The World Bank Implementation Status & Results Report DRC Reinsertion and Reintegration Project (P152903) DRC Reinsertion and Reintegration Project (P152903) AFRICA | Congo, Democratic Republic of | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 7 | ARCHIVED on 09-Jul-2019 | ISR37114 | Implementing Agencies: UEPN-DDR, Democratic Republic of Congo, Represented by the Ministry of Finance Key Dates Key Project Dates Bank Approval Date: 15-May-2015 Effectiveness Date: 27-Jan-2016 Planned Mid Term Review Date: 09-Apr-2018 Actual Mid-Term Review Date: 09-Apr-2018 Original Closing Date: 31-Dec-2019 Revised Closing Date: 31-Dec-2019 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to support the socio-economic reintegration of demobilized ex-combatants. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Reinsertion:(Cost $5.35 M) Component 2: Reintegration:(Cost $8.64 M) Component 3: Support to Demobilized Ex-combatants’ Households:(Cost $3.24 M) Component 4: Support to Vulnerable Groups:(Cost $1.17 M) Component 5: Project Management, Sensitization, Monitoring and Evaluation:(Cost $3.10 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The Reinsertion and Reintegration Project is entering its final phase of implementation and will close within a few months. All technical activities have thus stopped and a lessons learned workshop (with all implementing partners and other stakeholders) was organized in June 2019. The operating challenging context (security, logistics) will have prevented the Project to fully meet its objectives. 7/9/2019 Page 1 of 5 The World Bank Implementation Status & Results Report DRC Reinsertion and Reintegration Project (P152903) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Substantial High Substantial Other High High High Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes PDO: To support the socio-economic reintegration of demobilized ex-combatants. IN00703602 ►1. Direct project beneficiaries (disaggregated by gender) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4,700.00 4,700.00 4,800.00 Date 31-Oct-2015 30-Sep-2018 31-May-2019 30-Jun-2019 IN00703603 ►2. Adult individual beneficiaries participating in an economic activity 6 months after training completion (disaggregated by gender, individual or economic association, agrarian/non-agrarian) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 25.70 25.70 25.70 70.00 Date 31-Aug-2016 30-Sep-2018 31-May-2019 30-Jun-2019 IN00703604 ►3. Beneficiaries able to meet their monthly household food consumption needs after 6 months at the reintegration location (disaggregated by gender, individual or economic assoc., agrarian/non-agrarian (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 16.30 82.00 82.00 70.00 7/9/2019 Page 2 of 5 The World Bank Implementation Status & Results Report DRC Reinsertion and Reintegration Project (P152903) Date 31-May-2016 30-Sep-2018 31-May-2019 30-Jun-2019 IN00703605 ►4. Demobilized beneficiaries feel socially accepted by their communities after 6 months at the reintegration location (disaggregated by gender, individual or economic association, agrarian/non-agraria (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 82.00 82.00 82.00 45.00 Date 31-Aug-2016 30-Sep-2018 31-May-2019 30-May-2019 Intermediate Results Indicators by Components Component 1: Reinsertion IN00703686 ►1a. Demobilized adults completed reinsertion phase (disaggregated by gender) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4,700.00 4,700.00 4,560.00 Date 31-Oct-2015 30-Sep-2018 31-May-2019 30-May-2019 Component 2: Reintegration IN00703687 ►Indicator 1b: Economic associations established by individual beneficiaries (disaggregated by gender, agrarian/non-agrarian) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 87.00 87.00 300.00 Date 31-Aug-2016 30-Sep-2018 31-May-2019 30-Jun-2019 IN00703690 ►1c. Beneficiaries satisfied with reintegration support (disaggregated by gender, individual or economic association, agrarian/non-agrarian) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 6.90 6.90 6.90 65.00 Date 31-Oct-2015 30-Sep-2018 31-May-2019 30-Jun-2019 IN00703693 ►1d. Beneficiaries consuming at least 2 meals a day after 6 months at the reintegration location (disaggregated by gender, individual or economic association, agrarian/non-agrarian) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 27.50 27.50 27.50 70.00 Date 31-Aug-2016 30-Sep-2018 31-May-2019 30-Jun-2019 Component 3: Support to Demobilized Ex-combatants’ Households IN00703688 7/9/2019 Page 3 of 5 The World Bank Implementation Status & Results Report DRC Reinsertion and Reintegration Project (P152903) ►2a. Ex-combatant spouse or nominated household member report perceiving demobilized as socially reintegrated in the community (disaggregated by gender, agrarian/non-agrarian) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 90.60 90.60 90.60 70.00 Date 31-Aug-2016 30-Sep-2018 31-May-2019 30-Jun-2019 IN00703691 ►2b. Ex-combatant spouse or nominated household member participating in community activities (disaggregated by gender, agrarian/non-agrarian) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 73.20 73.20 73.20 60.00 Date 31-Aug-2016 30-Sep-2018 31-May-2019 30-Jun-2019 Component 4: Support to Vulnerable Groups IN00703689 ►3a. Psycho-social support provided to those identified as traumatized through screening (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 31-Oct-2015 30-Sep-2018 31-May-2019 30-Jun-2019 IN00703692 ►3b. Individual beneficiaries who received psycho-social support reporting improved mental health (disaggregated by gender, individual or economic association, agrarian/non-agrarian) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 65.00 Date 31-Oct-2015 30-Sep-2018 31-May-2019 30-Jun-2019 IN00703694 ►3c. Women ex-combatants report they were treated the same or better than male ex-combatants by the project. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 73.90 73.90 73.90 65.00 Date 31-Aug-2016 30-Sep-2018 31-May-2019 30-Jun-2019 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P152903 IDA-D0600 Effective USD 15.00 15.00 0.00 14.48 0.70 95% 7/9/2019 Page 4 of 5 The World Bank Implementation Status & Results Report DRC Reinsertion and Reintegration Project (P152903) P152903 TF-A0087 Closed USD 6.50 6.44 0.06 6.44 0.00 100% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P152903 IDA-D0600 Effective 15-May-2015 09-Jul-2015 27-Jan-2016 31-Dec-2019 31-Dec-2019 P152903 TF-A0087 Closed 15-May-2015 09-Jul-2015 27-Jan-2016 30-Jun-2016 30-Jun-2017 Cumulative Disbursements Restructuring History Level 2 Approved on 25-Jun-2016 ,Level 2 Approved on 02-Sep-2016 ,Level 2 Approved on 12-Dec-2016 Related Project(s) There are no related projects. 7/9/2019 Page 5 of 5