The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Reintegration of Ex-combatants Project (P160272) AFRICA | Central African Republic | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 3 | ARCHIVED on 10-Oct-2018 | ISR34296 | Implementing Agencies: Ministère de l'Economie, du Plan et de la Coopération, DDRR Project Implementation Unit Key Dates Key Project Dates Bank Approval Date: 13-Apr-2017 Effectiveness Date: 21-Dec-2017 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2020 Revised Closing Date: 31-Dec-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to support the social and economic reintegration of demobilized ex-combatants and improve access to socio-economic infrastructure and economic opportunities for host communities. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Social and Economic Reintegration Support:(Cost $16940000.00 M) Support to Host Communities:(Cost $9000000.00 M) Project Management:(Cost $4060000.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Unsatisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Unsatisfactory Overall Risk Rating High High Implementation Status and Key Decisions Pending the launch of the National Disarmament, Demobilization, Reintegration, and Repatriation Program (DDRR), the government, DDRR- PIU/Fiduciary Unit, with the support of the World Bank technical team, continued working to enhance the project technical readiness by: (i) validating the Work Plan and Annual Budget, (ii) finalizing the recruitment of the PIU key staff, in compliance with the World Bank procedures, and (iii) engaging in negotiation with implementing partners who will provide support to implement activities of socio-economic reintegration of ex- combatants, and construction and/or rehabilitation of small-scale social and economic infrastructure in host communities. In addition, the technical teams are discussing the way forward regarding the communication strategy which is gradually being operationalized in Bangui and in the project locations to facilitate favorable conditions for smooth activities’ implementation. 10/10/2018 Page 1 of 6 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Owing to delays in achieving necessary pre-conditions to launch the DDRR and associated uncertainties surrounding when disarmament can be initiated, the project will focus on implementing programmed community violence reduction activities while DDRR preparations continue. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic High High High Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability High High High Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Substantial Substantial Substantial Other High High High Overall High High High Results PDO Indicators by Objectives / Outcomes Support the social and economic reintegration of demobilized ex-combatants IN00561856 ►1. Number of ex-combatant beneficiaries (disaggregated by gender and armed group) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5,000.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561755 ►2. Percent of ex-combatant beneficiaries who are economically active (disaggregated by gender and type of economic activity) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 75.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561753 10/10/2018 Page 2 of 6 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) ►3. Percent of ex-combatant beneficiaries who report social acceptance by their communities (disaggregated by gender, age group, and armed group) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 65.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561857 ►4. Percent of host community members who report social acceptance of ex-combatants (disaggregated by age and gender) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 70.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561754 ►5. Beneficiaries who experience a feeling of greater security attributable to the project areas (disaggregated by gender) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 Improve access to socio-economic infrastructure and economic opportunities for host communities IN00561863 ►6. Number of community members with improved access to socio-economic infrastructure (of which female, children). (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 30,000.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2017 Intermediate Results Indicators by Components Support to Host Communities IN00561865 ►7. Number of completed small-scale socio-economic infrastructure sub-projects (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561866 ►8. Number of host community members participating in community-based decision making/participatory planning exercises (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,500.00 10/10/2018 Page 3 of 6 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561867 ►9. Number of host community members participating in capacity building activities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 6,000.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 Social and Economic Reintegration Support IN00561858 ►1. Percentage of ex-combatants who completed orientation, counseling and skills training (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 90.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561859 ►2. Percentage of vulnerable ex-combatants (identified as per criteria) who have received specialized support. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561860 ►3. Percentage of ex-combatants who receive follow-up reintegration support (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561862 ►4. Percentage of ex-combatants who are satisfied with follow-up reintegration support (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 95.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561861 ►5. Percentage of ex-combatants who are satisfied with the start-up reintegration support (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 90.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 IN00561864 ►6. Number ex-combatants who receive reintegration start-up support in time and in accordance with the PIM. (Number, Custom) 10/10/2018 Page 4 of 6 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5,000.00 Date 13-Apr-2017 -- 03-Oct-2018 13-Apr-2020 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P160272 IDA-D1800 Effective USD 30.00 30.00 0.00 1.09 30.48 3.5% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P160272 IDA-D1800 Effective 13-Apr-2017 22-Jun-2017 21-Dec-2017 31-Dec-2020 31-Dec-2020 Cumulative Disbursements 10/10/2018 Page 5 of 6 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 10/10/2018 Page 6 of 6