PROCUREMENT PLAN Southern African Power Pool (SAPP) – Program for Accelerating Transformational Energy Projects General 1. The PDO for this Project is to advance the preparation of selected priority regional energy projects in the Southern African Power Pool participating countries 2. Project ID No: (P126661) 3. Project Implementing Agency: Southern Africa Power Pool (SAPP) 4. Bank’s approval Date of the Procurement Plan: September 8, 2014 5. Date of General Procurement Notice: N/A 6. Period covered by this procurement plan: September 22, 2014 – March 22, 2016. This Procurement Plan covers a period of 18 months, including the period of implementation of the recently approved project preparation advance (PPA) and beyond. The Plan details the selected procurement packages that could be identified for this period, and notably those to be financed in the next few months under the PPA, as well as the related selection methods and Bank’s review obligations. The complete set of procurement packages will be identified when specific regional energy projects are selected for support and the needed procurement processes are better understood. The Plan will be updated accordingly and at least once a year throughout the life of the Project. I. Goods and Works and Non-Consulting Services 7. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Thresholds for Procurement Methods and Prior Review – Goods, Works and Non Consultant Services Expenditure Contract Value Contracts Subject to Category (Threshold) Procurement Prior Review USD Method Goods and Non <100,000 (other not m/vehicles) Shopping None Consultant <200,000(Motor Vehicles only) Shopping None Services All value Direct Contracting All Contracts UNOPs None NOTE: No Civil Works will be funded under the project 8. Prequalification. N/A 9. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines): N/A 10. Reference to (if any) Project Operational/Procurement Manual: SAPP Procurement Procedures Manual – March 2013 Version. The Procurement Procedure Manual currently in use by the SAPP (SAPP Procurement Procedures Manual) will be updated and strengthened. Once positively reviewed by the Bank and provided that it is found in conformity with the provisions of Paragraph 1.2 General Consideration and paragraph 1.4 General considerations as provided under the Banks Guidelines Procurement of Goods, Works and Non Consultant Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers and in the case of Goods, works and Non Consulting Services and Guidelines Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers both dated January 2011, the Manual will define the key procurement arrangements under the project and the preparation advance and notably those related to non-ICB procurement and selection of consultants. 11. Any Other Special Procurement Arrangements None 1 12. Procurement Packages with Methods and Time Schedule Procurement of Goods and Non-Consultant Services Estimated Expected Preq Prior or Expect Bid Plan/ Amount Proc Domestic Contract Description Ref No (yes / Post Opening Comments Actual in Method Preference Signature no) Review Date US $ Date GOODS Requirements will be quoted for and Computers, Plan 28,000 Shopping No No Post Sep 22, 2014 Oct 6, 2014 contracts awarded in separate lots as printers and SAPP/G/01/2014 computers, printers and software software Actual Plan 20,000 Shopping No No Post Sep 22, 2014 Oct 6, 2014 Office Furniture SAPP/G/02/2014 Actual Office Supplies / Plan 4,000 Shopping No No Post Sep 22, 2014 Oct 6, 2014 SAPP/NCS/01/2014 Utilities Actual Subtotal 52,000 NON-CONSULTANT SERVICES Plan 15,000 Office Rent SAPP/NCS/01/2014 Actual Travel costs / Car Plan 28,000 SAPP/NCS/02/2014 hire Actual Sub Total Non-Consultant Services 43,000 II. Selection of Consultants 13. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Thresholds for Consultants Selection Methods and Prior Review Contract Value Threshold Contracts Subject to Prior Review Expenditure Category Procurement Method (US$) (US$ millions) 1. Consulting Services QCBS, QBS >=200,000 All Contracts Firms CQS LCS, FBS <200,000 As in Procurement Plan SSS All values All Contracts Competitive Selection >=100,000 All Contracts 2. Individual Consultants IC Single Source Selection All Values All contracts NOTE: Contracts selected on basis of CQS, LCS and FBS may not exceed cost estimate of US$200,000 equivalent. 14. Terms of Reference (TOR): TOR for all consulting assignments (firms and individual consultants) irrespective of selection method or value will be subject to prior review by the Bank. 2 15. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. For engineering assignments estimated up to and below US$300,000 the short lists may comprise exclusively national firms 16. Any Other Special Selection Arrangements: None 17. Consulting Assignments with Selection Methods and Time 1 2 3 4 5 6 7 Expected proposal Comments/contract Selection Estimated Prior / Ref. No. Description Plan/Actual submission/ delivery or closing Method Cost in US$ Post Review opening Date date Project Acceleration Team Plan 30,000 Post Oct 20, 2014 Nov 3, 2015 SAPP/C/01/2014 Financial Management Specialist IC Actual Plan 30,000 Post Oct 20, 2014 Nov 3, 2015 SAPP/C/02/2014 Procurement Specialist IC Actual Plan 95,000 Post Oct 6, 2014 Oct 20, 2015 SAPP/C/03/2014 Project Coordinator IC Actual Plan 30,000 Post Nov 10, 2015 Nov 24, 2015 SAPP/C/04/2014 Environmental / Safeguards Specialist IC Actual Plan 10,000 Post Nov 10, 2014 Nov 24, 2015 SAPP/C/05/2014 Administrative Assistant IC Actual Subtotal 195,000 Studies Plan 190,000 Prior Nov 17, 2014 Jun 8, 2015 SAPP/C/07/2014 ESMF Consultant QCBS Actual Plan 150,000 Post Oct 13, 2014 Feb 3, 2016 SAPP/C/08/2014 Consultant to Update the SAPP Pool Plan CQS Actual Consultant to prepare the renewable Energy and Cloud Plan 180,000 Post Oct 20, 2014 Dec 10, 2015 SAPP/C/09/2014 mapping and Renewable Energy Integration Impact CQS Actual Assessment Analysis Consultant for the preparation of Regional Study Plan 170,000 Post Oct 20, 2014 May 10, 2015 SAPP/C/10/2014 Supporting Identification of Priority Regional Energy CQS Actual Projects Sub Total Studies 690,000 Total Consulting Services Assignments 885,000 18. Training ,workshops and consultations Estimated Expected Training/ Ref. No. Training, workshop and study tours Estimated Cost (US$) Duration workshop Date SAPP/CB &T/01/2014 Capacity building/Training for FM 10,000 TBA SAPP/CB &T/01/20141 Capacity building/Training for Procurement 10,000 TBA Sub Total Training , Workshops and Capacity Building 20,000 3 Notes: 1. Training and capacity Building: SAPP will identify the total cost of required training and prepare and submit to the Bank, for its prior review, a detailed training program. The training program will, inter alia, identify: (i) the training envisaged; (ii) the justification for the training, how it will lead to effective performance and implementation of the project (iii) the personnel to be trained; (iv) the selection methods of institutions or individuals conducting such training; (v) the institutions which will conduct training, if already selected; (vi) the duration of proposed training; and (vii) the cost estimate or specified cost of the training. Preparation and submission of a report, including to the Bank by the trainee upon completion of training would be mandatory. 2. Operating costs: For this project, the Bank has agreed with SAPP that the procurement methods for works, goods and non- consulting services as described in the Procurement Guidelines do not have to be followed for payments made for operating costs arising from the implementation of the project. Instead, the Bank has assessed SAPP’s own administrative procedures for these expenditures (during appraisal) and agrees that these procedures are adequate for procuring items for operating costs. The operating costs means the incremental expenses incurred by the Recipient on account of the activities, consisting of reasonable expenditures for travel cost, per diem for staff, office supplies, vehicle operation and maintenance, communication and insurance costs, banking charges, rental expenses, office and office equipment maintenance, utilities, document duplication/printing and consumables, except for salaries of the civil servants of the borrower country. These items will be procured using the implementing agency’s administrative procedures, which have been reviewed and found acceptable to the Bank. Contracts for these items should not be included in the procurement plan. 4 PROCUREMENT Africa : AFR RI-SAPP-Program for Accelerating Regional Energy/Transformational Projects PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2017-08-25 2019-10-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P126661 GPN Date: Project Name: AFR RI-SAPP-Program for Accelerating Regional Energy/Transformational Projects Loan / Credit No: IDA / H9890 Executing Agency(ies): Southern African Power Pool WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-34802-NC-DIR / ESMF Report translation IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 63,000.00 0.00 Canceled 2017-11-06 2017-11-11 2017-12-16 2018-06-14 and Printing ZW-SAPP-50450-NC-RFP / Open - Single Stage - One SAPP Transmission Grid IDA / H9890 Analytical support to SAPP Post Request for Bids 90,000.00 0.00 Canceled 2018-03-11 2018-04-12 2018-05-24 2018-06-23 2018-07-28 2019-01-24 International Envelope Maps Development ZW-SAPP-46472-NC-RFQ / Under Study Visit to the USA by Request for Single Stage - One IDA / H9890 Analytical support to SAPP Post Limited 90,000.00 0.00 Implementati 2019-02-18 2019-04-15 2019-10-12 the Environmental Sub- Quotations Envelope on Committee (ESC) ZW-SAPP-46471-NC-RFQ / STUDY TOUR BY SAPP Request for Single Stage - One TRANSMISION PRICING IDA / H9890 Analytical support to SAPP Post Limited 90,000.00 70,505.00 Signed 2019-02-18 2019-04-15 2019-10-12 Quotations Envelope TASK TEAM MEMBERS TO EUROPE AND INDIA ZW-SAPP-46468-NC-RFQ / STUDY TOUR BY SAPP OPERATING SUB- Request for Single Stage - One COMMITTEE MEMBERS IDA / H9890 Analytical support to SAPP Post Limited 90,000.00 0.00 Canceled 2019-02-15 2019-04-12 2019-10-09 Quotations Envelope TO POWER POOLS, NERC AND FERC IN THE UNITED STATES ZW-SAPP-73994-NC-DIR / SAPP Transmission Grid IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 100,000.00 71,127.64 Signed 2018-08-27 2018-09-01 2018-10-06 2019-04-04 Maps Development Page 1 ZW-SAPP-46474-NC-RFQ / Study Tour to Europe for Request for Single Stage - One IDA / H9890 Analytical support to SAPP Post Limited 90,000.00 0.00 Canceled 2019-02-18 2019-04-15 2019-10-12 the SAPP Executive Quotations Envelope Committee CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-25547-CS-QCBS / Quality And Cost- Open - EAPP SAPP Interconnection IDA / H9890 Project Preparation Funds Prior 500,000.00 829,359.44 Signed 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2018-08-21 Based Selection International Impact Studies Consultant ZW-SAPP-25548-CS-QCBS / Quality And Cost- Open - Luapula Environmental IDA / H9890 Project Preparation Funds Prior 200,000.00 381,187.30 Signed 2017-08-21 2017-08-21 2017-09-05 2017-10-03 2017-11-02 2017-12-07 2018-01-11 2019-01-11 Based Selection International Consultant ZW-SAPP-25549-CS-QCBS / Quality And Cost- Open - IDA / H9890 Analytical support to SAPP Prior 50,000.00 10,622.34 Signed 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-22 2017-08-23 2017-09-27 2018-09-27 Internal Auditors Based Selection International ZW-SAPP-28082-CS-QCBS / Quality And Cost- Open - Renewables energy IDA / H9890 Analytical support to SAPP Prior 350,000.00 0.00 Canceled 2017-09-11 2017-10-02 2017-11-15 2017-12-13 2018-01-12 2018-02-16 2018-03-23 2019-03-23 Based Selection International Integration Impact Study ZW-SAPP-28091-CS-QCBS / Produce roadmap for the Quality And Cost- Open - IDA / H9890 Analytical support to SAPP Prior 500,000.00 350,646.75 Signed 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2019-04-13 creation of the fund to Based Selection International remove congestion ZW-SAPP-36767-CS-QCBS / Quality And Cost- Open - IDA / H9890 Analytical support to SAPP Prior 1,006,000.00 1,006,000.00 Signed 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2017-11-17 2018-11-17 SAPP Pool Plan Based Selection International ZW-SAPP-47109-CS-QCBS / To Assess the Impact of Renewable Energy Quality And Cost- Open - IDA / H9890 Analytical support to SAPP Prior 175,000.00 459,604.59 Signed 2018-02-05 2018-02-26 2018-04-11 2018-05-09 2018-06-08 2018-07-13 2018-08-17 2018-12-15 Technologies on the Based Selection International Operations in the Southern African Power Pool: Part 1 ZW-SAPP-47110-CS-QCBS / To Assess the Impact of Renewable Energy Quality And Cost- Open - Under IDA / H9890 Analytical support to SAPP Prior 175,000.00 0.00 2018-02-26 2018-03-19 2018-05-02 2018-05-30 2018-06-29 2018-08-03 2018-09-07 2019-09-07 Technologies on the Based Selection International Implementation Operations in the Southern African Power Pool Part 2 ZW-SAPP-28097-CS-QCBS / Quality And Cost- Open - Under Develop Load forecast IDA / H9890 Analytical support to SAPP Prior 350,000.00 0.00 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2020-05-16 Based Selection International Implementation methodology for SAPP ZW-SAPP-48247-CS-QCBS / Quality And Cost- Open - Pending Mozambique Malawi IDA / H9890 Project Preparation Funds Prior 200,000.00 0.00 2019-01-01 2019-03-09 2019-04-22 2019-05-20 2019-06-19 2019-07-24 2019-08-28 2020-08-27 Based Selection International Implementation Regional Interconnector Project ZW-SAPP-28086-CS-CQS / Consultant Develop and operationalize Open - Pending IDA / H9890 Analytical support to SAPP Post Qualification 180,000.00 0.00 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 long term market International Implementation Selection surveillance in SAPP ZW-SAPP-28099-CS-QBS / Quality Based Open - Pending Transmission Pricing model IDA / H9890 Analytical support to SAPP Post 180,000.00 0.00 2019-05-01 2019-05-22 2019-07-05 2019-08-02 2019-09-01 2019-10-01 2019-11-05 2020-11-04 Selection International Implementation validation and wheeling Page 2 ZW-SAPP-28084-CS-QCBS / Quality And Cost- Open - Develop and implement a IDA / H9890 Analytical support to SAPP Post 800,000.00 716,100.00 Signed 2019-03-04 2019-03-25 2019-05-08 2019-06-05 2019-07-05 2019-08-09 2019-09-13 2020-09-12 Based Selection International Balancing Market for SAPP ZW-SAPP-28096-CS-QCBS / Preparatory work for Quality And Cost- Open - Pending IDA / H9890 Analytical support to SAPP Post 200,000.00 0.00 2019-06-03 2019-06-24 2019-08-07 2019-09-04 2019-10-04 2019-11-08 2019-12-13 2020-12-12 Business Opportunities on Based Selection International Implementation SAPP MTP ZW-SAPP-118444-CS-QCBS Quality And Cost- Open - Under / Zambia-Tanzania-Kenya IDA / H9890 Project Preparation Funds Post 1,500,000.00 0.00 2019-06-18 2019-07-09 2019-08-22 2019-09-19 2019-10-19 2019-11-23 2019-12-28 2020-12-27 Based Selection International Implementation (ZTK) Interconnector INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-30314-CS-INDV / Individual Setting up the Project To extend Environmental IDA / H9890 Prior Consultant Direct 100,000.00 136,236.42 Signed 2017-09-27 2017-09-28 2017-09-28 2017-11-02 2018-05-01 Acceleration Team advisors contract Selection ZW-SAPP-43423-CS-INDV / Individual Setting up the Project To extend the Senior IDA / H9890 Prior Consultant Direct 150,000.00 0.08 Signed 2018-01-12 2018-01-12 2018-01-15 2018-02-06 2018-08-05 Acceleration Team Transaction Advisor Contract Selection ZW-SAPP-43426-CS-INDV / Individual Setting up the Project To extend the Transaction IDA / H9890 Prior Consultant Direct 150,000.00 160,153.09 Signed 2018-01-12 2018-01-12 2018-01-15 2018-02-05 2018-08-04 Acceleration Team Advisor Contract Selection ZW-SAPP-43430-CS-INDV / Individual Setting up the Project To extend the Office IDA / H9890 Prior Consultant Direct 30,000.00 26,887.06 Signed 2018-01-12 2018-01-12 2018-01-15 2018-02-05 2018-08-04 Acceleration Team Administrator Coctract Selection ZW-SAPP-43437-CS-INDV / Mozambique Malawi Individual Regional Interconnector IDA / H9890 Analytical support to SAPP Post Consultant Limited 50,000.00 45,478.87 Signed 2018-01-12 2018-01-17 2018-02-07 2018-03-14 2018-09-10 Project, Review of Power Selection Pool Commercial Agreements ZW-SAPP-45217-CS-CDS / Updating and finalising the Environmental and Social IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 100,000.00 97,985.25 Signed 2018-01-26 2018-02-05 2018-04-11 2018-10-08 Management Framework (ESMF) ZW-SAPP-49291-CS-CDS / SAPP Pool Plan IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 100,000.00 300,000.00 Signed 2018-02-19 2018-03-01 2018-05-05 2018-11-01 Dissemination ZW-SAPP-50458-CS-INDV / Individual Individual Consultant for IDA / H9890 Analytical support to SAPP Post Consultant Limited 50,000.00 0.00 Canceled 2018-02-26 2018-03-03 2018-03-24 2018-04-28 2018-10-25 SAPP EXCO Workshop Selection Individual ZW-SAPP-54436-CS-INDV / Setting up the Project IDA / H9890 Post Consultant Open 35,000.00 17,300.41 Signed 2018-03-19 2018-05-07 2018-05-28 2018-07-02 2018-12-29 Office Administrator Acceleration Team Selection Page 3 ZW-SAPP-60299-CS-CDS / CONSULTING ASSIGNMENT TO SUPPORT TWINNING IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 100,000.00 50,000.00 Signed 2018-05-01 2018-05-11 2018-07-15 2019-01-11 ARRANGEMENT BETWEEN SAPP AND ENTSO-E TO BOLSTER SAPP CAPACITY Individual ZW-SAPP-68634-CS-INDV / Setting up the Project IDA / H9890 Prior Consultant Direct 100,000.00 127,072.47 Signed 2018-07-16 2018-07-26 2018-08-16 2018-09-20 2019-03-19 Procurement Specialist Acceleration Team Selection Individual ZW-SAPP-81270-CS-INDV / Setting up the Project IDA / H9890 Post Consultant Limited 35,000.00 11,883.58 Signed 2018-10-14 2018-10-19 2018-11-09 2018-12-14 2019-06-12 Office Aministrator Acceleration Team Selection Individual ZW-SAPP-81938-CS-INDV / Setting up the Project IDA / H9890 Post Consultant Limited 46,000.00 25,126.74 Signed 2018-10-22 2018-10-27 2018-11-17 2018-12-22 2019-06-20 Finance Administrator Acceleration Team Selection Individual ZW-SAPP-84114-CS-INDV / Setting up the Project Under IDA / H9890 Prior Consultant Open 408,000.00 0.00 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2021-03-07 Chief Transactions Advisor Acceleration Team Implementation Selection Individual ZW-SAPP-84115-CS-INDV / Setting up the Project Under IDA / H9890 Prior Consultant Open 360,000.00 0.00 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2021-03-07 Project Management Advisor Acceleration Team Implementation Selection ZW-SAPP-84129-CS-CDS / Communication Advisor for IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 50,000.00 25,700.00 Signed 2018-10-30 2018-11-05 2018-11-13 2018-12-13 the Pool Plan Dissemination Workshop ZW-SAPP-46476-CS-INDV / CAPACITY BUILDING Individual ACTIVITIES FOR THE IDA / H9890 Analytical support to SAPP Post Consultant Limited 100,000.00 0.00 Canceled 2018-12-03 2019-03-05 2019-03-26 2019-04-30 2019-10-27 SAPP QUALITY OF Selection SUPPLY WORKING GROUP Individual ZW-SAPP-84128-CS-INDV / Setting up the Project IDA / H9890 Post Consultant Open 216,000.00 0.00 Under Review 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2022-06-29 Procurement Specialist Acceleration Team Selection ZW-SAPP-94431-CS-CDS / Zambia Tanzania Environmental and Social IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 200,000.00 398,943.06 Signed 2019-02-04 2019-02-14 2019-04-20 2019-10-17 Impact Assessment (ESIA) Update ZW-SAPP-105363-CS-CDS / Review of the SAPP IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 10,000.00 3,208.45 Signed 2019-03-25 2019-04-04 2019-06-08 2019-12-05 transmission pricing code Individual ZW-SAPP-84118-CS-INDV / Setting up the Project IDA / H9890 Post Consultant Open 360,000.00 0.00 Under Review 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2022-08-31 Project Coordinator Acceleration Team Selection Individual ZW-SAPP-84123-CS-INDV / Setting up the Project IDA / H9890 Post Consultant Open 324,000.00 0.00 Under Review 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2022-08-31 Project Manager Acceleration Team Selection ZW-SAPP-84124-CS-INDV / Individual Setting up the Project Environmental and Social IDA / H9890 Post Consultant Open 252,000.00 0.00 Under Review 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2022-08-31 Acceleration Team Development Specialist Selection Page 4 ZW-SAPP-119018-CS-CDS / Under Mozambique Zambia IDA / H9890 Project Preparation Funds Prior Direct Selection 200,000.00 0.00 2019-06-23 2019-06-23 2019-06-23 2019-06-23 Implementation Geotechnical Investigations ZW-SAPP-119021-CS-CDS / Mozambique Zambia Under Technical Project deviation IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 200,000.00 0.00 2019-06-23 2019-07-03 2019-09-06 2020-03-04 Implementation of the transmission line in Zambia ZW-SAPP-119023-CS-CDS / Mozambique Zambia Under Environmental deviation of IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 200,000.00 0.00 2019-06-23 2019-07-03 2019-09-06 2020-03-04 Implementation the transmission line in Zambia Individual ZW-SAPP-119027-CS-INDV / Under IDA / H9890 Analytical support to SAPP Post Consultant Open 200,000.00 0.00 2019-06-17 2019-08-05 2019-08-26 2019-09-30 2020-03-28 Communication Advisor Implementation Selection Individual ZW-SAPP-136442-CS-INDV / Setting up the Project Pending IDA / H9890 Post Consultant Open 75,000.00 0.00 2019-10-13 2019-12-01 2019-12-22 2020-01-26 2020-07-24 Accounts Officer Acceleration Team Implementation Selection Page 5