E4647 v10 Tamil Nadu Road Sector Project - II Detailed Project Report (DPR) For Various Road  Improvement Works under PPC 01 of Tamil Nadu Road  Sector Project – II (TNRSP II)  g Environmental Management  Plan – SH 58 (Revision‐2) September 2014 (A Govt. of India Enterprise) RITES Bhawan Plot No. 1, Sector-29, Gurgaon (Haryana) – 122 001 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division TABLE OF CONTENTS CHAPTER 1: INTRODUCTION.............................................................................................................................. 4  1.1  ENVIRONMENTAL ASSESSMENT PROCESS ....................................................................................................... 6  1.2  OBJECTIVES OF ENVIRONMENTAL MANAGEMENT PLAN (EMP) ..................................................................... 7  1.3  UNIQUE CHARACTERISTICS OF PROJECT LOCATION – TAMIL NADU ............................................................... 7  1.4  ENVIRONMENTAL REGULATIONS APPLICABLE TO THE PROJECT .................................................................... 7  1.5  METHODOLOGY OF PREPARING EMP.............................................................................................................. 8  1.6  DEFINITION OF TERMS USED IN THE PROJECT .............................................................................................. 10  CHAPTER 2: PROJECT DESCRIPTION ............................................................................................................ 11  2.1.  REGIONAL SETTING OF THE PROJECT ROAD .................................................................................................. 11  2.2.  LINK DESCRIPTION ........................................................................................................................................ 11  2.3.  PROPOSED PROJECT IMPROVEMENTS ............................................................................................................ 16  2.4.  ENVIRONMENTAL ENHANCEMENT MEASURES ADOPTED IN THE PROJECT.................................................... 16  CHAPTER 3: ENVIRONMENTAL MANAGEMENT ACTION PLAN ........................................................... 18  CHAPTER 4: ARRANGEMENTS FOR IMPLEMENTATION OF EMAP..................................................... 42  4.1.  ORGANISATION, STAFFING AND RESPONSIBILITIES OF PMU......................................................................... 42  4.2.  ORGANISATION, STAFFING AND RESPONSIBILITIES OF CONSTRUCTION SUPERVISING CONSULTANT (CSC) . 45  4.3.  ORGANISATION, STAFFING AND RESPONSIBILITIES OF CONSTRUCTION CONTRACTOR ................................. 47  4.4.  INFORMATION DISSEMINATION ..................................................................................................................... 49  4.5.  GRIEVANCE REDRESSAL MECHANISM .......................................................................................................... 49  4.6.  TRAINING PROGRAMME ON ENVIRONMENTAL ASPECTS ............................................................................... 49  CHAPTER 5: ENVIRONMENTAL MONITORING AND REPORTING REQUIREMENTS....................... 51  5.1.  MONITORING AND REPORTING OF ENVIRONMENTAL MANAGEMENT MEASURES ......................................... 51  5.2.  ENVIRONMENTAL QUALITY MONITORING PLAN FOR THE PROJECT .............................................................. 53  CHAPTER 6: ENVIRONMENTAL BUDGET ..................................................................................................... 54  6.1.  MITIGATION/ENHANCEMENT MEASURES ...................................................................................................... 54  6.2.  COST ESTIMATES .......................................................................................................................................... 54  6.2.1  Surface Water Bodies .................................................................................................................... 55  6.2.2  Ground Water Bodies: ................................................................................................................... 55  6.2.3  Sensitive Receptors: ....................................................................................................................... 55  6.2.4  Forest............................................................................................................................................. 55  6.2.5  Compensatory Afforestation .......................................................................................................... 55  6.2.6  Religious/cultural and other Community assets ............................................................................ 55  6.2.7  Bus Stops ....................................................................................................................................... 56  Revision Level: R2 September, 2014 Page 1 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division LIST OF TABLES Table 1.1 Project Roads 4 Table 1.2: List of Environmental Regulations Applicable To the Project 7 Table 1.3: Guidelines in EMAP 9 Table 2.1: Environmental Data Sheet 13 Table 3.1: The Environmental Management Action Plan (EMAP) 19 Table 4.1: Staffing Pattern in Contractor’s Office 45 Table 4.2: Training Programme to the Contractor’s Staff 48 Table 6.1: Summary of Mitigation/Enhancement Measures 53 Table 6.2: Cost Estimates for Environmental Management LIST OF FIGURES Figure1.1: Index Map 5 Figure 2.1: Regional Setting of the Project Area 12 Figure 4.1: Institutional Organisation of TNRSP for EMP Implementation 41 Figure 4.2: Environmental Management Unit (EMU) Of TNRSP 41 Figure 4.3: Organisation Structure, TNRSP 42 LIST OF ANNEXURES Annexure 3.1. Guidelines for Siting, Management and Redevelopment of Construction Camps Annexure 3.2. Guidelines for Siting, Management and Redevelopment of Labour Camps Annexure 3.3. Guidelines for Siting, Management and Redevelopment of Quarrying and Stone Crushing Operations Annexure 3. 4. Guidelines for Siting, Management and Redevelopment of Borrow Areas Annexure 3.5. Guidelines forSiting, And Management of Debris Disposal Site Annexure 3.6. Guidelines for Preparing Comprehensive Waste Management Plan Annexure 3.7. Guidelines for Top Soil Conservation and Reuse Annexure 3. 8. Guidelines for Provision of Noise Barriers Annexure 3.9. Guidelines to Ensure Worker’s Safety during Construction Annexure 3.10. Guidelines for Preparation of Traffic Management Plan Annexure 3.11. Guidelines for Storage, Handling, Use and Emergency Response For Hazardous Substances Annexure 3.12 Guidelines for site clearance and tree felling Annexure 3.13 Guidelines for Soil erosion and sedimentation control Annexure 3.14 Guidelines for Arrangement with forest department Annexure 3.15 Guidelines for selection for tree species Annexure 3.16 Guidelines for environment friendly construction methodology Annexure 3. 17. Reporting Format for Identification of Construction Camp Site Annexure 3. 18. Reporting Formats for Identification of Labour Camp Site Annexure 3. 19. Reporting Format for Identification of Quarry and Stone Crusher Site Annexure 3. 20. Reporting Format for Identification of Borrow Areas Revision Level: R2 September, 2014 Page 2 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Annexure 3. 21. Reporting Format for Identification of Debris Disposal Site Annexure 3. 22. Reporting Format for Identification of Sources of Water for Construction Annexure 3. 23. Format for Register of Complaints and It’s Reporting Annexure 3. 24. Format for Register of Sites Opened and Closed and It’s Reporting Annexure 3. 25. Checklist for Monitoring Of Construction Camp Management Annexure 3. 26. Checklist for Monitoring Of Labour Camp Management Annexure 3. 27. Checklist for Monitoring Of Quarry and Stone Crusher Management Annexure 3. 28. Checklist for Monitoring Of Borrow Area Management Annexure 3. 29. Checklist forthe Monitoring Of Debris Disposal Site Management Annexure 3. 30. Check List for Monitoring Of Redevelopment of Construction Camp Site Annexure 3. 31. Check List for Monitoring Of Redevelopment of Labour Camp Site Annexure 3. 32. Check List for Monitoring Of Redevelopment of Quarry and Stone Crusher Site Annexure 3. 33. Check List for Monitoring Of Redevelopment of Borrow Areas Annexure 3. 34. Check List for Monitoring Of Redevelopment of Debris Disposal Site Annexure 3. 35. Reporting Format for Work Force Management Annexure 3. 36. Reporting Format for Occupational Health and Safety Measures Annexure 3. 37. Reporting Format for Top Soil Conservation Annexure 3. 38. Reporting Format for Water Sprinkling For Dust Suppression Annexure 3. 39. Reporting Format for Road Safety Measures during Construction Annexure 3. 40. Format for Register of Accidents and It’s Reporting Annexure 3. 41. Reporting Format for Environmental Quality Monitoring Annexure 3. 42. Reporting Format for Enhancement and Mitigation of Cultural Properties Annexure 3. 43. Reporting Format for Noise Barrier Construction Annexure 3.44. Reporting Format for Enhancement Measures Other Than Cultural Properties Annexure 3. 45. Reporting Format for Tree Plantation Annexure 3. 46. Reporting Format for Monthly Report from Contractor to CSC Annexure 3. 47. Reporting Format for Monthly Report from CSC toPMU Annexure 3. 48. List of Permissions to Be Obtained By the Contractor Annexure 3. 49. Schematic Diagram of Catch Drain and Oil Interceptors Annexure 3. 50. Proposed Chainages ofRetaining Wall Location Where Embankment Height Will Be Raised Annexure 3. 51. Sensitive Noise Receptors :impact, mitigation and enhancement Annexure 3. 52. Water Bodies Impact : Mitigation and Enhancement Annexure 3. 53. Schedule and Specification for Mitigation and Enhancement Measures Annexure 3. 54. Tree Planting and Environmental Enhancement Plan Annexure 3. 55. Environmental Enhancement Drawings, BOQ and Cost Annexure 3. 56. Cultural Properties : impact, mitigation and enhancement Annexure 5.1.Guidelines for monitoring program Revision Level: R2 September, 2014 Page 3 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division CHAPTER 1: INTRODUCTION The Government of Tamil Nadu under Tamil Nadu Road Sector Project I (TNRSP I) has improved the State Highways for a length of about 1800 km under various improvement programmes such as upgradation, enhanced periodical maintenance, performance based maintenance and Public Private Partnership. Under Tamil Nadu Road Sector Project II (TNRSP II), about 2100 km of State Highways is taken up for various improvement works. Both TNRSP I and TNRSP II road improvement programmes are under World Bank assistance. The TNRSP II is expected to cover up gradation, maintenance and improvement of the identified core road network. The total cost of the project in TNRSP II is estimated as Rs. 8500 crore approximately having five packages of roads (PPC01 to PPC05). RITES Limited has been awarded the Contract Package: PPC01 in October 2013 for preparation of Detailed Project Report (DPR). There are 10 roads having a total length of 407.301 km in TNRSP II (PPC 01), out of which 135.327 km is under phase I road are shown in Index Map at Figure 1.1 highlighted in blue color and described in Table 1.1. Table 1.1: Project Roads S. Project Road Section Road ID Chainage Length No. From To (km) 1 Kodambakkam – Sriperumbudur SH-113 Km 12.500 Km 28.800 16.300 2 Kanchipuram– Vandavasi Road SH-116 Km 14.115 Km 36.457 22.342 Km 2.900 Km 14.115 11.215 3 Sadras – Chengalpattu – Kanchipuram – SH-58 Km 0.000 Km 26.745 26.745 Arakkonam – Tiruthani Km 26.811 Km 107.350 80.539 4 Chennai – Pulicat SH-104 Km 0.000 Km 25.500 25.500 5 Arani – Villupuram SH-4 Km 29.280 Km 115.520 86.240 6 Cheyyur – Vandavasi – Polur SH-115 Km 0.000 Km 105.000 105.000 7 Tambaram-Mudichur-Sriperumbudur Road SH-110 Km 18.000 Km 23.500 5.500 8 Tiruvotiyur-Ponneri-Pancheti Road SH-56 Km 15.5000 Km 27.8000 12.300 9 ECR link: Cheyyur-Panayur Road ODR Km 0.000 Km 5.000 5.000 10 Pallavaram – Thuraipakkam Road (six SH 109 Km 0.000 Km 10.620 10.620 laning) Total 407.301 Note: Road shown in bold letters indicate Phase-I roads under TNRSP-II The present report on environmental management plan is prepared for SH 58 having a length of 26.745 km in accordance with the World Bank's guidelines to define the Environmental Management requirements to ensure environmental safeguards during construction and operation. . This requires World Bank and GOI clearances and approvals before construction can proceed. Revision Level: R2 September, 2014 Page 4 P Detailed Project ( Report (DPR) For Vari rovement Work ious Road Impr 1 of ks under PPC 01 Tamil Nadu Road Sector TNRSP II) r Project – II (T Environneemental Manag gement Plan Documen nt Ref: RITES/UUE/2553-61/SH H 58 ay Division Highwa URE 1. 2: IND FIGU DEX MAP Revision Level: R2 ber, 2014 Septemb Page 5 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division The most important parts of this document are that it comprises activity wise impacts and mitigation measures identified for each environmental attribute like land, water, air, noise, biological environment and social environment. A robust Monitoring and Reporting (M&R) system is in-built into it for various phases of the project and activities. This is supported by annexure, which provides (i) detailed guidelines to enable the contractor to implement the EMAP in an appropriate manner, (ii) monitoring formats for the contractor to report to CSC (Construction Supervision Consultant) and (iii) checklists for the CSC to monitor the implementation of EMAP. RAP provides compensation and rehabilitation, for direct (private properties) social impacts, while EMP provides other social impact mitigation and enhancement for direct (public properties) and indirect impacts. The  Link  Specific  EMAP  with  its  annexure  provides  specific  impacts,  mitigation  measures  and  enhancement details.  1.1 Environmental Assessment Process The Environmental Assessment and Environmental Management Plan (EMP) is prepared for Phase-I roads under TNRSP-II in package I (PPC 01) of TNRSP – II. This document addresses the corridor-specific Environmental Management Plan (EMP) for the 26.745km of Sadras - Chengalpattu road (SH 58) included in the TNRSP-II improvement programme. EIA and EMP reports identify the environmental impacts in the earlier stages of project preparation to incorporate necessary mitigation measures required to minimise those impacts as well as to enhance the positive factors. All environmental management/ mitigation costs have been included in the Bill of Quantities (BOQ) titled ‘Environmental impact mitigation works’. In addition to this an environmental monitoring and training budget is included separately as project costs. The project’s Social Impact Assessments is resulted in the preparation of a Resettlement Action Plan (RAP) for the proposed SH 58 road to address the land acquisition procedures and all associated social aspects such as compensation, resettlement and relocation. Similarly the environmental studies has led to the preparation of project specific EMPs. This document assists the Contractor and associated officials to mitigate or minimize the negative social and environmental impacts due to the construction and operation of the project and to enhance the positive impact of the project. The EA and EMP have been prepared to meet the GOI requirements as specified by the Ministry of Environment, Forests and Climate Change (MoEFCC) and meeting the requirements of the World Bank. Its purpose is to present an evaluation of potential impacts due to the proposed upgradation and realignment of the existing State Highway from Sadras - Chengalpattu. The document presents the impacts, mitigation measures and appropriate costs for the proposed mitigation measures. The environmental and social impact mitigation and enhancement details of the proposed action within the SH 58 corridor are presented and evaluated in detail in Environmental Assessment and Environmental Management Plan (EMP). Institutional strengthening for environmental management is also an essential part of this document for implementing contract provisions and other environmental mitigation and enhancement provisions. Revision Level: R2 September, 2014 Page 6 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 1.2 Objectives of Environmental Management Plan (EMP) The objectives of the Environmental Management Plan (EMP) are to • Define the Environmental management principles and guidelines for the pre- construction, construction and post construction phases of the road improvement. • Describe the practical mitigation measures that should be implemented on road improvement works to prevent or mitigate any negative environmental impacts and to enhance the positive issues. • Establish the roles and responsibilities of all parties involved in the implementation of environmental controls; • Establish monitoring and reporting system for facilitating appropriate implementation of EMP. 1.3 Unique Characteristics of Project Location – Tamil Nadu Tamil Nadu covers an area of 130,058 km2 and is the eleventh largest state in India. The bordering states are Kerala to the west, Karnataka to the North West and Andhra Pradesh to the North. To the east are the Bay of Bengal and the union territory of Pondicherry. Tamil Nadu is the southernmost tip of the Indian Peninsula and has a coastline of about 910 km, the country's third longest coastline. The project is located in a region of low seismic hazard with the exception of the western border areas that lie in a low to moderate hazard zone; as per the 2002 Bureau of Indian Standards (BIS) map. The project area falls in Zones II & III of the seismic zoning map of India. 1.4 Environmental Regulations Applicable To the Project Summary of environmental clearances/ permits/ approvals required for the project is presented in Table 1.2. During the pre-construction stage, the responsibility of obtaining clearances from concerned authority lies with TNRSP. The responsibility of clearances required for construction phase, but prior to work initiation lies with the contractor. TABLE 1.2: LIST OF ENVIRONMENTAL REGULATIONS APPLICABLE TO THE PROJECT S. Type of Statutory Applicability Project Responsibility No Clearance Authority Stage 1. Environmental MoEF/SEIAA Not Applicable Not Applicable Not Clearance Applicable 2. Forest Clearance for Forest Department, Applicable since Pre construction TNRSP land diversion TNRSP project road is passing through forest 3. Tree felling District Collector For roadside Pre construction TNRSP permission tree cutting 4. Explosive License Chief For storing fuel Construction The Contractor from Chief Controller of oil, lubricants, stage (Prior to Controller of Explosives, diesel etc. at initiation of any Explosives, petroleum & construction work) Explosive camp Safety Organization Revision Level: R2 September, 2014 Page 7 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S. Type of Statutory Applicability Project Responsibility No Clearance Authority Stage 5. Permission for CPCB Manufacture Construction The Contractor storage of hazardous storage and stage (Prior to chemical Import of initiation of any Hazardous work) Chemical 6. Quarry Lease Deed EC fromSEIAA Quarry Construction The Contractor and Quarry License and CTE AND operation (for stage (Prior to CTO new quarry) initiation of any fromTNPCBandDe work) partment of Geology and Mines 7. Permission for State Ground Water Extraction of Construction The Contractor extraction of ground board ground water stage (Prior to water for use in road initiation of any construction work) activities 8. Permission for use of Irrigation Use of surface Construction The Contractor water for Department water for stage (Prior to construction purpose construction initiation of any work) 9. Labour license from labour Engagement of Construction The Contractor commissioner Labour stage (Prior to office initiation of any work) 10. Extraction of sand District level Extraction of Construction The Contractor from rivers Expert committee Sand from stage (Prior to under district rivers initiation of any collector and work) local govt. body 1.5 Methodology of Preparing EMP Much of the environmental degradation that happens during the construction stage of a highway can be prevented or controlled, if there is an appropriate system in place. Hence, this EMAP has been specifically designed to capture all the impacts that take place during the entire life cycle of a project from design to operation stage. Accordingly, a thorough activity analysis was carried out listing out all the project activities, based on which an impact identification matrix was prepared to understand the impacts upon various environmental parameters such as land, water, air, noise, flora and fauna. Lastly, socio-economic impact upon people and solid waste generation was also considered as separate impacts. Based on this exercise, a totally new Environmental Management Plan (EMP) has been prepared suggesting various mitigation measures to avoid or minimize the impacts of the project on the environment during the pre-construction, construction and operation phases. Two sets of guidelines were prepared and incorporated in the EMAP table of EMP reports to enable the contractor to implement the project with least impact upon the environment– (i) Guidelines for entire project stretch including the project facilities like camps and sites and (ii) Guidelines exclusively for siting, management and restoration of project facilities like camps and sites. Table 1.3 gives the list of these guidelines: Revision Level: R2 September, 2014 Page 8 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division TABLE1.3: GUIDELINES IN EMAP S. No. TITLE A GUIDELINES FOR ENTIRE PROJECT STRETCH 1. Guidelines for preparing comprehensive waste management plan 2. Guidelines for top soil conservation and reuse 3. Guidelines for Provision of Noise Barriers 4. Guidelines to Ensure Worker’s Safety during Construction 5. Guidelines for Preparation of Traffic Management Plan 6. Guidelines for Storage, Handling, Use and Emergency Response For Hazardous Substances 7. Environmental monitoring plan B GUIDELINESFORPROJECTFACILITIES 1. Guidelines for siting, management and redevelopment of construction camps 2. Guidelines for siting, management and redevelopment of labour camps 3. Guidelines for siting, management and redevelopment of quarrying and stone crushing operations 4. Guidelines for siting, management and redevelopment of borrow areas 5. Guidelines for siting and management of debris disposal site The guidelines for project facilities have been structured with following objectives: i. It facilitates the selection of a site with least environmental impact, ii. It looks into the satisfaction of the land owner in case of leased out / rental out lands, iii. It guides the contractor with step by step measures in setting up of an efficient and environment friendly camp / site, iv. It ensure smooth, safe and efficient functioning of these camps and sites, v. It guides the contractor in preparing a camp / site management and restoration plan to be submitted to CSC (prior to setting up of the camp/site), and vi. It facilitates restoration of the site at the closure stage in a very environment friendly manner. EMP assigns the responsibilities for various actions identified to limit the adverse impacts of the project. An environmental monitoring plan and an institutional framework have been proposed as part of the EMP for proper implementation and monitoring of mitigation measures. The cost for implementing the proposed environmental mitigation measures and carrying out the environmental monitoring has been worked out and is presented as part of the EMP for necessary budgetary allocations as part of the project cost. In order to implement various environmental requirements during pre construction, construction and operational phases, all mitigation and enhancement measures have been clearly built in to the Environmental Management Plan. All necessary mitigation and enhancement costs have been part of the BOQ. Revision Level: R2 September, 2014 Page 9 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 1.6 Definition of Terms Used In the Project Links: All project roads are identified by link numbers in the Detailed Project Report. According to this, SH 58 has been assigned the link ID of L0581. Package: Packages are identified for the purpose of creating attractive construction contracts to National and International Contractors. A package average of 100 km of roads is made up of one or more Links. Contractors may not take interest in a contract if it is not of sufficient size and profitability to merit attention. A Contractor may bid for more than one contract package. The project road SH 58 is in Package I having link ID L0581. ROW: The Right of Way is the land width legally available to the TNRSP. The actual Right of Way can only be established after the legal verification of all adjoining properties. The ROW is often encroached upon on one or both sides. ROW details were not made available to the consultants and were defined by the Client as that area determined by the physical appearance of the existing limits of the Highway, which has been open to the public for unrestricted access over many years. Land Plan Schedule is getting prepared which will avail the existing ROW and land requirement as per the proposed ROW. Available Corridor: Since the legal ROW details are not available from the TNRSP, the consultants considered the existing corridor width that is physically available as defined above and referred to it as available corridor for the purpose of project preparation. Land Plan Schedule is getting prepared to avail the legal ROW corridor. Realignment: Realignment usually refers to an increase in the horizontal curve radius but may be generally applied to any change in the vertical or horizontal alignment of a road. Bypass: A bypass is the term usually applied to a road, which provides an alternative route around a congested urban area. This usually helps to divert traffic away from the urban centre. The bypass proposed for SH 58 is considered for study in Normal Road Schedule Project Private trees: These are trees situated in private properties within the required corridor and which will need to be compensated in monitory terms according to the Resettlement Action Plan. Public trees: Public trees are those trees that are located within the available corridor of the HD or on a Barren Land (no registered ownership but accounted as land of the Revenue Department). Revision Level: R2 September, 2014 Page 10 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environnemental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division CHAPTER 2: PROJECT DESCRIPTION 2.1. Regional Setting of the Project Road Tamil Nadu is the eleventh largest state by area and the sixth most populous state in India. 44 per cent of the state's population live in urban areas, the highest among large states in India. The state was ranked sixth among states in India according to the Human Development Index in 2011. Population density of Tamil Nadu is 555 per sq km which is higher than national average 382 per sq km. The bordering states of Tamil Nadu are Kerala to the west, Karnataka to the North West, Andhra Pradesh to the North and to the east are the Bay of Bengal and the union territory of Pondicherry. The project road connects Sadrasand Chengalpattu of Kanchipuram districts.Regional setting of the project road is shown in Figure 2.1. 2.2. Link Description The project road designated as SH 58, starts at Chainage km 0/000 near village Meyur and ends at the start of road over bridge (ROB) under construction near Chengalpattu railway station at Chainage km 26/811. Environmental Data Sheet Environmental data sheet comprises of chainage wise existing details of environmental and social features, road furniture details, location of cross drainage structures, water body and sensitive receptors details of the corridor (SH 58). Table 2.1 presents the Environmental Data Sheet for the proposed road SH 58. Revision Level: R2 September, 2014 Page 11 P Detailed Project ( Report (DPR) For Vari rovement Work ious Road Impr 1 of ks under PPC 01 Tamil Nadu Road Sector TNRSP II) r Project – II (T Environneemental Manag gement Plan Documen nt Ref: RITES/UUE/2553-61/SH H 58 ay Division Highwa G OF THE PROJECT FIGURE 2.1: REGIONAL SETTING P AREA A Revision Level: R2 ber, 2014 Septemb 2 Page 12 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division TABLE 2.1: ENVIRONMENTAL DATA SHEET Chainage Environmental and social features Bus stops Agriculture,Barren,Residenti Hospitals/Schools/ From To Left side of the road Right side of the road al,Commercial water Crematoria/ Grave body/Overhead Tank Yard 0.00 1.00 1Well ,3Temple, 1 Bus 1 Pond , 1 school , 1 Bus stop on LHS 1 well on LHS, 1 school on RHS stop, 1 Overhead Tank 3 Temple 1 Pond on RHS 3 Temples on LHS AR AR 1 Overhead Tank on LHS 3 Temples on RHS AR on the LHS AR on the RHS 1.00 2.00 AB AB AB on the LHS AB on the RHS 2.00 3.00 1 water logged area Water logged area 1 Bus stop on LHS 1 water logged area RHS 3 Temples on LHS 3 Temple, 1 Bus stop, AB 1 Water logged area LHS 1 Overhead Tank 1 Overhead Tank on LHS AB AB on the LHS AB on the RHS 3.00 4.00 3 Temple, 1 Bus stop, 1 school 1 Bus stop on LHS 1 Overhead Tank on LHS 1 school on RHS 1 Overhead Tank 3 Temples on LHS 4.00 5.00 1 Bus stop 1 Bus stop 1 Bus stop on LHS 1 Bus stop on RHS 5.00 6.00 1 Pond, 1 Bus stop 1 Bus stop 1 Bus stop on LHS 1 Pond on LHS 1 Bus stop on RHS 6.00 7.00 1 Temple, 1 Bus stop 1 Bus stop on RHS 1 Temples on LHS 7.00 8.00 1 Bus stop 1 school 1 Bus stop on LHS AB on the LHS AB AB AB on the RHS 8.00 9.00 1 school, 1 Temple, 1 Temple, 1 Overhead 2 Bus stop on LHS 1 Overhead Tank on RHS 1 Temples on LHS 2 Bus stop Tank ACR on the LHS 1 Temples on RHS ACR ACR ACR on the RHS 9.00 10.00 1Well, 1Pond, 1 Bus 1 Temple, 1 Bus stop 1 Bus stop on LHS 1 well on LHS, 1 Temples on RHS stop, 1 Overhead Tank ACR 1 Bus stop on RHS 1 Pond on RHS ACR 1 Overhead Tank on LHS ACR on the LHS ACR on the RHS 10.00 11.00 1 Temple, 2 Bus stop AB 2 Bus stop on LHS AB on the LHS 1 Temples on LHS Revision Level: R2 September, 2014 Page 13 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Chainage Environmental and social features Bus stops Agriculture,Barren,Residenti Hospitals/Schools/ From To Left side of the road Right side of the road al,Commercial water Crematoria/ Grave body/Overhead Tank Yard AB AB on the RHS 11.00 12.00 1 College /ITI, 1 Temple, 1 Overhead Tank on RHS 1 Temples on RHS 1 Overhead Tank 12.00 13.00 13.00 14.00 2 Temple 2 Overhead Tank 2 Overhead Tank on RHS 2 Temples on LHS 14.00 15.00 1Pond, 3 Temple, 1 College, 1 school 2 Overhead Tank on LHS 3 Temples on LHS 2 Overhead Tank 15.00 16.00 1 school 16.00 17.00 1 Temple, 1 Overhead Tank on RHS 1 Temples on RHS 1 Overhead Tank 17.00 18.00 2 Temple, 1 Bus stop AB 1 Bus stop on LHS AB on the LHS 2 Temples on LHS AB AB on the RHS 18.00 19.00 1 Bus stop AB 1 Bus stop on LHS AB on the LHS AB AB on the RHS 19.00 20.00 1 school, 2 Temple, 1 1 Temple, 1 Bus stop, 1 Bus stop on LHS 2 Overhead Tank on RHS 2 Temples on LHS Bus stop 2 Overhead Tank 1 Bus stop on RHS AB on the LHS 1 Temples on RHS AB AB AB on the RHS 20.00 21.00 1 Pond, 2 Temple 2 Bus stop, 2 Bus stop on RHS 1 Pond on LHS 2 Temples on LHS AB 1 Overhead Tank 1 Overhead Tank on RHS AB AB on the LHS AB on the RHS 21.00 22.00 AR 1Pond 1 Pond on RHS AR AR on the LHS AR on the RHS 22.00 23.00 1 Well , 1 school, 1 Bus stop 1 Bus stop on LHS 1 Well on LHS 2 Temples on LHS 2 Temple, 1 Bus stop, AR 1 Bus stop on RHS 1 Overhead Tank on LHS 1 Overhead Tank AR on the LHS AR AR on the RHS 23.00 24.00 1 Pond, 2 Temple 1 Pond 1 Pond on LHS 2 Temples on LHS AR ARB 1 Pond on RHS AR on the LHS ARB on the RHS Revision Level: R2 September, 2014 Page 14 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Chainage Environmental and social features Bus stops Agriculture,Barren,Residenti Hospitals/Schools/ From To Left side of the road Right side of the road al,Commercial water Crematoria/ Grave body/Overhead Tank Yard 24.00 25.00 1Well, 3 Temple, 2 Temple, 1 well on LHS 3 Temples on LHS 1 Overhead Tank 3 Overhead Tank 1 Overhead Tank on LHS 2 Temples on RHS ARB ARB 3 Overhead Tank on RHS ARB on the LHS AR B on the RHS 25.00 26.00 1 Bus stop, 1 Pond, 3 Temple, 1 Bus stop on LHS 1 Pond on RHS 1 Health care centre ARB 1 Overhead Tank 1 Overhead Tank on RHS RHS ARB ARB on the LHS 3 Temples on RHS AR B on the RHS 26.00 27.00 1 school, 3 Temple, 1 Temple, 2 Bus stop 2 Bus stop on LHS RB on the LHS 3 Temples on LHS 2 Bus stop RB 2 Bus stop on RHS R B on the RHS 1 Temples on RHS RB Source: - Data collected by RITES Team Note – A: Agriculture, B: Barren, R: Residential, C: Commercial Revision Level: R2 September, 2014 Page 15 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 2.3. Proposed Project Improvements Study mandates the improvement of the project road to two lane with paved shoulder standards with other improvements to make the road a standard facility. Improvement proposals formulated are based on the IRC guidelines and site specific requirements. The proposed improvements are aimed at easing traffic congestion, reducing the road accidents by improving physical characteristics of the road, which includes geometry, pavement strength, drainage and enhancing the aesthetics. General philosophy followed in formulating the improvement proposals are: • Limit the improvements within the land identified for the project. • Introduce transition to all the curves along the alignment • Utilize the available Right of Way to the maximum extent possible so as to avoid additional land acquisitions • Improve and introduce the project facilities • Improvement of road safety features Accordingly, the following optimum level of improvements is proposed: • Widening of the project road as the traffic warrants; • Strengthening/reconstruction of the existing pavement for the entire length; • Provision of footpath cum built-up drain at built-up and industrial locations; • Improving/redesigning sharp curves; • Widening/reconstruction of existing culverts and provision of additional culverts depending on the cross drainage requirements; • Bridge and cross drainage rehabilitation, widening and reconstruction. • Junction improvements; • Provision for pedestrian crossing facilities; • Provision of traffic signs and road furniture; • Provision of bus shelters, and • tree plantation 2.4. Environmental Enhancement Measures adopted in the Project General environmental enhancement measures proposed for the project are construction of retaining wall, construction of boundary wall, provision planting trees on the inner side of the sound insulating wall as noise barrier at sensitive locations, planting trees on both sides of the road at places where land is available, landscaping of junctions etc., Apart from this, public utilities such as construction of bus shelters and bus byes will be undertaken along the project corridor. Guidelines for siting, management and redevelopment of construction camps, labour camps, quarrying and stone crushing operations, borrow areas, debris disposal site are described in Annexure 3.1 to Annexure 3.5 while guidelines for waste management plan, top soil conservation and reuse, noise barriers, worker’s safety during construction, traffic management plan, storage, handling, management and emergency response for hazardous substances, site clearance, selection of tree species and environment friendly construction methodology are given in Annexure 3.6 to Annexure 3.16. Revision Level: R2 September, 2014 Page16 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division The environmental impact mitigation measures and enhancement measures proposed are covered under EMAP (Refer Table 3.1) and the environmental enhancement drawings, BOQ and Costare provided as Annexure 3.55. The tree planting and environmental enhancement plan are provided in Annexure 3.54. Guidelines for monitoring program given in Annexure 8.1 of Chapter 8 of EA report is reproduced here again for quick reference. Revision Level: R2 September, 2014 Page17 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division CHAPTER 3: ENVIRONMENTAL MANAGEMENT ACTION PLAN Environmental mitigation measures have been incorporated within the design process, including the avoidance of potential impacts through changes in the alignment and other means. Appropriate measures have also been identified for action in the construction and operational phases. Environmental Management Action Plan (EMAP) tabulates the measures identified for all phases i.e. the design, pre-construction, construction and operational phases identifying the nature of the potential environmental impact, their mitigation measures, the implementing agency and responsible organisation and where appropriate, the contractual clause or reference. EMAP is given in Table 3.1. The role and responsibility of the organisations mentioned in the table are mentioned below. State Pollution Control Board (SPCB): The State Pollution Control Board will be responsible for any matters related to air, water and noise pollution during construction and operational stages. Any matters related to this may be brought under their notice for solution. Forest Department: Any matters related to social forestry, forests, wildlife and trees etc should be consulted with the local DFO or Forest Range Officer, Forest Department depending upon the advice required. PMU and HD: PMU will be available only in the State head quarters at Chennai. Most of the work in the local level will be taken care of at the local HD level throughout Tamil Nadu. Final Design Consultant: Preparation of final road designs and contract documentation is based on the preliminary road designs and the formulation of the Environmental Management Plan and Environmental Management Action Plan recommendations. Environmental Specialist of PMU: ES will be responsible for all matters of environmental monitoring and inter Governmental co-ordination. Traffic Police and State Police: Any matters related to traffic and violation of traffic and other law and order issues may be taken up with the traffic police and State Police. Tamil Nadu Water Supply and Drainage Board (TWAD) : TWAD will be responsible for any matters relating to water supply, water taps, bore wells and tube wells along the sides of the roads. Irrigation Department: The irrigation department will be responsible for all matters relating to rivers, canals, waterways and irrigation canals. Local bodies (Panchayat and Municipal Authorities): Panchayat and Municipal authorities will be responsible for local bus waiting sheds, Panchayat and municipal public wells etc. Motor Vehicle Department: The motor vehicle department will be responsible for the issue and matters relating to Pollution under Control Certificates, driving licences etc. Revision Level: R2 September, 2014 Page18 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Fire Force and Fire Station: The matters relating to safety especially relating to fire safety may be taken up with the Fire force. Archaeological Department: All matters relating to ancient archaeological structures and historical monuments that may encounter during construction works or identified during pre- construction stage. Mining and Geology Department: All matters relating to quarry and sand materials may be referred to State Mining and Geology Department. Penalty for Non-conformity to EMP Clause No. Description Protection of the The Contractor shall implement all mitigation measures for which responsibility Environment is assigned to him as stipulated in the EMP Report. Any lapse in implementing the same will attract the penalty clause as detailed below: 1. All lapse in obtaining clearances / permissions under statutory regulations and violations of any regulations with regard to eco-sensitive areas shall be treated as a major lapse. 2. Any complaints of public, within the scope of the Contractor, formally registered with the CSC, or with the PWD complaint cell and communicated to the contractor, which is not properly addressed within the time period intimated by the CSC / PMU shall be treated as a major lapse. 3. Non-conformity to any of the mitigation measures stipulated in the EMP Report (other than stated above) shall be considered as a minor lapse. 4. On observing any lapses, CSC shall issue a notice to the Contractor, to rectify the same. 5. Any minor lapse for which notice was issued and not rectified, first and second reminders shall be given after one month from the original notice date and first reminder date respectively. Any minor lapse, which is not rectified, shall be treated as a major lapse from the date of issuing the second reminder. 6. If a major lapse is not rectified upon receiving the notice, CSC shall invoke the penalty clause, in the subsequent interim payment certificate. 7. Penalty for major lapses shall be with-holding of 10% of the interim payment certificate, subject to a maximum limit of Rs. 30 lakhs. 8. If the lapse is not rectified within three months after withholding the payment, the amount withheld shall be forfeited. 9. CSC shall submit the progress of work to Project Implementation Unit (PIU) on monthly basis. If progress of work is not found satisfactory, CSC issues notice in triplicate duly signed by Environmental Specialist. One copy is for TNRSP, CSC own file and one copy for Contractor. Receipt of the notice is signed by the contractor for the record purpose. Public Participation The participation of local people during field study was included in the study by conducting consultations discussing various issues concerning to the project. These consultations were done along the corridor which helped in Revision Level: R2 September, 2014 Page19 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division conducting the public consultation in an organised way as described below. Some of the findings collected are as described below. 1. People were concerned about the impact on environment with respect to tree loss 2. Majority of tree is tamarind and livelihood of local people is dependent on it. 3. People were found concerned about the impact on common facility like hand pump, tube wells, overhead tanks etc.. 4. People were found enthusiastic for development works of road and expressed all sorts of support during construction of the project, but suggested to minimize the social issues at the most. Structured Public Consultations Project Level Structured Public Consultation was conducted at Thirukazhukundram. Consultations were accomplished to collect the opinion/views on the project. At pre-scheduled date and venue, people were communicated to gather for consultation with the help of gram panchayat. Gathering was explained about the project activities and their consequences in brief. Queries of the participants were replied by the Consultant experts and at the same time their suggestions were also recorded. During the public consultation issues on trees, public utilities, community structures, employment and pollution during construction were discussed. Issue raised and suggestions given by the public is presented below. Photographs showing public consultation are shown in Figure. Summary of structured Public Consultation Location Issues Suggestions of Mitigation Measures Stakeholders Pollution Plantation of 10 trees per Afforestation in tree cutting consultation with forest department No problem with Monitoring for construction of project implementation of EMP will avoid construction nuisance Thirukazhukundram No pollution problem due to Monitoring for (SH-58) construction of project implementation of EMP will avoid construction nuisance Amenities Underground pipeline of All the utilities have water supply line disturbed identified which will be due to proposed road rehabilitated appropriately widening Employment Advantage to next Good road connectivity generation due to proposed encourages entrepreneur to development put industry and attracts tourist to visit the area. This creates employment. Revision Level: R2 September, 2014 Page20 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Revision Level: R2 September, 2014 Page21 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Table 3.1: The Environmental Management Action Plan (EMAP) Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause DESIGN PHASE General Standard cross section alternatives were used for the During Design PIU – TNRSP Design Not applicable in consideration of Project road design depending on the traffic requirement Consultant EA report Cross section and economic indicators. Alternatives Geometric Design The proposed alignment is selected/adjusted (within During PIU – TNRSP Design Not applicable in IRC/MoRTH specifications) alignment Consultant EA report - to minimize land disturbance design - to avoid culturally & environmentally sensitive areas – cultural properties, water bodies etc. Issues from Various issues raised were examined & suitably During Design PIU - TNRSP Design Chapter 5 EA stakeholder incorporated based on merit & other road safety Consultants Report Consultations measures. Avoidance of -No cultural properties along the alignment were During PIU – TNRSP Design Engineering Cultural Properties identified. alignment Consultants,Co Report, DPR -Religious Structures were avoided by adjustment of design ntractor alignment to the extent possible Preservation of tree Eccentric widening proposed TNRSP, Design During Engineering Department of Consultants, alignment Report, DPR Forest, TN. Contractor design Design Discharge As per MoRTH TNRSP Design During Design Not applicable in & Drainage design Consultants, EIA report Contractor Monitoring at The monitoring of Air, land, water and Noise has been During Design TNRSP Design Chapter 4: EA critical locations carried out at critical locations along the project corridor. Consultants Report This will serve as a benchmark for monitoring during Revision Level: R2 September, 2014 Page22 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause construction and operational phases. (Appendix 8.1: Monitoring Plan) Orientation of A comprehensive planning/orientation schedule has been During Design TNRSP Design Not applicable in Implementing prepared at different stages for TNRSP. Consultants EA report Agency External Influence Location and basic facilities at site are suggested in a During Design TNRSP Design Annexure 3.1 of construction way to cause minimum interference with the local Consultants, EMP Report camp system, for details refer Annexure 3.1: Guidelines for Contractor siting & layout of construction camp Diversion of Appropriate diversion of traffic schemes to ensure During Design PIU - TNRSP Design Engineering Traffic smooth traffic flow, minimize accidents during Consultants, Report, DPR and construction, design of diversionary signage Contractor Annexure 3.10 of EMP Accident black spot Improved road surface with improved road geometry, During design PIU - TNRSP Design Engineering Pedestrian facilities and Bus shelters is planned. Lining Stage. Traffic Police Consultants Report, DPR and signing is given a high priority for all road junctions. Traffic Safety Audits completed on the final design drawing and PoliceContracto corrective measures undertaken. r PRE-CONSTRUCTION PHASE Permissions/ Application for Tree felling permission to be submitted After centreline Department of PIU Annexure 7.1 of Approvals to Forest Department, GoTN/Other local Authority marking at site. Forest, TN EA report Application for Forest Land diversion (Not applicable for After centreline Department of PIU, SH 04) marking at site. Forest, TN Design Consultants Land Acquisition The land acquisition to be done as per `Right to Fair After proposed TNRSP, PIU, Land RAP/DPR Compensation and Transparency in Land Acquisition, centreline Revenue Acquisition Rehabilitation and Resettlement Act, 20 1 3` marking at site Department Officer (LAO- Revision Level: R2 September, 2014 Page23 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause TNRSP) PMC Property - Compensation to be paid to Project Affected Peoples Post design to TNRSP, PIU Acquisition based on the Resettlement Action Plan. Pre- Revenue R&R Officer RAP/DPR construction. Department, (TNRSP), PMC NGOs recommended in RAP Relocation of All community underground and over head utilities are to Post design to TNRSP PIU – R&R Engineering Utilities be shifted as per utility shifting plan, prior permission Pre- officer, Design Report, DPR should be obtained from regional offices of Electricity, construction Consultant, Telecommunications, OFC, Water works etc. Contractor Loss of Irrigation Mitigation/enhancement measures proposed in EA report Post design to TNRSP PIU, EA & EMP water source Pre- surface Water , Contractor Report (surface water) construction. Board /PHED Loss of Irrigation Financial compensation proposed Post design to TNRSP PIU, EMP Report water source Pre- Ground Water Contractor (Ground water) construction. Board /PHED Tree Felling Tree felling permission to be obtained from Forest Post design to TNRSP EMU, 3.2.3, Chapter 3 Department, GoTN/Other local Authority Pre- ,Department of Contractor EA Report construction. Forest, TN Religious/Cultural Mitigation/Enhancement measures have been proposed. Pre PIU – TNRSP Contractor 8.7.1.1 chapter- Properties There is no cultural properties along the corridor getting Construction 8, EA report. affected. Noise Sensitive Mitigation & Enhancement measures proposed. During design PIU – TNRSP Contractor 8.5.1 chapter-8, Receptors stage. EA report. Revision Level: R2 September, 2014 Page24 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause Existing Bus Stop Replacement Bus stop/ New Bus bays are proposed During design PIU – TNRSP Contractor Refer clause 2.8 stage. Transport chapter-2, EA corporation, report. Highway Dept. CONSTRUCTION PHASE Clearances, List of clearance Required prior to start of construction Construction TNRSP, SPCB, The Contractor General Approvals and Activity stage (Prior to CPCB, Chief Conditions of Permits Type of Clearance Applicability initiation of Controller of Contract Explosive License from For storing fuel oil, any work Explosives, Chief Controller of lubricants, diesel etc. District Explosives, Time period in Collector State getting the department of Permission for storage of Manufacture storage permission is Mines and hazardous chemical from and Import of 2-3 months. Geology, CPCB Hazardous Chemical State Ground Borrow Area, approval from Borrow area for Water Board, district collector, Consent excavation of earth State Irrigation letter, lease agreement with Department, the owner of land. Labour Quarry Lease Deed and Quarry operation (for commissioner Clause 111.3, Quarry License from State new quarry) officer, MoRTH Department of Mines and Contractor Geology Permission for extraction of Extraction of ground ground water for use in road water construction activities from State Ground Water board Permission for use of water Use of surface water Revision Level: R2 September, 2014 Page25 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause for construction purpose for construction from irrigation department Labor license from labor Engagement of Labor commissioner office Provide a copy of all necessary clearances to the PMC / EMU ¾ Adhere to all clearance terms and conditions ¾ Obtain written permission from private landholders to conduct construction activities on their land prior to commencing works. Environmental Monitoring is to be carried out regularly as per the During and SPCB, PIU – Contractor Annexure 8.1. Management frequency and locations mentioned in Annexure 8.1. after TNRSP, And Monitoring construction Contractor Facility Equipment for EMP (Meters, Vehicles and Buildings) Asphalting Asphalt mixing plants should be sited over 1000 m from During PIU- TNRSP, Contractor MORTH any communities. Mixing equipment should be well Construction Contractor Specification sealed, and be equipped with a dust-removal device. 111, 111.5 Operators should wear dust masks, ear protection and hard hats. AIR Gaseous Emissions Vehicles and machinery are to be maintained so that Beginning PIU - TNRSP, Contractor MORTH emissions conform to National Ambient air quality with & SPCB, Specification standards. throughout Contractor 111.1, 111.5 Revision Level: R2 September, 2014 Page26 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause All vehicles and machineries should obtain Pollution construction Under Control Certificates Dust Generation ¾ Vehicles delivering materials should be covered to Beginning PIU – TNRSP, Contractor MORTH reduce spills and dust blowing off the load. with & Contractor Specification ¾ Clearing and grubbing to be done, just before the start throughout 111.1, of next activity on that site. In case of time gap, water construction 111.5, should be sprinkled regularly till the start of next until 111.8, activity. asphalting is 111.9, ¾ Water to be sprayed during the construction phase, at completed and 111.10 mixing sites, approach roads & temporary roads. side slopes are ¾ In laying sub-base, water spraying is needed to aid covered. compaction of the material. After the compaction, water spraying should be carried out at regular intervals to prevent dust generation. ¾ Road surface should be cleaned with air compressor and vacuum cleaners prior to the construction works. Manual labour using brooms should be avoided, if used labour to be provided masks. ¾ Embankment slopes to be covered with turfing/stone pitching immediately after completion Equipment Construction plant and equipment will meet recognized During PIU – TNRSP, Contractor MORTH Spec Selection international standards for emissions and will be construction EMU – 106, IRC: 72- maintenance and maintained and operated in a manner that ensures that TNRSP, 1978; IRC: 90- operation relevant air, noise, and discharge regulations are met Contractor 1985, 111.5, 111.9, 111.10, 201.3 LAND Soil Erosion and Main reason of soil erosion is rains/monsoon, contractor Upon PIU – TNRSP, Contractor MoRTH Revision Level: R2 September, 2014 Page27 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause Sedimentation completion of EMU should plan the activities so that NO bare/ loose earth – Specification control surface is left out before the onset of monsoon, for construction TNRSP, 306, 307, 308 minimizing the soil erosion following preventive activities at Contractor measures to be taken such as these sites. During ¾ Embankment slopes to be covered, soon after construction completion ¾ Next layer/activity to be planned, soon after completion of, clearing and grubbing, laying of embankment layer, sub grade layer, sub-base layer, scarification etc. ¾ Top soil from borrow area, Debris disposal sites; borrow area, construction site to be protected/covered for soil erosion. ¾ Debris due to excavation of foundation, dismantling of existing cross drainage structure will be removed from the water course immediately. ¾ Diversions for bridges will be removed from the water course before the onset of monsoon. Loss of agricultural All areas of cutting and all areas to be permanently During PIU – TNRSP Contractor MORTH topsoil covered will be stripped to a depth of 150mm and stored construction EMU – Specification in stockpile. TNRSP, 301.3.2, 305.3.3 Top soil will be safeguard from erosion and will be Contractor reused as follows. ¾ Covering all borrow areas after excavation is over. ¾ Dressing of slopes of road embankment ¾ Agricultural field, acquired temporarily. Compaction of Soil Construction vehicles should operate within the Corridor During PIU – TNRSP Contractor MORTH and Damage to of Impact avoiding damage to soil and vegetation. construction EMU – Specification Revision Level: R2 September, 2014 Page28 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause Vegetation Diversions, access road used will be redeveloped by TNRSP, 201.2 contractor, to the satisfaction of the owner/villagers. Contractor Contamination of Guidelines of “Hazardous waste (management and During PIU – TNRSP Contractor 7.4.5, Chapter 7, soil handling) rules, 1989 will be enforced. Construction EMU – EA Report ¾ Plant to be setup 500m away from surface water TNRSP, body. Contractor ¾ Oil interceptor will be installed at construction site. ¾ Septic tank will be constructed for safe disposal of waste. ¾ EH & S guidelines will be followed to avoid contamination of soil and safe disposal of hazardous material Borrow pits NO borrow pit will be opened without the permission of During PIU – TNRSP Contractor IRC: 10 1961 supervision consultant. Construction EMU – MoRTH Spec. ¾ Written approval from owner to be submitted to TNRSP, 111.2, 305.2.2, EMU. Contractor 301; 305.2.2.2; ¾ Borrow pits have been identified outside the ROW. 305.4, 1002 ¾ Identification of borrow areas outside the ROW. Annexure 3.4 : Before opening additional borrow pits operating pits guidelines for shall be closed as per the IRC Specification borrow area ¾ Identification of borrow areas with consent of the management Environmental Expert confirming to the quality standards. ¾ Borrow areas shall preferably be selected from high land and/or waste land, where farmers are willing to lower their area for cultivation purposes. ¾ Enforceable provisions in contractual arrangements for opening and use of material borrow pits. ¾ Consent to operate after signing of formal agreement Revision Level: R2 September, 2014 Page29 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause ¾ Additional borrow pits not to be opened without the restoration of those areas no longer in use. ¾ Measures taken for rehabilitation of the borrow areas Quarry operations ¾ Quarrying will be carried out at approved and During PIU – TNRSP Contractor MoRTH licensed quarries only. Copy of licenses to be Construction EMU – Specification submitted to the EMU. TNRSP, 111.3, 302, ¾ Extraction of materials from designated quarries Contractor 305.2.2, after consent of Department of Mining and District 117;118; Administration 1002 ¾ Development of Quarry Redevelopment Plan Annexure 3.3 Material sources EMP Report. As far as possible contractor will use the approved material sources. In case on new quarry the instruction of Annexure 3.3: Guidelines for Aggregate Quarry Management will be applicable. WATER Loss of water ¾ Mitigation measures for loss of water bodies During PIU – TNRSP Contractor MORTH bodies recommended Construction Irrigation Dept, Specification (Surface/Ground) ¾ NO excavation from the bund of the water bodies. Contractor 111.4, 201.2, ¾ NO debris disposal near, any water body. 301, 304, 306 ¾ Prior written permission from authorities for use of water for construction activity should be submitted 8.4.1, Chapter 8, Revision Level: R2 September, 2014 Page30 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause to EMU. EA Report. ¾ Construction labours should be restricted from polluting the source or misusing the source. ¾ Shifting of source to be completed prior to disruption of the actual source. ¾ Source (potable or otherwise) such as wells, ponds or tube – well, etc to be replaced immediately, in case of accidental loss. ¾ Alternate measures to be taken/ensured during disrupted period. ¾ The location and sifting of the replaced source of water shall be as per design or as directed by the Engineer. ¾ In general, there should be only lateral displacement Alteration of ¾ Diversions should be constructed during dry season, Whenever PIU – TNRSP, Contractor MORTH drainage with adequate drainage facility, and will be encountered Irrigation Specification completely removed before the onset of monsoon. during Dept., 201.2,301, 304, ¾ Debris generated due to the excavation of foundation construction. Contractor 306, 312 or due to the dismantling of existing structure should be removed from the water course. Chapter-2 EA ¾ Silt fencing has to be provided on the mouth of report, discharge into natural streams. Engineering ¾ Continuous drain (lined/unlined) is provided, Report, DPR obstruction if any, to be removed immediately. Runoff, drainage ¾ Throughout continuous drain is provided. During PIU – TNRSP, Contractor MoRTH and Flood control ¾ Lined drain is provided at builtup locations for quick Construction Contractor Specification on site drainage. 305.3.7; 309; Revision Level: R2 September, 2014 Page31 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause ¾ Provision of adequately sized drainage structures at 309.3.6; 311.1; regular intervals in flood-prone areas and at crossing 311.2; 312.1; points (e.g. intermittent streams). 312.2 ¾ Erosion Augmentation of existing drainage and cross drainage (CD) structures ¾ Measures to prevent blockage to natural drainage pattern due to stacking of construction materials. ¾ Adequate facilities of drainage at construction site and camp in order to avoid stagnant water pools that also lead to soil Construction water ¾ Contractor has to provide list of sources During PIU – TNRSP Contractor MORTH availability (surface/ground) for approval from EMU. Construction EMU –TNRSP, Specification ¾ Prior to use of source contractor should obtain the Contractor 601.2.4 written permission from authority, to use the water 1010 in construction activity, and submit a copy to EMU. ¾ During construction only permitted quantity (permission taken) from approved sources should be used in construction activity. ¾ Water bodies shall not be used for drawing or disposal of water during construction. ¾ Water should be clean and free from injurious substances. ¾ Make availability of adequate water supply and its source before construction. ¾ Consent from authority to dig new tube-well. ¾ Steps for minimization of water wastage during construction. Revision Level: R2 September, 2014 Page32 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause Silting/sedimentati ¾ Measures suggested under “Soil Erosion and Throughout PIU – TNRSP, Contractor MORTH on Sedimentation control” have to be enforced. construction Irrigation Specification ¾ Silt fencing should be provided around water bodies. period. Dept., Forest 111.4, 306 ¾ Construction activities should be stopped near water Dept., bodies during monsoon. Contractor Contamination of ¾ Measures suggested under “Contamination of soil” Throughout PIU – TNRSP, Contractor MORTH water have to be enforced. construction EMU – TNRSP Specification ¾ Construction work close to water bodies should be period. SPCB, 111.1, 111.4, avoided during monsoon. Irrigation Dept, 111.9, 111.13, ¾ Labour camps are to be located away from water Contractor 122, 201.2, bodies. 201.4, ¾ Car washing/workshops near water bodies are to be 301.1.3.10, avoided. 304.3.3, 306 NOISE Noise ¾ Noise standard at processing sites, e.g. aggregate Beginning PIU – TNRSP, Contractor MORTH crushing plants, batching plant, hot mix plant are to and SPCB, Contractor Specification be strictly monitored to prevent exceeding of GOI throughout 111, 111.5 noise standards. construction ¾ Inventory of all equipments / machinery to be used by the contractor along with their PUC certificates, 8.5.1, Chapter 8, specifications. EA Report. ¾ Workers in the vicinity of strong noise to wear protectors and their working time should be limited as a safety measure. ¾ In construction sites within 150 m of sensitive receptors construction to be stopped from 22:00 to 06:00. Revision Level: R2 September, 2014 Page33 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause ¾ Machinery and vehicles should be maintained to keep their noise to a minimum. ¾ Noise barrier in terms of wall & plantation is proposed at noise sensitive locations. FLORA & FAUNA Loss of trees and ¾ Avenue plantation has to be taken up soon after After PIU – TNRSP, Contractor MORTH Avenue Planting completion of civil works. completion of Forest Dept., Specification, ¾ Community structures has to be enhanced with construction Contractor 111, 111.5, plantation activities 201.5, 306, 308 ¾ Pressure on trees due to increase in fuel demand 8.5.1 & 8.6.3 from labour be minimized by providing alternate Chapter 8, EA source of fuel like kerosene and LPG at subsidised Report. cost. Vegetation ¾ Clearing and grubbing should be avoided beyond During PIU – TNRSP, Contractor MORTH clearance that which is directly required for construction cleaning Forest Dept., Specification activities. operations Contractor 201.2 ¾ Next activity to be planned/started immediately, to During avoid dust generation and soil erosion during construction monsoon. ¾ Turfing / re-vegetation to be started soon after completion of embankment. Fauna ¾ Construction workers must protect natural resources During PIU – TNRSP, Contractor MORTH & wild animals. construction Forest Dept, Specification ¾ Hunting will be prohibited. Contractor 111.1, 111.6 ¾ Nesting grounds & migratory paths will be protected. SOCIO-ECONOMIC ENVIRONMENT Revision Level: R2 September, 2014 Page34 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause General Issues During PIU – TNRSP, Contractor MORTH Fear of ¾ Public participation sessions were/will be Construction Specification uncertainties conducted in different stages of project 111, 111.5, regarding future construction. 111.6, 112, Public Health ¾ Debris, so generated will be disposed to the 201.2, 201.3 & and Safety satisfaction of Engineer. 201, 302, 306 ¾ Monitoring of air, water, noise and land during construction and operation phase. Labour Camps ¾ Approval of Environment Expert for setting up of camp facility. ¾ Contractors should recruit the local people as laborers at least for unskilled and semi-skilled jobs. ¾ Hygiene and basic facilities should be ensured at labour camp to prevent the spread of disease. ¾ Awareness programme on communicable diseases ¾ Provision of Public health facilities such as drinking water, sanitation and toilets. ¾ Proper sewerage disposal system for labour Annexure 3.2 camps. ¾ Provision of first aid facilities, Day Crèche Facilities ¾ Sitting of construction camps away from water bodies forests/protected areas/ settlements Revision Level: R2 September, 2014 Page35 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause Allied activities Detailed traffic control plans shall be prepared and submitted to the engineer for approval 5 days prior to commencement of work on any section of road. Accidents and The contractor should provide, erect and maintain Safety barricades, including signs marking flags lights and flagmen as required by the Engineer. Religious/ Cultural ¾ A comprehensive mitigation/enhancement plan is During PIU – TNRSP, Contractor 8.7.1.1 chapter- Community prepared for each of the existing community construction Contractor 8, EA report. Structures/Sensitiv properties along the project corridor 8.5.1 chapter-8, e Noise receptors ¾ Precautions should be taken during construction, for EA report. accidental loss/damage of any communal property. ¾ Any loss during construction will be the solo responsibility of contractor and the damage will be repaired immediately up to the satisfaction of people, at contractor’s own cost. ¾ Through access/identification should be maintained during construction. Road side ¾ Bus shelter will be proposed at all built-up locations, During PIU – TNRSP, Contractor Engineering amenities in case already existing; the same will be repaired construction Contractor Report, DPR and rehabilitated. ¾ Pedestrian crossing is provided at major pedestrian crossings, providing zebra crossing, sign posts and speed breakers. ROAD SAFETY Accident with COMPLIANCE with “Rules” as defined in During TNRSP, State Contractor, Appendix 8.13, hazardous Environmental (Protection) Act, 1986, including: Construction Police & Fire local bodies EMP Report Revision Level: R2 September, 2014 Page36 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause materials ¾ For delivery of hazardous substances, three Station, SPCB, certificates issued by transportation department are EMU, required permit license, driving license, and Contractor guarding license. ¾ Vehicles delivering hazardous substances will be printed with standard signs. ¾ Public security, transportation and fire fighting departments will designate a special route for these vehicles. ¾ These vehicles can only be parked at designated parking lots. ¾ In case of spill of hazardous materials, relevant departments will be informed at once & dealt with it in accordance with spill contingency plan. OPERATIONAL PHASE AIR Dust Generation ¾ Avenue plantation to be maintained, casualties to be After PIU-TNRSP, Contractor 8.2, Chapter 8, replaced. completion of SPCB EA Report ¾ Avenue plantation includes species having dust construction absorption characteristic. activity ¾ Dust generation due to vehicle wheel will be reduced due to increased/widened paved surface. ¾ Maintenance of roads to be ensured. Air Pollution ¾ Air pollution monitoring program has been devised After EMU, SPCB Contractor 8.2, Chapter 8, for checking pollution level and suggesting remedial completion of Forest Dept, EA Report. measures. construction State Transport ¾ With the reduction in journey time, idle engine activity Dept., Traffic running time air pollution will reduce. Police Revision Level: R2 September, 2014 Page37 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause ¾ Avenues plantation is proposed throughout the corridor, casualties to be replaced. ¾ Avenue plantation includes species having air purifying characteristic. ¾ Enforce Pollution Under Control (PUC) Programs. The public will be informed about the regulations on air pollution of vehicles. ¾ Transport vehicles and other equipment shall conform to emission standards fixed by Statutory Agencies of Government of India or the State Government from time to time LAND Temporary land ¾ Borrow area redevelopment plan to be completed/ After EMU, SPCB, Contractor Annexure 3.4, acquisition enforced. completion of EMP Report & ¾ All temporary acquired land for construction of construction Engineering diversion, transportation of material etc should be Report, DPR redeveloped to the satisfaction of owner. ¾ Affected productive area to be poured with top soil. Soil erosion ¾ Embankment slopes to be re-vegetated, casualties to After EMU, SPCB, Contractor Annexure 3.13 be replaced. completion of EMP Report ¾ Residual spoils to be disposed properly. construction &Engineering Report, DPR Soil Contamination ¾ Accidental spills are potentially disastrous, but its After EMU, SPCB, Contractor 8.3.5 Chapter 8, probability is quite low as one of the objectives of completion of State Police, EA Report this project is to enhance road safety. construction State Transport Annexure 8.1 ¾ The public should be informed about the regulations Dept. EMP Report on land pollution. ¾ Monitoring of Land pollution to be done regularly as Revision Level: R2 September, 2014 Page38 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause per frequency and location mentioned in Appendix 8.1 and suggesting remedial measures. WATER Silting/sedimentati¾ Measures suggested under “soil erosion” to be After EMU, SPCB Contractor Annexure 3.13 on enforced. completion of EMP Report, ¾ De-silting of existing water bodies to be taken up. construction Engineering ¾ Silt fencing to be provided. Report, DPR Contamination of ¾ Discouraging local people from establishing After EMU, SPCB, Contractor Annexure 3.6 water workshops and car wash near public drinking water completion of State Police, EMP Report source. construction State Transport ¾ The public to be informed about the regulations on Dept. water pollution. respective ¾ Monitoring of water pollution to be done regularly as Municipal per frequency and location mentioned in Appendix Agency 8.1 and suggesting remedial measures. Maintenance of The urban drainage systems should be maintained to Especially at EMU, Contractor Engineering Storm Water accommodate storm water flow. the start & end respective Report, DPR Drainage System Cleaning/removing of spoils should be ensured of rains Municipal before/during the monsoon rains. Agency NOISE Noise ¾ HORN PROHIBITED sign post will be enforced. After SPCB, Traffic Contractor Annexure 3.8 ¾ Maintenance of noise barriers. completion of Police, State EMP Report, ¾ Discouraging local people from establishing sensitive construction Transport Dept. Engineering receptor near the road. Report, DPR ¾ The public to be informed about the regulations on noise pollution. ¾ Monitoring of noise pollution to be done regularly as Revision Level: R2 September, 2014 Page39 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause per frequency and location mentioned in Appendix 8.1 and suggesting remedial measures. FLORA & FAUNA Loss of trees and ¾ The avenue plantation should be completed, After EMU-TNRSP, Contractor Annexure 3.54, Avenue Planting maintained and casualties to be replaced. completion of Forest dept. EMP Report ¾ Discouraging local peoples from cutting construction tree/branches for fuel, cattle food etc. ¾ Educating people about the usefulness of trees. SOCIO-ECONOMIC ENVIRONMENT General issues ¾ Public consultation to be organized after completion Operation TNRSP, EMU Contractor NIL of construction to access the people phase opinion/grievances from the project intervention. ¾ Remedial measures to mitigate the impact due to project intervention to be incorporated in the operation phase. Religious/Cultural ¾ The mitigation/enhancement measures to be During EMU Contractor Annexure 3.56, structures & Noise completed, and trees to be maintained and casualties Maintenance EMP Report Sensitive sensitive to be replaced. period of receptors Highway ROAD SAFETY Protection of high ¾ Stabilization of altered (especially high emb.) Immediately TNRSP Contractor Engineering road embankments embankments. after Report ¾ Although stone pitching is provided, vigilance to be construction maintained. Safety and noise ¾ New buildings are prohibited within 50 m of the edge Throughout Local Bodies Local Bodies, IRC 35-1971 disturbance of carriageway. and after Contractor IRC 79-1981 Revision Level: R2 September, 2014 Page40 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Environmental Responsible Reference/Contr Mitigation/Enhancement measures Time frame Organisation Impact & Issues Organisation actual Clause ¾ No new schools and hospitals are allowed within 200 project IRC 93-1995 m of carriageway. Wherever required appropriate development noise barrier should be constructed. period Accident black spot ¾ Road surface to be maintained, pot holes to be filled During TNRSP, Contractor Engineering immediately. Operational Local Bodies Report, DPR ¾ Regular maintenance of sign post, painting/removal stage. of bills. ¾ Road marking to be maintained. ¾ People to be educated about the safety in following traffic rules. ¾ Speed limit to be enforced at sensitive locations. ¾ Lighting of major junctions near settlements. ¾ Mitigative /preventive measures for accident black spots, like traffic calming devises. 1 1 PMC: Project Management/Supervision Consultant, PIU: Project Implementation Unit, EMU: Environmental Management Unit Revision Level: R2 September, 2014 Page41 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division CHAPTER 4: ARRANGEMENTS FOR IMPLEMENTATION OF EMAP The Environmental Management Action Plan (EMAP) (Refer Table 3.1), which is an integral part of the Environmental Management Plan, identify the detailed impacts, propose the mitigation actions and mention the implementing organization and monitoring organization. The responsibility for the implementation of EMP is assigned to a number of parties, each with specific responsibilities. They are listed as follows: • Project Management Unit (PMU), that represents GoTN and is directly responsible for implementing the project • Construction Supervising Consultant (CSC), who will be in charge of supervising the Contractor • Construction Contractor, who is in charge of undertaking road construction work and environmental management plan works. This chapter looks into the organisation and staffing of each of these stakeholders along with their responsibilities. 4.1. Organisation, Staffing and Responsibilities of PMU Project Management Unit (PMU) for the project under scrutiny is TNRSP, which is a part of the Highway Department(HD) in general, as the project proponents, are responsible for the implementation of all road improvement works and environmental management activities. The TNRSP is executing the project work under the guidance of Project Director (PD) as its head. The Project Director is assisted on all technical issues by one Chief Engineer (Projects), one Superintendent Engineer, one Environmental Specialist, one Sociologist and Assistant Executive Engineer and Assistant Engineers. The PMU is having five field divisions comprising of one Executive Engineer (R&R Officer), 2 Assistant Executive Engineers and 9 Assistant Engineers and other supporting staff which will play a key role in implementation of EMP and R&R. The team will oversee the project related management activities of the project including the overall control of construction activities and implementation of contracts. The implementation of mitigating measures requires supervision from adequately trained staff within the HD. The institutional organisation for EMP implementation is shown in Figure 4.1 and Figure 4.2 shows a very flexible and practical Environmental Management Unit (EMU). The detailed structure of TNRSP is separately captured in Figure 4.3. Responsibilities of Chief Engineer in HD : S/he is responsible for acquisition of all necessary right-of-way (ROW) land and buildings, review and approval of detailed road designs, obtaining all necessary clearances for construction and related activities, review and approval of the road re-alignments and road works (including retaining walls and excavation sites) and liasoning with supervision consultants. Responsibilities of Environmental Specialist: The Environmental Specialist (ES) of TNRSP Project Management Unit (PMU) assists the Chief Engineer in the overseeing of environmental aspects of the construction contracts, including the enforcement of all monitoring provisions, and advice on the locations of construction and labour camps, etc. He is also familiar with the Indian environmental legislation, environmental monitoring, EMP implementation aspects etc. Revision Level: R2 September, 2014 Page 42 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division The Environmental engineer shall oversee day to day implementation of the environmental management plans pertaining to the construction contract for various roads and is also responsible for monitoring reports to World Bank. Additional recruitment if needed will be undertaken as necessary on contract basis. FIGURE 4.1 INSTITUTIONAL ORGANISATION OF TNRSP FOR EMP IMPLEMENTATION PMU, TNRSP Environmental Specialist FIGURE 4.2 ENVIRONMENTAL MANAGEMENT UNIT (EMU) OF TNRSP Environmental Specialist Revision Level: R2 September, 2014 Page 43 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division FIGURE 4.3 ORGANISATION STRUCTURE, TNRSP Environmental Specialist The main duties of the Environmental Specialist will include: • Collection and dissemination of relevant environmental documents including amendments to environmental protection acts issued by the Government and agencies such as the World Bank, Asian Development Bank (ADB) and other organisations. • Co-ordination with community groups, government departments, etc. on environmental issues and obtaining the necessary clearances from the regulatory authorities. • Monitoring the environmental aspects of the project during construction to ensure that the environmental requirements of the contract and the mitigation measures proposed in the EMP are implemented. • Advising Engineer and preparing environmental input for monthly progress report. • Development of guidelines or a code of good practice on low-cost environmental measures that can be implemented in the road construction and maintenance programs for the Highway Department. • Assistance to local governments in the restoration of the environmentally degraded portions of any existing Right-of-Way, which may revert to their control due to the construction of realignments. • Promotion of the policies adopted for the development of roadside amenities • Assistance with the road safety components and issues related to the effects of roadside environment on road safety and non-motorised traffic. • Laison with the EO of CSC and report to Superintending Engineer on all matters related to implementation of the Environmental Management Plan. • Issuing completion certificate for constructed road works for payment. Revision Level: R2 September, 2014 Page 44 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 4.2. Organisation, Staffing and Responsibilities of Construction Supervising Consultant (CSC) The Supervising Consultant will supervise the activities of the construction Contractor on behalf of Tamil Nadu State Highway Department and will be reporting directly to the Superintending Engineer. The Supervising Consultant will be responsible for the technical supervision of road layout, overseeing contract implementation and certifying works for payment. The roles of Construction Supervision Consultant are described below: • Supervision of the Contractor to ensure that work is undertaken according to the construction contract. • Inspection and reporting of Contractor activities to ensure effective implementation of the EMP. • Auditing of Contractor works and activities against conditions put forward in the EMP. • Issuing corrective action, requests and conduct follow up inspections and evaluation. • Reporting any exceptions to the Project Director. • Certifying completed constructed road works for payment. The CSC shall have all the required specialists including an Environmental officer (EO) and a Senior Construction Safety Specialist. The brief description of qualifications, duties and responsibilities of the Team Leader, Senior Construction Safety Specialist and Environmental Officer of the Construction Supervision Consultants (CSC) are as follows: Qualifications, roles and responsibilities of Team Leader: He shall be at least a graduate in Civil Engineering, with at least at least 20 years of professional experience out of which he should have worked as Team Leader/Project Manager or equivalent for minimum 4 years on supervision/construction of highway projects, preferably involving flexible pavements. Post Graduate qualification in civil engineering is desirable. His roles and responsibilities shall be as follows: • He will be overall in-charge of the project supervision team. • He shall be responsible for the overall implementation activities. • He shall be assisted by key Professionals and other support Staff. • He shall co-ordinate with the sub-ordinate team to ensure that the construction process is well controlled as per established procedures. • He will interact with the client. Qualifications, roles and responsibilities of Senior Construction Safety Specialist (SCSS): The candidate shall be at least a Graduate in civil engineering and preferably with post graduate qualification in Industrial and Construction safety. OSHAS certification will be mandatory. S/he needs a minimum of 10 years of relevant professional experience, out of which, s/he should have worked for at least 5 years at a road / bridge construction site in the capacity of a safety engineer. Experience in working on height / deep foundations and live traffic situation and imparting safety training to construction managers and workers will be highly desirable. • The SCSS will report to the Team leader of the Construction Supervision Team. Revision Level: R2 September, 2014 Page 45 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division • S/he will be responsible for reviewing and approving the construction zone safety plans and traffic management including all temporary works/staging along with the structural or bridge engineer to confirm the safety point of view. • The Safety Specialist will be responsible to guide the field supervision team and contractors site officers and should confirm whether safety measurements implemented in the field are complying with safety standards. • The safety specialist must report any job accident or safety violation to the concerned officials through team leader. When an employee is injured on the job, the construction safety officer will investigate the accident and handle any workers' compensation claims. • The safety specialist shall teach proper safety and health procedures to the entire construction workers. Also, he should take initiatives to conduct training programmes and moke safety drills which will help to update safety procedures as well as the importance of reporting a safety concern or injury. Qualifications, roles and responsibilities of Environment Officer (EO) of CSC: The candidate shall be M.Sc. Environmental Science or graduate in Civil / Environmental Engineering. The candidate shall have professional experience of at least 5 years relevant to environmental management in infrastructure projects. Experience in implementation of EMP in externally aided/FIDIC based major highway projects is preferable. He should have adequate experience in implementing EMPs and organizing training to Contractor’s and Employer’s staff. He should be familiar with requisite procedures involved in obtaining and implementing environmental clearance requirements for project roads. • The Environmental Officer (EO) will report to the Team leader of the Construction Supervision Team. The EO shall not instruct or direct the Contractor or Contractor’s men but can discuss various issues and environmental mitigation measures with all concerned directly or indirectly. • All matters related to environmental and social activities within the ROW such as latest EIA, SIA, RAP and other related documents should be available to the EO immediately after mobilisation. The Forest, environmental clearance, Tamil Nadu Pollution Control Board’s clearance conditions and other approval status should be specified. A status report prepared by PCC/ESMC of PMU would be required for the EO to start the work. • The Environmental Officer (EO) should be mobilised during the early stages of construction. This is to help the Contractor in identifying environmentally sound locations for Construction camps, hot mix plant, WMM plant and all other issues according to the Environmental Management Action Plan (EMAP). • The important role of EO during construction is to ensure the smooth implementation of EMAP and to address direct and indirect social issues arising out of implementation of the RAP. • The EO should visit incomplete construction work sites where there are no contractor’s current activities, active construction work sites and completed areas of the work sites and conduct regular meetings with the contractor in identifying gaps pertaining to both environment and construction safety. The EO will also visit the hot mix plant; quarries and crushers, borrow areas and others as per the necessity. EO has to ensure appropriate corrective and preventive action to the identified gaps in construction site in environmental aspects. Conduct regular meeting on environmental aspects with Environmental and Social Management Unit in HD. Revision Level: R2 September, 2014 Page 46 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division • The EO will assist the Engineer to ensure environmentally sound engineering practices. In addition, other specialists of the engineers’ team may also act and report on road safety related issues. • The EO will carry out consultation with the Contractor, contractor’s men, local Project Affected People (PAPs) and interest groups. The EO will also consult with NGOs to consider any problems (e.g. access problem to school, buildings, houses and business establishments) arising from construction activities. • The EO will assist in the compliance with various labour laws including the payment of minimum wages to the individual contract labourer’s especially ‘unskilled illiterate migrant labourers’. This has a direct bearing on the health and safety of the workers. • The EO will assist the Contractor, and the Highway Department in all matters related to public contacts including consultation, training and public relations. • The EO will prepare standard formats (if available they may be obtained from other projects that are being implemented or are completed recently) for the compliance of the environmental and social requirements. • The EO will ensure the procurement of materials that are included in the Bill of Quantities relating to environmental and social mitigation costs. • The EO will assist the HD and the Contractor in all training activities during construction supervision period. • The EO will prepare and submit regular reports to the team leader of CSC. • The EO will assist the various Environmental monitoring activities of the Contractor / HD. • The EO will be responsible to confirm whether the contractor has received all certifications in different sectors from the concerned authority to precede the work. • The EO in co-operation with the EO of PMU and Superintending Engineer will make sure the issuing of timely Work order for the Nurseries to be raised according to the ‘Landscaping, Tree planting and Environmental Enhancement Plan’. This will allow one year for the plants to attain the required size. 4.3. Organisation, Staffing and Responsibilities of Construction Contractor The construction Contractor shall be responsible for undertaking all duties and works assigned in the road construction contract, including all specified conditions in the EMAP. The construction Contractor should prepare an implementation plan of mitigating actions specified in the EMP Activity Table. The Contractor will work closely with the Supervising Consultant to ensure that works are constructed to standard. Throughout this EMP, the construction Contractor is referred to as the ‘Contractor’ and the supervising Consultant is referred to as the ‘Construction Supervising Consultant’ (CSC). Detailed staffing pattern in the contractor’s office is given below in Table 4.1. TABLE 4.1 STAFFING PATTERN IN CONTRACTOR’S OFFICE S .No. Designation Nos. 1 Contract Manager 1 2 Construction Planning Engineer 1 3 Site Engineer 4 4 Quality Control/Material Engineer 1 5 Bridge Engineer 1 6 Earth Works Supervisor 6 Revision Level: R2 September, 2014 Page 47 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S .No. Designation Nos. 7 Pavement Supervisor 2 8 Environmental Engineer 1 Roles and responsibilities of team leader of Contractor: The Team Leader of the Contractor shall be responsible for the timely implementation of EMP, as per the conditions stipulated in the Environmental Management Action Plan. S/he shall prepare an implementation plan of mitigating actions specified in the EMP Activity Table. H/she shall guide / supervise the ESE in ensuring that all construction work is undertaken in line with the requirements of EMP. The team leader shall ensure that the reporting procedures mentioned in EMAP and detailed out in Chapter 5 of this report is adhered to and required reports and management plans are submitted to CSC on time. The corrective actions, as suggested by CSC shall also be implemented and reported. S/he shall have good understanding of the contractual clauses,especially the penalty clause given in the bid document as well as Chapter-3 of this report. He also has to ensure that the responsibilities stipulated in EMAP for Defect Liability period are carried out. Qualifications, roles and responsibilities of Environment and Safety Officer (ESO) of Contractor: The candidate shall be M.Sc. in Environmental Science or B.Tech. in Civil/ Environmental Engineering with two years field experience in environmental management of transportation projects. The duties and responsibilities of the Environment and Safety Engineer in the contractor’s team are as follows: • To ensure that all the contractor activities are done in line with the EMP requirements. • To have good understanding of the contractual clauses, especially the penalty clause given in the bid document as well as Chapter-3 of this report. • To verify the appropriateness of all the EMP items. • To prepare a management and redevelopment plan for all the sites of identified project related ancillary facilities like (i) Construction camp, (ii) labour camp, (iii) quarry and stone crusher unit, (iv) borrow area and (v) debris disposal site in line with detailed guidelines given in EMP. • To ensure that all the five sites and camps mentioned activity is operated, managed and closed in line with management and redevelopment plan. • To ensure that the top soil preservation is done wherever required as per the guidelines. • To ensure the adoption of proper waste management practices in the plant sites, labour camps, construction camps and along the road (also pertains to the proper disposal of bituminous / concrete waste generated during construction). • To ensure that the Contractor does not violate any social norms such as employment of child labour, children at work sites, providing crèches, unhygienic working conditions and minimum wage considerations as per prevailing laws. • To ensure that all the MORTH specifications are available and followed in all the contractor activities. • To liaison with the Supervision Consultant and the PMU / HD on matters pertaining to the EMP. • To liaison with Government Agencies such as the Pollution Control Boards and Forest Department in order to obtain the required clearances, and to ensure that the Contractor activities are carried out in line with any conditions placed. Revision Level: R2 September, 2014 Page 48 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division • To ensure adoption of good construction-related safety practices and appropriate traffic management practices to ensure road safety during the construction phase. • To prepare and implement a plan for road safety, accidents and traffic management. • To demark the starting chainage & end chainage of the project as the construction zone, and provide sign boards as per accepted standards. • To inform and train all the contractor personnel on the IRC requirements on construction safety and on road safety. • To prepare and ensure implementation of an emergency response plan • To ensure the availability of first aid facilities. Reporting requirements of Contractor: The Contractor shall undertake regular reporting to CSC, comprising submission of reports as well as management and redevelopment plans to CSC as detailed in the Chapter -5 of this EMP. 4.4. Information Dissemination Information dissemination shall be undertaken by PMU at a macro level and by the Contractor in the project site at micro level. The wider dissemination of information to public shall be undertaken by PMU through the disclosure of EIA / EMP reports in the website of PMU. At the project site, i.e. the direct impact zone, information boards shall be displayed at critical and pre- identified locations to disseminate the project details. Such information boards shall display project name, contractor’s name, concerned official’s name in Contractor’s office with his designation and contact no., name and contact details of an authorised official in local HD divisional office. These information boards shall be approximately of size 5’ x 5’ and shall be designed and put up in such a way that public can easily read it from a distance. Such boards shall be set up, not only along active project stretches, but also at the sites of construction camps and labour camps and other project facilities like borrow area, quarry and stone crusher site and debris disposal site. These information boards shall also mention the availability of a complaint register with ESE of the Contractor. Under the RTI Act, 2005, Contractor is also duty bound to share any information demanded by the public, pertaining to any aspect of the project, as and when it is demanded. 4.5. Grievance Redressal Mechanism Superintending Engineer of TNRSP will Grievance Reddressal Mechanism (GRM) Officer supported by Environment specialist and other team members. All grievances registered will be complied within 15 days and will be displayed. There will be facilities to lodge the complaints by email, phone call and letter. The email address, phone number and correspondence address will be available on TNRSP website. 4.6. Training Programme on Environmental Aspects Training is an investment made on the human resource of the organization to provide and tone the competencies, required to do an existing job well and also to perform for future needs. Targeted and monitored training can set up an environment of good morale and productivity and contributes in creating a powerhouse of competencies for the organisation. This section deals with the training to be imparted to the Contractor’s staff by the EO and SCSS of CSC for Revision Level: R2 September, 2014 Page 49 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ensuring effective implementation of EMP. The training requirement could be broadly identified as given in Table 4.2 below. TABLE 4.2 TRAINING PROGRAMME TO THE CONTRACTOR’S STAFF Programme Particulars Duration Participants Awareness Skilled and unskilled labour General Awareness on programme for One day Environment and Safety Labourers Awareness programme for General Awareness on Engineers, supervisors and office One day Engineers and Environment and Safety staff Supervisors Contactor’s Responsibilities as per bid document and One day Orientation EMP Engineers including ESE Programme Reporting System as per One day EMP The need for additional and specialised training shall be examined and appropriate training will be undertaken as required. Revision Level: R2 September, 2014 Page 50 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division CHAPTER 5: ENVIRONMENTAL MONITORING AND REPORTING REQUIREMENTS 5.1. Monitoring and Reporting of Environmental Management Measures A robust monitoring and reporting system is mandatory to ensure compliance to EMAP by the contractor. The monitoring and reporting system evolved for TNRSP is integrated into EMAP table and its annexure. It comprises following three parts: (A) Monitoring and reporting of environmental management measures for project related facilities like construction camp, labour camp, quarry area, borrow area and debris disposal site, (B) Monitoring and reporting of environmental management measures for overall project, and (C) Monitoring and reporting of quality of environmental parameters like air, water and noise. This monitoring and reporting system attempts to pre-empt much of the environmental issues created during construction and post construction stages and provides the necessary feedback for CSC / PMU to make sure that EMAP is implemented in full spirit. Instead of a linear reporting system, this system works on a two way basis – initial reporting by contractor followed by monitoring by CSC based on contractor’s reports. Responsibilities for monitoring will rest with the Environmental Officer of the Supervising Consultant reporting to the PMU and EMU at TNRSP. The detailed procedure of reporting and monitoring system is as follows: (A) Monitoring and Reporting of Environmental Management Measures for Project Related Facilities Sage I – Site Identification: While initiating the project, the Contractor needs to identify suitable sites for project related ancillary facilities like construction camp, labour camp, quarry and stone crusher units, borrow area and debris disposal sites. The same shall be undertaken adhering to the criteria given in the respective guidelines for each of these sites given in Annexure 3.1 to 3.5. Once the site is identified by the Contractor, s/he shall prepare a site identification report furnishing all the details pertaining to the identified site using the reporting format given in Annexure 3.17 to 3.21 and submit it to the CSC. Subsequently, the EO of CSC has to visit each site and approve / reject the site with reasons. The EO of CSC has to give a copy of this format to the contractor after his approval / rejection with remarks. This reporting procedure needs to be undertaken for each and every parcel of land identified for any of the project related ancillary facility. Stage II – Setting up of Sites: On approval of a site, the Contractor has to prepare the Management and Redevelopment Plan for this site as per the relevant Guidelines given in Annexure 3.1 to 3.5 of EMP and submit to CSC for approval. In addition to the Management and Redevelopment Plans for sites, the Contractor has to prepare Comprehensive Waste Management Plan, Occupational Health and Safety Management Plan, Traffic Management Plan and Hazardous Substances Management Plan for all sites together, as per the Guidelines given in EMP Annexure 3.6, 3.9, 3.10 and 3.11 respectively. Subsequently, the EO of CSC needs to visit Revision Level: R2 September, 2014 Page 51 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division each site and approve the Management Plan. The EO of CSC has to give a copy of this management plan to the contractor after his approval with remarks / suggestions for additional mitigation measures. Any kind of activity could be initiated in a site only after getting approval from CSC for the Management and Redevelopment Plan for that site. These plans need to be prepared for each and every parcel of land identified as described above. Stage III –Operation of Sites: Once the Contractor receives approval for the Management and Redevelopment Plan, s/he can initiate activities on the site. All the activities shall be undertaken strictly in line with the said plan. CSC shall monitor the implementation of management plan monthly once through site visits and the Checklists for Monitoring the Environmental Management of Sites / Camps given in Annexure 3.25 to 3.34. Corrective actions with specific timeframe should be proposed for each environmental management measure, which is not implemented satisfactorily. A copy of the filled up checklist should be given to the ESE of the Contractor. CSC has to attach this format to the Monthly Report to be submitted to PMU, with details of corrective action taken by the Contractor. A Register of Sites Opened and Closed in the format given in Annexure 3.24 should be maintained by the contractor (preferably in A3 size paper) for each road. Details of each site opened should be entered in this register in chronological order. Whenever a site is closed, it should be recorded in this register with status of redevelopment. Clearances applicable for each site and the status of clearances should also be entered in this register. This same format shall be used to report the details of sites opened and closed to the CSC along with the Monthly Report of the Contractor. EO of CSC has to visit the sites, verify the details and approve the report with instruction to the contractor if any clearance is pending for any site or redevelopment is not done satisfactorily for any closed site. .A copy of the approved report with CSC’s remarks should be given to the ESE of the Contractor. The EO of CSC has to attach this format to the Monthly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Stage IV – Closure of Sites: Upon completion of the operation in any particular project ancillary facility site, the Contractor shall undertake redevelopment of the same, in line with the redevelopment plan which was already approved by CSC and intimate to CSC through the format for Register of Sites Opened and Closed. The Environmental Officer of the CSC shall monitor the same through site visit and the Checklists for Monitoring the Redevelopment of Sites / Camps provided in Annexures 3.17 to 3.24 and Annexures 3.25 to 3.34 as and when a site is closed and reported by the Contractor. Corrective actions with specific timeframe should be proposed for each environmental management measure, which is not implemented satisfactorily. A copy of the filled up checklist should be given to the ESE of the Contractor. CSC has to attach this format to the Monthly Report to be submitted to PMU, with details of corrective action taken by the Contractor. As described above, the reporting tasks for project facilities have been split and shared among contractor and CSC and its summary is given below: 31. • One time reporting by contractor to CSC at the stage of identification of sites and camps • One time reporting by contractor to CSC through management and redevelopment plans before setting up of sites and camps. • Monthly reporting of sites opened and closed by contractor to CSC • Monthly monitoring by CSC during the operation stage of sites and camps Revision Level: R2 September, 2014 Page 52 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division • One time monitoring by CSC after the closure of each site and camp (B) Monitoring and Reporting of Environmental Management Measures for Overall Project The Contractor shall undertake regular monthly reporting to CSC using the format given in Annexure 3.46, and all other reporting formats shall be attached to this monthly report as annexure. The Monthly Report captures the physical progress of the work, main issues / concerns, corrective actions taken, no. of workers in the reporting month etc. Further, CSC shall report monthly to PMU, summarising the issues / concerns and actions taken. This report has to be prepared in the format given in Annexure 3.47 and all other reports are to be attached to it as annexure. All the reporting formats given in Annexure 3.35 to 3.45 shall be used by the Contractor to report environmental management measures related to various aspects of the overall project. These reports are to be submitted monthly by the Contractor to the CSC. The EO of CSC shall visit the sites and verify the implementation of management measures and approve the reports. EO of CSC should give a copy of the approved reports to the ESE of the Contractor with his remarks. (C) Monitoring and Reporting of Environmental Quality Environmental quality monitoring shall be undertaken by the Contractor through an NABL approved Laboratory, based on the Environmental Quality Monitoring Plan. The monitoring results shall be reported by the Contractor to the CSC in the Reporting Format for Environmental Quality Monitoring given in Annexure 3.41 along with the Monthly Report, if monitoring was due in that month. A copy of the monitoring report given by the Laboratory has to be attached to this format. The CSC has to visit the sites and verify the details. Additional mitigation measures, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. 5.2. Environmental Quality Monitoring Plan for the Project For each of the environmental components, the monitoring plan specifies the technical aspects of monitoring like locations of monitoring, frequency of monitoring and duration, sampling method, parameters to be monitored and standards to be compared. The monitoring plan also specifies the applicable standards and implementation and supervising responsibilities. Guidelines for monitoring program are given in Annexure 8.1.The Annexure 8.1 is given with environmental standards for air, noise and water to be monitored during construction and operation of the project at Table 1.2A, 1.2B and 1.2C respectively. Revision Level: R2 September, 2014 Page 53 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division CHAPTER 6: ENVIRONMENTAL BUDGET 6.1. Mitigation/Enhancement Measures Mitigation measures proposed in the EMAP will be implemented by the Contractor. The works to be undertaken by the Contractor have been quantified and the quantities included in the respective BOQ items such as earth works, slope protection, noise barriers, road safety features, and shrub plantation. Provisional quantities have also been included for additional measures that may be identified during construction and for silt fencing which will depend on the Contractors work methods and site locations. Items and quantities have also been included for enhancement measures. The general environmental management measures to be followed by the contractor have been included in the specifications and this EMAP. These cannot be quantified and are to be included in the contract rates. A summary of the Mitigation/Enhancement Measures which have been proposed in Annexure 3.51, 3.52 and 3.56 of this report is presented in Table 6.1. TABLE 6.1: SUMMARY OF MITIGATION/ENHANCEMENT MEASURES S Direct Indirect Typical Asset Typical Measures N Impact Impact Measures Boundary Wall, Bench, 1 Temple/Church/Mosque 15 32 Nil Plantation, Realignment Retaining wall, 2 Pond 3 Desilting, Tree, 8 Nil Plantation, Realignment 3 Well 0 Nil (Compensation) 4 Nil 4 River 0 Nil 0 Nil Boundary Boundary Wall, 5 Hospital 0 1 Wall, Plantation Plantation Boundary Boundary Wall, 6 Educational Istitute 2 9 Wall, Plantation Plantation 7 Bus Stop 19 Nil 9 Nil 8 Overhead Tank 2 Nil 14 Nil 9 Grave yard/Crematoria 0 Realignment 3 Nil 10 Railway line 0 Nil 0 Nil Anganwadi/Woman training 11 0 Nil 0 Nil centre Total 41 80 6.2. Cost Estimates The cost estimates are done for the surface water bodies, ground water bodies, sensitive receptors, trees and religious/cultural and community structures which are described briefly as Revision Level: R2 September, 2014 Page 54 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division follows. The cost estimate for the implementation of the environmental management plan of the project is presented in Table 6.2. 6.2.1 Surface Water Bodies Surface water bodies are community-based and therefore enhancement measures are proposed. Mitigation/enhancement measures of surface water bodies which are directly affected are given. 6.2.2 Ground Water Bodies: Ground Water Bodies are privately-owned irrigation wells. Loss of such sources will be compensated in financial terms and no enhancement measures are proposed. Assets which experience no direct impact will not be provided any compensation. 6.2.3 Sensitive Receptors: All sensitive receptors i.e. schools, hospitals and religious/cultural features, whether or not subject to direct impact, the following measures are proposed. ¾ To construct boundary wall and plant trees where boundary wall is demolished. ¾ To repair wall where needed and plant trees ¾ Where feature is not directly impacted, plant trees and build wall along road to act as noise barrier, hence no separate noise barrier is provided. 6.2.4 Forest Provision for expenditure on diversion of forest land has been made under the following heads; ¾ Cost of forest land diverted to widening of road ¾ Afforestation on non forest land transferred to forest department by revenue department in lieu of forest land diverted 6.2.5 Compensatory Afforestation ¾ Avenue Plantation: Trees shall also be planted along the project corridors. Their number is included in compensatory afforestation. Costing has been done as perforest schedule of rate,including the plantation and maintenance cost for 3 years. ¾ Plantation at Enhancement sites: A number of tourist places are located along the project corridor. To enhance the aesthetic beauty of these locations, indigenous species of trees are proposed and their cost has been estimated. Their number is in addition to compensatory afforestation ¾ Landscaping at Junctions and medians etc: Cost if any will be included as part of engineering measures since geometric design has a direct bearing such plantation. 6.2.6 Religious/cultural and other Community assets Cost of mitigation/enhancement measures at religious/cultural and other community assets within the Corridor has been included. Revision Level: R2 September, 2014 Page 55 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 6.2.7 Bus Stops Bus stops with shelters are proposed in lieu of those which will be removed due to the Project and in additional locations in order to improve safety and increase road capacity. At locations where existing RoW is more than proposed RoW, recessed bus bays will be provided. Cost an account of bus shelters/bus bays forms part of engineering cost estimates and is therefore not included in environmental management cost. TABLE 6.2: COST ESTIMATES FOR ENVIRONMENTAL MANAGEMENT S NO Item Unit Rate Qty Cost Remarks A PRE-CONSTRUCTION PHASE 1 Tree felling permission No 1292 2a Forest clearance Covered under regulatory clearances 2b Forest land diversion cost To be done under transfer arrangement from Revenue Dept. 2c cost of forest land diverted to non Ha 0.544 Class 3 Open forest purpose Forest, MoEF, 2013 & FSI 2d Afforestation on non forest land No. 680 transferred to forest department by revenue department in lieu of forest land transferred by forest department 3 Tree cutting No. 1292 4 Utility shifting Covered under Engineering cost Total Cost B CONSTRUCTION PHASE 1 Mitigation Measures 1.1 Oil Interceptor No 1 1.2 Silt Fencing mtr 461 1.3 Recharge pit for urban drains No 0 1.4 Soak pit for Hand pumps/wells No 0 1.5 Relocation of ground water source No 0 CMRL Rate for open wells 2014, directly impacted irrigation well 1.6 Relocation of hand pumps No 5 CMRL Rate 2014, directly impacted hand pumps 1.7 Desilting/deepening of ponds No Item 49,76 TNPWD, Rs.30.75 for 10m lead+Rs.5.25/ever y additional lead Included in Item-6 of 10m=Rs.41.25/cu m. Escalated at 5%=Rs.43.31/cu m. Used LS rate Revision Level: R2 September, 2014 Page 56 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S NO Item Unit Rate Qty Cost Remarks Rs 1.5 lakh per pond 1.8 Retaining wall for ponds Rm Included in Item-6 2 Tree Plantation & protection 2.1 Avenue plantation & compensatory plantation 2.1.1 Compensatory plantation & 12920 a maintenance of sampling for 3 years 2.1.1 Avenue plantation & maintenance for No 5362 included at 1tree/10m b 3 years in item 2.1.1a 2.1.2 Tree Guards Brush wood fence No 5362 included in item 2.1.1a 2.2 Plantation in realignment location Included in item 2.1 3 Landscaping Sqm 0 4 Monitoring of Environmental attributes 4.1 Air quality 4.1.1 Hot mix plant 9    Awarded rates 2014, 4.1.2 Critical location 27    Air and Noise, 4.2 Noise levels        Monitoring : 4.2.1 Equipment yards 9    Hot Mix Plant, 4.2.2 Critical locations 27    one location per 4.3 Water quality         road, 4.3.1 Monitoring of water quality 24    Frequency : 24 4.4 Soil quality hourly        monitoring once 4.4.1 Monitoring of soil quality 24    in a season for 4.4.2 Additional soil monitoring 0    three season in a year for three years Water and Soil Monitoring Frequency : once in a season for three seasons in a year for three years 5 Orientation of IA staff Deemed to be included in consultancy fee 6 Mitigation/enhancement measures Revision Level: R2 September, 2014 Page 57 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S NO Item Unit Rate Qty Cost Remarks 6.1 Religious/cultural assets Temple, Km 26.400, RHS 1 Annexure 3.55 Temple, Km 26.200, LHS 1 Annexure 3.55 Temple, Km 26.140, RHS 1 Annexure 3.55 Temple,Km 25.900, LHS 1 Annexure 3.55 Temple, Km 24.400, RHS 1 Annexure 3.55 Temple, Km 23.858, RHS 1 Annexure 3.55 Temple, km 22.675, RHS 1 Annexure 3.55 Temple, km 17.600, RHS 1 Annexure 3.55 Temple, Km 13.300, RHS 1 Annexure 3.55 Temple, Km 10.800, RHS 1 Annexure 3.55 Temple, Km 6.147, RHS 1 Annexure 3.55 Temple, Km 3.300, RHS 1 Annexure 3.55 Temple, Km 2.700, RHS 1 Annexure 3.55 Temple Km 0.125, LHS 1 Annexure 3.55 6.2 Noise sensitive receptors Hospital, Km 25.675, LHS 1 Annexure 3.55 School, Km 26.650, LHS 1 Annexure 3.55 School, Km 22.350, RHS 1 Annexure 3.55 School, Km 19.200, RHS 1 Annexure 3.55 School, Km 15.000, RHS 1 Annexure 3.55 School, Km 14.900, RHS 1 Annexure 3.55 School, Km 14.200, LHS 1 Annexure 3.55 School, Km 11.675, RHS 1 Annexure 3.55 School, Km 8.045, RHS 1 Annexure 3.55 School, Km 7.300, LHS 1 Annexure 3.55 School, Km 3.390, LHS 1 Annexure 3.55 School, Km 0.050, LHS 1 Annexure 3.55 6.3 Surface Water Bodies Pond, Km 25.925, LHS 1 Annexure 3.55 Pond, Km 2.700, LHS 1 Annexure 3.55 Pond, Km 0.200, LHS 1 Annexure 3.55 6.4 other community utilities graveyards/crematoria Nil 6.5 Incidental spaces Nil Total cost of environmental measure during construction phase C GOOD ENGINEERING PRACTICES 1 Dust suppression Covered under Engineering Costs Revision Level: R2 September, 2014 Page 58 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S NO Item Unit Rate Qty Cost Remarks 2 Erosion control measures (turfing/pitching/seeding and mulching) 3 Provision of cross drainage and side drainage structures 4 General borrow area management and maintenance of haul road related to borrow areas 5 Air/ Noise pollution control measures in construction equipment 6 Management and disposal of scarified waste bituminous material 7 Provision of informatory signs 8 Bus shelters 9 Construction of Speed Humps 10 Cattle Crossings 11 Management of quarries Deemed to be included in contractor’s quoted rates 12 Redevelopment of Borrow Areas 13 Construction Camp Management Costs Will form a part of the Contractor's cost 14 Safety measures for workers D ITEMS COVERED UNDER THE RAP BUDGET 1 Relocation of private Properties 2 Relocation of private Water points (wells, tanks, water taps and hand pumps) Covered under RAP Budget 3 Relocation of graveyards, statues, motor sheds 4 Relocation of Other Community Assets (private) E OPERATION PHASE 1 Monitoring of Environmental Attributes during Operation Phase 1.1 Monitoring of Air Quality at 3 Critical Per  18 Three season in a Locations Sample  year for 2 years 1.2 Monitoring of Noise Levels at 3 Per  18 Three season in a Critical Locations Sample  year for 2 years 1.3 Monitoring of Water Quality at two Per  12 Three seasons in locations Sample  a year for 2 years 1.4 Monitoring of Soil Quality at two Per  12 Three season in a locations Sample  year for 2 years 1.5 Additional Soil Monitoring during Per 0 Throughout Spills Sample operation phase. say 20 yrs 1.6 Noise mitigation measures in form of noise barrier at sensitive receptors Included in item 6 2 Information Dissemination Covered under RAP Revision Level: R2 September, 2014 Page 59 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S NO Item Unit Rate Qty Cost Remarks 3 Additional Training for Land use Package 1   Management at Package Level Environmental Budget During   Operation Phase Sub Total (A+B+E) INR   GRAND TOTAL US$ @ INR US$   60.00/$ * The number of trees required for compensatory afforestation will be planted as avenue plantation. Revision Level: R2 September, 2014 Page 60 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.1: GUIDELINE FOR SITING, MANAGEMENT & REDEVELOPEMENT OF CONSTRUCTION CAMP (A) SITING The contractor based on the following guidelines shall identify the location of the construction site. The construction site shall be located: • The construction camps will be located at least 1000m away from major settlements in downwind direction. The living accommodation and ancillary facilities for labour shall be erected and maintained to standards and scales approved by the resident engineer. • A minimum 500m away from surface water course or body. • A minimum 1000m away from Wild life Sanctuary/Ecologically sensitive areas. • Should not be located in cultivable land unless unavoidable. • All sites used for camps must be adequately drained. • The camps must be located such that the drainage from and through the camps will not endanger any domestic or public water supply. • All sites must be graded, ditched and rendered free from depressions such that water may get stagnant and become a nuisance. (B) LAYOUT A conceptual layout of a typical construction site has been presented in Figure below. The Contractor during the progress of work will provide, erect and maintain necessary (temporary) living accommodation and ancillary facilities for labour to standards and scales approved by the engineer. All temporary accommodation must be constructed and maintained in such a fashion that uncontaminated water is available for drinking, cooking and washing. Safe drinking water should be provided to the dwellers of the construction camps. Adequate washing and bathing places shall be provided, and kept in clean and drained condition. Construction camps are to be sited away from vulnerable people and adequate health care is to be provided for the work force. Sanitation Facilities: Construction camps shall be provided sanitary latrines and urinals. Sewerage drains should be provided for the flow of used water outside the camp. Drains and ditches should be treated with bleaching powder on a regular basis. The sewage system for the camp must be properly designed, built and operated so that no health hazard occurs and no pollution to the air, ground or adjacent watercourses takes place. Compliance with the relevant legislation must be strictly adhered to. Garbage bins must be provided in the camp and regularly emptied and the garbage disposed off in a hygienic manner Shelter at Workplace: At every workplace, there shall be provided free of cost, four suitable shelters, two for meals and two others for rest, separately for use of men and women labourers. The height of shelter shall not be less than 3m from floor level to lowest part of the roof. Sheds shall be kept clean and the space provided shall be on the basis of at least 0.5m2 per head. Revision Level: R2 September, 2014 Page 61 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Canteen Facilities: A cooked food canteen on a moderate scale shall be provided for the benefit of workers wherever it is considered necessary. The contractor shall conform generally to sanitary requirements of local medical, health and municipal authorities and at all times adopt such precautions as may be necessary to prevent soil pollution of the site. First aid facilities: At every workplace, a readily available first-aid unit including an adequate supply of sterilized dressing materials and appliances will be provided. Workplaces remote and far away from regular hospitals will have indoor health units with two bed facility. Suitable transport will be provided to facilitate taking injured and ill persons to the nearest hospital. At construction camp an ambulance room containing the prescribed equipment and nursing staff will be provided. Health Care Facilities: Health problems of the workers should be taken care of by providing basic health care facilities through health centres temporarily set up for the construction camp. The health centre should have at least a doctor, nurses, duty staff, medicines and minimum medical facilities to tackle first-aid requirements or minor accidental cases, linkage with nearest higher order hospital to refer patients of major illnesses or critical cases. The health centre should have MCW (Mother and Child Welfare) units for treating mothers and children in the camp. Apart from this, the health centre should provide with regular vaccinations required for children. Day Crèche Facilities: At every construction site, provision of a day crèche shall be worked out so as to enable women to leave behind their children. At construction sites where 20 or more women are ordinarily employed, there shall be provided at least a hut for use of children under the age of 6 years belonging to such women. Huts shall not be constructed to a standard lower than that of thatched roof, mud walls and floor with wooden planks spread over mud floor and covered with matting. Huts shall be provided with suitable and sufficient openings for light and ventilation. There shall be adequate provision of sweepers to keep the places clean. There shall be two maidservants (or aayas) in the satisfaction of local medical, health, municipal or cantonment authorities. Where the number of women workers is more than 25 but less than 50, the contractor shall provide with at least one hut and one maidservant to look after the children of women workers. Size of crèches shall vary according to the number of women workers employed. Revision Level: R2 September, 2014 Page 62 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Typical Layout of Construction Camp Revision Level: R2 September, 2014 Page 63 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.2 GUIDELINES FOR SITING, MANAGEMENT AND REDEVELOPMENT OF LABOUR CAMPS A. OVERVIEW Staff-quarters include accommodation for Engineers / Supervisors and labour camp include accommodation for workers / labourers along with other basic amenities such as kitchen, potable water supply, sanitation (toilets, bathrooms, washing areas and water supply for such needs), first aid room as well as garbage collection and disposal facility. Staff quarters shall be provided with additional facilities of drawing room. The guidelines outlined here aims to facilitate the Contractor in implementing the measures in the EMP there by reducing the impact on the environment. A guidance note prepared by IFC and EBRD for the processes and standards of Workers Accommodation may be consulted for labour camp. B. CRITERIA FOR LOCATING THE SITE/S Following criteria should be followed in the siting of labour camps: 2 ˜ To the extent possible, agricultural lands and fertile lands shall be avoided . C. FINALIZATION OF SELECTED SITE/S After identification of the site, the Contractor should fill up the prescribed reporting format provided in EMAP and submit the same for approval to the CSC. The selected site/s shall be approved by Environmental Officer of CSC, after considering the compliance with the EMP clauses. No agreements or payments shall be made to the land owner/s prior to receipt of a written approval from the CSC. Any consequence of rejection prior to the approval shall be the responsibility of the Contractor and shall be made good at his own cost. After obtaining a written approval from the CSC for the selected site, the Contractor has to enter into an agreement with the landowner to obtain his/her consent before commencing any operation / activities in the land. The agreement should also mention its type, duration, amount and mode of payment as well as the preferences of the owner regarding site maintenance and redevelopment. D. DESIGNING AND SETTING UP OF LABOUR CAMP Following facilities should be provided in a labour camp to ensure safe, clean and hygienic accommodation for the workers. (i) Site preparation: The site should be graded and rendered free from depressions such that the water does not get stagnant anywhere. Fencing should be constructed all around the camp to prevent the trespassing of humans and animals. Green belt should be provided along the boundary and as detailed in the EMP, it should be integrated with storm water drain and sedimentation trenches as given in annexure in EMAP. No. of trees planted should not be less than three times the number of trees cut. The approved layout plan should be strictly adhered to while setting up the camp. (ii) Accommodation: Contractor will follow all relevant provisions of the Factories Act, 1948 Revision Level: R2 September, 2014 Page 64 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division and the Building and the other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 for construction and maintenance of labour camp. The height of the worker’s and labour accommodation shall not be less than 3mt. from floor level to the lowest part of the roof. The camps shall be floored with concrete, shall be kept clean, with proper cross ventilation, and the space provided shall be on the basis of one sq.mt per head or as per the relevant regulation, whichever is higher. Fire and electrical safety pre-cautions shall be adhered to. Cooking, sanitation and washing areas shall be provided separately. The Contractor will maintain necessary living accommodation and ancillary facilities (including provision of clean fuel to prevent damage to forests and to prevent fuel wood cutting and burning by labour) in functional and hygienic manner. The site must be graded and rendered free from depressions such that water does not get stagnant anywhere. The entire boundary of the site should be fenced all around with barbed wire so as to prevent the trespassing of humans and animals. Green belt should be provided along the boundary and it should be integrated with storm water drain and sedimentation trenches to reduce the surface run off as per clauses in EMAP. No. of trees planted should not be less than three times the number of trees cut. (iii) Drinking Water: The Contractor should provide potable water within the precincts of every workplace in a cool and shaded area, which is easily accessible as per standards set by the Building and other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996. All potable water storage facilities will be on a safely raised platform that is at least 1m above the surrounding ground level. Such facilities shall be regularly maintained from health and hygiene point of view. If necessary water purifier units shall be installed for providing potable water. As far as possible shallow wells should not be used as potable source of water. However, if water is drawn from any existing well, irrespective of its location from any polluting sources, regular disinfection of the water source (which may include application of lime, bleaching power and potassium permanganate solution) has to be ensured at weekly/fort nightly interval. All open wells will be entirely covered and will be provided with a trap door to prevent accidental fall and contamination from dust, litter etc. The trap door will be kept locked and opened only for cleaning or inspection, which will be done at least once in a month. A reliable pump will be fitted to each covered well. A drain shall be constructed around the well to prevent flow of contaminated water into the well from road, camp or other sources. Water quality testing of all potable water sources will be done every six months as per parameters prescribed in IS 10500: 2012. (iv) Sanitation Facilities: Adequate no. of toilets shall be provided separately for males and females (depending on their strength), screened from those of men and provided with markings in vernacular language. All such facilities must have adequate water supply with proper drainage and disposal facility. They shall be maintained, cleaned and disinfected daily using proper disinfectants. Location and design of soak pit should be in such a way that it doesn’t pollute the ground water. Drains and ditches should be treated with bleaching powder on a regular basis. The sewage system for the camp must be properly designed, built and operated so that no health hazard occurs and no pollution to the air, ground or adjacent watercourses takes place. Portable toilets may be brought to use and the night soil from such units has to be disposed Revision Level: R2 September, 2014 Page 65 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division through designated septic tanks so as to prevent pollution of the surrounding areas. In the main camp, no night soil or sewerage shall be disposed of at any place other than the septic tanks constructed at the site. All these facilities shall be inspected on a weekly basis to check the hygiene standards. (v) Waste Disposal: The Contractor should provide garbage bins in the camps and ensure that these are regularly emptied and disposed off in a hygienic manner. No incineration or burning of wastes shall be carried out by the Contractor. Separate bins shall be provided for biodegradable, non-biodegradable and domestic hazardous wastes. The disposal of kitchen waste and other biodegradable matter shall be carried out in pits covered with a layer of earth within the camp site. The Contractor may use the compost from such wastes as manure in the plantation sites. Discarded plastic bags, paper and paper products, bottles, packaging material, gunny bags, hessian, metal containers, strips and scraps of metal, PVC pipe scrubber and poly urethane foam, auto mobile spares, tubes, tires, belts, filters, waste oil, drums and other such materials shall be either reused or sold /given out for recycling. (vi) Day Crèche Facility: At every construction site, provision of a day crèche shall be made so as to enable women to leave behind their children while going to work. At least one attendant shall be provided to take care of the children at the crèche. At construction sites where 20 or more women are employed, there shall be at least one shelter for use of children under the age of 6 years belonging to such women. Shelters shall not be constructed to a standard lower than that of thatched roof, mud walls and floor with wooden planks spread over mud floor and covered with matting. Such areas shall be safely barricaded (no sharp sheets or barbed wires that may injure a child) from rest of the camp for the safety of children. Shelters shall be provided with suitable and sufficient openings for light and ventilation. There shall be adequate provision to keep the place clean. The size of a crèche may vary according to the number of children on a camp site. (vii) Mess and Kitchen Facilities: The Contractor shall adhere to the sanitary/hygiene requirements of local medical, health and municipal authorities at all times. Adopt such precautions as may be necessary to prevent soil and water pollution at the site while operating mess or kitchen facilities. (viii) First aid facilities: At every workplace, a readily available first-aid unit including an adequate supply of sterilized dressing materials and appliances should be provided. Workplaces remote and far away from regular hospitals should have indoor health units with one bed for every 250 workers. Suitable transport should be provided to facilitate taking injured and ill persons to the nearest hospital. Adequate personal protective equipments and fire fighting equipments as detailed out in EMP should be made available in the camp and provided to the staff / workers. (ix) Health Care Facilities: Health problems of the workers should be taken care of by providing basic health care facilities. If there is no hospital or clinic, which can be accessed in half an hour’s time, then a temporary health center should be set up for the construction camp. The health centre should have at least a doctor and a nurse, duty staff, medicines and minimum medical facilities to tackle first aid requirements or minor accidental cases, linkage with nearest higher order hospital to refer patients of major illnesses or critical cases. Revision Level: R2 September, 2014 Page 66 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division The health centre should have MCW (Mother and Child Welfare) units for treating mothers and children in the camp. Apart from this, the health centre should be provided with regular vaccinations required for children. The health centre should carryout quarterly awareness programme of HIV – AIDS with the help of AIDS control society as well as about community living and hygiene practices in day to day living. Posters should be exhibited in the health care clinic. There will be an awareness programmes about the spread of communicable diseases and precautionary measures to prevent these diseases E. OPERATION OF LABOUR CAMP Throughout the functioning period of the camp, hygienic environment must be ensured by (i) provision of safe drinking water, (ii) proper maintenance of toilets including daily cleaning and disinfection using proper disinfectants, (iii) regular cleaning of drains by removing the silt and solid waste, (if any) and iv) appropriate waste management practices. While it is of utmost importance to ensure that fire-fighting equipments like fire extinguishers are in working condition, it should also be monitored that construction workers use the personal protective equipments provided to them and they are replaced when necessary. All these facilities should be inspected on a weekly basis to achieve the desired levels of safety and hygiene standards. F. PREPARATION OF LABOUR CAMP MANAGEMENT AND RE-DEVELOPMENT PLAN After the site for the labour camp has been finalized and approved by CSC, the Contractor should prepare a labour camp management and redevelopment plan to be submitted to CSC for approval prior to setting up of the camp and it should comprise the following details: ˜ Section–1: Details of site: Copy of approved site identification report along with location plan on a village map or an FMB, showing the site, its survey no., access road, project stretch, distance from the project stretch, surrounding features and land use like residences, agricultural land, water bodies etc., photograph of the site showing the topography and other existing features. ˜ Section-2: Site preparation: Activities that should be undertaken for preparing the site based on EMP and this guideline. ˜ Section-3: Arrangements/ facilities within the camp: List of facilities to be provided along with its details like area, no of people to be accommodated and a layout plan showing the plan of the site with all the facilities planned like quarters, labour camps, mess, common facilities, toilet facilities and the vehicular and pedestrian movement paths. ˜ Section-4: Mitigation measures that should be undertaken as per the EMP and this guideline while setting up of the camp and operation of the camp should be separately listed out here. ˜ Sectoin-5: Other details: Any other relevant detail like list of awareness camps to be provided to workers, details of information dissemination etc. should be included. Revision Level: R2 September, 2014 Page 67 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ˜ Section 6: Re-development plan: which should indicate following points: (i) List of structures to be demolished and list of the clean up activities that needs to be undertaken, (ii) Proposed use of the land in the post construction phase, if it is a public property, (iii) Presence of existing facilities that could be put in use by the land owner if it is a leased out private land or by the community in case of a public property. ˜ Section-7: Annexure-(a) Working drawings: Electrical plan showing the electrical network planned for the site, location of generators, master switch boards etc. and plumbing drawing showing the network of water supply lines, water tank, drainage facilities etc. (b) Copy of permissions obtained from local governing body / community etc. as applicable, (c) Copy of agreement entered with site owner, in case of leased out sites. All the drawings should have north direction marked in it along with prevailing wind direction. Necessary dimensions and specifications should be provided where ever necessary. The labour camp management plan should be submitted to the CSC for a written approval before any physical work is undertaken on a particular site. The CSC will carefully examine the proposals in light of the various EMP and regulatory provisions and provide suggestions, as necessary to the Contractor who shall incorporate it in the management plan. Contractor shall be responsible for satisfactory and timely completion of these EMP requirements. Contractor needs to prepare this document for each different site identified and CSC shall undertake a thorough analysis of the said management and redevelopment plan through a site investigation and suggest additional mitigation measures depending on the site and as demanded by the features of the specific site. G. RE DEVELOPMENT OF THE LABOUR CAMP The Contractor should clear all temporary structures; dispose all building debris, garbage, night soils and any other waste as per the approved debris management plan. All disposal pits or trenches should be filled in, disinfected and effectively sealed off. Residual topsoil, if any will be distributed or spread evenly in plantation sites, on adjoining/near-by barren land or affected agricultural land adjacent to the RoW that has been impacted on account of any accidental spillage. Entire camp area should be left clean and tidy, in a manner keeping the adjacent lands neat and clear, at the Contractor’s expense, to the entire satisfaction of landowner and the CSC. These activities should be completed by the Contractor prior to demobilization. Once the Contractor finishes his job, he needs to obtain a certificate from the owner, stating that the site has been redeveloped to his/her satisfaction and in tune with the agreement. Then following documents needs to be submitted to the CSC by the Contractor: ˜ Copy of approved site identification report ˜ Photographs of the concerned site ‘before’ and ‘after’ setting up the camp. ˜ Certificate from the owner stating his/her satisfaction about status of re-development of the site. CSC shall ensure, through site verification that all clean-up and restoration operations are completed satisfactorily and a written approval should be given to the Contractor mentioning the Revision Level: R2 September, 2014 Page 68 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division same before the ‘works completion’ certificate is issued/recommended. The PMU shall ensure through site inspection that the Contractor and CSC have complied with all these provisions. The site can then be handed over to the concerned owner or local bodies or for local communities as the case may be. Certification/documentation pertaining to approval for clean-up and restoration operations and thereafter handing-over to the owner shall be properly maintained by the Contractor, Supervision Consultant and PMU. Revision Level: R2 September, 2014 Page 69 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.3: GUIDELINES FOR SITING, MANAGEMENT AND REDEVELOPMENT OF QUARRYING AND STONE CRUSHING OPERATIONS The Contractor will finalize the locations from the list given by DPR Consultant’s for procuring materials. The Contractor shall establish a new quarry only with the prior consent of the EO only in cases when: (i) Lead from existing quarries is uneconomical and (ii) Alternative material sources are not available. The Contractor shall prepare a Redevelopment Plan for the quarry site and get it approved by the EO/Supervision Consultant. The construction schedule and operations plans to be submitted to the EO prior to commencement of work shall contain a detailed work plan for procuring materials that includes procurement, transportation and storage of quarry materials. Operation & redevelopment plan (if a new quarry is opened)….. • Photograph of the quarry site prior to commencement • The quarry boundaries as well as location of the materials deposits, working equipments, stockpiling, access roads and final shape of the pit. • Drainage and erosion control measures at site. • Safety Measures during quarry operation. • Design for redevelopment of exhaust site. Option-A: Revegetating the quarry to merge with surrounding landscape: This is done by conserving and reapplying the topsoil for the vegetative growth. Option-B: Developing exhausted quarries as water bodies: The pit shall be reshaped and developed into pond, for harvesting rainwater. This option shall only be considered where the location of quarry is at the lowest point, i.e. surrounding areas/natural drainage slopes towards it. CONSTRUCTION STAGE Development of site: To minimize the adverse impact during excavation of material following measures are need to be undertaken: i)Adequate drainage system shall be provided to prevent the flooding of the excavated area ii) At the stockpiling locations, the Contractor shall construct sediment barriers to prevent the erosion of excavated material due to runoff iii)Construction of offices, laboratory, workshop and rest places shall be done in the up- wind of the plant to minimize the adverse impact due to dust and noise. iv) The access road to the plant shall be constructed taking into consideration location of units and also slope of the ground to regulate the vehicle movement within the plant. v) Incase of storage of blasting material, all precautions shall be taken as per The Explosive Rules, 1983. Revision Level: R2 September, 2014 Page 70 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division QUARRY OPERATIONS INCLUDING SAFETY i)Overburden shall be removed and disposed in line with Guidelines for Debris Disposal Site and management giving in Appendix-8.4. ii) During excavation, slopes shall be flatter than 20 degrees to prevent their sliding. Incases where quarry strata are good and where chances of sliding are less this restriction can be ignored. iii) In case of blasting, procedure and safety measures shall be taken as per The Explosive Rules, 1983 iv) The contractor shall ensure that all workers related safety measures shall be done as per guidelines for Workers and Safety attached as Appendix-8.12. v) The Contractor shall ensure maintenance of crushers regularly as per manufacturer’s recommendation. Topsoil will be excavated and preserved during transportation of the material measures shall be taken to minimize the generation of dust and prevent accidents. The EO and the Supervision Consultant shall review the quarry site for the management measures during quarry operation, including the compliance to pollution norms. POST CONSTRUCTION STAGE The Contractor shall restore all haul roads constructed for transporting the material from the quarries to construction site to their original state. The EO and the Supervision Consultant shall be entrusted the responsibility of reviewing the quarry site for the progress of implementation of Redevelopment Plan. These shall include the following two cases; • Redevelopment of quarries opened by the Contractor for the project • Redevelopment of existing quarries operated by other agencies In the first case, the Contractor shall be responsible for the Redevelopment Plan prior to completion after five years, during the defect liability period. The EO shall be responsible for reviewing this case of redevelopment prior to the issuing the defect liability certificate. In the second case, the redevelopment of exhaust quarry shall be the responsibility of the agency providing the permit to ensure the implementation of Redevelopment Plan. There are three possibilities: Case I- If the quarry is an existing one and is managed directly by the Contractor. Case II -If the quarry is an existing one and is managed directly by a sub-contractor from whom the Contractor is sourcing the materials. Case III - If the quarry is a new one and is managed directly by the Contractor from whom the contractor is sourcing the materials. Revision Level: R2 September, 2014 Page 71 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.4: GUIDELINES FOR SITING, MANAGEMENT AND REDEVELOPMENT OF BORROW AREAS MANAGEMENT Borrow areas will be finalized either form the list of locations recommended by DPR consultants or new areas identified by contractor. The finalization of locations identified by DPR consultant or identified by contractor depends upon the formal agreement between landowners and contractor and its suitability from civil engineering as well as environmental consideration. Meeting the guidelines/notifications as stipulated from time to time by the Ministry of Environment and Forests, Government of India, and local bodies, as applicable shall be the sole responsibility of the contractor. There will be one number of borrow areas for SH 58 considering one borrow areas at about 30 km interval. Total length of SH 58 is 26.811 km. Besides this certain precautions have to be taken to restrict unauthorized borrowing by the contractor. No borrow area shall be opened without permission of the Engineer/EO. The engineer in addition to the established practices, rules and regulation will also consider following criteria before approving the Borrow areas. (1) The borrow area should not be located in cultivable land unless unavoidable i.e. no suitable uncultivable land in the vicinity for borrowing or private landowners are willing to allow borrowing in their fields. (2) Along the roadside, borrow pits should be located 5m away from the toe line. (3) The loss of productive and agriculture soil should be minimum. (4) The loss of vegetation is almost nil or minimum. (5) Sufficient quality of soil is available. (6) The Contractor will ensure that suitable earth is available. After identification of borrow areas based on guidelines. Contractor will fill reporting format as under and submit the same for approval to the “Engineer” Once approved the contractor will adhere to the recommendation for borrow area to the satisfaction of Engineer. (1) In no case the depth of borrow area should exceed 2m from the existing ground level. (2) Borrow pits slope should be maintained, no steeper than 1 Vertical: 4 Horizontal. (3) In case of cultivable land, top soil (15cm) should be preserved and stockpiled. (4) Ridges of not less than 8m width should be left at intervals not exceeding 300m. Small drains to be cut through the ridges to facilitate drainage (5) Water pooling to be avoided/managed so that no disease spread due to water stagnation. Revision Level: R2 September, 2014 Page 72 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division (6) Borrow pits should be located at least 1000m away from settlements. (7) Precautionary measures as the covering of vehicles will be taken to avoid spillage during transportation of borrow area. (8) The unpaved surfaces used for the haulage of borrow materials should be maintained properly for dust suppression. (9) Haulage of material to embankments or other areas of fill shall proceed only when sufficient spreading and compaction facility is operating at the place of deposition, to minimize dust pollution. (10) Borrow pits located near settlements will be re-developed immediately after borrowing is completed. If spoils are dumped, that will be covered with a layers of stockpiled topsoil in accordance with compliance requirements with respect MOEF/SPCB guidelines (11) Redevelopment of the borrow areas to mitigate the impact will be the responsibility of the contractor. The contractor shall evolve site-specific redevelopment plans for each borrow area locations, which shall be implemented after the approval of the Engineer. (12) Borrow area near to any surface water body will be at least at a distance of 15m from the toe of the bank or high flood level, whichever is maximum. (13) During rains appropriate measures to be taken to minimize soil erosion, silt fencing to be provided as directed by Engineer/EO. (14) Borrow areas might be used for aquaculture in case landowner wants such development. In that case, such borrow area will be photographed after their post use restoration and Environment Expert of Supervision Consultant will certify the post use redevelopment. The Contractor will keep record of photographs of various stages i.e., before using materials from the location (pre-project), for the period borrowing activities (construction Phase) and after rehabilitation (post development), to ascertain the pre and post borrowing status of the area. Revision Level: R2 September, 2014 Page 73 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.5: GUIDELINES FOR SITING AND MANAGEMENT OF DEBRIS DISPOSAL SITES The locations of Disposal sites have to be selected such that: • Productive land to be avoided and available wasteland to be given preference. • Disposal sites to be located at least 1000m away from sensitive locations like Settlements, Water body, notified forest areas, Sanctuaries or any other sensitive locations. • Should be located in the downwind side of nearest settlement locations. • Disposal sites do not contaminate any water sources, rivers etc for this, site should be located away from water body and disposal site should be lined properly to prevent infiltration of water. • Public perception about the location of debris disposal site has to be obtained before finalizing the location. • Permission from the Villager/local community is to be obtained in writing by contractor for finalising the disposal site identified. • The Plan must be approved by EO/Supervision Consultant and PIU- TNRSP. PRECAUTIONS TO BE ADOPTED DURING DISPOSAL OF DEBRIS / WASTE MATERIAL The contractor shall take the following precautions while disposing off the waste material • During the site clearance and disposal of debris, the contractor will take full care to ensure that public or private properties are not damaged/affected, there is no dwellings below the dumpsite and that the traffic is not interrupted. • Contractor will dispose off debris only to the identified places or at other places only with prior permission of Engineer/EO. • In the event of any spoil or debris from the sites being deposited on any adjacent land, the contractor will immediately remove all such spoil debris and restore the affected area to its original state to the satisfaction of the Engineer/EO. • The contractor will at all times ensure that the entire existing drains within and adjacent to the site are kept safe and free from any debris. • Contractor will utilize effective water sprays during the delivery and handling of materials when dust is likely to be created and to dampen stored materials during dry and windy weather. • Materials having the potential to produce dust will not the loaded to a level higher than the side and tail boards and will be covered with a tarpaulin in good condition. • Care should always be taken to maintain the hydrological flow in the area. REHABILITATION OF DISPOSAL SITES The dumpsites filled only up to the ground level could be rehabilitated as per guidelines below and to be decided by the engineer and the supervision consultant Revision Level: R2 September, 2014 Page 74 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division • The dumpsites have to be suitably rehabilitated by planting local species of shrubs and other plants. Local species of trees has also to be planted so that the landscape is coherent and is in harmony with its various components. • In cases where a dumpsite is near to the local village community settlements, it could be converted into a play field by spreading the dump material evenly on the ground. Such playground could be made coherent with the landscape by planting trees all along the periphery of the playground. • Material excavated for foundation of bridge works should not be dumped in the water course; if same has to be refilled then precaution has to be taken so that the excavated material should not be carried away by flowing/rainy water, thereby silting the water course. • Care should always be taken to maintain the hydrological flow in the area. Revision Level: R2 September, 2014 Page 75 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.6 GUIDELINES FOR PREPARING COMPREHENSIVE WASTE MANAGEMENT PLAN A. OVERVIEW A comprehensive waste management plan shall be prepared by the Contractor prior to initiation of any works. The purpose of the plan is to provide standardized procedures for the clearance, removal and disposal of debris caused by major debris / waste generated during the construction work as well as to establish the most efficient and cost effective methods to resolve debris disposal issues. B. PREPARATION OF COMPREHENSIVE WASTE MANAGEMENT PLAN The Contractor should prepare a Comprehensive Waste Management Plan to be submitted to CSC for approval prior to setting up of construction and labour camp and it should comprise the following details: ˜ Categorization of waste into degradable, biodegradable and hazardous categories and list of different types of waste that falls in each of these categories. ˜ Estimates about the quantity of waste generated in each category and type of storage units required. ˜ Detail the provisions for storage and handling of waste until disposed. A plan of the respective camps / areas like construction camp, labour camp etc. to be attached indicating in it the space allocated for storage and handling of wastes. ˜ Detail the precautions to be taken while storing, handling and disposing each type of waste, trainings to be imparted to workers to create awareness about waste management. ˜ Details of each debris disposal site: Copy of approved site identification report along with location plan on a village map or an FMB, showing the debris disposal sites, site, its survey no., access road, project stretch, distance from the project stretch, surrounding features and land use like residences, agricultural land, water bodies etc., photograph of the site showing the topography and other existing features. C. TRAINING FOR PROJECT STAFF AND WORKERS All staff and workers involved in the highway construction should be imparted training about comprehensive waste management plan including the need for such a plan, its components and measures adopted by the Contractor for implementing it. In addition, all personnel involved should be made aware about various steps and measures each of them has to follow so as to ensure the compliance to the comprehensive waste management plan. D. PRECAUTIONS TO BE ADOPTED DURING DISPOSAL OF DEBRIS/WASTE MATERIAL The Contractor shall take the following precautions during transportation and disposal of debris/waste material: Revision Level: R2 September, 2014 Page 76 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ˜ A register should be kept for recording the deta ils of the waste generated and their disposal. ˜ The pre-designated disposal sites should be a part of Comprehensive Solid Waste Management Plan and should be identified as per the EMP clauses prior to initiation of any work on a particular section of the road. ˜ The Contractor will take full care to ensure that public or private properties are not damaged/ affected during the site clearance for disposal of debris and the traffic is not interrupted. ˜ All arrangements for transportation during dismantling and clearing debris, considered incidental to the work, will be implemented by the Contractor in a planned manner as approved and directed by the CSC. ˜ In the event of any accidental spill or spread of wastes onto adjacent parcels of land, the Contractor will immediately remove all such waste material/s and restore the affected area to its original state to the satisfaction of CSC. ˜ Contractor should ensure that any spoils/materials unsuitable for embankment fill shall not be disposed off near any water course; water body; agricultural land; natural habitats like grass lands, wet lands, flood plains, forests etc. pasture; eroded slopes; and in ditches, which may pollute the surrounding including water sources. ˜ Contractor should ensure effective water sprinkling during the handling and transportation of materials where dust is likely to be created. ˜ Materials having the potential to produce dust will not be loaded beyond the side and tail board level and will be covered with a tarpaulin in good condition. ˜ Any diversion required for traffic during disposal of debris shall be provided with traffic control signals and barriers after discussion with the local body and as approved by CSC. ˜ During the debris disposal, Contractor will take care of surrounding features and avoid any damage to trees and properties. ˜ Surplus fly ash, bottom ash and lime, if any, transported for use on this corridor shall not be left open and dumped at any disposal site. Contractor shall take care of such residual materials for use at any other location/s of new embankment construction work with proper protection measures ˜ No hazardous and contagious waste material shall be disposed at such locations. E. WASTE DISPOSAL IN CONSTRUCTION CAMP ˜ Concrete flooring and oil interceptors should be provided for hot mix plant area, workshops, vehicle washing and fuel handling area. ˜ POL (petroleum, oil and lubricants) waste shall be stored safely in separate containers and should be disposed off by transfer only to recycler/ re-refiners possessing valid authorization from the State Pollution Control Board and valid registration from the Revision Level: R2 September, 2014 Page 77 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Central Pollution Control Board. ˜ Used lead batteries, if any, should be disposed as per the Batteries (Management and Handling) Rules 2001. ˜ Water separated and collected from oil interceptor should be reused for dust suppression. ˜ There should be a register to record the details of the oil wastes generated at the workshops and oil storage areas. ˜ The Contractor will provide separate garbage bins in the camps and ensure that these are regularly emptied and disposed off in safe and scientific manner as per the Comprehensive Solid Waste Management Plans approved by the CSC. ˜ No incineration or burning of wastes shall be carried out. ˜ Discarded plastic bags, paper and paper products, bottles, packaging material, gunny bags, hessian, metal containers, strips and scraps of metal, PVC pipes, rubber and poly urethane foam, auto mobile spares, tubes, tires, belts, filters, waste oil, drums and other such materials shall be either reused or will be sold /given out for recycling. ˜ Septic tank must be provided for toilets and the sludge should be cleared by municipal exhausters. F. WASTE DISPOSAL IN LABOUR CAMP ˜ The Contractor should provide separate garbage bins in the camps for bio-degradable, non-degradable and domestic hazardous waste and ensure that these are regularly emptied and disposed off in safe and scientific manner. ˜ The disposal of kitchen waste and other biodegradable matter shall be carried out in pits covered with a layer of earth within the camp site to avoid smell and pests. The Contractor may use the compost from such wastes as manure in the plantation sites. ˜ Noon-biodegradable waste like discarded plastic bags, paper and paper products, bottles, packaging material, gunny bags, hessian, metal containers, strips and scraps of metal, PVC pipes, rubber and poly urethane foam, auto mobile spares, tubes, tires, belts, filters, waste oil, drums and other such materials shall be either reused or should be sold /given out for recycling. ˜ No incineration or burning of wastes should be carried out. ˜ Effluent treatment system like septic tank with soak pits provided for toilets should be sited, designed, built and operated in such a way that no health hazard occurs and no pollution to the air, ground or adjacent watercourses takes place. ˜ Soak pits must be provided to collect waste water from bathrooms and kitchen. G. DISPOSAL OF BITUMINOUS WASTE ˜ The bituminous waste should be used for development of roads inside the construction camps, haul roads or for filling pot holes in rural roads. Revision Level: R2 September, 2014 Page 78 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ˜ At locations identified for disposal of residual bituminous wastes, the disposal will be carried out over a 60 mm thick layer of rammed clay so as to eliminate the possibility of leaching of wastes into the ground water. ˜ The Contractor will suitably dispose off unutilized non-toxic debris either through filling up of borrows areas located in wasteland or at pre-designated disposal sites, subject to the approval of CSC. ˜ Debris generated from pile driving or other construction activities along the rivers and streams drainage channels shall be carefully disposed in such a manner that it does not flow into the surface water bodies or form puddles in the area. H. DISPOSAL OF NON BITUMINOUS WASTE ˜ Non-bituminous wastes other than fly ash may be dumped in borrow pits (preferably located in barren lands) where such borrow pits are not suitable to be re-developed as an economic source like pisci-culture or a source of irrigation. Such borrow pits can be filled up with non-bitumen wastes and then covered with a minimum 30cm layer of the soil, where plantation of trees and shrubs will be taken-up by the Contractor as a part of site rehabilitation. ˜ Local tree species suitable for such re-habitation work shall be selected in consultation with local community. I. REUSE OF DEBRIS GENERATED FROM DISMANTLING STRUCTURES AND ROAD SURFACE Debris generated due to the dismantling of existing road will be suitably reused in the proposed construction as follows ˜ Eighty percent (80%) of the sub-grade excavated from the existing road surface, excluding the scarified layer of bitumen, shall be reused in the civil works after improving the soil below the sub grade through addition of sand and suitable cementing material for qualitative up-gradation. ˜ The dismantled scraps of bitumen will be utilized for the paving of cross roads, access roads and paving works in construction sites and campus, temporary traffic diversions, haulage routes, parking areas along the corridor or in any other manner approved by the Environmental Officer of SC Revision Level: R2 September, 2014 Page 79 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.7 GUIDELINES FOR TOP SOIL CONSERVATION AND REUSE The top soil from all sites including road side widening and working area, cutting areas, quarry sites, construction camps, labour camps, haul roads in agricultural fields (if any) and areas to be permanently covered shall be stripped to a specified depth of 15 cm and stored in stock piles for reuse. A portion of temporarily acquired area and/or RoW edges will be earmarked for storing top soil. The locations for stacking will be pre-identified in consultation and with approval of environmental officer of SC. The following precautionary measures will be taken by the Contractor to preserve the stock piles till they are re-used: Stockpiles will be such that the slope doesn’t exceed 1:2 (vertical to horizontal), and height is restricted to 2 m. ˜To retain soil and allow percolation of water, the edges of pile will be protected by silt fencing. ˜Multiple handling kept to a minimum to ensure that no compaction occurs. ˜Such stockpiles shall be covered with empty gunny bags or will be planted with grasses to prevent the loss during rains. Such stockpiled topsoil will be utilized for: ˜Covering reclamation sites or other disturbed areas including quarry areas. ˜Top dressing and raising turfs in embankment slopes ˜Filling up of tree pits ˜For developing compensatory afforestation plantation ˜ In the agricultural fields of farmers, acquired temporarily that needs to be restored. Residual top soil, if there is any, shall be utilized for the plantations works along the road corridor. The utilization as far as possible shall be in the same area from where top soil was removed. The stripping, preservation and reuse shall be carefully inspected, closely supervised and properly recorded by the SC. Revision Level: R2 September, 2014 Page 80 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.8 GUIDELINES FOR PROVISION OF NOISE BARRIERS Mitigating the impact of increased noise levels at the sensitive receptor locations includes posting of signs prohibiting the use of horns, constructing a sound insulating wall and, to the extent possible, planting appropriate trees to serve as green noise barriers. Attenuation of sound can be achieved considerably by the combined effect of sound insulating walls and green barriers. Nevertheless the putting of green barriers requires at least 2-5m additional space between the solid barrier and the receptor. Principle of the designed barrier is explained in the design sections. Proposed project mitigation actions are cost effective when compared to the generally recommended expensive double glazed windows. A. SOUND INSULATING WALLS FOR SILENCE ZONES The design of a sound insulating wall comprises 23 cm thick brick wall which will act as a sound barrier. The typical cross section for the same is given in Figure 1. This can be provided adjacent to the road corridor where hospitals, medical centre, schools and other educational institutions are affected by the traffic noise. B. GREEN BARRIERS FOR SILENCE ZONES These are simply a thick layer of green plantation with limited foliage (eg. Ashoka Tree) acting as noise absorbers. These trees may be planted just inside and adjacent to the wall. While contractors will be responsible for the implementation of the civil work, tree plantation will be carried out by the Forest department under the tree-planting scheme of the project. The implementation aspects are provided in the EMP. In addition to the noise mitigation, the thick green layer will act as an air quality filter for traffic emission. A typical green barrier of 100m lengths will have 200 trees in 4 rows. Noise mitigation techniques will be employed as may be warranted at each of the sensitive receptor sites. Definitive noise levels will be empirically determined at each site and selection of the mitigation technique will be made on a site- specific basis in consultation with property owners. Co-ordination and implementation will be the responsibility of the Environmental officer of the supervision consultants (SC). Mitigation cost has been estimated as a part of the environmental costs of the project. Revision Level: R2 September, 2014 Page 81 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Figure 1. Typical Cross Section of a Noise Barrier Revision Level: R2 September, 2014 Page 82 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.9: GUIDELINES TO ENSURE WORKERS SAFETY DURING CONSTRUCTION SAFE LAYOUT IN THE CONSTRUCTION PLANT, CAMP AND QUARRY AREAS 1. Arrange border to perimeter fencing 2. Ensure good visibility and safe access at site entrances 3. Provide adequate warning signs at the entrance and exit where necessary 4. Provide adequate space/area for loading and unloading, storage of materials, plant and machinery 5. Display emergency procedure and statutory notices at conspicuous location 6. Consider welfare facilities required 7. Provide areas for dumping garbage and other waste materials, and also arrange for their regular clearance. 8. Arrange storage, transport and use of fuel, other flammable materials and explosives in line with the license requirements to be obtained from appropriate authorities 9. Plan emergency assembly points, fire escape routes and locate fire-fighting equipment 10. Provide access roads and plant movement areas within the site. 11. Ensure the availability of first aid facilities and display notices at the various works to show the location of these facilities 12. Provide proper drainage and sewage & drainage facilities HOUSE KEEPING PRACTICES 1. Maintain washrooms and canteens clean 2. Keep all walkways clear and unobstructed at all times 3. Ensure that spillages of oil and greasy 4. Stack raw materials and finished products clear of walkways or inside roads 5. Do not leave tools on the floor or in any location where they can be easily dislodged 6. Keep windows and light fitting clean 7. Maintain the workplace floors dry and in a non-slippery condition 8. Provide and maintain proper drainage system to prevent water ponding 9. Use metal bins for oily and greasy rags and store all flammable materials in appropriate bins, racks or cabinets. Ensure that the meal bins for storing oily and grease rags should be covered with lids. 10. Ensure that protruding nails in boards or walls are moved or bent over so that they do not constitute a hazard to people 11. Make sure that hazardous/dangerous chemicals are kept in the goods stores with the appropriate labelling, display of the material-safety-data-sheet (MSDS) and other precautionary measures Revision Level: R2 September, 2014 Page 83 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division 12. Display ‘no smoking’ signs in areas with high fire risks, e.g. paint stores, wood working area and others TREE FELLING • Use hard hats during tree felling • Ensure tools such as the axes are in good condition • Determine proper foot and body position when using the axe. Do not cut above your head • Wear appropriate foot protection • Carry a first aid kit to the site • Determine possible hazards in the area, e.g. electrical or telephone or other utility lines • Prior to felling, determine the safest direction for the fall • Determine the proper hinge size before directing the tree fall. NOISE HAZARDS AND ITS CONTROL 1. Note that indications of noise levels are: • You have to shout to be heard; • Your hearing is dulled just after work; • You get head noises or ringing in the ears after work; • You have difficulty hearing people while others are talking 2. Use sound level meters to measure. If the sound level exceeds 85 dB(A), then preventive measures should be taken 3. Make personnel aware of noisy areas by using suitable warning signs and insisting that ear protectors should necessarily be worn. 4. Reduce noise at source by improved maintenance, replacing noisy machines, screening with noise absorbing material, making changes to the process/equipment, controlling machine speeds, ensuring that two noise-generating machines are not running at the same time, using cutting oils and hydraulic breakers. 5. Appoint a competent person to carry out a detailed noise assessment of the site, designate ear protection zone, and give instructions on the necessary precautionary measures to be observed by site personnel, including the use of suitable type of ear protections. 6. Wear and maintain ear muffs and ear plugs as required 7. In construction or repair work, noise should be kept to a low-level bearing in mind the disturbance to local residents. ROAD WORKS 1. The use of signage is most important to caution the road users of possible unsafe conditions due to the road works. 2. Use the appropriate signage devices as required by the site conditions/situation. The devices include regulatory signs, delineators, barricades, cones, pavement markings, lanterns and traffic control lights. Revision Level: R2 September, 2014 Page 84 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division 3. In using signs, make sure that they are (i) simple, easy-to-understand and convey only one message, (ii) luminescent and with reflective properties, and iii) broad, prominent and of appropriate size. 4. In using barricades, make sure that you keep traffic away from work areas and you guide the drivers to keep along a safe, alternative path. 5. Ensure that proper personal protective equipment (PPE) is provided to all the workers. 6. Cover existing road signs and install new ones at appropriate locations taking into account the distances that would be required and reaction times. 7. Plan layout and traffic management so that hazard is not created. 8. Deploy flagmen, who control traffic at the work areas. 9. Flagmen should wear reflective safety vests along with hard hats 10. If required, use wireless devices for flagmen to co-ordinate from either ends of the road, where works are being carried out. ELECTRICAL HAZARDS IN CONSTRUCTION AREAS 1. Treat all wires as live wires 2. Never touch dangling wires, but report them to your manager 3. Unless you are a qualified electrician, do not attempt electrical repairs 4. Never use electrical equipment if you hands are wet or you are standing in water 5. If electrical equipment is sparking or smoking, turn the power off and report the condition to your supervisor 6. Never use electrical wires that have physical damage 7. Never allow equipment or traffic to run over electrical wires. USE AND STORAGE OF GAS/LPG 1. Store filled gas/LPG cylinder in the open area, i.e. outside of the building 2. Transport, store, use and secure cylinders in upright position 3. Ensure proper ventilation at the ground level in locations where gas/LPG is in use 4. Avoid physical damage to the cylinders 5. Never weld or cut on or near the cylinders 6. Store empty cylinders secured and upright 7. Make sure that the cylinder is closed immediately after use 8. Investigate immediately if there is the smell of LPG or gas 9. Never use destenched gas/LPG on site. 10. Make sure that there is no other unrelated fire in the vicinity of the cylinder Revision Level: R2 September, 2014 Page 85 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division OPERATION OF EXCAVATORS 1. Ensure that excavators are operated by authorized persons who have been adequately trained. 2. Prevent unauthorized movement or use of the excavators 3. Check regularly and maintain the machine thoroughly 4. Ensure that all relevant information, including those related to instruction, training, supervision and safe system of work are provided to the operators. 5. Ensure that the operation and maintenance manuals, manufacturer’s specifications, inspection and maintenance log books are provided for the use of the mechanics, service engineers or other safety personnel during periodic maintenance, inspection and examination. 6. During tipping or running alongside the trenches, excavators must be provided with stop blocks. 7. Excavators must be rested on firm ground during operation 8. Avoid operating the machine too close to an overhang, deep ditch or hope and be alter to potential carving edges, falling rocks and slides, rough terrain and obstacles. 9. Locate and identify underground services by checking with all utility companies before excavations. 10. Ensure that all excavations are supervised by experienced and competent persons. 11. When reversing or in caste the operator’s view is restricted, adequate supervision and signaling should be provided. 12. Ensure that the type and capacity of the excavator are properly chosen for the intended purposes and site conditions. Never use a machine for any purposes other than it is designed for. 13. Check and report for excessive wear and any breakage of the bucket, blade, edge, tooth and other working tools of the excavator. 14. Check that all linkages/hinges are properly lubricated and ensure that the linkage pins are secured. Never use improper linkage pins. 15. Never dismount or mount a moving machine 16. Work only with adequate ventilation and lighting 17. Ensure that the protective front screen of the driving cabin is fixed in position during excavations to avoid eye injury to the operator. 18. Ensure switch-off of the unattended vehicle. OPERATION OF TRUCKS AND DUMPERS 1. Ensure that only trained, authorized and licensed drivers operate the vehicles 2. Enlist the help of another worker before reversing the vehicle 3. Switch-off the engine of an unattended vehicle Revision Level: R2 September, 2014 Page 86 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division 4. Lower the tipping bodies when the machine is unattended, but if it is necessary to leave them in the raised position they should be blocked to prevent their fall. 5. Wear safety boots or shoes to avoid injuries during loading and unloading. 6. Carryout periodic servicing to the manufacturer’s requirements. All records of maintenance and repairs should be in writing or kept on site. 7. Keep the vehicle tidy and the cabin free from tools and material, which might obstruct the controls. 8. Keep to speed limits. 9. No passenger should be carried on a dumper except the driver 10. Never drive the vehicle across a slope 11. Provide stop blocks when the vehicle is tipping into or running alongside excavations 12. Do not overload the vehicle. 13. Carry only well secured loads 14. Park only on level ground, in neutral with the parking brake applied 15. Never mount of dismount from a moving vehicle GAS WELDING 1. Use the following personal protective equipment during welding • Face or hand shield fitted with filters • Goggles, particularly when chipping slag • Gloves long enough to protect wrists and forearms against heats, sparks, molten metal and radiation • High-top boots to prevent sparks from entering footwear. 2. Screen of the work area with sturdy opaque or translucent materials because glare can cause eye injury. 3. Key for opening the acetylene cylinder valve must be one the valve stem while the cylinder is in use so that the cylinder valve may be immediately shut-off in an emergency. 4. Ventilate the workplace using air blowers and exhaust fans to remove poisonous fumes and gases that are given off during welding 5. Take precautions against flying sparks and hot slag where welding is being done near flammable materials and check the area before leaving. 6. Do not weld material degreased with solvents until completely dry. 7. Do not use gas cylinders for supporting work or as rollers 8. Do not use oil grease on oxygen cylinder fittings 9. Do not use cylinders with damaged valves. 10. Do not use too much force if valves are stuck. 11. Replace valve caps after use Revision Level: R2 September, 2014 Page 87 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division 12. Search for leaks in equipment by using a solution of soapy water. 13. Shut the cylinder valve if acetylene from a cylinder catches fire at the valve or regulator due to leakage at a connection. 14. Treat all gas cylinders as “full” unless you are sure otherwise. 15. Never attempt to transfer acetylene from one cylinder to another or attempt to refill an acetylene cylinder. 16. Place portable fire extinguishers near the welding area 17. Secure all cylinders against accidental displacement. 18. Always lift gas cylinders. Do not slide them along the ground or drop them from trucks. 19. Keep gas cylinders in vertical position both in storage and when in use 20. Keep the work place dry, secure, free from combustible materials and obstruction. 21. Store the acetylene and oxygen cylinders separately, and in a proper store. 22. Keep the gas cylinders from source of heat, flammable materials, corrosive chemicals and fumes. MANUAL HANDLING AND LIFTING 1. Use mechanical equipment in lace of manual handling as far as possible. 2. Assess the manpower required to handle or life the load safety and arrange the manpower accordingly. 3. In handling hazardous materials, the workers shall be informed of the hazards and safety precautions. 4. All relevant persons shall be trained in the proper methods of lifting and carrying. 5. Where team work is required, select the persons whose ages and physical builds are compatible for teaming up. Coordinate the actions of the team members by giving necessary instructions. 6. Always lighten or suitably shape the load for manual handling as far as possible Keep a look out for splinters, sharp edges, loose banding and nails. 7. Clear path or obstruction and tripping hazards. 8. Stack and secure goods safety on trucks, otherwise they fall off and injure passers-by. 9. Use personal protective equipment such as gloves, safety shoes, etc. 10. Adopt the following procedure when you lift a load: 11. Stand close to the object. Have a firm footing with feet spread on either side of the road. 12. Bend the knees and keep your back as straight as you can 13. Grasp object firmly. Be sure grip will not slip 14. Breathe in and throw the shoulder backwards. 15. Straighten the legs, continuing to keep the back as straight as you can. 16. Hold object firmly close to the body Revision Level: R2 September, 2014 Page 88 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division 17. Always lift smoothly. Avoid jerky motions. Turn with feet instead of twisting the back. HANDLING CHEMICALS AND HAZARDOUS SUBSTANCES 1. Always substitute hazardous chemicals with harmless or less hazardous ones wherever possible. 2. Enclose the process using chemicals or provide other engineering controls such as local exhaust ventilation, a fume cupboard or a safety cabinet. 3. Exercise great care in the storage and use of chemicals because they may be explosive, poisonous, corrosive or combustible. 4. Separate different chemicals physically 5. Store chemicals classified as dangerous goods in a properly constructed and approved goods store. Keep proper records of all chemicals and hazardous substances delivered, stored and used on site. 6. Consider unknown substances and liquids as dangerous until proven otherwise. 7. All containers should be clearly labelled to indicate contents. Never use a wrongly labelled container for chemicals. 8. Prohibit smoking in the vicinity of dangerous chemicals 9. Ensure that you are wearing the correct personal protective equipment before you handle chemicals 10. Maintain the Material Safety Data Sheet of all chemicals for reference on safety precautions to be taken and the use of suitable PPE. 11. When opening containers, hold a rag over the cap or lid, as some volatile liquids tend to spurt up when released. 12. Wash before you eat and do not eat at the work place. 13. If the skin is splashed with a chemical, rinse it immediately with plenty of clean water. Eye should be flushed thoroughly with water followed by immediate medical attention. 14. Eye fountain, emergency shower and breathing apparatus should be available in the vicinity of the workplace. 15. Safety instructions for handling emergency situations should be displayed prominently at both the storage and use locations. FIRST AID 1. Provide first aid boxes at every site 2. Ensure that training on the use of the first aid box is provided to a handful of staff working in the site. 3. Display the list of persons who are trained on providing first aid. 4. Ensure that every first aid box is marked plainly “First Aid” in English and local language. 5. The responsible person or first aider should replenish the contents of the first aid box as necessary. Revision Level: R2 September, 2014 Page 89 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division PERSONAL PROTECTIVE EQUIPMENT General 1. Consider the provision of personal protective equipment only after all measures for removing or controlling safety hazards have been provided reasonably impractical. 2. Ensure that sufficient personal protective equipment are provided and that they are readily available for every person who may need to use them. 3. The management should ensure that all persons make full and proper use of the personal protective equipment provided. 4. Provide instruction and training in the proper use and care of any specific protective equipment where necessary 5. Do not wilfully misuse, interfere with or ill-treat any protective clothing and equipment provided. 6. Ensure that the personal protective equipment is in good condition. Report immediately any damage to the management for replacement. Always keep the personal protective equipment as clean as possible. Eye protection 1. Issue eye protection equipment where there is a foreseeable risk of eye injury 2. Ensure an adequate supply of goggles/shields is available. 3. Keep the goggles clean and make sure they are good fit. 4. Do not watch welding operations unless your eyes are protected from the damaging effect of flash. Head Protection 1. No person shall enter a construction site unless he is wearing a suitable safety helmet 2. Wear a safety helmet: • When there is the risk of being hit by falling objects • While on or near a construction site • During adverse weather conditions • When in any area designated as a “hard hat” area. 3. Provide identification labels to all helmets in some way to prevent random exchange among wearers, with one helmet exclusive to each person. 4. Inspect helmets for cracks of sign of impact or rough treatment before each usage. Destroy, remove and replace all worn, defective or damaged helmets. Hearing Protection 1. Provide ear plugs or ear muffs as required. Use re-usable ear plugs when the reduction required (15-25 dBA) is not excessive. Use ear muffs where a large attenuation of upto 40 dBA is demanded. 2. Do not use dry cotton wool for hearing protection because it cannot provide any. Revision Level: R2 September, 2014 Page 90 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division 3. Provide disposable ear plugs for infrequent visitors and ensure that they are never re-used. 4. Provide re-usable ear plugs for those who need to work continuously for a long period in a high noise area. 5. Use ear muffs with replaceable ear cushions because they deteriorate with age or may be damaged in use. 6. Avoid wearing spectacles with ear muffs. 7. Use soap and water or the recommended solvent for cleaning ear muffs. 8. Provide ear muffs for those who may need to get in and out of a high noise area frequently. RESPIRATORY PROTECTIVE EQUIPMENT 1. Wear suitable respirable for protection when there is a potential for small particles entering the lungs, e.g. emptying of cement bags. 2. Provide training to all persons using the respirators for their correct fitting, use, limitations and symptoms of exposure. 3. Clean and inspect all respirators before and after use. 4. Store respirators properly when not in use. Safety Footwear 1. Wear suitable footwear for work 2. Use safety footwear on site or in other dangerous areas 3. Wear suitable safety shoes or ankle boots when working anywhere where there is high risk of foot injuries from slippery or uneven ground, sharp objects, falling objects, etc. 4. All safety footwear, including safety shoes, ankle boots and rubber boots, should be fitted with steel toecaps. 5. Avoid wearing flip flops, high heeled shoes, slippers, light sport shoes in situations where there is a risk of foot injury. 6. Keep shoe lace knots tight. Hand Protection 1. Wear suitable gloves for selected activities such as welding & cutting and manual handling of materials & equipment. 2. Do not wear gloves where there is a risk of them becoming entangled in moving parts of machinery 3. Wash hands properly with disinfectant soap and clean water before drinking, eating or smoking. Wash hands immediately after each operation on site when the situation warrants. FIRE PREVENTION, FIGHTING AND EQUIPMENT Before fire breaks cut 1. Store flammable material in proper areas having adequate fire protection systems. 2. Display sufficient warning signs. Revision Level: R2 September, 2014 Page 91 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division 3. Train selected personnel to use these fire extinguishers 4. Inspect fire extinguishers regularly and replace as necessary 5. Fire escape route should be kept clear at all times and clearly indicated. 6. Know the escape route and assembly point. 7. Display escape route maps prominently on each floor 8. Carryout fire drill regularly. Designate fire officers 9. Install fire alarm wherever required and test regularly. 10. Provide sufficient exit signs at prominent locations for directing people to the escape staircases and routes. When fire breaks out. 1. Alert all persons 2. Put off the fire with appropriate fire extinguishers only when you are sure that you are safe to do so. 3. Escape if you are in danger through the fire escape route to assembly point 4. Fire officers to carryout head count at the assembly point. Incident and accident investigations 1. Carryout the investigation as quickly as possible. 2. Conduct interviews with as many witnesses as necessary 3. Do not rely on any one sole source of evidence 4. Use the following tools: Checklists for obtaining basic and typical information for accidents • Notebook • Tape records • Camera • Measuring tape • Special equipment for the particular investigation 5. Obtain answers to the following questions: • When did the accident occur? • Where did it occur? • Who was injured and what was damaged? • What caused the accident? • Why did it occur? • How could it have been prevented? • How can a recurrence be prevented? 6. Prepare a short but sufficient investigation report that contains the following: Revision Level: R2 September, 2014 Page 92 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division • A summary of what had happened • A summary of events prior to the accident • Information gathered during the investigation • Details of witnesses • Information on injury or loss sustained • Conclusions and possible causes of the accident • Recommendations to prevent recurrence • Supporting materials (photos, diagrams, etc.) WORKERS SAFETY DURING CONSTRUCTION Sl Stage and Nature of Construction Safety measures expected to be taken by the No. Hazard Contractors and Site Engineers 1 Excavation in soft loose & slushy The Excavation beyond 1.5 m to 2.00 m to be soil above 2.00 m depth sliding of done in steps of minimum 500 mm offsets as earth or collapsing of sides. shown in Clause 2.18.2(b) and also planking and strutting should be done as in Clause 2.19.1. 2 Excavation in slippery area (water Try to dewater the area and spread minimum 150 logged) – The labour may fall or mm thick sand layer to avoid slipping machinery on site may slip. 3 Excavation in Rock where chiseling For hammer work, only experienced and skilled is involved – The fall of hammer labour should be employed. Chisel should not be may injure the hand, small rock allowed to be held by hand, while hammering but pieces may injure the eyes and legs. chisel holding clamp should be provided. The labour should be provided with goggles and leg cover to protect eyes and legs, from injuries due to small rock pieces. 4 Excavation in Rock where blasting The work of blasting should be entrusted to only is involved - Careless handling may experienced persons. Provide sufficient length of lead to injury to main worker or a fuse to give ample margin of time from the time passerby. of lighting to the time of explosion. A danger zone at least 180m diameter is to be flagged off 10 minutes before actual firing. All workmen should be sent away from danger zone except the firing man, who should be provided with a whistle. 5 Excavation for drain across road or The area should be well barricaded & a red lamp manhole adjacent to a road – provided at night. A watchman should be deputed chances of a passer by falling into to prevent any movement of persons, or vehicles. the excavated portion 6 During Excavation or sometimes In places where the movement of snakes are more even while concreting – Snake bites the contractor should provide the labour with gum or Scorpion stings – boots, gloves etc. and also make snake antidotes available on site. A particular care that has to be taken on such site is to always keep a vehicle Revision Level: R2 September, 2014 Page 93 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Sl Stage and Nature of Construction Safety measures expected to be taken by the No. Hazard Contractors and Site Engineers available on site to rush the patient to a doctor. This applies to snake stinged patients as well. 7 Centring (form-work) and Many a times ballies joined together give way due scaffolding –Form-work collapse to weak joint. Hence the use of joined ballies while concreting or just before should be restricted. Only 2 joined ballies out of 8 concreting especially when wooden ballies should be allowed. In case of double ballies are used. staging for a Slab at a height, utmost care should be taken to see that the top balli rests on the bottom balli. A particular care that should be taken during each concreting operating of slabs and beams is that, one carpenter and two helpers with spare ballies, nails etc. should be deputed below the slab/beam that is being concreted to watch any disturbance in the supports of the form- work below during concreting and in case of any doubt the concreting should be stopped immediately and the form work strengthened. Never allow bricks below a balli to make up the required height. This is most dangerous. 8 Form-work for beams and slabs: This case is noticed when slender ballies are used The bottom of beam collapses and without bracing. In fact, no concreting should be many a times brings down the slab allowed without bracing at 300 mm above ground, as well, injuring the labour and and at mid way, in normal beams & slabs. The supervision staff. bracings should be for the support of beams as well as slabs. 9 Form-work for sides of a slab–The This is noticed when the carpenter fixes the side labour just rests his foot on the shuttering of a slab with a plank just tied by plank and looses balance and falls binding wire to the steel reinforcements and by resulting a fatal accident. wooden pieces nailed in wall and plank. This is so weak a portion that with little pressure the plank gives way. Hence side shuttering should be done with a direct balli support from ground or floor, and the practice of tying planks with binding wire to the steel reinforcement should be totally avoided. A temporary railing along the periphery of slab will guard the life of labour and supervision staff. 10 Form-work for beams and slabs– In fact, this is a most dangerous work. One should Opening the form- work–Accident be very careful while form-work is removed. Only due to fall of materials during trained carpenters should be deputed for the work. removing the forms. A safe resting place outside the area of slab as a temporary measure should be constructed from where the Slab can be removed safely. Removal of form-work during night should not be permitted Revision Level: R2 September, 2014 Page 94 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Sl Stage and Nature of Construction Safety measures expected to be taken by the No. Hazard Contractors and Site Engineers under any circumstances. 11 Scaffolding–Fall of work-man, This is a very common negligence on the part of Supervision Staff, Standing on labour who do scaffolding work. The Chalis on Chalis not tied properly or tied only which they work either span over it's complete at one end. length or is tied loosely and many a times at one (Chalis mainly made of Bamboos). end only. Hence, care must be taken that the Chali do not span over the full length but some middle support should be provided and also the same is tied properly on both ends. 12 Ladders–Balli or bamboo ladders – The ladders should be strong enough to bear the The horizontal member breaks and weight of a labour with materials on head. As far the person falls. Sometimes the top as possible a hand rail should be provided at one face just rests on wall and the whole end. The horizontal member should be preferably ladder tilts causing an accident. fixed with. Bolt& nuts or strong nails. When the ladder is placed across a wall the top portion should be tied firmly to a strong support so that the ladder does not move laterally. 13 Column Reinforcements–Column The tendency of bar-benders is to tie the vertical reinforcements mainly in steel with coir rope or 8 mm steel rods as ties on independent footings collapses – all four sides of the column reinforcement. This Injury to persons working nearby. method of supporting the column reinforcements results in a weak support. Hence, the column reinforcements should be supported by strong ballies on all four sides of reinforcements and as far as possible a combined platform should be constructed out of ballies over which the reinforcements can be supported. 14 Concreting chajjas – When chajjas While concreting chajjas care must be taken that are concreted without care and on the labour does not stand on the reinforcement and opening the form-work the chajja disturb the position. Separate scaffolding must be would collapse, causing injury to tied over which the labour can stand and work labour on top or bottom of chajja. without disturbing the reinforcements. The main reason is in chajja the steel is placed on top face but if the labour stands on the steel, it will bend and come to bottom face and hence the chajja will fall when form-work is removed, thus, causing injury to labour working on top, or bottom. 15 Dismantling–Dismantled materials When work of demolition is to be taken up the may fall on passerby or the person area should be closed for all outsiders. No one engaged in dismantling work may should be allowed up to 50 m. from the place of fall due to slipping. The dismantled demolition. The workers engaged in demolition materials may fall on persons should be asked to wear safety belts. Helmets working below. must be worn by all the workers engaged in dismantling work. The place should be strictly Revision Level: R2 September, 2014 Page 95 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Sl Stage and Nature of Construction Safety measures expected to be taken by the No. Hazard Contractors and Site Engineers guarded at night with red lights at prominent places, and watchman should be posted. 16 Electric-Connections/Cables etc. – The work in such places should not be allowed to High tension/L.T. Electric wire the workers themselves, but in such position the passing near the slab structure- work must be executed under the strict while bending, lifting or tying supervision of a responsible Foreman or a reinforcements the bar benders may Supervisor. sustain the Electric Shock, causing fatal injury. 17 Electric Connections/Cables etc. – Before taking up the work all available drawings Cables below ground may get should be studied, local enquiry to be made to punctured during excavation & thus know the position of cables and work in such area electrocute the labour working. should be got executed under strict supervision of Similarly when concreting is in an experienced Foreman or a Supervisor. progress the punctured cable may prone to be fatal to the labour. 18 Electric Connections/Cables etc. – The Electric wires should be maintained by an Temporary Electric lines near damp electrician who should regularly check up the walls, near joinery stretched on a insulation of wires especially placed near steel considerable length – There is every items & damp areas. chance that the wire may get cut due The temporary wiring should be supported to usage and may develop short properly. circuits/leakages etc. and may electrocute the person touching the As far as possible a good quality wire should be wire accidentally. used which may not get damaged easily. 19 Electric and gas welding work – All wiring works to be inspected by experienced Drilling, polishing work – Done by electrician. All wires to be properly insulated and temporary cables used on a number fixed at height on temporary poles. No welding of works – Due to the fact that the work should be permitted near damp area. The wires are old & when they come in welders to be provided with welder's goggles & contact with water even in the gloves. As far as possible machine in good process of curing the surrounding condition should be used. area may get affected due to leakage in the electric current thus causing damage to the workers & supervision staff. 20 Construction Machinery & Lifts – The Mixers with hopper should be operated by an Concrete Mixers – Safety experienced mixer operator and such mixers precautions. A mixer with hopper should not be allowed to be handled by a helper or tried to be operated by a helper a labour. could not release brake in time thus causing injury to the person near hopper- sometimes fatal one. Revision Level: R2 September, 2014 Page 96 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Sl Stage and Nature of Construction Safety measures expected to be taken by the No. Hazard Contractors and Site Engineers 21 Construction Machinery & Lifts - (1) A brick protection wall of minimum 1.00 m Lifts - Safety precautions. height should be constructed around the Lift Pit, thus, preventing the children going near the pit. A (1) The lift pit if left unguarded the special care should be taken to see that the children of workers may fall in the children are not allowed to come near the pit resulting in fatal accident machinery. (2) The manually operated brakes of (2) The condition of the lift must be maintained the lift failed or the properly. The lift operator should be well trained. communication between the The labour receiving the bucket at top should be labour at the top and the liftman smart and active enough to convey the message of failed and thus, the lift was not stopping & releasing the lift-to-lift operator controlled and resulted in fatal properly. accident. 22 Water Storage Tank for general use The water tanks constructed on site should be & curing - chances of children of protected by at least 1.00 m high walls on four workers falling in the tank with fatal sides, so that the children do not fall. accident. 23 Misuse of lift by labour and No person should be allowed to go to upper floors sometimes supervision staff The by lifts that are mainly meant for conveying the lifts that are meant for lifting building materials. Fatal accidents have taken materials used by labour to go to place due to above action of workers. upper floors – The labour thus travelling many a times get injured. 24 Site Cleaning–Cleaning top floors of This dangerous practice should not be allowed at buildings – Upper portion of any all. The materials should be brought to the ground structure – Throwing waste with the help of lift or the use of rope over pulley materials broken concrete pieces, with a bucket, thus bringing down materials brick bats, sand etc. straightway safely. from top to ground injuring person below or even a passerby. 25 Bar bending work-Helpers of bar This is a very bad practice. The helpers should benders to follow short cut method, bring the rods to ground with the help of lift or throw surplus steel pieces from top rope & pulley. floors to ground and may cause fatal injuries. Revision Level: R2 September, 2014 Page 97 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division ANNEXURE 3.10 GUIDELINES FOR PREPARATION OF TRAFFIC MANAGEMENT PLAN The Contractor shall at all times carry out work on the road in manner creating least interference to the flow of traffic with the satisfactory execution. For all works involving improvements to the existing state highway, the Contractor shall, in accordance with the directives of the CSC, provide and maintain, during execution of the work, a passage for traffic either along a part of the existing carriageway under improvement, or along a temporary diversion constructed close to the state highway. The Contractor shall take prior approval of the CSC regarding traffic arrangements during construction. A. ENSURING TRAFFIC SAFETY AND CONTROL Where subject to the approval of the Engineer the execution of the works requires temporary closure of road traffic use, the Contractor shall provide and maintain temporary traffic diversions. The diversions shall generally consist of 200 mm thickness of gravel 4.5 meters wide laid directly upon natural ground and where any additional earthworks are required for this purpose that will be provided under the appropriate payment items. Where the execution of the works requires single-lane operation on public road, the Contractor shall provide and maintain all necessary barriers, warning signs and traffic control signals to the approval of the Engineer. With the exception of temporary traffic arrangements or diversions required within the first 4 weeks of the Contract, the Contractor shall submit details of his proposals to the Engineer for approval no less than 4 weeks prior to the temporary arrangement or diversion being required. Details of temporary arrangements or diversions for approval as soon possible after the date of the Letter of Acceptance. The colour, configuration, size and location of all traffic signs shall be in accordance with the code of practice for road sign. In the absence of any detail or for any missing details, the signs shall be provided as directed by the Engineer (CSC). The Contractor shall take all necessary measures for the safety of traffic during construction and provide, erect and maintain such barricades, including signs, marking, flags, lights and flagmen as may be required by the Engineer for the formation and protection of traffic approaching or passing through the section of the road under improvement. Before taking up any construction, an agreed phased programme for the diversion of traffic or closer of traffic on the road shall be drawn up in consultation with the SE. At the points where traffic is to deviate from its normal path (whether on temporary diversion or part width of the Carriageway) the lane width path for traffic shall be clearly marked with the aid of pavement markings, painted drums or a similar device to the directions of the SE. At night, the passage shall be delineated with lanterns or other suitable light source. One-way traffic operation shall be established whenever the traffic is to be passed over part of the carriageway inadequate for two-lane traffic. This shall be done with the help of temporary traffic signals or flagmen kept positioned on opposite sides during all hours. For regulation of traffic, the flagmen shall be equipped with red and green flags and lanterns/lights. Revision Level: R2 September, 2014 Page 98 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division On both sides, suitable regulatory / warnings signs as approved by the SE shall be installed for the guidance of road users. On each approach, at least two signs shall be put up, one close to the point where transition of carriageway begins and the other 120 m away. The signs shall be of design and of reflectory type, if so directed by SE. Upon completion of the works for which the temporary traffic arrangements or diversions have been made, the Contractor shall remove all temporary installations and signs and reinstate all affected roads and other structures or installations to the conditions that existed before the work started, as directed by the Engineer. B. MAINTENANCE OF DIVERSIONS AND TRAFFIC CONTROL DEVICES Signs, lights, barriers and other traffic control devices, as well as the riding surface of diversion shall be maintained in a satisfactory condition till such time they are required as directed by the SE. The temporary traveled way shall be kept free of dust by frequent applications of water, if necessary. The signages and devices required includes the following: ˜ Barricading ˜ Men at work ˜ Keep Left ˜ Go slow ˜ Flag men ˜ Narrow signs ˜ Lantern(Amber Blinker) ˜ Traffic control Lights ˜ Cones Safety jackets and helmets should be provided to all the workers/ Engineers working on the road.Fixed mobile solid barricades must be placed between the workmen and traffic or pedestrian and traffic. All the safety signs should be according to IRC: 67 and IRC: SP: 55: 2001 Examples of some good practice in traffic control during construction are shown in the figures below. Revision Level: R2 September, 2014 Page 99 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Revision Level: R2 September, 2014 Page 100 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Assessment Report Document Ref: RITES/UE/2553-61/EMP Highway Division Revision Level: R2 September, 2014 Page 101 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.11: GUIDELINES FOR STORAGE, HANDLING, USE AND EMERGENCY RESPONSE FOR HAZARDOUS SUBSTANCES A1. REFUELING/MAINTENANCE PROCEDURE • There will be no storage of fuel, oil or fluids within 100m (or 50m) of the permanent water line. • Prior to re-fueling or maintenance, drip pans and containment pans will be placed under the equipment. Absorbent blankets may also be required to be placed under the equipment and hoses where there is a possibility of spillage to occur. • All used oils or fluids will be properly contained and transported to appropriately licensed (authorized) disposal facilities; • Following re-fueling and maintenance, the absorbent blankets (if any) and spill pans will be picked up and the fuel truck or container moved outside of the 100m (or 50m) wide area. Emergency Spill Procedure Should a spill occur, either though spillage or equipment failure, the applicable emergency spill procedure outlined in sections A-2 to A-4 must followed. A2. SPILL PROCEDURE (INSIDE THE STREAM) In the case of a spill, overflow or release fluid into the stream waterway (whether water is flowing during the spill or not), do what is practical and safely possible to control the situation, then get help. • Stop the flow o Stop the release into the stream waterway o Shutdown equipment o Close valves and pumps o Plug hoses • Remove Ignition Sources o Shut off vehicles and other engines o Do not allow tiger torches, vehicles, smoking or other sources of ignition near the area. Keep a fire extinguisher on hand but keep it a safe distance away from the potential ignition source (if a fire starts, the extinguisher must be easily accessible). • Contract the environmental Officer and initiate Emergency Response o Notify the site supervisor and the Contractor’s Environmental Officer as soon as possible o The Environmental Officer will review the situation and decide if Emergency Services like Fire Brigade are required o Appropriate parties to be notified of the spill are • The contractor’s Project Manager Revision Level: R2 September, 2014 Page 102 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division • The Engineer through his designated Environmental Officer • The Client • Regulatory Agencies like Pollution Control Board, Municipal Authorities, as applicable. • Site Safety Officer • Cleanup and Disposal o Emergency Services will be engaged for the containment, cleanup and disposal of contamination release into the environment • Reporting o The contractor’s Environmental Officer will document the event and submit reports to the EO/Engineer, the Client and appropriate regulatory agencies like the Pollution Control Board (s). • Procedure Review o The Engineer will review the report, determine if changes are required to procedures and recommend implementation of all required changes…. A3. SPILL PROCEDURE (ON LAND) In the case of a spill, overflow or release fluid onto land, do what is practical and safety possible to control the situation, and then get help. • Stop the flow o Stop the release into the water body o Shut down equipment o Close valves and pumps o Plug hoses • Remove Ignition Sources o Shut off vehicles and other engines o Do not allow tiger torches, vehicles, smoking or other sources of ignition near the area. Keep a fire extinguisher on hand but keep it a safe distance away from the potential ignition sources (if a fire starts the extinguisher must be easily accessible). • Contain the Spill o Dike around the spill to contain the material o Spread absorbent or place a spill blanket on the spill o Enlist the help of personnel on site o Notify your supervisor as soon as possible • Notification o Appropriate parties to be notified of the spill are: • The Contractor’s Project Manager Revision Level: R2 September, 2014 Page 103 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division • The Engineer through his designated Environmental Officer • The Client • Regulatory Agencies like Pollution Control Board, Municipal Authorities, as applicable • Site Safety Coordinator • Cleanup and Disposal o The Engineer’s Environmental Officer will ensure that a proper cleanup and disposal method is determined. • Reporting o The Contractor’s Environmental Officer will document the event and submit reports to the Engineer, the Client and appropriate regulatory agencies like the Pollution Control Board (s). • Procedure Review o The Engineer will review the report, determine if changes are required to procedures are recommend implementation of all required changes. A4. SPILL PROCEDURE (WITHIN PONDS) In the case of a spill, overflow or release fluid due to equipment or hose failure, do what is practical and safely possible to control the situation, then get help • Stop the flow o Stop the release o Shut down equipment o Close valves and pumps o Plug hoses • Remove Ignition Sources o Shut off vehicles and other engines o Do not allow tiger torches, vehicles, smoking or other sources of ignition near the area. Keep a fire extinguisher on hand but keep it a safe distance away from the potential ignition sources (if a fire starts the extinguisher must be easily accessible). • Contain the Spill o Stop any pumps that may be moving the water from the area where the spill occurred o Enlist the help of personnel on site o Notify your supervisor as soon as possible • Notification o Appropriate parties to be notified or the spill are: • The Contractor’s Project Manager Revision Level: R2 September, 2014 Page 104 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division • The Engineer through his designated Environmental Officer • The Client • Regulatory Agencies like Pollution Control Board, Municipal Authorities, as applicable • Site Safety Coordinator • Cleanup and Disposal o The Engineer’s Environmental Officer will ensure that a proper cleanup and disposal method is determined. Absorbent pads will soak up the spilled material. The pads will be contained and removed from site for disposal at a licensed (authorized) facility. • Reporting o The Contractor’s Environmental Officer will document the event and submit reports to the Engineer, the Client and appropriate regulatory agencies like the Pollution Control Board (s) • Procedure Review o The Engineer will review the report, determine if changes are required to procedures and recommend implementation of all required changes. Revision Level: R2 September, 2014 Page 105 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE3.12: GUIDELINES FOR SITE CLEARANCE AND TREE FELLING 1. VEGETATION CLEARANCE Vegetation clearance shall comprise uprooting of vegetation, grass, brushwood, shrubs, stumps, trees and saplings of girth upto 30 cm. measured at a height of one meter above the ground level. Where only clearance of grass is involved it shall be measured and paid for separately. The procedure/ steps involved for uprooting, skating and felling trees are described below. 1.1 Uprooting of Vegetation • The roots of trees and saplings shall be removed to a depth of 60 cm. Below ground level or 30 cm. below formation level or 15 cm below sub grade level, whichever is lower. • All holes or hollows formed due to removal of roots shall be filled up with earth rammed and levelled. • Trees, shrubs, poles, fences, signs, monuments, pipe lines, cables etc. within or adjacent to the area, which are not required to be disturbed during vegetation clearance shall be properly protected by the contractor at his own cost. Staking and Disposal • All useful materials obtained from clearing and grubbing operation shall be staked in the manner as directed by the Engineer. • Trunks and branches of trees shall be cleared of limbs and tops stacked properly at the places indicated by the Engineer- in – charge. These materials shall be the property of the Government. • All unserviceable materials are disposed off in such a manner that there is no livelihood of getting mixed up with the materials meant for construction. 6.3.1.1.1.1.1.1.1 Felling Trees • Markingoftress: Trees, above 30 cm girth (measured at a height of one meter above ground level) to be cut, shall be approved by the Engineer-in-charge and then marked at the site. • Felling of trees: Felling of trees shall include taking out roots up to 60 cm. below ground level or 30 cm. below formation level or 15 cm. below sub-grade level, whichever is lower. • Filling: All excavations below general ground level arising out of removal of trees, stumps etc. shall be filled with suitable material in 20 cm. layers and compacted thoroughly so that the surface at these points conforms to the surrounding area. • Sizing: The trunks and branches of trees shall be cleared of limbs and tops and cut into suitable pieces as directed by the Engineer-in-charge. • Staking: The serviceable materials shall be staked in the manner as directed by the Environmental specialist of Supervision Consultants/Engineer-in-charge. Revision Level: R2 September, 2014 Page 106 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division • Disposal: The material, which cannot be used or auctioned shall be removed from the area and disposed off as per the directions of the Engineer-in-charge. Unsuitable waste materials should not get mixed with construction material during disposal. ANNEXURE3.13: GUIDELINES FOR SOIL EROSION AND SEDIMENTATION CONTROL All materials shall meet commercial grade standards and shall be approved by the Engineer before being used in the work. CONSTRUCTION STAGE Prior to the start of the relevant construction, the Contractor shall submit to the Engineer for approval, his schedules for carrying out temporary and permanent erosion/sedimentation control works as are applicable for the items of clearing and grubbing, roadway and drainage excavation, embankment/sub-grade construction, bridges and other structures across water courses, pavement courses and shoulders. He shall also submit for approval his proposed method of erosion/sedimentation control on service road and borrow pits and his plan for disposal of waste materials. Work shall not be started until the erosion/sedimentation control schedules and methods of operations for the applicable construction have been approved by the Engineer. The surface area of erodible earth material exposed by clearing and grubbing, excavation, borrow and fill operations shall be limited to the extent practicable. The Contractor may be directed to provide immediate control measures to prevent soil erosion and sedimentation that will adversely affect construction operations, damage adjacent properties, or cause contamination of nearby streams or other watercourses. Such work may involve the construction of temporary berms, dikes, sediment basins, slope drains and use of temporary mulches, fabrics, mats, seeding, or other control devices or methods as necessary to control erosion and sedimentation. The Contractor shall be required to incorporate all permanent erosion and sedimentation control features into the project at the earliest practicable time as outlined in his accepted schedule to minimize the need for temporary erosion and sedimentation control measures. Temporary erosion/sedimentation and pollution control measures will be used to control the phenomenon of erosion, sedimentation and pollution that may develop during normal construction practices, but may neither be foreseen during design stage nor associated with permanent control features on the Project. Where erosion or sedimentation is likely to be a problem, clearing and grubbing operations should be so scheduled and performed that grading operations and permanent erosion or sedimentation control features can follow immediately thereafter if the project conditions permit; otherwise temporary erosion or sedimentation control measures may be required between successive construction stages. Under no conditions shall a large surface area of credible earth material be exposed at one time by clearing and grubbing or excavation without prior approval of the EO/Engineer. The Engineer may limit the area of excavation, borrow and embankment operations in progress, commensurate with the Contractor's capability and progress in keeping the finish grading, Revision Level: R2 September, 2014 Page 107 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division mulching, seeding and other such permanent erosion, sedimentation and pollution control measures, in accordance with the accepted schedule. Temporary erosion is sometimes caused due to the Contractor's negligence, carelessness or failure to install permanent controls. Sedimentation and pollution control measures then become necessary as a part of the work as scheduled or ordered by the Engineer, and these shall be carried out at the Contractor's own expense. Temporary erosion, sedimentation and pollution control work required, which is not attributed to the Contractor's negligence, carelessness or failure to install permanent controls, will be performed as ordered by the EO/Engineer. Temporary erosion, sedimentation and pollution control may include construction work outside the right of way where such work is necessary as a result of road construction such as borrow pit operations, service roads and equipment storage sites. The temporary erosion, sedimentation and pollution control features installed by the Contractor shall be maintained by him till these are needed, unless otherwise agreed by the Engineer. Revision Level: R2 September, 2014 Page 108 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE3.14: GUIDELINES FOR ARRANGEMENT WITH FOREST DEPARTMENT REGULATORY FRAMEWORK • The TNRSP under the provisions of the Forest (Conservation) Act, 1980 will submit a diversion proposal in the prescribed format through the State Forest Department to the concerned Regional Office of the Ministry of Environment and Forests, of the Govt. of India. The Regional Office is the competent authority to dispose of such proposal irrespective of the area involved. In line with current directives for every tree cut at least ten trees have to be planted. • Forest Department of the Government of TN after having identified the lands on the embankment and toes of the road will delineate the proposed area of compensatory afforestation on a suitable map. The Department of Forest will thereafter prepare an afforestation scheme providing therein the details of work schedule, the cost structure and proposed monitoring mechanism. FUNDING MECHANISM • The Ministry of Environment and Forests have constituted an authority known as Compensatory Afforestation Fund Management and Planning Authority, CAMPA for the purpose of management of money received from user agencies for compensatory afforestation. The TNRSP being the user agency in this project will be required to deposit the money as estimated by the State Forest Department to the CAMPA. • CAMPA shall release funds to the State in predetermined instalments through the State Level Management Committee as per the Annual Plan of Operations drawn by the State Forest Department MANAGEMENT AND MONITORING • Strip plantations should be properly fenced to prevent damages by biotic interference. • Wherever possible live- hedges may be provided; in such stretches live-hedges need be grown a year ahead of actual planting; such hedges may be reinforced by weaving with split bamboos. • It may also be explored as to whether communities along the roads can be involved in protection and maintenance of such plantations through a mechanism of sharing of usufructs. Revision Level: R2 September, 2014 Page 109 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.15: GUIDELINES FOR SELECTION OF TREE SPECIES 1. TREES TO BE AVOIDED: S Trees Name Characteristics No. 1 Eucalyptus (all All these tree species have very weak wood and species), Millenglonia consequently break easily in windstorm. After a Hortensis, Eugenia heavy storm, roads become blocked and traffic is jambolana, Albizzia stopped for a considerable length of time. During a lebbek, storm, these trees are threats to vehicles plying and Cassia siamca and pedestrians on the road. Besides the eucalyptus has a Ficus (all species). few other negative environmental impacts. 2 Acacia arabica, Acacia They are thorny trees to be avoided close to urban Modesta and Zizyphus stretches. Their thorns are nuisances for the Jujuba, etc pneumatic tyres of small vehicles. 3 Ficus bengalensis The Ficus species are of tap root system but flowing type (average depth of root system is 1.5m). Therefore, these, when mature, may overturn in strong-wind, storm, etc. Even the existing trees may be recommended for removal from safety points of view 2. TREES TO BE SELECTED: S Trees Name Characteristics No. 1 Azardiracta indica The leaves, barks are used for medicinal purposes, (Neem) and the seeds yield valuable oil. It can grow on alkaline usar soil 2 Maduca indica The fruit is edible and seeds yields oil. It is also (Mahua) ornamental 3 Tamarindus indica A beautiful tree, which stands the dust of roads very (Imli) well. Its fruit and timber are also valuable; suitable for dry area 4 Dalbergia sisoo Yields excellent timber (Shisham) 5 Mangifera indica Yield valuable fruit (Mango) 6 Safed siris A quick growing beautiful tree. Because of the light yellow colour of the trunk, it reflects even weak light. This is an excellent roadside tree. 3. DUST RESISTANCE: S No. Species 1 Ficus bengalensis 2 Ficus religiosa Revision Level: R2 September, 2014 Page 110 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S No. Species 3 Magnifera indica 4 Anthocephalus 5 Lagerstroemia 6 Polyalthia longifolia 7 Tectona grandis 8 Terminalia arjuna 9 Bauhinea variegata 4. POLLUTION RESISTANCE: S Species 1 Albizzia lebbek 2 Cassia Fistula 3 Ficus glomerata 4 Anthocephalus indicus 5 Polyalthis longifolia 6 Eucalyptus sp. Revision Level: R2 September, 2014 Page 111 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE3.16: GUIDELINE FOR ENVIRONMENT FRIENDLY CONSTRUCTION METHODOLOGY The contractor shall be deemed to have acquainted himself with the requirements of all the current statutes, ordinances, by-laws, rules and regulations or their instruments having the force of law including without limitation those relating to protection of the environment, health and safety, importation of labour, demolition of houses, protection of environment and procurement, transportation, storage and use of explosives, etc. 1. PROTECTION OF ENVIRONMENT (i) The contractor will take all necessary measures and precautions and ensure that the execution of the works and all associated operations on site or offsite are carried out in conformity with statutory and regulatory environmental requirements including those prescribed in EMP. (ii) The contractor will take all measures and precautions to avoid any nuisance or disturbance to inhabitants arising from the execution of works. (iii) All liquid waste products arising on the sites will be collected and disposed of at a location on or off the sites and in a manner that will not cause either nuisance or pollution. (iv) The contractor will at all times ensure that all existing water courses and drains within and adjacent to the site are kept safe and free from any contamination. (v) The contractor will submit details of his temporary drainage work system (including all surface channels, sediment traps, washing basins and discharge pits) to the Project Implementation Unit –TNRSP / Environment Officer for approval prior to commencing work on its construction. (vi) The contractor will arrange all the equipment in good condition to minimize dust, gaseous or other air-borne emissions and carry out the works in such a manner as to minimize adverse impact on air. (vii) Any vehicle with an open load-carrying area used for transporting potentially dust- producing material will have properly fitted side and tailboards. Materials having the potential to produce dust will not be loaded to a level higher than the side and tail boards and will be covered with a clean tarpaulin in good condition. (viii) The contractor will take all necessary measures to ensure that the operation of all mechanical equipment and condition processes on and off the site will not cause any unnecessary or excessive noise, taking into account applicable environmental requirements. (ix) The contractor will take necessary measures to maintain all plant and equipment in good condition. (x) Where the execution of the works requires temporary closure of road to traffic, the contractor will provide and maintain temporary traffic diversions subject to the approval of the EO/Engineer. Revision Level: R2 September, 2014 Page 112 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division (xi) Where the execution of the works requires single-lane operation on public road the contractor will provide and maintain all necessary barriers, warning signs and traffic control signals to the satisfaction of the EO/Engineer. (xii) Wherever traffic diversions, warning signs, traffic control signals, barriers and the like are required, the contractor will install them to the satisfaction of EO/Engineer prior to commencing the work, in that area. (xiii) Contractor will install asphalt plants and other machineries away from the populated areas as per laid down regulations. (xiv) Permit for felling of trees will be obtained from the forest department before the execution of any work. (xv) Trees and plants going to be uprooted will be duly compensated and maintained up to 3 years. (xvi) Mist sprays should be provided at appropriate places for preventing dust pollution during handling and stockpiling of stones and loose earth. (xvii)Over Burden (OB) waste dumps shall be sprayed with water, as they are the major source of air borne particulate matter. (xviii) OB waste dumps shall be reclaimed / afforested to bind the loose soil and to prevent soil erosion. The frequency of sprinkling should be fixed as per the seasonal requirement and in consultation with engineer. (xix) Regular water spraying on haulage roads during transportation of construction material by water sprinklers. The frequency of sprinkling should be fixed as per the seasonal requirements in consultation with engineer. (xx) Transfer point for transporting construction material shall be provided with appropriate hoods/ chutes to prevent dust emissions. (xxi) Dumping of construction material should be from an optimum height (preferably not too high), so as to reduce the dust blow. (xxii) Innovative approaches of using improvised machinery designs, with in-built mechanism to reduce sound emission. (xxiii) Procurement of drill loaders, dumbers and other equipment with noise proof system in operator’s cabin. (xxiv) Confining the equipment with heavy noise emissions in soundproof cabins, so that noise is not transmitted to other areas. (xxv) Regular and proper maintenance of noise generating machinery including the transport vehicles to maintain noise levels. (xxvi) Provisions should be made for noise absorbing pads at foundations of vibrating equipments to reduce noise emissions. 2. QUARRY OPERATIONS The Contractor shall obtain materials from quarries only after the consent of the Forest Department or other concerned authorities and in consultation with the EO/Engineer. The quarry operations shall be undertaken within the purview of the rules and regulations in force Revision Level: R2 September, 2014 Page 113 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division and instructions as mentioned in Appendix 8.3: Guidelines for Quarry Management and Appendix 8.3: Guidelines for Borrow Area Management. 3. PREVENTION OF WATER COURSES FROM SOIL EROSION AND SEDIMENTATION SILTATION The Contractor shall apply following mitigation measures to prevent sedimentation and pollution of watercourses. • To prevent increased siltation, if need be existing bridges maybe widened downstream side of the water body; • Cement and coal ash should be stacked together, fenced by bricks or earth wall, and kept away from water, to prevent leachate formation and contamination of surface and ground water; • During construction silt fencing could be used along the road at all surface water bodies which are directly impacted to prevent sediments from the construction site to enter into the watercourses. 4. POLLUTION FROM HOT-MIX PLANTS AND BATCHING PLANTS Bituminous hot-mix plants and concrete batching plants shall be located sufficiently away from habitation, agricultural operations. The Contractor shall take every precaution to reduce the levels of noise, vibration, dust and emissions from his plants and shall be fully responsible for any claims for damages caused to the owners of property, fields and residents in the vicinity. 5. ARRANGEMENT FOR TRAFFIC DURING CONSTRUCTION The Contractor shall at all times carry out work on the road in a manner creating least interference to the flow of traffic with the satisfactory execution. For all works involving improvements to the existing state highway, the Contractor shall, in accordance with the directives of the SE, provide and maintain, during execution of the work, a passage for traffic either along a part of the existing carriageway under improvement, or along a temporary diversion constructed close to the state highway. The Contractor shall take prior approval of the SE regarding traffic arrangements during construction. 6. TRAFFIC SAFETY AND CONTROL (i) Where subject to the approval of the Engineer the execution of the works requires temporary closure of road to traffic use, the Contractor shall provide and maintain temporary traffic diversions (ii) Where the execution of the works requires single-lane operation on public road, the Contractor shall provide and maintain all necessary barriers, warning signs and traffic control signals to the approval of the Engineer. (iii)With the exception of temporary traffic arrangements or diversions required within the first 4 weeks of the Contract, the Contractor shall submit details of his proposals to the Engineer for approval not less than 4 weeks prior to the temporary arrangement or diversion being required. Details of temporary arrangements or diversions for approval as soon as possible after the date of the Letter of Acceptance. Revision Level: R2 September, 2014 Page 114 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division (iv) The color, configuration, size and location of all traffic signs shall be in accordance with the code of practice for road sign. In the absence of any detail or for any missing details, the signs shall be provided as directed by the Supervising Engineer (SE). (v) The Contractor shall take all necessary measures for the safety of traffic during construction and provide, erect and maintain such barricades, including signs, marking, flags, lights and flagmen as may be required by the Engineer for the information and protection of traffic approaching or passing through the section of the road under improvement. Before taking up any construction, an agreed phased programme for the diversion of traffic or closer of traffic on the road shall be drawn up in consultation with the SE. (vi) At the points where traffic is to deviate from its normal path (whether on temporary diversion or part width of the carriageway) the lane width path for traffic shall be clearly marked with the aid of pavement markings, painted drums or a similar device to the directions of the SE. At night, the passage shall be delineated with lanterns or other suitable light source. (vii) One-way traffic operation shall be established whenever the traffic is to be passed over part of the carriageway inadequate for two-lane traffic. This shall be done with the help of temporary traffic signals or flagmen kept positioned on opposite sides during all hours. For regulation of traffic, the flagmen shall be equipped with red and green flags and lanterns / lights. (viii) On both sides, suitable regulatory / warnings signs as approved by the PIU- TNRSP shall be installed for the guidance of road users. On each approach, at least two signs shall be put up, one close to the point where transition of carriageway begins and the other 120 m away. The signs shall be of design and of reflectory type, if so directed by the Engineer. (ix) Upon completion of the works for which the temporary traffic arrangements or diversions have been made, the Contractor shall remove all temporary installations and signs and reinstate all affected roads and other structures or installations to the conditions that existed before the work started, as directed by the Engineer. 7. HEALTH AND SAFETY The contractor shall take all measures and precautions necessary to ensure the health, safety and welfare of all persons entitled to be on the site. Such precautions shall include those that, in the opinion of the Engineer, are reasonable to prevent unauthorized entry upon the site and to protect members of the public from any activities under the control of the contractor. The contractor’s responsibilities shall include but not be limited to: (i) The provision and maintenance of the Contractor’s Equipment in a safe working condition and the adoption of methods of work that are safe and without risks to the health of any person entitled to be on the site. (ii) The execution of suitable arrangements for ensuring safety and absence of risks to health in connection with the use, handling, storage, transport and disposal of articles and substances, (iii)The provision of lighting, including standby facilities in the event of failure that, in the opinion of the Engineer, is adequate to ensure the safe execution of any works that are to be carried out at right. Revision Level: R2 September, 2014 Page 115 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division (iv) The provision of protective clothing and safety equipment, with such personnel and equipment and such information, instruction, training and supervision as are necessary to ensure the health and safety at work of all persons employed on or entering on the site in connection with the works, including the Engineer’s supervisory staff, all in accordance with the laws. (v) Near towns, villages and all frequented places, trenches and foundation pits shall be securely fenced provided with proper caution signs and marked with lights at night to avoid accidents. Contractor shall take adequate protective measures to see that the excavation operations do not affect or damage adjoining structures. (vi) The contractor shall not use or generate any materials in the works, which are hazardous to the health of persons, animals or vegetation. Where it is necessary to use some substances, which can cause injury to the health of workers, the Contractor shall provide protective clothing or appliances to his workers. (vii) The contractor will take all measures necessary to safeguard the health; safety and welfare of all persons entitled to be on site and will ensure that works are carried out in a safe and efficient manner. (viii) The contractor will provide, and ensure the utilization of appropriate safety equipment for all workmen and staff employed directly or indirectly by the contractor. Such safety equipment will include but not be limited to the safety helmets, goggles and other eye protectors, hearing protectors, safety harnesses, safety equipment for working over water, rescue equipment, fire extinguishers and first-aid equipment. The personnel working at vulnerable locations at site will wear safety helmets and strong footwear. (ix) The contractor will provide an adequate number of latrines and other sanitary arrangements at areas of the site where work is in progress and ensure that they are regularly cleaned and maintained in a hygienic condition. 8. FIRST AID (i) The provision and maintenance of suitably equipped and staffed first aid stations throughout the extent of the works to the satisfaction of the Engineer. The contractor shall allow in his prices and the responsible for the costs of all such site welfare arrangements and requirements. (ii) Injuries might occur during the construction period. It is therefore pertinent to provide first aid facilities for all the construction workers. At construction camps and at all workplaces first aid equipment and nursing staff must be provided. Since many of the workplaces may be far away from regular hospitals, an indoor health unit having one bed facility every 150 workers needs to be provided. (iii)Adequate transport facilities for moving the injured persons to the nearest hospital must also be provided in ready to move condition. (iv) The first-aid units apart from an adequate supply of sterilized dressing material should contain other necessary appliances as per the factory rules. 9. MAINTENANCE (i) All buildings, rooms and equipment and the grounds surrounding them shall be maintained in a clean and operable condition and be protected from rubbish accumulation. Revision Level: R2 September, 2014 Page 116 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division (ii) Each structure made available for occupancy shall be of sound construction, shall assure adequate protection against weather, and shall include essential facilities to permit maintenance in a clean and operable condition.Comfort and safety of occupants shall be provided for by adequate heating, lighting, ventilation or insulation when necessary to reduce excessive heat. (iii)Each structure made available for occupancy shall comply with the requirements of the Uniform Building Code. This shall not apply to tent camps. 10. MAINTENANCE OF DIVERSIONS AND TRAFFIC CONTROL DEVICES Signs, lights, barriers and other traffic control devices, as well as the riding surface of diversion shall be maintained in a satisfactory condition till such time they are required as directed by the EO/Engineer. The temporary traveled way shall be kept free of dust by frequent applications of water, if necessary. Revision Level: R2 September, 2014 Page 117 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.17 REPORTING FORMAT FOR IDENTIFICATION OF CONSTRUCTION CAMP SITE A Project Details Date of reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Site Details 1. Place Name Landmark 2. Name of Panchayat / Revenue Municipality Village 3. Taluk District 4. Nearest Chainage location LHS/ RHS (km) of the project w.r.t. road project road 5. Area of site Current land use 6. Ownership of the Owned / leased Survey no. land 7. If leased / rented, name, address and contact details of owner 8. Distance from any major settlement or village 9. Distance from any major surface water course or body 10. Distance* from ecologically sensitive areas 11. Distance from the Project road 12. Width and type (paved or unpaved) of access road 13. No of trees with girth> 0.3m 14. No of trees to be cut 15. Is top soil conservation required (Yes/ No) (a) Location map List of enclosures: (b) Layout plan (c) Photographs of the site Revision Level: R2 September, 2014 Page 118 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division (d) List of machinery, equipments and vehicles to be used (e) List of schools and hospitals with in 200 m distance from the boundary of the camp C. Submitted by (Environment & Approved / Rejected by Submission Safety Engineer of Contractor) (Environmental Officer of CSC) Details Signature & date Name Designation Remarks by CSC * All distances are to be measured from the boundary of the site. Note: Contractor has to fill and submit this format to the CSC upon identification of each construction camp site. Subsequently, the EO of CSC has to visit the site and approve / reject the site with reasons. The EO of CSC has to give a copy of this format to the contractor after his approval / rejection with remarks. On approval of a site, the Contractor has to prepare the Management and Redevelopment Plan for this site as per the Guidelines given in EMP and submit to CSC for approval. Revision Level: R2 September, 2014 Page 119 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.18REPORTING FORMATS FOR IDENTIFICATION OF LABOUR CAMP SITE A Project Details Date of reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Site Details 1. Place Name Landmark 2. Name of Panchayat / Revenue Municipality Village 3. Taluk District 4. Nearest Chainage (km) location w.r.t. LHS/ RHS of the project road project road 5. Area of site Current land use 6. Ownership of the land Owned / leased Survey no. 7. If leased, name, address and contact details of owner 8. Distance* from any major settlement or village 9. Distance from any major surface water course or body 10. Distance from ecologically sensitive areas 11. Distance from the Project road 12. Width and type of access road 13. No of trees with girth> 0.3m 14. No of trees to be cut 15. Is top soil conservation required (Yes/ No) Location map List of Layout Plan enclosure: Photographs of the site C. Submitted by (Environment & Approved / Rejected by Submission Safety Engineer of Contractor) (Environmental Officer of CSC) Details Revision Level: R2 September, 2014 Page 120 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Signature & date Name Designation Remarks by CSC * All distances are to be measured from the boundary of the site. Note: Contractor has to fill and submit this format to the CSC upon identification of each Labour camp site. Subsequently, the EO of CSC has to visit the site and approve / reject the site with reasons. The EO of CSC has to give a copy of this format to the contractor after his approval / rejection with remarks. On approval of a site, the Contractor has to prepare the Management and Redevelopment Plan for this site as per the Guidelines given in EMP and submit to CSC for approval. Revision Level: R2 September, 2014 Page 121 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.19 REPORTING FORMAT FOR IDENTIFICATION OF QUARRY AND STONE CRUSHER SITE A Project Details Date of reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Site Details 1. Place Name Landmark 2. Name of Panchayat / Revenue Municipality Village 3. Taluk District 4. Nearest Chainage (km) of location w.r.t. LHS/ RHS the project road project road 5. Area of site Current land use 6. Ownership of the land Owned / leased Survey no. 7. If leased, name, address and contact details of owner 8. Type of material available and its quantity 9. Distance* of the site from: (i) any major settlement or village (ii) any major surface water course or body (iii) any bridge, water supply system, infiltration well or pumping installation (iv) any public road (v) ecologically sensitive areas (vi) nearest quarry / stone crusher 10. Distance from project road 11. Width and type of access road 12. No of trees with grid >0.3m 13. No of trees to be cut 14. Is top soil conservation required: Yes/ No 15. Place identified for top soil conservation List of enclosure: (a) Location map (b) Layout plan Revision Level: R2 September, 2014 Page 122 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division (c) Photographs of the site (d) List of schools and hospitals with in 200 m distance from the boundary of the site C. Submitted by (Environment & Approved / Rejected by Submission Safety Engineer of Contractor) (Environmental Officer of Details CSC) Signature & date Name Designation Remarks by CSC * All distances are to be measured from the boundary of the site. Note: Contractor has to fill and submit this format to the CSC upon identification of each quarry and stone crusher site. Subsequently, the EO of CSC has to visit the site and approve / reject the site with reasons. The EO of CSC has to give a copy of this format to the contractor after his approval / rejection with remarks. On approval of a site, the Contractor has to prepare the Management and Redevelopment Plan for this site as per the Guidelines given in EMP and submit to CSC for approval. Revision Level: R2 September, 2014 Page 123 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.20 REPORTING FORMAT FOR IDENTIFICATION OF BORROW AREAS (To be Submitted by Contractor for taking consent for opening of Borrow area) Construction Stage Report: Date ____ Month________ Year_________ Site Layout of Borrow Area and Proposed Borrow Area Redevelopment Plan to be attached with format Format to be submitted before target date as (decided by PIU) for establishing Borrow Areas Borrow Area No. BA Location of Borrow Area (Km______ Package ______) Sl. Remarks by Item Unit Details No SC/EO, if any 1 Details of Borrow Area a Date of Borrow Area becoming operational dd/mm/yy b Current Landuse c Distance from Nearest Settlement Km d No of settlements within 200m of Haul Road No. e No of settlements within 500m of Borrow Area No. f Total Capacity cum g No of Trees with girth more than 0.3 m No. h Length of Haul Road km i Width of Haul road m j Type of Haul Road metal/dir t k Size of Borrow Area sqkm l Area of Borrow Area km x km m Quantity Available cum n Distance of Nearest Water Source Type/Size/Capacity/Present Use/Ownership o Quantity of top soil removed cum p Detail of storage of topsoil q Daily/occasional use of the Borrow Area by the - community, if any r Probable reuse of Borrow pit-ask community - s Drainage channels/slope/characteristics of the area - 2 Enhancement Elements a Quantity of top soil removed sqm b Detail of storage of topsoil sqm c Adjoining land use/Natural elements d Nearby catchment for storing water e Erosion Control Programme f Preventive measures for i Leaching ii Mosquito Breeding Revision Level: R2 September, 2014 Page 124 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Sl. Remarks by Item Unit Details No SC/EO, if any iii Water run-off/contamination iv Any other environmental degradation 3 Details of workforce a Total No of Labourers No. b Total no of Male Workers No. c No of Male Workers below 18 years of age No. d Total No of Female Workers No. e No of Female workers below 18 years of age No. 4 Details of redevelopment, Plan to be enclosed Certified that the furnished information is correct the quality of work is as per good practice and all relevant information as required is attached Project Engineer (Supervision Consultant) (Contractor) Attach Photograph of Proposed Site, Location Map, and Agreement with land owner REHABILITATION PLAN MEASURES LOCATION 1: 4: LOCATION 2: 5: LOCATION 3: 6: REMARKS SUBMITTED CHECKED APPROVED SIGNATURE SIGNATURE ………………….. SIGNATURE ………………… ……………… NAME …………………. NAME ……………………… NAME …………………….. DESIGNATION ………….. CONTRACTOR CONSTRUCTION EXECUTIVE ENGINEER SUPERVISION CONSULTANT Revision Level: R2 September, 2014 Page 125 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.21 REPORTING FORMAT FOR IDENTIFICATION OF DEBRIS DISPOSAL SITE From ________ To _____ (Give chainage and nearest settlements from both ends) Criteria on which information for each site is to be collected Site 1 Site 2 Site 3 Site 4 Area covered (m2) Total Material that can be dumped within the site (m3) Depth to which dumping is feasible (m) Distance of nearest watercourse (m) Nearest Settlement (m) Date/s of Community Consultation/s Whether the community is agreeable to siting of dumping site (Y/N) Date of Permission from Village Council President(VCP) Proposed future use of the Site Selected Site (tick any one column only) Certified that the above information is correct to the best of my knowledge and belief. (Contractor) Verified: Date: Recommendation on the suitability of the site Signed: Date: Name & Designation: Decision Taken (tick one): Approved/Not Approved Signed: Date: Name and Designation of Deciding Authority Enclosure (Tick as appropriate) 1 Maps of each location 2 Photographs a Each dumping location b Each community consultation 3 Photocopies of permissions from VCPs Name and Designation of Verifier: Revision Level: R2 September, 2014 Page 126 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.22 REPORTING FORMAT FOR IDENTIFICATION OF SOURCES OF WATER FOR CONSTRUCTION A Project Details Date of Reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Site Details 1. Place Name Landmark 2. Name of Panchayat / Revenue Municipality Village 3. Taluk District 4. Nearest Chainage (km) location LHS/ RHS of the project road w.r.t. project road 5. Type of water body (River / Canal / lake) 6. Existing users 7. Ownership of the water body 8. Authority responsible for giving permission 9. If private, name, address and contact details of owner 10. Distance from project road 11. Width and type of access road Location map List of enclosure: Photographs of the site Revision Level: R2 September, 2014 Page 127 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division C. Approved / Rejected by Submission Submitted by (Environment & (Environmental Officer of Details Safety Engineer of Contractor) CSC) Signature & date Name Designation Remarks by CSC * All distances are to be measured from the boundary of the site. Ground water should not be used for construction. Note: Contractor has to fill and submit this format to the CSC upon identification of each water source for construction. Subsequently, the EO of CSC has to visit the site and approve / reject the site with reasons. The EO of CSC has to give a copy of this format to the contractor after his approval / rejection with remarks. Revision Level: R2 September, 2014 Page 128 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.23 FORMAT FOR REGISTER OF COMPLAINTS AND its REPORTING A Project Details Information 1. Name of project stretch and road no 2. Name and address of the Contractor 3. Contract date and duration B Details of Complaint Received Site Name Name and address Action taken Sl. Date of Complaint Signature of of person with with date No. Complaint contact details ESE of Contractor 1 2 3 A register in this format shall be maintained at each site office of the contractor. This same format shall be used to compile and report the details of complaints received at all sites to the CSC along with the Monthly Report of the Contractor. The EO of CSC has to give instruction to the Contractor, if any further action has to be taken on any complaint. Revision Level: R2 September, 2014 Page 129 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.24 FORMAT FOR REGISTER OF SITES OPENED AND CLOSED AND IT’S REPORTING A Project Details Information 1. Name of project stretch and road no Name and address of 2. the Contractor Contract date and 3. duration B Site Details Address of Site Name and Issue Date Expiry Site Redevel Signature (Place name, Address of of each Date of Closing opment of ESE of Site Landmark, the List of Clearance each Date Status Contractor Sl. Type of opening Revenue Village, Clearances Clearance Remarks No Site* Date Survey No., Required Panchayat, Taluk and District) 1 * Construction Camp / Labour camp / Quarry Area and Stone Crusher Unit / Borrow Area / Debris Disposal Site / Water Source. A site should be opened only after submitting the Management and Redevelopment Plan prepared as per the Guidelines given in EMP and got it approved by the EO of the CSC. A register in this format (preferably in A3 size paper) should be maintained by the contractor for each road. This same format shall be used to report the details of sites opened and closed to the CSC along with the Monthly Report of the Contractor. The EO of CSC has to give instruction to the contractor if any clearance is pending for any site. Revision Level: R2 September, 2014 Page 130 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.25 CHECKLIST FOR MONITORING OF CONSTRUCTION CAMP MANAGEMENT A Project Details Date of Monitoring: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Construction Camp with sl. no. in Register of Sites B. Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Whether concrete flooring and oil interceptors are provided for hot mix plant area and work shop, vehicle washing and fuel handling area? 2. Are all the first aid facilities provided in the camp? 3. Whether the plant is located in such a way that there are no residences, public institutions or hospital within a radius of 250 M from the centre of the plant? Revision Level: R2 September, 2014 Page 131 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 4. Whether the vehicle movement in and out of the camp is in a controlled manner? 5. Does water in cross drainage channels block? 6. Whether all the plant and machineries are well maintained and regularly serviced? 7. Whether all the drains and channels are covered? 8. Whether a green belt is provided along the periphery of camp? 9. Whether water is stored for dust suppression in the camp? 10. Whether sanitation facilities are provided for male and female? 11. Whether separate garbage bins are provided to collect the garbage? 12. Whether septic tanks with soak pits are provided? 13. Whether the location of soak pit is in such a way that it does not pollute the ground water? 14. Whether a qualified safety officer is appointed for ensuring safety? Revision Level: R2 September, 2014 Page 132 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 15. Whether noise barriers near sensitive receptors are provided? 16. Whether personal protective equipments are provided? 17. Whether warning sign boards are set up at the entrance gate for the public? 18. Whether all applicable clearances are obtained and valid till date? Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for each Construction Camp Quarterly. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Revision Level: R2 September, 2014 Page 133 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.26 CHECKLIST FOR MONITORING OF LABOUR CAMP MANAGEMENT A Project Details Date of Monitoring: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Labour Camp with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's observation Corrective Actions Proposed Remarks No. (Yes / No / Not Applicable) 1. Whether the camps are floored with concrete? 2. Are all the first aid facilities provided in the camp? 3. Whether the camp is located in such a way that there are no residences, public institutions or bio-sensitive area within a radius of 500 M from the camp? Revision Level: R2 September, 2014 Page 134 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 4. Whether the vehicle movement in and out of the camp is in a controlled manner? 5. Whether LPG for cooking is provided? 6. Whether safe drinking water is provided? 7. Whether all the drains and channels are covered? 8. Whether a green belt is provided along the periphery of camp? 9. Whether day care centers are provided with in the camp? 10. Whether sanitation facilities are provided separately for male and female? 11. Whether separate garbage bins are provided to collect the garbage? 12. Whether septic tanks with soak pits are provided? 13. Whether the location of soak pit is in such a way that it does not pollute the ground water? 14. Whether a qualified safety officer is appointed for ensuring safety? Revision Level: R2 September, 2014 Page 135 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 15. Whether proper fencing of the camp is done? 16. Whether the workers are well aware of cleanliness, hygiene, community livings, AIDS etc.? 17. Whether all applicable clearances are obtained and valid till date? Signature of Environment and Safety Engineer (ESE) of the Contractor with Signature of Environmental Officer of the CSC with date date Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for each Labour Camp Quarterly. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Revision Level: R2 September, 2014 Page 136 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.27 CHECKLIST FOR MONITORING OF QUARRY AND STONE CRUSHER MANAGEMENT A Project Details Date of Monitoring: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Quarry & Crusher with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Whether the crusher units and/or other dust- producing units are housed in a building with a wall of minimum 23 cm thickness and with suitable roofing? Revision Level: R2 September, 2014 Page 137 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 2. Whether quarry site is located at a distance of minimum 500 m. from human settlement, railway line, national highway, state highway, eco-sensitive area or district road*? 3. Whether stone quarry is located at a minimum distance of 50mts. from a water body4? 4. Whether the vehicle movement in and out of the camp is in a controlled manner? 5. Whether a dust extraction with collection system is provided in the crusher unit and all transfer points? 6. Whether safe drinking water is provided for the workers? 7. Whether a dust extraction unit with collection system is provided in the crusher unit and all transfer points? 8. Whether a green belt is provided along the periphery of quarry? 9. Whether adequate systems with water spray and sprinkling is provided for dust suppression? 10. Whether the roads inside the crusher premises is tarred or concreted? Revision Level: R2 September, 2014 Page 138 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 11. Whether separate garbage bins are provided to collect the garbage? 12. Whether the crusher, impactor and other connecting unit working time is restricted to day time (6 am to 6 pm)? 13. Whether dust sealing arrangement is provided in the impactor to avoid fugitive emission? 14. Whether the ambient sound level (Leq) at a distance of 1 m away from the boundary of the site is within 55 dB (A)? 15. Whether the occupier is conducting air monitoring on the suggested frequency? 16. Whether contour trenches are made to control soil erosion? 17. Whether workers are properly trained? 18. Whether sign boards of size 6’ x 4’ mentioning the project details and Contractor’s details are placed for public? 19. Whether the stack height of the D.G set is adequate? 20. Whether arrangement made for avoiding fugitive emission from plants/ premises are adequate? Revision Level: R2 September, 2014 Page 139 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 21. Whether natural drainage patterns are kept clear without not alteration or blockage? 22. Whether top soil conservation has been undertaken? 23. Whether all applicable clearances are obtained and valid till date? Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for each Quarry & Crusher Quarterly. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. 4 If this is not possible, given the topographical features of the region, specify the reasons clearly. Revision Level: R2 September, 2014 Page 140 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.28 CHECKLIST FOR MONITORING OF BORROW AREA MANAGEMENT A Project Details Date of Monitoring: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Borrow Area with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Whether the work at night is fully avoided? 2. Whether the approach road to the borrow area well maintained? 3. Whether the necessary traffic sign board is kept to control the traffic flow? Revision Level: R2 September, 2014 Page 141 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 4. Whether any record is kept for the number of trees cut? 5. Whether a record on total quantity of earth evacuated is maintained? 6. Whether all waste materials from the borrow area is properly disposed? 7. Whether the relaying of the preserved top soil is carried out? 8. Whether required signages for the protection of the works or safety and convenience of public provided? 9. Whether effective measures are taken to control nuisance and disturbance arising from the execution work? 10. Whether the excavation is carried out in such a manner that the activity will not damage adjacent properties or cause contamination of nearby stream or other water bodies? 11. Whether the land is leveled after completion of work? 12. Whether the borrow pits are redeveloped? Revision Level: R2 September, 2014 Page 142 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 13. Whether water logging is avoided? 14. Whether arrangements are made for regular sprinkling of water? 15. Whether all applicable clearances are obtained and valid till date? Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for each Borrow Area Quarterly. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Revision Level: R2 September, 2014 Page 143 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.29 CHECKLIST FOR THE MONITORING OF DEBRIS DISPOSAL SITE MANAGEMENT A Project Details Date of Monitoring: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Debris Disposal Site with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Whether the construction operations are carrying out in such a manner that no waste material is dumped or disposed off in an unhealthy manner that causes any environmental hazard? 2. Whether the debris forming work close to the streams and water bodies are generally avoided during the monsoon period? Revision Level: R2 September, 2014 Page 144 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 3. Whether the debris disposal site is at least 200 meter away from the surface water body? 4. Whether the debris disposal site is at least 500 meter away from the ecologically sensitive are, residential area or main road? 5. Whether the debris disposal along the water courses and close to the drainage channels are in such a manner that it do not cause any blockage to the flow of water? 6. Whether the bituminous waste is used as a surfacing material to the access roads to base camps, quarries, borrow area, temporary diversion, haulage routes etc.? 7. Whether the waste disposal details are submitted to the CSC in the prescribed format? 8. Whether the spoils from excavation of the river bed are disposing off at specified area suggested by the engineers? 9. Whether the debris generated due to dismantling of existing permanent structure is reused in the temporary diversion? 10. Whether the preserved topsoil is used for redevelopment of the area? Revision Level: R2 September, 2014 Page 145 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 11. Whether green belt is developed? 12. Whether all applicable clearances are obtained and valid till date? Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for each Debris Disposal Site Quarterly. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Revision Level: R2 September, 2014 Page 146 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.30 CHECK LIST FOR MONITORING OF REDEVELOPMENT OF CONSTRUCTION CAMP SITE A Project Details Date of Monitoring: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Construction Camp with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Are all the temporary structures cleared as per the list in the redevelopment plan? 2. Are all building debris, garbage, night soils and POL waste disposed off safely? 3. Are all disposal pits or trenches filled, disinfected and effectively sealed off? 4. Are the facilities that could be put to re-use maintained well? Revision Level: R2 September, 2014 Page 147 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 5. Are all the spills within the camp site effectively disposed off from the site? 6. All the area within the camp site is leveled and spread over with stored top soil. 7. Has the residual top soil been utilized effectively? 8. Has the entire camp area been made clean and tidy without disturbing the adjacent lands? 9. Are the plantations / green belt along the boundary of the camp maintained well? 10. Are the ‘before’ and ‘after’ scenarios of the site documented through photographs and submitted to CSC? 11 Are the conditions mentioned by the owner in the agreement adhered to? 12. If not, mention the details of the conditions that are not adhered to and further steps to be taken. 13. Can ‘works completion’ certificate be issued to this site? Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Revision Level: R2 September, 2014 Page 148 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for the redevelopment of each Construction Camp Site as and when it is closed. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Revision Level: R2 September, 2014 Page 149 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.31 CHECK LIST FOR MONITORING OF REDEVELOPMENT OF LABOUR CAMP SITE A Project Details Date of Monitoring: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Labour Camp with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Are all the temporary structures cleared as per the list in the redevelopment plan? 2. Are all building debris, garbage, night soils and POL waste disposed off safely? 3. Are all disposal pits or trenches filled, disinfected and effectively sealed off? 4. Are the facilities that could be put to re-use maintained well? Revision Level: R2 September, 2014 Page 150 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 5. Are all the spills within the camp site effectively disposed off from the site? 6. All the area within the camp site is leveled and spread over with stored top soil. 7. Has the residual top soil been utilized effectively? 8. Has the entire camp area been made clean and tidy without disturbing the adjacent lands? 9. Are the plantations / green belt along the boundary of the camp maintained well? 10. Are the ‘before’ and ‘after’ scenarios of the site documented through photographs and submitted to CSC? 11 Are the conditions mentioned by the owner in the agreement adhered to? 12. If not, mention the details of the conditions that are not adhered to and further steps to be taken. 13. Can ‘works completion’ certificate be issued to this site? Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Revision Level: R2 September, 2014 Page 151 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for the redevelopment of each Labour Camp Site as and when it is closed. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. ANNEXURE 3.32 CHECK LIST FOR MONITORING OF REDEVELOPMENT OF QUARRY AND STONE CRUSHER SITE A Project Details Date of Monitoring: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Quarry & Crusher with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Are all the temporary structures cleared as per the list in the redevelopment plan? Revision Level: R2 September, 2014 Page 152 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 2. Are all debris, garbage, night soils and POL waste disposed off safely? 3. Are the facilities that could be put to re-use maintained well? 4. Has the conserved top soil been reused? 5. Are the improvement measures identified in the redevelopment plan implemented? 6. If not, mention the measures yet to be implemented. 7. Has the residual top soil been utilized effectively? 8. Has the entire area been made clean and tidy without disturbing the adjacent lands? 9. Are the plantations / green belt along the boundary of the camp maintained well? 10. Has additional tree plantation been undertaken as mentioned in the re-development plan? 11 Has erosion control measures and slope stabilization measures been undertaken? Revision Level: R2 September, 2014 Page 153 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 12. Whether pits created by blasting are filled with overburden soil. 13. Has the local community been involved in the implementation of redevelopment plan? 14. Are the required photographs submitted to CSC? 15. Are the conditions mentioned by the owner in the agreement adhered to? 16. If not, mention the details of the conditions that are not adhered to and further steps to be taken. 17. Can ‘works completion’ certificate be issued to this site? Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for the redevelopment of each Quarry and Crusher Site as and when it is closed. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Revision Level: R2 September, 2014 Page 154 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.33 CHECK LIST FOR MONITORING OF REDEVELOPMENT OF BORROW AREAS A Project Details Date of Monitoring: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Borrow Area with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Has slope stabilization been undertaken along the edges (if there is a level difference)? 2. Is all the waste material raised from the borrow area disposed ofproperly? 3. Has the preserved top soil been used in redevelopment of site? Revision Level: R2 September, 2014 Page 155 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 4. Has the borrow areas been re-vegetated properly? 5. Is the cross drainage system and the flood water drains managed properly to avoid occurrence of flooding? 6. Are the borrow area pits re-developed? 7. Is the leveling of depression after filling-in of wastes undertaken? 8. Selection of Species as per OSRP Project Guidelines for plantation. 9. Has bund creation and temporary fencing been undertaken? 10. Ponds including creation of new ones and enhancing capacity of existing ones (for irrigation; pissiculture and general uses by people and/or cattle) Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for the redevelopment of each Borrow Area as and when it is closed. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Revision Level: R2 September, 2014 Page 156 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.34 CHECK LIST FOR MONITORING OF REDEVELOPMENT OF DEBRIS DISPOSAL SITE A Project Details Date of Monitoring: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Borrow Area with sl. no. in register of sites B Monitoring Details Sl. Environmental Management Measures CSC's Corrective Actions Proposed Remarks No. observation (Yes / No / Not Applicable) 1. Rehabilitation of the dump site by planting local shrubs and other plant species. 2. Conversion of debris site into farm land, playground, parking area, block plantation area etc. 3. Maintenance of the hydrological flow in the area. Signature of Environment and Safety Engineer (ESE) of the Contractor with date Signature of Environmental Officer of the CSC with date Note: The Environmental Officer of the CSC has to use this format to monitor the implementation of Environmental Management Measures for the redevelopment of each Debris Disposal Site as and when it is closed. Corrective actions with specific timeframe should be proposed for each Environmental Management Measure, which is not implemented satisfactorily. A copy of the filled up format should be given to the ESE of the Contractor. CSC has to attach this format to the Quarterly Report to be submitted to PMU, with details of corrective action taken by the Contractor. Revision Level: R2 September, 2014 Page 157 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.35 REPORTING FORMAT FOR WORK FORCE MANAGEMENT A Project Details Date of Reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Work Site with sl. no. in register of sites B. Status of work force Category of work Work Force left in the SI. force Work force in the Work force added in the reporting month (No.) Total work force in the No. Previous Month (No.) reporting month (No.) reporting month (No.) 1. Unskilled Labourers 2. Skilled labourers 3. Supervisors 4. Engineers 5. Office Staff Revision Level: R2 September, 2014 Page 158 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Sub Total Grand Total C. Categorization of work force Category of work Male Female Employment Status Residential Status SI. force Accommodation No. Status < 18 yrs. > 18 yrs. < 18 yrs. > 18 yrs. Regular Temporary Migrant Local Staying Others in Labour Camp / Quarters 1. Unskilled Labourers 2. Skilled labourers 3. Supervisors 4. Engineers 5. Office Staff Sub Total Grand Total Details of non-working migrated people, living in the Labour Camps / Staff Quarters as part of work force D. family Revision Level: R2 September, 2014 Page 159 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division No. of children (0-6 yrs.) No. of children (7-18 yrs.) No. of adults Male Female Total Male Female Total Male Female Total Grand Total E. Submission Details Submitted by (Environmental & Safety Engineer of Approved by (Environmental Officer of CSC) Contractor) Signature & date Name Designation Remarks by CSC Note: Contractor has to fill and submit this format to the CSC along with the Monthly Report. In addition to that, the Contractor has to maintain the database of work force in the form of a register. An attendance register for the work force should also be maintained by the Contractor. Contractor has to report the details of migrant work force to the nearest police station. The CSC has to visit the sites and verify the details. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 160 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.36 REPORTING FORMAT FOR OCCUPATIONAL HEALTH AND SAFETY MEASURES A Project Details Date of Reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Implementation Status of Health and Safety Measures Sl. Health and Safety Measures Remarks No. Implementation Status (Yes / No) 1 Appointment of qualified Environment and Safety Engineer 2 Approval for Construction Safety Management Plan by the Engineer. 3 Provision for flags and warning lights for potential hazards 4 Provision of adequate staging, form work and access (ladders with handrail) for works at a height of more than 3.0 m Revision Level: R2 September, 2014 Page 161 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 5 Provision of adequate shoring / bracing / barricading / lighting for all deep excavations of more than 3.0 m depth. 6 Provision for sufficient lighting especially for night time work 7 Construction Workers safety - Provision of personnel protective equipments A. Helmets B. Safety Shoe C. Dust masks D. Hand Gloves E. Safety Belts F. Reflective Jackets G. Earplugs for labour 8 Workers engaged in welding work shall be provided with welder protective shields 9 All vehicles are provided with reverse horns. 10 All scaffolds, ladders and other safety devices shall be maintained in as safe and sound condition Revision Level: R2 September, 2014 Page 162 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 11 Regular health checkup for labour/ Contractor's personnel 12 Ensuring the sanitary conditions and all waste disposal procedures & methods in the camps. 13 Provision for insurance coverage to the workers C. Submission Details Submitted by (Environment & Safety Engineer of Contractor) Approved by (Environmental Officer of CSC) Signature & date Name Designation Remarks by CSC Note: Contractor has to fill and submit this format to the CSC along with the Monthly Report. The CSC has to visit the sites and verify the details. Further mitigation measures, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 163 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.37 REPORTING FORMAT FOR TOP SOIL CONSERVATION A Project Details Date of Reporting: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Name of Site with sl. no. in register of sites B Top Soil Conservation Details SI. List of Activities Status (Yes / No) Remarks No. 1. Whether the location was pre-identified? 2. Whether the slope is <1:2? 3. Whether height is less than 2 m? 4. Whether edges of pile are protected by silt fencing? 5. Whether multiple handling is kept to a minimum 6. Whether measures are taken to prevent the loss during rains? Revision Level: R2 September, 2014 Page 164 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 7. Whether any other measures are provided? If yes, What is it? C. Submission Details Submitted by (Environment & Safety Engineer of Contractor) Approved by (Environmental Officer of CSC) Signature & date Name Designation Remarks by CSC Note: Contractor has to fill and submit this format to the CSC along with the Monthly Report. This format is to be filled for each site, after opening the site. The CSC has to visit the sites and verify the details. Further mitigation measures, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 165 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.38 REPORTING FORMAT FOR WATER SPRINKLING FOR DUST SUPPRESSION A Project Details Month and Year of reporting: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project 5. Location of water sprinkling B Water Sprinkling Details Particulars Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 3 1 No. of trips per day Quantity of Water Sprinkled (KLD) Revision Level: R2 September, 2014 Page 166 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division If not sprinkled, reason for the same C. Submission Details Submitted by (Environment & Safety Engineer of Approved by (Environmental Officer of CSC) Contractor) Signature & date Name Designation Remarks by CSC Note: Contractor has to fill this format for each construction site (preferably in A3 size paper) and submit to the CSC along with the Monthly Report. The CSC has to visit the sites and verify the details. Additional water sprinkling, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 167 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.39 REPORTING FORMAT FOR ROAD SAFETY MEASURES DURING CONSTRUCTION A Project Details Date of Reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Details of Safety Measures S.No Safety Measures Compliance Remarks Status (Yes / No) a. General 1 A qualified Environment and Safety Engineer should be appointed 2 A Traffic Management Plan should be prepared in accordance with IRC: SP: 55-2001 and got approved by the Engineer 3 Maintenance of existing road stretches handed over to the Contractor should be carried out b. Details of Construction Zone 1 Length of transition sub zone should be min 50 m for a speed of 50km/hr 2 Length of work sub zone in urban stretch should be<2 km Revision Level: R2 September, 2014 Page 168 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 3 Length of work sub zone in rural stretch should be 5-10 km C Signages in construction zones 1 Sign saying ‘Men at Work’ should be kept 1 km ahead of Transition sub zone 2 Supplementary sign saying Diversion 1 km should be provided 3 Sign saying ‘Road Closed ahead’ should be provided 4 Compulsory Turn Right/Left sign should be provided 5 Detour sign should be placed 6 Sharp Deviation sign should be placed at end of advance warning sub zone 7 Signage should be provided in Transition Sub Work Zone 8 Signage saying ‘Keep Right/Left should be provided 9 Signage should be placed in work sub zone 10 Hazard Marker should be placed where railing for CD structure on diversion starts 11 Barricade should be provided on either side of work sub zone Revision Level: R2 September, 2014 Page 169 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 12 Flag persons should be provided for traffic control 13 Flags and warning lights should be provided at Construction zones 14 Metal drum /empty bitumen drum delineator, painted in circumferential strips of alternate black and white 100mm wide 2 coats fitted with reflectors 3 Nos of 7.5cm diameter or Barricades/caution tapes should be provided in construction zones 15 Plastic crash barriers should be provided 16 Demarcations (fencing, guarding and watching) should be provided at bridge / culvert construction sites 17 Arrangements should be made for controlled access and entry to Construction zones 18 Regular Inspection of Work Zone Traffic Control Devices should be carried out by authorized contractor personnel 19 All vehicles should be provided with reverse horns 20 Speed of construction vehicles should be controlled through road safety training of drivers d. Signage in Termination sub zone Revision Level: R2 September, 2014 Page 170 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 1 Sign for indication of end of work zone should be placed 120m from end of termination sub zone e. Road Delineators 1 Roadway indicators should be provided 2 Hazard markers should be provided 3 Object markers should be provided C. Submission Details Submitted by (Environment & Safety Engineer of Approved by (Environmental Officer of CSC) Contractor) Signature & date Name Designation Remarks by CSC Note: Contractor has to fill this format and submit to the CSC along with the Monthly Report. The CSC has to visit the sites and verify the details. Additional safety measures, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 171 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.40 FORMAT FOR REGISTER OF ACCIDENTS AND its REPORTING A Project Details Date of Reporting: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Details of Accident and People Involved in Accident Name of site where accident happened Name and address of people involved in the accident Whether Contractor’s personnel or General public Details of Injury Details of treatment given Details of compensation given C Type of Accident (√) Fall of person from a height Explosion Slip, trip or fall on same level Fire Struck against fixed objects Contact with hot or corrosive substance Contact with poisonous gas or toxic Struck by flying or falling objects substances. Contact with poisonous gas or toxic Struck by moving objects substances Struck / caught by cable Hand tool accident Stepping on hail etc. Vehicle / Mobile plant accident Handling without machinery Machinery operation accident Crushing / burying Other (please specify) Drowning or asphyxiation Revision Level: R2 September, 2014 Page 172 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division D Agent Involved in Accident (√) Machinery Stair edge Portable power appliance Excavation / underground working Vehicle or associated Ladder equipment /machinery Material being handled, used or Scaffolding /gondola stored Gas, vapor, dust, fume or Construction formwork, shuttering and oxygen false work. Electricity supply cable, wiring Hand tools switchboard and associated equipment Floor edge Nail, sllnter or chipping Floor opening Other (Please specify) Left shaft E Unsafe Action Relevant to the Accident (√) Operating without authority Failure to use proper footwear Failure to secure objects Failure to use eye protector Making safety devices Failure to use respirator inoperative Working on moving or Failure to use proper clothing dangerous equipment Failure to use warn others or given Using un-safety equipment proper signals Adopting unsafe position or Horseplay posture Operating or working at unsafe No unsafe action speed Unsafe loading, Placing, mixing Others (please specify) et Failure to use helmet F Lack of Safety Measures Relevant to the Accident (√) No protective gear Unsafe layout of job, traffic etc. Defective protective gear Unsafe process of job methods Improper dress / footwear Poor housekeeping Improper guarding Lack of warning system Improper ventilation Defective tool, machinery or materials Improper illumination No unsafe condition Revision Level: R2 September, 2014 Page 173 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Improper procedure Others (please specify) G Personal Factor Relevant to the Accident (√) Incorrect attitude /motive No unsafe personal factor. Unsafe act by another person Other (please specify) H Details of Corrective and Preventive action taken 1 2 3 4 I Submission Details Approved by (Environmental Officer of CSC) Submitted by (Environment & Safety Engineer of Contractor) Signature & date Name Designation Remarks by CSC Note: Contractor has to fill this format as and when an accident happens and submit to the CSC along with the Monthly Report. The CSC has to visit the sites and verify the details. Additional safety measures, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 174 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.41 REPORTING FORMAT FOR ENVIRONMENTAL QUALITY MONITORING A Project Details Date of Reporting: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Environmental Monitoring Details Details of SI. Details of Monitoring Period of Details of values exceeding Reasons for pollution Corrective Remarks No Location Monitoring the relevant standards actions taken a. Air Monitoring 1. b. Water Monitoring 1. c. Noise Monitoring* Revision Level: R2 September, 2014 Page 175 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 1. C Submission Details Submitted by (Environment & Safety Engineer of Contractor) Approved by (Environmental Officer of CSC) Signature & date Name Designation Remarks by CSC * Noise monitoring along the road will be done by the CSC, using the Noise Meter of PMU. The CSC has to give the monitoring results to the Contractor for corrective actions, if any, required and including in this report. Note: The Contractor has to conduct Environmental Monitoring through a NABL approved Laboratory as per the Environmental Monitoring Plan given in the EMP, fill this format and submit to the CSC along with the Monthly Report, if monitoring was due in that month. A copy of the monitoring report given by the Laboratory has to be attached to this format. The CSC has to visit the sites and verify the details. Additional mitigation measures, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 176 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.42 REPORTING FORMAT FOR ENHANCEMENT AND MITIGATION OF CULTURAL PROPERTIES A Project Details Date of reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Details of Enhancement and Mitigation of Cultural Properties Sl. Location with % work Remarks and reasons for delay, if any. No. chainage completed C Submission Details Submitted by (Environment & Safety Approved by (Environmental Officer Engineer of Contractor) of CSC) Signature & date Name Designation Remarks by CSC Note: The Contractor has to fill the details of cultural properties for which enhancement and mitigation measures were carried out during the reporting month in this format and submit to the CSC along with the Monthly Report. Overall progress in this activity for the entire project road is to be included in the Monthly Report. The CSC has to visit the sites and verify the details. Additional mitigation measures, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 177 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.43 REPORTING FORMAT FOR NOISE BARRIER CONSTRUCTION A Project Details Date of reporting: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Details of Noise Barriers Constructed Sl. Location with % work Remarks and reasons for delay, if any. No . chainage completed C Submission Details Submitted by (Environment & Approved by (Environmental Safety Engineer of Contractor) Officer of CSC) Signature & date Name Designation Remarks by CSC Note: The Contractor has to fill the details of Noise Barriers constructed during the reporting month in this format and submit to the CSC along with the Monthly Report. Overall progress in this activity for the entire project road is to be included in the Monthly Report. The CSC has to visit the sites and verify the details. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 178 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.44 REPORTING FORMAT FOR ENHANCEMENT MEASURES OTHER THAN CULTURAL PROPERTIES A Project Details Date of reporting: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Details of Enhancement Measures Sl. Location with % work Remarks and reasons for delay, if any. No. chainage completed a Raising embankment height b Public water sources c Bus stops and bus bays Revision Level: R2 September, 2014 Page 179 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division d Water bodies e Auto / Jeep / Taxi stands f Sign Boards g Oxbow land (Type C) development h Any other measures Revision Level: R2 September, 2014 Page 180 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division C Submission Details Submitted by (Environment & Safety Approved by (Environmental Officer Engineer of Contractor) of CSC) Signature & date Name Designation Remarks by CSC Note: The Contractor has to fill the details of enhancement measures carried out for amenities / facilities other than cultural properties during the reporting month in this format and submit to the CSC along with the Monthly Report. Overall progress in this activity for the entire project road is to be included in the Monthly Report. The CSC has to visit the sites and verify the details. Additional mitigation measures, if required, can be suggested by the CSC. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 181 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.45 REPORTING FORMAT FOR TREE PLANTATION A Project Details Date of reporting: Name of project stretch and road 1. no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Details of Trees Planted Location with % work Remarks and reasons for delay, if chainage No. of completed any Sl. Trees to be No. Planted C Submission Details Approved by (Environmental Officer of CSC) Submitted by (Environment & Safety Engineer of Contractor) Signature & date Name Designation Remarks by CSC Note: The Contractor has to fill the details of Trees planted during the reporting month in this format and submit to the CSC along with the Monthly Report. Overall progress in this activity for the entire project road is to be included in the Monthly Report. The CSC has to visit the sites and verify the details. The EO of CSC has to give back a copy of this format to the contractor after his approval with remarks. Revision Level: R2 September, 2014 Page 182 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.46 REPORTING FORMAT FOR MONTHLY REPORT FROM CONTRACTOR TO CSC A Project Details Period of Reporting: 1. Name of project stretch and road no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project B Physical Progress Report Enhancement Physical Units carried Cumulative Measure target over from units (Nos.) previous month Units Units Units completed started in completed in carried over till end of Remarks / reporting reporting to next reporting % target reasons for SI. month month month month completed delay No (a) (b) (c) =(d a+b-c) 1. Noise barrier 2. Hand pumps 3 Bus Shelter 4 Sign Boards 5 Preserving and landscaping culture properties like shrines/hundi Revision Level: R2 September, 2014 Page 183 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division C. Details of Sites for Project Ancillary facilities Sl. No. Type of camp / site Cumulative No No of sites operational Cumulative Cumulative Remarks of sites opened No of sites No of sites redeveloped closed* 1. Construction camp 2. Labour camp 3. Quarry & stone crusher unit 4. Borrow Area 5. Debris disposal site 6. Water sources NA * A site will be considered closed after redeveloping and obtaining closure certificate from CSC. D. Summary of machinery and equipment available SI. Type of equipment / machinery / vehicles Nos. Validity date of PUC Remarks No. available certificate (as applicable) 1. E. Details of lapses and notices Sl. Details of notices issued by CSC Date of Type of lapse Notice No. * Corrective Remarks No. notice (Major / Minor) actions taken *In case of minor lapse, specify whether original notice, first reminder or second reminder. Revision Level: R2 September, 2014 Page 184 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division F. REPORTING FORMATS TO BE ANNEXED WITH THIS MONTHLY REPORT BY THE CONTRACTOR SL. REPORTING FORMAT SL. NO REPORTING FORMAT YES/NO NO. YES/NO 1 Format for Register of sites opened and closed and its 8 Reporting Format for Register of Accidents reporting and it’s Reporting 2 Format for Register of complaints and its reporting 9 Reporting Format for Enhancement and Mitigation of Cultural Properties 3 Reporting Format for Work Force Management 10 Reporting Format for Noise Barrier Construction 4 Reporting Format for Occupational Health and Safety 11 Reporting Format for Enhancement Measures Measures Other than Cultural Properties 5 Reporting Format for Top Soil Conservation 12 Reporting Format for Tree Plantation 6 Reporting Format for Water Sprinkling for Dust Suppression 13 Reporting Format for Environmental Quality Monitoring 7 Reporting Format for Road Safety Measures During - - - Construction G. SUBMITTED BY (ENVIRONMENT & SAFETY APPROVED BY (ENVIRONMENTAL OFFICER OF CSC) SUBMISSION ENGINEER OF CONTRACTOR) DETAILS Signature & date Name Designation Remarks by CSC Revision Level: R2 September, 2014 Page 185 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.47 REPORTING FORMAT FOR MONTHLY REPORT FROM CSC TO PMU A Project Details Period of Reporting: 1. Name of project stretch and link no. 2. Name and address of the Contractor 3. Contract date and duration 4. Status of completion of the project Physical Progress B. Report Sl. No. Enhancement Measure Physical Units carried Units Units Units Cumulative % target Remarks target over from started in completed carried units complete / reasons (Nos.) previous reporting in over to next completed till d for delay month month reporting month end of month reporting month (a) (b) (c) (d=a+b-c) 1. Noise barrier 2. Hand pumps 3. Bus Shelter Revision Level: R2 September, 2014 Page 186 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 4. Sign Boards Sl. No. Enhancement Measure Physical Units carried Units Units Units Cumulative % target Remarks target over from started in completed carried units complete / reasons (Nos.) previous reporting in over to next completed till d for delay month month reporting month end of month reporting month (a) (b) (c) (d=a+b-c) 5. Preserving and landscaping the cultural properties like shrines and hundi 6. Constructing new well 7. providing new water taps 8. Parking space for auto rickshaws, cars and jeep 9. Landscaping of type C oxbow lands 10. Planting trees along road side 11. Planting trees on inner side of sound insulating wall 12. Providing 1.2 m. high fencing under via duct Revision Level: R2 September, 2014 Page 187 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 13. Concrete flooring with slope drains and oil interceptors C. Details of Sites for Project Ancillary facilities Sl. No. Type of camp / site Cumulative No No of sites operational Cumulative Cumulative Remarks of sites opened No of sites No of sites redeveloped closed* 1. Construction camp 2. Labour camp 3. Quarry & stone crusher unit 4. Borrow Area 5. Debris disposal site 6. Water sources NA * A site will be considered closed after redeveloping and obtaining closure certificate from CSC. D. Summary of machinery and equipment available SI. No. Type of equipment / machinery / vehicles Nos. Validity date of PUC Remarks available certificate (as applicable) 1. Revision Level: R2 September, 2014 Page 188 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division E. Details of lapses and notices Sl. No. Details of notices issued by CSC Date of notice Type of lapse Notice Corrective actions Remarks (Major / No. * taken by Minor) Contractor *In case of minor lapse, specify whether original notice, first reminder or second reminder. F. Details of major lapses for which notices were issued during the current reporting month SI. No. List of major lapses Date of issuing notice Whether invoking penalty Remarks clause from next interim payment certificate is recommended? 1. 2. 3. 4. G. Details of minor lapses for which notices were issued during the current reporting month SI. No. List of minor lapses Date of issuing notice Whether invoking Remarks penalty clause from next interim payment certificate is Revision Level: R2 September, 2014 Page 189 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division recommended? Original First Second notice Reminder Reminder 2. 3. 4. 5. 6 7 8 H Reporting / Monitoring formats to be annexed with this monthly report by the CSC Sl. No. Reporting / Monitoring format Yes/No Reporting / Monitoring format Sl. No Yes/N o 1 Format for Register of sites opened and closed and its Checklist For Monitoring Of Construction reporting 14 Camp Management 2 Format for Register of complaints and its reporting Checklist For Monitoring Of Labour 15 Camp Management Revision Level: R2 September, 2014 Page 190 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 3 Reporting Format for Work Force Management Checklist For Monitoring Of Quarry And 16 Stone Crusher Management 4 Reporting Format for Occupational Health and Safety Checklist For Monitoring Of Borrow Area Measures 17 Management 5 Reporting Format for Top Soil Conservation Checklist For The Monitoring Of Debris 18 Disposal Site Management 6 Reporting Format for Water Sprinkling for Dust Suppression Check List For Monitoring Of 19 Redevelopment Of Construction Camp Site 7 Reporting Format for Road Safety Measures During Check List For Monitoring Of Construction 20 Redevelopment Of Labour Camp Site - Reporting Format for Register of Accidents and it’s Reporting Check List For Monitoring Of 8 21 Redevelopment Of Quarry And Stone Crusher Site Reporting Format for Enhancement and Mitigation of Cultural Check List For Monitoring Of 9 Properties 22 Redevelopment Of Borrow Areas Reporting Format for Noise Barrier Construction Check List For Monitoring Of 10 23 Redevelopment Of Debris Disposal Site Reporting Format for Enhancement Measures Other than 11 Cultural Properties Revision Level: R2 September, 2014 Page 191 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Reporting Format for Tree Plantation 12 Reporting Format for Environmental Quality Monitoring 13 I. SUBMITTED BY (Environmental officer of CSC) APPROVED BY (ENVIRONMENTAL Engineer of PMU) SUBMISSION DETAILS Signature & date Name Designation Remarks by PMU Revision Level: R2 September, 2014 Page 192 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.48 LIST OF PERMISSIONS TO BE OBTAINED BY THE CONTRACTOR Sl. Type of Clearance Statutory Applicability Project Stage Responsibility No Authority 1 Consent to Tamil Nadu For operating Construction Contractor Establish under the State hot mix (Prior to work Air (Prevention & Pollution plants, initiation) Control of Control Board crushers and Pollution) Act, construction 1981 and The camps Water (Prevention & Control of Pollution) Act, 1974. 2 Consent to Operate Tamil Nadu For operating Construction Contractor under the Air State hot mix (Prior to work (Prevention & Pollution plants, initiation) Control of Control Board crushers and Pollution) Act, construction 1981 and The camps Water (Prevention & Control of Pollution) Act, 1974. 3 Permission to store Tamil Nadu Storage and Construction Contractor Hazardous State Transportation (Prior to work Materials under Pollution of Hazardous initiation) Hazardous Waste Control Board Materials and (Management and Explosives Handling) Act 1989 4 Explosive license Chief Storage of Construction Contractor under The Controller of explosive (Prior to work Explosives Act (& Explosives, materials initiation) Rules), 1884 petroleum & (revised in 1983) Explosive Safety Organization 5 PUC certificate for Motor Vehicle For all Construction Contractor vehicles for Department of construction (Prior to work construction under Tamil Nadu vehicles initiation) Central Motor and Vehicle Act 1988 6 Quarry lease deeds Mining and Quarrying and Construction Contractor and license under Geology borrowing (Prior to work The Mines Act, Department of operations initiation) 1958 * Tamil Nadu Revision Level: R2 September, 2014 Page 193 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 7 Consent for ground Tamil Nadu Ground water Construction Contractor water extraction Ground Water extraction for (Prior to work Authority construction initiation) camps 8 Consent for Labour Labour Construction Contractor establishment of department of camps (Prior to work labour camp Tamil Nadu initiation) 9 Consent to establish Local Borrow area Construction Contractor borrow area* Penchant / (Prior to work Municipality initiation) Sl. Type of Statutory Applicability Project Stage Responsibility No Clearance Authority 10 Consent to Tamil Nadu For Operation Contractor Operate under the State establishing Air (Prevention Pollution Hot mix & Control of Control plants, Pollution) Act, Board Crushers, 1981 construction camps and batching plants 11 Consent to Tamil Nadu For Operation Contractor Operate under the State discharging Water Pollution of domestic (Prevention & Control waste water Control of Board through soak Pollution) Act, pit 1974 * In the case of quarry, burrow areas and sand mining sites, if the contractor does not owe the sites, the contractor has to ensure that the material is obtained from approved sites as per MoEF guidelines dated 18th May, 2012. Revision Level: R2 September, 2014 Page 194 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.49 SCHEMATIC DIAGRAM OF CATCH DRAIN AND OIL INTERCEPTORS Revision Level: R2 September, 2014 Page 195 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.50 PROPOSED CHAINAGES OF RETAINING WALL LOCATION WHERE EMBANKMENT HEIGHT WILL BE RAISED Chainage Length of raising S. No. Reason for raising From To section (m) Minor Bridge at 7064, Vertical 1 6/900 7/170 270 Geometric Improvement Minor Bridge at 8537, Vertical 2 8/350 8/730 380 Geometric Improvement Vertical Geometric Improvement 3 9/060 9/510 450 due submergence 4 11/950 12/630 680 Vertical Geometric Improvement Minor Bridge at 12461, Vertical 5 12/265 12/578 313 Geometric Improvement 6 21/730 21/870 140 Vertical Geometric Improvement 7 22/860 23/050 190 Vertical Geometric Improvement 8 23/620 23/760 140 Vertical Geometric Improvement Revision Level: R2 September, 2014 Page 196 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.51 SENSITIVE NOISE RECEPTORS :IMPACT, MITIGATION AND ENHANCEMENT Name of Locatio Distance Sl. Chainag Common n (Left / from Impact Mitigation/Enhancement No. e (Km.) Property Right) PCL (m) Existing boundary wall will be raised No and develop as noise barrier. Tree 1 26.675 Health Center Left 13.50 Direc Plantation. Horn prohibited sign post t will be provided Existing boundary wall will be raised No and develop as noise barrier. Tree 2 26.550 School Left 11 Direc Plantation. Horn prohibited sign post t will be provided Existing boundary wall will be raised No and develop as noise barrier. Tree 3 22.350 School Right 8.5 Direc Plantation. Horn prohibited sign post t will be provided Existing boundary wall will be raised No and develop as noise barrier. Tree 4 19.200 School Right 14 Direc Plantation. Horn prohibited sign post t will be provided Existing boundary wall will be raised No and develop as noise barrier. Tree 5 15.000 School Right 14 Direc Plantation. Horn t prohibited sign post will be provided No Tree Plantation. Horn prohibited sign 6 14.900 School Right 11.2 Direc post will be provided t No Tree Plantation. Horn sign post will 7 14.200 College Left 28 Direc be provided t Direc 8 11.675 ITI Right 10.5 Relocation t Shifting of boundary wall and Direc develop as noise barrier. Tree 9 8.045 School Right 4.2 t Plantation. Horn prohibited sign post will be provided Boundary wall will be constructed and develop as noise barrier. Tree 10 7.300 School Left 15.4 Plantation. Horn prohibited sign post will be provided Tree Plantation. Horn prohibited sign 11 3.390 School Left 14 post will be provided Tree Plantation. Horn prohibited sign 12 0.050 School Left 23.8 post will be provided Revision Level: R2 September, 2014 Page 197 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.52 WATER BODIES: IMPACT, MITIGATION AND ENHANCEMENT Distance Chaina Name of Locatio Sl. from ge Common n (Left / Impact Mitigation/Enhancement No. PCL (Km.) Property Right) (m) Tree plantation 1 25.925 Pond Left 7 Direct Impact Retaining wall on road side Water Tree plantation 2 2.700 Left 3.2 Direct Impact Retaining wall on road side logged Tree plantation 3 0.200 Pond Left 5 Direct Impact Retaining wall on road side Revision Level: R2 September, 2014 Page 198 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.53SCHEDULE AND SPECIFICATION FOR MITIGATION AND ENHANCEMENT MEASURES S Location (Chainage in Side Breadth (m) Height (m) Materials to be used Typical No. km) (LHS/RHS) Length(m) (Specification) Drawing (refer Drawing No.) Community Properties (Water Bodies) 1 25.925 Left 39 0.6 3 Reinforced Cement Concrete 2 2.7 Left 40 0.6 3 4 0.2 Left 82 0.6 3 5 Desilting of pond is done to enhance the capacity of the pond as a part of environmental enhancement measures 6 Plantation of 63 trees is proposed along the peripheri of pond as a environmental mitigation and enhancement measures Community Properties (School/hospital etc) 7 25.675 Left 7 0.23 1.2 Brickworks Refer Figure 8 26.65 Left 28.5 0.23 0.3 8.4 of Chapter 8 of EA Report 9 22.35 Right 18 0.23 0.3 10 19.2 Right 32.5 0.23 0.3 11 15 Right 80 0.23 0.3 12 8.045 Right 31.5 0.23 1.5 13 7.3 Left 29.4 0.23 1.5 Revision Level: R2 September, 2014 Page 199 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S Location (Chainage in Side Breadth (m) Height (m) Materials to be used Typical No. km) (LHS/RHS) Length(m) (Specification) Drawing (refer Drawing No.) 14 Plantation of 154 trees is proposed along the boundary wall as noise barrier as a environmental mitigation and enhancement measures 15 8.045 Right 40 rm Demolition of boundary wall 16 8.045 Right 1 Nos Gate 17 7.3 Left 1 Nos Gate Community Structures i.e. Temples etc. 18 26.4 Right 14.4 0.2 1.5 Brickworks Refer Figure 19 25.9 Left 15 0.2 1.5 8.4 of Chapter 8 of EA report 20 23.858 Right 10.5 0.2 1.5 21 10.8 Right 19.5 0.2 1.5 22 0.125 Left 31.5 0.2 1.5 23 Plantation of 31 trees is proposed along the boundary wall as noise barrier as a environmental mitigation and enhancement measures 24 26.4 Right 14.4 rm Demolition of temple wall 25 26.4 Right 2 Nos Seating Bench 26 25.9 Left 17 rm Demolition of boundary wall Revision Level: R2 September, 2014 Page 200 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S Location (Chainage in Side Breadth (m) Height (m) Materials to be used Typical No. km) (LHS/RHS) Length(m) (Specification) Drawing (refer Drawing No.) 27 25.9 Left 2 Nos Seating Bench 28 25.9 Left 1 Nos Gate 29 24.4 Right 3.5 rm Demolition of platform 30 24.4 Right 1 Nos Beating Bench 31 23.858 Right 12.5 rm Demolition of boundary wall 32 23.858 Right 1 Nos Seating bench 33 23.858 Right 1 Nos Gate 34 22.675 Right 1 Nos Demolition of mandapam 35 22.675 Right 1 Nos Seating Bench 36 17.6 Right 3.5 rm Demolition of platform 37 17.6 Right 1 Nos Seating Bench 38 13.3 Right 1 Nos Demolition of porch 39 13.3 Right 1 Nos Seating Bench 40 10.8 Right 19.5 rm Demolition of boundary wall 41 10.8 Right 2 Nos Seating Bench 42 10.8 Right 1 Nos Gate 43 3.3 Right 1 Nos Demolition of porch 44 2.7 Right 1 Nos Demolition of porch 45 2.7 Right 1 Nos Seating Bench 46 0.125 Left 33.5 rm Demolition of boundary wall 47 0.125 Left 1 Nos Seating Bench 48 0.125 Left 1 Nos Gate Revision Level: R2 September, 2014 Page 201 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S Location (Chainage in Side Breadth (m) Height (m) Materials to be used Typical No. km) (LHS/RHS) Length(m) (Specification) Drawing (refer Drawing No.) Environmental Monitoring during Construction 49 50 Air Quality Location 4 Nos 24 Hourly monitoring once in season for three seasons 51 Noise Quality Location 4 Nos 24 Hourly monitoring once in season for three seasons 52 Water Quality Location 2 Nos Water Quality monitoring once in a season for three seasons 53 Soil Quality Location 2 Nos Water Quality monitoring once in a season for three seasons Environmental Monitoring during Operation 54 Air Quality Location 3 Nos 24 Hourly monitoring once in season for three seasons for two years 55 Noise Quality Location 3 Nos 24 Hourly monitoring once in season for three seasons for two years 56 Water Quality Location 2 Nos Water Quality monitoring once in a season for three seasons for two years 57 Soil Quality Location 2 Nos Water Quality monitoring once in a season for three seasons for two years Compensatory Plantation Revision Level: R2 September, 2014 Page 202 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S Location (Chainage in Side Breadth (m) Height (m) Materials to be used Typical No. km) (LHS/RHS) Length(m) (Specification) Drawing (refer Drawing No.) 58 Avenue 12920 Nos Compensatory plantation and Plantation maintenance of sampling of 3 years Other Items 59 Oil Interceptor 1 Nos Brickworks Refer Figure 8.1 of Chapter 8 of EA Report 60 Silt fencing 461 rm Brickworks Refer Figure 8.3 of Chapter 8 of EA Report Revision Level: R2 September, 2014 Page 203 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.54 TREE PLANTING AND ENVIRONMENTAL ENHANCEMENT PLAN TREE REMOVAL FROM THE AVAILABLE CORRIDOR OF THE ROAD The road widening under the Tamil Nadu Road Sector Project (TNRSP) will necessitate removal of large number of trees from the roadsides. The details of the tree removal for SH 58 are described in Annexure 4.3 of EA report. ROAD SIDE AVENUE PLANTATION In the TNRSP project corridors, there is almost continuous avenue plantation. The trees within the available corridors are surveyed and tabulated in Annexure 4.3 of EA report. The common tree species found along the SH 58 are Banyan trees, Tamarind, Jamun, Gulmohar, Palm, Coconut, Peepal etc. The total number of trees to be removed from SH 58 is estimated as 1292 numbers for a length of 26.745 km. The tree removal is largely based on the land requirement for widening and strengthening of existing proposed road and for road safety issues. BENEFITS OF AVENUE PLANTING ALONG ROAD SIDES ¾ To produce a greener landscape. ¾ To give shade to travellers. ¾ To absorb excessive noise. ¾ To raise social forestry; ¾ To act as a natural filter to the traffic emissions. ¾ Tree planting control soil erosion and provide increased slope stability. COMPENSATORY TREE PLANTING The compensatory tree planting strategy is based on the survival rate. The survival rate in Tamil Nadu is good due to the favourable climatic conditions. Public trees: The project will plant at least ten the number of trees that will be removed from the TNRSP-II road corridor. The compensatory planting for Maintenance of project roads will also be considered. The total numbers of plants that will be necessary to be planted against the expected loss of 1292 trees is about 12920. As an environmental enhancement measures, the project will also aim to plant shrubs in road divider and other places wherever space will be found suitable. SELECTION OF LOCATIONS FOR AVENUE PLANTATION Criteria adopted for selection of locations for avenue tree plantation is based on availability of land margin within road boundary. Proposed RoW of all the three Phase I roads SH 04, SH 116 and SH 58 varies from min. 16m to max. 23m depending on the landuse pattern of the corridor. The proposed right of way (PROW) is indicated in Table. Avenue plantation is proposed on both sides of the road at 10 m centre to centre (c/c). Revision Level: R2 September, 2014 Page 204 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division TABLE 1.0 : Proposed Right of Way (SH 58) End ROW in PRoW in Proposed Start (KM) (KM) m Section m lanes 0 180 180 Built up 16 2 lane 180 2800 2620 Rural 23 2 lane 2800 4100 1300 Built up 16 2 lane 4100 4400 300 Rural 23 2 lane 4400 6500 2100 Built up 16 2 lane 6500 8000 1500 Rural 23 2 lane 8000 9400 1400 Built up 16 2 lane 9400 13700 4300 Rural 23 2 lane 13700 17200 3500 Built up 16 2 lane RHS-9m LHS- 17200 18000 800 Rural 11.5 2 lane 18000 18400 400 Built up 16 2 lane 18400 19000 600 Rural 23 2 lane 19000 20400 1400 Built up 16 2 lane RHS-9m 20400 21200 800 Rural LHS- 2 lane 11.5 21200 21600 400 Rural 23 2 lane 21600 26800 5200 Built up 16 2 lane SELECTION OF TREE SPECIES FOR PLANTING The selection tree for planting is based on the tree species likely to be removed. The list of tree species to be planted along the Phase I roads are given in Table 2.0. The recommended species are the same as that of the occurring species. Peepal and Bargad trees are avoided for avenue plantation while these can be planted at other locations like school, hospital, temple and pond. Table 2.0: List of Trees for Plantation Sr no Botanical name Common name 1. Tamarindus indica Tamrind 2. Azadirachta indica Neem 3. Borassus flaberiformis Tad palm 4. Phonix sylvestris Khajur palm 5. Ficus bengalensis Baragad 6. Ficus religiosa Papal 7. Syzygium cumini Jamun 8. Bombax ceiba Kante sawar 9. Bombax malabarica Silk cotton tree 10. Acacia nilotica Babool 11. Cassia auriculata Cassia 12. Acacia auriculoformis Australian acacia 13. Eucalyptus species Nilgiri Revision Level: R2 September, 2014 Page 205 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division 14. Casuarinas equisetifolia Suru 15. Ficus glomerata Umbar 16. Dalbergia sisoo Shisam 17. Prosopis julifera Prosopis PLANTATION SPECIFICATIONS DETAILS OF NURSERIES Tamil Nadu Forest Department has facilities for raising nurseries at various places at division and sub-division level within the study area.Depending on necessity, nurseries can be raised in nearby private lands taken on short-term lease by TNFD. Cost of plantation per tree is estimated as Rs 2200 which includes three years maintenance. MONITORING FORMATS Monitoring may be done on a bimonthly basis using the format given in Table 5.0. TABLE 5.0 MONITORING FORMAT NO. OF REMARK NO. OF PLANTS ON SPECIES AVERAGE LOCATION PLANTS SURVIVING GENERAL PLANTED HEIGHT PLANTED AND HEALTH PERCENTAGE OF PLANTS BIO MANURE Bio manures like compost, neem cake, Azatobactor are recommended instead of chemical fertilizers to make the scheme more eco friendly. About 10 gm Azatobactor together with 250 nd rd gram of neem cake or compost shall be used at the time of planting and as part of 2 and 3 year maintenance. Neem cake will also function as bio pesticide. Compost can be made from green leaves, coconut husk or urban waste materials. Normally the tree species suggested do not suffer from attack of pests and application of neem cake can be very effective prophylactic treatment. MULCHING AND PRUNING Mulching at the end of monsoon shall be done with coconut husk, grass or green leaves after under taking a soil working around the plant in order to conserve moisture. Frequent watering of trees shall also be carried out to protect them from severe summer. Pruning of branches during nd rd 2 and 3 year shall be carried out to ensure proper stem formation and to ensure that the branches will not obstruct the traffic on the road. PAYMENT SCHEDULE The major portion of the expenditure is at the pre planting and planting stages. Plantation will be carried out by the project contractor with first year maintenance and cost for the same is Revision Level: R2 September, 2014 Page 206 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division considered in BOQ. Second and third year maintenance will be carried out by contractor appointed by TNRSP. NOISE BARRIER Although dissipation of complete noise is expensive and difficult to implement, some cost effective methods can be employed to reduce the noise level considerably. In order to create a healthy noise barrier the following considerations would help. The species selection should be very careful. The selected species should have small but presence of innumerable green leaves each small leaf acting as noise attenuator. The space available between the school or silence zone and the road corridor could be the deciding factor. The number of rows required creates an effective noise shield for the given circumstances. This actually depend on the space available between the road corridor and the building The design provided is an ideal situation especially with regard to the location of school gate, assembly area, and tree planting area (three rows of trees completely sealing the entry of direct noise). The school activity area (ground for daily assembly, prayer meetings etc) should be planned away from the main high traffic road. This is applicable as guideline to new schools. The School gate should be away from the main traffic road. If the situation does not permit, the gate should be in any corner in such a way that the noise effect from the main road is minimum. Trees increase effectiveness of noise barrier manifold. The species recommended for the tree planting is Polyalthia longifolia Var Pendula (Asoka tree). However depending on the situation any trees with numerous relatively small leaves will be ideal. LINK SPECIFIC ACTION PLAN FOR TREE PLANTING TREE PLANTING AWARENESS CAMPAIGN An Environmental Monitoring Unit (EMU) under the Highway Department (HD) at Chennai will take up this activity coordinating with local Engineers of each affected district for Panchayat level awareness meetings. The Environmental Officer will be solely responsible for the various activities. The EO needs to identify and invite the local people to participate in the programme. The parties to be invited include 1) Representatives of parents, Students and teachers of the Schools and other educational institutions bordering t he Project road 2) Forest officials - They will supply seedlings of the appropriate varieties to the local people and to the schools for planting. 3) Project Management Unit (PMU of PWD) members 4) HD local Staff 5) NGOs in the region as the EO can select the most appropriate NGOs as the credibility of all NGOs can only be evaluated by their past activities. 6) Private Nursery owners 7) Panchayat representatives Revision Level: R2 September, 2014 Page 207 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Nurseries The forest nurseries of the Social forestry wing of the Department of Forests and Wild Life and also Tamilnadu Forest Department will provide the seedlings on a continuous basis. Frequency of meetings There should be at least four meetings at local Panchayat levels per year to evaluate the programme after planting of the trees. The meeting shall be attended by representative of school children’s and teachers at all levels of education in addition to Panchayat Authorities. The HD at State level should organize television and radio programmes in the local language. Sources of Funding Tree plantation cost is already included in the contractor cost which is part of bid document, which also includes the planting for noise barriers. Contractor will carry out planting trees along the corridor as and when the road construction is complete. This way, survival rate of trees can be ensured. The rest has to be raised locally. In Tamil Nadu, the panchayat authorities can provide local funding for organizing these meetings and action plans. The project provision for noise barriers also provides funding for schools and hospitals. CONCLUSION & POLICY RECOMMENDATIONS CONCLUSIONS The project is committed to plant a minimum of 12920 trees as against the removal of 1292 trees for SH 58. RECOMMENDATIONS After the construction of the road, there should be a determined effort to persuade the landowners on both sides to plant shade trees along safe sections and to discourage at unsafe sections. This activity shall be at micro level i.e. at the Panchayat or village level with people's involvement. The household should know why these activities are required. There should be a determined effort by local schools, hospitals, Panchayat Municipal and Police authorities towards this. The PMU will take up this activity for further follow up with a definitive action plan. The strategy discussed is a general approach, depending upon the local situation; there can be variations. HD will have to develop a monitoring mechanism for tree plantation along the road and other location during operational stage to have an excellent control on the land and resources. HD should consider the employment of local people for planting. Notes: This recommendation does not affect the existing trees. Wherever possible, the existing trees have been protected by making necessary design changes. Revision Level: R2 September, 2014 Page 208 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division APPENDIX 3.55 ENVIRONMENTAL ENHANCEMENT DRAWINGS, BOQ AND COST Mitigation/Enhancement of Community Properties Surface Water Bodies along SH 58 THIRUTHANI SADRAS Chainage (km) 25+925 Structure ID No Pond Village Name Chengalpattu Side (Left/Right) Left Distance from PCL (m) 7.0 Length x Breadth (m) 39 x 40 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Amount BOQ Item Description Unit Quantity Rate (Rs) No. (Rs.) No. 1 Tree plantation No. 16 2.1 2 Retaining wall on road side rm 39 6.3 3 Disilting No 1 Total Revision Level: R2 September, 2014 Page 209 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 2+700 Structure ID No Water loged area Village Name Vengapakkam Side (Left/Right) Left Distance from PCL (m) 3.2 Length x Breadth (m) 40 x 65 Proposed ROW (Equal on 11.5 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Amount BOQ Item Description Unit Quantity Rate (Rs.) No. (Rs.) No. 1 Tree plantation No. 21 2.1 2 Retaining wall on road side rm 40 6.3 3 Disilting No 1 Total Revision Level: R2 September, 2014 Page 210 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 0+200 Structure ID No Pond Village Name Mayur Side (Left/Right) Left Distance from PCL (m) 5 Length x Breadth (m) 82 x 45.5 Proposed ROW (Equal on 11.5 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Amount BOQ Item Description Unit Quantity Rate (Rs.) No. (Rs.) No. 1 Tree plantation No. 26 2.1 2 Retaining wall on road side rm 82 6.3 3 Disilting No 1 Total Revision Level: R2 September, 2014 Page 211 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Sensitive Receptors along SH 58 THIRUTHANI SADRAS Chainage (km) 25+675 Structure ID No Health Centre Village Name Alatakkam Side (Left/Right) Left Distance from PCL (m) 13.50 Length x Breadth (m) 7x5 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Amount ( BOQ Item Description Unit Quantity Rate (Rs.) No. Rs.) No. Existing boundary wall will be 1 rm 6.0 raised and develop as noise barrier 7 2 Tree Plantation No 1 2.1 3 Horn prohibited sign post Covered in engineering works Total Chainage (km) 26+650 Revision Level: R2 September, 2014 Page 212 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Structure ID No School Village Name Alatakkam Side (Left/Right) Left Distance from PCL (m) 11 Length x Breadth (m) 28.5 x 30 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. Existing boundary wall will be 1 rm 6.0 raised and develop as noise barrier 28.5 2 Tree Plantation No 12 2.1 3 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 213 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 22+350 Structure ID No School Village Name Nenmeli Side (Left/Right) Right Distance from PCL (m) 8.5 Length x Breadth (m) 18 x 20 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. Existing boundary wall will be 1 rm 18 6.0 raised and develop as noise barrier 2 Tree Plantation No 8 2.1 3 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 214 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 19+200 Structure ID No School Village Name Keerapakkam Side (Left/Right) Right Distance from PCL (m) 14 Length x Breadth (m) 32.5 x 80 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. Existing boundary wall will be 1 rm 6.0 raised and develop as noise barrier 32.5 2 Tree Plantation No 23 2.1 3 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 215 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 15+000 Structure ID No School Village Name Erumallai Side (Left/Right) Right Distance from PCL (m) 14 Length x Breadth (m) 80 x 100 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. Existing boundary wall will be 1 rm 6.0 raised and develop as noise barrier 80 2 Tree Plantation No 36 2.1 3 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 216 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 14+900 Structure ID No School Village Name Erumallai Side (Left/Right) Right Distance from PCL (m) 11.2 Length x Breadth (m) 29.4 x 40 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Tree Plantation No 14 2.1 2 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 217 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 14+200 Structure ID No College Village Name Kothimangalam Side (Left/Right) Left Distance from PCL (m) 28 Length x Breadth (m) 25 x 60 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Tree Plantation No 17 2.1 2 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 218 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 11+675 Structure ID No ITI/College Village Name Kotimangalam Side (Left/Right) Right Distance from PCL (m) 10.5 Length x Breadth (m) 7 x 23.8 Proposed ROW (Equal on 11.5 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Nil (Demolition) Nil Nil Nil Nil Nil Total NIL Revision Level: R2 September, 2014 Page 219 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 8+045 Structure ID No School Village Name Mullikolathur Side (Left/Right) Right Distance from PCL (m) 4.2 Length x Breadth (m) 31.5 x 21 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of Boundary Wall rm 40 2 Construction of Boundary Wall rm 31.5 6.0 3 Tree Plantation No 11 2.1 4 Gate no 1 5 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 220 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 7+300 Structure ID No School Village Name Narasogapuram Side (Left/Right) Left Distance from PCL (m) 15.4 Length x Breadth (m) 29.4 x 10.5 Proposed ROW (Equal on 11.5 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Construction of Boundary Wall rm 29.4 6.0 2 Tree Plantation No 8 2.1 3 Gate No 1 4 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 221 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 3+390 Structure ID No School Village Name Vembakkam Side (Left/Right) Left Distance from PCL (m) 14 Length x Breadth (m) 17 x 80 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Tree Plantation No 19 2.1 2 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 222 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 0+050 Structure ID No School Village Name Meyur Side (Left/Right) Left Distance from PCL (m) 23.8 Length x Breadth (m) 30 x 11.5 Proposed ROW (Equal on 8 either side of PCL) (m) Impact No direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Tree Plantation No 19 2.1 2 Horn prohibited sign post Covered in engineering works Total Revision Level: R2 September, 2014 Page 223 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Community Structures along SH 58 THIRUTHANI SADRAS Chainage (km) 26+400 Structure ID No Temple Village Name Chengalpattu Side (Left/Right) Right Distance from PCL (m) 7.7 Length x Breadth (m) 14.4 x9.1 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of temple Wall rm 14.4 6.0 2 Construction of temple Wall rm 14.4 6.0 3 Seating bench No 2 6.0 4 Tree Plantation No 2 2.1 Total Revision Level: R2 September, 2014 Page 224 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 26+200 Structure ID No Temple Village Name Chengalpattu Side (Left/Right) Left Distance from PCL (m) 7.7 Length x Breadth (m) 29 x 11.6 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Nil (demolition) nil nil nil nil nil Total NIL Revision Level: R2 September, 2014 Page 225 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 26+140 Structure ID No Temple Village Name Chengalpattu Side (Left/Right) Right Distance from PCL (m) 4.2 Length x Breadth (m) 7.7 x 4.9 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Nil (Realignment explored) nil nil nil nil nil Total NIL Revision Level: R2 September, 2014 Page 226 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 25+900 Structure ID No Church Village Name Chengalpattu Side (Left/Right) Left Distance from PCL (m) 7 Length x Breadth (m) 15 x 12.50 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of boundary Wall rm 17 6.0 2 Construction of boundary Wall rm 15 6.0 3 Seating bench No 2 6.0 4 Tree Plantation No 2 2.1 5 Gate no 1 6.0 Total Revision Level: R2 September, 2014 Page 227 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 24+400 Structure ID No Temple Village Name Mairinattam Side (Left/Right) Right Distance from PCL (m) 4.5 Length x Breadth (m) 3.5 x 8 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of platform rm 3.5 6.0 2 Seating bench No 1 6.0 3 Tree Plantation No 2 2.1 Total Revision Level: R2 September, 2014 Page 228 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 23+858 Structure ID No Temple Village Name Nehru Nagar Side (Left/Right) Right Distance from PCL (m) 7 Length x Breadth (m) 10.5 x 8 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of boundary Wall rm 12.5 6.0 2 Construction of boundary Wall rm 10.5 6.0 3 Seating bench No 1 6.0 4 Tree Plantation No 4 2.1 5 Gate no 1 6.0 Total Revision Level: R2 September, 2014 Page 229 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 22+675 Structure ID No Temple Village Name Nenmeli Side (Left/Right) Right Distance from PCL (m) 4.5 Length x Breadth (m) 3.5 x 10 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of mandapam No 1 6.0 2 Seating bench No 1 6.0 3 Tree Plantation No 1 2.1 Total Revision Level: R2 September, 2014 Page 230 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 17+600 Structure ID No Temple Village Name Thirukazhukundram Side (Left/Right) Right Distance from PCL (m) 7 Length x Breadth (m) 4 x 18 Proposed ROW (Equal on LHS 9 either side of PCL) (m) RHS 11.5 Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of platform rm 3.5 6.0 2 Seating bench No 1 6.0 3 Tree Plantation No 2 2.1 Total Revision Level: R2 September, 2014 Page 231 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 13+300 Structure ID No Church Village Name Kottimangalam Side (Left/Right) Right Distance from PCL (m) 10.5 Length x Breadth (m) 9.3 x 6.2 Proposed ROW (Equal on 11.5 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of porch No 1 6.0 2 Seating bench No 1 6.0 3 Tree Plantation No 4 2.1 Total Revision Level: R2 September, 2014 Page 232 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 10+800 Structure ID No Temple Village Name Mullikolathur Side (Left/Right) Right Distance from PCL (m) 9.5 Length x Breadth (m) 19.5 x 16.5 Proposed ROW (Equal on 11.5 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of boundary Wall rm 19.5 6.0 2 Construction of boundary Wall rm 19.5 6.0 3 Seating bench No 1 6.0 4 Tree Plantation No 4 2.1 5 Gate no 1 6.0 Total Revision Level: R2 September, 2014 Page 233 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 6+147 Structure ID No Temple Village Name Anupuram Side (Left/Right) Right Distance from PCL (m) 8.4 Length x Breadth (m) 15 x 27 Proposed ROW (Equal on 11.5 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Nil (Realignment explored) nil nil nil nil nil Total Nil Revision Level: R2 September, 2014 Page 234 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 3+300 Structure ID No Temple Village Name Vembakkam Side (Left/Right) Right Distance from PCL (m) 5.5 Length x Breadth (m) 3 dia Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolish No 1 Total Revision Level: R2 September, 2014 Page 235 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 2+700 Structure ID No Church Village Name Vengapakkam Side (Left/Right) Right Distance from PCL (m) 9.5 Length x Breadth (m) 10.5 x 16 Proposed ROW (Equal on 11.5 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( BOQ Item Description Unit Quantity No. Rs.) No. 1 Demolition of porch No 1 6.0 2 Seating bench No 2 6.0 3 Tree Plantation No 6 2.1 Total Revision Level: R2 September, 2014 Page 236 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Chainage (km) 0+125 Structure ID No Temple Village Name Meyur Side (Left/Right) Left Distance from PCL (m) 7 Length x Breadth (m) 31.5 x15.5 Proposed ROW (Equal on 8 either side of PCL) (m) Impact direct impact MITIGATION/ENHANCEMENT S. Rate ( Amount ( BOQ Item Description Unit Quantity No. Rs.) Rs.) No. 1 Demolition of boundary Wall rm 33.5 6.0 2 Construction of boundary Wall rm 31.5 6.0 3 Seating bench No 1 6.0 4 Tree Plantation No 4 2.1 5 Gate no 1 6.0 Total Revision Level: R2 September, 2014 Page 237 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ANNEXURE 3.56 CULTURAL PROPERTIES : IMPACT, MITIGATION AND ENHANCEMENT The project needs to develop measures for the rehabilitation of cultural properties that will be affected by the road improvement programme. This could be made a part of the broad R&R Principle and Policy Framework. The Environmental Budget within the EMP will undertake the environmental enhancement where as any land acquisition and rehabilitation will be part of the Resettlement Action Plan. The TNRSP has been guided by the Bank’s Draft Operational Policy 4.11, which exclusively deals with the cultural properties, in its handling of the affected cultural properties due to the project. Further, as desired by the Bank, this section of the EMP and RAP has been prepared as a separate safeguard measures exclusively for the TNRSP. What Does Cultural Property Mean? The United Nations term “Cultural Property” includes sites having archaeological (prehistoric), paleontological, historical, religious, and unique natural values. Cultural Property, therefore, encompasses both remains left by previous inhabitants, for example, shrines, and battlegrounds) and unique natural environmental features such as canyons and waterfalls. The rapid loss of cultural property in many countries is irreversible and often unnecessary. Detailed background information on all aspects of this note are contained in the technical paper of the same title, available from the office of Environmental and Scientific Affairs, Project Policy Department of UN, which is ready to provide assistance on request. Source: World Bank Draft OP 4.11 1. TYPES OF RELIGIOUS PROPERTIES IDENTIFIED IN THE PROJECT LOCATION The environmental and social surveys and the detailed social impact studies have identified all cultural properties (total 14 Nos) that will be affected by the SH 58 road widening. Their magnitude of being affected widely varies. The following types of cultural properties are found on the project roads: 1 Temple 2 Church 3 Mosque 4 Shrines of all the three major religions 5 Tree shrines/sacred groves Except the tree shrines, the others are not strictly “common property” because they are owned and managed by their respective registered “Society” or “Trust”. Few cultural properties have encroached on the Government land (as per RAP). Other properties are affected in terms of losing boundary walls or land. 2. DEFINITIONS Shrines are usually small structures, located in the vicinity of the main religious structure associated with all the three major religions of the State. The shrines usually serve the purpose of helping the road users obtain a quicker religious service, besides indicating the larger Revision Level: R2 September, 2014 Page 238 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division presence of the religious community in the locality. The shrines are a most important part of any place of worship. Normally a small shrine develops to a bigger place of worship with earlier shrine remaining as the most important part of the property. Temples are Hindu places of worship. There are private as well as community temples. Most of the temples are different from one another by way of age and idols (Shiva, Vishnu, Krishna etc). In a majority of the cases, the location has specific significance. Because of the same reason temples are usually located away from the Roads. Churches are Christian places of worship. There are no private Churches. The churches usually belong to different groups within Christianity (Catholic, Marthoma, Syrian, Pentecostal, etc). Except few cases the location has no specific significance for a church. Mosques are the places of worship of the Muslims. There are Sunny Mosques and Mujahiddin mosques. With regard to the rehabilitation policy, all mosques can be treated as belonging to the same type. There are no known location specific mosques in the project location. Tree shrines are usually associated with the Hindus. There are a few tree shrines located along the project roads. People worship the idols installed at the base of the trees as well as the trees. These trees have a special significance to the local community, which will usually oppose the removal of such tree shrines. The landscaping would be ideal. This will require extensive community consultation. Sacred groves are also usually associated with the Hindus. For this purpose they preserve a small forest, known as sacred groves. This represents the close association of man with nature. Usually, landscaping would be ideal for the sacred groves. Direct Impacts: The direct impacts to the cultural properties are of the following category. 1 Only Compound wall affected 2 Compound wall and part of the compound affected 3 Part of structure affected 4 Sanctum sanatorium affected – can be categorized as the complete structure affected 5 Only land affected 6 Complete cultural property affected 7 Loss of access/entrance, if the existing access is from the project roadside. Project Approach: In all cases, the mitigation actions are framed unique to that particular situation with respect to the available space, the unique characteristics of the religious structure affected and the local public and religious judgment. In other words, the project policy is unique to consider the widely varying situations for each cultural property. Impact Mitigation: The loss of land and assets of the cultural properties will be treated on par with the loss of other land and assets for the purpose of compensation and assistance. However, the project will, in addition, strive to enhance benefits to the affected cultural properties in consultation with their respective management/ Owners. The Project has a clear strategy to take people and affected parties in to confidence before taking Revision Level: R2 September, 2014 Page 239 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division any decision on shifting of structures especially religious structures. In general there would not be any involuntary shifting or relocation especially in the case of cultural properties. An outline benefits enhancement for the cultural properties is shown in the following table. STRATEGY FOR RESTORATION, RELOCATION ORRECONSTRUCTION OF CULTURAL PROPERTIES EXTENT OF IMPACT SL IF CONSULTATION CONDUCTED BENEFIT ON CULTURAL NO. CONSENSUS OBTAINED ENHANCEMENT PROPERTIES 1 Only Compound wall Reconstruction of wall parallel to the Access/entrance and land beneath affected present compound wall. Loss of land provided through compensated. one of the sides 2 Compound wall and part Reconstruction of wall parallel to the of compound affected existing wall. Loss of land compensated. - Do - If land is available adjacent to the property, will be purchased. 3 Structure affected Alternate structure constructed and all - Do - pre-status restored. 4 Sanctum sanctorum Complete structure reconstructed and all - Do - affected pre-status restored. 5 Only land affected Alternate land provided, preferably, if available, adjacent to the existing -Do- location. 6 Complete cultural Relocation of site identified by the property affected cultural property authorities and -Do- rebuilding of the property. 3. OTHER IMPACTS TO CULTURAL PROPERTIES INCLUDE: Indirect/Induced impacts: The construction of road or realignments or bypasses sometime will result in induced impacts obstructing the cultural properties in various ways. In the instances of such events the highway authority will assist through consultation and other means (Highway Protection Act, 2000) restoring the importance of the shrine. This will be mostly applicable along the new alignments. 4. CULTURAL PROPERTY REHABILITATION ACTION PLAN The Rehabilitation Action Plan include environmental enhancement, design changes to save the structure from being affected. It was also planned to make design changes or adjustments to save the cultural properties from being affected. 5. CULTURAL PROPERTY IMPACT ASSESSMENT, MITIGATION AND ENHANCEMENT PLAN The cultural properties that will be affected by the SH 58widening are shown table below. Revision Level: R2 September, 2014 Page 240 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division List of religious/culturaland othercommunity assets and mitigation Distance Name of Location Mitigation/Enhancement Sl. Chainage from Common (Left / Impact ( As per Appendix 8.14 & No. (Km.) PCL Property Right) Generic enhancement) (m) Direct 1 26.400 Temple Right 7.7 Temple wall D&R Impact Direct 2 26.200 Temple Left 7.7 Generic Enhancement Impact Direct 3 26.140 Temple Right 4.2 Realignment Explored Impact Direct 4 25.900 Church Left 7 Boundary Wall D&R Impact Direct Base platform & one Idol 5 24.400 Temple Right 4.5 Impact D Direct 6 23.858 Temple Right 7 B. Wall D&R Impact Direct 7 22.675 Temple Right 4.5 Front mandapam D Impact Direct Base platform partially 8 17.600 temple Right 7 Impact D&R Direct 9 13.300 Church Right 10.5 Front porch D Impact Direct 10 10.800 Temple Right 9.5 Boundary fencing D&R Impact Direct 11 6.147 Temple Right 8.4 Realignment Explored Impact Direct 12 3.300 Rath Right 5.5 D Impact Direct 13 2.700 Church Right 9.5 Front porch demolished Impact Direct 14 0.125 Temple Left 7 Boundary Wall D&R Impact The team found out three distinct cases for impact mitigation. These are Design changes made to save cultural properties: Accordingly most of the cultural properties have been saved. Relocation necessary: In few cases some land acquisition will also be necessary. Environmental Enhancement and landscaping:At least in many cases cultural property enhancement measures are necessary. Revision Level: R2 September, 2014 Page 241 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division APPENDIX 8.1: GUIDELINES FOR MONITORINGPROGRAM Environmental Monitoring Plan To ensure the effective implementation of the EMP, it is essential that an effective monitoring programme be designed and carried out. Broad objectives of the monitoring programme are: • To evaluate the performance of mitigation measures proposed in the EMP • To suggest improvements in the management plans, if required • To satisfy the statutory and community obligations The monitoring programme contains monitoring plan for all performance indicators, reporting formats and necessary budgetary provisions. Monitoring plan for performance indicators and reporting system is presented in the following sections. Performance Indicators The Performance Indicators and monitoring plans prepared for Project Implementation are presented in Table 1.1. TABLE 1.1: PERFORMANCE INDICATORS FOR PROJECT IMPLEMENTATION Sl. Indicator Details Stage No. A Environmental Condition Indicators and Monitoring Plan Pre Construction 1 Air Quality Construction Operation Pre Construction 2 Noise Levels The parameters to be monitored, frequency and Construction duration of monitoring as well as the locations Operation to be monitored will be as per the Monitoring Pre Construction Water Plan prepared (Refer Table 1.3) 3 Construction Quality Operation Pre Construction 4 Soil Quality Construction Operation B Environmental Management Indicators and Monitoring Plan Location of construction camps have to be Construction 1 identified and parameters indicative of Pre-construction Camps environment in the area has to be reported Location of borrow areas have to be identified 2 Borrow Areas and parameters indicative of environment in the Pre-construction area has to be reported. Progress of tree removal marked for cutting is 3 Tree Cutting Pre-construction to be reported Revision Level: R2 September, 2014 Page 242 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Sl. Indicator Details Stage No. Tree Progress of measures suggested as part of the 4 Construction Plantation Strategy is to be reported C Management & Operational Performance Indicators 1 Survival Rate The number of trees surviving during each visit of Trees will be compared with the number of saplings Operation planted 2 Status The PU will undertake site visits to determine Regarding how many borrow areas have been rehabilitated Rehabilitation in line with the landowner’s request and to their Operation of Borrow full satisfaction. Areas 3 Soil Erosion Visual monitoring and operation inspection of embankments will be carried out once in three Operation months. Monitoring Parameters and Standards The Environmental monitoring of the parameters involved and the threshold limits specified are discussed below: Ambient Air Quality Monitoring (AAQM) The air quality parameters viz: Sulphur Dioxide (SO2), Particulate Matter (PM10) & Particulate Matter (PM2.5) , Oxides of Nitrogen (NOX), Carbon Monoxide (CO), Hydro-Carbons (HC), shall be regularly monitored at identified locations from the start of the construction activity. The air quality parameters shall be monitored in accordance with the National Ambient Air Quality Standards as given in Table 1.2A. The duration and the pollution parameters to be monitored and the responsible institutional arrangements are detailed out in the Environmental Monitoring Plan Table 1.3 and specific details in chapter on baseline environment. Table 1.2A National Ambient Air Quality Standards Industrial, Ecologically Sensitive Time Weighted Pollutant Residential, Rural & Area (notified by Average Other Area Central Government Sulphur Dioxide (SO2), µg/ m3 Annual 50 20 24 Hours** 80 80 Nitrogen Dioxide as NO2, µg/ Annual 40 30 m3 24 Hours** 80 80 Particulate Matter (size less Annual 60 60 than 10µm) or PM10µg/ m3 24 Hours** 100 100 Particulate Matter (size less Annual * 40 40 than 2.5µm) or PM2.5 µg/ m3 24 Hours** 60 60 Ozone (O3) µg/ m3 8 hours** 100 100 1Hours** 180 180 Lead (Pb) µg/ m3 Annual * 0.50 0.50 Revision Level: R2 September, 2014 Page 243 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Industrial, Ecologically Sensitive Time Weighted Pollutant Residential, Rural & Area (notified by Average Other Area Central Government 24 Hours** 1.0 1.0 Carbon Monoxide (CO) mg/m3 8 Hours** 02 02 1 Hour** 04 04 Ammonia (NH3) µg/ m3 Annual * 100 100 24 Hours** 400 400 Benzene (C6H6)˜ µg/ m3 Annual * 05 05 Benzo (a) pyrene Annual * 01 01 (BaP)particulate phase only ng/m3 Arsenic (AS)˜ng/m 3 Annual * 06 06 Nickel (Ni) ng/m3 Annual * 20 20 Source: Central Pollution Control Board Notification dated 18th November 2009 * Annual arithmetic mean of minimum 104 measurements in a year at a particular site taken twice a week hourly at uniform intervals ** 24 hourly or 08 hourly or 01 hourly monitored values, as applicable, shall be complied with 98% of the time in a year. 2% of the time, they may exceed the limits but not on two consecutive days of monitoring. Noise Quality Monitoring The noise levels shall be monitored at already designated locations in accordance with the Ambient Noise Quality standards given in Table 1.2B. The duration and the noise pollution parameters to be monitored and the responsible institutional arrangements are detailed in the Environmental Monitoring Plan Table 1.3 and specific details in chapter on baseline environment. Table 1.2B National Standard of Noise Category of Zones Leq in dB(A) Day* Night Industrial 75 70 Commercial 65 55 Residential 55 45 Silence Zone ** 50 40 Source: MoEF 1. Day time shall mean from 6.00 a.m. to 10.00 p.m. 2. Night time shall mean from 10.00 p.m. to 6.00 a.m. not less than 100 metres around hospitals, educational institutions and courts. The silence zones are zones which are declared as such by the competent authority. 3. Mixed categories of areas may be declared as one of the four above mentioned categories by the competent authority. Water Quality Monitoring Water quality parameters such as pH, BOD, COD, DO coliform count, total suspended solids, total dissolved solids, Iron, etc. shall be monitored at all identified locations during the construction stage as per standards prescribed by Central Pollution Control Board and Indian Standard Drinking water specifications IS 10500, 2012, presented in Table 1.2C. The duration and the pollution parameters to be monitored and the Revision Level: R2 September, 2014 Page 244 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division responsible institutional arrangements are detailed out in the Environmental Monitoring Plan Table 1.3 and specific details in chapter on baseline environment. Table 1.2C: National Standard of Water S. Characteristic Requireme Permissible Remarks No. nt limit in the (Acceptable absence of Limit) alternate source Essential Characteristics 1 Colour, Hazen units, Max 5 15 Extended to 15 only, if toxic substances are not suspected in absence of alternate source 2 Odour Agreeable Agreeable a) Test cold and when heated b) Test at several dilutions 3 pH Value 6.5 to 8.5 No relaxation - 4 Taste Agreeable Agreeable Test to be conducted only after safety has been established 5 Turbidity NTU, max 1 5 - 6 Total dissolved solids, mg/l, 500 2000 - Max 7 Aluminium (as Al), mg/l Max 0.03 0.2 - 8 Ammonia (as total ammonia-N), 0.5 No relaxation - mg/l Max 9 Anionic detergents (as MBAS), 0.2 1.0 - mg/l, Max 10 Barium (as Ba), mg/l, max 0.7 No relaxation - 11 Boron (as B), mg/l Max 0.5 1.0 - 12 Calcium (as Ca) mg/l, Max 75 200 - 13 Chloramines (as Cl2), mg/l, Max 4.0 No relaxation - 14 Chloride (as Cl) mg/l, Max 250 1000 - 15 Copper (as Cu) mg/l, Max 0.05 1.5 - 16 Fluoride (as F) mg/l, Max 1.0 1.5 - 17 Free residual Chlorine, mg/l, 0.2 1 To be applicable only when Min water is chlorinated. Tested at consumer end. When protection against viral infection is required, it should be minimum 0.5 mg/l 18 Iron (as Fe) mg/l, max 0.3 No relaxation Total concentration of manganese (as Mn) and iron (as Fe) shall not exceed 0.3mg/l 19 Magnesium (as Mg) mg/l, Max 30 100 - 20 Manganese (as Mn) mg/l, Max 0.1 0.3 - 21 Mineral oil, mg/l Max 0.5 No relaxation - 22 Nitrate (as NO3) mg/l, Max 45 No relaxation - 23 Phenolic compounds (as 0.001 0.002 - C6H5OH) mg/l, Max Revision Level: R2 September, 2014 Page 245 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division S. Characteristic Requireme Permissible Remarks No. nt limit in the (Acceptable absence of Limit) alternate source 24 Selenium (as Se), mg/l, Max 0.01 No relaxation - 25 Silver (as Ag), mg/l, Max 0.1 No relaxation - 26 Sulphate (as SO4) mg/l, Max 200 400 May be extended to 400 provided that Magnesium does not exceed 30 27 Sulphide (as H2S) mg/l, max 0.05 No relaxation - 28 Total alkalinity as calcium 200 600 - carbonate, mg/l Max 29 Total Hardness (as CaCO3) 200 600 - mg/l, Max 30 Zinc (as zn), mg/l, Max 5 15 - 31 Cadmium (as Cd), mg/l, Max 0.003 No relaxation - 32 Cyanide (as CN), mg/l, Max 0.05 No relaxation - 33 Lead (as Pb), mg/l, Max 0.01 No relaxation - 34 Mercury (as Hg) mg/l, Max 0.001 No relaxation - 35 Molybdenum (as Mo) mg/l, max 0.07 No relaxation - 36 Nickle (as Ni), mg/l, max 0.02 No relaxation - 37 Polychlorinated biphenyls, mg/l, 0.0005 No relaxation - max 38 Polynuclear aromatic 0.0001 No relaxation - hydrocarbons (as PAH) mg/l, Max 39 Total Arsenic (as As), mg/l, 0.01 0.05 - Max 40 Total Chromium (as Cr) mg/l, 0.05 No relaxation - Max 41 Trihalomethanes - Bromoform, mg/l, max 0.1 No relaxation Dibromochloromethane, mg/l, 0.1 No relaxation max 0.06 No relaxation Bromodichloromethane, mg/l, 0.2 No relaxation max Chloroform, mg/l, max 42 Radioactive materials - a) Alpha emitters Bq/l max 0.1 No relaxation b) Beta emitters pci/l, Max 1.0 No relaxation Monitoring Plans for Environment Condition For each of the environmental components, the monitoring plan specifies the parameters to be monitored; location of the monitoring sites; frequency and duration of monitoring. The monitoring plan also specifies the applicable standards, implementation and supervising responsibilities. The monitoring plan for the various environmental condition indicators of the project in construction and operation stages is presented in Table 1.3. Monitoring plan does not include the requirement of arising out of Regulation Provision such as obtaining NOC/ consent for plant site operation. Revision Level: R2 September, 2014 Page 246 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Revision Level: R2 September, 2014 Page 247 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Table 1.3: Environmental Monitoring Plan Project Implementatio Attribute Parameter Standards Frequency Duration Location Stage n 24 hourly Along the road (1. sampling once in Anupuram, 2. a season for three Thirukazhukundra Constructio season in a year Constructi m, 3. Chengalpattu n EMU- Three seasons on Period near railway TNRSP (Winter, Summer Station) and Post Air (prevention and Monsoon) Hot mix Plant Air CO, NOx, Control of PM10, PM2.5, Pollution) Rules, 24 hourly and SO2 sampling once in Along the road (1. CPCB, 1994 a season for three Anupuram, 2. season in a year Thirukazhukundra Operation for two years m, 3. Chengalpattu 2 Years EMU- near railway Three seasons TNRSP Station) (Winter, Summer and Post Monsoon) Along the road (1. EMU- All essential Indian Standards One grab Meiyur 2 TNRSP Constructio characteristics for Inland Surface sampling once in Constructi Water Thirukazhukundra n and some of Waters (IS: 2296, a season for three on Period m). desirable 1982) and for seasons in a year characteristics Drinking Water (IS Revision Level: R2 September, 2014 Page 248 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Project Implementatio Attribute Parameter Standards Frequency Duration Location Stage n as decided by : 10500 - 2012) Along the road (1. One grab the Meiyur 2 sampling once in Operation Environmental Thirukazhukundra a season for three 2 Years Specialist of the m). EMU- seasons in a year PMC and TNRSP for 2 years TNRSP Along the road (1. hourly sampling Anupuram, 2. for one day once Thirukazhukundra Constructio Constructi EMU- in a season for m, 3. Chengalpattu n on Period TNRSP three season in a near railway year Station) Noise levels on MoEF Noise Rules, Hot mix Plant dB (A) scale 2000 Noise Along the road (1. hourly sampling Anupuram, 2. for one day once Thirukazhukundra in a season for m, 3. Chengalpattu Operation EMU- three season in a near railway year for two 2 Years TNRSP Station) years Along the road (1. Threshold for each One grab Meiyur 2 Soil Constructio Monitoring of contaminant set by sampling once in Constructi Thirukazhukundra n Pb, SAR and IRIS database of a season for three on Period EMU- m). Oil & Grease USEPA until seasons in a year TNRSP national standards Hot mix Plant Revision Level: R2 September, 2014 Page 249 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Project Implementatio Attribute Parameter Standards Frequency Duration Location Stage n are promulgated Along the road (1. One grab Meiyur 2 sampling once in Operation Thirukazhukundra a season for three 2 Years EMU- m). seasons in a year TNRSP for 2 years Borrow Constructio As per Borrow area area n - Once in a month - location Contractor Guidelines As per Areas where Tree Operation EMU- Rehabilitation Quarterly - plantation is being plantation stage TNRSP Plan done Revision Level: R2 September, 2014 Page 250 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division ENVIRONMENTAL MONITORING LOCATIONS In addition of the critical locations selected during design stage, the environmental monitoring will also be done at the construction camp site and plant site during construction stage. List of critical locations for caring out monitoring is presented in chapter 4 of EIA report: Baseline environment. REPORTING PROCEDURES Mitigation and enhancement measures adopted in the final design have been identified in the contract documents and Bill of quantities so that performance and completion is effective. The periodic site visits of the EO/Engineer/EE of the PU will keep a record of progress as well as the site-specific EMP implementation records. The frequent meeting of the EO/Engineer with the Contractors will ensure any information and communication gap with regard to the Construction phase environmental management at construction site; labour and construction camps quarry and borrow areas etc. It is necessary that the EO/Engineer should visit the sites for evolving a concept for the Environmental Management with regard to the siting of various construction requirements. The various reporting guidelines and arrangements are presented in TABLE 1.4. DESIRED MONITORING AND REPORTING PROCESS AND RESPONSIBILITIES. Revision Level: R2 September, 2014 Page 251 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division TABLE 1.4: DESIRED MONITORING AND REPORTING PROCESS AND RESPONSIBILITIES Contractor PMC Consultant PIU-TNRSP Reporting from Format Implementation Oversee Field TNRSP to World Item Stage Reporting to Reporting to No. and Reporting to Supervision Compliance Bank) TNRSP EMU, TNRSP TA Consultant Monitoring Identification for disposal P1 Pre -construction One Time One Time One Time One Time One Time One Time locations Setting up of Construction P2 Pre- construction One Time One Time One Time One Time One Time One Time Camp P3 Establishment of Borrow areas Pre- construction Monthly Monthly Quarterly Quarterly Quarterly Quarterly Before start of P4 Establishment of HMP/ BMP One Time One Time One Time One Time One Time One Time construction Road Safety and Traffic P5 Pre- construction Monthly Monthly Monthly Monthly Quarterly Quarterly Management Arrangement for Temporary P6 Pre- Construction Monthly Monthly Monthly Quarterly Quarterly Quarterly Land Immediately During P7 Pollution Monitoring Pre- Construction Quarterly on receipt of Quarterly Quarterly Quarterly Monitoring results During construction P8 Tree cutting/Stump Removal Monthly Monthly Monthly Quarterly Quarterly Quarterly period Identification of Source of P9 Pre- construction One Time One Time One Time One Time One Time One Time water for Construction During Construction C1 Details of earth work Monthly Monthly Monthly Quarterly Quarterly Quarterly period During Construction C2 Details of Hot Mix Plant Monthly Monthly Monthly Quarterly Quarterly Quarterly period During Construction C3 Details of landfill locations/ Monthly Monthly Monthly Quarterly Quarterly Quarterly period Details of Machinery in During Construction C4 Monthly Monthly Monthly Quarterly Quarterly Quarterly Operations period C5 Redevelopment of borrow areas During construction Monthly Monthly Monthly Quarterly Half Yearly Quarterly Revision Level: R2 September, 2014 Page 252 Detailed Project Report (DPR) For Various Road Improvement Works under PPC 01 of Tamil Nadu Road Sector Project – II (TNRSP II) Environmental Management Plan Document Ref: RITES/UE/2553-61/SH 58 Highway Division Contractor PMC Consultant PIU-TNRSP Reporting from Format Implementation Oversee Field TNRSP to World Item Stage Reporting to Reporting to No. and Reporting to Supervision Compliance Bank) TNRSP EMU, TNRSP TA Consultant Monitoring period During construction C6 Safety Check List Monthly Monthly Monthly Quarterly Half Yearly Quarterly period Immediately During construction After C7 Accident Report After Accident on receipt of Quarterly Half Yearly Quarterly period Accident report During construction During C8 Pollution Monitoring Quarterly Quarterly Quarterly Quarterly Quarterly period Monitoring C9 Enhancement Measures During Construction Monthly Monthly Monthly Quarterly Quarterly Quarterly Restoration of Construction Immediate after C10 One Time One Time One Time One Time One Time Quarterly Sites Construction O1 Pollution Monitoring During Operation - - - Quarterly Quarterly Quarterly Revision Level: R2 September, 2014 Page 253