The World Bank Report No: ISR16359 Implementation Status & Results Colombia Bogota Urban Services Project (P074726) Public Disclosure Copy Operation Name: Bogota Urban Services Project (P074726) Project Stage: Implementation Seq.No: 24 Status: ARCHIVED Archive Date: 15-Oct-2014 Country: Colombia Approval FY: 2003 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 13-Mar-2003 Original Closing Date 31-Oct-2007 Planned Mid Term Review Date 12-Sep-2005 Last Archived ISR Date 30-Mar-2014 Effectiveness Date 05-Aug-2003 Revised Closing Date 30-Sep-2014 Actual Mid Term Review Date 27-Sep-2005 Project Development Objectives Project Development Objective (from Project Appraisal Document) The objectives of the Projects are: (i)to improve quality of life of low income families (estratos 1 and 2) by increasing access, coverage, quality, reliability, and inter- agency coordination in the provision of water, sanitation, transport and related basic services; (ii) to improve city's mobility by providing better access to the public transport system, and improving road safety, traffic management and transport planning; and (iii) to strengthen the institutional and administrative framework for an efficient and sustainable delivery of urban services throughout the city. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost A. IMPROVED MOBILITY 180.86 B. URBAN UPGRADING 76.34 C. INSTITUTIONAL STRENGTHENING 14.46 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status Overview Overall, the original Project progressed in a satisfactory manner. This AF finances the scale-up of the original Project's Component A: Improved Mobility, which consists of the conceptualization and detailed engineering studies of the Integrated Mass Transit System for the city, including Bogotá's first underground metro line; and Component C: Institutional Development, which includes technical assistance to the City Page 1 of 6 The World Bank Report No: ISR16359 Government’s Urban Development Institute (IDU) for road administration system and support to Bogotá's Cadastre Unit for enhanced cadastral management and institutional strengthening. The Colombian-Spanish consortium in charge of the detailed engineering studies for the Bogota Metro is advancing well and on time, meeting the 15 month calendar, and completes Public Disclosure Copy the studies according to contract scope. Bogota will amend the design studies contract to allow additional studies to be done since the original location of the train depots has been moved to a further location due to soil problems in the original location and land availability issues, and hence the project now requires an operational 4 kilometer link to reach to the depot. This amendment will extend the duration of the contract and increase the scope and will be covered with local resources. The consortium has already started working on this extension. The city administration is programming an open forum to present the results of the study in October, 2014. The Metro project will continue his preparation where the Bank will provide through different instruments (Grants, advisory services) support to the two main stakeholders (Nation and City of Bogota) in different aspects like financing structuring, institutional set up, project management). The results of the study are being published and the city is planning on advancing towards project structuring and bidding stages using the designs as main input for these stages. The rest of project's components has been accomplished and some of them with high innovation and state of the art information. The achievements under the Institutional Development Component are complete and in quality highly satisfactory for the Team, and can be summarized as follows: (i) organizational redesign and institutional strengthening of the Cadastre Unit, including the processes of cadastral update and conservation, and the design and implementation of a geographic information system to generate spatial data of Bogotá; and (ii) definition of the road users costs to be managed by the Instituto de Desarrollo Urbano (IDU) for Bogotá, and implementation of the evaluation tools of Road Networks (RONET), which continues its implementation and is rated satisfactory. The implementation and PDO rating is Moderately Satisfactory. The achievements under the Institutional Development Component are complete and in quality highly satisfactory for the Team, and can be summarized as follows: (i) organizational redesign and institutional strengthening of the Cadastre Unit, including the processes of cadastral update and conservation, and the design and implementation of a geographic information system to generate spatial data of Bogotá; and (ii) definition of the road users costs to be managed by the Instituto de Desarrollo Urbano (IDU) for Bogotá, and implementation of the evaluation tools of Road Networks (RONET), which continues its implementation and is rated satisfactory. The loan is closing on September 30, 2014. Locations Country First Administrative Division Location Planned Actual Colombia Not Entered Usme Public Disclosure Copy Colombia Not Entered Usaquen Colombia Not Entered Suba Colombia Not Entered Bosa Colombia Not Entered Distrito Capital de Bogota Colombia Bogota D.C. Bogota ✔ Colombia Not Entered Bolivar Page 2 of 6 The World Bank Report No: ISR16359 Country First Administrative Division Location Planned Actual Colombia Not Entered Chapinero Public Disclosure Copy Colombia Not Entered San Cristobal Colombia Not Entered Kennedy Colombia Not Entered Rafael Uribe Colombia Not Entered Santa Fe del Tintal Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Improvement of overall city mobility as shown Text Value See intermediate outcome by the intermediate outcomes indicators. indicators Date 31-Jul-2011 Comments Several intermediate indicators assess overall improvement in city mobility, including: (1)increased number of Km covered by the busway system; (2) number of passengers transported; (3) increased number of Km interconnecting bike paths; (4) Increased number of km in feeder roads, (5) number of passengers users of feeder roads, (6) number of traffic related accidents, (7) increase in use of bike paths, and (8) Public Disclosure Copy number of road safety programs presented. Improve quality of life in UPZ, as shown by the Text Value 80% acceptance of results in intermediate outcomes indicators survey Date 31-Jul-2008 Comments Several intermediate indicators assess overall improvement in the quality of life in UPZs, including:(1) Page 3 of 6 The World Bank Report No: ISR16359 number of new water supplyconnections, (2) number of new sewerage connections, (3) number of Public Disclosure Copy barrios legalized,(4) number of titling processes finished, (5) number of environmental plans prepared, (6) number of families resettled, (7) number of families trained in improvement works, and (8) number works constructed by community. Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target For indicator 1: 1) Increased Number of Km Text Value 1) 0; 2) 750,000; 3)0 1) 10.2 Km; 2) 1.660.000; and covered by the busway system, 2) Number of 3) 15Km passengers transported; 3) Increased Date 05-Aug-2003 14-Jun-2010 31-Oct-2008 Numberof Km interconnecting bike paths; Comments The number of passengers moved by Transmilenio has increased significantly For indicator 1: 1) Increased # of km in feeder Text Value 1)0; 2) Not available; (3) N/A; 1) This indicator should be roads, 2) Number of passengers users of (4) 3% revised to 111.1 km instead of feeder roads, 3) Number of traffic 338 km; 2) 340,000; (3) 5% relatedaccidents, 4) increase in use of bike Date 08-May-2003 17-Dec-2009 31-Oct-2008 paths, Comments For indicator 1: Number of road safety Text Value N/A 5 programs programs presented, Date 05-Aug-2003 17-Dec-2009 31-Oct-2008 Comments For indicator 2: 1) Number of new water supply Text Value N/A 1) 15.671; 2) 83.234; 3) 55; Public Disclosure Copy connections, 2) Number of new sewerage and 4) 534 connections, 3) Number of barrios legalized,4) Date 08-May-2003 17-Dec-2009 31-Oct-2008 Number of titling processes finished, Comments For 2: 1) Number of environmental plans Text Value Not applicable 1)2, 2)1,995, 3)1,066, 4)55 prepared, 2) Number of families resettled, 3) Date 08-May-2003 17-Dec-2009 31-Jul-2008 Number of families trained in improvement Comments works, 4) Number works constructed by community. Page 4 of 6 The World Bank Report No: ISR16359 Six proposed studies for integrated mass Yes/No Value No Yes Yes transport system to be delivered Date 21-Oct-2008 27-Jul-2011 31-Mar-2012 Comments The six studies are: 1. 1. Conceptual Design of Public Disclosure Copy Conceptual Design of Bogota's Metro (Completed); Bogota's Metro; 2. Detailed 2. Detailed Engineering Engineering Design for Design for Bogota's First Bogota's First Metro Line; 3. Metro Line (underway); 3. LegalStructuring forBogota's Legal Structuring forBogota's First Metro Line; 4. Financial First Metro Line (underway); Structuring for Bogota's First 4. Financial Structuring for Metro Line; 5. Social Bogota's First Metro Line Assessment for Bogota'sFirst (underway). Metro Line; 6. Environmental Assessment for Bogota's First Metro Line Planned TA components for IDU to be Yes/No Value No Yes Yes delivered Date 21-Oct-2008 14-Jun-2010 31-Mar-2012 Comments Users costs Assessment HDM-4 and RONET Training Planned TA to Cadastre Unit to be delivered Yes/No Value No Yes Yes Date 21-Oct-2008 14-Jun-2010 31-Mar-2012 Comments Indicators: 1. Properties with 1. Properties with Cadastral Indicators: 1. Properties with Cadastral information updated information updated Cadastral information updated (50,000); 2. Lag in the (2,180,605); 2. Lag in the (700,000); 2. Lag in the Property Tax Base (5 yrs); 3. Property Tax Base (1yrs); 3. Property Tax Base (3yrs); 3. Reform to the Cadastre's Reform to the Cadastre's Reform to the Cadastre's institutional architecture (No); institutional architecture institutional architecture Upgrading of 3 cadastral (Underway); 4. Upgrading of (Yes);4. Upgrading of 3 processes (updating, 3 cadastral processes cadastral processes upgrading and cartography); (updating, upgrading and (updating, upgrading and 5. Updated properties with cartography) Yes; 5. Updated cartography); 5. Updated cadastral information properties with cadastral properties with cadastral Public Disclosure Copy incorporated to new database information incorporated to information incorporated to (0); 6. Integrated real-estate new database (N/A); 6. new database (2,000,000); 6. information repository (0); 7. Integrated real-estate Integrated real-estate Design and Implementation of information repository (0); 7. information repository (1); 7. spatial data (0) Design and Implementation of Design and Implementation of spatial data (1) spatial data (1) Data on Financial Performance (as of 29-Apr-2014) Financial Agreement(s) Key Dates Page 5 of 6 The World Bank Report No: ISR16359 Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P074726 IBRD-71620 Closed 13-Mar-2003 04-Jun-2003 05-Aug-2003 31-Oct-2007 31-Jul-2010 P074726 IBRD-76090 Closed 21-Oct-2008 23-Feb-2009 26-Jun-2009 31-Jul-2011 30-Sep-2014 Public Disclosure Copy Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P074726 IBRD-71620 Closed USD 100.00 100.00 0.00 100.00 0.00 100.00 P074726 IBRD-76090 Closed USD 30.00 30.00 0.00 15.27 14.73 51.00 Disbursement Graph Key Decisions Regarding Implementation Public Disclosure Copy There are no key decisions for disclosure. Restructuring History Board Approved on 21-Oct-2008, Level two Approved on 12-Sep-2011, Level two Approved on 18-May-2012, Level two Approved on 27-Jun-2013 Related Projects P112852-CO (AF) Bogota Urban Services Page 6 of 6