Procurement Plan for Project of Integrated Urban and Tourism Development I. General 1. Bank’s approval Date of the procurement Plan [Original: July 15,2016]: Revision 1 of Updated Procurement Plan, May 2017 2. Date of General Procurement Notice: April 26, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year May 2017 to October 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Contract Procurement Method Bank Prior Review Category Value (USD) >= 5,000,000 ICB All >/=US$10 million contracts < 5,000,000 NCB First contract Civil Works <200,000 Shopping First contract NA DC US$60,000 >= 1,000,000 ICB All >/=US$1million contracts Goods <1,000,000 NCB First contract <100,000 Shopping First contract NA DC US$60,000 4. Reference to (if any) Project Operational/Procurement Manual: Project Operational Manual for World Bank Loan Project P155875 PIUDT issued by Albanian Development Fund on 24.04.2017 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 Review Domestic Preference Ref. No. Description Packages by Bank Comments (yes/no) (Prior/Post) Summary of the 2 No ICB (Works) AL- Berat Town of ADF15547- integrated Urban Prior CW-RFB upgrading Saranda tourism C1W-S3 No Prior gateway integrated urban upgrading Summary of the 14 No Post NCB (Works) AL- Saranda staircase ADF15534- rehabilitation No Post CW-RFB Project Urban Regeneration of AL- the existing ADF15536- No Post promenade CW-RFB “Naim Frasheri” in Saranda Ali Pasha AL- historic trail and ADF15538- slopes No Post CW-RFB stabilization – Gjirokastra AL- Street lightening ADF15539- historic center – No Post CW-RFB Gjirokstra AL- Bazaar coble ADF15540- stone roads No Post CW-RFB rehabilitation Gjirokastra AL- museum city ADF15541- No Post integrated urban CW-RFB upgrading Upgrading the AL- renovation of ADF15536- No Post systems of CW-RFB museums Rehabilitation of AL- Cobblestone ADF28554- road “Mihal No Prior CW-RFB Komneno”, Berat castle Upgrading to AL- vehicle access ADF15545- road “Muzak No Post CW-RFB Topia”, Berat Castle Visual upgrading No AL- of selected ADF15542- Post heritage CW-RFB landscape AL- Street lightening ADF15548- No Post – Permet CW-RFB AL- Permet ADF15549- integrated urban No Post CW-RFB upgrading Integrated AL- upgrading of ADF15550- No Post selected touristic CW-RFB area AL- Tourism Product ADF15551- development in 4 No Post CW-RFB municipalities Summary of the 6 No Post NCB (Goods) Solid waste AL-ADF- equipment for 15581-GO- No Prior Himara transfer RFB station Solid W collection AL-ADF- equipment(Gjirok 15582-GO- No Post astra/other as RFB needed Financial AL-ADF- Management 15583-GO- No Post Equipment for 4 RFB municipalities Asset AL-ADF- Management 15609-GO- No Post Equipment for 4 RFB municipalities AL-ADF- GIS equipment 15584-GO- and licenses for No Post RFB 4 municipalities Equipment for tourism AL-ADF- information 15586-GO- No Post management and RFB statistic improvement Summary of the 4 No Post SH (Goods) Equipment for AL-ADF- local destination 15585-GO- No Prior management RFB entities Office AL-ADF- equipment and 15588-GO- licenses for No Post RFB project implementation Purchase of AL-ADF- additional 44382-GO- accessories for No Post RFB smart board of ADF AL-ADF- 44382-GO- Vehicles No Post RFB III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Consultant QCBS, QBS, FBS, >/= USD 500,000 ; NA Services LCS and CQS* >=US$200,000 for IC and NA SSS >/=US$5,000 for SSS NA IC 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Review Ref. No. Description of Assignment Packages by Bank Comments (Prior/ Post) Summary of QCBS 8 AL-ADF- Concept, Design and Supervision of 44317-CS- Post Saranda Urban Upgrading (line 3) QCBS AL-ADF- Concept, Design and Supervision Urban 39736-CS- Post Upgrading Gjirokastra (line 7) QCBS AL-ADF- Concept, Design and Supervision of the 31055-CS- Berat and Permet Integrated Urban Post QCBS Upgrading (line 12 and14) AL-ADF- Site Management, Detailed design and 15563-CS- construction supervision for Infrastructure Prior QCBS of IUTS AL-ADF- Market Research & Development 15567-CS- Strategy for the South of Albania & four Post QCBS municipalities AL-ADF- Market Development for the South of 15568-CS- Albania (Tourism products promotion, Prior QCBS line 16 and component 2 works) AL-ADF- Tourism Product and value chain 15570-CS- development in selected municipalities Prior QCBS (line 16) AL-ADF- 44317-CS- Guesthouse branding and market delivery Prior QCBS Summary of CQS 9 Post AL-ADF- Design and Supervision Gjirokastra 15556-CS- Post system of museums (line 8) CQS AL-ADF- Supervision of fast truck subproject Berat 37871-CS- Post & Permet CQS AL-ADF- Supervision of fast truck subproject 37532-CS- Post Gjirokastra & Saranda CQS AL-ADF- Detailed design and construction 15562-CS- supervision for Infrastructure for Post CQS Viewpoints along the touristic circuit AL-ADF- Asset Management system - assessment 15565-CS- and technical specification for goods (line Post CQS 43) AL-ADF- Geographic Information Systems - 15566-CS- assessment and technical specification for Post CQS goods (line 44) AL-ADF- Tourism Information Management system 15574-CS- Post and Statistics Improvement - assessment CQS and technical specification of goods (line 46) AL-ADF- 15580-CS- Results Assessment (M&E) Post INDV AL-ADF- Design and urban regeneration of the 15557-CS- existing promenade “Naim Frasheri”, Post CQS Sarande Summary of IC 7 Post AL-ADF- International expert on conservation and 15559-CS- structural restoration of monuments and Post INDV historic buildings. (line 4) AL-ADF- Financial Management Systems - 15566-CS- assessment and technical specifications Post INDV for goods. (line 42) AL-ADF- Project Coordinator - Urban Specialist 15576-CS- Prior PCU INDV AL-ADF- 15576-CS- Tourism Specialist - PCU Prior INDV AL-ADF- 15577-CS- Architect - PCU Prior INDV AL-ADF- 15578-CS- Cultural Heritage Consultant Post INDV AL-ADF- 15579-CS- Site Management Consultant Post INDV PROCUREMENT Albania : Project for Integrated Urban and Tourism Development (PIUTD) PLAN General Information Country: Albania Banks Approval Date of the Original Procurement Plan: 2017-05-22 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-05-17 Project ID: P155875 GPN Date: 2017-05-23 Project Name: Project for Integrated Urban and Tourism Development (PIUTD) Loan / Credit No: IBRD / 86560 Executing Agency(ies): Albanian Development Fund WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15534-CW-RFB / Component 1: Urban Upgrading Single Stage - One Under Saranda Staircase Rehabilitation IBRD / 86560 Post Request for Bids Open - National 894,776.70 2017-05-19 2017-05-24 2017-07-05 2017-08-04 2017-09-08 2018-02-08 and Infrastructure Improvement Envelope Implementation Project AL-ADF-15543-CW-RFB / Rehabilitation of Cobblestone Component 1: Urban Upgrading Single Stage - One IBRD / 86560 Prior Request for Bids Open - National 0.00 Canceled 2017-05-18 2017-05-23 2017-07-04 2017-08-03 2017-09-07 2018-02-07 Road "Mihal Komneno" to Berat and Infrastructure Improvement Envelope castle AL-ADF-16753-CW-RFB / Rehabilitation of Cobblestone Component 1: Urban Upgrading Single Stage - One IBRD / 86560 Prior Request for Bids Open - National 0.00 Canceled 2017-06-02 2017-06-28 2017-06-07 2017-07-19 2017-08-18 2017-09-22 2018-03-21 Road "Mihal Komneno" to Berat and Infrastructure Improvement Envelope castle AL-ADF-28554-CW-RFB / Rehabilitimi i rrugës hyrëse Component 1: Urban Upgrading Single Stage - One Under IBRD / 86560 Prior Request for Bids Open - National 0.00 2017-09-14 2017-09-21 2017-09-19 2017-09-25 2017-10-31 2017-11-30 2018-01-04 2018-07-03 "Mihal Komneno" për në Kala and Infrastructure Improvement Envelope Implementation dhe Tabja AL-ADF-15537-CW-RFB / Component 1: Urban Upgrading Single Stage - Two Pending Saranda Tourism Gateway IBRD / 86560 Post Request for Bids Open - International 0.00 2018-06-05 2018-06-10 2018-07-22 2018-10-04 2018-11-08 2020-07-08 and Infrastructure Improvement Envelope Implementation Integrated Urban Upgrading. AL-ADF-15545-CW-RFB / Component 1: Urban Upgrading Single Stage - One Pending Upgrading of vehicle access road IBRD / 86560 Post Request for Bids Open - National 0.00 2018-03-01 2018-03-06 2018-04-17 2018-05-17 2018-06-21 2019-01-19 and Infrastructure Improvement Envelope Implementation "Muzak Topia" to Berat castle AL-ADF-15536-CW-RFB / Urban Regeneration of the Existing Component 1: Urban Upgrading Single Stage - One Pending IBRD / 86560 Post Request for Bids Open - National 0.00 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 2019-03-21 Promenade "Naim Frasheri" in and Infrastructure Improvement Envelope Implementation Saranda AL-ADF-15538-CW-RFB / Ali Component 1: Urban Upgrading Single Stage - One Pending Pasha historic trail and slopes IBRD / 86560 Post Request for Bids Open - National 0.00 2018-11-30 2018-12-05 2019-01-16 2019-02-15 2019-03-22 2019-10-22 and Infrastructure Improvement Envelope Implementation stabilization - Gjirokastra AL-ADF-15539-CW-RFB / Street Component 1: Urban Upgrading Single Stage - One Pending lighting historic center - IBRD / 86560 Post Request for Bids Open - National 0.00 2018-03-30 2018-04-04 2018-05-16 2018-06-15 2018-07-20 2018-12-20 and Infrastructure Improvement Envelope Implementation Gjirokastra AL-ADF-15540-CW-RFB / Component 1: Urban Upgrading Single Stage - One Bazaar cobble stone roads IBRD / 86560 Post Request for Bids Open - National 0.00 Canceled 2018-02-28 2018-03-05 2018-04-16 2018-03-05 2018-05-16 2018-06-20 2019-05-20 and Infrastructure Improvement Envelope rehabilitation AL-ADF-15541-CW-RFB / Component 1: Urban Upgrading Single Stage - One Pending Gjirokastra Museum City IBRD / 86560 Post Request for Bids Open - National 0.00 2019-02-18 2019-02-23 2019-04-06 2019-05-06 2019-06-10 2021-02-07 and Infrastructure Improvement Envelope Implementation Integrated Urban Upgrading AL-ADF-15542-CW-RFB / Component 1: Urban Upgrading Single Stage - One Pending Upgrading and renovation of IBRD / 86560 Post Request for Bids Open - National 0.00 2019-01-14 2019-01-19 2019-03-02 2019-04-01 2019-05-06 2020-09-04 and Infrastructure Improvement Envelope Implementation system of museums AL-ADF-15546-CW-RFB / Visual Component 1: Urban Upgrading Single Stage - One Pending Upgrading of selected heritage IBRD / 86560 Post Request for Bids Open - National 0.00 2018-05-28 2018-06-02 2018-07-14 2018-08-13 2018-09-17 2019-01-17 and Infrastructure Improvement Envelope Implementation landscape AL-ADF-15547-CW-RFB / Berat Component 1: Urban Upgrading Single Stage - Two Pending Town of Integrated Urban IBRD / 86560 Prior Request for Bids Open - International 0.00 2018-12-17 2018-12-22 2019-02-02 2019-04-17 2019-05-22 2020-12-20 and Infrastructure Improvement Envelope Implementation Upgrading AL-ADF-15548-CW-RFB / Street Component 1: Urban Upgrading Single Stage - One IBRD / 86560 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-06-14 2018-07-19 2018-10-18 lighting - Permet and Infrastructure Improvement Envelope AL-ADF-15549-CW-RFB / Component 1: Urban Upgrading Single Stage - One Pending Permet integrated urban IBRD / 86560 Post Request for Bids Open - National 0.00 2018-11-30 2018-12-05 2019-01-16 2019-02-15 2019-03-22 2020-07-21 and Infrastructure Improvement Envelope Implementation upgraded AL-ADF-15550-CW-RFB / Component 2: Touristic Sites Single Stage - One Pending Integrated upgrading of selected IBRD / 86560 Post Request for Bids Open - National 0.00 2019-04-16 2019-04-21 2019-06-02 2019-07-02 2019-08-06 2021-02-02 Upgrading Envelope Implementation touristic sites. AL-ADF-51671-CW-RFB / Component 2: Touristic Sites Single Stage - One Pending IBRD / 86560 Post Request for Bids Open - National 0.00 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-07-17 Construction of viewpoints Upgrading Envelope Implementation AL-ADF-15551-CW-RFB / Component 3:Tourism Market Single Stage - One Pending Tourism Product development in IBRD / 86560 Post Request for Bids Open - National 0.00 2019-03-25 2019-03-30 2019-05-11 2019-06-10 2019-07-15 2022-04-14 and Product Development Envelope Implementation 4 municpalities AL-ADF-62551-CW-RFB / Component 1: Urban Upgrading Single Stage - One Pending Bazaar cobblestone roads IBRD / 86560 Post Request for Bids Open - National 0.00 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2019-03-03 and Infrastructure Improvement Envelope Implementation rehabilitation AL-ADF-63100-CW-RFQ / Street Component 1: Urban Upgrading Request for Single Stage - One Pending IBRD / 86560 Post Limited 0.00 2018-06-04 2018-07-30 2019-01-26 lighting - Permet and Infrastructure Improvement Quotations Envelope Implementation Page 1 GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15581-GO-RFB / Solid Component 3:Tourism Market Single Stage - One waste equipment for Himara IBRD / 86560 Prior Request for Bids Open - National 0.00 Canceled 2017-05-30 2017-06-04 2017-07-16 2018-01-31 2017-08-15 2017-09-19 2018-01-19 and Product Development Envelope transfer station AL-ADF-15583-GO-RFB / Component 3:Tourism Market Single Stage - One Pending Financial Management IBRD / 86560 Post Request for Bids Open - National 0.00 2018-06-20 2018-06-25 2018-08-06 2018-09-05 2018-10-10 2019-03-12 and Product Development Envelope Implementation Equipment for 4 municipalities AL-ADF-15584-GO-RFB / GIS Component 3:Tourism Market Single Stage - One Pending equipment and licenses for 4 IBRD / 86560 Post Request for Bids Open - National 0.00 2018-11-20 2018-11-25 2019-01-06 2019-02-05 2019-03-12 2019-09-09 and Product Development Envelope Implementation municipalities AL-ADF-15589-GO-RFQ / Component 4: Implementation Request for Single Stage - One Under IBRD / 86560 Post Open - National 131,517.71 2017-07-05 2017-08-30 2017-11-30 Vehicles Support Quotations Envelope Implementation AL-ADF-15609-GO-RFB / Asset Component 3:Tourism Market Single Stage - One Pending Management Equipment for 4 IBRD / 86560 Post Request for Bids Open - National 0.00 2018-09-03 2018-09-08 2018-10-20 2018-11-19 2018-12-24 2019-07-24 and Product Development Envelope Implementation municipalities AL-ADF-44382-GO-RFQ / Purchase of additional Component 4: Implementation Request for Single Stage - One Pending IBRD / 86560 Post Open - National 0.00 2018-01-24 2018-03-21 2018-09-17 accessories for smart board of Support Quotations Envelope Implementation ADF's meeting room AL-ADF-15582-GO-RFB / Solid W collection Component 3:Tourism Market Single Stage - One Pending IBRD / 86560 Post Request for Bids Open - National 0.00 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-07-12 equipment(Gjirokastra/other as and Product Development Envelope Implementation needed) AL-ADF-15585-GO-RFB / Component 3:Tourism Market Request for Single Stage - One Pending Equipment for local destination IBRD / 86560 Prior Open - National 0.00 2019-02-17 2019-04-14 2019-07-13 and Product Development Quotations Envelope Implementation management entities AL-ADF-15586-GO-RFB / Equipment for tourism Component 3:Tourism Market Single Stage - One Pending IBRD / 86560 Post Request for Bids Open - National 0.00 2019-02-14 2019-02-19 2019-04-02 2019-05-02 2019-06-06 2019-10-07 information management and and Product Development Envelope Implementation statistic improvement AL-ADF-15588-GO-RFQ / Office Component 4: Implementation Request for Single Stage - One Pending equipment and licenses for IBRD / 86560 Post Open - National 0.00 2018-03-25 2018-05-20 2018-08-20 Support Quotations Envelope Implementation project implementation AL-ADF-54729-GO-RFB / Solid Component 3:Tourism Market Single Stage - One Under waste equipment for Himara IBRD / 86560 Post Request for Bids Open - National 0.00 2018-04-10 2018-04-15 2018-03-28 2018-05-27 2018-06-26 2018-07-31 2019-01-27 and Product Development Envelope Implementation transfer station NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15552-CS-QCBS / Concept, Design and Supervision Component 1: Urban Upgrading Quality And Cost- IBRD / 86560 Prior Open - International 0.00 Canceled 2017-05-30 2017-06-20 2017-08-03 2017-08-31 2017-09-30 2017-11-04 2017-12-09 2020-07-09 of Saranda Urban Upgrading (line and Infrastructure Improvement Based Selection 3) AL-ADF-15557-CS-CQS / Consultant Design of Urban Regeneration of Component 1: Urban Upgrading Under IBRD / 86560 Post Qualification Open - National 0.00 2017-07-11 2017-05-25 2017-08-01 2017-09-14 2017-10-14 2017-11-18 2018-05-20 the Existing Promenade "Naim and Infrastructure Improvement Implementation Selection Frasheri" in Saranda. (line 2) AL-ADF-15562-CS-CQS / Detailed design and construction Consultant Component 2: Touristic Sites Under supervision for Infrastructure for IBRD / 86560 Post Qualification Open - International 0.00 2017-05-29 2017-06-19 2017-09-28 2017-08-02 2017-09-01 2017-10-06 2019-05-06 Upgrading Implementation Viewpoints along the touristic Selection circuit AL-ADF-15570-CS-QCBS / Tourism Product and value chain Component 3:Tourism Market Quality And Cost- Pending IBRD / 86560 Prior Open - International 0.00 2017-06-30 2017-07-21 2017-09-03 2017-10-01 2017-10-31 2017-12-05 2018-01-09 2021-02-08 development in selected and Product Development Based Selection Implementation municipalities (line 16) AL-ADF-15567-CS-QCBS / Market Research & Development Component 3:Tourism Market Quality And Cost- Under IBRD / 86560 Post Open - International 324,092.59 2017-05-26 2017-06-16 2017-06-15 2017-07-30 2017-10-17 2017-08-27 2017-09-26 2017-10-31 2017-12-05 2018-07-05 Strategy for the South of Albania and Product Development Based Selection Implementation & four municipalities Consultant AL-ADF-15580-CS-INDV / Component 4: Implementation IBRD / 86560 Post Qualification Open - National 0.00 Canceled 2019-03-12 2019-03-26 2019-05-21 2019-06-25 2022-06-25 Results Assessment (M&E) Support Selection AL-ADF-15561-CS-CQS / Consultant Supervision of fast truck Component 1: Urban Upgrading IBRD / 86560 Post Qualification Open - International 0.00 Canceled 2017-05-31 2017-06-21 2017-08-04 2017-09-03 2017-10-08 2019-02-08 subproject ( line and Infrastructure Improvement Selection 1,2,4,5,6,9,10,13) Page 2 AL-ADF-15555-CS-QCBS / Concept, Design and Supervision Component 1: Urban Upgrading Quality And Cost- of the Berat and Permet IBRD / 86560 Prior Open - International 0.00 Canceled 2017-05-31 2017-09-26 2017-06-21 2017-08-04 2017-09-01 2017-10-01 2017-11-05 2017-12-10 2020-06-09 and Infrastructure Improvement Based Selection Integrated Urban Upgrading ( line 12 and14) AL-ADF-31055-CS-QCBS / Concept, Detail Designs and Component 1: Urban Upgrading Quality And Cost- Under supervision for Integrated Urban IBRD / 86560 Post Open - International 0.00 2017-10-04 2017-10-25 2017-10-04 2017-12-08 2018-01-05 2018-02-04 2018-03-11 2018-04-15 2019-04-15 and Infrastructure Improvement Based Selection Implementation Upgrading Municipalities of Berati and Përmeti AL-ADF-21339-CS-QBS / Component 1: Urban Upgrading Quality Based Supervision of fast truck sub- IBRD / 86560 Post Open - National 0.00 Canceled 2017-07-20 2017-08-10 2017-09-23 2017-10-21 2017-11-20 2017-12-20 2018-01-24 2019-01-24 and Infrastructure Improvement Selection project (Saranda and Gjirokastra) AL-ADF-37532-CS-CQS / Consultant Supervision of fast truck Component 1: Urban Upgrading Pending IBRD / 86560 Post Qualification Open - National 0.00 2017-11-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2018-09-26 subproject (Saranda and and Infrastructure Improvement Implementation Selection Gjirokastra) AL-ADF-21342-CS-QBS / Component 1: Urban Upgrading Quality Based Supervision of fast truck sub- IBRD / 86560 Post Open - National 0.00 Canceled 2017-07-21 2017-08-11 2017-09-24 2017-10-22 2017-11-21 2017-12-21 2018-01-25 2019-01-25 and Infrastructure Improvement Selection project (Berat and Permet) AL-ADF-37871-CS-CQS / Supervision services for fast-truck Consultant Component 1: Urban Upgrading Pending sub-project in urban upgrading IBRD / 86560 Post Qualification Open - National 0.00 2017-11-22 2017-12-13 2018-01-26 2018-02-25 2018-04-01 2018-09-28 and Infrastructure Improvement Implementation and infrastructure improvement Selection (Berat and Permet) AL-ADF-15553-CS-QCBS / Concept, Design and Supervision Component 1: Urban Upgrading Quality And Cost- IBRD / 86560 Prior Open - International 0.00 Canceled 2017-06-30 2017-07-21 2017-09-03 2017-10-01 2017-10-31 2017-12-05 2018-01-09 2020-07-09 Urban Upgrading Gjirokastra (line and Infrastructure Improvement Based Selection 7) AL-ADF-15563-CS-QCBS / Site Management, Detailed design Component 2: Touristic Sites Quality And Cost- Pending IBRD / 86560 Post Open - International 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-01 2018-07-31 2018-09-04 2018-10-09 2020-06-07 and construction supervision for Upgrading Based Selection Implementation Infrastructure of IUTS AL-ADF-44317-CS-QCBS / Municipality of Saranda - Detailed Designs and Component 2: Touristic Sites Quality And Cost- Under IBRD / 86560 Post Open - International 0.00 2018-01-17 2018-02-07 2018-03-23 2018-04-20 2018-05-20 2018-06-24 2018-07-29 2019-07-29 Construction Supervision for Upgrading Based Selection Implementation Saranda Tourism Gateway Integrated Urban Upgrading AL-ADF-39736-CS-QCBS / Concept, Design and Supervision Component 1: Urban Upgrading Quality And Cost- Pending IBRD / 86560 Post Open - International 0.00 2017-12-07 2017-12-28 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 Urban Upgrading Gjirokastra (line and Infrastructure Improvement Based Selection Implementation 7) AL-ADF-15556-CS-CQS / Consultant Design and Supervision Component 1: Urban Upgrading Pending IBRD / 86560 Post Qualification Open - National 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2020-08-21 Gjirokastra system of museums and Infrastructure Improvement Implementation Selection (line 8) AL-ADF-15565-CS-CQS / Asset Consultant Management system - Component 3:Tourism Market Pending IBRD / 86560 Post Qualification Open - National 0.00 2018-04-27 2018-05-18 2018-07-01 2018-07-31 2018-09-04 2019-04-04 assessment and technical and Product Development Implementation Selection specification for goods (line 43) AL-ADF-15566-CS-CQS / Consultant Geographic Information Systems Component 3:Tourism Market Pending IBRD / 86560 Post Qualification Open - National 0.00 2018-06-14 2018-07-05 2018-08-18 2018-09-17 2018-10-22 2019-04-23 - assessment and technical and Product Development Implementation Selection specification for goods (line 44) AL-ADF-15568-CS-QCBS / Market Development for the Component 3:Tourism Market Quality And Cost- Pending South of Albania (Tourism IBRD / 86560 Post Open - International 0.00 2018-06-18 2018-07-09 2018-08-22 2018-09-19 2018-10-19 2018-11-23 2018-12-28 2021-10-27 and Product Development Based Selection Implementation products promotion, line 16 and component 2 works) AL-ADF-15573-CS-QCBS / Component 3:Tourism Market Quality And Cost- Pending Guesthouse branding and market IBRD / 86560 Post Open - International 0.00 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2022-08-11 and Product Development Based Selection Implementation delivery AL-ADF-15574-CS-CQS / Tourism Information Management Consultant system and Statistics Component 3:Tourism Market Pending IBRD / 86560 Post Qualification Open - National 0.00 2018-11-23 2018-12-14 2019-01-27 2019-02-26 2019-04-02 2019-11-02 Improvement - assessment and and Product Development Implementation Selection technical specification of goods (line 46) AL-ADF-62578-CS-CQS / Primary Data Collection, Development of Mid-Term and Consultant Component 4: Implementation Pending End Follow up Surveys, IBRD / 86560 Post Qualification Open - National 0.00 2018-05-14 2018-05-16 2018-06-29 2018-07-29 2018-09-02 2019-03-01 Support Implementation Assessment of PDO findings Selection achievement in the framework of PIUTD INDIVIDUAL CONSULTANTS Page 3