Procurement Plan (For Contracts not yet initiated – to be entered in STEP) I. General 1. Project Information Country: Malawi Project Name: Shire Valley Transformation Program - 1 Project ID: P158805 2. Project Implementation Agency: Ministry of Agriculture, Irrigation and Water Development 3. Date of the Procurement Plan: 1st July,2017 4. Period Covered by this procurement plan: 1st July, 2017 to 31st December,2018 II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category (US$ millions) Open Open Request for International National Quotation (RfQ) Works ≥7 ≥ 7.0 <7 ≤ 0.2 Goods, IT, and non- ≥1 ≥1 <1 ≤ 0.2 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ million) (US$ millions) Consulting Services Engineering and Construction Supervision Consultants (Firms) ≥2 ≤ 0.2 ≤ 0.3 Individual Consultants ≥ 0.1 NA. NA. [Overall Project Procurement Risk is SUBSTANTIAL] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. 1 Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 2 III. Packages for Goods, Works and Non-Consulting Services Sr./ No Contract Description Estimated Review by Market Approach Selection Evaluation Procurement Prequalif Domestic Expected Expected date of Cost (US$) Bank (Open-National/ Method (RFP, Options Process: ication Preference date of bid/ Contract (Prior/Post) International RFB, RFQ, DS (BAFO, Rated (Single/Multiple (Yes/ No) (Yes/No) proposal Signature Limited etc.) etc.) Criteria etc.) Stages; One/Two opening Envelopes etc) Goods 1 Survey Equipment (Land Based) 527000 Post Open-National RFB One Envelope No No 2018/02/20 2018/04/02 2 IT and Communication Equipment 40000 Post Limited RFQ One Envelope No No 2018/02/23 2018/04/05 3 Procurement of Motor Vehicles 350000 Post Open-National RFB One Envelope No No 2018/02/23 2018/04/05 4 Communication Materials 100000 Post Limited RFQ One Envelope No No 2018/02/23 2018/04/05 5 NRM Equipment for wildlife management 70000 Post Limited RFQ One Envelope No No 2018/02/20 2018/04/02 6 Vehicles under GEF 150000 Post Open-National RFB One Envelope No No 2018/02/23 2018/04/05 7 Office equipment 150000 Post Limited RFQ One Envelope No No 2018/02/23 2018/04/05 Works 1 Construction of Intake, MC1, MC2 43734000 Prior Open- RFB One Envelope Yes No 2018/03/30 2018/04/20 including Office at Chikwawa and International Residences 2 Construction of Secondary canals, 38142680 Prior Open- RFB One Envelope Yes No 2018/11/10 2019/01/15 Drainages, access roads, Night storage and International flood protection 3 Upgrading Park Infrastructure Mwabvi, 675000 Post Open-National RFB One Envelope No No 2018/11/10 2019/01/15 Lengwe and Majete 4 Upgrading Park Fencing Mwabvi and 250000 Post Open-National RFB One Envelope No No 2018/11/10 2019/01/15 Lengwe 5 Office Refurbishment and extension in 200000 Post Limited RFQ One Envelope No No 2018/06/12 2018/08/23 Chikwawa and Blantyre 6 Department of Lands Registry Office 200000 Post Open-National RFB One Envelope No No 2018/06/12 2018/08/23 Construction, Chikwawa Non-Consulting Services 1 Vehicle maintenance 350000 Post Limited RFQ One Envelope No No NA. NA. 3 IV. Packages for Consulting Services Sr. No Contract Description Estimated Review by Market Approach Selection Method Shortlisting Expected date of bid/ Expected date of Cost (US$) Bank (Open-National/ (QCBS, FBBS, (Yes/ No) proposal opening Contract Signature (Prior/Post) International LCBS, QBS, Limited etc.) CQS, DS etc.) 1 Detailed Design of MC3, Secondary canals on 7500000 Prior Open- QCBS Yes 2017/11/27 2018/02/20 farm works and Construction Supervision of International Intake, Main canals, Secondary canals and on farm works 2 Land governance for Securing land tenure and 7100000 Prior Open- QCBS Yes 2017/11/27 2018/02/20 Resettlement Action Plan International 3 Agriculture Specialist Consultancy on production, 6569000 Prior Open- QCBS Yes 2018/02/18 2018/04/25 marketing and value chain development International 4 Consultancy for Environmental and Social Impact 400,000 Prior Open- QCBS Yes 2018/11/27 2019/02/20 Assessment and RAP for Shire Valley International Transformation Program-2 5 Detailed design and preparation of Tender 2500000 Prior Open- QCBS Yes 2018/11/27 2019/02/20 Documents for Phase 2 International 6 Consultancy for Design and supervision of works 750000 Prior Open- QCBS Yes 2018/02/02 2018/04/25 for Mwabvi Lengwe and Majete upgrade works International 7 500000 Prior Open- QCBS Yes 2018/02/02 2018/04/25 Planning and M&E support to PMT International 8 Research and Documentation on social change and 400000 Prior Open-National QCBS Yes 2018/07/10 2018/09/28 dynamics 9 50000 Post Open-National INDV Yes 2019/02/04 2018/04/24 Investment Assistance Panel- Specialist 1 10 50000 Post Open-National NDV Yes 2019/02/04 2018/04/24 Investment Assistance Panel- Specialist 2 11 50000 Post Open-National NDV Yes 2019/02/04 2018/04/24 Investment Assistance Panel- Specialist 3 12 Diagnostic studies on agri-spatial solutions for 652000 Prior Open- QCBS Yes 2019/02/04 2019/04/24 Phase II International 13 50000 Post Open-National NDV Yes 2018/04/27 2018/07/18 Consultancy for IT Support 14 180000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 Social Safeguards Specialist 15 180000 Prior Open- National NDV Yes 2017/11/30 2018/02/26 Environmental Safeguards Specialist 16 240000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 Agriculture Commercialization Specialist Lead 3 17 TA on WUA and WUA Federation formation, and 200000 Prior Open-National NDV Yes 2018/11/27 2019/02/20 on farm water management planning 18 200000 Prior Open-National NDV Yes 2018/04/02 2018/04/25 TA for PPP 19 Project Coordinator 300000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 4 20 Irrigation Engineer Lead 1 240000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 21 Community Development Specialist Lead 2 240000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 22 Financial Procurement Specialist 210000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 23 Procurement Specialist 144000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 24 Executive Assistant 72000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 25 Communications Officer 72000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 26 Senior Procurement Specialist 210000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 27 Monitoring and Evaluation Specialist also 180000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 responsible for GRM 28 Assistant Financial Management Specialist 144000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 29 External Audit 250000 Prior Open-National NDV Yes 2018/05/31 2018/08/19 30 Support Staff 360000 Post Open-National NDV Yes 2018/04/13 2018/07/04 31 Agriculture and Commercialization Specialist, 240000 Prior Open-National NDV Yes 2017/11/30 2018/02/26 Lead 3 32 Design and construction of 60000 Post Open-National QCBS Yes 2018/02/02 2018/04/25 office refurbishment and extension in Chikwawa and Blantyre, including Land Registry office 5 PROCUREMENT Malawi : Shire Valley Transformation Project- Phase 1 PLAN General Information Country: Malawi Bank’s Approval Date of the Original Procurement Plan: 2018-01-09 2019-09-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158805 GPN Date: 2017-09-19 Project Name: Shire Valley Transformation Project- Phase 1 Loan / Credit No: IDA / Q9550, IDA / 61470 Executing Agency(ies): Ministry of Agriculture, Irrigation and Water Development WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-43003-CW- RFB / Construction of Pending Open - Single Stage - One Secondary Canal, Drainages, IDA / Q9550 Irrigation Service Provision Prior Request for Bids 38,142,680.00 0.00 Implementati 2019-07-01 2019-09-16 2019-09-16 2019-07-06 2019-11-25 2019-12-25 2020-01-29 2021-07-22 International Envelope access roads, Nignt storage, on drainage and flood protection MW-MOAIWD-61737-CW- Under RFB / Construction of Open - Single Stage - One IDA / 61470 Irrigation Service Provision Prior Request for Bids 20,067,000.00 0.00 Implementati 2018-05-18 2018-08-03 2018-08-03 2018-05-23 2018-10-12 2018-11-11 2018-12-16 2020-06-08 intake, first 6 km of Main International Envelope on Canal 1 (MC1) MW-MOAIWD-42365-CW- Pending Project Management and Request for Single Stage - One RFB / Office Refurbishment IDA / 61470 Post Limited 200,000.00 0.00 Implementati 2019-04-10 2019-06-05 2019-12-02 Coordination Quotations Envelope and extensioin in Blantyre on MW-MOAIWD-43001-CW- Open - Single Stage - One RFB / Construction of MCI IDA / 61470 Irrigation Service Provision Prior Request for Bids 71,767,000.00 0.00 Canceled 2018-12-19 2019-03-06 2019-03-06 2018-12-24 2019-05-15 2019-06-14 2019-07-19 2021-01-09 International Envelope and MC2 MW-MOAIWD-87847-CW- Open - Single Stage - One Under RFB / Construction of MC1 IDA / 61470 Irrigation Service Provision Prior Request for Bids 71,767,000.00 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 International Envelope Review and MC2 MW-MOAIWD-62074-CW- RFB / Construction of Land Pending Single Stage - One Registry and Irrigation IDA / 61470 Irrigation Service Provision Post Request for Bids Open - National 1,900,000.00 0.00 Implementati 2019-02-22 2019-02-27 2019-04-10 2019-05-10 2019-06-14 2019-12-11 Envelope Offices and Residences at on Chikwawa GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-42967-GO- Under Project Management and Request for Single Stage - One RFQ / Communication IDA / 61470 Post Open - National 100,000.00 23,168.44 Implementati 2019-01-05 2019-03-02 2019-08-29 Coordination Quotations Envelope Materials on MW-MOAIWD-42956-GO- Land Tenure and Natural Pending Single Stage - One RFB / Survey Equipment IDA / 61470 Resources Management Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-01-31 2019-02-05 2019-03-19 2019-04-18 2019-05-23 2019-11-19 Envelope (Land Based) Support on MW-MOAIWD-42380-GO- Under Project Management and Request for Single Stage - One RFQ / IT and IDA / Q9550 Post Limited 40,000.00 43,941.95 Implementati 2018-12-15 2019-02-09 2019-08-08 Coordination Quotations Envelope Communication Equipment on Page 1 MW-MOAIWD-42271-GO- Under Project Management and Single Stage - One RFB / Procurement of Motor IDA / 61470 Post Request for Bids Open - National 350,000.00 0.00 Implementati 2018-12-03 2018-12-08 2019-01-19 2019-02-18 2019-03-25 2019-09-21 Coordination Envelope Vehicles on Pending MW-MOAIWD-105424-GO- Project Management and Request for Single Stage - One IDA / 61470 Post Limited 80,000.00 0.00 Implementati 2019-03-23 2019-05-18 2019-06-17 RFQ / Office Equipment Coordination Quotations Envelope on Pending MW-MOAIWD-42969-GO- Project Management and Request for Single Stage - One IDA / 61470 Post Limited 70,000.00 0.00 Implementati 2019-08-07 2019-10-02 2020-03-30 RFQ / Office Furniture Coordination Quotations Envelope on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-42480-NC- Project Management and Request for Single Stage - One IDA / Q9550 Post Open - National 350,000.00 0.00 Canceled 2018-03-27 2018-05-22 2018-11-18 RFQ / Vehicle Maintenance Coordination Quotations Envelope MW-MOAIWD-129948-NC- Pending Project Management and Request for Single Stage - One RFQ / Radio and Video IDA / 61470 Post Limited 50,000.00 0.00 Implementati 2019-09-25 2019-11-20 2020-05-18 Coordination Quotations Envelope production on MW-MOAIWD-129973-NC- Pending Project Management and Request for Single Stage - One RFQ / 2020 Calendars and IDA / 61470 Post Limited 60,000.00 0.00 Implementati 2019-09-27 2019-11-22 2020-05-20 Coordination Quotations Envelope Diaries on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-42381-CS- QCBS / Detailed design, Construction Supervision and Quality And Cost- Open - IDA / Q9550 Irrigation Service Provision Prior 7,500,000.00 0.00 Under Review 2018-07-01 2018-07-22 2018-09-04 2018-10-02 2018-11-01 2018-12-06 2019-01-10 2020-01-10 Quality assurance for the Based Selection International Shire valley Irrigation Scheme MW-MOAIWD-43009-CS- QCBS / Detailed design and Quality And Cost- Open - Pending IDA / Q9550 Irrigation Service Provision Prior 2,500,000.00 0.00 2019-04-17 2019-05-08 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 preaparation of Tender Based Selection International Implementation Documents for Phase 2 MW-MOAIWD-42968-CS- QCBS / Research and Project Management and Quality And Cost- Open - Pending IDA / 61470 Prior 400,000.00 0.00 2018-12-31 2019-01-21 2019-03-06 2019-04-03 2019-05-03 2019-06-07 2019-07-12 2020-07-11 documentation on social Coordination Based Selection International Implementation change and dynamics MW-MOAIWD-43010-CS- QCBS / Consultancy for Land Tenure and Natural Quality And Cost- Open - Design and supervision of IDA / 61470 Resources Management Prior 750,000.00 0.00 Canceled 2018-06-26 2018-07-17 2018-08-30 2018-09-27 2018-10-27 2018-12-01 2019-01-05 2020-01-05 Based Selection International works for Mwabvi, Majete Support and Lengwe upgrade works MW-MOAIWD-42991-CS- QCBS / TA on WUA and Quality And Cost- Open - Pending IDA / 61470 Irrigation Service Provision Post 200,000.00 0.00 2019-12-30 2020-01-20 2020-03-04 2020-04-01 2020-05-01 2020-06-05 2020-07-10 2021-07-10 WUA formation and on farm Based Selection International Implementation water management Page 2 MW-MOAIWD-42992-CS- QCBS / Diagnostic studies Agriculture Development Quality And Cost- Open - Pending IDA / 61470 Post 652,000.00 0.00 2021-09-30 2021-10-21 2021-12-04 2022-01-01 2022-01-31 2022-03-07 2022-04-11 2023-04-11 on agri-spatial solutions for and Commercialization Based Selection International Implementation Phase II MW-MOAIWD-87827-CS- CQS / Design and Construction Supervision of Consultant Under Office Rehabilitation in IDA / 61470 Irrigation Service Provision Post Qualification Open - National 250,000.00 0.00 2018-12-14 2019-01-04 2019-02-17 2019-03-19 2019-04-23 2019-10-20 Implementation Blantyre and Construction Selection Supervision for Office block and residences in Chikwawa MW-MOAIWD-81036-CS- CQS / Design and Consultant Project Management and construction supervision of IDA / 61470 Post Qualification Open - National 60,000.00 0.00 Canceled 2018-10-18 2018-11-08 2018-12-22 2019-01-21 2019-02-25 2019-08-24 Coordination Office refurbishment and Selection extension in Blantyre MW-MOAIWD-42998-CS- QCBS / Agriculture Agriculture Development Quality And Cost- Open - Specialist Consultancy on IDA / 61470 Prior 6,569,000.00 0.00 Under Review 2019-01-21 2019-02-11 2019-03-27 2019-04-24 2019-05-24 2019-06-28 2019-08-02 2020-08-01 and Commercialization Based Selection International production, market and value chain development MW-MOAIWD-42291-CS- QCBS / Consultancy for Land Tenure and Natural Environmental and Social Quality And Cost- Open - Pending IDA / Q9550 Resources Management Post 400,000.00 0.00 2019-04-19 2019-05-10 2019-06-23 2019-07-21 2019-08-20 2019-09-24 2019-10-29 2020-10-28 Impact Assessment (ESIA) Based Selection International Implementation Support for Shire Valley Transformation Program-2 MW-MOAIWD-42955-CS- Land Tenure and Natural QCBS / Land governance for Quality And Cost- Open - IDA / Q9550 Resources Management Prior 7,100,000.00 0.00 Canceled 2018-04-17 2018-05-08 2018-06-21 2018-07-19 2018-08-18 2018-09-22 2018-10-27 2019-10-27 securing Land Tenure and Based Selection International Support Resettlement Action Plan MW-MOAIWD-88919-CS- QCBS / Land Governance Land Tenure and Natural Quality And Cost- Open - Under for securing Land Tenure IDA / 61470 Resources Management Prior 1,200,000.00 0.00 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2020-07-01 Based Selection International Implementation and Resettlement Action Support Plans MW-MOAIWD-42848-CS- Project Management and Least Cost IDA / 61470 Post Open - National 250,000.00 0.00 Canceled 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2019-11-13 LCS / External Audit Coordination Selection MW-MOAIWD-42954-CS- Project Management and Quality And Cost- Open - QCBS / Planning and M&E IDA / 61470 Prior 500,000.00 0.00 Canceled 2018-07-12 2018-08-02 2018-09-15 2018-10-13 2018-11-12 2018-12-17 2019-01-21 2020-01-21 Coordination Based Selection International support to PMT MW-MOAIWD-89347-CS- QCBS / Planning, Monitoring Project Management and Quality And Cost- Open - Under IDA / 61470 Post 500,000.00 0.00 2018-12-31 2019-01-21 2019-03-06 2019-04-03 2019-05-03 2019-06-07 2019-07-12 2020-07-11 and Evaluation Support to Coordination Based Selection International Implementation Project Management Team Consultant MW-MOAIWD-125676-CS- Project Management and Open - Under IDA / 61470 Post Qualification 250,000.00 0.00 2019-08-30 2019-09-20 2019-11-03 2019-12-03 2020-01-07 2020-07-05 CQS / Baseline Study Coordination International Implementation Selection MW-MOAIWD-125671-CS- CQS / Design and Consultant Development of Shire Valley Project Management and Open - IDA / 61470 Post Qualification 300,000.00 0.00 Under Review 2019-08-30 2019-09-20 2019-11-03 2019-12-03 2020-01-07 2020-07-05 Transformation Program Coordination International Selection (SVTP) Management Information System INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-42959-CS- CDS / Detailed Design and Tender Document Under IDA / Q9550 Irrigation Service Provision Prior Direct Selection Direct 250,000.00 0.00 2017-06-13 2017-06-23 2017-08-27 2018-02-23 preparation for Intake Implementation Structure and main canal 1 up to chainage 6+000 MW-MOAIWD-42475-CS- Individual Project Management and INDV / Procurement IDA / Q9550 Prior Consultant Open 144,000.00 40,947.00 Signed 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 Coordination Specialist Selection MW-MOAIWD-42995-CS- Individual Project Management and INDV / Community IDA / Q9550 Prior Consultant Open 240,000.00 54,153.79 Signed 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 Coordination Development Specialist Selection MW-MOAIWD-42483-CS- Individual Project Management and INDV / Financial IDA / Q9550 Prior Consultant Open 210,000.00 49,334.04 Signed 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 Coordination Management Specialist Selection MW-MOAIWD-42447-CS- Individual Project Management and INDV / Communication IDA / Q9550 Post Consultant Open 72,000.00 41,100.24 Signed 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 Coordination Officer Selection MW-MOAIWD-42441-CS- Individual Project Management and INDV / Senior Procurement IDA / Q9550 Prior Consultant Direct 210,000.00 49,386.24 Signed 2018-02-26 2018-03-08 2018-03-29 2018-05-03 2019-05-03 Coordination Specialist Selection Individual MW-MOAIWD-42370-CS- Project Management and IDA / Q9550 Prior Consultant Open 300,000.00 60,845.32 Signed 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 INDV / Project Coordinator Coordination Selection MW-MOAIWD-42338-CS- Individual Project Management and INDV / Assistant Financial IDA / Q9550 Prior Consultant Open 144,000.00 36,259.08 Signed 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 Coordination Management Specialist Selection Individual MW-MOAIWD-42296-CS- Project Management and IDA / Q9550 Post Consultant Open 72,000.00 21,425.82 Signed 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 INDV / Executive Assistant Coordination Selection MW-MOAIWD-43006-CS- Individual Project Management and INDV / Environmental IDA / Q9550 Prior Consultant Open 180,000.00 43,286.72 Signed 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2019-06-13 Coordination Safeguards Specialist Selection MW-MOAIWD-42994-CS- Individual Project Management and Under INDV / Social Safeguards IDA / Q9550 Prior Consultant Open 180,000.00 0.00 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2019-06-13 Coordination Implementation Specialist Selection MW-MOAIWD-42284-CS- Individual Project Management and INDV / Agriculture and IDA / Q9550 Prior Consultant Open 240,000.00 49,677.12 Signed 2018-05-10 2018-06-28 2018-07-19 2018-08-23 2019-08-23 Coordination Commercialization Specialist Selection MW-MOAIWD-42996-CS- Individual INDV / Monitoring and Project Management and IDA / Q9550 Prior Consultant Open 180,000.00 42,851.64 Signed 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 Evaluation Specialist also Coordination Selection responsible for GRM MW-MOAIWD-42349-CS- Individual INDV / Investment Agriculture Development Pending IDA / Q9550 Post Consultant Open 50,000.00 0.00 2019-03-19 2019-05-07 2019-05-28 2019-07-02 2019-12-29 Assessment Panel- specialist and Commercialization Implementation Selection 1 Page 4 MW-MOAIWD-42368-CS- Individual INDV / Investment Agriculture Development Pending IDA / Q9550 Post Consultant Open 50,000.00 0.00 2019-03-19 2019-05-07 2019-05-28 2019-07-02 2019-12-29 Assessment Panel- specialist and Commercialization Implementation Selection 3 Individual MW-MOAIWD-43008-CS- Project Management and IDA / Q9550 Prior Consultant Open 240,000.00 0.00 Canceled 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2019-06-11 INDV / Irrigation Engineer Coordination Selection MW-MOAIWD-78212-CS- Individual Project Management and INDV / Irrigation Specialist IDA / 61470 Prior Consultant Open 240,000.00 0.00 Canceled 2018-09-30 2018-11-18 2018-12-09 2019-01-13 2019-07-12 Coordination (PPPC) Selection Individual MW-MOAIWD-81035-CS- Project Management and IDA / 61470 Prior Consultant Open 240,000.00 0.00 Canceled 2018-10-19 2018-12-07 2018-12-28 2019-02-01 2019-07-31 INDV / Irrigation Engineer Coordination Selection MW-MOAIWD-87823-CS- Individual Under INDV / TA as Irrigation IDA / 61470 Irrigation Service Provision Post Consultant Open 240,000.00 0.00 2018-11-29 2019-01-17 2019-02-07 2019-03-14 2019-09-10 Implementation Specialist (PPPC) Selection MW-MOAIWD-87825-CS- Individual Project Management and Under INDV / Technical Assistance IDA / 61470 Post Consultant Open 240,000.00 0.00 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2019-09-11 Coordination Implementation as Irrigation Engineer Selection MW-MOAIWD-42451-CS- Individual Project Management and INDV / Consultancy for IT IDA / 61470 Post Consultant Open 50,000.00 0.00 Under Review 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 Coordination support Selection MW-MOAIWD-43012-CS- Individual INDV / Investment Agriculture Development Pending IDA / 61470 Post Consultant Open 50,000.00 0.00 2019-03-19 2019-05-07 2019-05-28 2019-07-02 2019-12-29 Assessment Panel- specialist and Commercialization Implementation Selection 2 Individual MW-MOAIWD-42476-CS- Project Management and Pending IDA / 61470 Post Consultant Open 360,000.00 0.00 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2020-06-12 INDV / Support Staff Coordination Implementation Selection Individual MW-MOAIWD-42444-CS- Pending IDA / Q9550 Irrigation Service Provision Post Consultant Open 200,000.00 0.00 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 INDV / TA for PPP Implementation Selection Page 5