I. General 1. Project Name: P162646 - Strengthening Social Protection Project 2. Bank’s approval Date of the procurement Plan: June 12, 2018 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: II. Goods and Works and non-consulting services. Prior Review Threshold: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “Moderate”): (a) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 4 million; (b) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 15 million; The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ million Prefere (Prior / Post) nce (yes/no) 1 Procuremen 741,081 1 No Prior t of livestock for distribution under the Asset Transfer scheme 2 Procurement 4,722,998 6 No Post of goods III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.4 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) 1 Studies and MIS 142,857 1 Prior TA for NFNCS 2 Technical 186,861 1 Post supervision of public works contracts in 30 Districts 3 Selection of a 1,500,000 1 Post consultant(s) to conduct ESIAs and RAPs for PW and EPW projects 4 Recruitment of 1,249,714 5 Post staff PROCUREMENT Rwanda : Strengthening Social Protection Project PLAN General Information Country: Rwanda Bank’s Approval Date of the Original Procurement Plan: 2018-06-13 2019-10-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162646 GPN Date: Project Name: Strengthening Social Protection Project Loan / Credit No: IDA / 61690 Executing Agency(ies): Local Administrative Entities Development Agency WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-LODA-65496-GO-RFQ / Component 3: Delivery Pending Request for Single Stage - One Supply of IT equipment for IDA / 61690 Systems, Policy and Post Open - National 0.00 Implementati 2018-08-01 2018-09-26 2018-10-26 Quotations Envelope 3 NSDS SPIU staffs Program Management on RW-LODA-65499-GO-RFB / Component 3: Delivery Pending Single Stage - One Supply of IT equipment for IDA / 61690 Systems, Policy and Post Request for Bids Open - National 0.00 Implementati 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-03-04 Envelope SPIU staffs and LG staffs Program Management on Component 1: Improving RW-LODA-RUBAVU-86399- coverage, adequacy and Pending GO-RFB / Tender for Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-01-25 2019-01-30 2019-03-13 2019-04-12 2019-05-17 2019-11-13 purchase of tools and Envelope 2020 Umurenge Program on equipment (VUP) cash transfers Component 1: Improving RW-LODA-KIREHE-87403- coverage, adequacy and Pending GO-RFB / Supply of Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-12-17 2018-12-22 2019-02-02 2019-03-04 2019-04-08 2019-10-05 construction materials for Envelope 2020 Umurenge Program on public works projects (VUP) cash transfers Component 1: Improving RW-LODA-KIREHE-87404- coverage, adequacy and Pending GO-RFB / Supply of Single Stage - One IDA / 61690 effectiveness of the Vision Prior Request for Bids Open - National 0.00 Implementati 2018-12-12 2018-12-17 2019-01-28 2019-02-27 2019-04-03 2019-09-30 equipment and tools for Envelope 2020 Umurenge Program on public works projects (VUP) cash transfers Component 1: Improving RW-LODA-NYARUGURU- coverage, adequacy and Pending 87405-GO-RFB / Supply of Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-11-16 2018-11-21 2019-01-02 2019-02-01 2019-03-08 2019-09-04 Construction materials for Envelope 2020 Umurenge Program on Road maintenance (VUP) cash transfers RW-LODA-NYARUGURU- Component 1: Improving 87406-GO-RFB / Supply of coverage, adequacy and Pending Single Stage - One materials to be used by IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-01-08 2019-01-13 2019-02-24 2019-03-26 2019-04-30 2019-10-27 Envelope Public Works beneficiaries 2020 Umurenge Program on in VUP (VUP) cash transfers Page 1 Component 1: Improving RW-LODA-NYANZA-87407- coverage, adequacy and Pending GO-RFB / Supply materials Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-11-16 2018-11-21 2019-01-02 2019-02-01 2019-03-08 2019-09-04 for the construction of Public Envelope 2020 Umurenge Program on Work in Nyanza District (VUP) cash transfers RW-LODA-NYARUGENGE- Component 1: Improving 87408-GO-RFB / Supply of coverage, adequacy and Pending construction materials for Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-11-16 2018-11-21 2019-01-02 2019-02-01 2019-03-08 2019-09-04 the Rehabilitation of the Envelope 2020 Umurenge Program on murrum road Ruliba- (VUP) cash transfers Mwendo, 4.5km RW-LODA-NYARUGENGE- Component 1: Improving 87409-GO-RFB / Supply of coverage, adequacy and Pending construction materials for Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-11-16 2018-11-21 2019-01-02 2019-02-01 2019-03-08 2019-09-04 the Rehabilitation of Nzove- Envelope 2020 Umurenge Program on Nyamweru murrum road in (VUP) cash transfers Kanyinya Sector, 5km RW-LODA-RUBAVU-87413- Component 1: Improving GO-RFB / Tender for supply coverage, adequacy and Pending Single Stage - One of construction materials for IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-01-25 2019-01-30 2019-03-13 2019-04-12 2019-05-17 2019-11-13 Envelope road under public works 2020 Umurenge Program on projects (VUP) cash transfers Component 1: Improving RW-LODA-RUBAVU-87414- coverage, adequacy and Pending GO-RFB / Tender for Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-01-25 2019-01-30 2019-03-13 2019-04-12 2019-05-17 2019-11-13 purchase of tools and Envelope 2020 Umurenge Program on equipment (VUP) cash transfers Component 1: Improving RW-LODA-RUSIZI-87416-GO- coverage, adequacy and Pending RFB / Supply of construction Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-11-23 2018-11-28 2019-01-09 2019-02-08 2019-03-15 2019-09-11 materials for public works Envelope 2020 Umurenge Program on projects (VUP) cash transfers Component 1: Improving RW-LODA-RUSIZI-87417-GO- coverage, adequacy and Pending RFB / Supply of equipment Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-12-10 2018-12-15 2019-01-26 2019-02-25 2019-04-01 2019-09-28 and tools for public works Envelope 2020 Umurenge Program on projects (VUP) cash transfers RW-LODA-NGOMA-87415- Component 1: Improving GO-RFB / Supply of coverage, adequacy and Under Single Stage - One construction materials for IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2019-10-08 Envelope public works projects in 2020 Umurenge Program on Ngoma District (VUP) cash transfers RW-LODA-NGOMA-87419- Component 1: Improving GO-RFB / Supply of coverage, adequacy and Pending Single Stage - One equipment and tools for IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2019-10-08 Envelope public works projects for 2020 Umurenge Program on Ngoma District (VUP) cash transfers RW-LODA-87420-GO-RFB / Component 1: Improving Supply of Construction coverage, adequacy and Pending Single Stage - One materials for Road IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-12-24 2018-12-29 2019-02-09 2019-03-11 2019-04-15 2019-10-12 Envelope maintenance for Rwamagana 2020 Umurenge Program on District (VUP) cash transfers RW-LODA-RWAMAGANA- Component 1: Improving 87421-GO-RFB / Tender for coverage, adequacy and Pending maintenance of Roads in Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-11-16 2018-11-21 2019-01-02 2019-02-01 2019-03-08 2019-09-04 Public Works beneficiaries Envelope 2020 Umurenge Program on in VUP for Rwamagana (VUP) cash transfers District Page 2 Component 1: Improving RW-GASABO-LODA-88425- coverage, adequacy and Pending GO-RFB / Supply of Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-02-22 2019-02-27 2019-04-10 2019-05-10 2019-06-14 2019-12-11 construction materials under Envelope 2020 Umurenge Program on Public Works projects (VUP) cash transfers RW-GASABO-LODA-88426- Component 1: Improving GO-RFB / Supply of coverage, adequacy and Pending Single Stage - One equipment and tools for E- IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2018-12-28 2019-01-02 2019-02-13 2019-03-15 2019-04-19 2019-10-16 Envelope Public under Works bank 2020 Umurenge Program on Projects (VUP) cash transfers Component 1: Improving RW-LODA-NYAGATARE- coverage, adequacy and Pending 98721-GO-RFB / Supply of Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 construction materials for Envelope 2020 Umurenge Program on public works projects (VUP) cash transfers Component 1: Improving RW-LODA-NYAGATARE- coverage, adequacy and Pending 98722-GO-RFB / Supply of Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 equipment and tools for Envelope 2020 Umurenge Program on public works projects (VUP) cash transfers RW-LODA-NGORORERO- Component 1: Improving 98729-GO-RFB / Supply of coverage, adequacy and Pending materials to be used in cPW Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 in the sectors of Envelope 2020 Umurenge Program on INDIRO,MATYAZO and (VUP) cash transfers KAVUMU Component 1: Improving RW-LODA-RUSIZI-98740-GO- coverage, adequacy and Pending RFB / Supply of construction Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 materials for public works Envelope 2020 Umurenge Program on projects (VUP) cash transfers Component 1: Improving RW-LODA-RUSIZI-98742-GO- coverage, adequacy and Pending RFB / Supply of equipment Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 and tools for public works Envelope 2020 Umurenge Program on projects (VUP) cash transfers RW-LODA-GAKENKE-98896- Component 1: Improving GO-RFB / Purchase and coverage, adequacy and Pending Single Stage - One supply of materials for roads IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 Envelope construction and radical 2020 Umurenge Program on teracing in VUP Sectors (VUP) cash transfers RW-LODA-BUGESERA- Component 1: Improving 98909-GO-RFB / Supply of coverage, adequacy and Pending Single Stage - One Local Material for Roads to IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 Envelope be Constructed Under VUP 2020 Umurenge Program on cPW Program (VUP) cash transfers RW-LODA-HUYE-103040-GO- RFB / Supply of construction Component 1: Improving materials and tools coverage, adequacy and Pending Single Stage - One equipment for road IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 Envelope maintenance(18,009km) in 2020 Umurenge Program on sholi cell in Gishamvu and (VUP) cash transfers karama sector(6km) RW-LODA-HUYE-103044-GO- Component 1: Improving RFB / Supply of construction coverage, adequacy and Pending materials and tools Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 equipment for road Envelope 2020 Umurenge Program on maintenance IN Nkenke (VUP) cash transfers sector and karama sector Page 3 RW-LODA-HUYE-103045-GO- RFB / Supply of construction Component 1: Improving materials and tools coverage, adequacy and Pending Single Stage - One equipment for Radical IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 Envelope terraces constructed in 2020 Umurenge Program on Bunazi cell(10ha) in Karama (VUP) cash transfers sector RW-LODA-KAYONZA- 103046-GO-RFB / Supply of Component 1: Improving construction material to coverage, adequacy and Pending Single Stage - One rehabilitate CYINZOVU- IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 Envelope MUNAGA KABURA and 2020 Umurenge Program on KABURA RWAMUGARA (VUP) cash transfers Feeder roads RW-LODA-KAYONZA- Component 1: Improving 103047-GO-RFB / Supply of coverage, adequacy and Pending construction materials for Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 maintenance of kabare sector Envelope 2020 Umurenge Program on roads through VUP (VUP) cash transfers expanded public works RW-LODA-KAYONZA- Component 1: Improving 103048-GO-RFB / Supply of coverage, adequacy and Pending construction materials to Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 rehabilitate KARAMBI- Envelope 2020 Umurenge Program on NGOMERI-BUGARURA- (VUP) cash transfers RWINSHEKE Feeder roads RW-LODA-RULINDO-103052- Component 1: Improving GO-RFB / supply of coverage, adequacy and Pending Single Stage - One construction materials for IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 Envelope maintenance of roads in 2020 Umurenge Program on Rulindo District (VUP) cash transfers RW-LODA-MUSANZE- 103183-GO-RFB / Supply of Component 1: Improving construction materials coverage, adequacy and Pending cements, stones and, trees, Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 fer a beton, Clay soil and Envelope 2020 Umurenge Program on laterite for PW roads in (VUP) cash transfers Gataraga Sector and Remera Sector RW-LODA-GICUMBI-103185- GO-RFB / Supply of Component 1: Improving construction materials and coverage, adequacy and Pending Single Stage - One tools, equipment for road IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 Envelope maintenance in Gicumbi 2020 Umurenge Program on District in VUP Classical (VUP) cash transfers Public Works RW-LODA-GICUMBI-103186- Component 1: Improving GO-RFB / Supply of coverage, adequacy and Pending materials for road Single Stage - One IDA / 61690 effectiveness of the Vision Post Request for Bids Open - National 0.00 Implementati 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 maintenance in Gicumbi Envelope 2020 Umurenge Program on District in VUP Expanded (VUP) cash transfers Public Works NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 4 Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-LODA-65483-CS-QCBS / Component 3: Delivery Hiring a firm for Technical Quality And Cost- Pending IDA / 61690 Systems, Policy and Post Open - National 0.00 2018-12-07 2018-12-28 2019-02-10 2019-03-10 2019-04-09 2019-05-14 2019-06-18 2020-06-17 supervision of public works Based Selection Implementation Program Management contracts in 30 Districts RW-LODA-65503-CS-NPO / Component 3: Delivery Recruitment of a national Non-Profit IDA / 61690 Systems, Policy and Prior Open - National 0.00 Canceled 2018-12-28 2019-01-18 2019-03-03 2019-04-02 2019-05-07 2020-05-06 level NGO to develop HBCC Organizations Program Management modules and deliver training RW-LODA-65488-CS-INDV / Component 3: Delivery Selection of a consultant(s) Quality And Cost- Pending IDA / 61690 Systems, Policy and Post Open - National 0.00 2018-12-07 2018-12-28 2019-02-10 2019-03-10 2019-04-09 2019-05-14 2019-06-18 2020-06-17 to conduct ESIA and RAPs Based Selection Implementation Program Management for PW and EPW projects RW-LODA-65507-CS-INDV / hiring a firm to Conduct Component 3: Delivery Quality And Cost- Pending baseline study on Nutrition IDA / 61690 Systems, Policy and Post Open - National 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-04 2019-06-03 2019-07-08 2019-08-12 2020-08-11 Based Selection Implementation Sensitive Direct Support Program Management (NSDS) RW-LODA-117455-CS-QCBS Component 3: Delivery / Recruitment of a national Quality And Cost- Pending IDA / 61690 Systems, Policy and Post Open - National 0.00 2019-05-31 2019-06-21 2019-08-04 2019-09-01 2019-10-01 2019-11-05 2019-12-10 2021-12-09 level NGO to develop HBCC Based Selection Implementation Program Management modules and deliver training RW-LODA-129533-CS-QCBS Component 3: Delivery Quality And Cost- Pending / Operation review of home IDA / 61690 Systems, Policy and Post Open - National 0.00 2019-10-31 2019-11-21 2020-01-04 2020-02-01 2020-03-02 2020-04-06 2020-05-11 2021-05-11 Based Selection Implementation community based child care Program Management INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-LODA-64860-CS-INDV / Component 3: Delivery Individual Recruitment Social Protection IDA / 61690 Systems, Policy and Post Consultant Open 1,604.22 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-11 2019-09-11 Coordinator Program Management Selection RW-LODA-64863-CS-INDV / Component 3: Delivery Individual Recruitment of IDA / 61690 Systems, Policy and Post Consultant Open 1,148.85 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Environmental Safeguards Program Management Selection Specialist RW-LODA-64866-CS-INDV / Component 3: Delivery Individual Recruitment of Social IDA / 61690 Systems, Policy and Post Consultant Open 915.04 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Safeguards Specialist Program Management Selection RW-LODA-64867-CS-INDV / Component 3: Delivery Individual Recruitment of Procurement IDA / 61690 Systems, Policy and Post Consultant Open 798.31 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Specialist Program Management Selection RW-LODA-64869-CS-INDV / Component 3: Delivery Individual Recruitment of Financial IDA / 61690 Systems, Policy and Post Consultant Open 798.24 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Compliance Monitoring Program Management Selection Specialist RW-LODA-64873-CS-INDV / Component 3: Delivery Individual Under Recruitment of Internal IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Implementation Auditor Program Management Selection Page 5 RW-LODA-64874-CS-INDV / Component 3: Delivery Individual Recruitment of Financial IDA / 61690 Systems, Policy and Post Consultant Open 798.31 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Management Program Management Selection Specialist/Accountant RW-LODA-64876-CS-INDV / Component 3: Delivery Individual Under Recruitment of Data IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Implementation Analysts Specialist Program Management Selection RW-LODA-64925-CS-INDV / Component 3: Delivery Individual Recruitment of Social Under IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Protection Specialist/Safety Implementation Program Management Selection Nets RW-LODA-64928-CS-INDV / Component 3: Delivery Individual Recruitment of Social IDA / 61690 Systems, Policy and Post Consultant Open 798.24 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Protection Program Management Selection Specialists/Livelihoods RW-LODA-64929-CS-INDV / Component 3: Delivery Individual Recruitment of Monitoring, IDA / 61690 Systems, Policy and Post Consultant Open 798.31 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Evaluation & Learning Program Management Selection Specialist RW-LODA-64933-CS-INDV / Recruitment of Social Component 3: Delivery Individual Protection MEIS IDA / 61690 Systems, Policy and Post Consultant Open 915.04 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Specialists/Database and Program Management Selection Application Administrator RW-LODA-64936-CS-INDV / Recruitment of Social Component 3: Delivery Individual Under Protection MEIS IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Implementation Specialists/Software Program Management Selection development RW-LODA-65221-CS-INDV / Component 3: Delivery Individual Recruitment of Nutrition Under IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Sensitive Direct Support Implementation Program Management Selection Project Manager RW-LODA-65222-CS-INDV / Component 3: Delivery Individual Recruitment of Public Under IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Finance Management Implementation Program Management Selection Specialist (NSDS) RW-LODA-65225-CS-INDV / Component 3: Delivery Individual Recruitment of Nutrition M, IDA / 61690 Systems, Policy and Post Consultant Open 798.24 Signed 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 E and Learning Specialist Program Management Selection RW-LODA-65505-CS-INDV / Develop MEIS/Nutrition Component 3: Delivery Individual Pending Sensitive Direct Support IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2019-01-24 2019-03-14 2019-04-04 2019-05-09 2020-05-08 Implementation Module and provide Program Management Selection maintenance services RW-LODA-65506-CS-INDV / Component 3: Delivery Individual Recruitment of 30 District Under IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-08-30 2018-10-18 2018-11-08 2018-12-13 2019-12-13 Data Management Staffs as Implementation Program Management Selection part of SPIU. RW-LODA-65572-CS-INDV / Component 3: Delivery Individual Pending Recruitment of a technical IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2019-03-22 2019-05-10 2019-05-31 2019-07-05 2020-07-04 Implementation Assistance to support PFM Program Management Selection RW-LODA-65623-CS-INDV / Component 3: Delivery Individual hiring an individual Pending IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-10-26 2018-12-14 2019-01-04 2019-02-08 2019-08-07 consultant for MEIS upgrade Implementation Program Management Selection & HMIS link Page 6 RW-LODA-65823-CS-INDV / Component 3: Delivery Individual Social Protection (SP) IDA / 61690 Systems, Policy and Post Consultant Open 0.00 Canceled 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-03-25 Financial Management Program Management Selection Specialist RW-LODA-64938-CS-INDV / Component 3: Delivery Individual Pending Recruitment of Data IDA / 61690 Systems, Policy and Prior Consultant Open 0.00 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-09-26 Implementation Management Specialist Program Management Selection RW-LODA-65491-CS-INDV / Component 3: Delivery Individual Hiring of TA for Studies Pending IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2018-06-07 2018-07-26 2018-08-16 2018-09-20 2019-09-20 and MIS Technical Assistant Implementation Program Management Selection to support NECDP/ NFNCS Component 1: Improving RW-LODA-RUBAVU-86393- coverage, adequacy and Individual CS-INDV / Tender for hiring Pending IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2018-11-26 2019-01-14 2019-02-04 2019-03-11 2019-09-07 individual consultants for Implementation 2020 Umurenge Program Selection public works supervision (VUP) cash transfers Component 1: Improving RW-LODA-RUBAVU-87410- coverage, adequacy and Individual Pending CS-INDV / Tender for hiring IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2018-11-26 2019-01-14 2019-02-04 2019-03-11 2019-09-07 Implementation individual consultants 2020 Umurenge Program Selection (VUP) cash transfers RW-GASABO-LODA-88440- Component 1: Improving CS-INDV / Recruitment of coverage, adequacy and Individual Pending 11 short term contractual IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2019-09-14 Implementation staffs to supervise PW 2020 Umurenge Program Selection projects (VUP) cash transfers RW-LODA-NYAGATARE- Component 1: Improving 98720-CS-INDV / coverage, adequacy and Individual Pending Recruitment of 11 short IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 Implementation term contractual staff to 2020 Umurenge Program Selection supervise PW Projects (VUP) cash transfers RW-LODA-NGORORERO- 98727-CS-INDV / Component 1: Improving Consultancy service for the coverage, adequacy and Individual Pending supervision of works under IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 Implementation cPW in the sectors of 2020 Umurenge Program Selection HINDIRO,MATYAZO and (VUP) cash transfers KAVUMU Component 1: Improving RW-LODA-RUSIZI-98736-CS- coverage, adequacy and Individual INDV / Recruitment of 4 Pending IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 short term contractual staff Implementation 2020 Umurenge Program Selection to supervise PW projects (VUP) cash transfers Component 1: Improving RW-LODA-KAMONYI-98906- coverage, adequacy and Individual CS-INDV / Recruitment of Pending IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 short term contractual staffs Implementation 2020 Umurenge Program Selection to supervise PW projects (VUP) cash transfers Component 1: Improving RW-LODA-KAMONYI-98908- coverage, adequacy and Individual CS-INDV / Recruitment of Pending IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 short term technical Implementation 2020 Umurenge Program Selection assistant (VUP) cash transfers RW-LODA-103030-CS-INDV Component 3: Delivery Individual / Social Protection (SP) Under IDA / 61690 Systems, Policy and Post Consultant Open 0.00 2019-03-13 2019-05-01 2019-05-22 2019-06-26 2019-12-23 Financial Management Implementation Program Management Selection Specialist Page 7 RW-LODA-MUSANZE- Component 1: Improving 103055-CS-INDV / coverage, adequacy and Individual Recruitment of short term Pending IDA / 61690 effectiveness of the Vision Post Consultant Open 0.00 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 contractual staff to supervise Implementation 2020 Umurenge Program Selection PW contract in Remera (VUP) cash transfers Sector Page 8