Large Scale Irrigation Modernization Project Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: 5 may 2015]: Revision 2 of Updated Procurement Plan, March 28, 2017 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. Works Above US$ 15 million All 2. Goods Above US$ 4 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2 million 2. Single Source All 3. Individual Above US$ 400,000 July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule July 9, 2010 PROCUREMENT Morocco : MA-Large Scale Irrigation Modernization Project PLAN General Information Country: Morocco Bank’s Approval Date of the Original Procurement Plan: 2017-04-26 2019-09-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150930 GPN Date: Project Name: MA-Large Scale Irrigation Modernization Project Loan / Credit No: IBRD / 85140 Executing Agency(ies): ORMVA HAOUZ WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ORMVAH-REF-2 / FOURNITURE, TRANSPORT ET POSE DE LA Component 1: Improving CONDUITE D’ADDUCTION Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 20,065,404.00 2,059,151.69 Signé 2017-02-27 2017-03-04 2017-04-15 2017-05-15 2017-06-19 2017-12-16 ET SES OUVRAGES Envelope Infrastructure ANNEXES DU SECTEUR BOUIDA CONDUITE SOUS- PRESSION ORMVAH-REF-7 / Réseau Component 1: Improving d'irrigation partie Amont: Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 7,700,000.00 7,843,120.54 Signé 2017-12-01 2018-01-01 2018-01-31 2018-03-02 2018-04-16 2019-12-07 Conduites + Bornes blocs et Envelope Infrastructure prises propriétés ORMVAH-REF-8 / Réseau Component 1: Improving d'irrigation partie Aval: Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 6,800,000.00 5,508,070.26 Signé 2018-09-01 2018-10-01 2018-10-31 2018-11-30 2019-01-15 2020-09-05 Conduites + Bornes blocs et Envelope Infrastructure prises propriétés ORMVAH-REF-6 / Ouvrages Component 1: Improving de tête et raccordement à la Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 600,000.00 1,352,418.79 Signé 2017-12-01 2018-01-01 2018-01-31 2018-03-17 2018-04-16 2019-04-11 conduite d'adduction au Envelope Infrastructure point K Component 3: Supporting ORMVAH-REF-10 / Tarvaux the Project Implementing Single Stage - One de rénovation des locaux IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2018-02-01 2018-03-03 2018-04-02 2018-04-17 2018-06-16 2019-07-11 Envelope administratifs Irrigation Network and to Implement the Project ORMVAH-REF-15 / TRAVAUX Component 3: Supporting D’AMENAGEMENT ET the Project Implementing D’ENTRETIEN DES Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 39,394.00 32,530.04 Signé 2018-11-07 2018-11-12 2018-12-03 2018-12-13 2018-12-29 2019-04-28 BATIMENTS DE LA Envelope Irrigation Network and to SALLE DE REUNION DU Implement the Project CMV BOUIDA DE L’ORMVA DU HAOUZ. ORMVAH-REF-13 / FOURNITURE, TRANSPORT ET INSTALLATION DU MATERIEL D’EQUIPEMENT Component 1: Improving DE LA STATION DE Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 2,402,034.00 2,674,550.40 Signé 2018-08-16 2018-08-21 2018-10-02 2018-11-01 2018-12-06 2020-05-29 FILTRATION, Y COMPRIS Envelope Infrastructure TRAVAUX DE GENIE CIVIL, DANS LE SECTEUR DE BOUIDA DE LA TASSAOUT AMONT. Page 1 ORMVAH-REF-24 / Réseau Component 1: Improving d'irrigation+ bornes Single Stage - One En attente IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 5,500,000.00 0.00 2019-03-23 2019-03-28 2019-04-18 2019-05-18 2019-06-22 2020-12-13 d'irrigation du secteur Envelope d'exécution Infrastructure Bouida (partie 3) ORMVAH-REF-26 / TRAVAUX Component 3: Supporting D’AMENAGEMENT ET the Project Implementing Single Stage - One En cours D’ENTRETIEN DES IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 20,000.00 0.00 2019-04-24 2019-04-29 2019-05-20 2019-06-19 2019-07-24 2019-11-21 Envelope d'exécution BATIMENTS DE CMV Irrigation Network and to BOUIDA DE L’ORMVA DU Implement the Project HAOUZ. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ORMVAH-REF-12 / ACQUISITION ET INSTALLATION DES EQUIPEMENTS Component 1: Improving NECESSAIRES POUR LE Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 44,820.00 40,917.51 Signé 2017-09-12 2017-10-12 2017-11-03 2017-12-03 2017-12-29 2018-09-25 SUIVI DE LA NAPPE Envelope Infrastructure DANS LA ZONE DE RECONVERSION D’IRRIGATION DU SECTEUR BOUIDA ORMVAH-REF-1 / REALISATION DE CAMPAGNES D’ANALYSESDE Component 1: Improving CARACTERISATION DE Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 33,187.20 34,712.10 Signé 2017-01-11 2017-01-16 2017-02-27 2017-03-29 2017-05-03 2017-10-30 REFERENCES DES Envelope Infrastructure PARAMETRES ENVIRONNEMENTAUX LOCALISEE DANS SECTEUR BOUIDA ORMVAH-REF-16 / EQUIPEMENT EN Component 3: Supporting MATERIELS ET the Project Implementing Single Stage - One MOBILIERS DE LA SALLE IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 28,787.00 31,416.35 Signé 2018-11-07 2018-11-09 2018-11-30 2018-12-10 2018-12-27 2019-04-26 Envelope DE REUNION DU CMV Irrigation Network and to BOUIDA DE L’ORMVA DU Implement the Project HAOUZ. ORMVAH-REF-21 / Component 3: Supporting fourniture et livraison de the Project Implementing Single Stage - One véhicules pour l'ORMVA du IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 125,000.00 131,001.07 Signé 2018-12-10 2018-12-31 2019-01-30 Envelope Haouz lot n°2: 10 véhicules Irrigation Network and to utilitaires diesel Implement the Project ORMVAH-REF-27 / Component 3: Supporting Acquisition et installation the Project Implementing des équipements nécessaires Single Stage - One En attente IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 20,000.00 0.00 2019-04-24 2019-04-29 2019-05-20 2019-06-19 2019-07-24 2020-07-23 pour le système Envelope d'exécution Irrigation Network and to d'avertissement à l'irrigation Implement the Project BOUIDA Component 3: Supporting ORMVAH-REF-28 / the Project Implementing Acquisition et installation Single Stage - One En attente IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 40,000.00 0.00 2019-04-24 2019-04-29 2019-05-01 2019-05-31 2019-07-05 2020-01-01 des équipements pour Envelope d'exécution Irrigation Network and to extension SIG BOUIDA Implement the Project Page 2 ORMVAH-REF-20 / Component 3: Supporting fourniture et livraison de the Project Implementing Single Stage - One véhicules pour l'ORMVA du IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 150,000.00 138,175.88 Signé 2018-12-10 2018-12-18 2019-01-17 Envelope Haouz lot n°1: 6 véhicules Irrigation Network and to 4x4 diesel Implement the Project NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ORMVAH-REF-9 / Component 1: Improving Single Stage - One En attente Laboratoire pour le contrôle IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 150,000.00 0.00 2017-02-01 2017-03-03 2017-04-02 2017-05-17 2017-06-16 2020-12-27 Envelope d'exécution des travaux Infrastructure ORMVAH-REF-5 / Travaux Component 1: Improving topographique pour Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2017-09-10 2017-10-10 2017-11-09 2018-01-08 2018-02-13 2020-01-13 l'établissement du dossier Envelope Infrastructure d'expropriation ORMVAH-REF-14 / PRESTATION pour la mise en œuvre du Plan de Component 3: Supporting Gestion de l’Environnement the Project Implementing Single Stage - One (PGE)( secteur Bouida) : Le IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 66,816.00 59,024.73 Signé 2017-07-14 2017-07-19 2017-08-30 2017-09-29 2017-11-03 2021-10-13 Envelope Suivi et contrôle des Irrigation Network and to chantiers et la Formation Implement the Project des techniciens de l’entreprise ORMVAH-REF-19 / Organisation d'une visite Component 3: Supporting technique aux périmètres the Project Implementing irrigués au Protugal Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 40,000.00 34,077.90 Signé 2018-12-22 2018-12-30 2019-04-29 concernant la formation dans Envelope Irrigation Network and to le cadre de l'appui aux Implement the Project agences d'exécution (HEBERGEMENT) ORMVAH-REF-18 / Organisation d'une visite Component 3: Supporting technique aux périmètres the Project Implementing irrigués au Protugal Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 20,000.00 24,005.54 Signé 2018-12-19 2018-12-29 2019-04-28 concernant la formation dans Envelope Irrigation Network and to le cadre de l'appui aux Implement the Project agences d'exécution (TRANSPORT) ORMVAH-REF-22 / Formation: Organisation Component 3: Supporting d'une visite technique aux the Project Implementing périmètres irrigués l Single Stage - One En attente IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 40,000.00 0.00 2019-04-29 2019-06-24 2019-10-22 concernant la formation dans Envelope d'exécution Irrigation Network and to le cadre de l'appui aux Implement the Project agences d'exécution (HEBERGEMENT) ORMVAH-REF-23 / Formation: Organisation Component 3: Supporting d'une visite technique aux the Project Implementing périmètres irrigués Single Stage - One En attente IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 20,000.00 0.00 2019-04-29 2019-06-24 2019-10-22 concernant la formation dans Envelope d'exécution Irrigation Network and to le cadre de l'appui aux Implement the Project agences d'exécution (TRANSPORT) Page 3 ORMVAH-REF-25 / Component 1: Improving prestations de laboratoire Single Stage - One En attente IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 100,000.00 0.00 2019-03-23 2019-03-28 2019-04-18 2019-05-18 2019-06-22 2020-06-16 pour control et suivi des Envelope d'exécution Infrastructure travaux du secteur Bouida CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ORMVAH-REF-3 / L’Assistance technique pour le suivi et le contrôle des Component 1: Improving Sélection fondée Open - travaux de reconversion à IBRD / 85140 Irrigation Network A posteriori sur la qualité et 6,600,000.00 1,069,459.06 Signé 2016-10-07 2016-10-28 2016-12-11 2017-01-08 2017-02-07 2017-03-14 2017-04-18 2018-04-18 International l'irrigation localisée du Infrastructure le coût secteur Bouida du périmètre de la Tessaout Amont. ORMVAH-REF-4 / La Mission d'assistance technique consiste en la réalisation des prestations Component 2: Supporting Sélection fondée Open - En attente suivantes: IBRD / 85140 Farmers’ Access to Improved A posteriori sur la qualité et 100,000.00 0.00 2017-10-11 2017-10-12 2018-02-17 2018-03-17 2018-04-16 2018-05-21 2018-06-25 2019-06-25 International d'exécution Formation des agriculteurs Irrigation Technologies le coût Formation du personnel d'encadrement Essais et démonstrations ORMVAH-REF-17 / l’Assistance technique pour Component 2: Supporting Sélection fondée l’appui aux agriculteurs et à IBRD / 85140 Farmers’ Access to Improved A posteriori sur la qualité et Open - National 800,000.00 664,338.59 Signé 2017-02-01 2017-03-01 2017-06-29 2017-07-27 2017-08-26 2017-09-30 2017-11-04 2021-10-14 leurs partenaires du secteur Irrigation Technologies le coût Bouida du périmètre de la Tessaout Amont  AMI 01/2019/ORMVAH/SGRID / PRESTATIONS D’ASSISTANCE TECHNIQUE ET ACCOMPAGNEMENT POUR L’EXPLOITATION ET LA Component 2: Supporting Sélection fondée MAINTENANCE DES En attente IBRD / 85140 Farmers’ Access to Improved A posteriori sur la qualité et Open - National 935,040.00 0.00 2019-09-02 2019-09-17 2019-10-31 2019-11-28 2019-12-05 2019-12-17 2020-01-21 2021-01-20 EQUIPEMENTS HYDRO- d'exécution Irrigation Technologies le coût AGRICOLES DANS LES SECTEURS DE RECONVERSION COLLECTIVE EN IRRIGATION LOCALISEE DANS LE PERIMETRE DU HAOUZ INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4