Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan: March ......, 2017 3. Date of General Procurement Notice: ............................ 4. Period covered by this procurement plan: March 17 to Jan 2018. II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (PRT) Comments US$ (Millions) 1. Works (Including turnkey, supply & 5 High installation of plant and equipment and PPP) 2. (Goods; Information Technology & Non- 1.5 High Consulting Services) 3. Consultant Services (Firms) 0.5 High 4. Consultant Services (Individual Consultants) 0.2 High 2. Pre-qualification NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: Domestic Preference shall apply. 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. 9. Renewal or extension of individual consultants contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 17, 2017 PROCUREMENT Uganda : Uganda Energy for Rural Transformation III PLAN General Information Country: Uganda Bank’s Approval Date of the Original Procurement Plan: 2017-03-24 2019-12-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133312 GPN Date: Project Name: Uganda Energy for Rural Transformation III Loan / Credit No: IDA / 56530 Executing Agency(ies): Ministry of Energy and Mineral Development WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MEMD-6022-CW-RFQ / Pending Minor Civil Works for Request for Single Stage - One IDA / 56530 On-grid Energy Access Post Limited 60,000.00 0.00 Implementati 2018-04-06 2018-06-01 2018-11-28 pico/micro sites (6 Sites)- Quotations Envelope on PSFU UG-MEMD-6015-CW-RFB / Procurement of works for Supply, installation and maintenance of Energy Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 1,500,000.00 0.00 Canceled 2017-05-28 2017-08-06 2017-10-30 2018-01-01 2018-03-11 2019-05-09 Packages for 100 Post International Envelope Primary Education Institutions in Lots 1&2(MOES) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MEMD-6029-GO-RFQ / Pending Product Software upgrade- Request for Single Stage - One IDA / 56530 On-grid Energy Access Post Limited 50,000.00 0.00 Implementati 2017-03-20 2017-05-15 2017-11-11 (Accounting system ) for Quotations Envelope on UECCC UG-MEMD-6048-GO-RFB / Supply and installation of Pending Single Stage - One distribution lines for IDA / 56530 On-grid Energy Access Post Request for Bids Open - National 360,000.00 0.00 Implementati 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 2018-11-20 Envelope Household access (6 sets) - on PSFU UG-MEMD-13496-GO-RFB / Procurement of works for Supply & Installation maintenance of Energy Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 2,700,000.00 2,437,674.95 Signed 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Packages for Water Supply International Envelope Schemes in Small Towns and Rural Growth Centres (12-14 schemes)-MoWE UG-MEMD-7337-GO-RFB / Supply and installation of Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 4,500,000.00 2,288,650.61 Signed 2017-02-14 2017-02-19 2017-04-02 2017-05-02 2017-06-06 2017-12-03 solar energy packages for International Envelope 374 Health centres (MoH) UG-MEMD-7437-GO-RFB / Single Stage - One Procurement of a Double IDA / 56530 On-grid Energy Access Post Request for Bids Open - National 40,000.00 51,874.23 Signed 2016-12-30 2017-01-04 2017-02-15 2017-03-17 2017-04-21 2017-10-18 Envelope cabin Page 1 UG-MEMD-15330-GO-RFQ / Procurement of 50 Tablets Request for Single Stage - One IDA / 56530 On-grid Energy Access Post Limited 30,000.00 26,914.05 Signed 2017-06-06 2017-07-29 2017-09-10 for the ERT III Baseline Quotations Envelope Survey UG-MEMD-15112-GO-RFB / Procurement of Satellite Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 988,041.00 0.00 Canceled 2017-05-18 2017-05-31 2017-07-14 2017-08-04 2017-09-20 2017-12-20 Imagery Requirements for International Envelope ERT III UG-MEMD-48035-GO-DIR / Supply, Installation & training of geophysical data Institutional Strengthening IDA / 56530 Post Direct Selection Direct 15,000.00 23,000.00 Signed 2018-02-21 2018-02-26 2018-04-02 2018-09-29 processing software Geotools and Impacts Monitoring (Magnetotelluric and TDEM Intepretation software) UG-MEMD-40434-GO-RFB / Procurement of AERIAL Single Stage - One IDA / 56530 Off-grid Energy Access Post Request for Bids Open - National 48,420.00 77,373.07 Signed 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 Imagery Equipment and Envelope Software for MEMD UG-MEMD-48036-GO-DIR / Supply of six (6) porous pot Institutional Strengthening IDA / 56530 Post Direct Selection Direct 15,000.00 0.00 Canceled 2018-02-21 2018-02-26 2018-04-02 2018-09-29 electrode for Magnetotelluric and Impacts Monitoring equipment UG-MEMD-47591-GO-DIR / Supply of geophysical data Institutional Strengthening IDA / 56530 Post Direct Selection Direct 35,500.00 36,000.00 Signed 2018-08-15 2018-08-20 2018-09-24 2019-03-23 processing software(Empower) and Impacts Monitoring &Training UG-MEMD-72497-GO-RFB / Supply and installation of two (2) fixed meter (Lot 1) Institutional Strengthening Open - Single Stage - One IDA / 56530 Post Request for Bids 1,040,000.00 1,014,390.50 Signed 2018-08-15 2018-09-06 2018-10-18 2018-11-17 2018-12-22 2019-06-20 and six (6) portable and Impacts Monitoring International Envelope meter(Lot 2) testing equipment. UG-MEMD-72500-GO-RFB / Supply & Installation of Open - Single Stage - One Energy Packages for Water IDA / 56530 Off-grid Energy Access Post Request for Bids 800,942.00 788,023.60 Signed 2018-08-30 2018-09-21 2018-11-02 2018-12-02 2019-01-06 2019-07-05 International Envelope Pumping Systems - Lot 3 (5 schemes) UG-MEMD-73138-GO-RFB / Supply and installation of Single Stage - One IDA / 56530 On-grid Energy Access Post Request for Bids Open - National 353,500.00 346,173.24 Signed 2018-08-30 2018-09-04 2018-10-16 2018-11-15 2018-12-20 2019-06-18 seven (7) household wiring Envelope demo-cubicles UG-MEMD-6011-GO-RFB / Pending Procurement of 60 solar Request for Single Stage - One IDA / 56530 On-grid Energy Access Post Limited 30,000.00 0.00 Implementati 2018-09-26 2018-11-21 2019-05-20 maintenance tool kits for Quotations Envelope on District based technicians UG-MEMD-73999-GO-RFQ / Office furniture for USEA & Pending ERT III PSFU unit (6 Request for Single Stage - One IDA / 56530 Off-grid Energy Access Post Limited 7,532.00 0.00 Implementati 2018-09-26 2018-11-21 2019-05-20 Filing cabinets, 6 Office Quotations Envelope on tables , 14 Office chairs &1 seater boardroom set) Page 2 UG-MEMD-73997-GO-RFQ / Office equipment for USEA & ERT III PSFU unit (6 desk top computers, a Pending Request for Single Stage - One printer, multipurpose IDA / 56530 Off-grid Energy Access Post Limited 11,153.00 0.00 Implementati 2018-09-04 2018-10-30 2019-04-28 Quotations Envelope photocopier, a projector a on digital camera for field photography & Internet connection equipment) UG-MEMD-94457-GO-RFB / Supply, installation and maintenance of Energy Under Open - Single Stage - One Packages for 89 Post IDA / 56530 Off-grid Energy Access Prior Request for Bids 1,500,000.00 0.00 Implementati 2019-01-21 2019-01-26 2019-03-09 2019-04-08 2019-05-13 2019-11-09 International Envelope Primary Education on Institutions in Lots 1&2 (MOES) UG-MEMD-98603-GO-RFB / Under Procurement of a motor Request for Single Stage - One IDA / 56530 Off-grid Energy Access Post Limited 50,000.00 0.00 Implementati 2019-03-05 2019-04-30 2019-10-27 vehicle for Ministry of Quotations Envelope on Health UG-MEMD-102710-GO-RFB / Supply, Installation, Commissioning and Under Open - Single Stage - One Maintenance of Solar IDA / 56530 Off-grid Energy Access Prior Request for Bids 2,200,000.00 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 International Envelope Photovoltaic (PV) Energy on Packages in 180 Health Centres in 42 Districts UG-MEMD-121401-GO-RFB / Supply, Installation and Commissioning of Solar Under Open - Single Stage - One Photovoltaic Energy for IDA / 56530 Off-grid Energy Access Prior Request for Bids 2,300,000.00 0.00 Implementati 2019-06-28 2019-07-03 2019-08-18 2019-09-17 2019-11-05 2020-05-11 International Envelope Water Supply Schemes Lot on 4 (5No. Systems) and Lot 5 (6No. Systems) UG-MEMD-129765-GO-RFB / Procurement of a Double Pending Single Stage - One cabin pick up (2.8Ltrs) for IDA / 56530 Off-grid Energy Access Post Request for Bids Open - National 60,000.00 0.00 Implementati 2019-09-06 2019-09-11 2019-10-23 2019-11-22 2019-12-27 2020-06-24 Envelope ERT III implementation on actvities -MoEs Component UG-MEMD-144050-GO-RFQ Pending / Computers and Request for Single Stage - One IDA / 56530 Off-grid Energy Access Post Limited 12,465.75 0.00 Implementati 2019-11-12 2020-01-07 2020-07-05 Accessories (7 computers and Quotations Envelope on 1 projector) for UECCC UG-MEMD-144051-GO-RFQ Pending / Supply of office furniture Request for Single Stage - One IDA / 56530 Off-grid Energy Access Post Limited 7,397.26 0.00 Implementati 2019-11-13 2020-01-08 2020-07-06 (2 lockable filling cabinets Quotations Envelope on and 4 sector workstation) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MEMD-48039-NC-DIR / Institutional Strengthening Upgrade of MTU-5A (6) to IDA / 56530 Post Direct Selection Direct 112,760.00 113,760.00 Signed 2018-08-15 2018-08-20 2018-09-24 2019-03-23 and Impacts Monitoring MTU-5C receivers UG-MEMD-73143-NC-RFB / Institutional Strengthening Single Stage - One Media campaign to sensitize IDA / 56530 Post Request for Bids Open - National 200,000.00 200,880.85 Signed 2018-09-17 2018-09-22 2018-11-03 2018-12-03 2019-01-07 2019-07-06 and Impacts Monitoring Envelope general public and wire-men Page 3 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MEMD-13578-CS-CQS / TA to facilitate the development of the strategic Consultant framework and IDA / 56530 On-grid Energy Access Post Qualification Open - National 62,500.00 70,214.60 Signed 2016-05-30 2017-01-05 2017-03-17 2017-07-31 2017-09-04 2018-03-03 establishment of institutional Selection systems for the Uganda Solar Energy Association UG-MEMD-13583-CS-QCBS / TA to support provision of electricity to isolated places Quality And Cost- Open - IDA / 56530 On-grid Energy Access Post 250,000.00 172,199.14 Signed 2015-12-11 2016-06-17 2017-01-20 2017-06-30 2017-07-30 2017-09-03 2017-10-08 2018-10-08 through development of Based Selection International pico/micro hydro schemes(PSFU) UG-MEMD-13562-CS-CQS / Preparation of a Master Consultant Open - guarantee agreement and a IDA / 56530 On-grid Energy Access Post Qualification 100,000.00 98,800.00 Signed 2015-10-10 2016-06-16 2016-06-21 2016-09-15 2016-10-20 2017-04-18 International working capital facility Selection agreement(UECCC) UG-MEMD-13559-CS-QCBS / Designs preparation and Quality And Cost- Open - Pending supervision of water supply IDA / 56530 On-grid Energy Access Post 450,000.00 0.00 2014-11-04 2015-02-20 2015-05-18 2015-07-07 2015-07-21 2015-09-30 2015-12-15 2017-11-13 Based Selection International Implementation solar energy packages rural centres(MoWE) UG-MEMD-13593-CS-QCBS / Needs assessment and Quality And Cost- Open - IDA / 56530 On-grid Energy Access Post 220,000.00 0.00 Canceled 2015-03-27 2015-07-02 2015-07-31 2015-11-30 2015-12-30 2016-06-22 2016-09-14 2017-05-19 Supervison of installation of Based Selection International Energy Packages for MoES UG-MEMD-15599-CS-CQS / Designing of UECCC Consultant Open - Working capital facility for IDA / 56530 Off-grid Energy Access Post Qualification 290,000.00 0.00 Canceled 2016-04-13 2016-05-31 2016-07-20 2016-09-14 2016-12-21 2017-06-30 International solar companies and partial Selection risk guarantee for PFIS UG-MEMD-7449-CS-QCBS / Quality And Cost- Open - IDA / 56530 On-grid Energy Access Prior 700,000.00 0.00 Canceled 2017-02-16 2017-03-09 2017-04-22 2017-05-20 2017-06-19 2017-07-24 2017-08-28 2018-08-28 Cost of Service Study Based Selection International UG-MEMD-16946-CS-CQS / Consultancy Services for Consultant Institutional Strengthening Environmental Audit of the IDA / 56530 Post Qualification Open - National 65,000.00 63,415.40 Signed 2017-06-15 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 and Impacts Monitoring Solar PV Energy Packages Selection UNDER ERT-II UG-MEMD-7466-CS-CQS / Consultancy services Environmental and Social Consultant Impact Assessment (ESIA) of IDA / 56530 On-grid Energy Access Prior Qualification Open - National 300,000.00 0.00 Canceled 2017-02-16 2017-03-09 2017-04-22 2017-05-22 2017-06-26 2017-06-30 the Impact of the Isimba Selection Hydropower Project on the Kalagala Offset Area UG-MEMD-13564-CS-CQS / Designing of UECCC Consultant Working capital facility for Open - IDA / 56530 On-grid Energy Access Post Qualification 290,000.00 0.00 Canceled 2015-10-10 2016-06-17 2016-07-20 2016-09-15 2017-04-24 2017-10-21 solar companies and partial International Selection risk guarantee for PFIS (UECCC) Page 4 UG-MEMD-7867-CS-CQS / TA to develop interventions Consultant to scale up wiring IDA / 56530 On-grid Energy Access Post Qualification Open - National 40,000.00 44,323.11 Signed 2017-04-19 2017-04-19 2017-04-19 2017-04-19 2017-05-10 2017-11-06 installations across the Selection (PSFU) UG-MEMD-127016-CS-CQS / Technical Assitance for Consultant training of wiremen across Open - Under IDA / 56530 Off-grid Energy Access Post Qualification 220,000.00 0.00 2019-08-23 2019-09-13 2019-10-27 2019-11-26 2019-12-31 2020-06-28 the country in the International Implementation Selection selected National colleges(ERA) UG-MEMD-135531-CS-QCBS / Consultancy services for Development of a regulatory framework for Institutional Strengthening Quality And Cost- Open - Under IDA / 56530 Prior 850,000.00 0.00 2019-10-11 2019-11-01 2019-12-15 2020-01-12 2020-02-11 2020-03-17 2020-04-21 2020-12-30 determination,monitoring and Impacts Monitoring Based Selection International Implementation ,auditing and improvement of the reliability of supply UG-MEMD-135532-CS-QCBS / Consultancy services for development of a Institutional Strengthening Quality And Cost- Open - regulatory framework to IDA / 56530 Prior 1,300,000.00 0.00 Under Review 2019-10-24 2019-11-14 2019-12-28 2020-01-25 2020-02-24 2020-03-30 2020-05-04 2020-12-31 and Impacts Monitoring Based Selection International facilitate the private investment in transmission facilities UG-MEMD-135536-CS-QCBS / Consultancy services for Institutional Strengthening Quality And Cost- Open - Under implementation of of IDA / 56530 Prior 1,500,000.00 0.00 2019-10-30 2019-11-20 2020-01-03 2020-01-31 2020-03-01 2020-04-05 2020-05-10 2020-12-28 and Impacts Monitoring Based Selection International Implementation regulatory information Management System UG-MEMD-138923-CS-CQS / Consultancy for identification of public Consultant institutions to be electrified Institutional Strengthening Open - IDA / 56530 Prior Qualification 400,000.00 0.00 Under Review 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2020-08-20 with solar installations and and Impacts Monitoring International Selection development of an alternative payment option for energy under EASP UG-MEMD-144062-CS-CQS Consultant / Consultant to prepare Pending IDA / 56530 Off-grid Energy Access Post Qualification Open - National 30,000.00 0.00 2019-11-08 2019-11-29 2020-01-12 2020-02-11 2020-03-17 2020-09-13 Interest Rate Setting Policy Implementation Selection (UECCC) UG-MEMD-145997-CS-CQS / Consultancy firm to recruit 5 staff (Environment,health and Consultant Pending safety,Procurement ,social IDA / 56530 Off-grid Energy Access Post Qualification Open - National 27,397.00 0.00 2019-11-25 2019-12-16 2020-01-29 2020-02-28 2020-04-03 2020-09-30 Implementation and Gender Specialist and Selection two transaction execution Specialsits ) for UECCC under EASP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MEMD-7871-CS-INDV / Individual Pending Procurement of a Treasury IDA / 56530 On-grid Energy Access Post Consultant Open 65,397.00 0.00 2016-09-30 2017-04-05 2017-04-26 2017-05-31 2017-11-27 Implementation Specialist (UECCC) Selection Page 5 UG-MEMD-13579-CS-INDV Individual / Recruitment of Risk Pending IDA / 56530 On-grid Energy Access Post Consultant Open 139,886.00 0.00 2015-10-10 2016-07-20 2016-09-15 2016-10-17 2019-10-17 Specialist (three year Implementation Selection contract) UG-MEMD-13576-CS-CDS / TA-Project management IDA / 56530 On-grid Energy Access Post Direct Selection Direct 170,000.00 138,080.88 Signed 2016-06-20 2016-06-20 2016-09-09 2018-09-10 services - Component Manager, PSFU component UG-MEMD-13563-CS-CDS / Individual TA - Project management IDA / 56530 On-grid Energy Access Post Consultant Open 68,000.00 68,000.00 Signed 2016-05-30 2016-10-24 2016-11-03 2016-11-10 2018-11-10 services - Project Officer- Selection PSFU Component UG-MEMD-7457-CS-CDS / Contract for Coordination IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 297,000.00 0.00 Canceled 2017-02-16 2017-02-26 2017-05-02 2018-06-30 Manager-ERT III(2 Years) UG-MEMD-7460-CS-CDS / Contract for Project IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 198,000.00 0.00 Canceled 2017-02-16 2017-02-26 2017-05-02 2018-06-30 Accountant -ERT III &ESDP(2 Years) UG-MEMD-7468-CS-INDV / Consultancy Services for Environmental Audit of the IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 65,000.00 0.00 Canceled 2017-05-05 2017-05-10 2017-07-14 2018-01-10 Solar PV Energy Packages UNDER ERT-II UG-MEMD-7868-CS-INDV / Individual Investment short-term IDA / 56530 On-grid Energy Access Post Consultant Open 36,000.00 0.00 Canceled 2016-09-30 2017-04-04 2017-04-25 2017-05-30 2017-11-26 consultant (6 months)- Selection UECCC UG-MEMD-29492-CS-CDS / Tendering and Evaluation Support for the Supply, Installation, Commissioning and Maintenance of Solar IDA / 56530 Off-grid Energy Access Post Direct Selection Direct 20,977.00 20,977.00 Signed 2017-09-29 2017-10-09 2017-12-13 2018-06-11 Energy Packages For Ministry of Education and Sports under the Energy for Rural Transformation Phase 3 Project (ERT III) UG-MEMD-65578-CS-CDS / Procurement of consultancy Services for the Coordination Institutional Strengthening IDA / 56530 Prior Direct Selection Direct 152,207.80 155,625.50 Signed 2018-06-11 2018-06-21 2018-06-30 2018-12-27 Manager -Energy for Rural and Impacts Monitoring Transformation Phase III for a period of two years. UG-MEMD-67930-CS-CDS / CONSULTANCY SERVICES OF ERTIII & ESDP Institutional Strengthening IDA / 56530 Post Direct Selection Direct 26,250.00 23,889.88 Signed 2018-06-26 2018-06-27 2018-06-29 2018-12-31 PROJECT ACCOUNTANT and Impacts Monitoring FOR A PERIOD OF SIX MONTHS UG-MEMD-73998-CS-CDS / ERT III PSFU project IDA / 56530 Off-grid Energy Access Post Direct Selection Direct 19,000.00 0.00 Canceled 2018-08-31 2018-09-10 2018-11-14 2019-05-13 Officer (one year contract) UG-MEMD-89295-CS-CDS / Contract for Project Institutional Strengthening IDA / 56530 Prior Direct Selection Direct 105,000.00 0.00 Canceled 2018-12-06 2018-12-16 2018-12-26 2020-12-31 Accountant -ERT III & and Impacts Monitoring GERP (2 Years) Page 6 UG-MEMD-92626-CS-CDS / Contract for Project Institutional Strengthening IDA / 56530 Post Direct Selection Direct 105,000.00 105,515.07 Signed 2018-12-24 2019-01-03 2019-03-09 2019-09-05 Accountant -ERT III & and Impacts Monitoring GERP (2 Years) UG-MEMD-104355-CS-CDS Institutional Strengthening / Chief Executive Officer for IDA / 56530 Post Direct Selection Direct 54,194.00 43,337.60 Signed 2019-04-05 2019-04-15 2019-06-19 2019-12-16 and Impacts Monitoring USEA (PSFU) UG-MEMD-107727-CS-INDV Individual / Communication and Under IDA / 56530 Off-grid Energy Access Post Consultant Open 26,891.20 0.00 2019-04-05 2019-05-24 2019-06-14 2019-07-19 2020-01-15 Membership Officer for Implementation Selection USEA (PSFU UG-MEMD-107732-CS-INDV Individual Under / Finance Officer for USEA IDA / 56530 Off-grid Energy Access Post Consultant Open 26,891.20 0.00 2019-04-05 2019-05-24 2019-06-14 2019-07-19 2020-01-15 Implementation (PSFU Selection UG-MEMD-125926-CS-INDV Individual Under / Administrative Support IDA / 56530 Off-grid Energy Access Post Consultant Open 9,000.00 0.00 2019-08-28 2019-10-16 2019-11-06 2019-12-11 2020-06-08 Implementation Officer (PSFU) Selection Page 7