PROCUREMENT PLAN (Textual Part) Project information: Nigeria [Third National Fadama Development Project (Additional Financing II)] (North East Food Security and Livelihood Emergency Support) [P158535] Project Implementation agency: [National Fadama Coordination Office and States] Date of the Procurement Plan: [25th January 2018] Period covered by this Procurement Plan: [January – December 2018] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitutes the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Not Applicable], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Not Applicable”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goodsas specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Not Applicable] Other Relevant Procurement Information. Not Applicable. PROCUREMENT Nigeria : THIRD NATIONAL FADAMA DEVELOPMENT PROJECT (FADAMA III) PLAN General Information Country: Nigeria Banks Approval Date of the Original Procurement Plan: 2018-03-07 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-03-08 Project ID: P096572 GPN Date: Project Name: THIRD NATIONAL FADAMA DEVELOPMENT PROJECT (FADAMA III) Loan / Credit No: IDA / 52930, IDA / 58490 Executing Agency(ies): NATONAL FADAMA III NATIONAL COORDINATING OFFICE, LAGOS, KANO, NIGER, ANAMBRA, ENUGU, BAUCHI, KOGI, BORNO, ADAMAWA, GOMBE WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NFCO-AF-CW-RFQ-1-18 / Project Administration, Request for Single Stage - One Pending IDA / 52930 Post Limited 71,895.00 0.00 2018-06-19 2018-08-14 2018-09-13 Fadama House rehabilitation Monitoring and Evaluation Quotations Envelope Implementation NFCO-AF-CW-RFQ-2-18 / Small-Scale Community-owned Request for Single Stage - One Pending Construction of Fadama IDA / 52930 Post Limited 196,078.00 0.00 2018-03-24 2018-05-19 2018-07-18 Infrastructure Quotations Envelope Implementation Commodity Market in FCT NFCO-AF II-CW-NS-01-18 / Support to National research Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 38,046.00 0.00 2018-06-11 2018-07-16 2018-08-30 Institute for renovation of the Support Investment Program Quotations Envelope Implementation dilapidated facilities NFCO-AF II-CW-NS-02-18 / Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 16,340.00 0.00 2018-08-12 2018-10-07 2018-11-06 Renovation of Fadama House Support Investment Program Quotations Envelope Implementation LSFCO-CW-03-18 / Small-Scale Community-owned Single Stage - One Pending Construction of specialized IDA / 52930 Post Request for Bids Open - National 815,661.00 0.00 2018-03-12 2018-03-17 2018-04-28 2018-05-28 2018-07-02 2018-12-29 Infrastructure Envelope Implementation market with other facilities. LSFCO-CW-08-18 / Provision of Small-Scale Community-owned Request for Single Stage - One Pending Borehole for 2no Aggregation IDA / 52930 Post Limited 9,788.00 0.00 2018-03-10 2018-05-05 2018-11-01 Infrastructure Quotations Envelope Implementation Centers KNSFCO-CW-RFQ-1-18 / Small-Scale Community-owned Request for Single Stage - One Pending CONSTRUCTION OF 100 NOS IDA / 52930 Post Limited 16,390.00 0.00 2018-04-15 2018-06-10 2018-12-07 Infrastructure Quotations Envelope Implementation WASHBORES KNSFCO-CW-RFQ-2-18 / CONSTRUCTION 6 NOS Small-Scale Community-owned Request for Single Stage - One Pending IDA / 52930 Post Limited 4,910.00 0.00 2018-04-22 2018-06-17 2018-06-21 CONCRETE SLAB FOR RICE Infrastructure Quotations Envelope Implementation FARMERS KNSFCO-CW-RFQ-3-18 / Small-Scale Community-owned Request for Single Stage - One Pending DESILTING AND REPAIRS OF IDA / 52930 Post Limited 194,480.00 0.00 2018-04-29 2018-06-24 2018-12-21 Infrastructure Quotations Envelope Implementation EARTH DAM 12KM AT WATARI KNSFCO-CW-RFQ-4-18 / DESILTING/DREDGING AND Small-Scale Community-owned Request for Single Stage - One Pending IDA / 52930 Post Limited 327,500.00 0.00 2018-03-18 2018-05-13 2018-05-22 STONE PITCHING AT Infrastructure Quotations Envelope Implementation BUNKURE LIBC KNSFCO-CW-RFQ-7-18 / CONSTRUCTION OF 10 NOS Small-Scale Community-owned Request for Single Stage - One Pending BOREHOLE FOR YOUTH AND IDA / 52930 Post Limited 32,780.00 0.00 2018-05-07 2018-07-02 2018-07-08 Infrastructure Quotations Envelope Implementation WOMEN PRODUCTION CLUSTER NSFCO/RFQ/CW-01/018 / Construction of Culvert, Stone piching and reinforced concrete Small-Scale Community-owned Request for Single Stage - One Pending wall along 15.53km Feeder Road IDA / 52930 Post Limited 185,000.00 0.00 2018-03-25 2018-05-20 2018-11-16 Infrastructure Quotations Envelope Implementation at Majin-Gari Farm Settlement and Edozhigi Farm Settlement in Niger State NSFCO/RFQ/CW-02/018 / Construction of Culvert, Stone piching and reinforced concrete Small-Scale Community-owned Request for Single Stage - One Pending wall along 15.570km Feeder IDA / 52930 Post Limited 175,000.00 0.00 2018-04-01 2018-05-27 2018-11-23 Infrastructure Quotations Envelope Implementation Road at Loguma Farm Settlement and Baddegi Farm Settlement in Niger State NSFCO/RFQ/CW-03/018 / Construction of Head Works at Small-Scale Community-owned Request for Single Stage - One Pending IDA / 52930 Post Limited 190,000.00 0.00 2018-04-21 2018-06-16 2018-12-13 160ha Surface Irrigation Project Infrastructure Quotations Envelope Implementation at Edozhigi in Niger State NSFCO/RFQ/CW-04/018 / Construction of 860m Coveyance Canal, Tractor Crossing and Small-Scale Community-owned Request for Single Stage - One Pending Drilling of Tube wells at 140ha IDA / 52930 Post Limited 200,000.00 0.00 2018-04-28 2018-06-23 2018-12-20 Infrastructure Quotations Envelope Implementation Irrigation Project in Loguma and 130ha Irrigation Project in Egbanti in Niger State BSFCO/AF II/CAP/03/18 / Construction of market Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Open - National 123,000.00 0.00 2018-04-08 2018-06-03 2018-11-30 stalls/culverts etc in 25 Support Investment Program Quotations Envelope Implementation communities KGSFCO-CW-01-18 / Additional Small-Scale Community-owned Request for Single Stage - One Pending works on the 35.82km feeder IDA / 52930 Post Limited 163,934.00 0.00 2018-03-10 2018-05-05 2018-11-01 Infrastructure Quotations Envelope Implementation roads KGSFCO-CW-02-18 / Drilling of Small-Scale Community-owned Request for Single Stage - One Pending boreholes at the IDA / 52930 Post Limited 63,607.00 0.00 2018-03-03 2018-04-28 2018-10-25 Infrastructure Quotations Envelope Implementation aggregation/processing centres Page 1 KGSFCO-CW-03-18 / Small-Scale Community-owned Request for Single Stage - One Pending Construction of toilets at IDA / 52930 Post Limited 28,852.00 0.00 2018-03-31 2018-05-26 2018-11-22 Infrastructure Quotations Envelope Implementation processing centres KGSFCO-CW-04-18 / Perimeter Small-Scale Community-owned Request for Single Stage - One Pending fencing and demarcation of IDA / 52930 Post Limited 86,557.00 0.00 2018-03-24 2018-05-19 2018-11-15 Infrastructure Quotations Envelope Implementation processing sheds BOSFCO/AFII/CW/RFQ/2018/2 / Rehabilitation of Earth Dams, Small-Scale Community-owned Request for Single Stage - One Pending IDA / 52930 Post Limited 65,574.00 0.00 2018-03-17 2018-05-12 2018-11-08 Cannals and Ponds etc - Borno Infrastructure Quotations Envelope Implementation Central BOSFCO/AFII/CW/RFQ/2018/3 / Rehabilitation of Earth Dams, Small-Scale Community-owned Request for Single Stage - One Pending IDA / 52930 Post Limited 65,574.00 0.00 2018-03-17 2018-05-12 2018-11-08 Cannals and Ponds - Borno Infrastructure Quotations Envelope Implementation South BOSFCO/AFII/CW/RFQ/2018/4 / Rehabilitation of Earth Dams, Small-Scale Community-owned Request for Single Stage - One Pending IDA / 52930 Post Limited 65,574.00 0.00 2018-02-10 2018-04-07 2018-10-04 Cannals and Ponds - Borno Infrastructure Quotations Envelope Implementation North ADSFCO/AFII/CW/01/18 / Small-Scale Community-owned Request for Single Stage - One Pending Rehabilitation of small earth IDA / 58490 Post Limited 98,361.00 0.00 2018-04-20 2018-06-15 2018-12-12 Infrastructure Quotations Envelope Implementation Dams & Irrigation System,etc ADSFCO/AFII/CW/02/18 / Small-Scale Community-owned Request for Single Stage - One Pending Construction of Hand Pump IDA / 58490 Post Limited 112,328.00 0.00 2018-04-25 2018-06-20 2018-12-17 Infrastructure Quotations Envelope Implementation Boreholes, etc ADSFCO/AFII/CW/03/18 / Small-Scale Community-owned Request for Single Stage - One Pending Construction of infrastructure IDA / 58490 Post Limited 128,361.00 0.00 2018-04-25 2018-06-20 2018-12-17 Infrastructure Quotations Envelope Implementation (Shops & Market Stalls, etc) ADSFCO/AFII/CW/04/18 / Small-Scale Community-owned Request for Single Stage - One Pending Construction of infrastructure IDA / 58490 Post Limited 152,754.00 0.00 2018-05-02 2018-06-27 2018-12-24 Infrastructure Quotations Envelope Implementation (Culverts & Access Road, etc) BSFCO/AF II/CAP/01/18 / Rehabilitaiton of earthdam, Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 123,000.00 0.00 2018-04-08 2018-06-03 2018-11-30 boreholes, wells etc in 25 Support Investment Program Quotations Envelope Implementation communities BSFCO/AF II/CAP/02/18 / Food Security and Livelihoods Request for Single Stage - One Pending Provision of groundwater irrigation IDA / 58490 Post Limited 82,000.00 0.00 2018-04-08 2018-06-03 2018-11-30 Support Investment Program Quotations Envelope Implementation scheme in 25 communities BOSFCO/AFII/CW/RFQ/2018/1 Small-Scale Community-owned Request for Single Stage - One Pending / Drilling of Boreholes And IDA / 52930 Post Limited 262,300.00 0.00 2018-03-17 2018-05-12 2018-11-08 Infrastructure Quotations Envelope Implementation Tubewells GSFCO/AFII/CW/RFQ/07/18 / Rehabilitation of Earth dams, Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 120,220.00 0.00 2018-03-31 2018-05-26 2018-06-25 canals, Ponds, etc. in 22 Support Investment Program Quotations Envelope Implementation Communities GSFCO/AFII/CW/RFQ/08/18 / Provision of Boreholes, Ground Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 120,220.00 0.00 2018-03-31 2018-05-26 2018-06-25 Water Irrigation Scheme etc. in Support Investment Program Quotations Envelope Implementation 22 Communities GSFCO/AFII/CW/RFQ/09/18 / Construction of Market Stalls, Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 120,220.00 0.00 2018-03-31 2018-05-26 2018-06-25 Culverts, Veterinary Clinics, Lock- Support Investment Program Quotations Envelope Implementation up Shops etc. in 22 Communities GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Capacity Building, Local NFCO-AF-GO-RFQ-1-18 / Government, and Request for Single Stage - One Under Production of Quarterly Fadama IDA / 52930 Post Limited 42,480.00 0.00 2018-02-11 2018-02-15 2018-04-08 2019-02-07 Communications and Information Quotations Envelope Implementation III-AF Newsletter Support NFCO-AF-GO-RFQ-2-18 / Project Administration, Request for Single Stage - One Pending Procurement of Office IDA / 52930 Post Limited 980.00 0.00 2018-05-26 2018-07-21 2018-08-04 Monitoring and Evaluation Quotations Envelope Implementation Intercomms Accessories NFCO-AF-GO-RFQ-3-18 / Advisory Services and Input Request for Single Stage - One Pending Production of sample paper IDA / 52930 Post Limited 6,536.00 0.00 2018-04-09 2018-06-04 2018-06-18 Support Quotations Envelope Implementation voucher NFCO-AF-GO-RFQ-4-18 / Procurement of specialized Support to the ADPs and Request for Single Stage - One Pending IDA / 52930 Post Limited 3,270.00 0.00 2018-08-21 2018-10-16 2018-12-16 equipment to provide Institutional Adaptive Research Quotations Envelope Implementation Support NFCO-AF-GO-RFQ-7-18 / Procurement of multi functional Request for Single Stage - One Under IDA / 52930 Asset Acquisition Post Limited 25,800.00 0.00 2018-02-12 2018-02-14 2018-04-09 2018-06-08 and multi tool motorized mini Quotations Envelope Implementation tiller NFCO-AF-GO-RFQ-8-18 / Project Administration, Request for Single Stage - One Pending IDA / 52930 Post Limited 22,880.00 0.00 2018-03-10 2018-05-05 2018-05-19 Procurement of vehicle spares Monitoring and Evaluation Quotations Envelope Implementation NFCO-AF-GO-RFQ-9-18 / Office Project Administration, Request for Single Stage - One Under Equipments(printer,photocopier, IDA / 52930 Post Limited 13,400.00 0.00 2018-02-27 2018-04-24 2018-05-08 Monitoring and Evaluation Quotations Envelope Implementation scanner,laptop) NFCO-AF-GO-RFQ-10-18 / Project Administration, Request for Single Stage - One Under IDA / 52930 Post Limited 26,144.00 0.00 2018-02-20 2018-02-27 2018-04-17 2018-05-01 Supply of office Cosumables Monitoring and Evaluation Quotations Envelope Implementation Page 2 Capacity Building, Local NFCO-AF-GO-RFQ-11-18 / Government, and Request for Single Stage - One Under Mass production of study reports IDA / 52930 Post Limited 32,680.00 0.00 2018-03-04 2018-02-27 2018-04-29 2018-05-13 Communications and Information Quotations Envelope Implementation in publication form Support NFCO-AF-GO-RFQ-12-18 / Project Administration, Request for Single Stage - One Pending Supply of dispatch rider IDA / 52930 Post Limited 1,630.00 0.00 2018-03-12 2018-05-07 2018-05-21 Monitoring and Evaluation Quotations Envelope Implementation motorcycle NFCO-AF-GO-RFQ-13-18 / Procurement of Furniture and Request for Single Stage - One Pending IDA / 52930 Asset Acquisition Post Limited 98,039.00 0.00 2018-03-12 2018-05-07 2018-07-06 Cooling Equipment for Fadama Quotations Envelope Implementation Community Market in FCT NFCO-AF II-GO-NS-01-18 / Food Security and Livelihoods Request for Single Stage - One Pending Production of Household and IDA / 58490 Post Limited 19,445.00 0.00 2018-03-11 2018-05-06 2018-06-05 Support Investment Program Quotations Envelope Implementation Community Record Books NFCO-AF II-GO-NS-02-18 / Food Security and Livelihoods Request for Single Stage - One Pending Production of food assistance, IDA / 58490 Post Limited 1,945.00 0.00 2018-03-18 2018-05-13 2018-06-12 Support Investment Program Quotations Envelope Implementation Livelohood & input vouchers NFCO-AF II-GO-NS-03-18 / Food Security and Livelihoods Request for Single Stage - One Pending Production of crop, livestock, IDA / 58490 Post Limited 18,301.00 0.00 2018-03-25 2018-04-29 2018-05-29 Support Investment Program Quotations Envelope Implementation fisheries manuals NFCO-AF II-GO-NS-04-18 / Production of extension Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 16,340.00 0.00 2018-05-07 2018-07-02 2018-08-01 documentary for farmers across Support Investment Program Quotations Envelope Implementation North East NFCO-AF II-GO-NS-05-18 / Mass production of studies, Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 32,680.00 0.00 2018-10-15 2018-12-10 2019-01-19 assesment & Consultants' Support Investment Program Quotations Envelope Implementation reports form inception NFCO-AF II-GO-NS-06-18 / Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 16,340.00 0.00 2018-04-09 2018-05-14 2018-06-13 Office consumables Support Investment Program Quotations Envelope Implementation NFCO-AF II-GO-NS-07-18 / Food Security and Livelihoods Request for Single Stage - One Pending Procurement of Office equipment IDA / 58490 Post Limited 14,657.00 0.00 2018-04-23 2018-06-11 2018-07-11 Support Investment Program Quotations Envelope Implementation for Supervising agencies NFCO-AF II-GO-NS-08-18 / Support to National Research Food Security and Livelihoods Request for Single Stage - One Under Institute for procurement of IDA / 58490 Post Limited 31,863.00 0.00 2018-04-02 2018-03-06 2018-05-01 2018-05-31 Support Investment Program Quotations Envelope Implementation equipment ( 60KVA genrator & others) LSFCO-GO-01-18 / procurement of simple tools for road Request for Single Stage - One Pending maintenance and repairs such as IDA / 52930 Asset Acquisition Post Limited 4,894.00 0.00 2018-04-14 2018-06-09 2018-12-06 Quotations Envelope Implementation wheel barrow, cutlass ,digger, measuring tape, shovel , LSFCO-GO-05-18 / Procurement Project Administration, Request for Single Stage - One Pending IDA / 52930 Post Limited 8,972.00 0.00 2018-05-02 2018-06-27 2018-12-24 of Photocopier, Ac and Generator Monitoring and Evaluation Quotations Envelope Implementation Capacity Building, Local LSFCO-GO-07-18 / Production Government, and Request for Single Stage - One Pending of site demarcation/location IDA / 52930 Post Limited 3,263.00 0.00 2018-04-14 2018-06-09 2018-12-06 Communications and Information Quotations Envelope Implementation boards. Support Capacity Building, Local KNSFCO-GO-RFQ-1-18 / Government, and Request for Single Stage - One Pending PROCUREMENT OF MEDIA IDA / 52930 Post Limited 8,830.00 0.00 2018-02-24 2018-04-21 2018-05-31 Communications and Information Quotations Envelope Implementation EQUIPMENT Support KNSFCO-GO-RFB-2-18 / Single Stage - One Pending PROCUREMENT OF IDA / 52930 Asset Acquisition Post Request for Bids Open - National 363,930.00 0.00 2018-03-14 2018-03-19 2018-04-30 2018-05-30 2018-07-04 2018-07-13 Envelope Implementation PROCESSING EQUIPMENT KNSFCO-GO-RFQ-3-18 / Request for Single Stage - One Pending PROCUREMENT OF TRACTOR IDA / 52930 Asset Acquisition Post Limited 2,620.00 0.00 2018-03-12 2018-05-07 2018-05-11 Quotations Envelope Implementation TRACKING EQUIPMENT KNSFCO-GO-RFQ-4-18 / Request for Single Stage - One Pending PROCUREMENT OF WATER IDA / 52930 Asset Acquisition Post Limited 81,960.00 0.00 2018-03-19 2018-05-14 2018-11-10 Quotations Envelope Implementation PUMPS-SPRAYERS-CRATES KMSFCO-GO-RFQ-5-18 / Project Administration, Request for Single Stage - One Pending PROCREMENT OF 30KVA IDA / 52930 Post Limited 16,340.00 0.00 2018-04-02 2018-05-28 2018-06-27 Monitoring and Evaluation Quotations Envelope Implementation GENERATOR KNSFCO-GO-RFQ-6 / Project Administration, Request for Single Stage - One Pending PROCUREMENT OF LIGHT IDA / 52930 Post Limited 3,930.00 0.00 2018-04-08 2018-06-03 2018-07-03 Monitoring and Evaluation Quotations Envelope Implementation TRAP FOR INSECTS NSFCO/RFQ/GO-02/018 / Request for Single Stage - One Pending Tractor Tracking equipment for 10 IDA / 52930 Asset Acquisition Post Limited 30,000.00 0.00 2018-03-10 2018-05-05 2018-11-01 Quotations Envelope Implementation Tractors Capacity Building, Local AN/SFCO/PROC/GO/RFQ/18/01 Government, and Request for Single Stage - One Pending IDA / 52930 Post Limited 1,635.00 0.00 2018-03-15 2018-05-10 2018-11-06 / Provision of extension leaflets Communications and Information Quotations Envelope Implementation Support Capacity Building, Local AN/SFCO/PROC/GO/RFQ/18/02 Government, and Request for Single Stage - One Pending / Quarterly Production of IDA / 52930 Post Limited 5,220.00 0.00 2018-02-17 2018-04-14 2018-10-11 Communications and Information Quotations Envelope Implementation Newsletter Support Capacity Building, Local AN/SFCO/PROC/GO/RFQ/18/03 Government, and Request for Single Stage - One Pending / Production of Farm Record IDA / 52930 Post Limited 3,265.00 0.00 2018-02-11 2018-04-08 2018-10-05 Communications and Information Quotations Envelope Implementation books in Igbo Language Support Page 3 AN/SFCO/PROC/GO/RFQ/18/04 Support to the ADPs and Request for Single Stage - One Pending / Installation of Solar Panel IDA / 52930 Post Limited 3,265.00 0.00 2018-02-25 2018-04-22 2018-10-19 Adaptive Research Quotations Envelope Implementation (Support to ADP) AN/SFCO/PROC/GO/RFQ/18/05 Request for Single Stage - One Pending / Tractor Tracking Equipment and IDA / 52930 Asset Acquisition Post Limited 10,440.00 0.00 2018-03-17 2018-05-12 2018-11-08 Quotations Envelope Implementation Data Capturing AN/SFCO/PROC/GO/RFQ/18/06 Project Administration, Request for Single Stage - One Pending / Procurement of 2 Laptops and IDA / 52930 Post Limited 2,610.00 0.00 2018-02-13 2018-04-10 2018-10-07 Monitoring and Evaluation Quotations Envelope Implementation Acceccories AN/SFCO/PROC/GO/RFQ/18/07 Project Administration, Request for Single Stage - One Pending / Production of Farmers Photo IDA / 52930 Post Limited 3,265.00 0.00 2018-10-08 2018-12-03 2019-06-01 Monitoring and Evaluation Quotations Envelope Implementation Album ENSFCO/GO/18/01 / Production Capacity Building, Local of Enugu Fadama III Project Government, and Request for Single Stage - One Pending IDA / 52930 Post Limited 4,918.00 0.00 2018-11-12 2019-01-07 2019-07-06 Additional Financing 1 Communications and Information Quotations Envelope Implementation Compendium Support Capacity Building, Local ENSFCO/GO/18/02 / Production Government, and Request for Single Stage - One Pending of Information, Educational and IDA / 52930 Post Limited 1,639.00 0.00 2018-04-10 2018-06-05 2018-12-02 Communications and Information Quotations Envelope Implementation Communication Materials. Support ENSFCO/GO/18/03 / Procurement of one number (1) 5kva Inverter with four (4) Support to the ADPs and Request for Single Stage - One Under IDA / 52930 Post Limited 2,131.00 0.00 2018-03-04 2018-03-04 2018-04-29 2018-10-26 batteries for Enugu State Adaptive Research Quotations Envelope Implementation Agricultural Ptogramme ICT Center ENSFCO/GO/18/04 / Request for Single Stage - One Pending Procurement of two (2) sets of IDA / 52930 Asset Acquisition Post Limited 85,246.00 0.00 2018-03-17 2018-05-12 2018-11-08 Quotations Envelope Implementation Tractors ENSFCO/GO/18/05 / Procurement and installation of Request for Single Stage - One Pending IDA / 52930 Asset Acquisition Post Limited 3,410.00 0.00 2018-03-26 2018-05-21 2018-11-17 two (2) sets of Tractors tracking Quotations Envelope Implementation equipment and data capture ENSFCO/GO/18/06 / Procurement of Road Signs for Installation at strategic locations Project Administration, Request for Single Stage - One Pending on various roads rehabilitated or IDA / 52930 Post Limited 3,148.00 0.00 2018-03-20 2018-05-15 2018-11-11 Monitoring and Evaluation Quotations Envelope Implementation constructed by Enugu State FADAMA III Project Additional Financing 1. ENSFCO/GO/18/07 / Project Administration, Request for Single Stage - One Under Procurement of five (5) numbers IDA / 52930 Post Limited 1,721.00 0.00 2018-03-05 2018-03-05 2018-04-30 2018-10-27 Monitoring and Evaluation Quotations Envelope Implementation of Hand held GPS Equipment BSFCO/AF II/NS/01/18 / food Food Security and Livelihoods Request for Single Stage - One Pending items for IDPs Bauchi North IDA / 58490 Post Limited 55,000.00 0.00 2018-03-17 2018-05-12 2018-06-11 Support Investment Program Quotations Envelope Implementation Senatorial District BSFCO/AF II/CS/04/18 / Food Security and Livelihoods Request for Single Stage - One Pending Provision of non-farm livelihood IDA / 58490 Post Limited 137,000.00 0.00 2018-03-24 2018-05-19 2018-06-18 Support Investment Program Quotations Envelope Implementation support BSFCO/AF II/CS/05/18 / Food Security and Livelihoods Request for Single Stage - One Pending Provision of crop livelihood IDA / 58490 Post Limited 137,000.00 0.00 2018-03-24 2018-05-19 2018-06-18 Support Investment Program Quotations Envelope Implementation support BSFCO/AF II/CS/06/18 / Food Security and Livelihoods Request for Single Stage - One Pending Provision of livestock/fisheries IDA / 58490 Post Limited 137,000.00 0.00 2018-03-24 2018-05-19 2018-06-18 Support Investment Program Quotations Envelope Implementation livelihood support KGSFCO-GO-01-18 / Production Capacity Building, Local of information, Education and Government, and Request for Single Stage - One Pending IDA / 52930 Post Limited 1,607.00 0.00 2018-03-20 2018-05-15 2018-11-11 Communication materials and Communications and Information Quotations Envelope Implementation roll-up banners Support Capacity Building, Local KGSFCO-GO-02-18 / Production Government, and Request for Single Stage - One Pending IDA / 52930 Post Limited 2,000.00 0.00 2018-08-18 2018-10-13 2019-04-11 of farmers photo album Communications and Information Quotations Envelope Implementation Support BOSFCO/AFII/GO/RFQ/2018/04 Food Security and Livelihoods Request for Single Stage - One Pending / Provision of Livestock and IDA / 52930 Post Limited 327,870.00 0.00 2018-03-10 2018-05-05 2018-11-01 Support Investment Program Quotations Envelope Implementation Fisheries for Livelihood Support BOSFCO/AFII/GO/RFQ/2018/05 Food Security and Livelihoods Request for Single Stage - One Pending / Provision of Crop for Livelihood IDA / 52930 Post Limited 163,935.00 0.00 2018-03-10 2018-05-05 2018-11-01 Support Investment Program Quotations Envelope Implementation Support BOSFCO/AFII/GO/RFQ/2018/06 Food Security and Livelihoods Request for Single Stage - One Pending / Provision of Non-Farm for IDA / 52930 Post Limited 163,935.00 0.00 2018-03-10 2018-05-05 2018-11-01 Support Investment Program Quotations Envelope Implementation Livelihood Support BOSFCO/AFII/GO/RFQ/2018/07 Request for Single Stage - One Pending IDA / 52930 Asset Acquisition Post Limited 787.00 0.00 2018-02-17 2018-04-14 2018-10-11 / Procurement Four Refrigerators Quotations Envelope Implementation ADSFCO/AFII/GO/01/18 / Food Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 65,574.00 0.00 2018-03-21 2018-05-16 2018-11-12 Items to IDPs (Northern Zone) Support Investment Program Quotations Envelope Implementation ADSFCO/AFII/GO/02/18 / Food Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 65,574.00 0.00 2018-03-21 2018-05-16 2018-11-12 Items to IDPs (Central Zone) Support Investment Program Quotations Envelope Implementation ADSFCO/AFII/GO/03/18 / Food Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 65,574.00 0.00 2018-03-21 2018-05-16 2018-11-12 Items to IDPs (Southern Zone) Support Investment Program Quotations Envelope Implementation ADSFCO/AFII/GO/04/18 / Request for Single Stage - One Pending Provision of Crops for Livelihood IDA / 58490 Asset Acquisition Post Limited 262,296.00 0.00 2018-04-07 2018-06-02 2018-11-29 Quotations Envelope Implementation Support IDPs Page 4 ADSFCO/AFII/GO/05/18 / Provision of Livestock & Request for Single Stage - One Pending IDA / 58490 Asset Acquisition Post Limited 196,722.00 0.00 2018-04-14 2018-06-09 2018-12-06 Fisheries Livelihood Support to Quotations Envelope Implementation IDPs ADSFCO/AFII/GO/06/18 / Request for Single Stage - One Pending Provision of Non-Farm Livelihood IDA / 58490 Asset Acquisition Post Limited 32,787.00 0.00 2018-04-14 2018-06-09 2018-12-06 Quotations Envelope Implementation Support to IDPs. GSFCO/AF II/GDS/RFQ/01/18 / Food Security and Livelihoods Request for Single Stage - One Under Food Items to IDPs - Gombe IDA / 52930 Post Limited 48,087.00 0.00 2018-03-10 2018-05-05 2018-06-04 Support Investment Program Quotations Envelope Implementation North Senatorial District GSFCO/AF II/GDS/RFQ/02/18 / Food Security and Livelihoods Request for Single Stage - One Under Food Items to IDPs - Gombe IDA / 52930 Post Limited 48,087.00 0.00 2018-03-10 2018-05-05 2018-06-04 Support Investment Program Quotations Envelope Implementation Central Senatorial District GSFCO/AF II/GDS/RFQ/03/18 / Food Security and Livelihoods Request for Single Stage - One Under Food Items to IDPs - Gombe IDA / 52930 Post Limited 48,087.00 0.00 2018-03-10 2018-05-05 2018-06-04 Support Investment Program Quotations Envelope Implementation South Senatorial District GSFCO/AF II/GDS/RFQ/04/18 / Food Security and Livelihoods Request for Single Stage - One Pending Provision of Crop Livelihood IDA / 52930 Post Limited 120,000.00 0.00 2018-03-24 2018-05-19 2018-06-18 Support Investment Program Quotations Envelope Implementation Support to IDPs GSFCO/AF II/GDS/RFQ/06/18 / Request for Single Stage - One Pending Provision of Non- Farm Livelihood IDA / 52930 Asset Acquisition Post Limited 120,000.00 0.00 2018-03-24 2018-05-19 2018-06-18 Quotations Envelope Implementation Support to IDPs NG-BAUCHI NFDPIII ADF 2- 48553-GO-RFQ / food items for Food Security and Livelihoods Request for Single Stage - One Pending IDA / 58490 Post Limited 55,000.00 0.00 2018-03-17 2018-05-12 2018-11-08 IDPs Bauchi South Senatorial Support Investment Program Quotations Envelope Implementation District BSFCO/AF II/NS/02/18 / food Food Security and Livelihoods Request for Single Stage - One Pending items for IDPs Bauchi Central IDA / 58490 Post Limited 55,000.00 0.00 2018-03-17 2018-05-12 2018-06-11 Support Investment Program Quotations Envelope Implementation Senatorial District NFCO-AF-GO-RFQ-5-18 / Request for Single Stage - One Pending Procurement of 10 No tractor for IDA / 52930 Asset Acquisition Post Limited 458,000.00 0.00 2018-03-06 2018-05-01 2018-06-30 Quotations Envelope Implementation 5 PC States NFCO-AF-GO-RFQ-6-18 / Request for Single Stage - One Pending Procurement of tipping trailer and IDA / 52930 Asset Acquisition Post Limited 98,039.00 0.00 2018-03-06 2018-05-01 2018-06-30 Quotations Envelope Implementation other equipment GSFCO/AF II/GDS/RFQ/05/18 / Food Security and Livelihoods Request for Single Stage - One Pending Provision of Live Stock/ Fisheries IDA / 58490 Post Limited 120,000.00 0.00 2018-03-24 2018-05-19 2018-06-18 Support Investment Program Quotations Envelope Implementation Livelihood Support to IDPs NSFCO/RFQ/GO-01/018 / Request for Single Stage - One Pending Procurement of Generator for ICT IDA / 52930 Asset Acquisition Post Limited 1,000.00 0.00 2018-03-24 2018-04-18 2018-04-25 Quotations Envelope Implementation Centre NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NFCO-AF-NC-DIR-1-18 / Hosting Project Administration, Pending of Fadama III AF unmanaged IDA / 52930 Post Direct Selection Direct 5,140.00 0.00 2018-06-21 2018-06-26 2018-07-31 2019-01-27 Monitoring and Evaluation Implementation website NFCO-AF-NC-DIR-2-18 / Project Administration, Pending Upgrade of Project GIS IDA / 52930 Post Direct Selection Direct 800.00 0.00 2018-05-04 2018-05-09 2018-06-13 2018-07-13 Monitoring and Evaluation Implementation Laboratory NFCO-AF-NC-DIR-3-18 / Project Administration, Pending Renewal of contract for Vehicles IDA / 52930 Post Direct Selection Direct 45,750.00 0.00 2018-03-06 2018-03-11 2018-04-15 2018-05-15 Monitoring and Evaluation Implementation Insurance NFCO-AF-NC-DIR-4-18 / Project Administration, Pending Renewal of contract for Elevator IDA / 52930 Post Direct Selection Direct 6,540.00 0.00 2018-03-19 2018-03-24 2018-04-28 2018-11-19 Monitoring and Evaluation Implementation maintenance NFCO-AF-NC-DIR-5-18 / Project Administration, Pending Renewal of contract for cleaning IDA / 52930 Post Direct Selection Direct 11,760.00 0.00 2018-10-01 2018-10-06 2018-11-10 2019-09-30 Monitoring and Evaluation Implementation services for Fadama House NFCO-AF-NC-DIR-6-18 / Project Administration, Pending Renewal of contract for security IDA / 52930 Post Direct Selection Direct 11,760.00 0.00 2018-08-01 2018-08-06 2018-09-10 2019-08-01 Monitoring and Evaluation Implementation services for Fadama House NFCO-AF-NC-DIR-7-18 / Project Administration, Pending Renewal of contract for Arc GIS IDA / 52930 Post Direct Selection Direct 12,460.00 0.00 2018-03-08 2018-03-13 2018-04-17 2018-05-17 Monitoring and Evaluation Implementation online Licencing NFCO-AF-NC-RFQ-1-18 / Project Administration, Request for Single Stage - One Under Deployment of high Capacity IDA / 52930 Post Limited 19,610.00 0.00 2018-02-14 2018-02-28 2018-04-11 2018-04-25 Monitoring and Evaluation Quotations Envelope Implementation internet Services NFCO-AF II-NC-DIR-01-18 / Project Administration, Pending IDA / 58490 Post Direct Selection Direct 4,901.00 0.00 2018-03-01 2018-03-06 2018-04-10 2018-05-10 Vehicles premium insurance Monitoring and Evaluation Implementation NFCO-AF-NC-DIR-8-18 / Supply and Installation of Tracking Project Administration, Pending IDA / 52930 Post Direct Selection Direct 115,410.00 0.00 2018-02-19 2018-02-24 2018-03-31 2018-09-27 Device on 44 Tractors and Mobile Monitoring and Evaluation Implementation App CONSULTING FIRMS Page 5 Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ENSFCO/CS/18/10 / Enviromental Audit of activities Consultant Project Administration, Pending under Fadama III Project IDA / 52930 Post Qualification Open - National 11,475.00 0.00 2018-04-16 2018-05-07 2018-06-20 2018-07-20 2018-08-24 2019-02-20 Monitoring and Evaluation Implementation Additional Financing 1, Enugu Selection State Consultant KGSFCO-CS-02-18 / Conduct of Project Administration, Pending IDA / 52930 Post Qualification Open - National 26,230.00 0.00 2018-05-21 2018-06-11 2018-07-25 2018-08-24 2018-09-28 2019-03-27 environmental and social audit Monitoring and Evaluation Implementation Selection Consultant KGSFCO-CS-03-18 / Conduct of Small-Scale Community-owned Pending IDA / 52930 Post Qualification Open - National 11,475.00 0.00 2018-04-16 2018-05-07 2018-06-20 2018-07-20 2018-08-24 2019-02-20 pest study Infrastructure Implementation Selection Capacity Building, Local KGSFCO-CS-06-18 / Production Consultant Government, and Pending of documentary-'The Journey So IDA / 52930 Post Qualification Open - National 10,492.00 0.00 2018-08-18 2018-09-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 Communications and Information Implementation Far Fadama III AF' Selection Support Capacity Building, Local KGSFCO-CS-071-18 / Consultant Government, and Pending Production of TV & Radio IDA / 52930 Post Qualification Open - National 9,836.00 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2019-01-19 Communications and Information Implementation Jingles for Fadama III AF Selection Support INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NFCO-AF-CS-INDV-1-18 / Engagement of consultant for the Advisory Services and Input Individual Consultant Pending IDA / 52930 Post Limited 8,480.00 0.00 2018-03-29 2018-04-03 2018-04-24 2018-05-29 2018-06-28 Development of Tomato Package Support Selection Implementation of Practices NFCO-AF-CS-INDV-2-18 / Consultant to evaluate ASIC and Advisory Services and Input Individual Consultant Pending IDA / 52930 Post Limited 20,530.00 0.00 2018-04-24 2018-04-29 2018-05-20 2018-06-24 2018-07-24 SMART Farmer Support Selection Implementation Performance/Record Books NFCO-AF-CS-INDV-3-18 / Advisory Services and Input Individual Consultant Pending Upgrade of Fadama III AF input IDA / 52930 Post Limited 40,930.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-06-14 Support Selection Implementation voucher platform NFCO-AF-CS-INDV-4-18 / Engagement of consultant for Support to the ADPs and Individual Consultant Pending Development of new e - IDA / 52930 Post Limited 6,540.00 0.00 2018-02-28 2018-03-05 2018-03-26 2018-04-30 2018-05-30 Adaptive Research Selection Implementation extension platform for data capturing and SMS broadcast NFCO-AF-CS-INDV-5-18 / Engagement of consultant to Advisory Services and Input Individual Consultant Pending IDA / 52930 Post Limited 14,500.00 0.00 2018-11-08 2018-11-13 2018-12-04 2019-01-08 2019-03-09 develop Extension and Advisory Support Selection Implementation Services Guidelines NFCO-AF-CS-INDV-6-18 / Engagement of consultant for Support to the ADPs and Individual Consultant Under IDA / 52930 Post Limited 53,920.00 0.00 2018-02-02 2018-02-14 2018-02-07 2018-02-22 2018-02-28 2018-04-04 2018-05-04 Rice, Cassava, Sorghum and Adaptive Research Selection Implementation Tomato value chain development NFCO-AF-CS-INDV-7-18 / Project Administration, Individual Consultant Pending Engagement of Procurement IDA / 52930 Prior Limited 62,750.00 0.00 2018-06-01 2018-06-06 2018-06-27 2018-08-01 2019-01-28 Monitoring and Evaluation Selection Implementation Consultants NFCO-AF-CS-INDV-8-18 / Engagenent of consultant for Advisory Services and Input Individual Consultant Pending Production of Management IDA / 52930 Post Limited 16,340.00 0.00 2018-03-09 2018-03-14 2018-04-04 2018-05-09 2018-06-08 Support Selection Implementation Practice Log book on Management of Tuta Absoluta Capacity Building, Local NFCO-AF-CS-INDV-9-18 / Government, and Individual Consultant Pending Documentaries on Fadama AF IDA / 52930 Post Limited 49,020.00 0.00 2018-03-16 2018-03-21 2018-04-11 2018-05-16 2018-07-15 Communications and Information Selection Implementation the journey so far Support NFCO-AF II-CS-INDV-01-18 / Food Security and Livelihoods Individual Consultant Under Consultancy on Media and IDA / 58490 Post Limited 26,144.00 0.00 2018-02-06 2018-02-15 2018-02-11 2018-02-16 2018-02-20 2018-02-27 2018-03-03 2018-08-30 Support Investment Program Selection Implementation Communication NFCO-AF II-CS-INDV-02-18 / Consultancy on ducumentary of Food Security and Livelihoods Individual Consultant Pending AF II success stories in IDA / 58490 Post Limited 16,340.00 0.00 2018-10-23 2018-10-28 2018-11-18 2018-12-23 2019-02-06 Support Investment Program Selection Implementation Adamawa, Borno and Yobe States NFCO-AF II-CS-INDV-03-18 / Consultancy on documentary of Food Security and Livelihoods Individual Consultant Pending IDA / 58490 Post Limited 16,340.00 0.00 2018-10-23 2018-10-28 2018-11-18 2018-12-23 2019-02-06 AF II success stories in Bauchi, Support Investment Program Selection Implementation Gombe and Taraba States NFCO-AF II-CS-INDV-04-18 / Project Administration, Individual Consultant Pending Agricultural Geo-database IDA / 58490 Post Limited 21,242.00 0.00 2018-05-23 2018-05-28 2018-06-18 2018-07-23 2018-09-21 Monitoring and Evaluation Selection Implementation development for North East NFCO-AF II-CS-INDV-05-18 / Food Security and Livelihoods Individual Consultant Pending IDA / 58490 Post Limited 6,536.00 0.00 2018-08-30 2018-09-04 2018-09-25 2018-10-30 2018-12-14 Financial management review Support Investment Program Selection Implementation NFCO-AF II-CS-INDV-06-18 / Food Security and Livelihoods Individual Consultant Pending IDA / 58490 Post Limited 16,340.00 0.00 2018-09-04 2018-09-09 2018-09-30 2018-11-04 2018-12-19 Procurement management review Support Investment Program Selection Implementation NFCO-AF II-CS-INDV-07-18 / Food Security and Livelihoods Individual Consultant Pending Studies on status of malnutrition IDA / 58490 Post Limited 16,340.00 0.00 2018-05-31 2018-06-05 2018-06-26 2018-07-10 2018-09-08 Support Investment Program Selection Implementation in the intervening communities Page 6 LSFCO-CS-01-18 / Production of Capacity Building, Local TV/Radio Jingles in Pidgin, Government, and Individual Consultant Pending IDA / 52930 Post Limited 1,631.00 0.00 2018-05-04 2018-05-09 2018-05-30 2018-07-04 2018-12-31 English & Yoruba languages for Communications and Information Selection Implementation awareness creation Support LSFCO-CS-04-18 / Scripting, Capacity Building, Local Editing and Production of Government, and Individual Consultant Pending IDA / 52930 Post Limited 9,788.00 0.00 2018-06-04 2018-06-09 2018-06-30 2018-08-04 2019-01-31 Agricultural Communications and Information Selection Implementation Magazine/Bulletin/News Letter Support Capacity Building, Local LSFCO-CS-06-18 / Scripting, Government, and Individual Consultant Pending Editing and Documentaries - IDA / 52930 Post Limited 3,915.00 0.00 2018-07-02 2018-07-07 2018-07-28 2018-09-01 2019-02-28 Communications and Information Selection Implementation Journey So Far II& III Support LSFCO-CS-07-18 / Engagement of Center Pivot Irrigation System Small-Scale Community-owned Individual Consultant Pending (CPIS) service provider on 1-year IDA / 52930 Post Limited 13,051.00 0.00 2018-04-17 2018-04-22 2018-05-13 2018-06-17 2018-12-14 Infrastructure Selection Implementation operation, maintenance and replacement. LSFCO-CS-08-18 / Supervision Project Administration, Individual Consultant Pending IDA / 52930 Post Limited 13,051.00 0.00 2018-04-22 2018-04-27 2018-05-18 2018-06-22 2018-12-19 on Market infrastructure Monitoring and Evaluation Selection Implementation LSFCO-CS-10-18 / Engagement Advisory Services and Input Individual Consultant Pending of Consultant on Productivity IDA / 52930 Post Limited 9,788.00 0.00 2018-05-08 2018-05-13 2018-06-03 2018-07-08 2019-01-04 Support Selection Implementation improvement of selected crop LSFCO-CS-11-18 / Preparation Project Administration, Individual Consultant Pending and Evaluation of site specific IDA / 52930 Post Limited 2,284.00 0.00 2018-04-23 2018-04-28 2018-05-19 2018-06-23 2018-12-20 Monitoring and Evaluation Selection Implementation ESMPs (irrigation sites e.t.c.) KNSFCO-CS-INDV-1-18 / Small-Scale Community-owned Individual Consultant Pending IDA / 52930 Post Limited 8,580.00 0.00 2018-05-09 2018-05-14 2018-06-04 2018-07-09 2018-07-09 SUPERVISION OF ROADS Infrastructure Selection Implementation KNSFCO-CS-INDV-2-18 / CONDUCT SURVEY ON Project Administration, Individual Consultant Pending IDA / 52930 Post Limited 9,840.00 0.00 2018-05-16 2018-05-21 2018-06-11 2018-07-16 2018-09-14 STATUS OF PROJECT Monitoring and Evaluation Selection Implementation IMPLEMENTATION KNSFCO-CS-INDV-3-18 / PEST Project Administration, Individual Consultant Pending IDA / 52930 Post Limited 9,840.00 0.00 2018-06-07 2018-06-12 2018-07-03 2018-08-07 2018-11-05 SURVEY Monitoring and Evaluation Selection Implementation NSFCO/CS/INDV-04/018 / Project Administration, Individual Consultant Pending Evironmental Audit of Fadama III IDA / 52930 Post Limited 12,000.00 0.00 2018-05-15 2018-05-20 2018-06-10 2018-07-15 2019-01-11 Monitoring and Evaluation Selection Implementation Additional Financing NSFCO/CS/INDV-02/018 / Beneficiary Impact Evaluation Project Administration, Individual Consultant Pending IDA / 52930 Post Limited 15,000.00 0.00 2018-07-12 2018-07-17 2018-08-07 2018-09-11 2019-03-10 Study of Fadama III Additional Monitoring and Evaluation Selection Implementation Financing LSFCO-CS-14-18 / Project Administration, Individual Consultant Pending Environmental Audit of Fadama III IDA / 52930 Post Limited 16,313.00 0.00 2018-07-04 2018-07-09 2018-07-30 2018-09-03 2019-03-02 Monitoring and Evaluation Selection Implementation AF LSFCO-CS-12-18 / Pest Survey Project Administration, Individual Consultant Pending IDA / 52930 Post Limited 11,419.00 0.00 2018-04-23 2018-04-28 2018-05-19 2018-06-23 2018-12-20 Conducted Monitoring and Evaluation Selection Implementation LSCO-CS-01-18 / Beneficiaries Impact Assessment Study ( Project Administration, Individual Consultant Pending Independent Review and IDA / 52930 Post Limited 16,313.00 0.00 2018-05-22 2018-05-27 2018-06-17 2018-07-22 2019-01-18 Monitoring and Evaluation Selection Implementation Assessment of Project Beneficiaries) AN/SFCO/PROC/CS/INDV/18/08 / Engagement of Service provider Small-Scale Community-owned Individual Consultant Pending IDA / 52930 Post Limited 6,525.00 0.00 2018-04-16 2018-04-21 2018-05-12 2018-06-16 2018-12-13 for 1yr training on Central Pivot Infrastructure Selection Implementation and Irrigation System (CPIS). AN/SFCO/PROC/CS/INDV/18/09 Project Administration, Individual Consultant Pending / Environmental Audit for Fadama IDA / 52930 Post Limited 22,840.00 0.00 2018-07-08 2018-07-13 2018-08-03 2018-09-07 2019-03-06 Monitoring and Evaluation Selection Implementation III AF AN/SFCO/PROC/CS/INDV/18/10 Project Administration, Individual Consultant Pending IDA / 52930 Post Limited 11,420.00 0.00 2018-06-03 2018-06-08 2018-06-29 2018-08-03 2019-01-30 / Pest Survey Monitoring and Evaluation Selection Implementation AN/SFCO/PROC/CS/INDV/18/11 Project Administration, Individual Consultant Pending / Agricultural Waste IDA / 52930 Post Limited 6,525.00 0.00 2018-07-23 2018-07-28 2018-09-08 2018-10-13 2019-04-11 Monitoring and Evaluation Selection Implementation Management AN/SFCO/PROC/CS/INDV/18/12 / Installation of Road Sign at Project Administration, Individual Consultant Pending IDA / 52930 Post Limited 1,635.00 0.00 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2018-12-07 strategic locations for Roads and Monitoring and Evaluation Selection Implementation Irrigation Project AN/SFCO/PROC/CS/INDV/18/13 Project Administration, Individual Consultant Pending / Preparation of Environmental IDA / 52930 Post Limited 1,631.00 0.00 2018-04-20 2018-04-25 2018-05-16 2018-06-20 2018-12-17 Monitoring and Evaluation Selection Implementation Project Site Specific ESMP ENSFCO/CS/18/08 / Production Capacity Building, Local and airing of Documentaries - Government, and Individual Consultant Pending IDA / 52930 Post Limited 1,639.00 0.00 2018-05-03 2018-05-08 2018-05-29 2018-07-03 2018-12-30 Journey So Far (Success Communications and Information Selection Implementation Stories) Support ENSFCO/CS/18/11 / Environmental and Social Impact Project Administration, Individual Consultant Pending IDA / 52930 Post Limited 4,918.00 0.00 2018-04-23 2018-04-28 2018-05-19 2018-06-23 2018-12-20 (ESMPs) on all irrigation sites in Monitoring and Evaluation Selection Implementation Enugu State. KGSFCO-CS-01-18 / Design Small-Scale Community-owned Individual Consultant Pending and supervision of additional IDA / 52930 Post Direct 26,625.00 0.00 2018-02-12 2018-02-22 2018-03-15 2018-04-19 2018-10-16 Infrastructure Selection Implementation works KGSFCO-CS-04-18 / Impact Project Administration, Individual Consultant Pending IDA / 52930 Post Direct 21,311.00 0.00 2018-10-31 2018-11-10 2018-12-01 2019-01-05 2019-07-04 evaluation study Monitoring and Evaluation Selection Implementation Page 7 KGSFCO-CS-05-18 / ICR Project Administration, Individual Consultant Pending IDA / 52930 Post Direct 16,393.00 0.00 2018-10-31 2018-11-10 2018-12-01 2019-01-05 2019-07-04 preparation and review Monitoring and Evaluation Selection Implementation BOSFCO/AFII/CS/RFQ/2018/1 / Advisory Services and Input Individual Consultant Pending IDA / 52930 Post Limited 9,840.00 0.00 2018-04-05 2018-04-10 2018-05-01 2018-06-05 2018-12-02 Extension content development Support Selection Implementation BOSFCO/AFII/CS/RFQ/2018/2 / Advisory Services and Input Individual Consultant Pending Provision of requied advisory and IDA / 52930 Post Limited 9,180.00 0.00 2018-03-05 2018-03-10 2018-03-31 2018-05-05 2018-11-01 Support Selection Implementation extension services NSFCO/CS/CDS-01/018 / Small-Scale Community-owned Pending Supervision of Feeder Road IDA / 52930 Post Direct Selection Direct 20,000.00 0.00 2018-03-26 2018-04-05 2018-06-09 2018-12-06 Infrastructure Implementation Construction NSFCO/CS/INDV-03/018 / Pest Project Administration, Individual Consultant Pending Surveying of Fadama III IDA / 52930 Post Limited 10,000.00 0.00 2018-04-16 2018-04-21 2018-05-12 2018-05-25 2018-08-28 Monitoring and Evaluation Selection Implementation Additional Financing Page 8