Public Disclosure Copy The World Bank Implementation Status & Results Report Urban Scale Building Energy Efficiency and Renewable Energy (P130786) Urban Scale Building Energy Efficiency and Renewable Energy (P130786) EAST ASIA AND PACIFIC | China | Energy & Extractives Global Practice | Global Environment Project | Investment Project Financing | FY 2013 | Seq No: 12 | ARCHIVED on 18-Apr-2019 | ISR36696 | Implementing Agencies: Ministry of Housing and Urban-Rural Development, Beijing Housing and Urban-Rural Development Commission, Beijing Development and Reform Commission, Ningbo Housing and Urban-Rural Development Commission, Ministry of Finance, Center of Science and Technology for Construction (CSTC) Key Dates Key Project Dates Bank Approval Date: 26-Apr-2013 Effectiveness Date: 26-Aug-2013 Planned Mid Term Review Date: 31-Oct-2016 Actual Mid-Term Review Date: 31-Oct-2016 Original Closing Date: 31-Dec-2018 Revised Closing Date: 31-Dec-2019 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed project development objective is to improve selected national and city-level policies for (1) the promotion of low-carbon, adaptive and livable urban forms; (2) an increase in energy efficiency in public and commercial buildings; and, (3) the scale-up of commercially viable rooftop solar PV deployment. The global environment objective of the proposed project is to reduce carbon dioxide emissions from buildings in selected Chinese cities by supporting improved policy making and implementation in promoting low-carbon, adaptive and livable urban forms, increasing energy efficiency in public and commercial buildings, and scaling up commercially viable rooftop solar PV deployment. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name 1. Promoting the Development of Low-Carbon, Adaptive and Livable Urban Forms:(Cost $8.76 M) 2. Improving Energy Efficiency in Public and Commercial Buildings:(Cost $18.53 M) 3. Scaling up Commercially Viable Rooftop Solar PV Deployment:(Cost $2.00 M) 4. Project Management:(Cost $1.50 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating Substantial Moderate Implementation Status and Key Decisions 4/18/2019 Page 1 of 8 Public Disclosure Copy The World Bank Implementation Status & Results Report Urban Scale Building Energy Efficiency and Renewable Energy (P130786) Last December 2018, the project was restructured, mainly to extend its closing date to December 31, 2019 to align the duration of the support that this project is providing to the Beijing Roof Top Sunshine School Energy and Environment project also financed by the World Bank. As a consequence, the project is on track to complete all activities and achieve or exceed all its targets. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Low Low Macroeconomic -- Low Low Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Substantial Low Institutional Capacity for Implementation and Sustainability -- Substantial Low Fiduciary -- Moderate Moderate Environment and Social -- Low Low Stakeholders -- Substantial Low Other -- -- -- Overall -- Substantial Moderate Results PDO Indicators by Objectives / Outcomes Promotion of low-carbon, adaptive and livable urban forms IN00692084 ►LOCAL urban planning and design principles recommended for inclusion in statutory urban planning standards and regulations (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No Yes Yes Date 01-May-2013 30-Apr-2018 01-Apr-2019 31-Dec-2019 Standard / Regulation Name Revised Content In order to increase the species and quantity of trees, it is advisable to adopt the multi-layer green space structure “Standards for Planning and Design Comments: combining tree, irrigation and grass. The contents of of Urban Residential Areas” promoting three-dimensional greening and other greening GB50180-2018 methods have been implemented in the revision of residential area standards. 4/18/2019 Page 2 of 8 Public Disclosure Copy The World Bank Implementation Status & Results Report Urban Scale Building Energy Efficiency and Renewable Energy (P130786) Divide suitable functional zones and guide functional zoning by slow-moving scale. Promoting the Way of Dividing Residential Communities by Walking Scale of 15 Minutes Living Circle. “Standards for Planning and Design of Urban Residential Areas” Construction of non-point source treatment facilities such GB50180-2018, “Urban Drainage as rainwater purification tank, concave green space and Planning Standard” GB50318-2017, underground purification system in buffer zone to filter and “Urban Waterlogging Planning purify initial rainwater. Standard” (formulation) To create a pedestrian-friendly block, the block scale “Standards for Planning and Design should meet the requirements of reasonable branch of Walking and Bicycle Systems” network density, and be compatible with the requirements (draft for approval) of location, land use type and development control. Guiding public transport-oriented land development model (TOD), advocating intensive and efficient land development along public transport corridors and around public transport stations. According to the multi-center urban structure system, traffic facilities and services should be allocated at different levels, emphasizing the mutual support between the urban central system and the traffic system. Define the development mode of public transport, including “Standards for Planning of Urban the composition mode of public transport system, the scale Integrated Transportation System” of public transport network, layout mode and connection GB/T51328-2018 mode, and emphasize the construction of multi-level public transport system. Based on travel distance and traffic characteristics, function zoning of slow-moving units is divided, planning strategies and requirements are formulated, and pedestrian and bicycle traffic networks and nodes are reasonably laid out. Traffic organization carries out fine design to ensure the space-time priority of green traffic mode. Increase in energy efficiency in public and commercial buildings IN00692086 ►Energy performance benchmarking and disclosure (EPB&D) program for large public and commercial buildings developed at the national level and mandatory adoption by select cities. (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-May-2013 30-Apr-2018 01-Apr-2019 31-Dec-2019 4/18/2019 Page 3 of 8 Public Disclosure Copy The World Bank Implementation Status & Results Report Urban Scale Building Energy Efficiency and Renewable Energy (P130786) Pilot Situation Beijing Completed Ningbo Completed Comments: Qingdao Undergoing Chongqing Undergoing Scale-up of commercially viable rooftop solar PV deployment IN00692085 ►Number of renewable energy service contracts signed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 310.00 312.00 400.00 Date 01-May-2013 30-Apr-2018 31-Dec-2018 31-Dec-2019 IN00692087 ►CO2 emissions reduction associated with GEF assistance (Tones/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 15,300.00 66,845.00 70,000.00 Date 01-May-2013 30-Apr-2018 31-Dec-2018 31-Dec-2019 66845 tones = 67046138.4kwh * 0.997kg/kwh * 0.001,67046138.4 which is the cumulative Power generation (kWh) of all completed grid-connected projects up to 31-Feb-2018, and 0.997 is the conversion Comments: coefficient of CO2 emission reduction (kg/kwh). Overall Comments PDO As part of the restructuring, the target for "Number of renewable energy service contracts signed", has been adjusted to reflect the adjustment of the same indicator for another IBRD financed project, the Beijing Roof Top Sunshine School Project, under which these contracts are established and for which this project is providing support for monitoring results and TA not related to this indicator. Attached Aide-mémoire provides detailed evidences and explanations supporting the actual values. Intermediate Results Indicators by Components 3. Scaling up Commercially Viable Rooftop Solar PV Deployment IN00692090 ►Installed rooftop solar PV capacity under the Beijing Rooftop Solar PV Scale-up Project (Megawatt, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 42.90 36.50 100.00 4/18/2019 Page 4 of 8 Public Disclosure Copy The World Bank Implementation Status & Results Report Urban Scale Building Energy Efficiency and Renewable Energy (P130786) Date 01-Jan-2013 30-Apr-2018 04-Apr-2019 31-Dec-2019 IN00692093 ►Improved knowledge of local grid company about handling grid-connected rooftop PV systems (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-May-2013 30-Apr-2018 31-Dec-2018 30-Jun-2018 IN00692096 ►Establishment of Beijing solar energy information portal (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-May-2013 30-Apr-2018 31-Dec-2018 30-Jun-2018 IN00692098 ►Renewable energy education delivery in public schools enhanced (number of demonstration laboratories established) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 10.00 20.00 Date 01-May-2013 30-Apr-2018 31-Dec-2018 31-Dec-2019 2. Improving Energy Efficiency in Public and Commercial Buildings IN00692089 ►National and city BEP&D pilot programs implemented (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 3.00 Date 01-May-2013 30-Apr-2018 01-Apr-2019 31-Dec-2019 1. Beijing building energy consumption benchmarking tool (completed) 2. Ningbo EPB&D pilot (completed) 3. Study on implementation of the information disclosure system on energy consumption and energy Comments: efficiency of public buildings in Chongqing (Undergoing) 4. Research on Publicity Systems of Comprehensive Energy Efficiency Benchmarking Methods in Public Buildings and Renewable-energy Demonstration Projects in Qingdao (Undergoing) IN00692092 ►Selected building EE and green building policies in Beijing improved and new policies informed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-May-2013 30-Apr-2018 28-Feb-2019 30-Jun-2018 IN00692095 ►Outreach to local stakeholders and training of local trades in Beijing (number of people trained) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1,750.00 2,150.00 1,000.00 Date 01-May-2013 30-Apr-2018 28-Feb-2019 30-Jun-2018 In June 20th, the 2018 first stage assembly building training was organized, and in November 8th, the Comments: 2018 second period assembly architecture training was organized to carry out a public lecture on the 4/18/2019 Page 5 of 8 Public Disclosure Copy The World Bank Implementation Status & Results Report Urban Scale Building Energy Efficiency and Renewable Energy (P130786) development, design, production, construction, supervision, cost, decoration and BIM of the related work in green building and assembly building. Participants: Technical personnel, management personnel and civil engineering college students, nearly 400 people. IN00692097 ►Floor area of green buildings in Beijing received certificates (Square Meter(m2), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 3,000,000.00 32,206,600.00 35,198,500.00 15,000,000.00 Date 01-Jan-2013 30-Apr-2018 31-Dec-2018 30-Jun-2018 By the end of December 31, 2018, the total area of green construction project of Beijing green construction evaluation sign bulletin board was 3519.85 million square meters, of which one star 321.75 million square meters, two star 1920.76 million square meters, and three star grade 1277.34 million Comments: square meters; the design logo was 2945.16 million square meters, and the operation sign was 574.69 million square meters. IN00692099 ►Bioclimatic and cost-optimal green building designs demonstrated in Ningbo (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-May-2013 30-Apr-2018 15-Mar-2019 31-Dec-2019 1. New green building at Ningbo University has been completed and is undergoing one year of operation to receive its green building and energy efficiency certification. Comments: 2. Ningbo Kitchen Waste Treatment Plant has obtained “three-star evaluation identity of green building design” and is in trial operation. IN00692100 ►Green building policies in Ningbo improved and new policies informed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-May-2013 30-Apr-2018 15-Mar-2019 30-Jun-2018 1. Technical Guideline for Special Planning’s Compilation of Green Building in Zhejiang Province; 2. Special planning for green buildings in Ningbo; 3. Implementation rules for green building design in Ningbo; Comments: 4. Energy Efficiency Evaluation Technologies and Implementing Rules for Civil Buildings; 5. Building and structure vertical planting (green roofs and building façade) implementation guideline in Ningbo. IN00692101 ►Outreach to local stakeholders and training of local trades in Ningbo (number of people trained) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,015.00 2,100.00 800.00 Date 01-May-2013 30-Apr-2018 15-Mar-2019 30-Jun-2018 1. Promoting the Development of Low-Carbon, Adaptive and Livable Urban Forms IN00692088 ►Urban form studies completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 4.00 4/18/2019 Page 6 of 8 Public Disclosure Copy The World Bank Implementation Status & Results Report Urban Scale Building Energy Efficiency and Renewable Energy (P130786) Date 01-May-2013 30-Apr-2018 01-Apr-2019 31-Dec-2019 Project Name Status Beijing urban form study Completed Ningbo urban form study Completed Comments: Urban form study and LOCAL urban planning pilot cities through TA grants Undergoing Research and compilation on Low-Carbon oriented Regulatory Detailed Planning for Core Area of Jinzhong Starting District of Shanxi Transformation and Undergoing Comprehensive Reform Demonstration Zone (Taiyuan) IN00692091 ►Mayors and city planning officials trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,966.00 3,428.00 150.00 Date 01-May-2013 30-Apr-2018 01-Apr-2019 30-Jun-2018 IN00692094 ►City pilots of Local urban planning and design completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 1.00 3.00 Date 01-May-2013 30-Apr-2018 01-Apr-2019 31-Dec-2019 Xixian New Area (completed): Outline of Regulatory Detailed Planning on China's Western Technological Innovation Harbor Taiyuan City (undergoing): Research and compilation on Low-Carbon oriented Regulatory Detailed Comments: Planning for Core Area of Jinzhong Starting District of Shanxi Transformation and Comprehensive Reform Demonstration Zone Ningbo City (undergoing): Damuwan New Town and Xiangshan urban area. Overall Comments IR Attached Aide-mémoire provides detailed evidences and explanations supporting the actual values. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P130786 TF-14522 Effective USD 12.00 12.00 0.00 8.68 3.32 72% 4/18/2019 Page 7 of 8 Public Disclosure Copy The World Bank Implementation Status & Results Report Urban Scale Building Energy Efficiency and Renewable Energy (P130786) Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P130786 TF-14522 Effective 04-Jul-2013 04-Jul-2013 26-Aug-2013 31-Dec-2018 31-Dec-2019 Cumulative Disbursements Restructuring History Level 2 Approved on 31-Mar-2018 ,Level 2 Approved on 18-Dec-2018 Related Project(s) There are no related projects. 4/18/2019 Page 8 of 8