The World Bank Report No: ISR11374 Implementation Status & Results Papua New Guinea PNG: Building a More Disaster and Climate Resilient Transport Sector (P129322) Public Disclosure Copy Operation Name: PNG: Building a More Disaster and Climate Resilient Project Stage: Implementation Seq.No: 2 Status: ARCHIVED Archive Date: 16-Dec-2013 Transport Sector (P129322) Country: Papua New Guinea Approval FY: 2012 Product Line: Recipient Executed Activities Region: EAST ASIA AND PACIFIC Lending Instrument: Technical Assistance Loan Implementing Agency(ies): Department of Works Key Dates Board Approval Date 28-Nov-2011 Original Closing Date 30-Jun-2015 Planned Mid Term Review Date 17-Feb-2014 Last Archived ISR Date 29-Jan-2013 Effectiveness Date 16-May-2012 Revised Closing Date 30-Jun-2015 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of this project is to improve the resilience of PNG to the impact of natural disasters and climate change in the transport sector through building capacity for hazard risk assessment affecting the transport sector. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Establishing a System for Risk Assessment 0.58 Supporting Data Collection Strengthening for Better Data Generation 1.04 Carrying out Small Works 0.68 Ensuring Effective Monitoring and Evaluation 0.03 Ensuring Effective Project Management 0.35 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Moderate Implementation Status Overview The pace of implementation has gradually picked up, specially in the third quarter of 2013, after effectiveness delay and slow progress the first year of implementation. Department Page 1 of 4 The World Bank Report No: ISR11374 of Works is now evaluating proposals from consulting firms for procurement of Component 1 (Establishing a system of risk assessment). Under Component 2 (Support for Strengthening Data Collection for Better Data Generation), specifications for supply and installation of equipment for National Maritime Safety Agency (NMSA), Department of Mineral Policy & Geo-Hazards Management and National Weather Service have been agreed with respective agencies and procurement process have been initiated. Under Component 3 (Small Works), DOW has defined the scope and methodology to carry out small works to demonstrate effective measures for enhancing disaster/climate resilience, and preparing Public Disclosure Copy procurement. Locations No Location data has been entered Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Data related with disaster is actively utilized Text Value Data (Hazard, Exposure, and Data utilization and updating Data actively utilized and and continuously updated risk) is partial and not not yet improved. continuously updated regularly updated or actively utilized. Date 07-Dec-2011 12-Nov-2013 31-Dec-2015 Comments Work in progress A system of disater risk assessment is in place Percentage Value 25.00 25.00 100.00 Date 07-Dec-2011 12-Nov-2013 30-Jun-2015 Comments Data and analytical tools A set of new data collection already generated by other will build upon available data. initiatives such as the Pacific Catastrophic Risk Assessment and Financing Initiative (PCRAFI) exist. Roads and bridges are analyzed for disaster Kilometers Value 0.00 0.00 10.00 risks Date 07-Dec-2013 12-Nov-2013 30-Jun-2015 Comments Work in progress This is a broad estimate of the Public Disclosure Copy target and subject to revision. Installation of the equipment provided under Number Value 0.00 0.00 3.00 Component B Date 07-Nov-2012 12-Nov-2013 30-Jun-2015 Comments Equipment includes automated tidal gauges, automated weather stations, and soil testing equipment. Page 2 of 4 The World Bank Report No: ISR11374 Training on the use of the equipment provided Text Value 0.00 0.00 25.00 under Component B is carried out for effective Date 07-Nov-2012 12-Nov-2013 30-Jun-2015 future use Comments 25 people to be trained Public Disclosure Copy Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target A user-friendly manual for design and Number Value 0.00 0.00 1.00 construction of disaster risk management Date 07-Nov-2012 12-Nov-2013 30-Jun-2015 works is developed Comments Data on Financial Performance (as of 26-Nov-2013) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P129322 TF-11267 Effective 07-Dec-2011 07-Dec-2011 16-May-2012 30-Jun-2015 30-Jun-2015 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P129322 TF-11267 Effective USD 2.67 2.67 0.00 0.25 2.42 9.00 Disbursement Graph Public Disclosure Copy Page 3 of 4 The World Bank Report No: ISR11374 Key Decisions Regarding Implementation No key decisions for disclosure. Public Disclosure Copy Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Public Disclosure Copy Page 4 of 4