Myanmar: Modernization of Public Financial Management Project Procurement Plan for FY 2017 – 2018 I. General 1. Project information: Country: Myanmar Borrower/Recipient: Ministry of Planning and Finance Project Name: Modernization of Public Financial Management Project Project ID No: P144952 Project Implementing Agencies: 1. Ministry of Planning and Finance, 2. Office of Auditor General of the Union 2. Bank’s approval date of the Procurement Plan: XX May 2017 3. Date of General Procurement Notice: 27 Feb, 2014 4. Period covered by this procurement plan: 12 months (01 April 2017 to 31 March 2018) 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement and Guidelines Selection and Employment of Consultants Type of Market Approaches Thresholds Prior Review Procurement International National- National Comments Threshold Open RFQ (Shopping) Works (Including USD 3m and Less than Less than Recommended to US$ 2 mil. turnkey supply and above US$3m US$1m advertise for 7 days for installation of plant RFQ above USD 50,000. and equipment) Goods, information USD 1m and Less than Less than Recommended to US$ 1 mil. technology and non- above US$1m US$0.5m advertise for 7 days for consulting services RFQ above USD 50,000. Consultants (Firms) USD 0.1m Less than Not CQS method may be US$ 0.3 mil. and above US$0.1m applicable used up to USD 500,000. Use of full RFP mandatory for CQS above USD 300,000. Limits on market approaches do not apply to individual consultants. Consultant US$ 0.2 mil. (Individuals) 2. Procurement of all contracts for Goods financed wholly or partially by the project will be carried out through the applicable procurement methods in accordance with the thresholds in the above table and as defined against each contract package in the procurement plan. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Any Other Special Selection Arrangements: N/A Procurement Packages with Methods and Time Schedule Packages Covering All Implementation Agencies 1 2 3 4 5 6 7 8 9 Estimated Review by Expected Ref. No. Pre- Domestic Cost Procurement Bank Bid- Implementing and/or MPFMp- Contract (Description) qualification Preference Package Method (Prior/ Opening Beneficiary Unit/s MIAs- (yes/no) (yes/no) (US$) Post) Date Nil Sub Total US$ 0 Procurement Packages with Methods and Time Schedule Internal Revenue Department (A) 1 2 3 4 5 6 7 8 9 Estimated Review Expected Ref. No. Pre- Domestic Contract Cost Procurement by Bank Bid- Implementing and/or MPFMp- qualification Preference (Description) Package Method (Prior/ Opening Beneficiary Unit/s MIAs- (yes/no) (yes/no) (US$) Post) Date Information Systems for Integrated Tax Administration System ICB- – COTS development/ Internal Revenue 7,500,000 ICB IS2S No No Prior Jul-17 IS301 customization, supply, Department and implementation (Software and Associated Hardware) Sub Total US$ 7,500,000 Procurement Packages with Methods and Time Schedule Budget Department (B1) 1 2 3 4 5 6 7 8 9 Expected Implementing Ref. No. Pre- Domestic Review by Estimated Cost Procurement Bid- and/or MPFMp- Contract (Description) qualification Preference Bank Package (US$) Method Opening Beneficiary B1 (yes/no) (yes/no) (Prior/Post) Date Unit/s Budget Direct Department GS302 Books for Mini Library 1,000 No No Post Oct-17 (Package GS203 Contracting brought forward from PP No 3) Lot 1: All-in-One Desktop Computer for Mini Library (5 Budget nos) Department GS303 Lot 2: Notebook Computer (5 23,000 Shopping No No Post Dec-17 (Package GS202 brought forward nos) from PP No 3 Lot 3: Tablets for Mini-Library and merged) (10 nos) Lot 1: High volume Scanner (11 Shopping Budget GS304 nos) 155,000 No No Post Nov-17 Advertised Department Lot 2: Motorized scanner (1 no) Lot 1 - Copiers Item 1: Copier machine (8 nos) Item 2: Copier with Binder (4 nos) Item 3: Copy Printer A3 (1 no) Lot 2 – Duplicator machine (2 Shopping Budget GS305 175,000 No No Post Oct-17 nos) Advertised Department Lot 3 – Printers Item 1 – Laser Printer (30 nos) Item 2 – Color Inkjet Printer (10 nos) Budget GS306 Office Furniture for Staff 50,000 Shopping No No Post Oct-17 Department Electrical Equipment Lot 1: Online UPS (3 nos) Budget GS307 40,000 Shopping No No Post Oct-17 Lot 2: Ethernet Router (2 nos) Department Lot 3: CCTV Camera (5 nos) Budget GS308 Software for Office application 42,000 Shopping No No Post Oct-17 Department Sub Total US$ 486,000 Procurement Packages with Methods and Time Schedule Planning Department (B2) 1 2 3 4 5 6 7 8 9 Expected Ref. No. Pre- Domestic Review by Implementing Procurement Bid- MPFMp- Contract (Description) Estimated qualification Preference Bank and/or Beneficiary Method Opening B2- Cost (US$) (yes/no) (yes/no) (Prior/Post) Unit/s Date Planning Dept Lot 1: States & Region Data Communication Equipment: Offices 36 nos, Self Admin zones & GS309 Lot 1: 3G Modems (122 nos) 6,000 Shopping No No Post Aug-17 District offices 86 nos. Lot 2: Switch 24 ports (5 nos) (Package GS204 from PP No 3 brought forward) Electrical Power Equipment: Planning Department (O) Dec 15 Lot 1: Electrical Transformer (1 GS310 18,000 Shopping No No Post (R) Dec-16 (Package GS205 no) (R) Jul-17 brought forward from Lot 2: Electrical Generator (1 no) PP No 3) Planning Department H.O. 50 nos, States & Region Offices 6 nos Shopping Self Admin zones & GS311 Desktop Computers (130 nos) 275,000 No No Post Jul-17 Distt offices 74 nos Advertised (Package GS207 brought forward from PP No 3 and merged) Item 1: Laser Printer (50 nos) GS312 Item 2: Colour Copier (1 no) 30,000 Shopping No No Post Oct-17 Planning Department Item 3: Projector (1 no) GS313 Air Conditioners (15 nos) 7,500 Shopping No No Post Oct-17 Planning Department WS314 Renovation of Training Room 8,500 Shopping Works No No Post Sep-17 Planning Department PAPRD Lot 1: Laptop Computers (25 nos) GS315 94,000 Shopping No No Post Sep-17 PAPRD Lot 2: Server with software Refurbishing of Training room GS316 2,500 Shopping No No Post Sep-17 PAPRD (wall paper) GS317 Drone (2 nos) 2,800 Shopping No No Post Nov-17 PAPRD Furniture: Item 1: Table for teachers (2 nos) Item 2: Computer tables (25 nos) GS318 5,000 Shopping No No Post Aug-18 PAPRD Item 3: Chair with arms (2 nos) Item 4: Chair w.o. arms (20 nos) Item 5: Wood file cabinet (2 nos) Sub Total US$ 449,300 Procurement Packages with Methods and Time Schedule Treasury Department (C1) 1 2 3 4 5 6 7 8 9 Expected Implementing Ref. No. Pre- Domestic Review by Procurement Bid- and/or MPFMp- Contract (Description) Estimated qualification Preference Bank Method Opening Beneficiary C1- Cost (US$) (yes/no) (yes/no) (Prior/Post) Date Unit/s Treasury Building Renovation for Shopping Department WS319 15,000 No No Post Jul-17 (Package WS217 Training & Meeting rooms Works brought forward from PP No 3) Treasury GS320 Air Conditioners (20 nos) 17,000 Shopping No No Post Aug-17 Department Furniture Item 1: Steel Cabinet (20 nos) Item 2: File Shelf (10 nos) Treasury GS321 Item 3: Table (30 nos) 31,000 Shopping No No Post Dec-17 Department Item 4: Chairs (40 nos) Item 5: Meeting table & chairs (2 sets) Treasury GS322 Net Book/Laptop (10 nos) 10,000 Shopping No No Post Dec-17 Department Meeting room Conference Treasury GS323 15,000 Shopping No No Post Dec-17 system (2 sets) Department Treasury GS324 Generator Switch & accessories 8,000 Shopping No No Post May-16 Department Treasury Server Room IT Equipment and Department Infrastructure Shopping GS325 272,000 No No Prior Feb-17 Status: (Supply of Hardware, Software, Advertised Bid advertised on installation, configuration, 8 Feb 2017, commissioning, operational Bids opening 21 managed services. Mar 2017 (Package GS239 IT Equipment – Servers, SAS brought forward Storage, Switches, Network devices, from PP No 3) Firewalls, Eqpt racks. Software – Windows Server software, Sharepoint, SQL/Database, Cloud, Enterprise Virtualization. Infrastructure – UPS, Automatic Voltage Stabilizer, Power Distbn utilities, Precision air conditioning, access Control, CCTV.) Sub Total US$ 368,000 Procurement Packages with Methods and Time Schedule Myanmar Economic Bank (C2) 1 2 3 4 5 6 7 8 9 Expected Implementing Ref. No. Pre- Domestic Review by Procurement Bid- and/or MPFMp- Contract (Description) Estimated qualification Preference Bank Method Opening Beneficiary C2- Cost (US$) (yes/no) (yes/no) (Prior/Post) Date Unit/s Status: Revised draft bid document submitted to WB IS326 Core Banking Solution 5,000,000 ICB-IS2S No No Prior Jun-17 on 3 Mar 2017 (Package IS218 brought forward from PP No 3) Remote location Recovery Data Myanmar GS327 2,140,000 ICB-IS1S No No Prior Dec-17 Centre Economic Bank Air conditioners Myanmar GS328 Lot 1: Stand type (4 nos) 80,200 Shopping No No Post Oct-17 Economic Bank Lot 2: Split type (166 nos) IT Equipment Lot 1: Desktop Computers (225 Myanmar nos) Economic Bank GS329 Lot 2: Desktop Servers (75 nos) 1,460,000 ICB No No Prior Jun-17 (Package GS240 brought forward Lot 3: Laptop Computers (20 nos) from PP No 3 Lot 4: Routers (75 nos) and merged) Lot 5: Online UPS (150 nos) Myanmar GS330 Furniture 5,000 Shopping No No Post Oct-17 Economic Bank Subtotal US$ 8,685,200 Procurement Packages with Methods and Time Schedule Joint Public Accounts Committee (D1) 1 2 3 4 5 6 7 8 9 Expected Implementing Ref. No. Pre- Domestic Review by Estimated Procurement Bid- and/or MPRMp- Contract (Description) qualification Preference Bank Cost Method Opening Beneficiary D1- (yes/no) (yes/no) (Prior/Post) (US$) Date Unit/s GS331 Furniture for Office 69,000 Shopping No No Post Sep-17 JPAC IT Equipment Lot 1: Desktop Computers (25 nos) Lot 2: Laptop Computers (30 nos) GS332 Lot 3: Printers (Item 1: Colour printer 80,000 Shopping No No Post Jan-18 JPAC Qty 5 nos; Item 2: Heavy duty printers Qty 2 nos; Item 3: Copier Qty 8 nos) Lot 4: Scanner (Qty 5 nos) Electronic Equipment: Item 1: Telephone (7 nos) Item 2: Headphones (25 nos) JPAC GS333 4,000 Shopping No No Post May-17 Item 3: 1TB Ext. Hard disk (5 nos) Item 4: Ext. CD/DVD Drive (2 nos) Item 5: Television set (3 nos) Direct Contracting GS334 Reference Books for PAC 15,000 No No Post May-17 JPAC (Several, each <$5000) Diesel Electric Generator 150kVA for GS335 26,000 Shopping No No Post Nov-17 JPAC Data Centre IT Infrastructure Upgrading of Hluttaw: Network (Media converter, Fibre cabling, Firewall, VPN, SAN switch, LAN switch, Transceivers, Fbric-enables 48 port switch, PAC-Rack, Wireless AP) Equipment Racks Software (Resource management software, Analytical reporting software, Help Desk software, Data analysis software, Windows Server 2012 for Data Center, Microsoft Sharepoint (200 users), Shopping GS336 Microsoft SQL Server Database, Antivirus 275,000 No No Post Nov-17 Advertised for Server, MS Exchange (200 users) Data Security System LAN Wiring for Pyithu PAC and Amyotha PAC Server (10G Transceiver, HP BL460c Gen9 Blade Server, Direct connect SAS Storage, HP 6Gb BL Switch, HP BLc VC Flex Module fiber connectors, 16 Port HP KVM IP switches) SAN Storage Subtotal US$ 469,000 Procurement Packages with Methods and Time Schedule Office of Auditor General (D2) 1 2 3 4 5 6 7 8 9 Review Expected Implementing Ref. No. Estimated Pre- Domestic by Procureme Bid- and/or MPFM Contract (Description) Cost qualificatio Preference Bank nt Method Opening Beneficiary p-D2- (US$) n (yes/no) (yes/no) (Prior/ Date Unit/s Post) Direct GS337 Book drive scanner (1 no) 2,200 No No Post Aug 17 OAG Contracting Direct GS338 Video camera (1 no) 2,000 No No Post May 17 OAG Contracting Direct GS339 Digital Voice Recorder 1,500 No No Post Jun 17 OAG Contracting IT Equipment: Lot 1: Computers with Licensed Shopping GS340 228,000 No No Post Jul-17 OAG software (100 nos) Advertised Lot 2: Multipurpose copiers (3 nos) GS341 Office Furniture 61,300 Shopping No No Post May-17 OAG Sub Total US$ 295,000 Procurement Packages with Methods and Time Schedule Budget Department (E1) – Public Finance Management Academy 1 2 3 4 5 6 7 8 9 Expected Implementing Ref. No. Pre- Domestic Review by Estimated Cost Procurement Bid- and/or MPFMp- Contract (Description) qualification Preference Bank Package (US$) Method Opening Beneficiary E1 (yes/no) (yes/no) (Prior/Post) Date Unit/s IT Equipment & Office Eqpt Lot 1: Desktop computers (50 Budget Dept nos) with MS Office software; Package Shopping GS342 Lot 2: Projectors (4 nos); Lot 3: 100,000 No No Post Nov-17 GS232 of PP Advertised Integrated copier Fax machine (4 No 3 carried nos) over & merged Lot 3: Multipurpose copier (2 nos) Refurbishing of Class rooms for Budget Dept PFM Academy Package GS343 Lot 1: Remote building 85,000 Shopping No No Post Oct-17 GS233 of PP connection networking No 3 carried Lot 2: Refurbishing of rooms over Budget Dept Direct Package Acquisition of Reference Contracting GS344 10,000 No No Post Feb-18 GS234 of PP materials - Books, Journals (Several, with No 3 carried each < $5000) over Budget Dept Package Video Conferencing System (1 GS345 55,000 Shopping No No Post Dec-17 GS236 of PP set) No 3 carried over Budget Dept Electrical Appliances Package GS346 Item 1: Refrigerator (2 no) 1,500 Shopping No No Post Dec-17 GS237 of PP Item 2: Water Cooler (1 no) No 3 carried over Air Conditioners: GS347 Item 1: Stand type (5 nos) 7,500 Shopping No No Post Dec-17 Budget Dept Item 2: Split type (10 nos) Electrical Transformer with GS348 20,000 Shopping No No Post Dec-17 Budget Dept accessories GS349 Audio system for Learning centre 50,000 Shopping No No Post Jan-18 Budget Dept GS350 Furniture for Class rooms 50,000 Shopping No No Post Jan-18 Budget Dept ICT Server room and Infrastructure: Class room ICT (Work station PCs & UPS, 40 sets; Cisco 48 port switch, LAN wiring, raised floor, Wifi AP) Shopping GS351 Server room ICT (Rack server, HP 160,000 No No Post Dec-18 Budget Dept MSA 2040, Cisco core switches, Advertised Firewall, Precision Air Conditioning system, UPS, stabilizer, Camera monitoring system) Data Wiring Sub Total US$ 539,000 Procurement Packages with Methods and Time Schedule Budget Department (E2) 1 2 3 4 5 6 7 8 9 Expected Implementing Ref. No. Pre- Domestic Review by Estimated Cost Procurement Bid- and/or MPFMp- Contract (Description) qualification Preference Bank Package (US$) Method Opening Beneficiary E2 (yes/no) (yes/no) (Prior/Post) Date Unit/s Nil Sub Total US$ 0 Total for Goods, IS, & Works Packages US$ 18,791,500 Consultancy Assignments with Selection Methods and Time Schedule Expected Estimated Review by Ref. No. Proposal Contract (Description) Costs Selection Method Bank Assignment Implementing Dept. MPFMp- Submission (US$) (Prior/Post) Duration Date Internal Revenue Department Brought forward from earlier Individual Consultant PP No 3, package ref A- A-C301 International Lottery Advisor 145,000 Selection Prior Jan-17 6 months C203. Interviews conducted on 27 Dec 2016. TER submitted to WB on 17 Feb 2017. Internal Revenue Department Brought forward from earlier International Audit Advisor – Individual Consultant PP No 3, package ref A- A-C302 347,000 Selection Prior Jan-17 12 months LTO (Additional) C226. Interviews conducted on 14 Mar 2017. Internal Revenue Department Brought forward from earlier International Audit Advisor – Individual Consultant PP No 3, package ref A- A-C303 347,000 Selection Prior Mar-17 12 months MTO-1 C228. EOIs received up to 11 Mar 2017 International Audit Advisor – Individual Consultant A-C304 347,000 Selection Prior May-17 12 months Internal Revenue Department MTO-1 (Additional) IRD-1, PD-1, OAG-1, BD-2, MIA- MEB-1 National IT consultants to support Individual Consultant 12 months Brought forward from earlier C305 to 192,000 Selection Post May-17 IT Directorate (6 positions) (each) PP No 3, package ref MIA- 310 C221 to C-225. Planning Department National Macroeconomic Individual Consultant Brought forward from earlier B2-C311 40,000 Selection Post May-17 12 months PP No 3, package ref B2- Consultant/Trainer) C207 National Specialist on OTC Individual Consultant Myanma Economic Bank C2-C312 6,000 Selection Post Jul-17 6 months Brought forward from earlier System PP No 3, package ref B2- C213 National IT Specialist for CORE Individual Consultant C2-C313 30,000 Selection Post May-17 12 months Myanma Economic Bank Bnking Individual Consultant C2-C314 National Elec Power Specialist 30,000 Selection Post May-17 12 months Myanma Economic Bank Individual Consultant C2-C315 National Lawyer 2,000 Selection Post May-17 1 month Myanma Economic Bank Joint Public Accounts Committee National Budget Expert on Individual Consultant D1-C316 40,500 Selection Post May-17 12 months Brought forward from earlier Strategic Plan PP No 3, package ref D1- C214 180 days Joint Public Accounts Committee International Expert for Strategic Individual Consultant over a D1-C317 200,000 Selection Prior May-17 Brought forward from earlier Plan period of 12 PP No 3, package ref D1- months C215 National Audit Expert on Individual Consultant Joint Public Accounts D1-C318 40,500 Selection Post May-17 12 months Committee Strategic Plan Individual Consultant Joint Public Accounts D1-C319 Support staff for Budget Expert 15,000 Selection Post May-17 12 months Committee Individual Consultant Joint Public Accounts D1-C320 Support staff for Audit Expert 15,000 Selection Post May-17 12 months Committee Individual Consultant Joint Public Accounts D1-C321 Support staff for Economist 15,000 Selection Post May-17 12 months Committee Consultancy services (firm) for E1-C322 Curriculum Development for 200,000 CQS Post May-17 3 months Budget Department PFM Academy Total for Consultants US$ 2,012,000 Total for Procurement Plan US$ 20,803,500 PROCUREMENT Myanmar : Modernization of Public Finance Management PLAN General Information Country: Myanmar Bank’s Approval Date of the Original Procurement Plan: 2017-08-08 2019-06-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144952 GPN Date: Project Name: Modernization of Public Finance Management Loan / Credit No: IDA / 54020, TF / 17910 Executing Agency(ies): Ministry of Planning and Finance WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MPFMP-C1-WS319 / Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2018-08-16 2018-10-18 2019-04-16 Building Renovation Quotations Envelope GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GS102 / Supply of IT Open - Single Stage - One IDA / 54020 Prior Request for Bids 2,686,348.00 Completed Equipment International Envelope GS101 / Pre-Fabricated Open - Single Stage - One IDA / 54020 Prior Request for Bids 11,371,084.34 Signed Data Centers International Envelope MPFMp-D1-GS 227 / Mini Request for Open - Data Centre and IDA / 54020 Prior 434,949.02 Signed Quotations International Infrastructure MPFMP-C2-IS326 / Core Request for Open - IDA / 54020 Prior Multi Stage 14,183,909.05 Terminated 2017-04-21 2017-05-04 2017-07-20 2017-12-03 2018-01-29 2019-07-23 Banking Solution Proposals International MPFMP-C2-GS327 / Open - Single Stage - One Remote location Recovery TF / 17910 Prior Request for Bids 1,060,680.59 Signed 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 2018-08-04 International Envelope Data Centre MPFMP-C2-GS329 / IT Equipment Lot 1: Desktop Computers (225nos) Lot 2: Desktop Servers (75 Open - Single Stage - One IDA / 54020 Prior Request for Bids 637,695.89 Signed 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 nos) International Envelope Lot 3: Laptop Computers (20 nos) Lot 4: Routers (75 nos) Lot 5: Online UPS (150nos) MM-MOPF-31520-GO-RFP / Information Systems for Integrated Tax Administration System-COTS Request for Open - IDA / 54020 Prior Multi Stage 6,089,371.92 Signed 2017-10-10 2017-10-15 2017-12-24 2018-04-07 2018-05-12 2019-11-03 development/customization,su Proposals International pply and implementation (Software and Associated Hardware) MPFMP-B1-GS303 / Lot 1: All-in-One Desktop Computer for Mini Library Request for Single Stage - One IDA / 54020 Post Limited 16,961.18 Completed 2018-01-07 2018-03-04 2018-08-31 (5 nos) Quotations Envelope Lot 2: Notebook Computer (7 nos) MPFMP-B1-GS304 / Lot 1: Request for Single Stage - One High volume Scanner (11 IDA / 54020 Post Open - National 133,869.86 Completed 2017-09-08 2017-12-29 2018-02-27 Quotations Envelope nos) Page 1 MPFMP-B1-GS305 / Lot 1 - Copier machine (8 nos) Lot 2 – Duplicator machine (2 nos) Lot 3 – Printers Request for Single Stage - One Item 1 – Laser Printer (30 IDA / 54020 Post Open - National 83,693.68 Completed 2017-09-08 2017-12-29 2018-02-27 Quotations Envelope nos) Item 2 – Color Inkjet Printer (10 nos) Lot 4- Copy Printer A3 (1 no) MPFMP-B1-GS306 / Office Request for Single Stage - One IDA / 54020 Post Limited 51,127.98 Completed 2018-01-01 2018-02-26 2018-08-25 Furniture for Staff Quotations Envelope MPFMP-B1-GS307 / Electrical Equipment Lot 1: Online UPS Item 1: Online UPS 3 KVA (3 nos) Request for Single Stage - One Item 2: Online UPS 6 KVA IDA / 54020 Post Limited 6,780.81 Completed 2018-01-07 2018-03-04 2018-08-31 Quotations Envelope (1 no) Lot 2: Ethernet Router (2 nos) Lot 3: CCTV Camera (10 nos) MPFMP-B1-GS355 / Request for Single Stage - One IDA / 54020 Post Limited 2,614.56 Completed 2018-01-07 2018-03-04 2018-08-31 Recorders - Voice (10 nos) Quotations Envelope MPFMP-B1-GS356 / Paper Request for Single Stage - One IDA / 54020 Post Limited 3,158.08 Completed 2018-01-09 2018-03-06 2018-09-02 Shredder (11 nos) Quotations Envelope MPFMP-B1-GS357 / Water Request for Single Stage - One IDA / 54020 Post Limited 1,642.05 Completed 2018-01-06 2018-03-03 2018-08-30 Cooler (15 nos) Quotations Envelope MPFMP-B1-GS359 / Request for Single Stage - One Ceiling type air conditioner IDA / 54020 Post Limited 1,898.58 Completed 2017-12-05 2018-01-30 2018-07-29 Quotations Envelope with accessories (2 nos) MPFMP-B1-GS360 / Request for Single Stage - One Motorized Projection Screen IDA / 54020 Post Limited 199.85 Completed 2017-12-05 2018-01-30 2018-07-29 Quotations Envelope (1 no) MPFMP-B2-GS310 / Electrical Power Equipment: Lot 1: Electrical Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2018-01-13 2018-03-10 2018-09-06 Transformer (1 no) Quotations Envelope Lot 2: Electrical Generator (1 no) MPFMP-B2-GS311 / Request for Single Stage - One Desktop Computers (130 IDA / 54020 Post Open - National 162,087.53 Completed 2017-11-17 2018-02-28 2018-03-30 Quotations Envelope nos) MPFMP-B2-GS312 / Item 1: Laser Printer (50 nos) Request for Single Stage - One Item 2: Colour Copier (1 IDA / 54020 Post Limited 21,992.85 Completed 2017-08-05 2017-09-30 2018-03-29 Quotations Envelope no) Item 3: Projector (1 no) MPFMP-B2-GS313 / Air Request for Single Stage - One IDA / 54020 Post Limited 5,760.61 Completed 2017-08-30 2017-10-25 2018-04-23 Conditioners (15 nos) Quotations Envelope MPFMP-B2-WS314 / Request for Single Stage - One Renovation of Training IDA / 54020 Post Limited 6,338.54 Completed 2017-11-19 2018-01-14 2018-07-13 Quotations Envelope Room MPFMP-B2-GS316 / Refurbishing of Training room (wall partitions, false Request for Single Stage - One IDA / 54020 Post Limited 6,456.30 Completed 2017-06-24 2017-08-19 2018-02-15 ceiling, wood file cabinets, Quotations Envelope wall paper, electrical re- wiring) Page 2 MPFMP-B2-GS318 / Furniture: Item 1: Table for teachers (2 nos) Request for Single Stage - One IDA / 54020 Post Limited 5,686.78 Completed 2017-08-16 2017-10-11 2018-04-09 Item 2: Computer tables (25 Quotations Envelope nos) Item 3: Chair w.o. arms (25 nos) MPFMP-B2-GS352 / Request for Single Stage - One IDA / 54020 Post Limited 1,514.54 Completed 2017-08-16 2017-10-11 2018-04-09 Projector, 1 no Quotations Envelope MPFMP-B2-GS353 / Air- Request for Single Stage - One IDA / 54020 Post Limited 1,442.25 Completed 2017-07-23 2017-09-17 2018-03-16 conditioners (3nos) Quotations Envelope MPFMP-B2-GS354 / Colour Request for Single Stage - One IDA / 54020 Post Limited 5,219.97 Completed 2017-08-14 2017-10-09 2018-04-07 copier (1 no) Quotations Envelope MPFMP-C1-GS320 / Air Request for Single Stage - One IDA / 54020 Post Limited 10,887.37 Completed 2017-09-16 2017-11-11 2018-05-10 Conditioners (20 nos) Quotations Envelope MPFMP-C1-GS321 / Furniture Item 1: Steel Cabinet (20 nos) Request for Single Stage - One Item 2: File Shelf (10 nos) IDA / 54020 Post Limited 24,134.72 Completed 2017-09-29 2017-11-24 2018-05-23 Quotations Envelope Item 3: Table (30 nos) Item 4: Chairs (40 nos) Item 5: Meeting table & chairs (2 sets) MPFMP-C1-GS322 / Net Request for Single Stage - One IDA / 54020 Post Limited 9,543.60 Completed 2018-01-10 2018-03-07 2018-09-03 Book/Laptop (10 nos) Quotations Envelope MPFMP-C1-GS324 / Request for Single Stage - One Generator Switch & IDA / 54020 Post Limited 6,068.22 Completed 2017-09-19 2017-11-14 2018-05-13 Quotations Envelope accessories MPFMP-C1-GS361 / Request for Single Stage - One Transformer with accessories IDA / 54020 Post Limited 0.00 Canceled 2018-01-10 2018-03-07 2018-09-03 Quotations Envelope (1 no) MPFMP-C2-GS328 / Air conditioners Request for Single Stage - One IDA / 54020 Post Limited 65,879.83 Completed 2018-01-10 2018-03-07 2018-09-03 Lot 1: Stand type (4 nos) Quotations Envelope Lot 2: Split type (166 nos) MPFMP-C2-GS330 / Request for Single Stage - One IDA / 54020 Post Limited 3,528.02 Completed 2018-01-10 2018-03-07 2018-09-03 Furniture Quotations Envelope MPFMP-D1-GS331 / Request for Single Stage - One IDA / 54020 Post Limited 37,556.21 Completed 2017-09-20 2017-11-15 2018-05-14 Furniture for Office Quotations Envelope MPFMP-D1-GS332 / IT Equipment Lot 1: Desktop Computers (25 nos) Lot 2: Laptop Computers (30 nos) Request for Single Stage - One IDA / 54020 Post Limited 97,709.34 Completed 2017-10-22 2017-12-17 2018-06-15 Lot 3: Printers (Item 1: Quotations Envelope Colour printer Qty 5 nos; Item 2: Heavy duty printers Qty 2 nos; Item 3: Copier Qty 8 nos) Lot 4: Scanner (Qty 5 nos) MPFMP-D1-GS333 / Electronic Equipment: Item 1: Telephone (7 nos) Item 2: Headphones (25 nos) Request for Single Stage - One IDA / 54020 Post Limited 2,912.05 Completed 2017-10-30 2017-12-25 2018-06-23 Item 3: 1TB Ext. Hard disk Quotations Envelope (5 nos) Item 4: Ext. CD/DVD Drive (2 nos) Item 5: Television set (3 nos) MPFMP-D1-GS335 / Diesel Request for Single Stage - One Electric Generator 150kVA IDA / 54020 Post Limited 26,315.06 Completed 2018-01-10 2018-03-07 2018-09-03 Quotations Envelope for Data Centre Page 3 MPFMP-D1-GS336 / IT Infrastructure Upgrading of Hluttaw: Lot1:LAN Network,Firewall,VPN,tool kit,wireless addition Lot2:Network Operations Request for Single Stage - One IDA / 54020 Post Open - National 196,914.17 Completed 2017-12-16 2018-02-10 2018-08-09 Centre Quotations Envelope Lot3:Software-MS Exchange(100 licenses),Photoshop Adobe Serial,Share Point Enhancement,PHP Runner Software License MPFMP-E1-GS348 / Request for Single Stage - One Electrical Transformer with IDA / 54020 Post Limited 0.00 Canceled 2018-01-13 2018-03-10 2018-09-06 Quotations Envelope accessories MPFMP-E1-GS349 / Audio Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2018-01-13 2018-03-10 2018-09-06 system for Learning centre Quotations Envelope MPFMP-E1-GS350 / Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2018-01-13 2018-03-10 2018-09-06 Furniture for Class rooms Quotations Envelope MPFMP-B2-GS315 / Lot 1: Laptop Computers (25nos) Request for Single Stage - One IDA / 54020 Post Limited 40,126.65 Completed 2018-01-09 2018-03-06 2018-09-02 Lot 2: Server with software Quotations Envelope & LAN C1 GS 364 / HP BL 4 60 Request for Single Stage - One c Gen 9 Blade 4 sets & IDA / 54020 Post Limited 0.00 Canceled 2018-01-07 2018-03-04 2018-04-04 Quotations Envelope HPE Trans-receiver (1) set MPFMP-C1-GS325 / Server Request for Single Stage - One Room IT Equipment and IDA / 54020 Post Open - National 396,016.83 Completed 2017-02-08 2017-06-13 2017-12-10 Quotations Envelope Infrastructure MPFMP-B1-GS401 / Item Request for Single Stage - One 1: Notebook Computer (10 IDA / 54020 Post Limited 43,381.48 Completed 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope nos) Item 2: Laptop (20 nos) MPFMP-B1-GS403 / Water Request for Single Stage - One IDA / 54020 Post Limited 821.50 Completed 2018-05-02 2018-06-15 2018-07-13 Cooler (8 nos) Quotations Envelope MPFMP-B1-GS404 / Request for Single Stage - One Ceiling Type Aircon with IDA / 54020 Post Limited 5,168.85 Completed 2018-05-07 2018-06-14 2018-06-29 Quotations Envelope Accessories (3 nos) MPFMP-B2-GS406 / Fax Request for Single Stage - One IDA / 54020 Post Limited 10,558.60 Completed 2018-06-04 2018-07-16 2018-08-06 Machine (28 nos) Quotations Envelope MPFMP-B2-GS408 / Item Request for Single Stage - One 1: Colour Copier (1 no) IDA / 54020 Post Limited 4,288.03 Completed 2018-06-04 2018-07-13 2018-08-13 Quotations Envelope Item 2: Printer (1 no) MPFMP-B2-GS409 / Measuring Instruments: Item 1: Specrta Distance Meter (4 nos) Request for Single Stage - One IDA / 54020 Post Limited 5,178.11 Completed 2018-06-16 2018-08-18 2019-02-14 Item 2: Rebound Measuring Quotations Envelope Meter (1 no) Item 3: Profoscope Cover Meter (1 no) MPFMP-B2-GS410 / LAN Request for Single Stage - One IDA / 54020 Post Limited 21,027.56 Completed 2018-06-04 2018-07-13 2018-08-10 Network Quotations Envelope MPFMP-C1-GS412 / Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2018-05-02 2018-06-11 2018-07-09 Recorder (9 nos) Quotations Envelope MPFMP-D1-GS414 / Item 1: Punch (300 sheets) (10 Request for Single Stage - One IDA / 54020 Post Limited 2,539.18 Completed 2018-05-02 2018-06-15 2018-07-06 nos) Quotations Envelope Item 2: Stapler (300 sheets) (21 nos) MPFMP-D1-GS415 / Request for Single Stage - One IDA / 54020 Post Limited 498.98 Completed 2018-05-02 2018-06-15 2018-07-06 Trolley (6 nos) Quotations Envelope Page 4 MPFMP-D1-GS416 / Item 1: Flip Chart Dimension 1000x700 mm (10 nos) Item 2: Banner Stand (10 nos) Request for Single Stage - One IDA / 54020 Post Limited 10,714.33 Completed 2018-05-02 2018-06-11 2018-07-02 Item 3: Magnetic Glass Quotations Envelope Marker Board Stand (1 nos) Item 4: Ibimatic/c150 Pro (Plastic Binding) (6 nos) Item 5: Collector (2 nos) MPFMP-D1-GS417 / Item 1: CB 78-99 Acrylic Door Cupoard 78" K/D (20 nos) Item 2: 6 Door Locker (LK 09 DD) (10 nos) Request for Single Stage - One Item 3: Rack (Wood) (30 IDA / 54020 Post Limited 9,171.74 Completed 2018-05-02 2018-06-11 2018-07-11 Quotations Envelope nos) Item 4: Metal Book Shelf (10 nos) Item 5: S-001 Book Shelf (10 nos) MPFMP-D1-GS418 / Audio Request for Single Stage - One IDA / 54020 Post Limited 16,817.99 Completed 2018-06-04 2018-07-12 2018-07-26 System (2 nos) Quotations Envelope MPFMP-D1-GS419 / Item 1: Printer (Black/White) (10 nos) Request for Single Stage - One Item 2: Duplo DP-A 120 (2 IDA / 54020 Post Limited 20,858.80 Completed 2018-06-04 2018-07-16 2018-08-16 Quotations Envelope nos) Item 3: Digital Multifunction Copier (2 nos) MPFMP-D1-GS420 / Water Request for Single Stage - One IDA / 54020 Post Limited 736.19 Completed 2018-05-02 2018-06-11 2018-07-02 Cooler (4 nos) Quotations Envelope MPFMP-D1-GS421 / Item 1: Swivel Chair (6 nos) Item 2: Table for Advisor (6'x4') (6 nos) Item 3: Staff Table (10 nos) Request for Single Stage - One Item 4: Meeting Chair (20 IDA / 54020 Post Limited 10,039.02 Completed 2018-06-04 2018-07-12 2018-08-03 Quotations Envelope nos) Item 5: Meeting Top Table (3'x9') (1 nos) Item 6: Meeting Chair Steel (40 nos) MPFMP-D1-GS422 / HP Request for Single Stage - One Server and Storage (Specific IDA / 54020 Post Limited 70,709.87 Completed 2018-08-02 2018-09-21 2018-10-22 Quotations Envelope Brand) MPFMP-D1-GS423 / Ramco Human Capital Management IDA / 54020 Post Direct Selection Direct 0.00 Canceled 2018-06-01 2018-06-04 2018-07-13 2018-08-10 (HCM) (with License) (1 nos) (Specific Brand) MPFMP-D1-GS424 / Vmware ESXi Version 6.5 IDA / 54020 Post Direct Selection Direct 4,729.37 Completed 2018-06-01 2018-06-04 2018-07-20 2018-08-20 (with License) (5 nos) (Specific Brand) MPFMP-D1-GS425 / Asset Request for Single Stage - One Management Software (with IDA / 54020 Post Limited 8,082.53 Completed 2018-06-04 2018-07-13 2018-08-10 Quotations Envelope License) MPFMP-E1-GS426 / Sound Request for Single Stage - One System with Accessories (1 IDA / 54020 Post Limited 5,969.81 Completed 2018-06-04 2018-07-13 2018-08-10 Quotations Envelope nos) MPFMP-E1-GS427 / Request for Single Stage - One Training Table and Seat IDA / 54020 Post Limited 16,798.18 Completed 2018-05-02 2018-06-11 2018-07-09 Quotations Envelope (100 nos) MPFMP-B1-GS302 / Books IDA / 54020 Post Direct Selection Direct 646.62 Completed 2018-07-01 2018-07-16 2018-08-30 2019-02-26 for Mini Library MPFMP-B1-GS358 / Video Request for Single Stage - One IDA / 54020 Post Limited 30,759.15 Completed 2018-06-30 2018-09-01 2019-02-28 Conference System (1 no) Quotations Envelope Page 5 MPFMP-C1-GS323 / Request for Single Stage - One Meeting room Conference IDA / 54020 Post Limited 0.00 Canceled 2018-01-07 2018-03-04 2018-08-31 Quotations Envelope system (2 sets) Pending MPFMP-D1-GS334 / IDA / 54020 Post Direct Selection Direct 0.00 Implementati 2018-08-01 2018-08-16 2018-09-26 2018-10-24 Reference Books for PAC on MPFMP-E1-GS343 / Request for Single Stage - One Refurbishing of Learning IDA / 54020 Post Limited 46,573.32 Completed 2018-06-16 2018-08-18 2019-02-14 Quotations Envelope Center MPFMP-E1-GS347 / Air Request for Single Stage - One Conditioners with TF / 17910 Post Limited 3,305.24 Completed 2018-06-07 2018-08-09 2019-02-05 Quotations Envelope accessories (6 nos) MPFMP-C1-GS411 / Request for Single Stage - One IDA / 54020 Post Limited 24,328.05 Completed 2018-06-04 2018-07-13 2018-08-10 Desktop (25 nos) Quotations Envelope MPFMP-C1-GS413 / Item 1: Table (30 nos) Request for Single Stage - One IDA / 54020 Post Limited 4,300.48 Completed 2018-06-02 2018-07-12 2018-08-09 Item 2: Armless Chair (30 Quotations Envelope nos) MPFMP-D1-GS428 / Software for Human Capital Request for Single Stage - One IDA / 54020 Post Limited 5,674.73 Completed 2018-06-16 2018-08-11 2019-02-07 Management (HCM) (with Quotations Envelope License) (1 nos) MPFMP-D1-GS429 / Item 1: Book Shelf (Wooden) (7) Request for Single Stage - One IDA / 54020 Post Limited 3,338.66 Completed 2018-08-28 2018-09-20 2018-09-25 nos Quotations Envelope Item 2: Cabinet with 3 sides of glasses (5) nos MPFMP-D1-GS430 / CD Request for Single Stage - One IDA / 54020 Post Limited 1,878.00 Completed 2018-08-28 2018-09-21 2018-09-25 Drive (5 nos) Quotations Envelope MPFMP-B1-GS502 / UPS Request for Single Stage - One IDA / 54020 Post Limited 2,705.86 Signed 2018-11-10 2019-01-28 2019-03-29 (30 nos) Quotations Envelope MPFMP-B1-GS504 / Supply and installation of air conditioners - Item 1: Ceiling type Air Request for Single Stage - One Conditioner with Accessories IDA / 54020 Post Limited 24,838.66 Completed 2018-11-10 2019-01-28 2019-03-29 Quotations Envelope (8 nos) Item 2: Split type Air Conditioner with Accessories (10 nos) MPFMPB1-GS505 / Supply of Computers - Pending Item 1: Note Book Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-11-10 2019-01-28 2019-04-28 Computer (5 nos) Quotations Envelope on Item 2: Laptop Computers (20 nos) MPFMP-B1-GS506 / Office Request for Single Stage - One IDA / 54020 Post Limited 17,279.21 Completed 2018-11-10 2019-01-28 2019-03-29 Furniture for Staff Quotations Envelope Pending MPFMP-B1-GS507 / Voice Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-11-10 2019-01-28 2019-03-29 Recorder (4GB) (7 nos) Quotations Envelope on MPFMP-B1-GS508 / Supply of Office Equipment: Item 1: Collator Booklet System ((1 nos) Pending Item 2: Collator (1 nos) Request for Single Stage - One IDA / 54020 Post Open - National 0.00 Implementati 2018-12-08 2019-03-16 2019-06-14 Item 3: Digital Color Quotations Envelope on Production Press with Perfect Binder (1 nos) Item 4: FKS Printbind (1 nos) MPFMP-B1-GS509 / E- Request for Single Stage - One IDA / 54020 Post Limited 2,723.72 Signed 2018-11-10 2019-01-28 2019-03-29 Book Reader (6 nos) Quotations Envelope Page 6 MPFMP-B1-GS511 / Pending Microsoft Exchange Software Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-08 2019-02-25 2019-04-26 Licence for Mini Data Quotations Envelope on Center (1 no) MPFMP-B1-GS513 / WiFi Pending Access Point (AP) with Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-08 2019-02-25 2019-04-26 Accessories for H.O Quotations Envelope on (4 nos) MPFMP-B1-GS514 / Request for Single Stage - One External Hard Disk Drive IDA / 54020 Post Limited 622.34 Completed 2018-11-10 2019-01-28 2019-03-29 Quotations Envelope (5 nos) MPFMP-B1-GS515 / Supply Pending and Installation of Raised Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-08 2019-02-25 2019-05-26 Flooring & LAN Network Quotations Envelope on for New Building MPFMP-B1-GS518 / Pending Reference Books for Mini IDA / 54020 Post Direct Selection Direct 0.00 Implementati 2018-12-03 2018-12-08 2019-01-19 2019-03-20 Library on MPFMP-B2-GS524 / Office Request for Single Stage - One Table for Expert Room (4 IDA / 54020 Post Limited 421.61 Completed 2018-11-10 2019-01-28 2019-03-29 Quotations Envelope nos) MPFMP-B2-GS527 / Supply Pending of IT Equipment - Servers, Request for Single Stage - One IDA / 54020 Post Open - National 0.00 Implementati 2018-12-08 2019-03-16 2019-07-14 Data Storage and Related Quotations Envelope on Software and accessories MPFMP-B2-GS529 / Supply Request for Single Stage - One & Installation of Air IDA / 54020 Post Limited 783.78 Completed 2018-11-10 2019-01-28 2019-03-29 Quotations Envelope Conditioner (2 nos) MPFMP-B2-GS530 / Supply of Cameras - Item 1: CCTV Camera (2 Request for Single Stage - One nos) IDA / 54020 Post Limited 10,016.35 Signed 2018-11-10 2019-01-28 2019-04-28 Quotations Envelope Item 1: Video Camera (5 nos) Item 2: Camera (9 nos) MPFMP-B2-GS531 / Risk Request for Single Stage - One Software (single user IDA / 54020 Post Limited 2,020.38 Signed 2018-12-08 2019-02-25 2019-04-26 Quotations Envelope license) (2 nos) MPFMP-B2-GS532 / Project Request for Single Stage - One Progress Monitoring IDA / 54020 Post Limited 4,906.80 Signed 2018-12-08 2019-02-25 2019-08-24 Quotations Envelope Application Software MPFMP-B2-GS533 / Supply of Measuring Instruments: Item 1: Silver Schmidt (Rebound) (4 nos) Item 2: Pundit Pulse Echo (3 nos) Pending Request for Single Stage - One Item 3: Profometer (3 nos) IDA / 54020 Post Open - National 0.00 Implementati 2018-12-08 2019-03-13 2019-06-11 Quotations Envelope Item 4: Equotip Bambino 2 on (4 nos) Item 5: Caliper (15 nos) Item 6: Distance Meter (11 nos) Item 7: Profoscope (5 nos) MPFMP-B2-GS534 / Supply of IT Equipment: Lot 1: Desktop Computer Pending Request for Single Stage - One (23 nos) IDA / 54020 Post Limited 0.00 Implementati 2018-11-10 2019-01-28 2019-04-28 Quotations Envelope Lot 2: Laptop Computer (15 on nos) Lot 3: Tablet (10 nos) MPFMP-B2-GS535 / Request for Single Stage - One IDA / 54020 Post Limited 426.09 Signed 2018-11-10 2019-01-28 2019-02-27 Cutting Machine (13 nos) Quotations Envelope Pending MPFMP-B2-GS538 / Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-11-10 2019-01-28 2019-03-29 Projector (2 nos) Quotations Envelope on Page 7 MPFMP-C1-GS541 / Supply of IT Equipment: Pending Lot 1: Desktop Computer Request for Single Stage - One IDA / 54020 Post Open - National 0.00 Implementati 2018-12-08 2019-03-16 2019-06-14 (50 nos) Quotations Envelope on Lot 2: Laptop Computer (20 nos) MPFMP-C1-GS543 / Office Equipment - Request for Single Stage - One Item 1: Paper Shredder (5 IDA / 54020 Post Limited 4,130.51 Completed 2018-11-12 2019-01-16 2019-02-20 Quotations Envelope nos) Item 2: Binders (2 nos) MPFMP-C1-GS544 / Office Furniture - Item 1: Arm less Chairs for Request for Single Stage - One TF / 17910 Post Limited 1,663.96 Signed 2018-11-12 2019-01-09 2019-03-10 Staff (50 nos) Quotations Envelope Item 2: Arm less Chairs for Meeting Room (25 nos) MPFMP-C1-GS545 / Request for Single Stage - One Projector with Motorized IDA / 54020 Post Limited 3,092.99 Completed 2018-11-12 2019-01-12 2019-03-13 Quotations Envelope Screen (3 nos) MPFMP-C1-GS547 / Lot1: Item 1 - UPS(6nos), Item 2: Online UPS(1nos) Lot2: Finger Print-Time Attendance(1nos) Lot3:CCTV Camera(1set) Pending Request for Single Stage - One Lot4:Recorder (4nos) IDA / 54020 Post Limited 0.00 Implementati 2018-11-12 2019-01-16 2019-03-17 Quotations Envelope Lot5:Hard Disk Drive(5nos) on Lot6:7.1k NLSAS 3.5Hard Drive(15nos) Lot7:Wireless Access Point(2nos) Lot8:Half Rack(1nos) MPFMP-C2-GS549 / IT Equipment-Supply of Under Open - Single Stage - One Desktop Computers with IDA / 54020 Prior Request for Bids 758,482.00 Implementati 2018-12-03 2018-12-21 2019-02-01 2019-03-18 2019-05-17 2019-08-15 International Envelope licensed software (Quantity on 541 nos) Pending MPFMP-C2-GS550 / Supply Request for Single Stage - One IDA / 54020 Post Open - National 0.00 Implementati 2018-12-08 2019-02-02 2019-08-01 of Routers (63 nos) Quotations Envelope on MPFMP-C2-GS553 / Request for Single Stage - One Network Switch (16 Ports) IDA / 54020 Post Limited 4,203.71 Signed 2018-11-12 2019-01-20 2019-03-21 Quotations Envelope (45 nos) MPFMP-C2-GS554 / Supply Request for Single Stage - One and Installation of Air- IDA / 54020 Post Limited 81,145.69 Signed 2018-11-16 2018-12-28 2019-02-27 Quotations Envelope conditioners (209 nos) MPFMP-C2-GS555 / Request for Single Stage - One IDA / 54020 Post Limited 15,712.92 Signed 2018-11-09 2019-01-16 2019-03-17 Projector (14 nos) Quotations Envelope MPFMP-E1-GS557 / Supply Pending of Laptop Computer (with Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-10 2019-02-10 2019-05-11 suite of Microsoft Office Quotations Envelope on software) (30 nos) MPFMP-E1-GS558 / Request for Single Stage - One Multifunction Copier (B/W) IDA / 54020 Post Limited 2,577.49 Completed 2018-12-10 2019-02-17 2019-05-18 Quotations Envelope (1 nos) MPFMP-E1-GS559 / Supply and Installation of Air- conditioners - Request for Single Stage - One Item 1: Ceiling type Air IDA / 54020 Post Limited 7,077.98 Completed 2018-12-10 2019-02-17 2019-04-19 Quotations Envelope Conditioner (2 nos) Item 2: Split type Air Conditioner (4 nos) Pending MPFMP-E1-GS560 / Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-10 2019-02-20 2019-04-21 Portable Speaker (2 nos) Quotations Envelope on Page 8 MPFMP-E1-GS561 / Appliance for PFM Academy Pending Request for Single Stage - One Item 1: Refrigerator (1 nos) IDA / 54020 Post Limited 0.00 Implementati 2018-12-11 2019-02-17 2019-03-23 Quotations Envelope Item 2: Water Cooler (3 on nos) MPFMP-E1-GS562 / Pending Request for Single Stage - One Furniture for Classrooms of IDA / 54020 Post Limited 0.00 Implementati 2018-12-10 2019-02-17 2019-04-19 Quotations Envelope PFM Academy on MPFMP-E1-GS563 / Supply Pending Request for Single Stage - One of Wifi Access Point (AP) IDA / 54020 Post Limited 0.00 Implementati 2018-12-10 2019-02-17 2019-03-20 Quotations Envelope with Accessories on Pending MPFMP-E1-GS565 / Request for Single Stage - One IDA / 54020 Post Open - National 0.00 Implementati 2019-01-11 2019-03-15 2019-05-14 Furniture for PFM Academy Quotations Envelope on MPFMP-E1-GS567 / Video Pending Request for Single Stage - One Conferencing System and IDA / 54020 Post Limited 0.00 Implementati 2019-01-07 2019-02-22 2019-04-23 Quotations Envelope Accessories on MPFMP-E1-GS568 / Sound Request for Single Stage - One System with Accessories (2 IDA / 54020 Post Limited 6,851.10 Completed 2019-01-07 2019-03-17 2019-05-17 Quotations Envelope sets) MPFMP-E1-GS569 / Supply Pending Request for Single Stage - One and Installation of IDA / 54020 Post Limited 0.00 Implementati 2019-01-07 2019-03-17 2019-06-15 Quotations Envelope Generator with Accessories on Pending MPFMP-E1-GS570 / CCTV Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2019-01-11 2019-03-20 2019-05-20 Camera (2 sets) Quotations Envelope on MPFMP-E1-GS571 / Request for Single Stage - One Projector with Motorized IDA / 54020 Post Limited 21,962.23 Signed 2019-01-07 2019-03-17 2019-05-19 Quotations Envelope Screen (7 nos) MPFMP-E1-GS572 / Supply of Photocopying Machines - Item 1: Multi-function Copier (Color) (1 nos) Request for Single Stage - One Item 2: Black and White IDA / 54020 Post Limited 22,683.48 Signed 2019-01-07 2019-03-20 2019-06-18 Quotations Envelope Multi-function Copier (B/W) (2 nos) Item 3: Multi-function Copier with feeder (2 nos) MPFMP-E1-GS573 / Electrical Appliance for the Office Pending Request for Single Stage - One Item 1: Refrigerator ( 4 IDA / 54020 Post Limited 0.00 Implementati 2019-01-07 2019-03-13 2019-05-12 Quotations Envelope nos) on Item 2: Water Cooler (12 nos) MPFMP-E1-GS574 / Television sets for instructional purposes for Request for Single Stage - One IDA / 54020 Post Limited 5,665.34 Completed 2019-01-07 2019-03-17 2019-05-16 PFM Academy Quotations Envelope Item 1: 32" LCD TV (5 nos) Item 2: 55" LED TV (4 nos) MPFMP-E1-GS575 / Office Request for Single Stage - One Equipment - Collator and IDA / 54020 Post Limited 36,087.32 Signed 2019-01-07 2019-03-17 2019-06-15 Quotations Envelope Booklet System MPFMP-E1-GS576 / Server Room IT Equipment for PFM Academy (Wifi AP,Rack Server,Rack, Switch, Storage Pending Request for Single Stage - One Server,CORE Switch, IDA / 54020 Post Open - National 0.00 Implementati 2019-04-10 2019-07-30 2019-09-28 Quotations Envelope PAC,UPS,Stabalizer, on Fabric,KVM,Installation,Wind ow Server 2016,Wiring Data,Installation, Symantec Endpoint Protection License) Page 9 MPFMP-B1-GS501 / Paper Request for Single Stage - One IDA / 54020 Post Limited 882.35 Completed 2018-11-10 2019-01-28 2019-03-29 Shredders (3 nos) Quotations Envelope MPFMP-B2-GS-309 / Data Communication Equipment: Request for Single Stage - One Lot 1: 3G Modems (122 TF / 17910 Post Limited 0.00 Canceled 2018-07-31 2018-10-02 2019-03-31 Quotations Envelope nos) Lot 2: Switch 24 ports (5nos) Pending MPFMP-B2-GS407 / Books IDA / 54020 Post Direct Selection Direct 0.00 Implementati 2018-12-05 2018-12-12 2019-02-04 2019-02-25 for Library on MPFMP-E1-GS363 / Request for Single Stage - One Projector with motorized IDA / 54020 Post Limited 3,053.92 Completed 2018-12-18 2019-03-07 2019-05-06 Quotations Envelope screen (1 nos) MPFMP-D1-GS578 / Video Request for Single Stage - One Conferencing System IDA / 54020 Post Limited 44,045.78 Signed 2018-11-06 2019-01-24 2019-04-24 Quotations Envelope upgrade MPFMP-D1-GS579 / CCTV Request for Single Stage - One IDA / 54020 Post Limited 1,435.57 Signed 2018-11-13 2019-01-31 2019-04-01 system Quotations Envelope MPFMP-D1-GS580 / Pending Request for Single Stage - One Firewall for the JPAC IT IDA / 54020 Post Limited 0.00 Implementati 2018-11-20 2019-02-23 2019-05-24 Quotations Envelope Network System on MPFMP-D1-GS581 / JPAC Pending Request for Single Stage - One Network Operations Center IDA / 54020 Post Limited 0.00 Implementati 2018-11-17 2019-02-04 2019-04-05 Quotations Envelope Software Licenses on MPFMP-D1-GS582 / Request for Single Stage - One Electricity Supply Voltage IDA / 54020 Post Limited 12,332.82 Signed 2018-11-27 2019-02-14 2019-04-15 Quotations Envelope Stabilizer MPFMP-D1-GS583 / Compouters - Pending Item 1 - Desktop Request for Single Stage - One TF / 17910 Post Limited 0.00 Implementati 2018-11-26 2019-02-13 2019-05-14 Computers (7 nos) Quotations Envelope on Item 2 - Laptop Computers (60 nos) MPFMP-D1-GS584 / IT Pending Request for Single Stage - One Network Infrastructure for e- IDA / 54020 Post Limited 0.00 Implementati 2018-12-05 2019-02-22 2019-05-23 Quotations Envelope Parliament on MPFMP-D1-GS585 / Pending Websites for States and Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-01 2019-02-18 2019-05-19 Regions Hluttaw Offices (4 Quotations Envelope on websites & web pages) MPFMP-D1-GS586 / Video Pending Conferencing systems for Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-05 2019-02-22 2019-05-23 States and Region offices of Quotations Envelope on Hluttaw (4 sets) MPFMP-D1-GS587 / IT Pending Network equipment for Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-12 2019-03-17 2019-06-15 creating Redundancy for Quotations Envelope on MDC and networks and ISP MPFMP-D1-GS588 / IT Pending Equipment for Redundancy Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-23 2019-03-28 2019-06-26 in the System for Servers Quotations Envelope on and Storage MPFMP-D1-GS589 / Software Licenses - Item 1: Share Point 2016 Enterprise CAL license (150 nos) Item 2: Share Point CAL Pending Request for Single Stage - One Standard license (1000 nos) IDA / 54020 Post Limited 0.00 Implementati 2019-01-21 2019-04-26 2019-07-25 Quotations Envelope Item 3: WinSvr CAL 2016 on OLP NL Gov User CAL (1000 nos) Item 4: Exchange Std CAL 2016 OLP NL Gov User CAL (196 nos) Page 10 MPFMP-C1-GS546 / IT Equipment for Upgrading Server Room (Level 1, 16-port Switch, 48 Under port LAN Switch, HPE Request for Single Stage - One IDA / 54020 Post Limited 109,882.66 Implementati 2018-11-20 2018-12-30 2019-01-29 BL460C Gen9 10/20Gb FLB Quotations Envelope on CTO Blade, Tape Backup HW/SW, MS Exchange Standard Server, MS Exchange User Cal) MPFMP-C1-GS548 / IT Equipment for Treasury Pending Request for Single Stage - One Server Room Redundancy IDA / 54020 Post Limited 0.00 Implementati 2019-04-13 2019-06-19 2019-08-18 Quotations Envelope (Server, Storage, Core on Switch, etc,) MPFMP-C2-GS551 / Supply of Printers: Lot 1: Passbook Printer Pending Request for Single Stage - One (396 nos) IDA / 54020 Post Open - National 0.00 Implementati 2018-12-08 2019-03-16 2019-06-14 Quotations Envelope Lot 2: Item 1 - Dot Matrix on Printer (32 nos), Item 2: Laser Printer (49 nos) MPFMP-C2-GS552 / Supply of Office Equipment - Request for Single Stage - One IDA / 54020 Post Limited 46,848.61 Signed 2018-12-14 2019-02-17 2019-05-18 Item 1: Scanner (81 nos) Quotations Envelope Item 2: Copier (14 nos) MPFMP-B2-GS525 / Lot 1: Supply of Copiers and Printers: Item 1: Color Copier (27 nos), Item 2: Pending Request for Single Stage - One Injet Color Printer (A4) (5 IDA / 54020 Post Open - National 0.00 Implementati 2018-12-29 2019-04-06 2019-07-05 Quotations Envelope nos), Item 3: Printer (323 on nos). Lot 2: Supply of Fax machines (403 nos) MPFMP-B2-GS536 / Supply of Office Equipment Lot 1: Copiers and Printers Pending Request for Single Stage - One - Item 1: Color Copier (5 IDA / 54020 Post Open - National 0.00 Implementati 2018-12-08 2019-02-02 2019-04-03 Quotations Envelope nos), Item 2: Printer (10 on nos). Lot 2: Scanners (10 nos) MPFMP-C1-GS542 / Supply of Printers & Copier - Pending Request for Single Stage - One Item 1: Color Printer (2 IDA / 54020 Post Limited 0.00 Implementati 2019-01-08 2019-03-21 2019-05-21 Quotations Envelope nos) on Item 2: Color Copier (1 nos) MPFMP-B1-GS503 / Supply of Office Equipment: Item 1: Scanner (10 nos), Request for Single Stage - One IDA / 54020 Post Limited 79,282.40 Signed 2019-01-19 2019-04-08 2019-06-07 Item 2: Copier B&W with Quotations Envelope feeder (10 nos), Item 3: Book Scanner (1 no.) MPFMP-C1-GS540 / Supply and Installation of Office Request for Single Stage - One IDA / 54020 Post Limited 26,535.97 Completed 2018-12-10 2019-02-22 2019-04-24 LAN wiring and Raised Quotations Envelope Flooring for 2 Rooms MPFMP-D1-GS590 / Pending Request for Single Stage - One Furniture for Office: IDA / 54020 Post Limited 0.00 Implementati 2018-12-15 2019-01-26 2019-02-25 Quotations Envelope Meeting tables and Chairs on MPFMP-D1-GS591 / RAM Pending Memory card 16 GB for Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2018-12-29 2019-02-23 2019-04-24 enhancing the capacity of Quotations Envelope on existing DL Server (1 set) MPFMP-C1-GS593 / Treasury Automation system Pending application software - IDA / 54020 Post Direct Selection Direct 0.00 Implementati 2018-11-12 2018-11-17 2018-12-22 2019-09-18 Financial Information on Reporting Systems for Treasury (FIRST) Page 11 MPFMP-C1-GS431 / Treasury Automation system application software - IDA / 54020 Prior Direct Selection Direct 0.00 Canceled 2018-09-17 2018-09-22 2018-11-26 2019-05-25 Financial Information Reporting Systems for Treasury (FIRST) MPFMP-B1-GS402 / Copier Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2018-06-04 2018-07-16 2018-08-13 (B/W) with feeder (10 nos) Quotations Envelope MPFMP-B1-GS405 / Book Request for Single Stage - One Scanner for E-Library (1 IDA / 54020 Post Limited 0.00 Canceled 2018-07-03 2018-08-13 2018-09-03 Quotations Envelope nos) MPFMP-B1-GS512 / SUpply of Vmware Sphere Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2018-12-08 2019-02-25 2019-03-27 ESXi 6.5 Enterprise plus Quotations Envelope Software Licence (2 nos) MPFMP-B1-GS517 / Development & Supply of Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2018-12-08 2019-02-25 2019-08-24 Application based on Share Quotations Envelope Point Software MPFMP-B1-GS519 / IT Equipment for Server Room (Rack Server, (OS + SQL License Version, 2016, Request for Single Stage - One IDA / 54020 Post Limited 0.00 Canceled 2019-02-06 2019-04-26 2019-08-24 Firewall), Rack for Quotations Envelope Servers/ref diagram, Online UPS,Management Switch, Stabilizer) MPFMP-B1-GS520 / Refurbishing of the ICT Room (Raised Floor, Server Room Partation, Painting Wall, LAN Wiring, Door Request for Single Stage - One Access System, CCTV, Air IDA / 54020 Post Limited 0.00 Canceled 2018-11-10 2019-01-28 2019-04-28 Quotations Envelope Conditioner, Smoke and Fire Alarm, Built-in Computer Tables, Built-in Chair, Electrical System Re- Wiring) MPFMP-B1-IS521 / Supply, installation, and support for Open - Single Stage - One IDA / 54020 Prior Request for Bids 0.00 Canceled 2018-10-15 2018-10-30 2018-12-11 2019-01-25 2019-03-10 2019-09-06 Pension Management International Envelope Information System MPFMP-E1-GS564 / Refurbishing of PFM Academy - False ceiling & soundproofing, interior wall covering/painting, divider Pending Request for Single Stage - One partitions (movable & IDA / 54020 Post Open - National 0.00 Implementati 2019-09-06 2019-11-01 2020-04-29 Quotations Envelope immovable), floor covering, on curtains, raised flooring, & built-in cabinets, installation of fire alarm system & PA system MPFMP-E1-GS592 / Pending Reference Books, Academic IDA / 54020 Post Direct Selection Direct 0.00 Implementati 2019-09-01 2019-09-06 2019-10-11 2020-04-08 Journals for PFM Academy on MPFMP-B1-GS516 / Government Accounting System (GAS) Software for Pending the several accounts Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2019-04-22 2019-06-18 2019-09-16 maintained in the Budget Quotations Envelope on Department (standalone software for automating the accounting) MPFMP-B2-GS522 / Government Accounting Information System Pending Software for Planning Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2019-04-24 2019-06-19 2019-09-17 Department related to Quotations Envelope on Revenue and Expenditure (standalone software for the automating of the accounting function) Page 12 MPFMP-C1-GS539 / Development, Supply, and Implementation of Government Human Resources Management Pending System (GHRMS) for Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2019-04-03 2019-05-29 2019-08-27 Treasury Department Quotations Envelope on (standalone software for specific requirement for the automation of accounting of staff leave, attendance, manpower planning) MPFMP-B2-GS595 / Item 1: LCD Computer Monitor Pending Request for Single Stage - One (Qty 3 nos) IDA / 54020 Post Limited 0.00 Implementati 2019-06-19 2019-08-14 2019-09-13 Quotations Envelope Item 2: Translator Device on (1 set of 20 + 2 Users) MPFMP-C2-IS526 / Supply, implementation and support Request for Single Stage - One Under of a CORE Banking System IDA / 54020 Prior Limited 0.00 2019-05-31 2019-06-15 2019-07-15 2019-08-14 2019-09-27 2021-03-27 Proposals Envelope Review (CBS) and related linkages for Myanma Economic Bank MPFMP-B2-GS594 / Item 1: Video Conference System (1 set). Pending Request for Single Stage - One Item 2: Meeting room audio IDA / 54020 Post Open - National 0.00 Implementati 2019-06-19 2019-09-07 2019-11-26 Quotations Envelope conference system (PA on System)(1 set - Chair + 30 members) MPFMP-B1-GS596 / Lot 1: Furniture - Cupboard (25 Pending nos), File Rack (25 nos), Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2019-06-24 2019-08-19 2019-09-18 File Drawer cabinet (25 Quotations Envelope on nos). Lot 2: Water Cooler (6 nos) MPFMP-E1-GS597 / Office Equipment Lot 1: Multi touch Display monitor (5 nos), Lot 2: Electronic Capture Pending Boards (5 nos), Request for Single Stage - One IDA / 54020 Post Open - National 0.00 Implementati 2019-07-15 2019-09-25 2019-12-24 Lot 3: PA Audio System Quotations Envelope on with LED Video Screen and accessories, Lot 4: Mic/Audio Conferencing System (31 nos) MPFMP-E1-GS598 / Air Pending Request for Single Stage - One Conditioners with IDA / 54020 Post Open - National 0.00 Implementati 2019-07-29 2019-10-09 2020-01-07 Quotations Envelope accessories on MPFMP-E1-GS599 / Office equipment Item 1: Flip Charts (30 nos), Item 2: Safe Box (1 no) Pending Request for Single Stage - One Item 3: Paper Shredder (3 IDA / 54020 Post Limited 0.00 Implementati 2019-07-21 2019-09-15 2019-10-15 Quotations Envelope nos) on Item 4: Coffee machine (1 no) Item 5: Fire Extinguisher (20 nos) MPFMP-E1-GS600 / Printers Item 1: Du-plex printer (1 no) Pending Item 2: Card printer & Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2019-08-05 2019-09-30 2019-10-30 cards (1 no) Quotations Envelope on Item 3: Laser Printer (15 nos) Item 4: Inkjet color printer (5 nos) MPFMP-E1-GS601 / Projectors: Pending 1. Laser Projectors with Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2019-07-31 2019-09-25 2019-10-25 motorized screen (1 no) Quotations Envelope on 2. Full HD Projector with motorized screen (1 no) Page 13 MPFMP-E1-GS602 / Furnishings: Pending Request for Single Stage - One 1. Carpet (6 nos) IDA / 54020 Post Limited 0.00 Implementati 2019-08-19 2019-10-14 2019-11-13 Quotations Envelope 2. Picture frames with on artwork MPFMP-E1-GS566 / Supply Pending and Installation of Request for Single Stage - One IDA / 54020 Post Limited 0.00 Implementati 2019-06-18 2019-08-26 2019-11-24 Transformer and Accessories Quotations Envelope on for PFM Academy MPFMP-E1-GS577 / Supply & Installation of of Pending Request for Single Stage - One Earthing materials & IDA / 54020 Post Limited 0.00 Implementati 2019-08-07 2019-10-08 2020-01-06 Quotations Envelope Landscaping materials and on services for PFM Academy NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-C003/ C2-C117 / Consultant Open - Upgrading MEB's IDA / 54020 Prior Qualification 358,488.00 Signed International Operational system Selection MPFMP-E1-C322 / Consultant Consultancy services (firm) Open - IDA / 54020 Post Qualification 104,768.17 Signed 2017-05-31 2017-06-21 2017-08-04 2017-09-03 2017-10-08 2018-04-06 for Curriculum Development International Selection for PFM Academy MPFMP-E1-C502 / Consultancy Services for Consultant Provision of Training Pending IDA / 54020 Post Qualification Open - National 0.00 2019-02-01 2019-02-22 2019-04-07 2019-06-06 2019-07-11 2020-07-05 Modules Delivery (Team of Implementation Selection Trainers) for the PFM Academy INDIVIDUAL CONSULTANTS Page 14