The World Bank Implementation Status & Results Report VIETNAM: Haiphong Urban Transport Project (P111548) VIETNAM: Haiphong Urban Transport Project (P111548) EAST ASIA AND PACIFIC | Vietnam | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2011 | Seq No: 18 | ARCHIVED on 28-May-2019 | ISR37045 | Implementing Agencies: Transport Construction and investment Project Management Unit, SOCIALIST REPUBLIC OF VIETNAM Key Dates Key Project Dates Bank Approval Date: 29-Mar-2011 Effectiveness Date: 28-Jul-2011 Planned Mid Term Review Date: 06-Oct-2014 Actual Mid-Term Review Date: 06-Oct-2014 Original Closing Date: 31-Dec-2016 Revised Closing Date: 29-Feb-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve urban accessibility and strengthen capacity for urban transport management and planning in Haiphong. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Strategic Urban Road:(Cost $263.58 M) Public Transport Improvement:(Cost $8.04 M) Capacity Building:(Cost $4.99 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Main activities under component B and C have been completed. However, there has been no significant progress made under the civil works contracts under component A since the last mission in October 2018. The reasons for slowness are difficulties in resettlement and Budget Allocation and Medium Term Public Investment Plan 2016- 2020 (MTIP). 1. Continued delays in resettlement especially in An Duong and Hai An districts, and the resultant slow progress of five civil works contracts have been observed. The City is requested to resolve all complaints to complete all land acquisition and resettlement activities by May 31, 2019. 2. Inadequate budget allocation for the project has also caused slow progress of works. The project needs about VND 900 billion from now until completion, VND 656 billion has been allocated to the project under MTIP 2016-2020. The city is requested to propose the allocation 5/28/2019 Page 1 of 8 The World Bank Implementation Status & Results Report VIETNAM: Haiphong Urban Transport Project (P111548) of the remaining VND 110 billion to ensure timely completion of the project, and the city should also find alternative funding sources to address the gap. 3. While the completion dates of works contracts are either end of Nov. 2019 or Dec. 2019, the Supervision Consultancy contract (CS2A) will close on December 31, 2019. However, given the remaining land acquisition works, the time required to implement soft soil treatment on the newly/to be handed sections, the PMU need to prepare a plan to continue the supervision services beyond December 31, 2019, until completion of Defect Liability Periods for all the civil works. The Bank team strongly recommended the PMU to negotiate with CS2A consultant on further extension. 5/28/2019 Page 2 of 8 The World Bank Implementation Status & Results Report VIETNAM: Haiphong Urban Transport Project (P111548) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate 5/28/2019 Page 3 of 8 The World Bank Implementation Status & Results Report VIETNAM: Haiphong Urban Transport Project (P111548) Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Moderate Moderate Environment and Social -- Substantial Substantial Stakeholders -- Low Low Other -- Moderate Moderate Overall -- Substantial Substantial Results PDO Indicators by Objectives / Outcomes Reduce travel time on project corridors IN00701926 ►NH5 - Nam Hai (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target c=24 c=38.77 c=37.15 c=18 t=27 t=42.4 t=41.7 t=21.6 Value b=27 b=42.67 b=38.75 b=21.6 mc=36 mc=38.6 mc=38.06 mc=27 Date 31-Dec-2009 31-Aug-2018 22-Mar-2019 29-Feb-2020 IN00701928 ►Bac Son - Nam hai (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target c=n/a c=17 Cannot measure since Cannot measure since t=n/a t=20 Value the roads has not been the roads has not been b=n/a b=20 completed completed mc=n/a mc=24 Date 31-Dec-2009 31-Aug-2018 22-Mar-2019 29-Feb-2020 Increase number of passenger on Bus Line 2 IN00701927 ►Increase number of passenger on Bus line 2 (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target 2827 people/ day (- 2781 people/ day (- 4177 people/day Value 3410 people/day 17.1%) 18.4%) (+22.5%) Date 31-Dec-2009 31-Aug-2018 22-Mar-2019 29-Feb-2020 Establishment of geographic information system (GIS) for urban road IN00701910 ►Establishment of geographic information system (GIS) for urban road (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target 5/28/2019 Page 4 of 8 The World Bank Implementation Status & Results Report VIETNAM: Haiphong Urban Transport Project (P111548) Value N/A N/A N/A GIS available Date 31-Dec-2009 31-Aug-2018 22-Mar-2019 29-Feb-2020 Intermediate Results Indicators by Components Strategic Urban Road IN00701929 ►Direct project beneficiaries of the road (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 50,030.00 78,206.00 78,206.00 74,207.00 Date 31-Dec-2010 20-Apr-2018 20-Feb-2019 29-Feb-2020 This will be surveyed in end of the project as well. Comments: IN00701932 ►Roads constructed, non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Dec-2010 20-Apr-2018 20-Feb-2019 29-Feb-2020 IN00701934 ►Direct project beneficiaries of the road (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 3,410.00 2,870.00 2,781.00 4,175.00 Date 31-Dec-2010 20-Apr-2018 20-Feb-2019 29-Feb-2020 The project was expected that target value increased 5% in the 3rd year, 12.5% in the 4th year and 22.5% Comments: in the last year. IN00701937 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 42.00 53.40 51.10 42.00 Public Transport Improvement IN00701930 ►Bus Service Frequency (Minutes, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 20.00 20.00 20.00 15.00 Date 31-Dec-2010 31-Aug-2018 20-Feb-2019 29-Feb-2020 5/28/2019 Page 5 of 8 The World Bank Implementation Status & Results Report VIETNAM: Haiphong Urban Transport Project (P111548) Bus service frequency is every 20 minutes, equivalent to the baseline data. The frequency is not Comments: improved due to the low number of passengers. IN00701933 ►perception of bus quality and passenger satisfaction on Line 2 (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 10.00 77.60 94.70 60.00 Date 31-Dec-2010 31-Aug-2018 20-Feb-2019 29-Feb-2020 Survey results showed that the satisfied passengers increased to 81% and the unsatisfied ones was 19%. They have found it safer and smoother travel when using the bus. However, there are 23.3% Comments: passengers unsatisfied with bus fare. IN00701935 ►development of an institutional framework for a Public Transport Authority (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value no Yes Yes yes Date 31-Dec-2010 31-Aug-2018 20-Feb-2019 29-Feb-2020 IN00701936 ►reduced traffic volume on NH5-Nam Hai (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value below below below below Date 31-Dec-2010 31-Aug-2018 22-Feb-2019 29-Feb-2020 IN00701938 NH10-Quan Tru (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target c = 3024 c=3949 c=3886 c = 3789 t = 3775 t=476 t=6163 t = 2980 Value b = 1155 b=6614 b=429 b = 1239 mc = 15289 mc=23341 mc=23813 mc = 13384 Date 31-Dec-2010 31-Aug-2018 22-Feb-2019 29-Feb-2020 IN00701939 Quan Tru-Nam Hai (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target c = 2224 c=4592 c=4633 c = 2095 t = 4098 t=540 t=5867 t = 966 Value b = 856 b=5536 b=537 b = 709 mc = 19609 mc=34971 mc=25248 mc = 11358 Date 31-Dec-2010 31-Aug-2018 22-Feb-2019 29-Feb-2020 Capacity Building IN00701931 ►human resource development plans executed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 5/28/2019 Page 6 of 8 The World Bank Implementation Status & Results Report VIETNAM: Haiphong Urban Transport Project (P111548) Value 0.00 3.00 3.00 3.00 Date 31-Dec-2010 31-Aug-2018 20-Feb-2019 29-Feb-2020 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P111548 IDA-49000 Effective USD 175.00 175.00 0.00 125.53 34.58 78% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P111548 IDA-49000 Effective 29-Mar-2011 31-May-2011 28-Jul-2011 31-Dec-2016 29-Feb-2020 Cumulative Disbursements 5/28/2019 Page 7 of 8 The World Bank Implementation Status & Results Report VIETNAM: Haiphong Urban Transport Project (P111548) Restructuring History Level 2 Approved on 29-Aug-2014 ,Level 2 Approved on 09-Jun-2015 ,Level 2 Approved on 09-Jun-2016 ,Level 2 Approved on 22-Dec-2016 Related Project(s) There are no related projects. 5/28/2019 Page 8 of 8