with Accompanying Single Stage - One multiplication des IDA / 52240 A posteriori Demande de prix Limited 7,567.00 7,132.71 Achevé 2018-03-16 2018-04-10 2018-04-24 Measures to Boost Envelope documents des Pratiques Household Productivity familiales essentielles CM-UGP-PFS-26101-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2017-10-11 2017-11-13 2018-11-13 Autos et Motos du Nord- Supporting Project Envelope Ouest Management Laying the Foundations of CM-UGP-PFS-6311-NC-RFQ a Safety Net System and Single Stage - One / Fourniture de police IDA / 52240 A posteriori Demande de prix Limited 8,250.00 3,228.19 Achevé 2018-04-06 2018-05-11 2019-05-06 Supporting Project Envelope d'assurance pour 20 motos Management CM-UGP-PFS-26060-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 8,500.00 1,867.92 Achevé 2018-05-01 2018-06-01 2018-06-22 Systèmes de sécurité pour Supporting Project Envelope les motos du projet (20) Management CM-UGP-PFS-37512-NC- RFQ / Avenant N°2 au contrat d'assurance du Cash Transfer Program personnel pour la prise en Passation de with Accompanying compte des relais IDA / 52240 A posteriori marché de gré à Direct 30,000.00 34,099.31 Signé 2018-03-30 2018-04-06 2018-05-04 2018-10-31 Measures to Boost communautaires recrutés gré Household Productivity dans le cadre de la sensibilisation sur les pratiques familiales essentielles CM-UGP-PFS-47572-NC- Cash Transfer Program RFB / Fourniture des with Accompanying Single Stage - One IDA / 52240 A posteriori Demande de prix Limited 130,000.00 127,074.00 Signé 2018-05-07 2018-07-02 2019-07-02 polices d'assurance au Measures to Boost Envelope personnel du Projet Filets Household Productivity Sociaux CM-UGP-PFS-72576-NC- RFQ / Multiplication de certains documents pour la collecte des données sur les Laying the Foundations of PFE de la phase pilote a Safety Net System and Single Stage - One pour une période de 6 mois IDA / 52240 A posteriori Demande de prix Limited 8,250.00 7,116.25 Achevé 2018-09-16 2018-10-28 2018-11-11 Supporting Project Envelope et des questionnaires et Management autres documents pour la collecte des données dans le cadre de la première évaluation interne du Projet CM-UGP-PFS-92192-NC- Cash Transfer Program RFQ / Multiplication de with Accompanying Single Stage - One certains documents de IDA / 52240 A posteriori Demande de prix Limited 6,500.00 5,551.26 Signé 2019-01-15 2019-02-26 2020-02-26 Measures to Boost Envelope collecte de données des PFE Household Productivity pour une période d'un an MOF-CM-UGP-PFS-6233- NC-RFQ / Recrutement des Cash Transfer Program agences de paiement pour with Accompanying Single Stage - One le paiement de 19500 IDA / 52240 A posteriori Demande de prix Limited 351,000.00 142,058.17 Signé 2017-02-27 2017-05-01 2019-10-28 Measures to Boost Envelope menages beneficiaires du Household Productivity cycle 2 des transferts monetaires en 3 lots Page 4 CM-UGP-PFS-121194-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - One En cours polices d'assurance pour les IDA / 62230 A posteriori Demande de prix Limited 28,000.00 0.00 2019-09-10 2019-11-05 2020-11-04 Supporting Project Envelope d'exécution autos du Projet Filets Management Sociaux CM-UGP-PFS-121367-NC- RFB / FOURNITURE D’UNE POLICE Laying the Foundations of D'ASSURANCE MALADIE a Safety Net System and Single Stage - One En cours POUR UN AN EN IDA / 62230 A posteriori Appel d'offres Open - National 164,000.00 0.00 2019-08-30 2019-09-14 2019-10-26 2019-11-25 2019-12-23 2020-12-22 Supporting Project Envelope d'exécution FAVEUR DU PERSONNEL Management DU PROJET FILETS SOCIAUX ET LEURS FAMILLES (2019-2020) CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Process Expression of Request for Opening of Technical Evaluation of / Description Component Review Type Method Amount Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal (US$) Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6358-CS-CQS / ONG pour THIMO: 7000 bénéficiaires dans 2 communes de l'Extrême Sélection fondée Nord, 2 communes de l'Est sur les IDA / 52240 Public Works Program Pilot A posteriori Open - National 429,190.00 367,605.09 Achevé 2017-02-07 2017-02-28 2017-04-13 2017-05-13 2017-06-17 2017-12-14 pour la phase 3 et 6000 qualifications des bénéficiaires: 2 communes consultants Adamaoua, 1 commune Nord pour la phase 4 en 2017 (1 ONG par région) CM-UGP-PFS-54735-CS- CQS / Consultant pour le Cash Transfer Program Sélection fondée développement d'un progiciel with Accompanying sur les IDA / 52240 A posteriori Open - National 167,500.00 135,528.54 Signé 2018-05-30 2018-06-20 2018-08-03 2018-09-02 2018-10-07 2019-04-05 de gestion intégré pour le Measures to Boost qualifications des système d'information du Household Productivity consultants Projet Filets Sociaux INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6328-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,950.00 10,372.40 Signé 2017-02-06 2017-03-27 2017-04-17 2017-05-22 2017-06-16 Measures to Boost Blangoua du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6334-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,950.00 10,368.36 Signé 2017-02-06 2017-03-27 2017-04-17 2017-05-22 2017-06-16 Measures to Boost Goulfey du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6337-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 15,500.00 12,422.62 Signé 2017-02-06 2017-03-27 2017-04-17 2017-05-22 2017-06-21 Measures to Boost Makari du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6339-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 10,372.40 Signé 2017-02-06 2017-03-27 2017-04-17 2017-05-22 2017-06-16 Measures to Boost GOBO du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6340-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 10,379.07 Signé 2017-02-06 2017-03-27 2017-04-17 2017-05-22 2017-06-16 Measures to Boost BOURRHA du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6341-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 10,379.07 Signé 2017-02-06 2017-03-27 2017-04-17 2017-05-22 2017-06-16 Measures to Boost Koza du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6342-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 10,372.40 Signé 2017-02-06 2017-02-13 2017-02-14 2017-02-24 2017-03-21 Measures to Boost Mogodé du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6344-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 15,500.00 11,613.54 Signé 2017-02-06 2017-02-13 2017-02-14 2017-02-24 2017-03-26 Measures to Boost Banyo du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6346-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 10,381.76 Signé 2017-02-06 2017-02-13 2017-02-14 2017-02-24 2017-03-21 Measures to Boost Tcheboa du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6347-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 9,829.76 Signé 2017-02-06 2017-02-13 2017-02-14 2017-02-24 2017-03-21 Measures to Boost Mayo Oulo du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6348-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 9,707.50 Signé 2017-02-06 2017-02-24 2017-02-26 2017-02-28 2017-03-25 Measures to Boost Rey Bouba du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6349-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 9,716.26 Signé 2017-02-06 2017-02-09 2017-02-10 2017-02-12 2017-03-09 Measures to Boost Touboro du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6350-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 11,772.77 Signé 2017-02-06 2017-02-18 2017-02-28 2017-03-04 2017-03-29 Measures to Boost Kette du cycle 2 des Household Productivity transferts monetaires Page 5 CM-UGP-PFS-6351-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 9,713.75 Signé 2017-02-06 2017-02-18 2017-02-28 2017-03-04 2017-03-29 Measures to Boost Belo du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6352-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 12,500.00 9,703.73 Signé 2017-02-06 2017-02-18 2017-02-28 2017-03-04 2017-03-29 Measures to Boost Menchum Valley du cycle 2 Household Productivity des transferts monetaires CM-UGP-PFS-6353-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 15,500.00 9,020.07 Achevé 2017-02-06 2017-02-18 2017-02-28 2017-03-04 2017-03-29 Measures to Boost Douala 3 du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6354-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying ciblage et l'enregistrement à IDA / 52240 A posteriori Individuel Open 15,500.00 9,264.24 Signé 2017-02-06 2017-02-18 2017-02-28 2017-03-04 2017-03-29 Measures to Boost Yaoundé du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6355-CS- INDV / Consultant chargé d'améliorer les modules du volet économique notamment formation en AGR ( Cash Transfer Program agriculture, petit commerce, with Accompanying IDA / 52240 A posteriori Individuel Open 26,260.00 22,361.04 Achevé 2017-02-10 2017-02-25 2017-03-02 2017-03-12 2017-04-17 gestion de l'argent, élevage) Measures to Boost et former les bénéficiaires Household Productivity dans ces modules à l'Extrême Nord dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6356-CS- INDV / Consultant chargé d'améliorer les modules du volet économique : Cash Transfer Program formation en AGR ( with Accompanying agriculture,petit commerce, IDA / 52240 A posteriori Individuel Open 28,460.00 24,278.93 Achevé 2017-02-10 2017-02-25 2017-03-02 2017-03-12 2017-04-17 Measures to Boost gestion de l'argent, élevage) Household Productivity et former les bénéficiaires dans ces modules dans le Nord et l'Adamaoua dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6357-CS- INDV / Consultant chargé d'améliorer les modules du volet économique : formation en AGR ( Cash Transfer Program agriculture,petit commerce, with Accompanying IDA / 52240 A posteriori Individuel Open 31,400.00 26,919.25 Achevé 2017-02-10 2017-02-25 2017-03-02 2017-03-12 2017-04-17 gestion de l'argent, élevage) Measures to Boost et former les bénéficiaires Household Productivity dans ces modules dans le Nord O, Est, Dla, Ydé dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6421-CS- INDV / Expert IDA / 52240 Public Works Program Pilot A priori Individuel Open 63,840.00 0.00 Annulé 2017-02-17 2017-04-07 2017-04-28 2017-06-02 2017-11-29 environnemental et social du PFS Laying the Foundations of CM-UGP-PFS-6423-CS- a Safety Net System and IDA / 52240 A priori Individuel Open 1,920.00 0.00 Annulé 2017-02-07 2017-03-28 2017-04-18 2017-05-23 2017-06-28 INDV / Assistant Comptable Supporting Project Management Laying the Foundations of CM-UGP-PFS-6424-CS- a Safety Net System and IDA / 52240 A priori Individuel Open 1,920.00 0.00 Annulé 2017-02-07 2017-03-28 2017-04-18 2017-05-23 2017-06-28 INDV / Assistant SPM Supporting Project Management CM-UGP-PFS-6327-CS-CDS Cash Transfer Program Sélection de / protocole d'accord avec with Accompanying IDA / 52240 A priori consultants par Direct 900,000.00 0.00 Annulé 2017-02-06 2017-02-16 2017-03-03 2017-09-29 l'INS pour le dénombrement Measures to Boost entente directe et l'enquête PMT du cycle Household Productivity 2 CM-UGP-PFS-14406-CS- INDV / Opérateur Terrain Cash Transfer Program commune Mayo Moskota with Accompanying IDA / 52240 A posteriori Individuel Open 12,960.00 7,006.15 Signé 2017-05-19 2017-06-04 2017-06-11 2017-06-21 2019-06-21 (Extrême Nord) pour les Measures to Boost transferts monetaires Household Productivity d'urgence CM-UGP-PFS-14407-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and IDA / 52240 A posteriori Individuel Open 24,000.00 55,333.37 Signé 2017-05-08 2017-05-09 2017-05-10 2017-05-10 2019-05-10 contrat de l'Assistante du Supporting Project Coordonnateur du Projet Management CM-UGP-PFS-14409-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and IDA / 52240 A posteriori Individuel Open 19,200.00 44,266.70 Signé 2017-05-05 2017-05-06 2017-05-07 2017-05-07 2019-05-07 contrat de la Secrétaire de Supporting Project l'Unité de Gestion du Projet Management CM-UGP-PFS-14410-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and IDA / 52240 A posteriori Individuel Open 16,800.00 38,438.87 Signé 2017-05-05 2017-05-06 2017-05-07 2017-05-07 2019-05-07 contrat Chauffeur 1 de Supporting Project l'Unité de Gestion du Projet Management CM-UGP-PFS-14411-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and IDA / 52240 A posteriori Individuel Open 16,800.00 38,438.87 Signé 2017-05-05 2017-05-06 2017-05-07 2017-05-07 2019-05-07 contrat Chauffeur 2 Unité Supporting Project de Gestion du Projet Management CM-UGP-PFS-14412-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and contrat de l'Agent de liaison IDA / 52240 A posteriori Individuel Open 16,800.00 32,191.68 Signé 2017-05-05 2017-05-06 2017-05-07 2017-05-07 2019-05-07 Supporting Project de l'Unité de Gestion du Management Projet CM-UGP-PFS-14463-CS- Laying the Foundations of INDV / Avenant au contrat a Safety Net System and IDA / 52240 A posteriori Individuel Open 12,960.00 0.00 Annulé 2017-06-09 2017-06-12 2017-06-13 2017-06-15 2019-06-15 de l'operateur de terrain de Supporting Project Yaoundé 7 Management CM-UGP-PFS-14460-CS- Laying the Foundations of INDV / Avenant au contrat a Safety Net System and IDA / 52240 A posteriori Individuel Open 3,240.00 0.00 Annulé 2017-06-09 2017-06-12 2017-06-13 2017-06-15 2017-12-12 de l'opératrice de terrain de Supporting Project la commune de Douala 2 Management Page 6 CM-UGP-PFS-14490-CS- Laying the Foundations of INDV / Avenant au contrat a Safety Net System and IDA / 52240 A posteriori Individuel Open 16,800.00 0.00 Annulé 2017-06-15 2017-06-23 2017-06-25 2017-06-29 2019-06-29 de Technicienne de surface Supporting Project de l'UGP Management CM-UGP-PFS-14454-CS- Laying the Foundations of INDV / Avenant au contrat a Safety Net System and IDA / 52240 A posteriori Individuel Open 19,200.00 34,575.36 Résilié 2017-06-09 2017-06-12 2017-06-13 2017-06-15 2019-06-15 du point focal de la ville Supporting Project de Douala Management CM-UGP-PFS-16811-CS- Laying the Foundations of INDV / renouvellement de a Safety Net System and IDA / 52240 A posteriori Individuel Direct 12,960.00 25,629.07 Signé 2017-06-09 2017-06-11 2017-06-12 2017-06-13 2019-06-03 contrat opérateur de terrain Supporting Project 1 commune de MOKOLO Management CM-UGP-PFS-16814-CS- Laying the Foundations of INDV / renouvellement a Safety Net System and IDA / 52240 A posteriori Individuel Direct 12,960.00 23,513.04 Signé 2017-06-09 2017-06-12 2017-06-13 2017-06-14 2019-06-04 contrat opérateur de terrain Supporting Project 2 commune de MOKOLO Management CM-UGP-PFS-16821-CS- Laying the Foundations of INDV / Renouvellement de a Safety Net System and contrat de l'opérateur de IDA / 52240 A posteriori Individuel Direct 12,960.00 23,513.04 Signé 2017-06-09 2017-06-12 2017-06-13 2017-06-15 2019-06-05 Supporting Project terrain de la commune de Management MAGA CM-UGP-PFS-16823-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and contrat de l'opérateur de IDA / 52240 A posteriori Individuel Direct 3,240.00 22,483.20 Signé 2017-06-09 2017-06-10 2017-06-11 2017-06-12 2017-12-09 Supporting Project terrain de la commune de Management Kar Hay Laying the Foundations of CM-UGP-PFS-16925-CS- a Safety Net System and INDV / Avenant au contrat IDA / 52240 A priori Individuel Open 63,840.00 0.00 Annulé 2017-06-12 2017-06-15 2017-06-19 2017-06-21 2019-06-11 Supporting Project du SPM du Projet Management Laying the Foundations of CM-UGP-PFS-14451-CS- a Safety Net System and INDV / Renouvellement du IDA / 52240 A priori Individuel Open 46,000.00 0.00 Annulé 2017-06-09 2017-06-10 2017-06-14 2017-06-15 2019-06-15 Supporting Project contrat Comptable Management CM-UGP-PFS-14446-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and contrat de l'Expert IDA / 52240 A priori Individuel Open 63,840.00 0.00 Annulé 2017-06-09 2017-06-09 2017-06-10 2017-06-15 2019-06-15 Supporting Project Informatique et Responsable Management SIG du Projet CM-UGP-PFS-14452-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and IDA / 52240 A priori Individuel Direct 38,400.00 0.00 Annulé 2017-06-09 2017-06-12 2017-06-13 2017-06-15 2019-06-15 contrat du Responsable Supporting Project Régional Extrême Nord Management CM-UGP-PFS-25501-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and responsable régional du IDA / 52240 A posteriori Individuel Open 19,200.00 13,917.36 Signé 2017-08-31 2017-09-26 2017-10-03 2017-10-13 2018-10-13 Supporting Project Nord ouest du projet Management Filets Sociaux CM-UGP-PFS-25504-CS- Laying the Foundations of INDV / Consultant chargé a Safety Net System and de la Conception et l' appui IDA / 52240 A posteriori Individuel Open 21,500.00 80,692.20 Signé 2017-09-01 2017-09-29 2017-10-06 2017-10-16 2018-04-19 Supporting Project à la mise en œuvre du Management plan de communication CM-UGP-PFS-25520-CS- INDV / Recrutement de 4 consultants pour le ciblage des bénéficiaires de la phase 2 des transferts Laying the Foundations of monetaires d'urgence dans a Safety Net System and IDA / 52240 A posteriori Individuel Open 36,400.00 30,128.36 Achevé 2017-09-07 2017-10-12 2017-10-19 2017-10-27 2017-11-16 les département du Logone Supporting Project et Chari (Communes de Management Blangoua, Goulfey, Makari) et dans le département du Mayo Tsanaga(commune de Mayo Moskota CM-UGP-PFS-25782-CS- Laying the Foundations of INDV / Avenant N°01 au a Safety Net System and contrat de l'Expert IDA / 52240 A posteriori Individuel Open 38,095.25 157,236.52 Signé 2017-09-06 2017-09-09 2017-09-10 2017-09-11 2018-09-11 Supporting Project informatique et responsable Management SIG UGP CM-UGP-PFS-25786-CS- Laying the Foundations of INDV / Avenant N°02 au a Safety Net System and contrat du Spécialiste en IDA / 52240 A posteriori Individuel Open 38,095.25 71,473.92 Signé 2017-09-06 2017-09-09 2017-09-10 2017-09-11 2018-09-11 Supporting Project passation des Marchés de Management l'UGP CM-UGP-PFS-25787-CS- Laying the Foundations of INDV / Avenant N°1 au a Safety Net System and IDA / 52240 A posteriori Individuel Open 35,555.57 134,620.67 Signé 2017-09-06 2017-09-09 2017-09-10 2017-09-11 2018-09-11 contrat du Comptable de Supporting Project l'UGP Management CM-UGP-PFS-25794-CS- INDV / Avenant N°1 au Laying the Foundations of contrat du Responsable a Safety Net System and IDA / 52240 A posteriori Individuel Open 19,200.00 86,985.26 Signé 2017-09-06 2017-09-09 2017-09-10 2017-09-11 2018-09-11 régional du Projet Filets Supporting Project Sociaux dans l'Extrême Management Nord CM-UGP-PFS-25517-CS- INDV / Consultant chargé de la sensibilisation des Cash Transfer Program bénéficiaires du Cycle 2 (i) with Accompanying IDA / 52240 A posteriori Individuel Open 58,180.00 43,182.70 Signé 2017-09-07 2017-10-12 2017-10-19 2017-10-27 2018-02-24 à l'Extrême Nord, (ii) au Measures to Boost Nord et à l'Adamaoua, (iii) Household Productivity à l'Est, au Nord-ouest, à Douala et à Yaoundé CM-UGP-PFS-6326-CS-CDS Cash Transfer Program Sélection de / Protocole d'accord avec with Accompanying IDA / 52240 A priori consultants par Direct 500,000.00 391,776.36 Signé 2017-08-31 2017-08-31 2017-09-16 2018-05-14 l'INS pour la réalisation de Measures to Boost entente directe l'enquête de base Household Productivity CM-UGP-PFS-25509-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires dans with Accompanying la commune de Koza, IDA / 52240 A posteriori Individuel Open 40,800.00 49,307.71 Signé 2017-11-30 2017-12-30 2018-01-06 2018-01-14 2019-01-14 Measures to Boost département du Mayo Household Productivity Tsanaga, Région de l'Extrême Nord Page 7 CM-UGP-PFS-25508-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires dans with Accompanying la commune de Bourrha, IDA / 52240 A posteriori Individuel Open 40,800.00 46,287.84 Signé 2017-12-30 2018-01-29 2018-02-03 2018-02-11 2019-02-11 Measures to Boost département du Mayo Household Productivity Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25512-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires dans with Accompanying la commune de Mogode, IDA / 52240 A posteriori Individuel Open 40,800.00 69,189.81 Signé 2017-11-30 2017-12-30 2018-01-06 2018-01-14 2019-01-14 Measures to Boost département du Mayo Household Productivity Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25515-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires dans with Accompanying IDA / 52240 A posteriori Individuel Open 40,800.00 50,528.89 Signé 2017-11-30 2018-01-02 2018-01-09 2018-01-17 2019-01-17 la commune de Mayo-Oulo, Measures to Boost département du Mayo Louti, Household Productivity Région du Nord CM-UGP-PFS-25516-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires dans with Accompanying IDA / 52240 A posteriori Individuel Open 40,800.00 68,555.87 Signé 2017-11-30 2018-01-04 2018-01-11 2018-01-19 2019-01-19 la commune de Tcheboa, Measures to Boost département de la Bénoué, Household Productivity Région du Nord CM-UGP-PFS-37431-CS- Laying the Foundations of INDV / Chauffeur de a Safety Net System and IDA / 52240 A posteriori Individuel Open 6,840.00 10,274.36 Signé 2017-12-27 2018-01-20 2018-01-22 2018-01-29 2019-01-29 l'antenne régionale du Supporting Project Projet du Nord- Ouest Management CM-UGP-PFS-37432-CS- Laying the Foundations of INDV / Secrétaire de a Safety Net System and IDA / 52240 A posteriori Individuel Open 9,600.00 15,722.34 Signé 2017-12-28 2018-01-23 2018-01-28 2018-02-04 2019-02-04 l'antenne régionale du Supporting Project Projet du Nord Ouest Management Laying the Foundations of CM-UGP-PFS-37434-CS- a Safety Net System and INDV / Point focal du IDA / 52240 A posteriori Individuel Open 9,600.00 14,584.42 Signé 2017-11-30 2017-12-22 2017-12-26 2017-12-28 2018-12-28 Supporting Project Projet de la ville de Douala Management CM-UGP-PFS-25972-CS- CQS / Avenant au contrat N°001/MINEPAT/CTS/PFS/C APM/2017 du 23 mars 2017 de l'ONG chargée de la Sélection de mise en œuvre des THIMO IDA / 52240 Public Works Program Pilot A posteriori consultants par Direct 99,042.50 93,748.34 Signé 2017-12-18 2017-12-25 2018-01-18 2018-07-17 3 dans l'Extrême Nord entente directe avec 4000 bénéficiaires pour la mise en œuvre des THIMO 5 avec 3000 bénéficiaires dans la région du Nord-ouest CM-UGP-PFS-25907-CS- CQS / Avenant au contrat N°002/MINEPAT/CTS/PFS/C APM/2017 du 23 mars 2017 de l'ONG chargée de la Sélection de mise en œuvre des THIMO IDA / 52240 Public Works Program Pilot A posteriori consultants par Direct 99,042.50 92,937.44 Achevé 2017-12-18 2017-12-25 2018-01-18 2018-07-17 3 dans la région de l'Est entente directe avec 3000 bénéficiaires pour la mise en œuvre des THIMO 5 avec 3000 bénéficiaires dans la région de l'Est CM-UGP-PFS-47367-CS- INDV / Consultant individuel chargé IDA / 52240 Public Works Program Pilot A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-03-30 2018-04-04 2018-04-18 2018-04-28 2018-05-28 d'actualiser la carte des THIMO du Projet Filets Sociaux CM-UGP-PFS-47368-CS- INDV / Consultants Cash Transfer Program individuels (3) chargés du with Accompanying ciblage des bénéficiaires de IDA / 52240 A posteriori Individuel Open 20,256.00 0.00 Annulé 2018-04-06 2018-05-09 2018-05-23 2018-06-02 2018-07-17 Measures to Boost la phase 3 des transferts Household Productivity monétaires d'urgence dans la région du Nord Ouest CM-UGP-PFS-47363-CS- INDV / Consultants individuels (03) chargés de Cash Transfer Program compléter et d'améliorer les with Accompanying manuels de formation et de IDA / 52240 A posteriori Individuel Open 63,040.00 87,765.09 Signé 2018-03-09 2018-04-14 2018-04-28 2018-05-12 2019-05-12 Measures to Boost former les bénéficiaires sur Household Productivity les AGR pour le cycle 2 des transferts monétaires du Projet Filets CM-UGP-PFS-47362-CS- Cash Transfer Program INDV / Consultant with Accompanying individuel chargé de la IDA / 52240 A posteriori Individuel Open 8,250.00 7,158.24 Signé 2018-03-15 2018-04-17 2018-04-24 2018-04-30 2019-04-30 Measures to Boost traduction des documents Household Productivity du projet en anglais CM-UGP-PFS-25526-CS- INDV / Consultant chargé Laying the Foundations of de l'accompagnement en a Safety Net System and IDA / 52240 A posteriori Individuel Open 12,000.00 0.00 Annulé 2017-09-15 2017-10-11 2017-10-16 2017-10-24 2018-10-24 TOM2PRO, TOM2PAIE, Supporting Project TOM2MONITORING et Management TOM2MARCHE CM-UGP-PFS-25881-CS- Laying the Foundations of INDV / Consultant chargé a Safety Net System and IDA / 52240 A posteriori Individuel Open 8,250.00 7,201.62 Achevé 2018-04-17 2018-05-13 2018-05-20 2018-06-17 2018-12-14 du développement du site Supporting Project WEB Management Laying the Foundations of CM-UGP-PFS-16899-CS- a Safety Net System and INDV / Avenant au contrat IDA / 52240 A posteriori Individuel Open 76,190.00 71.57 Signé 2017-10-02 2017-10-13 2017-10-18 2017-10-23 2019-10-13 Supporting Project de l'auditeur interne Management Cash Transfer Program CM-UGP-PFS-47928-CS- with Accompanying INDV / Assistant au suivi IDA / 52240 A posteriori Individuel Open 12,000.00 10,966.15 Signé 2018-04-20 2018-05-30 2018-06-13 2018-07-04 2019-07-04 Measures to Boost évaluation Household Productivity CM-UGP-PFS-47923-CS- Cash Transfer Program INDV / Recrutement d'un with Accompanying IDA / 52240 A posteriori Individuel Open 12,000.00 13,228.50 Signé 2018-04-04 2018-05-07 2018-05-21 2018-06-18 2019-06-18 Spécialiste en Passation des Measures to Boost Marché Assistant Household Productivity Page 8 CM-UGP-PFS-54610-CS- INDV / consultant Cash Transfer Program individuel pour l'assistance with Accompanying à la migration comptable IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-04-16 2018-04-21 2018-05-12 2018-06-16 2018-12-13 Measures to Boost vers le nouveau référentiel Household Productivity comptable SYSCOHADA révisé CM-UGP-PFS-54615-CS- INDV / consultant pour Cash Transfer Program assister l'UGP à l'utilisation with Accompanying IDA / 52240 A posteriori Individuel Limited 8,250.00 10,408.76 Signé 2018-04-20 2018-04-25 2018-05-16 2018-06-20 2019-06-20 optimale des logiciels Measures to Boost TOM2PRO, TOM2PAIE et Household Productivity TOM2MARCHE CM-UGP-PFS-54616-CS- INDV / Consultant pour la conception du masque de Cash Transfer Program saisie, la supervision de la with Accompanying IDA / 52240 A posteriori Individuel Limited 8,250.00 7,097.50 Signé 2018-04-25 2018-04-30 2018-05-21 2018-06-25 2018-12-22 saisie et l'analyse des Measures to Boost données de la première Household Productivity évaluation interne du Projet IDA CM-UGP-PFS-47366-CS- INDV / Consultant Cash Transfer Program individuel chargé with Accompanying d'actualiser la carte de IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-04-30 2018-05-05 2018-05-19 2018-05-29 2018-06-28 Measures to Boost pauvreté pour les transferts Household Productivity monétaires du Projet Filets Sociaux CM-UGP-PFS-47370-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de du point focal du Projet with Accompanying IDA / 52240 A posteriori consultants par Direct 3,600.00 3,181.63 Signé 2018-04-20 2018-04-27 2018-05-03 2018-10-30 dans le Département du Measures to Boost entente directe Mberé, région de Household Productivity l'Adamaoua CM-UGP-PFS-25974-CS- CQS / Contrat ONG pour Sélection de la phase 6 des THIMO IDA / 52240 Public Works Program Pilot A posteriori consultants par Direct 99,042.50 85,366.88 Achevé 2018-05-30 2018-06-09 2018-07-30 2019-01-26 pour 3000 bénéficiaires dans entente directe 2 communes de la région du Nord CM-UGP-PFS-47376-CS- INDV / Avenant au contrat de l'opérateur de terrain de Cash Transfer Program Sélection de la commune de la commune with Accompanying IDA / 52240 A posteriori consultants par Direct 2,430.00 2,169.08 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 de la commune de kai kai Measures to Boost entente directe département du Mayo Household Productivity Danay, région de l'extrême Nord CM-UGP-PFS-47377-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 la commune de Méri, Measures to Boost entente directe département du Diamaré, Household Productivity région de l'Extrême Nord CM-UGP-PFS-47378-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 la commune de Ndoukoula, Measures to Boost entente directe département du Diamaré, Household Productivity région de l'Extrême Nord CM-UGP-PFS-47379-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,430.00 2,169.08 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 la commune de Guider, Measures to Boost entente directe département du Mayo Louti, Household Productivity région du Nord CM-UGP-PFS-47430-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 la commune de Lagdo, Measures to Boost entente directe département de la Bénoué, Household Productivity région du Nord CM-UGP-PFS-47431-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain N° Sélection de with Accompanying 1 de la commune de IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 Measures to Boost Bibemi (ADAMOU entente directe Household Productivity Bienvenu), département de la Bénoué, région du Nord CM-UGP-PFS-47432-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain N° Sélection de with Accompanying 2 de la commune de IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 Measures to Boost Bibemi (GOUDOUM entente directe Household Productivity GRANA Dieunedort), département de la Bénoué, région du Nord CM-UGP-PFS-47433-CS- INDV / Avenant au contrat de l'opérateur de terrain de Cash Transfer Program la commune de Kar Hay Sélection de with Accompanying pour la commune de IDA / 52240 A posteriori consultants par Direct 8,100.00 8,495.18 Signé 2018-04-18 2018-04-22 2018-04-28 2019-04-28 Measures to Boost Makary dans le entente directe Household Productivity département du Logone et Chari, région de l'Extrême Nord CM-UGP-PFS-47434-CS- Cash Transfer Program INDV / Avenant au contrat Sélection de with Accompanying de la secrétaire de IDA / 52240 A posteriori consultants par Direct 16,800.00 15,497.59 Signé 2018-04-24 2018-04-28 2018-05-04 2019-12-30 Measures to Boost l'antenne régionale de entente directe Household Productivity l'Extrême Nord CM-UGP-PFS-47435-CS- Cash Transfer Program INDV / Avenant au contrat with Accompanying IDA / 52240 A posteriori Individuel Direct 11,340.00 7,980.91 Signé 2018-03-05 2018-03-12 2018-03-17 2018-03-25 2019-12-15 du chauffeur de l'antenne Measures to Boost régionale du Nord Household Productivity CM-UGP-PFS-47369-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de du point focal du with Accompanying IDA / 52240 A posteriori consultants par Direct 3,600.00 3,188.07 Signé 2018-04-25 2018-04-29 2018-05-05 2018-11-01 département du Diamaré Measures to Boost entente directe dans la région de l'Extrême Household Productivity Nord Page 9 CM-UGP-PFS-47371-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain Sélection de with Accompanying N°1 de la commune de DIR IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 Measures to Boost (HEBGASSO Jean entente directe Household Productivity Baptiste) département du Mbéré, région de l'Adamaoua CM-UGP-PFS-47372-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain N° Sélection de with Accompanying 2 de la Commune de Dir IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 Measures to Boost (HOULAO Pierre) entente directe Household Productivity département du Mbéré, région de l'Adamoua CM-UGP-PFS-47375-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain Sélection de with Accompanying N°2 de la commune de IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 Measures to Boost BOGO( Wanie Bernard) entente directe Household Productivity département du Diamaré, région de l'Extrême Nord CM-UGP-PFS-47373-CS- INDV / Avenant au contrat Cash Transfer Program de l'opératrice de terrain Sélection de with Accompanying N°1 de la commune de IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 2018-04-28 2018-05-04 2018-10-31 Measures to Boost BOGO, département du entente directe Household Productivity Diamaré, région de l'Extrême Nord CM-UGP-PFS-59671-CS- Cash Transfer Program Sélection de CDS / Opérateur de terrain with Accompanying IDA / 52240 A posteriori consultants par Direct 3,240.00 2,391.05 Signé 2018-04-30 2018-05-10 2018-05-19 2018-11-15 de la commune de Douala Measures to Boost entente directe 4 Household Productivity CM-UGP-PFS-59673-CS- Cash Transfer Program INDV / Recrutement du with Accompanying Responsable régional de IDA / 52240 A posteriori Individuel Open 19,200.00 16,630.56 Signé 2018-05-04 2018-06-06 2018-06-13 2018-06-22 2019-06-22 Measures to Boost l'antenne du Nord du Projet Household Productivity Filets Sociaux CM-UGP-PFS-59789-CS- CDS / Audit financier et comptable des comptes du Projet de Remise à niveau Cash Transfer Program des Réseaux de Transport Sélection de with Accompanying d'Electricité et Réforme du IDA / 52240 A posteriori consultants par Direct 54,000.00 46,581.42 Signé 2018-04-26 2018-04-30 2018-05-14 2020-05-13 Measures to Boost Secteur (PRRTERS): entente directe Household Productivity exercices 2017-2018 - 2019 et du Projet Filets Sociaux (PFS) : exercices 2017-2018 CM-UGP-PFS-67474-CS- CDS / Avenant au contrat Laying the Foundations of Sélection de de l'opérateur de terrain de a Safety Net System and IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé 2018-06-29 2018-07-03 2018-07-09 2019-01-05 la commune de Yaoundé Supporting Project entente directe 1er NGO SICK ELEANOR Management RHOLY épouse KAM CM-UGP-PFS-67475-CS- CDS / Avenant au contrat Laying the Foundations of de l'opérateur de terrain de Sélection de a Safety Net System and la commune de Funfong, IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé 2018-06-29 2018-07-03 2018-07-09 2019-01-05 Supporting Project département du Boyo région entente directe Management du Nord Ouest AGHA-AH EVARISTUS ALANJI CM-UGP-PFS-67477-CS- CDS / Avenant au contrat de l'opérateur de terrain de Laying the Foundations of Sélection de la commune de Balikumbat a Safety Net System and IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé 2018-06-29 2018-07-03 2018-07-09 2019-01-05 département du Ngo Supporting Project entente directe Ketungja région du Nord Management Ouest TAJIPUKU ALPHONSE TAMIGHANG CM-UGP-PFS-67478-CS- CDS / avenant au contrat de l'opérateur de terrain N1 Laying the Foundations of Sélection de de la commune de a Safety Net System and IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé 2018-06-29 2018-07-03 2018-07-09 2019-01-05 Messamena département du Supporting Project entente directe Haut Nyong région de l'Est Management TSALA MVOGO BERNARD JEAN CM-UGP-PFS-67479-CS- Laying the Foundations of CDS / Avenant au contrat Sélection de a Safety Net System and du point focal du IDA / 52240 A posteriori consultants par Direct 4,800.00 4,195.15 Signé 2018-06-29 2018-07-03 2018-07-09 2019-01-05 Supporting Project département du Haut entente directe Management Nyong région de l'Est MBILLA Pierre Valery CM-UGP-PFS-67481-CS- CDS / avenant au contrat Laying the Foundations of de l'opérateur de terrain Sélection de a Safety Net System and N°2 de la commune de IDA / 52240 A posteriori consultants par Direct 2,160.00 1,887.82 Signé 2018-07-02 2018-07-06 2018-07-12 2018-11-09 Supporting Project Messamena ESSOMBA entente directe Management YANNICK ALBERT NGUEM CM-UGP-PFS-67482-CS- CDS / Avenant au contrat Laying the Foundations of de l'opérateur de terrain Sélection de a Safety Net System and N°2 de la commune de IDA / 52240 A posteriori consultants par Direct 540.00 471.95 Achevé 2018-06-29 2018-07-03 2018-07-08 2018-08-07 Supporting Project Lagdo, département de la entente directe Management Bénoué, région du Nord SIRINA ELVIS CM-UGP-PFS-67517-CS- Laying the Foundations of Sélection de INDV / Responsable a Safety Net System and IDA / 52240 A posteriori consultants par Direct 38,095,248.00 0.00 Annulé 2018-06-29 2018-07-04 2018-07-11 2019-07-11 Administratif et Financier Supporting Project entente directe du Projet Management CM-UGP-PFS-72586-CS- Laying the Foundations of INDV / Recrutement d'un a Safety Net System and IDA / 52240 A posteriori Individuel Direct 5,940.00 5,136.94 Signé 2018-08-23 2018-09-02 2018-09-23 2018-10-28 2019-10-28 opérateur de terrain pour la Supporting Project commune de Koza Management CM-UGP-PFS-81429-CS- INDV / consultants national sénior chargé d'appuyer la Laying the Foundations of Banque mondiale et le a Safety Net System and Projet Filets Sociaux dans IDA / 52240 A posteriori Individuel Limited 24,600.00 21,307.91 Achevé 2018-10-18 2018-10-25 2018-11-15 2018-12-20 2019-03-20 Supporting Project la préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun Page 10 CM-UGP-PFS-83718-CS- Laying the Foundations of INDV / Responsable a Safety Net System and IDA / 52240 A posteriori Individuel Open 38,096.00 32,568.58 Signé 2018-11-11 2018-12-30 2019-01-20 2019-02-24 2021-02-23 Administratif et Financier Supporting Project du Projet Filets Sociaux Management CM-UGP-PFS-83719-CS- Laying the Foundations of INDV / Expert en a Safety Net System and IDA / 52240 A posteriori Individuel Open 38,095.00 25,544.73 Signé 2018-11-11 2018-12-30 2019-01-20 2019-02-24 2020-02-24 sauvegardes sociales du Supporting Project Projet Filets Sociaux Management CM-UGP-PFS-83720-CS- Laying the Foundations of INDV / coach du a Safety Net System and responsable des activités IDA / 52240 A posteriori Individuel Open 38,095.00 19,480.26 Signé 2018-11-18 2019-01-06 2019-01-27 2019-03-03 2019-08-30 Supporting Project d'accompagnement du Projet Management Filets Sociaux CM-UGP-PFS-83722-CS- Laying the Foundations of INDV / Assistant en a Safety Net System and IDA / 52240 A posteriori Individuel Open 14,400.00 10,329.66 Signé 2018-11-18 2019-01-06 2019-01-27 2019-03-03 2020-03-02 Gestion des Ressources Supporting Project Humaines et du matériel Management CM-UGP-PFS-83723-CS- Laying the Foundations of INDV / Assistant au a Safety Net System and Responsable du Systeme IDA / 52240 A posteriori Individuel Open 14,400.00 9,119.51 Signé 2018-11-18 2019-01-06 2019-01-27 2019-03-03 2020-03-02 Supporting Project d'Information Management du Projet Filets Sociaux MOF-CM-UGP-PFS-14460- Laying the Foundations of Sélection de CS-CDS / Avenant au a Safety Net System and IDA / 52240 A posteriori consultants par Direct 3,240.00 2,785.30 Signé 2017-06-09 2017-06-13 2017-06-16 2017-12-13 contrat de l'opératrice de Supporting Project entente directe terrain de la commune de Management Douala 2 MOF-UGP-PFS-14463-CS- Laying the Foundations of Sélection de CDS / Avenant au contrat a Safety Net System and IDA / 52240 A posteriori consultants par Direct 12,960.00 25,147.34 Signé 2017-01-12 2017-06-12 2017-06-23 2019-06-23 de l'operateur de terrain de Supporting Project entente directe Yaoundé 7 Management MOF-UGP-PFS-14490-CS- Laying the Foundations of Sélection de CDS / Avenant au contrat a Safety Net System and IDA / 52240 A posteriori consultants par Direct 16,800.00 14,442.29 Signé 2017-06-15 2017-06-23 2017-07-02 2019-07-02 de Technicienne de surface Supporting Project entente directe de l'UGP Management MOF-CM-UGP-PFS-6421-CS- Laying the Foundations of INDV / Expert a Safety Net System and IDA / 52240 A posteriori Individuel Open 63,840.00 81,486.50 Signé 2017-02-17 2017-04-07 2017-04-28 2017-06-02 2019-06-02 environnemental et social Supporting Project du PFS Management Laying the Foundations of MOF-CM-UGP-PFS-6423-CS- a Safety Net System and IDA / 52240 A posteriori Individuel Open 9,600.00 27,305.89 Signé 2017-02-07 2017-03-28 2017-04-18 2017-05-23 2018-05-23 INDV / Assistant Comptable Supporting Project Management Laying the Foundations of MOF-CM-UGP-PFS-6424-CS- a Safety Net System and IDA / 52240 A posteriori Individuel Open 9,600.00 6,156.07 Résilié 2017-02-07 2017-03-28 2017-04-18 2017-05-23 2018-05-23 INDV / Assistant SPM Supporting Project Management Laying the Foundations of CM-UGP-PFS-108883-CS- a Safety Net System and INDV / Auditeur interne du IDA / 52240 A posteriori Individuel Open 45,714.00 29,878.57 Signé 2019-04-19 2019-06-16 2019-07-07 2019-08-04 2020-08-03 Supporting Project Projet Filets Sociaux Management CM-UGP-PFS-111619-CS- CDS / Avenant N°01 au Cash Transfer Program contrat de l'Opérateur de Sélection de with Accompanying Terrain 1 de la Commune IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé 2019-05-22 2019-06-01 2019-08-05 2019-12-05 Measures to Boost de Banyo, Département du entente directe Household Productivity Mayo Banyo, Région de l'Adamaoua CM-UGP-PFS-111629-CS- CDS / Avenant Contrat de Cash Transfer Program l'Opérateur de Terrain 2 de Sélection de with Accompanying la Commune de Banyo, IDA / 52240 A posteriori consultants par Direct 2,160.00 1,845.59 Signé 2019-05-22 2019-06-01 2019-08-05 2019-12-05 Measures to Boost Département du Mayo entente directe Household Productivity Banyo, Région de l'Adamaoua CM-UGP-PFS-111638-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,898.00 2,459.26 Signé 2019-05-22 2019-06-01 2019-08-05 2020-01-16 la Commune de Bélo, Measures to Boost entente directe Département du Boyo, Household Productivity Région du Nord-Ouest CM-UGP-PFS-111640-CS- Cash Transfer Program CDS / Avenant au contrat Sélection de with Accompanying de l'Opérateur de Terrain 1 IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 2019-06-01 2019-08-05 2020-01-16 Measures to Boost de Douala IIIe, Ville de entente directe Household Productivity Douala CM-UGP-PFS-111642-CS- Cash Transfer Program CDS / Avenant de Sélection de with Accompanying l'Opérateur de Terrain 2 de IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 2019-06-01 2019-08-05 2020-01-16 Measures to Boost la Commune de Douala entente directe Household Productivity IIIe, Ville de Douala CM-UGP-PFS-111643-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain 1 de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 2019-06-01 2019-08-05 2020-01-16 la Commune de Ketté, Measures to Boost entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111658-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain 2 de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 2019-06-01 2019-08-05 2020-01-16 la Commune de Ketté, Measures to Boost entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111662-CS- Cash Transfer Program CDS / Avenant contrat de Sélection de with Accompanying l'Opératrice de Terrain 1 de IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 2019-06-01 2019-08-05 2020-01-16 Measures to Boost la Commune de Yaoundé entente directe Household Productivity IIe, Ville de Yaoundé CM-UGP-PFS-111664-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying la Commune de Blangoua, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 2019-06-01 2019-08-05 2019-11-04 Measures to Boost Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord Page 11 CM-UGP-PFS-111670-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying la Commune de Bourha, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 2019-06-01 2019-08-05 2019-11-04 Measures to Boost Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111678-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying la Commune de Gobo, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 2019-06-01 2019-08-05 2019-11-04 Measures to Boost Département du Mayo entente directe Household Productivity Danay, Région de l'Extrême- Nord CM-UGP-PFS-111681-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying la Commune de Goulfey, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 2019-06-01 2019-08-05 2019-11-04 Measures to Boost Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111685-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying la Commune de Koza, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 2019-06-01 2019-08-05 2019-11-04 Measures to Boost Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111688-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying la Commune de Makari, IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé 2019-05-22 2019-06-01 2019-08-05 2020-05-06 Measures to Boost Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111691-CS- CDS / Avenant de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying la Commune de Mogodé, IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé 2019-05-22 2019-06-01 2019-08-05 2020-05-06 Measures to Boost Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111692-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé 2019-05-22 2019-06-01 2019-08-05 2019-12-05 la Commune de Mayo Oulo, Measures to Boost entente directe Département du Mayo Household Productivity Louti, Région du Nord CM-UGP-PFS-111696-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé 2019-05-22 2019-06-01 2019-08-05 2020-05-06 la Commune de Rey Bouba, Measures to Boost entente directe Département du Mayo Rey, Household Productivity Région du Nord CM-UGP-PFS-111698-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying IDA / 52240 A posteriori consultants par Direct 4,898.00 4,124.22 Signé 2019-05-22 2019-06-01 2019-08-05 2020-05-06 la Commune de Tchéboa, Measures to Boost entente directe Département de la Bénoué, Household Productivity Région du Nord CM-UGP-PFS-111699-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain 1 de with Accompanying IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé 2019-05-22 2019-06-01 2019-08-05 2019-12-05 la Commune de Touboro, Measures to Boost entente directe Département du Mayo Rey, Household Productivity Région du Nord CM-UGP-PFS-111725-CS- CDS / Avenant contrat Cash Transfer Program Sélection de Point Focal du Projet Filets with Accompanying IDA / 52240 A posteriori consultants par Direct 4,293.00 22,491.60 Signé 2019-05-22 2019-06-01 2019-08-05 2020-01-16 Sociaux dans le Measures to Boost entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111726-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Filets Sélection de with Accompanying Sociaux dans le IDA / 52240 A posteriori consultants par Direct 7,200.00 6,109.96 Signé 2019-05-22 2019-06-01 2019-08-05 2020-05-06 Measures to Boost Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111727-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Filets Sélection de with Accompanying Sociaux dans le IDA / 52240 A posteriori consultants par Direct 3,200.00 2,715.54 Signé 2019-05-22 2019-06-01 2019-08-05 2019-12-05 Measures to Boost Département du Mayo entente directe Household Productivity Banyo, Région de l'Adamaoua CM-UGP-PFS-111735-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Filets Sélection de with Accompanying Sociaux dans le IDA / 52240 A posteriori consultants par Direct 2,400.00 2,036.65 Signé 2019-05-22 2019-06-01 2019-08-05 2019-11-04 Measures to Boost Département du Mayo entente directe Household Productivity Danay, Région de l'Extrême- Nord CM-UGP-PFS-111737-CS- CDS / Avenant contrat Cash Transfer Program Sélection de Point Focal du Projet Filets with Accompanying IDA / 52240 A posteriori consultants par Direct 7,200.00 6,109.96 Signé 2019-05-22 2019-06-01 2019-08-05 2020-05-06 Sociaux dans le Measures to Boost entente directe Département Mayo Tsanaga, Household Productivity Région de l'Extrême-Nord CM-UGP-PFS-111739-CS- Cash Transfer Program CDS / Avenant contrat Sélection de with Accompanying Point Focal du Projet Filets IDA / 52240 A posteriori consultants par Direct 4,293.00 22,491.60 Signé 2019-05-22 2019-06-01 2019-08-05 2020-01-16 Measures to Boost Sociaux dans la Ville de entente directe Household Productivity Yaoundé CM-UGP-PFS-121795-CS- CDS / Consultant chargé de l'élaboration de la Laying the Foundations of Sélection de méthodologie de choix et a Safety Net System and En attente IDA / 62230 A posteriori consultants par Direct 28,000.00 0.00 2019-11-30 2019-12-19 2020-02-13 2020-03-14 d’opérationnalisation du Supporting Project d'exécution entente directe choix des communes Management bénéficiaires du Projet Filets Sociaux Page 12 CM-UGP-PFS-141084-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente la Région de l'Adamaoua IDA / D2980 A posteriori Individuel Open 38,400.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 Supporting Project d'exécution pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141091-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente IDA / D2980 A posteriori Individuel Open 38,400.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 la Région de l'Est pour la Supporting Project d'exécution cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141097-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 38,400.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 la Région du SUD pour la Supporting Project d'exécution cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141107-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente la Région du SUD-OUEST IDA / 62230 A posteriori Individuel Open 38,400.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 Supporting Project d'exécution pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141118-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente Secrétaire de l'antenne IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2020-01-06 2020-03-02 2020-03-23 2020-04-27 2022-04-27 Supporting Project d'exécution régionale du Sud-Ouest du Management Projet Filets Sociaux CM-UGP-PFS-141123-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente Chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-01-06 2020-03-02 2020-03-23 2020-04-27 2022-04-27 Supporting Project d'exécution régionale du Sud-Ouest du Management Projet Filets Sociaux CM-UGP-PFS-141124-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente Secrétaire de l'antenne IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2020-01-20 2020-03-16 2020-04-06 2020-05-11 2022-05-11 Supporting Project d'exécution régionale Sud du Projet Management Filets Sociaux CM-UGP-PFS-141129-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente Chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-01-06 2020-03-02 2020-03-23 2020-04-27 2022-04-27 Supporting Project d'exécution régionale Sud du Projet Management Filets Sociaux CM-UGP-PFS-141130-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente Secrétaire de l'antenne IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2020-01-06 2020-03-02 2020-03-23 2020-04-27 2022-04-27 Supporting Project d'exécution régionale de l'Est du Projet Management Filets Sociaux CM-UGP-PFS-141131-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente Chauffeur de l'antenne IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-01-06 2020-03-02 2020-03-23 2020-04-27 2022-04-27 Supporting Project d'exécution régionale de l'Est du Projet Management Filets Sociaux CM-UGP-PFS-141133-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente Secrétaire de l'antenne IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2020-01-06 2020-03-02 2020-03-23 2020-04-27 2022-04-27 Supporting Project d'exécution régionale de l'Adamaoua du Management Projet Filets Sociaux CM-UGP-PFS-141134-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente Chauffeur de l'antenne IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-01-06 2020-03-02 2020-03-23 2020-04-27 2022-04-27 Supporting Project d'exécution régionale de l'Adamaoua du Management Projet Filets Sociaux CM-UGP-PFS-141161-CS- INDV / Recrutement de 3 Opérateurs de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente Touboro, département du IDA / D2980 A posteriori Individuel Open 38,880.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 Supporting Project d'exécution Mayo-Rey, région du Nord Management pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141163-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune d'Ebolowa II, a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 département de la Mvila, Supporting Project d'exécution région du Sud pour le cycle Management 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141162-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de a Safety Net System and En attente Meyomessala, Département IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 Supporting Project d'exécution du Dja et Lobo, région du Management Sud pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141164-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Ma'am, a Safety Net System and En attente Département de la Vallée IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 Supporting Project d'exécution du Ntem, région du Sud Management pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141167-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Meiganga, a Safety Net System and En attente IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 département du Mbéré, Supporting Project d'exécution région de l'Adamaoua pour Management la phase 3 des Transferts Monétaires d'Urgence Page 13 CM-UGP-PFS-141168-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Ngaoui, a Safety Net System and En attente IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 département du Mbéré, Supporting Project d'exécution région de l'Adamaoua pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141170-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Waza, a Safety Net System and En attente département du Logone et IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 Supporting Project d'exécution Chari, région de l'Extrême Management Nord pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141171-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Fotokol, a Safety Net System and En attente département du Logone et IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 Supporting Project d'exécution Chari, région de l'Extrême Management Nord pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141173-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Bamenda I, a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 département de MEZAM, Supporting Project d'exécution région du Nord-Ouest pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141174-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Bamenda a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 II, département de MEZAM, Supporting Project d'exécution région du Nord-Ouest pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141176-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Bamenda a Safety Net System and En attente III, département de IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 Supporting Project d'exécution MEZAM, région du Nord- Management Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141178-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Limbé I, a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 département de Fako, Supporting Project d'exécution région du Sud-Ouest pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141179-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Limbé II, a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 département de Fako, Supporting Project d'exécution région du Sud-Ouest pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141180-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Limbé III, a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2019-12-02 2020-01-27 2020-02-17 2020-03-23 2022-03-23 département de Fako, Supporting Project d'exécution région du Sud-Ouest pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141183-CS- INDV / Recrutement d'un Point Focal dans le Laying the Foundations of département du Logone et a Safety Net System and En attente IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2019-12-10 2020-02-04 2020-02-25 2020-03-31 2022-03-31 Chari, région de l'Extrême Supporting Project d'exécution Nord pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141184-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans le a Safety Net System and En attente département du Mayo Rey, IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2019-12-10 2020-02-04 2020-02-25 2020-03-31 2022-03-31 Supporting Project d'exécution région du Nord pour la Management cycle 3 des Transferts Monétaires ordinaires CM-UGP-PFS-141187-CS- INDV / Recrutement d'un Point Focal dans le Laying the Foundations of département du Mayo Kani, a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2019-12-10 2020-02-04 2020-02-25 2020-03-31 2022-03-31 région de l'Extrême Nord Supporting Project d'exécution pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141188-CS- INDV / Recrutement d'un Laying the Foundations of point Focal dans la ville a Safety Net System and En attente de Douala, région du IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2019-12-10 2020-02-04 2020-02-25 2020-03-31 2022-03-31 Supporting Project d'exécution littoral pour la phase 3 Management des Transferts Monétaires ordinaires CM-UGP-PFS-141191-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans la ville de a Safety Net System and En attente IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2019-12-10 2020-02-04 2020-02-25 2020-03-31 2022-03-31 Yaoundé pour la cycle 3 Supporting Project d'exécution des Transferts Monétaires Management ordinaires Page 14