The World Bank Implementation Status & Results Report GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) AFRICA | Cote d'Ivoire | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 1 | ARCHIVED on 07-Dec-2018 | ISR34383 | Implementing Agencies: PRICI (PCU), Ministry of Finance Key Dates Key Project Dates Bank Approval Date: 29-Jun-2018 Effectiveness Date: -- Planned Mid Term Review Date: -- Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2025 Revised Closing Date: 31-Dec-2025 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to support the improvement of urban management, logistics efficiency, port accessibility, and urban mobility in the Greater Abidjan Area (GAA) and to provide immediate and effective response to eligible crisis or emergency. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Urban Planning, Services and Governance:(Cost $74.00 M) Urban Transport Infrastructure:(Cost $173.20 M) Logistics Services and Competitiveness:(Cost $142.20 M) Program Management and Monitoring:(Cost $11.00 M) Contingent Emergency Response Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Satisfactory Overall Risk Rating -- High Implementation Status and Key Decisions The Greater Abidjan Port - City Integration Project was approved by the World Bank Board on June 29, 2018. The credit is not yet effective (expected by December 7, 2018), but the execution of the preparation activities are satisfactory. The project is, generally, in good progress for its effectiveness and the launch of its main activities. The procurement plan was revised and published. 12/7/2018 Page 1 of 8 The World Bank Implementation Status & Results Report GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial -- Substantial Macroeconomic Substantial -- Substantial Sector Strategies and Policies Substantial -- Substantial Technical Design of Project or Program High -- High Institutional Capacity for Implementation and Sustainability Substantial -- Substantial Fiduciary Substantial -- Substantial Environment and Social High -- High Stakeholders Substantial -- Substantial Other Low -- Low Overall High -- High Results PDO Indicators by Objectives / Outcomes Improved urban management IN00640566 ►Percentage of urban authorizations/construction permits compliant to DUPs (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 No change- project not effective Comments: Improved logistics efficiency IN00640567 ►Reduced average access time to PAA (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640570 12/7/2018 Page 2 of 8 The World Bank Implementation Status & Results Report GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) ►Number of trucks coming from hinterland that access the port (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 200.00 -- 200.00 10.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 Improved port accessibility IN00640568 ►Number of trucks stationed in informal parking in the PAA area (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1,300.00 -- 1,300.00 200.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 Improved urban mobility IN00640569 ►Reduced average travel time on the VGE (between Solibra intersection and Akwaba intersection) (Minutes, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 24.00 -- 24.00 13.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 Intermediate Results Indicators by Components Component 1: Urban Planning, Services and Governance IN00640574 ►Number of DUPs adopted (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640577 ►Number of agreed priority activities to improve the lagoon waterway transport are done (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640580 ►Percentage of streets labeled (Percentage, Custom) 12/7/2018 Page 3 of 8 The World Bank Implementation Status & Results Report GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) Baseline Actual (Previous) Actual (Current) End Target Value 3.00 -- 0.00 80.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640583 ►Improvement of Road Safety for Pedestrians and Cyclists (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 25.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640586 ►Green Zone development plan adopted (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640587 ►Percentage of agreed priority activities for the development of the Green Zone are done (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640588 ►Urban Transport Master Plan Developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640589 ►Identification of MGS (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640590 ►Technical assistance for the SDUGA implementing agencies (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640591 12/7/2018 Page 4 of 8 The World Bank Implementation Status & Results Report GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) ►Number of facilities that specifically address women’s identified mobility and security constraints (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640592 ►Number of footbridges (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 6.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 Component 2: Urban Transport Infrastructure IN00640573 ►Roads constructed (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 13.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640576 Roads constructed - non-rural (Kilometers, Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 13.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640578 ►Roads rehablitated (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4.40 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640582 Roads rehabilitated - non-rural (Kilometers, Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4.40 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640584 ►Akwaba intersection works done (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes 12/7/2018 Page 5 of 8 The World Bank Implementation Status & Results Report GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 Component 3: Logistics Services and Competitiveness IN00640572 ►Logistics platform developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640575 ►Adoption of legal and institutional framework for logistics platform (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640579 ►Traffic managed by terminals connected to the TAS (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640581 ►Curriculum of logistics training programs adopted (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 IN00640585 ►Number of persons trained under the logistics program (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 150.00 Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 Component 4: Project Management IN00640571 ►Share of grievances registered related to delivery of project that are addressed (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 12/7/2018 Page 6 of 8 The World Bank Implementation Status & Results Report GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) Date 28-Jun-2018 -- 28-Jun-2018 31-Dec-2025 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Not P159697 IDA-62720 USD 315.00 315.00 0.00 0.00 295.65 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P159697 IDA-62720 29-Jun-2018 10-Sep-2018 -- 31-Dec-2025 31-Dec-2025 Effective Cumulative Disbursements 12/7/2018 Page 7 of 8 The World Bank Implementation Status & Results Report GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT (P159697) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/7/2018 Page 8 of 8