Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Low-Carbon Development in Orinoquia region Project (P160680) Sustainable Low-Carbon Development in Orinoquia region Project (P160680) LATIN AMERICA AND CARIBBEAN | Colombia | Environment & Natural Resources Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2018 | Seq No: 1 | ARCHIVED on 26-Jun-2018 | ISR32847 | Implementing Agencies: Ministry of Agriculture and Rural Development (MADR), Ministry of Environment and Sustainable Development (MADS), National Planning Department (DNP), Instituto de Hidrologia, Meteorologia y Estudios Ambientales (IDEAM), Republic of Colombia Key Dates Key Project Dates Bank Approval Date:16-Feb-2018 Effectiveness Date:-- Planned Mid Term Review Date:18-Nov-2020 Actual Mid-Term Review Date:-- Original Closing Date:-- Revised Closing Date:-- Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve enabling conditions for sustainable and low-carbon landscape planning and management in project targeted areas. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Integrated Land- Use Planning and Improved Governance for Deforestation Control:(Cost $5.90 M) Sustainable Land- Use Management:(Cost $6.10 M) Definition of Emission Reduction Program and Monitoring, Reporting and Verification:(Cost $6.00 M) Project Coordination, Management, Monitoring and Evaluation:(Cost $2.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  --  Moderately Unsatisfactory Overall Implementation Progress (IP)  --  Moderately Satisfactory Overall Risk Rating  --  Substantial 6/26/2018 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Low-Carbon Development in Orinoquia region Project (P160680) Implementation Status and Key Decisions This is the first project ISR, which is filed, as required, within the first 3 months after RVP approval. The project is expected to be declared effective no later than September 4, 2018. Project activities are expected to initiate directly after effectiveness. In order to achieve effectiveness, it is proposed to reach an agreement between the Government and the WB on the required solution for the institutional arrangement by June 25, 2018. It is further proposed the Government sends a request for restructuring to the Bank by July 5, 2018. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Substantial  --  Substantial Macroeconomic  Moderate  --  Moderate Sector Strategies and Policies  Substantial  --  Substantial Technical Design of Project or Program  Substantial  --  Substantial Institutional Capacity for Implementation and Sustainability  Substantial  --  High Fiduciary  Substantial  --  Substantial Environment and Social  Substantial  --  Substantial Stakeholders  Moderate  --  Moderate Other  --  --  -- Overall  Substantial  --  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Municipalities that as result of the project incorporate sustainable and low-carbon landscape management criteria into land planning and land tenure instruments (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 7.00 Date 29-Jan-2018 -- -- 14-Jan-2022 6/26/2018 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Low-Carbon Development in Orinoquia region Project (P160680) PHINDPDOTBL  Agricultural policy instruments for promoting the adoption of sustainable and low-carbon landscape management in selected areas are adopted, as a result of the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 4.00 Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDPDOTBL  Emission Reductions Program for the Orinoquia region submitted for decision by the BioCarbon Fund (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 29-Jan-2018 -- -- 14-Jan-2022 Overall Comments Intermediate Results Indicators PHINDIRITBL  1.1. Municipal Land Tenure Plans that take account of environmental and gender criteria (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1.00 Date 29-Jan-2018 -- -- 14-Jan-2022 6/26/2018 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Low-Carbon Development in Orinoquia region Project (P160680) PHINDIRITBL  1.2. Technical guidelines to integrate sustainable and low-carbon landscape management criteria in ZIDRES regulations adopted by MADR (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1.00 Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  1.3. Technical guidelines for the interoperability of the National Environmental System (SIAC) and the National Multipurpose Cadaster System, adopted by MADS and IDEAM (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1.00 Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  1.4. Environmental Zoning finalized in two project priority municipalities (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 931,800.00 Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  1.5. Development Programs with Territorial Approach (PDETs) with environmental criteria (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 3.00 Date 29-Jan-2018 -- -- 14-Jan-2022 6/26/2018 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Low-Carbon Development in Orinoquia region Project (P160680) PHINDIRITBL  1.6. Inter-institutional protocol for deforestation control in targeted deforestation hotspots developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  2.1. Guidelines on low-carbon technologies and practices to support extension and technical assistance activities in prioritized landscapes developed and validated (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 2.00 Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL 2.2. Farm level training modules in sustainable and low-carbon agricultural practices in selected landscapes developed (with gender considerations) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 5.00 Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  2.3 Number of land users who have received training (% women) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 5,000.00 Date 29-Jan-2018 -- -- 14-Jan-2022 6/26/2018 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Low-Carbon Development in Orinoquia region Project (P160680) PHINDIRITBL  Percentage women (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 25.00 PHINDIRITBL  2.4. Agreements in key agricultural value chains signed between private and public sector for development of sustainable and low-carbon productive systems (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 4.00 Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  2.5. Financial and non-financial incentive mechanisms to promote adoption of sustainable and low-carbon practices developed under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 4.00 Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  3.1. Emissions baselines established and technically reviewed following ISFL methodological requirements (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 29-Jan-2018 -- -- 14-Jan-2022 6/26/2018 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Low-Carbon Development in Orinoquia region Project (P160680) PHINDIRITBL  3.2. Information system for safeguards for Orinoquia’s ER program operational (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL 3.3. Benefit Sharing Plan (BSP) for ER Program developed in a participatory manner and approved by the Project Steering Committee (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  3.4 AFOLU MRV system established (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 29-Jan-2018 -- -- 14-Jan-2022 PHINDIRITBL  3.5. Grievance Redress Mechanism designed and established (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 29-Jan-2018 -- -- 14-Jan-2022 Overall Comments 6/26/2018 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Low-Carbon Development in Orinoquia region Project (P160680) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/26/2018 Page 8 of 8 Public Disclosure Copy