Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Revision of Updated Procurement Plan, August 2017 2. Date of General Procurement Notice: October 10, 2016 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Category Prior Review Threshold Comments US$ 1. Goods and >= US$2 million All 2. Works >= US$ 10 million All 3. (Non-Consultant Services) >= US$2 million All 2. Prequalification. _Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: At sub-national levels (Commune/Sangkat and Community), provisions of the Project Implementation Manual (PIM) dated March 30, 2016 which has been agreed by the Bank will apply. The PIM provides for processes and procedures for procurement at sub-national levels. 4. Reference to (if any) Project Operational/Procurement Manual: the Project Implementation Manual (PIM) dated March 30, 2016 has been agreed by the Bank. 5. Summary of the Procurement Packages 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) LASE Upgrade 1.5 1 No Post NCB D/NC Earth Road to DDS/ Late-Rite W/NC Roads B/05/1 (106.96Km) 7 LASE Construction 1.3 1 No Post NCB D/NC of Late-Rite DDS/ Roads = W/NC 29km B/03/1 7 LASE Land 2.4 1 No Post NCB D/NC Preparation DDS/ Agriculture- W/NC Bulldozing, B/02/1 Leveling. 7 Total:2,355.5 0Ha LASE Construction 1.1 1 No Post NCB D/NC of 11 small DDS/ dams. W/NC B/06/1 7 LASE Construction 2.86 1 No Post NCB D/NC of earth roads DDS/ (130Km) W/NC B/04/1 7 LASE Household 0.12 1 No Post NCB D/NC Start-Up DDS/ Packages for G/NC Daung 700 B/12/1 HH (Solar 7 lamp, Tent plastic, mat, blanket, water jar, water filter) LASE Office 0.18 1 No Post NCB D/NC equipment DDS/ (computers & G/NC Photocopy B/03/1 Machines) 6 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) >= US$1,000,000 2. Individual >= US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) LASED/N Consulting 0.12 1 Post CQS CDDS/F/3 firm for 5/17 Irrigation Design (8 sites) LASED/N Baseline 0.07 1 Post CQS CDDS/IC/3 Survey in 0/17 year 2017 (Local Firm) LASED/N Impact 0.05 1 Post CQS CDDS/IC/3 Survey for 1/18 2nd year of the project/Mid- term review (Local Firm) LASED/N Final Impact 0.12 1 Post CQS CDDS/IC/3 Survey 2/21 PROCUREMENT Cambodia : KH-Land Allocation for Social and Economic Development Project II PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2016-08-18 Revised Plan Date(s): (comma delineated, leave blank if none)2019-10-17 Project ID: P150631 GPN Date: 2016-10-10 Project Name: KH-Land Allocation for Social and Economic Development Project II Loan / Credit No: IDA / 58070 Executing Agency(ies): National Committee for Sub-National Democratic Development Secretariat WORKS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMMUNE NO 07/17 / Sub-component 1.2: Land Request for Single Stage - Water well (Afredes) for IDA / 58070 Preparation and Post Open - National 63,333.33 62,890.00 Signed 2017-06-06 2017-08-01 2018-08-01 Quotations One Envelope Thmey 19 Units Infrastructure Development COMMUNE NO 08/17 / Sub-component 1.2: Land Request for Single Stage - Water well (Afredes) for IDA / 58070 Preparation and Post Open - National 20,000.00 9,900.00 Signed 2017-06-06 2017-08-01 2018-08-01 Quotations One Envelope Chambak 6 Units Infrastructure Development COMMUNE NO 10/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 34,750.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Tipo 1 QTY 1 Unit COMMUNE NO 11/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 34,750.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Tipo 2 QTY 1 Unit COMMUNE NO 12/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 34,400.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Choamkravien QTY 1 Unit COMMUNE NO 13/17 / House for Nurses & Sub-component 1.2: Land Teachers (8mx 20m Preparation and Request for Single Stage - x4Rooms, each room IDA / 58070 Post Open - National 35,000.00 32,400.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope equipped with internal Development kitchen & bathroom) for Chambak QTY 1 Unit COMMUNE NO 14/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 31,500.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Sambok QTY 1 Unit COMMUNE NO 15/17 / House for Nurses & Teachers Ceramic tile Sub-component 1.2: Land floor (W=9.2m, L=16.2m, Preparation and Request for Single Stage - IDA / 58070 Post Open - National 35,000.00 34,850.00 Signed 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 Infrastructure Quotations One Envelope rooms's W.C & 4 places Development of kitchend) for Changkrang QTY 1 Unit COMMUNE NO 16/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 34,700.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Thmey QTY 1 Unit COMMUNE NO 17/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 30,400.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Dar QTY 1 Unit COMMUNE NO 18/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 34,886.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Ksach Sar QTY 1 Unit COMMUNE NO 19/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 34,720.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Sambok Kriel QTY 1 Unit COMMUNE NO 20/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 34,869.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 Development rooms's W.C & 4 places of kitchend) for Peam QTY 1 Unit COMMUNE NO 21/17 / House for Nurses & Sub-component 1.2: Land Teachers (8mx 20m Preparation and Request for Single Stage - x4Rooms, each room IDA / 58070 Post Open - National 35,000.00 34,800.00 Signed 2017-07-06 2017-08-31 2018-08-31 Infrastructure Quotations One Envelope equipped with internal Development kitchen & bathroom) for Chhean Loeung QTY 1 Unit COMMUNE NO 22/17 / House for Nurses & Teachers Ceramic tile Sub-component 1.2: Land floor (W=9.2m, L=16.2m, Preparation and Request for Single Stage - IDA / 58070 Post Open - National 35,000.00 33,942.00 Signed 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 Infrastructure Quotations One Envelope rooms's W.C & 4 places Development of kitchend) for Raksmey Samaki QTY 1 Unit COMMUNE NO 23/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - IDA / 58070 Post Open - National 29,000.00 28,900.00 Signed 2017-06-06 2017-08-01 2018-07-31 Ceramic tile floor Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Dar (1). Total: 1 Unit COMMUNE NO 24/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - IDA / 58070 Post Open - National 29,000.00 28,950.00 Signed 2017-06-06 2017-08-01 2018-07-31 Ceramic tile floor Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Thmey (1). Total: 1 Unit COMMUNE NO 25/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - Ceramic tile floor IDA / 58070 Post Open - National 29,000.00 27,400.00 Signed 2017-06-06 2017-08-01 2018-07-31 Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Chambak (1). Total: 1 Unit Page 1 COMMUNE NO 26/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - Ceramic tile floor IDA / 58070 Post Open - National 29,000.00 28,800.00 Signed 2017-06-06 2017-08-01 2018-07-31 Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Choamkravien (1). Total: 1 Unit COMMUNE NO 27/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - Ceramic tile floor IDA / 58070 Post Open - National 29,000.00 25,400.00 Signed 2017-06-06 2017-08-01 2018-08-01 Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Tipo 2 (1). Total: 1 Unit COMMUNE NO 29/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - IDA / 58070 Post Open - National 29,000.00 26,400.00 Signed 2017-06-06 2017-08-01 2018-08-01 Ceramic tile floor Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Peam (1). Total: 1 Unit COMMUNE NO 30/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - Ceramic tile floor IDA / 58070 Post Open - National 29,000.00 28,850.00 Signed 2017-06-06 2017-08-01 2018-08-31 Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Chean Loeung (1). Total: 1 Unit COMMUNE NO 31/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - Ceramic tile floor IDA / 58070 Post Open - National 29,000.00 28,780.00 Signed 2017-06-06 2017-08-01 2018-08-01 Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Ksach Sor (1). Total: 1 Unit COMMUNE NO 32/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - Ceramic tile floor IDA / 58070 Post Open - National 29,000.00 26,300.00 Signed 2017-06-06 2017-08-01 2018-08-01 Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Chum Kreal (1). Total: 1 Unit COMMUNE NO 33/17 / Construction of Sub-component 1.2: Land Community Centre Preparation and Request for Single Stage - Ceramic tile floor IDA / 58070 Post Open - National 29,000.00 27,565.00 Signed 2017-06-06 2017-08-01 2018-08-01 Infrastructure Quotations One Envelope (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Prey Thom (1). Total: 1 Unit LASED/NCDDS/W/NCB/02/ 17 / Land Preparation Agriculture-Buldozing, Leveling:LOT1: S.Kriel(100), Sub-component 1.2: Land Ksa.Sar(126.50),Peam(116.5 Preparation and Request for Single Stage - IDA / 58070 Post Open - National 2,355,500.00 1,913,405.75 Signed 2017-02-01 2017-02-06 2017-03-20 2017-04-19 2017-05-24 2017-11-20 0), Chh.loeung(103), Infrastructure Bids One Envelope Ra.Samaki(200), TP1(276), Development TP2 (226.50), S.bok(100), Ch.Krang(59), Dar(97), Thmey(174)&Chambak(277) . LOT2:Daung (500).Grand Total:2,355.50Ha LASED/NCDDS/W/NCB/07/ 17 / Construction of Primary Schools (5Rooms, 4WCs, 1Well, 1Flag Pole) Sub-component 1.2: Land Incl. 250chairs connected Preparation and Request for Single Stage - with tables, 5Tables & IDA / 58070 Post Open - National 711,111.11 693,314.40 Signed 2017-09-15 2017-09-20 2017-11-01 2017-12-01 2018-01-05 2018-07-04 Infrastructure Bids One Envelope 5Chairs and Whiteboards Development for: Tipo1, Chambak, Sambok, Raksmey Samaki (KSP), Ksach Sar (KCH), Choamkravien and Daung (2units) Total:8Units LASED/NCDDS/W/SP/01/17 / "Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - IDA / 58070 Post Open - National 158,888.89 127,836.37 Signed 2017-12-20 2018-02-14 2018-08-13 (W4.5mxT0.15m): Main Infrastructure Quotations One Envelope Road, KPT Development Tipo 1 and 2 = 11km. " COMMUNE/KPT/W/37/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Pending Preparation and Request for Single Stage - (W4.5mxT0.15m):, Tipo 1 IDA / 58070 Post Open - National 61,677.78 0.00 Implementa 2018-08-06 2018-10-01 2019-03-30 Infrastructure Quotations One Envelope (AR3=0.95km, tion Development ART=0.71km, AR2=1.26km, AR4=1,35) Total= 4.27km. (Package1) LASED/NCDDS/W/NCB/05/ 17 / Upgrade Earth Road to Late-Rite Roads(W4.5mxT0.15m):LOT 1: Tipo1(9.47km), Tipo2 (10.53km) and Main Road Sub-component 1.2: Land (11km). Total 31km. LOT Preparation and Request for Single Stage - IDA / 58070 Post Open - National 1,544,977.78 0.00 Canceled 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2017-12-22 2018-06-20 2: S.Kriel(19km), Infrastructure Bids One Envelope K.Sar(10.80km), Development Peam(11.44km), Chh.Loeung(13.72km) & Ra.Samaki(21km). Total: 75.96km. Grand Total 106.96Km LASED/NCDDS/W/NCB/03/ 17 / Construction of Lot Sub-component 1.2: Land 1. Late-Rite Roads Pending Preparation and Request for Single Stage - (W5xT0.15xE0.5m) = IDA / 58070 Post Open - National 1,342,000.00 0.00 Implementa 2019-01-01 2019-01-06 2019-02-17 2019-03-19 2019-04-23 2019-10-20 Infrastructure Bids One Envelope 22km. Lot 2. Earth Roads tion Development (W5xT0.15xE0.5m) for Daung = 29km LASED/NCDDS/W/SP/09/17 / Build board Construction, Installation Sub-component 1.2: Land and Renew Banner (New Preparation and Request for Single Stage - IDA / 58070 Post Open - National 116,666.67 107,060.85 Signed 2018-04-07 2018-06-02 2018-11-29 bill board 3 sites at KSP, Infrastructure Quotations One Envelope KPT and KCH) and Development Renews banner for existing bill board 9 sites. COMMUNE/KRT/W/54/18 / Construction of Health Sub-component 1.2: Land Posts (3 rooms, fense Preparation and Request for Single Stage - 400m, gate 1, well1, WC IDA / 58070 Post Open - National 36,666.67 34,900.00 Signed 2018-03-06 2018-05-01 2018-10-28 Infrastructure Quotations One Envelope 2rooms, pipe culvert 1, Development incinerator 1, 200m of laterite road). 1 Unit for Da, KRT COMMUNE/KRT/W/55/18 / Construction of Health Sub-component 1.2: Land Posts (3 rooms, fense Preparation and Request for Single Stage - 400m, gate 1, well1, WC IDA / 58070 Post Open - National 36,666.67 36,200.00 Signed 2018-03-06 2018-05-01 2018-10-28 Infrastructure Quotations One Envelope 2rooms, pipe culvert 1, Development incinerator 1, 200m of laterite road). 1 Unit for Thmey, KRT. LASED/NCDDS/W/NCB/08/ 17 / Construction of Health Posts (3 rooms, fense 400m, gate 1, well1, Sub-component 1.2: Land WC 2rooms, pipe culvert Preparation and Request for Single Stage - IDA / 58070 Post Open - National 183,333.33 0.00 Canceled 2017-02-06 2017-04-03 2018-04-03 1, incinerator 1, 200m of Infrastructure Quotations One Envelope laterite road). Da (1 Development Unit), Thmey (1 Unit) Ksach Sar (1 Unit), Chhean Loeung (1 Unit) and Daung (1 Unit). Total 5 Units. Page 2 LASED/NCDDS/W/NCB/01/ 17 / 1) Concrete Poles in Agriculture & Residential Lands (0.12 x 0.12 x Sub-component 1.2: Land 0.75m) = (5000 Poles), 2) Preparation and Request for Single Stage - Concrete Poles in Forestry IDA / 58070 Post Open - National 160,555.56 0.00 Canceled 2017-10-07 2017-12-02 2018-05-31 Infrastructure Quotations One Envelope & in SLC Sites Development (0.3x0.3x0.4x1.5m) (150 Poles) and 3) Concrete Poles in Stream and Canal (0.2x0.2x1.5m) for Daung (200 Poles). LASED/NCDDS/W/NCB/09/ 18 / Upgrade Earth Road to Late-Rite Road(W4.5mxT0.15m):LOT1 :KPT,Tipo=15 lines=15.73km,LOT2: KCH Sub-component 1.2: Land A) KrangLvea =22 Lines Preparation and Request for Single Stage - IDA / 58070 Post Open - National 1,128,544.44 946,643.43 Signed 2018-08-22 2018-08-27 2018-10-08 2018-11-07 2018-12-12 2019-12-12 25.14km),B)Peam =17 Infrastructure Bids One Envelope Lines(11.44km),C)Chhean Development Loeung=10 Lines (9.57km)=46.15km & LOT3: KSP,RaksmeySamaki=5 Lines= 16.25km. GrandTotal=78.13Km. COMMUNE/KCH/W/42/18 / Upgrade Earth Road to Late-Rite Roads Sub-component 1.2: Land Pending (W4.5mxT0.15m): Sambok Preparation and Request for Single Stage - IDA / 58070 Post Open - National 67,311.11 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Kriel, Krang Lvea Infrastructure Quotations One Envelope tion Commune, KCH = Development (URR/5lines = 4.66km). (Package 2). COMMUNE/KCH/W/46/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Pending Preparation and Request for Single Stage - (W4.5mxT0.15m): Chhean IDA / 58070 Post Open - National 59,944.44 0.00 Implementa 2018-05-09 2018-07-04 2018-12-31 Infrastructure Quotations One Envelope Loeung Commune, KCH = tion Development (URR/12lines) = 4.15km. (Package 1). COMMUNE/KCH/W/56/18 / Construction of Health Sub-component 1.2: Land Posts (3 rooms, fense Preparation and Request for Single Stage - 400m, gate 1, well1, WC IDA / 58070 Post Open - National 36,666.67 29,967.00 Signed 2018-04-22 2018-06-17 2018-12-14 Infrastructure Quotations One Envelope 2rooms, pipe culvert 1, Development incinerator 1, 200m of laterite road). 1 Unit for Ksach Sar, KCH. COMMUNE/KCH/W/57/18 / Construction of Health Posts (3 rooms, fense Sub-component 1.2: Land Pending 400m, gate 1, well1, WC Preparation and Request for Single Stage - IDA / 58070 Post Open - National 36,666.67 0.00 Implementa 2018-04-22 2018-06-17 2018-12-14 2rooms, pipe culvert 1, Infrastructure Quotations One Envelope tion incinerator 1, 200m of Development laterite road). 1 Unit for Chhean Loeung, KCH. COMMUNE/KCH/W/59/18 Sub-component 1.2: Land / Ploughing (2 Times) for Pending Preparation and Request for Single Stage - Peam Commune (116.5Ha), IDA / 58070 Post Open - National 12,944.44 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope Samaki Meanchey District, tion Development Kg. Chhnang COMMUNE/KCH/W/60/18 Sub-component 1.2: Land / Ploughing (2 Times) for Pending Preparation and Request for Single Stage - Chheanloeurng Commune IDA / 58070 Post Open - National 11,444.44 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope (103Ha), Samaki tion Development Meanchey District, Kg. Chhnang. COMMUNE/KSP/W/49/18 / Upgrade Earth Road to Late-Rite Roads Sub-component 1.2: Land (W4.5mxT0.15m): Raksmey Preparation and Request for Single Stage - Samaki, KSP = IDA / 58070 Post Open - National 68,611.11 67,345.00 Signed 2018-04-14 2018-06-09 2018-12-06 Infrastructure Quotations One Envelope (Up1=3.40km, Up2=0.30 Development km, Up3=0.15 km, Up4=0.30 km, Up5=0.30 km, and Up6=0.30km) = 4.75km. (Package 1) COMMUNE/KPT/W/53/18 / Construction of Health Sub-component 1.2: Land Posts (3 rooms, fense Pending Preparation and Request for Single Stage - 400m, gate 1, well1, WC IDA / 58070 Post Open - National 36,666.67 0.00 Implementa 2018-11-20 2019-01-15 2019-07-14 Infrastructure Quotations One Envelope 2rooms, pipe culvert 1, tion Development incinerator 1, 200m of laterite road). 1 Unit for Daung, KPT. COMMUNE NO 05/17 / Sub-component 1.2: Land Pending Water well (Afredes) for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 54,000.00 0.00 Implementa 2018-09-19 2018-11-14 2019-05-13 Daung (Site I) : Total: 18 Infrastructure Quotations One Envelope tion Units Development COMMUNE/KSP/W/61/18 Sub-component 1.2: Land / Ploughing (2 Times) for Preparation and Request for Single Stage - Reaksmey Samaki IDA / 58070 Post Open - National 22,222.22 21,600.00 Signed 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope Commune (200Ha), Oral Development District, Kg. Speu. COMMUNE/KPT/W/62/18 / Ploughing (2 Times) Sub-component 1.2: Land Tipo 1 = 354.44Ha & Preparation and Request for Single Stage - IDA / 58070 Post Open - National 64,548.89 46,075.20 Signed 2018-05-23 2018-07-18 2019-01-14 Tipo 2 =226.5Ha, Total = Infrastructure Quotations One Envelope 580.94Ha for Tipo Development Commune, Suntuk District, Kg. Thom. COMMUNE/KRT/W/67/18 Sub-component 1.2: Land Pending / Ploughing (2 Times) for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 19,333.33 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Thmey Commune (174Ha), Infrastructure Quotations One Envelope tion Chetr Borey, Kratie. Development COMMUNE/KRT/W/68/18 Sub-component 1.2: Land Pending / Ploughing (2 Times) for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 30,777.78 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Chambak Commune Infrastructure Quotations One Envelope tion (277Ha), Prek Prasab, Development Kratie. COMMUNE/KPT/W/63/18 Sub-component 1.2: Land Pending / Ploughing (2 Times) for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 55,555.56 0.00 Implementa 2019-02-06 2019-04-03 2019-09-30 Daung Commune (500Ha), Infrastructure Quotations One Envelope tion Suntuk District, Kg. Development Thom. COMMUNITY/KCH/W/45/1 8 / Planting in Sub-component 1.2: Land Community Agriculture Land (Sowing Preparation and IDA / 58070 Post Driven Open - National 2,777.78 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Seed or Planting Seedling Infrastructure Development cover crop) for community Development in Sambok Kriel (100Ha), KCH. COMMUNITY/KCH/W/46/1 8 / Planting in Sub-component 1.2: Land Community Agriculture Land (Sowing Preparation and IDA / 58070 Post Driven Open - National 3,513.89 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Seed or Planting Seedling Infrastructure Development cover crop) for community Development in Ksach Sar (126.50Ha), KCH. COMMUNITY/KCH/W/47/1 8 / Planting in Sub-component 1.2: Land Community Agriculture Land (Sowing Preparation and IDA / 58070 Post Driven Open - National 3,236.11 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Seed or Planting Seedling Infrastructure Development cover crop) for community Development in Peam (116.50Ha), KCH. COMMUNITY/KCH/W/48/1 8 / Planting in Sub-component 1.2: Land Community Agriculture Land (Sowing Preparation and IDA / 58070 Post Driven Open - National 2,861.11 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Seed or Planting Seedling Infrastructure Development cover crop) for community Development in Chheanloeung (103Ha), KCH. COMMUNITY/KSP/W/49/18 / Planting in Agriculture Sub-component 1.2: Land Land (Sowing Seed or Community Preparation and Planting Seedling cover IDA / 58070 Post Driven Open - National 5,555.56 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Infrastructure crop) for community in Development Development Raksmey Samaki (200Ha), KSP. Page 3 COMMUNITY/KPT/W/42/18 / Planting in Agriculture Sub-component 1.2: Land Community Land (Sowing Seed or Preparation and IDA / 58070 Post Driven Open - National 9,845.56 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Planting Seedling cover Infrastructure Development crop) for community in Development Tipo 1, KPT (354.44Ha) COMMUNITY/KPT/W/43/18 / Planting in Agriculture Sub-component 1.2: Land Community Land (Sowing Seed or Preparation and IDA / 58070 Post Driven Open - National 6,291.67 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Planting Seedling cover Infrastructure Development crop) for community in Development Tipo 2 , KPT (226.50Ha) COMMUNITY/KRT/W/50/18 / Planting in Agriculture Sub-component 1.2: Land Land (Sowing Seed or Community Preparation and Planting Seedling cover IDA / 58070 Post Driven Open - National 6,111.11 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Infrastructure crop) for community in Development Development Sambok, KRT (100Ha+120Ha=220Ha). COMMUNITY/KRT/W/51/18 / Planting in Agriculture Sub-component 1.2: Land Land (Sowing Seed or Community Preparation and Planting Seedling cover IDA / 58070 Post Driven Open - National 3,861.11 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Infrastructure crop) for community in Development Development Changkrang, KRT (59Ha+80Ha=139Ha) COMMUNITY/KRT/W/52/18 / Planting in Agriculture Sub-component 1.2: Land Community Land (Sowing Seed or Preparation and IDA / 58070 Post Driven Open - National 2,694.44 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Planting Seedling cover Infrastructure Development crop) for community in Development Dar, KRT (97Ha) COMMUNITY/KRT/W/53/18 / Planting in Agriculture Sub-component 1.2: Land Community Land (Sowing Seed or Preparation and IDA / 58070 Post Driven Open - National 4,833.33 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Planting Seedling cover Infrastructure Development crop) for community in Development Thmey, KRT (174Ha) COMMUNITY/KRT/W/54/18 / Planting in Agriculture Sub-component 1.2: Land Community Land (Sowing Seed or Preparation and IDA / 58070 Post Driven Open - National 7,694.44 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Planting Seedling cover Infrastructure Development crop) for community in Development Chambak, KRT (277Ha) COMMUNITY/KPT/W/44/18 / Planting in Agriculture Sub-component 1.2: Land Community Land (Sowing Seed or Preparation and IDA / 58070 Post Driven Open - National 13,888.89 0.00 Canceled 2019-05-08 2019-05-13 2019-06-24 2019-07-24 2019-08-28 2020-02-24 Planting Seedling cover Infrastructure Development crop) for community in Development Daung, KPT (500Ha) COMMUNE NO 06/17 / Sub-component 1.2: Land Pending Water well (Afredes) for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 51,000.00 0.00 Implementa 2019-01-20 2019-03-17 2019-09-13 Daung (Site II): Total: 17 Infrastructure Quotations One Envelope tion Units Development COMMUNE/KPT/W/34/18 Sub-component 1.2: Land / Concrete Poles in Preparation and Request for Single Stage - Agriculture Lands (0.12 x IDA / 58070 Post Open - National 72,000.00 28,800.00 Signed 2019-01-20 2019-03-17 2019-09-13 Infrastructure Quotations One Envelope 0.12 x 0.75m) = (3600 Development Poles) for Daung, KPT. COMMUNE/KPT/W/35- 36/18 / Concrete Poles in Residential Lands (0.12 x 0.12 x 0.75m= 1400 Poles) Sub-component 1.2: Land and Concrete Poles in Preparation and Request for Single Stage - IDA / 58070 Post Open - National 44,600.00 21,300.00 Signed 2018-09-22 2018-11-17 2019-05-16 Forestry (0.3x0.3x0.4x1.5m Infrastructure Quotations One Envelope = 150 Poles) and Concrete Development Poles in Stream and Canal (0.2x0.2x1.5m = 200 Poles) for Daung, KPT. COMMUNITY/KPT/W/39/18 Sub-component 1.2: Land / Instalation Concrete Community Pending Preparation and Poles in Agriculture IDA / 58070 Post Driven Open - National 18,000.00 0.00 Implementa 2019-01-15 2019-01-20 2019-03-03 2019-04-02 2019-05-07 2019-11-03 Infrastructure Lands (0.12 x 0.12 x Development tion Development 0.75m) = (3600 Poles) for Daung, KPT. COMMUNE NO 09/17 / House for Nurses & Sub-component 1.2: Land Teachers Ceramic tile Pending Preparation and Request for Single Stage - floor (W=9.2m, L=16.2m, IDA / 58070 Post Open - National 35,000.00 0.00 Implementa 2018-12-19 2019-02-13 2019-08-12 Infrastructure Quotations One Envelope H=6.82m, 4 bed room, 4 tion Development rooms's W.C & 4 places of kitchend) for Daung QTY 1 Unit COMMUNE NO 28/17 / Construction of Sub-component 1.2: Land Pending Community Centre Preparation and Request for Single Stage - IDA / 58070 Post Open - National 29,000.00 0.00 Implementa 2019-01-02 2019-02-27 2019-08-26 Ceramic tile floor Infrastructure Quotations One Envelope tion (W=7.2m, L=17.2m, Development H=6.62m, Warehouse, 2 rooms's W.C) for Daung (1). Total: 1 Unit COMMUNE NO 01/17 / Sub-component 1.2: Land Repair Earth Roads for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 22,000.00 21,614.12 Signed 2018-05-29 2018-07-24 2019-07-24 Sambok (6.6km). Total: Infrastructure Quotations One Envelope 6.6Km Development COMMUNE NO 02/17 / Sub-component 1.2: Land Repair Earth Roads for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 22,000.00 21,576.00 Signed 2018-05-29 2018-07-24 2019-07-24 Changkrang (6.6km) Total: Infrastructure Quotations One Envelope 6.6Km Development COMMUNE NO 03/17 / Sub-component 1.2: Land Request for Single Stage - Repair Earth Roads for IDA / 58070 Preparation and Post Open - National 13,333.33 9,934.00 Signed 2018-05-29 2018-07-24 2019-07-24 Quotations One Envelope Thmey (4km). Total: 4Km Infrastructure Development COMMUNE NO 04/17 / Sub-component 1.2: Land Request for Single Stage - Repair Earth Roads for IDA / 58070 Preparation and Post Open - National 26,000.00 25,497.00 Signed 2018-05-29 2018-07-24 2019-07-24 Quotations One Envelope Dar (7.8km). Total: 7.8 Infrastructure Km Development COMMUNE/KRT/W/64/18 Sub-component 1.2: Land / Ploughing (2 Times) for Pending Preparation and Request for Single Stage - Sambok Commune IDA / 58070 Post Open - National 24,444.44 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope (100Ha+120Ha=220Ha), tion Development Chetr Borey, Kratie. COMMUNE/KRT/W/65/18 Sub-component 1.2: Land / Ploughing (2 Times) for Pending Preparation and Request for Single Stage - Changkrang Commune IDA / 58070 Post Open - National 15,444.44 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope (59Ha+80Ha=139Ha), tion Development Chetr Borey, Kratie. COMMUNE/KRT/W/66/18 Sub-component 1.2: Land Pending / Ploughing (2 Times) for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 10,777.78 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Dar Commune (97Ha), Infrastructure Quotations One Envelope tion Chetr Borey, Kratie. Development COMMUNITY/KCH/W/07A/ 18 / 1) Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Community Pending Lands (0.12x0.12x0.75m) = Preparation and IDA / 58070 Post Driven Open - National 18,900.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 (700 Poles) and 2) Infrastructure Development tion Concrete Poles in Forestry Development & in SLC Sites (0.3x 0.3x 0.4x 1.5m) for Sambok Kriel (20 Poles). COMMUNITY/KCH/W/08A/ Sub-component 1.2: Land 18 / Concrete Poles in Community Pending Preparation and Agriculture & Residential IDA / 58070 Post Driven Open - National 10,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Infrastructure Lands (0.12x0.12x0.75m) Development tion Development for Ksach Sar (400 Poles). Page 4 COMMUNITY/KCH/W/09A/ 18 / 1) Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Community Pending Lands (0.12x0.12x0.75m) = Preparation and IDA / 58070 Post Driven Open - National 12,100.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 (400 Poles) and Concrete Infrastructure Development tion Poles in Forestry & in Development SLC Sites (0.3x0.3x0.4x1.5m) for Peam (30 Poles). COMMUNITY/KCH/W/34A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 25,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Culverts (H1xL6m) for Infrastructure Development tion Sambok Kriel: 10 Units. Development COMMUNITY/KCH/W/35A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 37,500.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Culverts (H1xL6m) for Infrastructure Development tion Ksach Sar: 15 Units Development COMMUNITY/KCH/W/36A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 12,500.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Culverts (H1xL6m) for Infrastructure Development tion Peam: 5 Units Development COMMUNITY/KCH/W/37A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 25,000.00 0.00 Implementa 2018-06-06 2018-06-11 2018-07-23 2018-08-22 2018-09-26 2019-03-25 Culverts (H1xL6m) for Infrastructure Development tion Chhean Loeun: 10 Units. Development COMMUNITY/KSP/W/10A/ 18 / 1) Concrete Poles in Forestry & in SLC Sites Sub-component 1.2: Land Community Pending (0.3x0.3x0.4x1.5m) (20 Preparation and IDA / 58070 Post Driven Open - National 2,570.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Poles) and 2) Concrete Infrastructure Development tion Poles in Stream and Development Canal (0.2x0.2x1.5m) for Raksmey Samaki (26 Poles). COMMUNITY NO 10/18 / 1) Concrete Poles in Forestry & in SLC Sites Sub-component 1.2: Land (0.3x0.3x0.4x1.5m) (20 Preparation and Request for Single Stage - IDA / 58070 Post Open - National 2,570.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 Poles) and 2) Concrete Infrastructure Quotations One Envelope Poles in Stream and Development Canal (0.2x0.2x1.5m) for Raksmey Samaki (26 Poles) COMMUNITY/KSP/W/38A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 37,500.00 0.00 Implementa 2018-06-15 2018-06-20 2018-08-01 2018-08-31 2018-10-05 2019-01-03 Culverts (H1xL6m) for Infrastructure Development tion Raksmey Samaki: 15 Development Units COMMUNITY NO 38/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 37,500.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Raksmey Samaki: 15 Development Units COMMUNITY NO 17/18 Sub-component 1.2: Land / Planting Grass of Earth Preparation and Request for Single Stage - IDA / 58070 Post Open - National 18,750.00 0.00 Canceled 2018-03-06 2018-05-01 2018-10-28 Roads (W5xT0.15xE0.5m) Infrastructure Quotations One Envelope for Tipo 1 (15Km) Development COMMUNITY/KPT/W/17A/ Sub-component 1.2: Land Community Pending 18 / Planting Grass of Preparation and IDA / 58070 Post Driven Open - National 18,750.00 0.00 Implementa 2019-03-15 2019-03-20 2019-05-01 2019-05-31 2019-07-05 2019-10-03 Earth Roads Infrastructure Development tion (W5xT0.15xE0.5m) for Development Tipo 1 (15Km) COMMUNITY NO 18/18 Sub-component 1.2: Land / Planting Grass of Earth Preparation and Request for Single Stage - IDA / 58070 Post Open - National 15,000.00 0.00 Canceled 2018-03-06 2018-05-01 2018-10-28 Roads (W5xT0.15xE0.5m) Infrastructure Quotations One Envelope for Tipo 2 (12Km) Development COMMUNITY/KPT/W/18A/ Sub-component 1.2: Land Community Pending 18 / Planting Grass of Preparation and IDA / 58070 Post Driven Open - National 15,000.00 0.00 Implementa 2019-03-15 2019-03-20 2019-05-01 2019-05-31 2019-07-05 2019-10-03 Earth Roads Infrastructure Development tion (W5xT0.15xE0.5m) for Development Tipo 2 (12Km) COMMUNITY NO 32/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 27,500.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Tipo 1 (10), Kg. Thom: 11 Development Units. COMMUNITY/KPT/W/32A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 27,500.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Culverts (H1xL6m) for Infrastructure Development tion Tipo 1 (10), Kg. Thom: 11 Development Units. COMMUNITY/KPT/W/33A/ Sub-component 1.2: Land 18 / Construction of Pipe Community Pending Preparation and Culverts (H1xL6m) for IDA / 58070 Post Driven Open - National 27,500.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Infrastructure Tipo 2 (10), Kg. Thom. Development tion Development Total: 11 Units. COMMUNITY NO 01/18 / Concrete Poles and Sub-component 1.2: Land Installation in Agriculture Preparation and Request for Single Stage - IDA / 58070 Post Open - National 17,700.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 & Residential Lands Infrastructure Quotations One Envelope (0.12x0.12x0.75m) for Development Sambok, Kratie (708 Poles). COMMUNITY/KRT/W/01A/ 18 / Concrete Poles and Sub-component 1.2: Land Community Pending Installation in Agriculture Preparation and IDA / 58070 Post Driven Open - National 17,700.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 & Residential Lands Infrastructure Development tion (0.12x0.12x0.75m) for Development Sambok, Kratie (708 Poles). COMMUNITY NO 02/18 Sub-component 1.2: Land / Concrete Poles in Preparation and Request for Single Stage - Agriculture & Residential IDA / 58070 Post Open - National 17,500.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 Infrastructure Quotations One Envelope Lands (0.12x0.12x0.75m) Development for Changkrang (700 Poles). COMMUNITY/KRT/W/02A/ Sub-component 1.2: Land 18 / Concrete Poles in Community Pending Preparation and Agriculture & Residential IDA / 58070 Post Driven Open - National 17,500.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Infrastructure Lands (0.12x0.12x0.75m) Development tion Development for Changkrang (700 Poles). COMMUNITY NO 05/18 / Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Lands (0.12x0.12x0.75m) = Preparation and Request for Single Stage - IDA / 58070 Post Open - National 6,950.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 (250 Poles) and Concrete Infrastructure Quotations One Envelope Poles in Forestry & in Development SLC Sites (0.3x0.3x0.4x1.5m) for Thmey (10 Poles) COMMUNITY/KRT/W/05A/ 18 / Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Community Pending Lands (0.12x0.12x0.75m) = Preparation and IDA / 58070 Post Driven Open - National 6,950.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 (250 Poles) and Concrete Infrastructure Development tion Poles in Forestry & in Development SLC Sites (0.3x0.3x0.4x1.5m) for Thmey (10 Poles) COMMUNITY NO 06/18 Sub-component 1.2: Land / Concrete Poles in Preparation and Request for Single Stage - Agriculture & Residential IDA / 58070 Post Open - National 6,750.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 Infrastructure Quotations One Envelope Lands (0.12x0.12x0.75m) Development for Chambak (270 Poles). COMMUNITY/KRT/W/06A/ Sub-component 1.2: Land 18 / Concrete Poles in Community Pending Preparation and Agriculture & Residential IDA / 58070 Post Driven Open - National 6,750.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Infrastructure Lands (0.12x0.12x0.75m) Development tion Development for Chambak (270 Poles). Page 5 COMMUNITY NO 07/18 / 1) Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Lands (0.12x0.12x0.75m) = Preparation and Request for Single Stage - IDA / 58070 Post Open - National 18,900.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 (700 Poles) and 2) Infrastructure Quotations One Envelope Concrete Poles in Forestry Development & in SLC Sites (0.3x 0.3x 0.4x 1.5m) for Sambok Kriel (20 Poles) COMMUNITY NO 08/18 Sub-component 1.2: Land / Concrete Poles in Preparation and Request for Single Stage - Agriculture & Residential IDA / 58070 Post Open - National 10,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 Infrastructure Quotations One Envelope Lands (0.12x0.12x0.75m) Development for Ksach Sar (400 Poles). COMMUNITY NO 09/18 / 1) Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Lands (0.12x0.12x0.75m) = Preparation and Request for Single Stage - IDA / 58070 Post Open - National 12,100.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 (400 Poles) and Concrete Infrastructure Quotations One Envelope Poles in Forestry & in Development SLC Sites (0.3x0.3x0.4x1.5m) for Peam (30 Poles). COMMUNITY/KRT/W/13A/ Sub-component 1.2: Land Community Pending 18 / Planting Grass of Preparation and IDA / 58070 Post Driven Open - National 7,500.00 0.00 Implementa 2019-01-08 2019-01-13 2019-02-24 2019-03-26 2019-04-30 2019-07-29 Earth Roads Infrastructure Development tion (W5xT0.15xE0.5m). for Development Sambok (6km). COMMUNITY NO 13/18 Sub-component 1.2: Land / Planting Grass of Earth Preparation and Request for Single Stage - IDA / 58070 Post Open - National 7,500.00 0.00 Canceled 2018-03-06 2018-05-01 2018-10-28 Roads (W5xT0.15xE0.5m). Infrastructure Quotations One Envelope for Sambok (6km). Development COMMUNITY NO 14/18 Sub-component 1.2: Land / Planting Grass of Earth Preparation and Request for Single Stage - IDA / 58070 Post Open - National 7,500.00 0.00 Canceled 2018-03-06 2018-05-01 2018-10-28 Roads (W5xT0.15xE0.5m) Infrastructure Quotations One Envelope for Changkrang (6km). Development COMMUNITY/KRT/W/15A/ Sub-component 1.2: Land Community Pending 18 / Planting Grass of Preparation and IDA / 58070 Post Driven Open - National 10,000.00 0.00 Implementa 2019-01-08 2019-01-13 2019-02-24 2019-03-26 2019-04-30 2019-07-29 Earth Roads Infrastructure Development tion (W5xT0.15xE0.5m) for Da Development (8km). COMMUNITY/KRT/W/19A/ Sub-component 1.2: Land Community Pending 18 / Construction of Box Preparation and IDA / 58070 Post Driven Open - National 16,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (2x3x6m) for Infrastructure Development tion Sambok (1 Unit) Development COMMUNITY/KRT/W/20A/ Sub-component 1.2: Land Community Pending 18 / Construction of Box Preparation and IDA / 58070 Post Driven Open - National 16,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (2x3x6m) for Infrastructure Development tion Changkrang (1 Unit) Development COMMUNITY/KRT/W/21A/ Sub-component 1.2: Land Community Pending 18 / Construction of Box Preparation and IDA / 58070 Post Driven Open - National 16,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (2x3x6m) for Dar Infrastructure Development tion (1 Unit) Development COMMUNITY/KRT/W/22A/ Sub-component 1.2: Land Community Pending 18 / Construction of Box Preparation and IDA / 58070 Post Driven Open - National 32,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (2x3x6m) for Infrastructure Development tion Thmey (2 Units) Development COMMUNITY/KRT/W/23A/ Sub-component 1.2: Land Community Pending 18 / Construction of Box Preparation and IDA / 58070 Post Driven Open - National 32,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (2x3x6m) for Infrastructure Development tion Chambak. Phase 1 (2 Development Units) COMMUNITY/KRT/W/24A/ Sub-component 1.2: Land Community Pending 18 / Construction of Box Preparation and IDA / 58070 Post Driven Open - National 32,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (2x3x6m) for Infrastructure Development tion Chambak. Phase 2 (2 Development Units) COMMUNITY/KRT/W/25A/ Sub-component 1.2: Land Community Pending 18 / Construction of Box Preparation and IDA / 58070 Post Driven Open - National 32,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (2x3x6m) for Infrastructure Development tion Chambak. Phase 3 (2 Development Units) COMMUNITY/KRT/W/26A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 20,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (H1xL6m) for Infrastructure Development tion Sambok, Kratie: 8 Units Development COMMUNITY/KRT/W/27A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 20,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (H1xL6m) for Infrastructure Development tion Changkrang, Kratie: 8 Development Units COMMUNITY/KRT/W/28A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 15,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (H1xL6m) for Infrastructure Development tion Dar, Kratie: 6 Units Development COMMUNITY/KRT/W/29A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 17,500.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (H1xL6m) for Infrastructure Development tion Thmey, Kratie: 7 Units Development COMMUNITY/KRT/W/30A/ Sub-component 1.2: Land Community Pending 18 / Construction of Pipe Preparation and IDA / 58070 Post Driven Open - National 10,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Culverts (H1xL6m) for Infrastructure Development tion Chambak, Kratie: 4 Units Development COMMUNITY/KTM/W/11A/ Sub-component 1.2: Land Community Pending 18 / Concrete Poles in Preparation and IDA / 58070 Post Driven Open - National 15,750.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Stream and Canal Infrastructure Development tion (0.2x0.2x1.5m) for Development Chaomkravien (350 Poles). COMMUNITY/KTM/W/16A/ Sub-component 1.2: Land Community Pending 18 / Planting Grass of Preparation and IDA / 58070 Post Driven Open - National 6,250.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Earth Roads Infrastructure Development tion (W5xT0.15xE0.5m) for Development Choamkravien (5Km) COMMUNITY/KTM/W/31A/ Sub-component 1.2: Land 18 / Construction of Pipe Community Pending Preparation and Culverts (H1xL6m) for IDA / 58070 Post Driven Open - National 20,000.00 0.00 Implementa 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Infrastructure Choamkravien, Kg. Cham: Development tion Development 8 Units COMMUNE/KCH/W/58/18 / Ploughing (2 Times) for Sub-component 1.2: Land Sambok Kriel (100Ha) and Pending Preparation and Request for Single Stage - for Ksach Sar (126.50Ha), IDA / 58070 Post Open - National 25,166.67 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope Total 226.50 Ha, tion Development Kranglovea Commune, Samaki Meanchey District, Kg. Chhnang. COMMUNITY/KPT/W/41/18 / Instalation Concrete Poles in in Residential Lands (0.12 x 0.12 x Sub-component 1.2: Land Community Pending 0.75m = 1400 Poles) and Preparation and IDA / 58070 Post Driven Open - National 9,900.00 0.00 Implementa 2018-09-17 2018-09-22 2018-11-03 2018-12-03 2019-01-07 2019-07-06 Concrete Poles in Forestry Infrastructure Development tion (0.3x0.3x0.4x1.5m = 150 Development Poles) and Concrete Poles in Stream and Canal (0.2x0.2x1.5m = 200 Poles) for Daung, KPT. COMMUNE/KPT/W/38/18 / Upgrade Earth Road to Late-Rite Roads Sub-component 1.2: Land (W4.5mxT0.15m): Tipo 1 Preparation and Request for Single Stage - IDA / 58070 Post Open - National 75,111.11 0.00 Canceled 2018-08-06 2018-10-01 2019-03-30 (AR6=1.30km, AR=14km, Infrastructure Quotations One Envelope AR16=0.85km, AR18=0.46, Development and AA1= 1.42) Total= 5.2km. (Package2) Page 6 COMMUNE/KPT/W/39/18 / Upgrade Earth Road to Late-Rite Roads Sub-component 1.2: Land (W4.5mxT0.15m): Tipo 2 Preparation and Request for Single Stage - IDA / 58070 Post Open - National 84,933.33 0.00 Canceled 2018-07-07 2018-09-01 2019-02-28 (AR01=1.10km, Infrastructure Quotations One Envelope AR02=1.20km, Development AR03=1.20km, AR04=1.13km, ARAR05=1.25km)= Total:5.88km (Package 1) COMMUNE/KPT/W/40/18 / Upgrade Earth Road to Late-Rite Roads Sub-component 1.2: Land (W4.5mxT0.15m): Tipo 2 Preparation and Request for Single Stage - IDA / 58070 Post Open - National 67,166.67 0.00 Canceled 2018-07-07 2018-09-01 2019-02-28 (AR06=1.10km, Infrastructure Quotations One Envelope AR07=1.15km, Development AR08=1.00km, AR09=0.60km, AR10=0.80km)= Total:4.65km (Package 2) COMMUNE/KCH/W/41/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - IDA / 58070 Post Open - National 77,133.33 0.00 Canceled 2018-04-07 2018-06-02 2018-11-29 (W4.5mxT0.15m): Sambok Infrastructure Quotations One Envelope Kriel = (URR/7lines = Development 5.34km). (Package 1) COMMUNE/KCH/W/43/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - IDA / 58070 Post Open - National 69,333.33 0.00 Canceled 2018-04-07 2018-06-02 2018-11-29 (W4.5mxT0.15m): Ksach Infrastructure Quotations One Envelope Sar = (URR/2lines & Development UAR/6lines = 4.8km). COMMUNE/KCH/W/44/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - IDA / 58070 Post Open - National 81,900.00 0.00 Canceled 2018-04-07 2018-06-02 2018-11-29 (W4.5mxT0.15m): Peam = Infrastructure Quotations One Envelope (URR/9lines) = 5.67km. Development (Package 1) COMMUNE/KCH/W/45/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - IDA / 58070 Post Open - National 83,344.44 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 (W4.5mxT0.15m): Peam = Infrastructure Quotations One Envelope (URR/5lines & Development UAR/3lines). Total = 5.77km. (Package 2) COMMUNE/KCH/W/47/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - IDA / 58070 Post Open - National 63,555.56 0.00 Canceled 2018-07-07 2018-09-01 2019-02-28 (W4.5mxT0.15m):Chhean Infrastructure Quotations One Envelope Loeung = (UAR/4lines). Development Total = 4.40km. (Package 2) COMMUNE/KCH/W/48/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - IDA / 58070 Post Open - National 74,677.78 0.00 Canceled 2018-07-07 2018-09-01 2019-02-28 (W4.5mxT0.15m):Chhean Infrastructure Quotations One Envelope Loeung = (UAR/6lines). Development Total = 5.17km. (Package 3) COMMUNE/KSP/W/50/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - (W4.5mxT0.15m): Raksmey IDA / 58070 Post Open - National 75,833.33 0.00 Canceled 2018-02-06 2018-04-03 2018-09-30 Infrastructure Quotations One Envelope Samaki, KSP = (Up7=3.50 Development km, and Up9=1.75km) = 5.25km. (Package 2) COMMUNE/KSP/W/51/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - (W4.5mxT0.15m): Raksmey IDA / 58070 Post Open - National 74,388.89 0.00 Canceled 2018-02-06 2018-04-03 2018-09-30 Infrastructure Quotations One Envelope Samaki, KSP = (Up8=1.65 Development km, and Up10=3.50km) = 5.15km. (Package 3) COMMUNE/KSP/W/52/18 / Upgrade Earth Road to Sub-component 1.2: Land Late-Rite Roads Preparation and Request for Single Stage - (W4.5mxT0.15m): Raksmey IDA / 58070 Post Open - National 84,500.00 0.00 Canceled 2018-03-06 2018-05-01 2018-10-28 Infrastructure Quotations One Envelope Samaki, KSP - Main = Development (Up11=5.85km) = 5.85km. (Package 4) LASED/NCDDS/W/SP/02/18 / "Upgrade Earth Road to Late-Rite Roads Sub-component 1.2: Land (W4.5mxT0.15m): Main Preparation and Request for Single Stage - IDA / 58070 Post Open - National 216,666.67 0.00 Canceled 2018-08-06 2018-10-01 2019-03-30 Road KCH Infrastructure Quotations One Envelope Sambokreal = 9km and Development Khsach Sor = 6km. (Total = 15km)" COMMUNITY NO 33/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - Culverts (H1xL6m) for IDA / 58070 Post Open - National 27,500.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Infrastructure Quotations One Envelope Tipo 2 (10), Kg. Thom. Development Total: 11 Units COMMUNITY NO 15/18 Sub-component 1.2: Land / Planting Grass of Earth Preparation and Request for Single Stage - IDA / 58070 Post Open - National 10,000.00 0.00 Canceled 2018-03-06 2018-05-01 2018-10-28 Roads (W5xT0.15xE0.5m) Infrastructure Quotations One Envelope for Da (8km). Development COMMUNITY NO 19/18 Sub-component 1.2: Land / Construction of Box Preparation and Request for Single Stage - IDA / 58070 Post Open - National 16,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (2x3x6m) for Infrastructure Quotations One Envelope Sambok (1) Development COMMUNITY NO 20/18 Sub-component 1.2: Land / Construction of Box Preparation and Request for Single Stage - IDA / 58070 Post Open - National 16,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (2x3x6m) for Infrastructure Quotations One Envelope Changkrang (1 Unit) Development COMMUNITY NO 21/18 Sub-component 1.2: Land / Construction of Box Preparation and Request for Single Stage - IDA / 58070 Post Open - National 16,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (2x3x6m) for Dar Infrastructure Quotations One Envelope (1 Unit) Development COMMUNITY NO 22/18 Sub-component 1.2: Land / Construction of Box Preparation and Request for Single Stage - IDA / 58070 Post Open - National 32,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (2x3x6m) for Infrastructure Quotations One Envelope Thmey (2 Units) Development COMMUNITY NO 23/18 Sub-component 1.2: Land / Construction of Box Preparation and Request for Single Stage - IDA / 58070 Post Open - National 32,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (2x3x6m) for Infrastructure Quotations One Envelope Chambak. Phase 1 (2 Development Units) COMMUNITY NO 24/18 Sub-component 1.2: Land / Construction of Box Preparation and Request for Single Stage - IDA / 58070 Post Open - National 32,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (2x3x6m) for Infrastructure Quotations One Envelope Chambak. Phase 2 (2 Development Units) COMMUNITY NO 25/18 Sub-component 1.2: Land / Construction of Box Preparation and Request for Single Stage - IDA / 58070 Post Open - National 32,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (2x3x6m) for Infrastructure Quotations One Envelope Chambak. Phase 3 (2 Development Units) COMMUNITY NO 26/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 20,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Sambok, Kratie: 8 Units Development COMMUNITY NO 27/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 20,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Changkrang, Kratie: 8 Development Units COMMUNITY NO 28/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 15,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Dar, Kratie: 6 Units Development Page 7 COMMUNITY NO 29/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 17,500.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Thmey, Kratie: 7 Units Development COMMUNITY NO 30/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 10,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Chambak, Kratie: 4 Units Development COMMUNITY NO 31/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - Culverts (H1xL6m) for IDA / 58070 Post Open - National 20,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Infrastructure Quotations One Envelope Choamkravien, Kg. Cham: Development 8 Units COMMUNITY NO 16/18 Sub-component 1.2: Land / Planting Grass of Earth Preparation and Request for Single Stage - IDA / 58070 Post Open - National 6,250.00 0.00 Canceled 2018-08-06 2018-10-01 2019-03-30 Roads (W5xT0.15xE0.5m) Infrastructure Quotations One Envelope for Choamkravien (5Km) Development COMMUNITY NO 11/18 Sub-component 1.2: Land / Concrete Poles in Preparation and Request for Single Stage - IDA / 58070 Post Open - National 15,750.00 0.00 Canceled 2018-06-06 2018-08-01 2019-08-01 Stream and Canal Infrastructure Quotations One Envelope (0.2x0.2x1.5m) for Development Chaomkravien (350 Poles). COMMUNITY NO 34/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 25,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Sambok Kriel: 10 Units Development COMMUNITY NO 35/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 37,500.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Ksach Sar: 15 Units Development COMMUNITY NO 36/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 12,500.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Peam: 5 Units Development COMMUNITY NO 37/18 Sub-component 1.2: Land / Construction of Pipe Preparation and Request for Single Stage - IDA / 58070 Post Open - National 25,000.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Culverts (H1xL6m) for Infrastructure Quotations One Envelope Chhean Loeun: 10 Units Development COMMUNITY/KRT/W/14A/ Sub-component 1.2: Land Community Pending 18 / Planting Grass of Preparation and IDA / 58070 Post Driven Open - National 7,500.00 0.00 Implementa 2019-01-08 2019-01-13 2019-02-24 2019-03-26 2019-04-30 2019-07-29 Earth Roads Infrastructure Development tion (W5xT0.15xE0.5m) for Development Changkrang, KRT (6km). COMMUNE/TKM/W/69/19 / Construction of Sub-component 1.2: Land Pending community market (size Preparation and Request for Single Stage - IDA / 58070 Post Open - National 15,000.00 0.00 Implementa 2019-03-06 2019-05-01 2019-10-28 5m x 6m roof zine and Infrastructure Quotations One Envelope tion concrete basement) in Development Choamkravien, TKM. Toatl: 1 Unit COMMUNE/KCH/W/70/19 / Construction of Sub-component 1.2: Land Pending community market (size Preparation and Request for Single Stage - IDA / 58070 Post Open - National 15,000.00 0.00 Implementa 2019-03-06 2019-05-01 2019-10-28 5m x 6m roof zine and Infrastructure Quotations One Envelope tion concrete basement) in Development Peam, KCH. Total: 1 Unit COMMUNE/KPT/W/71/19 Sub-component 1.2: Land / Construction of Pending Preparation and Request for Single Stage - community market (size IDA / 58070 Post Open - National 15,000.00 0.00 Implementa 2019-03-06 2019-05-01 2019-10-28 Infrastructure Quotations One Envelope 5m x 6m roof zine and tion Development concrete basement) in Tipo, KPT. Total: 1 Unit COMMUNE/KRT/W/72/19 Sub-component 1.2: Land / Construction of Pending Preparation and Request for Single Stage - community market (size IDA / 58070 Post Open - National 15,000.00 0.00 Implementa 2019-03-06 2019-05-01 2019-10-28 Infrastructure Quotations One Envelope 5m x 6m roof zine and tion Development concrete basement) in Dar, KRT. Total: 1 Unit COMMUNE/KRT/W/73/19 / Repair Existing Earth Road in SAMBOK (A006 (AT001)=0.70km, Sub-component 1.2: Land Pending A004b=0.48km, Preparation and Request for Single Stage - IDA / 58070 Post Open - National 30,099.97 0.00 Implementa 2019-03-15 2019-05-10 2019-11-06 A010=1.26km, Infrastructure Quotations One Envelope tion A001b=1.55km, Development S007=1.940km, A007=0.780km, A024=1.015km, A034=1.300km) in KRT- Total=9.03Km COMMUNE/KRT/W/74/19 / Repair Existing Earth Sub-component 1.2: Land Road in CHANGKRANG Pending Preparation and Request for Single Stage - (La Or village=4.10km, IDA / 58070 Post Open - National 23,266.64 0.00 Implementa 2019-03-16 2019-05-11 2019-11-07 Infrastructure Quotations One Envelope S029=0.650km, tion Development A013b=1.13km, A15b=1.10km) in KRT- Total=6.98Km COMMUNE/KRT/W/75/19 Sub-component 1.2: Land / Repair Existing Earth Pending Preparation and Request for Single Stage - Road in DAR IDA / 58070 Post Open - National 9,066.66 0.00 Implementa 2019-03-25 2019-05-20 2019-11-16 Infrastructure Quotations One Envelope (S004=1.32km, tion Development A007=1.00km, S012=0.40km) - in KRT. Total=2.72Km COMMUNE/KRT/W/76/19 / Repair Existing Earth Road in THMEI Sub-component 1.2: Land Pending (A002a=1.07km, Preparation and Request for Single Stage - IDA / 58070 Post Open - National 28,633.30 0.00 Implementa 2019-03-25 2019-05-20 2019-11-16 A012a=1.39km, S006A = Infrastructure Quotations One Envelope tion 0.467 KM, A006a=1.703, Development S004a=0.467km, Boeung Svay Chrum road=3.50km) - in KRT. Total= 8.59Km LASED/NCDDS/W/NCB/04/ 17 / Construction Earth Roads(W5xT0.15xE0.5m):L OT1:Sambok(14.975),Ch.kra ng(6),Dar(8),Thmey(10), Sub-component 1.2: Land Chambak(29.091),Choamkr Preparation and Request for Single Stage - IDA / 58070 Post Open - National 2,860,000.00 2,404,574.45 Signed 2019-02-20 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2019-12-09 avien- Infrastructure Bids One Envelope TKM(5),TP1(15),TP2(12).To Development tal:100.410km.LOT2:S.Kriel (14), Ks.Sar(14),Peam(14),Chh.Lo eung(7),Ra.Samaki(7).Total: 29.590km.GrandTotal:130K m LASED/NCDDS/W/NCB/10/ 19 / Construction of Community Rain Water Storage at Thmey 1 line (L:600m, TW:5m, Laterite Sub-component 1.2: Land Pending Layer, 1 Double Box Preparation and Request for Single Stage - IDA / 58070 Post Open - National 294,776.67 0.00 Implementa 2019-02-15 2019-02-20 2019-04-03 2019-05-03 2019-06-07 2019-12-04 Culvert with lifting Gates) Infrastructure Bids One Envelope tion and Chambak 1 line Development (L:160m, TW:5m,Laterite Layer, 1 Double Box Culvert with Lifting Gates) in KRT. Total: 2 lines. LASED/NCDDS/W/NCB/11/ 19 / Construction of Community Natural Live Stream Storage at Tipo Sub-component 1.2: Land Pending Commune 1 line (L:600m, Preparation and Request for Single Stage - IDA / 58070 Post Open - National 322,493.33 0.00 Implementa 2019-02-20 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2019-12-09 TW:5m, Laterite Layer, Infrastructure Bids One Envelope tion Double Box Culvert with Development lifting Gates, and One line of Spillway structure of 45 m) in KPT. Total: 1 line LASED/NCDDS/W/NCB/12/ 19 / Construction of Community Natural Live Stream Storage 1 line: Sub-component 1.2: Land Pending Dyke (L:200m, TW:5m, Preparation and Request for Single Stage - IDA / 58070 Post Open - National 338,888.89 0.00 Implementa 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 2020-04-17 Laterite Layer, Double Infrastructure Bids One Envelope tion Box Culvert with lifting Development Gates, One line of Spillway structure of 45m) at Prey Thom, KSP, Total: 1 line Page 8 LASED/NCDDS/W/NCB/13/ 19 / Construction of Community Rain Water Storage at 1)Ksach Sar 1 Sub-component 1.2: Land line(L:200m, TW:5m), 2) Pending Preparation and Request for Single Stage - Kiri Aphivath 1 line IDA / 58070 Post Open - National 416,222.22 0.00 Implementa 2019-06-20 2019-06-25 2019-08-06 2019-09-05 2019-10-10 2020-04-07 Infrastructure Bids One Envelope (L:150m,TW:5m), 3) tion Development Sambok Kreal 1 line (Dyke L:80m, TW:5m) and 4) Pond at Sok Senchey (80mx50m) in KCH. Total: 3 lines & 1 Pond. LASED/NCDDS/W/NCB/06/ 17 / Small Dam(W4xSite Slop1:2, average embankment, length depends on each site,1spill Sub-component 1.2: Land way 20m,water double Preparation and Request for Single Stage - IDA / 58070 Post Open - National 980,000.00 0.00 Canceled 2018-09-03 2018-09-08 2018-10-20 2018-11-19 2018-12-24 2019-06-22 gates (2x2m=4m):Lot Infrastructure Bids One Envelope 1:S.bok(1),Ch.krang(1), Development Thmey(1),Chambak(1),TP1( 1),TP2(1)&Daung(1).Lot 2:Sb.Kriel(1),Ks.Sar(1),Pea m(1) and R.Samaki(1).Total: 11Unit COMMUNITY/KRT/W/55/19 Sub-component 1.2: Land Pending / Planting Grass of Earth Preparation and IDA / 58070 Post Direct Selection Direct 11,287.50 0.00 Implementa 2019-06-17 2019-06-22 2019-07-27 2020-01-23 Roads (W5xT0.15xE0.5m). Infrastructure tion for SAMBOK, (9.03km) Development COMMUNITY/KRT/W/56/19 Sub-component 1.2: Land Pending / Planting Grass of Earth Preparation and IDA / 58070 Post Direct Selection Direct 8,725.00 0.00 Implementa 2019-03-20 2019-03-25 2019-04-29 2019-10-26 Roads (W5xT0.15xE0.5m) Infrastructure tion for CHANGKRANG Development (6.98km) COMMUNITY/KRT/W/57/19 Sub-component 1.2: Land Pending / Planting Grass of Earth Preparation and IDA / 58070 Post Direct Selection Direct 3,400.00 0.00 Implementa 2019-06-20 2019-06-25 2019-07-30 2020-01-26 Roads (W5xT0.15xE0.5m) Infrastructure tion for DAR (2.72km) Development COMMUNITY/KRT/W/58/19 Sub-component 1.2: Land Pending / Planting Grass of Earth Preparation and IDA / 58070 Post Direct Selection Direct 10,737.50 0.00 Implementa 2019-06-20 2019-06-25 2019-07-30 2020-01-26 Roads (W5xT0.15xE0.5m) Infrastructure tion for THMEI (8.59km) Development COMMUNITY/KRT/W/59/19 Sub-component 1.2: Land Pending / Repair health post in Preparation and IDA / 58070 Post Direct Selection Direct 3,000.00 0.00 Implementa 2019-03-20 2019-03-25 2019-04-29 2019-10-26 CHAMBAK which was Infrastructure tion built during LASED I Development COMMUNITY/KRT/W/60/19 Sub-component 1.2: Land Pending / Fence for health post in IDA / 58070 Preparation and Post Direct Selection Direct 3,000.00 0.00 Implementa 2019-03-15 2019-03-20 2019-04-24 2019-10-21 CHAMBAK 300m Infrastructure tion Development GOODS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/G/NCB/07/ 16 / OfficeFurniture:Nat.+3New Provi:(30MeetChr, 28Desks, 58Chr, 4MeetTab, Component 2: Project Request for Single Stage - 2Filingcabi,3SlidingCabi,6Fi IDA / 58070 Post Open - National 40,110.00 37,270.50 Signed 2017-02-06 2017-04-03 2018-04-03 Management Quotations One Envelope lingCabi). 3Distr:(15Des, 45Chr, 3SlidingCabi, 3FilingCabi, 3MeetTab) 5NewHP:(10Des,10Char,5Sl idingCabi,5FilingCabi+4Dra w, 5Connected 3Cha,10Bed,5WaterFilter) LASED/NCDDS/G/SP/10/17 / GPS Mapping+Licenses: NCDDS 2, GSSLC 4, GDA 5, (KCH,KSP,TBM) 3, Total GPS:14 units. Sub-Component 1.1: Social Concrete Test Hammer for Land Concession Request for Single Stage - IDA / 58070 Post Open - National 44,311.11 42,260.00 Signed 2017-02-06 2017-04-03 2017-09-30 3 new provinces 3 & for Investment Planning and Quotations One Envelope NCDDS 1. Dynamic Cone Prioritization Penetrometer(DCP) for new provinces 3 and NCDDS 1. Topography Survey for new provinces 3 &NCDDS 1. LASED/NCDDS/G/NCB/01/ Sub-component 1.3: 16 / Vehicles : 9 Pickup Request for Single Stage - IDA / 58070 Agriculture and Post Open - National 270,000.00 243,531.00 Signed 2016-11-14 2016-11-19 2016-12-31 2017-01-30 2017-03-06 2017-09-02 Trucks for National Level Bids One Envelope Livelihood Development and Sub-National. LASED/NCDDS/G/SP/06/16 Component 2: Project Request for Single Stage - / Software (GIS, IDA / 58070 Post Open - National 24,200.00 15,760.00 Signed 2016-11-26 2017-01-21 2018-01-21 Management Quotations One Envelope Accounting) for NCDDS, GSSLC & GDA LASED/NCDDS/G/NCB/02/ 16 / Motorcycles: for Province(KSP: 10, KCH: 10, TBK: 10), for District: Sub-component 1.2: Land (SMC: 5, OR: 5, PBL:5), Preparation and Request for Single Stage - IDA / 58070 Post Open - National 115,500.00 100,170.00 Signed 2016-12-31 2017-01-05 2017-02-16 2017-03-18 2017-04-22 2018-04-22 for Communes: (CL:1, Infrastructure Bids One Envelope PM:1, RSMSK:1, DG:1, Development KLV:1), for NCDDS: 3 Units, GSSLC: 3 Units, GDA: 7 Units. Total 63 Units LASED/NCDDS/G/NCB/03/ 16 / Computer&Photocopy Machine: Lot 1: Nat.: 37Laptops,3LaserJet Printers, 4Scaners. Provi.: 49Laptops, 5LaserJet Component 2: Project Request for Single Stage - Printer & 5Scaner. IDA / 58070 Post Open - National 177,460.00 191,151.40 Signed 2016-11-30 2016-12-05 2017-01-16 2017-02-15 2017-03-22 2018-03-22 Management Bids One Envelope Distr.:14Laptops, 7LaserJet Printers.Lot 2: Nat.: 3Photocopy, 4LCD Projector+Screen, Provi.:5Photocopy & 5LCD Projector+Screen LASED/NCDDS/G/SP/08/16 Sub-Component 1.1: Social Request for Single Stage - / Soil Testing Kits (16 IDA / 58070 Land Concession Post Limited 2,720.00 0.00 Canceled 2017-02-06 2017-04-03 2017-10-03 Quotations One Envelope kits) Investment Planning and Prioritization LASED/NCDDS/G/SP/01A/1 Sub-component 1.3: Request for Single Stage - 7 / 1 Pickup Trucks for IDA / 58070 Agriculture and Post Open - National 30,000.00 27,000.00 Signed 2017-10-06 2017-12-01 2018-04-03 Quotations One Envelope National Level. Livelihood Development LASED/NCDDS/G/SP/05/16 / Building new networking data center for LASED- Component 2: Project Request for Single Stage - NCDDS (1 server IDA / 58070 Post Open - National 36,000.00 0.00 Canceled 2016-12-06 2017-01-31 2018-01-31 Management Quotations One Envelope machine, fiber optic cable, and network accessory) and Internet Service Provider LASED/NCDDS/G/NCB/03A /18 / Laptop for National and Sub-National Level (4 for GDH, 2 for GDA and Component 2: Project Request for Single Stage - IDA / 58070 Post Open - National 54,400.00 55,220.00 Signed 2018-03-06 2018-05-01 2018-07-30 27 for NCDDS and 5 Management Quotations One Envelope Provinces) and 1 Desktop for (Large Monitor) for GDH. Total: 34 units LASED/NCDDS/G/SP/04/16 / Camera Equipment. A) National level: 1) Professional Camera (3 Sub-Component 1.1: Social units) and Professional Land Concession Request for Single Stage - Video Camera (3 units) IDA / 58070 Post Open - National 32,000.00 16,900.00 Signed 2018-04-07 2018-06-02 2018-08-31 Investment Planning and Quotations One Envelope for LASED-GSSLC Prioritization Communication, LASED- NCDDS & GDA. B) Provincial: 1) Camera (5 units); 2) Aircon (6 units). Page 9 LASED/NCDDS/G/SP/05A/1 6 / Building new networking data center for LASED-NCDDS (1 server, Component 2: Project Request for Single Stage - IDA / 58070 Post Open - National 48,650.00 46,840.80 Signed 2018-05-06 2018-07-01 2018-09-29 Back up Storage 4TB, Management Quotations One Envelope UPS, Other Software license, Internet service 4 years) and Android Tablet (50 Tablets) LASED/NCDDS/G/SP/09/17 / 1). Mobile loud speaker (Loud Speaker, Stand, Transmitter and Receiver) for LASED GSSLC, Sub-component 1.3: Request for Single Stage - NCDDS and GDA. Toal: 3 IDA / 58070 Agriculture and Post Limited 11,500.00 11,950.00 Signed 2018-04-07 2018-06-02 2018-11-29 Quotations One Envelope sets. 2). Loud Speaker ( Livelihood Development Loud Speaker, Microphone, Ampli, Battery and Electrical line) for 12 SLC Community Toal: 14 sets. LASED/NCDDS/G/NCB/11/ 17 / Agriculture Start-Up Sub-component 1.2: Land Packages for Daung 700 Preparation and Request for Single Stage - IDA / 58070 Post Open - National 280,000.00 206,229.76 Signed 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 2019-09-21 HH (Agri kits 8 items, Infrastructure Bids One Envelope rice 200kg/HH, vegetable Development seeds 6 items, plants 5 items) LASED/NCDDS/G/NCB/12/ 17 / Household Start-Up Sub-component 1.2: Land Pending Packages for Daung 700 Preparation and Request for Single Stage - IDA / 58070 Post Open - National 116,666.67 0.00 Implementa 2018-07-02 2018-07-07 2018-08-18 2018-09-17 2018-10-22 2019-04-20 HH (Solar lamp, Tent Infrastructure Bids One Envelope tion plastic, mat, blanket, Development water jar, water filter) LASED/NCDDS/G/NCB/13/ Sub-component 1.2: Land 17 / Shelter Construction Preparation and Request for Single Stage - IDA / 58070 Post Open - National 217,777.78 223,080.00 Signed 2018-05-01 2018-05-06 2018-06-17 2018-07-17 2018-08-21 2019-02-17 Materials (40 Zincs/HH) Infrastructure Bids One Envelope for Daung 700HH Development COMMUNE/KCH/G/03A/18 / Supply Cover Crops ( Sub-component 1.2: Land Mug bean = 20kgs/Ha and Pending Preparation and Request for Single Stage - Cashew = 210 IDA / 58070 Post Open - National 19,416.67 0.00 Implementa 2018-05-23 2018-07-18 2018-10-16 Infrastructure Quotations One Envelope Seedlings/Ha) for Peam tion Development Commune (116.5Ha), Samaki Meanchey District, Kg. Chhnang. COMMUNE/KCH/G/04A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Sub-component 1.2: Land Pending Cashew = 210 Preparation and Request for Single Stage - IDA / 58070 Post Open - National 17,166.67 0.00 Implementa 2018-05-23 2018-07-18 2018-10-16 Seedlings/Ha) for Infrastructure Quotations One Envelope tion Chheanloeurng Commune Development (103Ha), Samaki Meanchey District, Kg. Chhnang. COMMUNE/KSP/G/05- 06A/18 / Supply Cover Sub-component 1.2: Land Crops ( Mug bean = Preparation and Request for Single Stage - 20kgs/Ha and Cashew = IDA / 58070 Post Open - National 33,333.33 33,120.00 Signed 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope 210 Seedlings/Ha) for Development Reaksmey Samaki Commune (200Ha), Oral District, Kg. Speu. COMMUNE/KPT/G/07- 11A/18 / Supply Cover Crops ( Mug bean = Sub-component 1.2: Land 20kgs/Ha and Cashew = Preparation and Request for Single Stage - 210 Seedlings/Ha) Tipo 1 IDA / 58070 Post Open - National 96,823.33 923,804.64 Signed 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope = 354.44Ha & Tipo 2 Development =226.5Ha, Total = 580.94Ha for Tipo Commune, Suntuk District, Kg. Thom. COMMUNE/KRT/G/12A/18 / Supply Cover Crops ( Sub-component 1.2: Land Mug bean = 20kgs/Ha and Pending Preparation and Request for Single Stage - Cashew = 210 IDA / 58070 Post Open - National 36,666.67 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope Seedlings/Ha) for Sambok tion Development Commune (100Ha+120Ha=220Ha), Chetr Borey, Kratie. COMMUNE/KRT/G/15- 16A/18 / Supply Cover Sub-component 1.2: Land Crops ( Mug bean = Preparation and Request for Single Stage - 20kgs/Ha and Cashew = IDA / 58070 Post Open - National 29,000.00 28,779.60 Signed 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope 210 Seedlings/Ha) for Development Thmey Commune (174Ha), Chetr Borey, Kratie. COMMUNE/KRT/G/17- 19A/18 / Supply Cover Sub-component 1.2: Land Crops ( Mug bean = Pending Preparation and Request for Single Stage - 20kgs/Ha and Cashew= IDA / 58070 Post Open - National 46,166.67 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope 210 Seedlings/Ha) for tion Development Chambak Commune (277Ha), Prek Prasab, Kratie. COMMUNE/KPT/G/20- 24A/18 / Supply Cover Sub-component 1.2: Land Crops ( Mug bean = Pending Preparation and Request for Single Stage - 20kgs/Ha and Cashew= IDA / 58070 Post Open - National 83,333.33 0.00 Implementa 2019-02-06 2019-04-03 2019-09-30 Infrastructure Quotations One Envelope 210 Seedlings/Ha) for tion Development Daung Commune (500Ha), Suntuk District, Kg. Thom. COMMUNE/KCH/G/01- 02A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Cashew = Sub-component 1.2: Land Pending 210 Seedlings/Ha) for Preparation and Request for Single Stage - IDA / 58070 Post Open - National 37,750.00 0.00 Implementa 2018-05-23 2018-07-18 2018-10-16 Sambok Kriel (100Ha)and Infrastructure Quotations One Envelope tion for Ksach Sar (126.50Ha), Development Total 226.50 Ha, Kranglovea Commune, Samaki Meanchey District, Kg. Chhnang COMMUNE/G/02/18 / Planting in Agriculture Land (Ploughing and Sub-component 1.2: Land Seedling for Cover Crop) Preparation and Request for Single Stage - IDA / 58070 Post Open - National 35,138.89 0.00 Canceled 2018-01-06 2018-03-03 2018-08-30 for Ksach Sar (126.50Ha), Infrastructure Quotations One Envelope Kranglovea Commune, Development Samaki Meanchey District, Kg. Chhnang COMMUNE/G/23/18 / Planting in Agriculture Sub-component 1.2: Land Land (Ploughing and Preparation and Request for Single Stage - Seedling for Cover Crop) IDA / 58070 Post Open - National 27,777.78 0.00 Canceled 2018-01-06 2018-03-03 2018-08-30 Infrastructure Quotations One Envelope for Daung Commune, Development Prasad Balang, Kg. Thom. PHASE 4 (100Ha) of 500Ha COMMUNE/KRT/G/13A/18 / Supply Cover Crops ( Sub-component 1.2: Land Mug bean = 20kgs/Ha and Pending Preparation and Request for Single Stage - Cashew= 210 IDA / 58070 Post Open - National 23,166.67 0.00 Implementa 2018-05-23 2018-07-18 2019-01-14 Infrastructure Quotations One Envelope Seedlings/Ha) for tion Development Changkrang Commune (59Ha+80Ha=139Ha), Chetr Borey, Kratie COMMUNE/KRT/G/14A/18 / Supply Cover Crops ( Sub-component 1.2: Land Mug bean = 20kgs/Ha and Preparation and Request for Single Stage - IDA / 58070 Post Open - National 16,166.67 15,729.52 Signed 2018-05-23 2018-07-18 2019-01-14 Cashew = 210 Infrastructure Quotations One Envelope Seedlings/Ha) for Dar Development Commune (97Ha), Chetr Borey, Kratie. LASED/NCDDS/G/UN/01/19 Sub-component 1.3: Pending / Vehicles (SUV) for GDH, UN Agencies IDA / 58070 Agriculture and Post Direct 108,000.00 0.00 Implementa 2019-02-01 2019-02-06 2019-03-13 2019-09-09 NCDDS & GDA, total = 3 (Direct) Livelihood Development tion units LASED/NCDDS/G/SP/11/19 Sub-component 1.2: Land Request for Single Stage - / Solar Panel for teacher IDA / 58070 Preparation and Post Open - National 14,400.00 14,193.00 Signed 2019-03-06 2019-05-01 2019-10-28 Quotations One Envelope and nurse house, total = Infrastructure 9 sets Development Page 10 LASED/NCDDS/G/SP/12/19 / DGPS for KRT and Sub-component 1.2: Land KPT, total = 2 units Pending Preparation and Request for Single Stage - GPS for GDH (2 units), IDA / 58070 Post Open - National 61,000.00 0.00 Implementa 2019-03-20 2019-05-15 2019-11-11 Infrastructure Quotations One Envelope GDA (4 units) , and 5 tion Development units for KCH, KRT, KPT, KSP and TKM), toal = 11 units LASED/NCDDS/G/SP/13/19 Sub-Component 1.1: Social / Tape Recorder (3 units Land Concession Request for Single Stage - for NCDDS, GDH, and IDA / 58070 Post Open - National 3,200.00 3,160.00 Signed 2019-03-25 2019-05-20 2019-11-16 Investment Planning and Quotations One Envelope GDA and 5 units for 5 Prioritization provinces), total = 8 units LASED/NCDDS/G/SP/14/1 9 / Agriculture Materials:L ot 1: Soil Auger (ឧបករណ៌ខួ ងដី) for GDA, Total = 2 u nits Sub-component 1.3: Pending Request for Single Stage - Lot 2: Hatchery Machine ( IDA / 58070 Agriculture and Post Open - National 14,277.78 0.00 Implementa 2019-04-15 2019-06-10 2019-12-07 Quotations One Envelope ម៉ាស៊ីនភ្ញាស់ពងមាន់) (2 units Livelihood Development tion for Sambok, 2 units for C hangkrang, 2 units of Cha mkravien, 2 units for Tipo , 2 units for Rasmey Sam aki) Total = 10 units COMMUNE/KSP/G/20/19 Sub-component 1.2: Land Pending / Water tank with Preparation and Request for Single Stage - IDA / 58070 Post Open - National 10,500.00 0.00 Implementa 2019-03-06 2019-05-01 2019-07-30 supporter and tube Infrastructure Quotations One Envelope tion (Rasmey Samaki, KSP), Development Total = 3 units COMMUNE/KPT/G/21/19 Sub-component 1.2: Land Pending / Water tank for health Preparation and Request for Single Stage - IDA / 58070 Post Open - National 2,000.00 0.00 Implementa 2019-04-15 2019-06-10 2019-09-08 post in Dong SLC, KPT, Infrastructure Quotations One Envelope tion total = 1 units Development NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/IC/35/17 / Insurance (Group Personal Accident and Health Pending Component 2: Project Request for Single Stage - Insurance and Vehicle IDA / 58070 Post Open - National 108,900.00 0.00 Implementa 2017-03-01 2017-03-06 2017-04-17 2017-05-17 2017-06-21 2021-12-31 Management Bids One Envelope Insurance (Third Party tion Liability Driver and Passenger) CONSULTING FIRMS Activity Reference No. Actual Short List and Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of / Description Component Review Type Method Amount Terms of Reference Draft Request for Technical Proposals Evaluation Report Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual LASED/NCDDS/IC/30/17 / Sub-Component 1.1: Social Consultant Baseline Survey in year IDA / 58070 Land Concession Post Qualification Open - National 70,000.00 69,998.05 Signed 2017-01-31 2017-02-21 2017-04-06 2017-05-06 2017-06-10 2018-06-10 2017 (Local Firm) Investment Planning and Selection Prioritization LASED/NCDDS/F/35/17 / Sub-Component 1.1: Social Consultant Consulting firm for IDA / 58070 Land Concession Post Qualification Open - National 120,000.00 119,997.50 Signed 2017-09-15 2017-10-06 2017-11-19 2017-12-19 2018-01-23 2018-06-12 Irrigation Design (8 sites) Investment Planning and Selection Prioritization LASED/NCDDS/IC/31/18 / Sub-Component 1.1: Social Consultant Impact Survey for 2nd Land Concession Pending IDA / 58070 Post Qualification Open - National 50,000.00 0.00 2018-07-10 2018-07-31 2018-09-13 2018-10-13 2018-11-17 2019-11-17 year of the project/Mid- Investment Planning and Implementation Selection term review (Local Firm) Prioritization Sub-component 1.2: Land Consultant LASED/NCDDS/IC/32/21 / Open - Pending IDA / 58070 Preparation and Post Qualification 90,000.00 0.00 2021-07-13 2021-08-03 2021-09-16 2021-10-16 2021-11-20 2022-07-12 Final Impact Survey International Implementation Infrastructure Selection Development LASED/NCDDS/IC/34/17 / Service Provider for Sub-component 1.3: Quality Based Open - Implementation IDA / 58070 Agriculture and Post 514,100.00 589,967.25 Signed 2018-06-01 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-01 2018-12-06 2023-04-30 Selection International Community Development Livelihood Development Fund (for 5 years) INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/IC/10/17 / Individual Component 2: Project Admin and Finance IDA / 58070 Post Consultant Open 56,470.59 35,209.47 Signed 2017-01-01 2017-02-19 2017-03-12 2017-04-16 2021-12-31 Management Assistant at NCDDS Selection LASED/NCDDS/IC/11/17 / Individual Component 2: Project Admin and Finance IDA / 58070 Post Consultant Open 56,470.59 35,209.37 Signed 2017-01-01 2017-02-19 2017-03-12 2017-04-16 2021-12-31 Management Assistant at GDA-MAFF Selection LASED/NCDDS/IC/12/17 / Individual Component 2: Project Admin and Finance IDA / 58070 Post Consultant Open 56,470.59 34,126.12 Terminated 2017-01-01 2017-02-19 2017-03-12 2017-04-16 2021-12-31 Management Assistant at GSSLC Selection LASED/NCDDS/IC/04/16 / Sub-component 1.2: Land Individual Project Finance Consultant IDA / 58070 Preparation and Prior Consultant Open 148,235.29 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2021-08-31 at GSSLC & GDA Infrastructure Selection Development LASED/NCDDS/IC/01/16 / Sub-component 1.2: Land Individual National Operation and IDA / 58070 Preparation and Prior Consultant Open 148,235.29 0.00 Canceled 2016-08-16 2016-10-04 2016-10-25 2016-11-29 2021-08-31 M&E Advisor at NCDDS Infrastructure Selection Development LASED/NCDDS/IC/05/16 / Sub-component 1.2: Land Individual National Infrastructure IDA / 58070 Preparation and Prior Consultant Open 118,588.24 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2020-11-30 Advisor at GSSLC Infrastructure Selection Development LASED/NCDDS/IC/06/16 / Sub-component 1.2: Land Individual National Operation and IDA / 58070 Preparation and Prior Consultant Open 148,235.29 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2021-08-31 M&E Advisor at GSSLC Infrastructure Selection Development LASED/NCDDS/IC/07/16 / Sub-component 1.3: Individual National Agriculture & IDA / 58070 Agriculture and Prior Consultant Open 148,235.29 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2021-08-31 Rural Development Livelihood Development Selection Advisor at GDA - MAFF LASED/NCDDS/IC/08/16 / Sub-component 1.2: Land Individual National Communication IDA / 58070 Preparation and Prior Consultant Open 118,588.24 0.00 Canceled 2016-12-01 2017-01-19 2017-02-09 2017-03-16 2020-11-30 & Strategy Advisor at Infrastructure Selection NCDDS Development LASED/NCDDS/IC/13/17 / Sub-Component 1.1: Social One Provincial GIS, Individual Land Concession Safeguard and IDA / 58070 Post Consultant Open 101,647.06 56,587.00 Signed 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-04-15 Investment Planning and Environemental Advisor at Selection Prioritization LASED Kratie LASED/NCDDS/IC/14/17 / One Provincial GIS, Sub-Component 1.1: Social Individual Safeguard and Land Concession IDA / 58070 Post Consultant Open 101,647.06 75,689.25 Signed 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-04-15 Environemental Advisor Investment Planning and Selection for LASED Kg. Thom and Prioritization Thbong Khmum LASED/NCDDS/IC/15/17 / One Provincial GIS, Sub-Component 1.1: Social Individual Safeguard and Land Concession IDA / 58070 Post Consultant Open 101,647.06 72,085.00 Signed 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-04-15 Environmental Advisor for Investment Planning and Selection LASED Kampong Speu Prioritization and Kampong Chhnang. LASED/NCDDS/IC/16/17 / Sub-component 1.2: Land Individual Provincial Operation IDA / 58070 Preparation and Post Consultant Open 109,411.76 64,876.50 Signed 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Advisor for LASED Infrastructure Selection Kratie. Development Page 11 LASED/NCDDS/IC/17/17 / Sub-component 1.2: Land Individual Provincial Operation IDA / 58070 Preparation and Post Consultant Open 109,411.76 54,064.00 Terminated 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Advisor for LASED Tbong Infrastructure Selection Khmum. Development LASED/NCDDS/IC/18/17 / Sub-component 1.2: Land Individual Provincial Operation IDA / 58070 Preparation and Post Consultant Open 109,411.76 58,749.00 Signed 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Advisor for LASED Kg. Infrastructure Selection Thom. Development LASED/NCDDS/IC/19/17 / Sub-component 1.2: Land Individual Provincial Operation IDA / 58070 Preparation and Post Consultant Open 109,411.76 58,668.00 Signed 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Advisor for LASED Kg. Infrastructure Selection Speu. Development LASED/NCDDS/IC/20/17 / Sub-component 1.2: Land Individual Provincial Operation IDA / 58070 Preparation and Post Consultant Open 109,411.76 64,876.50 Signed 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Advisor for LASED Kg. Infrastructure Selection Chhnang. Development LASED/NCDDS/IC/21/16 / Sub-component 1.2: Land Individual Provincial Finance Preparation and IDA / 58070 Post Consultant Open 109,411.76 52,262.00 Terminated 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Consultant for LASED Infrastructure Selection Kratie. Development LASED/NCDDS/IC/22/16 / Sub-component 1.2: Land Individual Provincial Finance Preparation and IDA / 58070 Post Consultant Open 109,411.76 64,876.50 Terminated 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Consultant for LASED Infrastructure Selection Thbong Khmum. Development LASED/NCDDS/IC/23/16 / Sub-component 1.2: Land Individual Provincial Finance Preparation and IDA / 58070 Post Consultant Open 109,411.76 37,845.00 Terminated 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Consultant for LASED Kg. Infrastructure Selection Thom. Development LASED/NCDDS/IC/24/16 / Sub-component 1.2: Land Individual Provincial Finance Preparation and IDA / 58070 Post Consultant Open 109,411.76 46,855.00 Terminated 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Consultant for LASED Kg. Infrastructure Selection Speu. Development LASED/NCDDS/IC/25/16 / Sub-component 1.2: Land Individual Provincial Finance Preparation and IDA / 58070 Post Consultant Open 109,411.76 46,855.00 Terminated 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Consultant for LASED Kg. Infrastructure Selection Chhnang. Development LASED/NCDDS/IC/01A/16 Sub-component 1.2: Land Individual / Senior Sub-National Preparation and IDA / 58070 Post Consultant Open 155,294.12 134,747.00 Signed 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Project Management Infrastructure Selection Advisor at NCDDS Development LASED/NCDDS/IC/05A/16 Sub-component 1.2: Land Individual / Senior National Preparation and IDA / 58070 Post Consultant Open 118,588.24 113,262.00 Signed 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 Infrastructure Advisor at Infrastructure Selection GSSLC Development LASED/NCDDS/IC/06A/16 Sub-component 1.2: Land Individual / Senior National Preparation and IDA / 58070 Post Consultant Open 176,470.59 154,680.00 Terminated 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Operation and M&E Infrastructure Selection Advisor at GSSLC Development LASED/NCDDS/IC/07A/16 Sub-component 1.3: Individual / Senior National IDA / 58070 Agriculture and Post Consultant Open 148,235.29 106,605.00 Signed 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Agriculture & Rural Livelihood Development Selection Development Advisor at GDA - MAFF LASED/NCDDS/IC/08A/16 Sub-component 1.2: Land Individual / National Communication IDA / 58070 Preparation and Post Consultant Open 118,588.24 105,626.91 Signed 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 & Strategy Advisor at Infrastructure Selection NCDDS Development LASED/NCDDS/IC/26/16 / Sub-component 1.2: Land Individual Provincial Infrastructure IDA / 58070 Preparation and Post Consultant Open 87,529.41 64,876.50 Signed 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 Engineer at LASED Infrastructure Selection Kratie Development LASED/NCDDS/IC/27/16 / Sub-component 1.2: Land Individual Provincial Infrastructure Preparation and IDA / 58070 Post Consultant Open 87,529.41 64,876.50 Signed 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 Engineer for LASED Kg. Infrastructure Selection Thom and Thbong Development Khmum LASED/NCDDS/IC/28/16 / Sub-component 1.2: Land Provincial Infrastructure Individual Preparation and Engineer for LASED IDA / 58070 Post Consultant Open 87,529.41 66,679.00 Signed 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 Infrastructure Kampong Speu and Selection Development Kampong Chhnang. LASED/NCDDS/IC/29/17 / Sub-Component 1.1: Social International Short-Term Individual Land Concession Consultant for Internal IDA / 58070 Post Consultant Open 100,000.00 83,720.93 Signed 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 Investment Planning and Review and Report Selection Prioritization (1month x 6times) LASED/NCDDS/IC/33/21 / Sub-Component 1.1: Social Individual National Consultant for Land Concession Pending IDA / 58070 Post Consultant Open 65,000.00 0.00 2020-12-31 2021-02-18 2021-03-11 2021-04-15 2021-12-31 Preparing Project Investment Planning and Implementation Selection Completion Report. Prioritization LASED/NCDDS/IC/37/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 27,748.65 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Sambok, KRT LASED/NCDDS/IC/38/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 21,473.38 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for ChangKrang, KRT LASED/NCDDS/IC/39/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 34,688.25 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Da, KRT LASED/NCDDS/IC/40/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 21,473.38 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Thmey, KRT LASED/NCDDS/IC/41/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 16,076.32 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Chambak, KRT LASED/NCDDS/IC/42/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 29,346.23 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Choamkravien, TKM LASED/NCDDS/IC/43/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 31,329.12 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Tipo, KPT LASED/NCDDS/IC/44/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 38,205.00 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Dong, KPT LASED/NCDDS/IC/45/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 30,434.00 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Kraing Lavea, KCH LASED/NCDDS/IC/46/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 29,091.32 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Chheanloeung, KCH LASED/NCDDS/IC/47/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 31,329.12 Terminated 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Peam, KCH Page 12 LASED/NCDDS/IC/48/17 / Sub-component 1.3: Individual Community Development IDA / 58070 Agriculture and Post Consultant Open 48,000.00 26,853.53 Signed 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 and Agriculture Facilitator Livelihood Development Selection for Raksmeysamaki, Oral, KSP LASED/NCDDS/IC/09/16 / Sub-component 1.2: Land Individual Procurement and Contract Preparation and IDA / 58070 Prior Consultant Open 104,470.59 0.00 Canceled 2016-08-22 2016-10-10 2016-10-31 2016-12-05 2021-07-31 Management Assistant at Infrastructure Selection NCDDS Development LASED/NCDDS/IC/02/16 / Sub-component 1.2: Land Individual National Procurement and Preparation and IDA / 58070 Prior Consultant Open 158,117.65 0.00 Canceled 2016-08-22 2016-10-10 2016-10-31 2016-12-05 2020-07-31 Contract Management Infrastructure Selection Advisor at NCDDS Development LASED/NCDDS/IC/03/16 / Sub-component 1.2: Land Individual Project Finance Consultant IDA / 58070 Preparation and Prior Consultant Open 148,235.29 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2021-08-31 at NCDDS Infrastructure Selection Development LASED-NCDDS-IC-02A-16 Sub-component 1.2: Land / Senior National Individual Preparation and Procurement and Contract IDA / 58070 Post Consultant Open 158,117.65 158,258.00 Signed 2016-08-31 2016-10-19 2016-11-09 2016-12-14 2020-12-13 Infrastructure Management Advisor at Selection Development NCDDS LASED-NCDDS-IC-03A-16 Sub-component 1.2: Land / Senior National Project Individual Preparation and Financial Management IDA / 58070 Post Consultant Open 176,470.59 70,400.00 Signed 2016-09-11 2016-12-07 2016-12-28 2017-02-01 2021-12-31 Infrastructure Consultant at NCDDS, Selection Development GSSLC and GDA LASED-NCDDS-IC-09A-16 Sub-component 1.2: Land Individual / Procurement and Preparation and IDA / 58070 Post Consultant Open 104,470.59 66,375.00 Signed 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2021-12-31 Contract Management Infrastructure Selection Assistant at NCDDS Development LASED/NCDDS/IC/36A/17 / One Consultant for Individual Component 2: Project Develop and Upgrade of IDA / 58070 Post Consultant Open 86,000.00 82,950.00 Signed 2017-08-28 2017-10-16 2017-11-06 2017-12-11 2019-02-04 Management Management Information Selection System (MIS) for District LASED/NCDDS/IC/36/17 / One Consultant for Individual Component 2: Project Develop and Upgrade of IDA / 58070 Post Consultant Open 40,000.00 0.00 Canceled 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2019-05-13 Management Management Information Selection System (MIS) for District LASED/NCDDS/IC/50/17 / Sub-Component 1.1: Social Individual One Consultant for IDA / 58070 Land Concession Post Consultant Open 23,760.00 63,300.00 Signed 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2021-12-31 Annual Progress Survey Investment Planning and Selection Prioritization Individual LASED/NCDDS/IC/49/17 / Component 2: Project IDA / 58070 Post Consultant Open 112,941.18 108,335.29 Signed 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2021-12-31 IT Adviser Management Selection LASED/NCDDS/IC/51/18 / One National Consultant Sub-Component 1.1: Social Individual for PIM revision of Land Concession Pending IDA / 58070 Post Consultant Open 16,000.00 0.00 2018-11-01 2018-12-20 2019-01-10 2019-02-14 2019-08-13 LASEDII (Lumpsum Investment Planning and Implementation Selection Contract external short Prioritization term consultant out put base) LASED/NCDDS/IC/52/18 / One National Consultant for Small scale Solar- Sub-Component 1.1: Social irrigation system study in Individual Land Concession Pending 2 sites in Dar and Choam IDA / 58070 Post Consultant Open 30,000.00 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 Investment Planning and Implementation krovien (Lumpsum Selection Prioritization Contract external short term consultant out put base for study (2 sites) for LASED II. LASED/NCDDS/IC/53/18 / One National Consultant Sub-Component 1.1: Social for Socio Economic Individual Land Concession Pending baseline survey (Lumpsum IDA / 58070 Post Consultant Open 20,000.00 0.00 2018-08-01 2018-09-19 2018-10-10 2018-11-14 2019-05-13 Investment Planning and Implementation Contract external short Selection Prioritization term consultant out put base for LASED II LASED/NCDDS/IC/54/18 / One National Consultant Sub-Component 1.1: Social for Effectiveness Individual Land Concession Pending application of safeguard IDA / 58070 Post Consultant Open 25,000.00 0.00 2018-10-01 2018-11-19 2018-12-10 2019-01-14 2019-07-13 Investment Planning and Implementation assessment (Lumpsum Selection Prioritization Contract short term consultant out put base) for LASED II LASED/NCDDS/IC/55/18 / Individual Component 2: Project Under M&E and Training IDA / 58070 Post Consultant Open 33,882.35 0.00 2018-08-06 2018-09-24 2018-10-15 2018-11-19 2021-11-18 Management Implementation Assistant (MTA) Selection LASED/NCDDS/IC/25A/18 Sub-component 1.2: Land Individual / Provincial Finance Preparation and Under IDA / 58070 Post Consultant Open 96,411.76 0.00 2018-08-24 2018-10-12 2018-11-02 2018-12-07 2021-12-31 Consultant for LASED Kg. Infrastructure Implementation Selection Chhnang. (New) Development LASED/NCDDS/IC/56/19 / Sub-component 1.3: Individual Senior Agronomist and IDA / 58070 Agriculture and Post Consultant Open 94,823.53 92,510.29 Signed 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2021-12-31 Value Chain Adviser for Livelihood Development Selection GDA LASED/NCDDS/IC/57/19 / Consultant for Sub-Component 1.1: Social Individual Measurement the Land Concession Pending IDA / 58070 Post Consultant Open 20,000.00 0.00 2019-04-19 2019-06-07 2019-06-28 2019-08-02 2020-01-31 awareness and Investment Planning and Implementation Selection understanding of LRs and Prioritization project team on the LASED II and SLC. LASED/NCDDS/F/36/19 / Contract with NGOs to Sub-component 1.3: form and strengthen the Pending IDA / 58070 Agriculture and Post Direct Selection Direct 40,000.00 0.00 2019-05-01 2019-05-11 2019-07-15 2021-12-31 community forestry Implementation Livelihood Development conservation in project target sites. LASED/NCDDS/IC/17A/19 Sub-component 1.2: Land Individual Pending / Provincial Operation IDA / 58070 Preparation and Post Consultant Open 54,705.88 0.00 2019-03-15 2019-05-03 2019-05-24 2019-06-28 2021-12-31 Implementation Advisor for LASED Infrastructure Selection Thbong Khmum. Development LASED/NCDDS/IC/23A/19 Sub-component 1.2: Land Individual / Provincial Finance Preparation and Pending IDA / 58070 Post Consultant Open 56,529.41 0.00 2019-03-25 2019-05-13 2019-06-03 2019-07-08 2021-12-31 Consultant for LASED Kg. Infrastructure Implementation Selection Thom. (New) Development LASED/NCDDS/IC/06B/19 Sub-component 1.2: Land Individual / New Senior National Preparation and IDA / 58070 Post Consultant Open 91,176.50 90,485.29 Signed 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2021-12-31 Operation and M&E Infrastructure Selection Advisor at GDH Development LASED/NCDDS/IC/59/19 / National Short-Term Sub-component 1.2: Land Consultant for Social Risk Preparation and Pending IDA / 58070 Post Direct Selection Direct 13,500.00 0.00 2019-08-29 2019-09-08 2019-11-12 2020-02-10 Management Framework Infrastructure Implementation Development for LASED Development III Preparation LASED/NCDDS/IC/60/19 / National Short-Term Sub-component 1.2: Land Consultant for Preparation and Pending Environmental Risk IDA / 58070 Post Direct Selection Direct 13,500.00 0.00 2019-08-29 2019-09-08 2019-11-12 2019-11-21 Infrastructure Implementation Management Framework Development Development for LASED III Preparation LASED/NCDDS/IC/61/19 / Sub-component 1.2: Land National Monitoring and Preparation and Pending IDA / 58070 Post Direct Selection Direct 78,400.00 0.00 2019-08-29 2019-09-08 2019-11-12 2021-12-31 Evaluation Consultant for Infrastructure Implementation LASED II at NCDDS Development Page 13 LASED/GDH/IC/62/19 / Sub-component 1.2: Land National Monitoring and Preparation and Pending IDA / 58070 Post Direct Selection Direct 78,400.00 0.00 2019-08-29 2019-09-08 2019-11-12 2021-12-31 Evaluation Consultant for Infrastructure Implementation LASED II at GDH Development LASED/NCDDS/IC/58/19 / Sub-component 1.2: Land International Short-Term Preparation and Pending IDA / 58070 Post Direct Selection Direct 18,750.00 0.00 2019-09-26 2019-10-06 2019-12-10 2020-01-04 Consultant for Infrastructure Implementation Environmental Development Management LASED/NCDDS/IC/47A/19 Sub-component 1.3: Individual / Community Development Pending IDA / 58070 Agriculture and Post Consultant Open 22,400.00 0.00 2019-09-26 2019-11-14 2019-12-05 2020-01-09 2021-12-31 and Agriculture Facilitator Implementation Livelihood Development Selection for Peam, KCH (New) KH-NCDDS-135175-CS- Sub-component 1.2: Land CDS / International Short Preparation and Pending IDA / 58070 Post Direct Selection Direct 30,000.00 0.00 2019-09-26 2019-10-06 2019-12-10 2020-01-19 Term Consultant for Infrastructure Implementation Social Risk Management Development LASED/NCDDS/IC/21A/19 Sub-component 1.2: Land Individual / Provincial Finance Preparation and Pending IDA / 58070 Post Consultant Open 45,588.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2021-12-31 Consultant for LASED Infrastructure Implementation Selection Kratie (New) Development LASED/NCDDS/IC/22A/19 Sub-component 1.2: Land Individual / Provincial Finance Preparation and Pending IDA / 58070 Post Consultant Open 45,588.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2021-12-31 Consultant for LASED Infrastructure Implementation Selection Tbong Khmum (New) Development LASED/NCDDS/IC/24A/19 Sub-component 1.2: Land Individual / Provincial Finance Preparation and Pending IDA / 58070 Post Consultant Open 45,588.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2021-12-31 Consultant for LASED Kg. Infrastructure Implementation Selection Speu. (New) Development LASED/GDH/IC/12A/19 / Individual Component 2: Project Pending Admin and Finace IDA / 58070 Post Consultant Open 23,529.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2021-12-31 Management Implementation Assistant at GDH (New) Selection LASED/GDH/IC/63/19 / Sub-Component 1.1: Social Short-term consultant to Individual Land Concession Pending produce Orthophoto for IDA / 58070 Post Consultant Open 7,600.00 0.00 2019-11-05 2019-12-24 2020-01-14 2020-02-18 2020-08-16 Investment Planning and Implementation Land Activities in Daung Selection Prioritization Site, KPT LASED/GDH/IC/64/19 / Sub-Component 1.1: Social Short-term Consultant to Individual Land Concession Pending Update, Revised PIM / IDA / 58070 Post Consultant Open 30,000.00 0.00 2019-11-15 2020-01-03 2020-01-24 2020-02-28 2020-08-26 Investment Planning and Implementation COM for LASED III, Selection Prioritization Including ICLT chapter. Page 14