Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: Marhc 11, 2019 2. Date of General Procurement Notice: March 2015. 3. Period covered by this procurement plan: Until December 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 4 million 3. ICB (Works) Above US$ 15 million 4. NCB (Works) Above US$ 15 million 5. Non-Consultant Services Above US$4 million 6 Consultants (firms) Above US$ 2 million 7. Consultant Individuals Above 0.4 million 2. Prequalification. Not applicable. 4. Any Other Special Procurement Arrangements: NA July 9, 2010 PROCUREMENT Mexico : MEXICO Sustainable Energy Technologies Development for Climate Change PLAN General Information Country: Mexico Bank’s Approval Date of the Original Procurement Plan: 2019-03-19 2019-10-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145618 GPN Date: Project Name: MEXICO Sustainable Energy Technologies Development for Climate Change Loan / Credit No: TF / 19403 Executing Agency(ies): Secretaria de Energia WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRODETES-57-CP-B- DGIDTFRH / Adquisición de Solicitud de Single Stage - One Ejecución licencia de uso del Sistema TF / 19403 Project Management Posterior Limited 391.76 0.00 2019-09-07 2019-11-02 2019-12-02 cotizaciones Envelope pendiente Contable CONTPAQ i, 2018- 2019. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TF-019403-SENER-CF-SBCC- Regional Needs Assessments PREVIA-2015-0047 / for ACE technologies and Selección basada Open - TF / 19403 Previa 300,000.00 214,282.75 Firmado 2015-10-15 2015-11-13 2016-01-08 2016-01-15 2016-02-15 2016-02-16 2016-07-15 Evaluacion de Necesidad Clean Energy Regional en calidad y costo International Regional 1 Investment Plans (CERIPs) TF-019403-SENER-CF-SBCC- Regional Needs Assessments PREVIA-2015-0050 / for ACE technologies and Selección basada Open - TF / 19403 Previa 300,000.00 243,850.56 Firmado 2015-10-15 2015-11-13 2016-01-08 2016-01-15 2016-02-15 2016-02-16 2016-07-15 Evaluacion de Necesidad Clean Energy Regional en calidad y costo International Regional 2 Investment Plans (CERIPs) PRODETES-7-SBCC-CF- Regional Needs Assessments DGEL-DGIDTFRH / for ACE technologies and Selección basada Ejecución Evaluación de Necesidad TF / 19403 Posterior Open - National 300,000.00 0.00 2016-09-14 2016-10-05 2016-11-18 2016-12-16 2017-01-15 2017-02-19 2017-03-26 2018-03-26 Clean Energy Regional en calidad y costo pendiente Regional 3 (Estados de: Investment Plans (CERIPs) Nuevo León y Tamaulipas) Page 1 PRODETES-8-SBCC-CF- DGEL-DGIDTFRH / Regional Needs Assessments Evaluación de Necesidad for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 300,000.00 0.00 2016-09-14 2016-10-05 2016-11-18 2016-12-16 2017-01-15 2017-02-19 2017-03-26 2018-03-26 Regional 4 (Estados de: Clean Energy Regional en calidad y costo pendiente Jalisco, Michoacán, Colima y Investment Plans (CERIPs) Nayarit) PRODETES-9-SBCC-CF- DGEL-DGIDTFRH / Regional Needs Assessments Evaluación de Necesidad for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 300,000.00 0.00 2016-09-14 2016-10-05 2016-11-18 2016-12-16 2017-01-15 2017-02-19 2017-03-26 2018-03-26 Regional 5 (Estados de: Baja Clean Energy Regional en calidad y costo pendiente California, Baja California Investment Plans (CERIPs) Sur, Sinaloa y Sonora) PRODETES-10-SBCC-CF- Regional Needs Assessments DGEL-DGIDTFRH / for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 300,000.00 0.00 2016-09-14 2016-10-05 2016-11-18 2016-12-16 2017-01-15 2017-02-19 2017-03-26 2018-03-26 Evaluación de Necesidad Clean Energy Regional en calidad y costo pendiente Regional 6 (Distrito Federal) Investment Plans (CERIPs) PRODETES-11-SBCC-CF- Regional Needs Assessments DGEL-DGIDTFRH / for ACE technologies and Selección basada Ejecución Evaluación de Necesidad TF / 19403 Posterior Open - National 300,000.00 0.00 2016-09-14 2016-10-05 2016-11-18 2016-12-16 2017-01-15 2017-02-19 2017-03-26 2018-03-26 Clean Energy Regional en calidad y costo pendiente Regional 7 (Estados de: Investment Plans (CERIPs) México y Querétaro) PRODETES-13-SBCC-CF- DGEL-DGIDTFRH / Regional Needs Assessments Evaluación de Necesidad for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 300,000.00 0.00 2016-09-14 2016-10-05 2016-11-18 2016-12-16 2017-01-15 2017-02-19 2017-03-26 2018-03-26 Regional 9 (Estados de: Clean Energy Regional en calidad y costo pendiente Chihuahua, Coahuila y Investment Plans (CERIPs) Durango) PRODETES-50-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución Regional Expost 4 (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Clean Energy Regional en calidad y costo pendiente de: Jalisco, Michoacán, Investment Plans (CERIPs) Colima y Nayarit). PRODETES-12-SBCC-CF- DGEL-DGIDTFRH / Regional Needs Assessments Evaluación de Necesidad for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 300,000.00 0.00 2015-10-02 2015-10-23 2015-12-06 2016-01-03 2016-02-02 2016-03-08 2016-04-12 2017-04-12 Regional 8 (Estados de: Clean Energy Regional en calidad y costo pendiente Hidalgo, Morelos, Puebla, Investment Plans (CERIPs) Tlaxcala y Veracruz). PRODETES-47-SBCC-CF- DGIDTFRH / Evaluación Regional Needs Assessments Regional Expost 1 (Estados for ACE technologies and Selección basada TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 de Aguascalientes, San Luis Clean Energy Regional en calidad y costo Potosí, Guanajuato y Investment Plans (CERIPs) Zacatecas). PRODETES-48-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Regional Expost 2 (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Clean Energy Regional en calidad y costo de: Chiapas Guerrero y Investment Plans (CERIPs) Oaxaca). PRODETES-49-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Regional Expost 3 (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Clean Energy Regional en calidad y costo de: Nuevo León y Investment Plans (CERIPs) Tamaulipas). PRODETES-56-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Regional Expost 10 (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Clean Energy Regional en calidad y costo de: Campeche Quintana Roo, Investment Plans (CERIPs) Tabasco y Yucatán). Page 2 PRODETES-53-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Regional Expost 7 (Estados Clean Energy Regional en calidad y costo de: México y Querétaro). Investment Plans (CERIPs) PRODETES-52-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Regional Expost 6 (Ciudad Clean Energy Regional en calidad y costo de México). Investment Plans (CERIPs) PRODETES-51-SBCC-CF- DGIDTFRH / Evaluación Regional Needs Assessments Regional Expost 5 (Estados for ACE technologies and Selección basada TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 de: Baja California, Baja Clean Energy Regional en calidad y costo California Sur, Sinaloa y Investment Plans (CERIPs) Sonora). PRODETES-55-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Regional Expost 9 (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Clean Energy Regional en calidad y costo de: Chihuahua, Coahuila y Investment Plans (CERIPs) Durango). PRODETES-54-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Regional Expost 8 (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 Cancelado 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Clean Energy Regional en calidad y costo de: Hidalgo, Morelos, Puebla, Investment Plans (CERIPs) Tlaxcala y Veracruz). PRODETES-70-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución Regional Expost 4 (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 Clean Energy Regional en calidad y costo pendiente de: Jalisco, Michoacán, Investment Plans (CERIPs) Colima y Nayarit). PRODETES-86-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 Regional Expost 7, (Estados Clean Energy Regional en calidad y costo pendiente de: México y Querétaro) Investment Plans (CERIPs) PRODETES-88-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución Regional Expost 9, (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 Clean Energy Regional en calidad y costo pendiente de: Chihuahua, Coahuila y Investment Plans (CERIPs) Durango) PRODETES-81-SBCC-CF- DGIDTFRH / Evaluación Regional Needs Assessments Regional Expost 1, (Estados for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 de: Aguascalientes, San Luis Clean Energy Regional en calidad y costo pendiente Potosí, Guanajuato y Investment Plans (CERIPs) Zacatecas). PRODETES-85-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 Regional Expost 6, (Ciudad Clean Energy Regional en calidad y costo pendiente de México) Investment Plans (CERIPs) PRODETES-87-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución Regional Expost 8, (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 Clean Energy Regional en calidad y costo pendiente de: Hidalgo, Morelos, Puebla, Investment Plans (CERIPs) Tlaxcala y Veracruz) Page 3 PRODETES-89-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución Regional Expost 10, (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 Clean Energy Regional en calidad y costo pendiente de: Campeche Quintana Roo, Investment Plans (CERIPs) Tabasco y Yucatán). PRODETES-82-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución Regional Expost 2, (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 Clean Energy Regional en calidad y costo pendiente de: Chiapas, Guerrero y Investment Plans (CERIPs) Oaxaca) PRODETES-84-SBCC-CF- DGIDTFRH / Evaluación Regional Needs Assessments Regional Expost 5, (Estados for ACE technologies and Selección basada Ejecución TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 de: Baja California, Baja Clean Energy Regional en calidad y costo pendiente California Sur, Sinaloa y Investment Plans (CERIPs) Sonora) PRODETES-83-SBCC-CF- Regional Needs Assessments DGIDTFRH / Evaluación for ACE technologies and Selección basada Ejecución Regional Expost 3, (Estados TF / 19403 Posterior Open - National 158,000.00 0.00 2019-10-11 2019-10-31 2019-12-16 2020-02-28 2020-04-08 2020-05-25 2020-06-29 2020-10-29 Clean Energy Regional en calidad y costo pendiente de Nuevo León y Investment Plans (CERIPs) Tamaulipas) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TF019403-SENER-CI- Regional Needs Assessments RECON-PREV-2016-0197 / for ACE technologies and ESPECIALISTA EN TF / 19403 Previa Individual Open 37,500.00 37,647.56 Cancelado Clean Energy Regional ADQUISICIONES PARA LA Investment Plans (CERIPs) UREP PRODETES-16-RE-CI-DGEL- Regional Needs Assessments DGIDTFRH / for ACE technologies and ESPECIALISTA EN TF / 19403 Previa Individual Open 37,500.00 34,484.10 Rescindido Clean Energy Regional ADQUISICIONES PARA LA Investment Plans (CERIPs) UREP PRODETES-28-3CV-CI- Ejecución DGEL-DGIDTFRH / Líder de TF / 19403 Project Management Posterior Individual Limited 42,875.00 0.00 2017-07-07 2017-07-12 2017-08-02 2017-09-06 2018-03-05 pendiente Proyecto Componente 2 PRODETES-29-RE-CI- DGIDTFRH / Recontratación del Coordinador General de la UREP, es una Continuación de los Servicios Ejecución TF / 19403 Project Management Posterior Individual Direct 27,800.31 0.00 2017-07-17 2017-07-27 2017-08-17 2017-09-21 2018-03-20 contratados previamente, pendiente mediante los contratos PRODETES-17-3CV-CI-DGEL y PRODETES -22-RE-CI- DGEL-DGIDTFRH PRODETES-30-3CV-CI- DGIDTFRH / Consultor para el Diseño, Desarrollo e Regional Needs Assessments Implementación de un for ACE technologies and Ejecución TF / 19403 Posterior Individual Limited 58,439.60 0.00 2017-07-20 2017-07-25 2017-08-15 2017-09-19 2018-03-18 Sistema de Información de Clean Energy Regional pendiente las Evaluaciones de Investment Plans (CERIPs) Necesidades Regionales (ENR) del PRODETES Page 4 PRODETES-32-3CV-CI- DGIDTFRH / Enlace de Ejecución Adquisiciones con los TF / 19403 Project Management Posterior Individual Limited 18,513.40 0.00 2017-10-06 2017-10-11 2017-11-01 2017-12-06 2018-06-04 pendiente Ganadores de los Premios Prodetes PRODETES-39-RE-CI- DGIDTFRH / Recontratación del Asistente Ejecutivo General de la UREP, es una Ejecución TF / 19403 Project Management Posterior Individual Direct 15,073.96 0.00 2017-10-12 2017-10-22 2017-11-12 2017-12-17 2018-06-15 Continuación de los Servicios pendiente contratados previamente, mediante el contrato PRODETES-15-3CV-CI-DGEL. PRODETES-40-RE-CI- DGIDTFRH / Recontratacion del Especialista en Adquisiciones para la UREP, es una Continuación Ejecución TF / 19403 Project Management Posterior Individual Direct 40,392.87 0.00 2017-10-12 2017-10-22 2017-11-12 2017-12-17 2018-06-15 de los Servicios contratados pendiente previamente, mediante los contratos PRODETES-1-3CV- CI-DGEL y PRODETES-16- RE-CI-DGEL PRODETES-41-RE-CI- DGIDTFRH / Recontratacion del Especialista Administrativo y Financiero para la UREP, es una Ejecución Continuación de los Servicios TF / 19403 Project Management Posterior Individual Direct 40,392.87 0.00 2017-10-30 2017-11-09 2017-11-30 2018-01-04 2018-07-03 pendiente contratados previamente, mediante los contratos PRODETES-2-3CV-CI-DGEL y PRODETES-18-RE-CI- DGEL PRODETES-43-RE-CI- DGIDTFRH / Coordinador General de la UREP, es una Continuación de los Servicios contratados previamente, Ejecución TF / 19403 Project Management Posterior Individual Direct 63,601.92 0.00 2017-12-21 2017-12-31 2018-01-21 2018-02-25 2018-08-24 mediante los contratos pendiente PRODETES-17-3CV-CI-DGEL, PRODETES -22-RE-CI-DGEL- DGIDTFRH y PRODETES-29- RE-CI-DGIDTFRH PRODETES-44-CD-CI- DGIDTFRH / Consultor para la Asistencia Técnica en Materia de Aspectos de Grants and technical Modelo de Negocios a los assistance for private Ejecución Ganadores de los Premios TF / 19403 Posterior Individual Direct 74,279.62 0.00 2017-12-21 2017-12-31 2018-01-21 2018-02-25 2018-08-24 enterprises in the ACE pendiente GEF-SENER a las sector Tecnologias Verdes. (Primer Convocatoria).- Continuación del PRODETES -24-3CV-CI- DGEL-DGIDTFRH PRODETES-45-3CV-CI- DGIDTFRH / Consultor para Grants and technical la Asistencia Técnica en assistance for private Ejecución Materia de Aspectos Legales TF / 19403 Posterior Individual Limited 14,674.49 0.00 2019-03-04 2019-03-09 2019-03-30 2019-05-04 2019-10-31 enterprises in the ACE pendiente a los Ganadores de los sector Premios GEF-SENER a las Tecnologias Verdes. Page 5 PRODETES-46-RE-CI- DGIDTFRH / Líder de Proyecto Componente 1 Es una Continuación de los Ejecución Servicios contratados TF / 19403 Project Management Posterior Individual Direct 48,597.68 0.00 2018-02-14 2018-02-24 2018-03-17 2018-04-21 2018-10-18 pendiente previamente, mediante el contrato PRODETES-3-3CV- CI-DGEL y PRODETES-20- RE-CI-DGEL. PRODETES-58-RE-CI- DGIDTFRH / Líder de Proyecto Componente 2 Es una Continuación de los Ejecución TF / 19403 Project Management Posterior Individual Direct 46,011.34 0.00 2018-07-20 2018-07-30 2018-08-20 2018-09-24 2019-03-23 Servicios contratados pendiente previamente, mediante el contrato PRODETES-28-3CV- CI-DGEL-DGIDTFRH. PRODETES-60-RE-CI- DGIDTFRH / Especialista en Adquisiciones para la UREP, es una Continuación de los Servicios contratados TF / 19403 Project Management Posterior Individual Direct 44,617.06 43,495.83 Firmado 2018-11-05 2018-11-15 2018-12-06 2019-01-10 2019-07-09 previamente, mediante los contratos PRODETES-1-3CV- CI-DGEL, PRODETES-16-RE- CI-DGEL y PRODETES-40- RE-CI-DGIDTFRH PRODETES-61-RE-CI- DGIDTFRH / Coordinador General de la UREP, es una Continuación de los Servicios contratados previamente, mediante los contratos Ejecución TF / 19403 Project Management Posterior Individual Direct 63,956.51 0.00 2018-11-14 2018-11-24 2018-12-15 2019-01-19 2019-07-18 PRODETES-17-3CV-CI-DGEL, pendiente PRODETES-22-RE-CI-DGEL- DGIDTFRH, PRODETES-29- RE-CI-DGIDTFRH y PRODETES-43-RE-CI- DGIDTFRH PRODETES-62-RE-CI- DGIDTFRH / Especialista Administrativo y Financiero para la UREP, es una Continuación de los Servicios Ejecución contratados previamente, TF / 19403 Project Management Posterior Individual Direct 41,430.13 0.00 2018-11-21 2018-12-01 2018-12-22 2019-01-26 2019-07-25 pendiente mediante los contratos PRODETES-2-3CV-CI-DGEL, PRODETES-18-RE-CI-DGEL y PRODETES-41-RE-CI- DGIDTFRH PRODETES-63-RE-CI- DGIDTFRH / CONSULTOR PARA LA CELEBRACIÓN DE TALLERES A LOS ASPIRANTES DEL PREMIO Grants and technical PRODETES 2018 EN assistance for private Ejecución MATERIA DE MODELO DE TF / 19403 Posterior Individual Direct 18,362.21 0.00 2018-04-04 2018-04-14 2018-05-05 2018-06-09 2018-12-06 enterprises in the ACE pendiente NEGOCIOS Y sector MERCADOTECNIA. Capacitar a los aspirantes al Premio PRODETES 2018 en materia de modelo de negocios y mercadotecnia. Page 6 PRODETES-64-3CV-CI- DGIDTFRH / “Consultor para la asistencia técnica a Grants and technical los Ganadores de los assistance for private Ejecución Premios GEF – SENER a TF / 19403 Posterior Individual Limited 15,862.68 0.00 2019-03-05 2019-03-10 2019-03-31 2019-05-05 2019-11-01 enterprises in the ACE pendiente las Tecnologías Verdes en sector materia de cumplimiento de las salvaguardas ambientales y sociales del PRODETES” PRODETES-71-3CV-CI- DGIDTFRH / Consultor para la Asistencia Técnica en Grants and technical Materia de Aspectos de assistance for private Ejecución TF / 19403 Posterior Individual Limited 13,959.16 0.00 2019-03-05 2019-03-10 2019-03-31 2019-05-05 2019-11-01 Adquisiciones a los enterprises in the ACE pendiente Ganadores de los Premios sector GEF-SENER a las Tecnologías Verdes PRODETES-72-RE-CI- DGIDTFRH / Líder de Proyecto Componente 1 Es una Continuación de los Servicios contratados Ejecución TF / 19403 Project Management Posterior Individual Direct 39,085.65 0.00 2019-02-21 2019-03-03 2019-03-24 2019-04-28 2019-10-25 previamente, mediante el pendiente contrato PRODETES-3-3CV- CI-DGEL, PRODETES-20-RE- CI-DGEL y PRODETES-46- RE-CI-DGIDTFRH PRODETES-73-RE-CI- DGIDTFRH / Líder de Proyecto Componente 2 Es una Continuación de los Servicios contratados Ejecución TF / 19403 Project Management Posterior Individual Direct 19,542.83 0.00 2019-06-14 2019-06-24 2019-07-15 2019-08-19 2020-02-15 previamente, mediante el pendiente contrato PRODETES-28-3CV- CI-DGEL-DGIDTFRH y PRODETES-58-RE-CI- DGIDTFR. PRODETES-74-SD-CI- DGIDTFRH / Consultor para la Asistencia Técnica en Materia de Aspectos de Modelo de Negocios a los Grants and technical Ganadores de los Premios assistance for private Ejecución TF / 19403 Posterior Individual Direct 45,684.53 0.00 2019-03-04 2019-03-14 2019-04-04 2019-05-09 2019-11-05 GEF-SENER a las enterprises in the ACE pendiente Tecnologias Verdes. sector Continuación del PRODETES -24-3CV-CI-DGEL-DGIDTFRH y PRODETES-44-CD-CI- DGIDTFRH Page 7