P113971- MADAGASCAR INTEGRATED GROWTH POLES AND CORRIDORS PROJECT (IDA 5564MG) Summarized Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: Original: April 2015 - Revised January 2016 2. Date of General Procurement Notice: 09 June 2015 3. Period covered by this procurement plan: January 2017 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Type of Procurement Prior Review Threshold Comments US$ 1. Works (including Turnkey, supply & >US$ 15,000,000 All Installation of Plant and equipment and PPP) 2. Goods, Information Technology and >US$ 4,000,000 All non-consulting Services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness Review by Estimated Domestic Ref. Bank Description Cost Packages Preference Comments No. (Prior / US$ million (yes/no) Post) Summary of the NCB (Works) 2,50 1 No Post Travaux de construction d’un réservoir d’eau et pose de conduites 1-T-22 2,50 1 dans la ville de Toliara – Région Atsimo Andrefana Summary of the NCB (Works) 0,85 3 No Post Travaux d'aménagement du Tsingy 2-T-23 0,50 1 Rouge à Diana Travaux d'aménagement de la Mer 3-T-23 0,15 1 d'Emeraude à Diana Travaux de réhabilitation de bâtiment 4-T-24 pour le centre de contrôle du cacao à 0,20 1 Ambanja Summary of the NCB (goods) 0,25 3 No Post Acquisition de matériels et équipements pour la mise en place de 1-F-24 culture de stevia pour 20 ha pilotes 0,25 3 (achats multiples: kits pompe d’irrigation solaire, plants) Summary of the Shopping (Works) 0,83 22 No Post Review by Estimated Domestic Ref. Bank Description Cost Packages Preference Comments No. (Prior / US$ million (yes/no) Post) Travaux de renforcement, sécurisation 5-T-21 et protection des guichets uniques de 0,02 1 Diégo Travaux de renforcement, sécurisation 6-T-21 et protection des guichets uniques de 0,02 1 Ambanja Travaux de réhabilitation des bureaux 7-T-21 de 13 communes (Diana-Atsimo 0,22 4 Andrefana-Anosy) (vague 3) Travaux de réhabilitation des bureaux 8-T-21 de 22 communes (Diana-Atsimo 0,30 11 Andrefana-Anosy) (vague 4 et fin) Travaux d'assainissement et d'embellissement des 3 communes 9-T-21 0,18 3 pilotes Anakao, Belalanda/Mangily, Ramena (pôles touristiques) Petits travaux d'embellissement 10-T-23 touristique des villes de Tuléar et de 0,10 2 Diégo Summary of the Shopping (goods) 0,87 49 No Post Fournitures et Equipements des 2-F-21 Régions et STD pour opérationnaliser 0,02 1 les pôles SIG SITEF Fourniture de matériels et d'équipements dans le cadre de l'assainissement et l'embellissement de 3-F-21 0,10 3 3 communes touristiques pilotes (Anakao, Belalanda/Mangily, Ramena) Fourniture d'équipements et matériels divers (mobiliers de bureau, 4-F-23 bureautiques, informatiques, outils 0,10 10 d'animation technologique, équipements et accessoires divers…) Achat d'équipement et matériels pour 5-F-24 l'holothuriculture (enclos, tour de guet, 0,23 5 aire de cuisson) Aquisition d'équipements pour le 6-F-24 0,05 1 centre de contrôle de cacao 2 ème vague d'achat d'équipements dans le cadre du renforcement des 7-F-24 capacités techniques des préparateurs 0,07 3 de cacao (bacs de fermentation, aires de séchage, etc) Acquisition de semences de qualité de 8-F-24 0,01 1 pois de cap Acquisition de matériels, mobiliers, matériels informatiques, équipements 9-F-1 et accessoires pour les centres 0,03 3 d'affaires/CCI dans les régions et le Ministère de la Justice Acquisition de matériels, équipements et fournitures pour la mise en place du 10-F-23 centre d'information et de 0,01 2 documentation pour les guides dans les deux régions Acquisition de matériels, équipements 11-F-23 et fournitures pour les guides agréés 0,02 4 (gilets etc…) Review by Estimated Domestic Ref. Bank Description Cost Packages Preference Comments No. (Prior / US$ million (yes/no) Post) Acquisition de matériels, équipements 12-F-23 et fournitures en appui à la formation 0,05 4 technique des artisans Fourniture d'équipements et production de supports de communication dans le cadre de la 13-F-1 0,03 5 participation à des évènements nationaux et internationaux (achats multiples) Achat d'équipements et de matériels pour l'algoculture (corde, piquets, 14-F-24 0,17 7 flotteurs, table de séchage, barque, fournitures pour magasin de stockage) Summary of the Non-Consultant 0,03 3 No Post Services (goods) Fourniture de services pour la saisie et le traitement des données fiscales des 15-F-21 0,01 1 communes rurales dans la Région Diana Fourniture de services pour la saisie et le traitement des données fiscales des 16-F-21 0,01 1 communes rurales dans la Région Atsimo Andrefana Fourniture de services pour la saisie et le traitement des données fiscales des 17-F-21 0,01 1 communes rurales dans la Région Anosy III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of procurement Prior Review Threshold Comments 1. Firms > US$ 2,000,000 Whether it is competitive or direct selection 2. Individual >US$ 400,000 Whether it is competitive or direct selection 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule Review by Estimated Cost Ref. No. Description of Assignment Packages Bank Comments US$ million (Prior / Post) Summary of number of contracts that will be let 0,45 1 Post under QCBS 1-C-1 Etude de faisabilité du Park Ehoala 0,45 1 Summary of number of contracts that will be let 0,15 1 Post under CQS Assistance Technique pour le développement de 2-C-23 0,15 1 routes aériennes Review by Estimated Cost Ref. No. Description of Assignment Packages Bank Comments US$ million (Prior / Post) Summary of number of contracts that will be let - - under Individual Summary of number of contracts that will be let 0,28 10 Post under SSS Renforcement de capacités du core team du Projet dans divers thèmes: infrastructures, gestion 3-C-3 de projet, administration, comptabilité, passation 0,04 7 des marchés, tourisme, agribusiness et chaînes de valeur... 4-C-23 Formation des guides touristiques en secourisme 0,02 1 Appui complémentaire à la clôture du partenariat 5-C-23 stratégique pour AIR MADAGASCAR 0,20 1 (transaction advisor) Renouvellement du contrat du Spécialiste Sénior 6-C-3 0,02 1 en Passation des Marchés Summary of number of contracts that will be let 0,05 1 Post under MOU Mise en œuvre du plan semencier avec le MAEP 7-C-24 0,05 1 (frais d'activités) Summary of number of contracts that will be let 1,18 9 Post under QCBS Etude de faisabilité d'un site d'enfouissement de 8-C-22 0,08 1 déchets à Diégo Etudes de faisabilité économiques et techniques 9-C-22 de pistes rurales et touristiques dans les régions 0,05 1 Diana et Atsimo Andrefana Etudes de faisabilité économiques et techniques 10-C-22 de réhabilitations d'ouvrages hydrauliques 0,05 1 agricoles dans la région Atsimo Andrefana Etude APD de la réhabilitation de la piste RN7 11-C-22 vers Saint Augustin et de la piste du cacao du 0,12 1 Haut Sambirano Etude APD pour la réhabilitation d'un total de 24 12-C-22 km de Voiries urbaines à Tuléar, Diégo et 0,30 1 Ambanja ainsi que la route de Ramena Etude de faisabilité et Master Plan aéroports de 13-C-23 Diégo et Tuléar avec ADEMA (reformulé en 0,45 1 préparation PIC2-2) Etude sur le changement d'hotes de certains 14-C-24 0,03 1 parasites du cotonnier Recrutement de consultant pour les mesures 15-C-24 d'adaptation au changement climatique pour les 0,03 1 filières agricoles Assistance technique pour l'élaboration de la stratégie d'appui au renforcement de capacités du 16-C-23 0,07 1 personnel touristique dans les 2 régions) (dans le cadre de la préparation du PIC 2-2) Summary of number of contracts that will be let 0,13 2 Post under CQS Formation en communication de crise auprès du 17-C-23 0,10 1 Conseil du Tourisme Consultance pour le développement d'outils 18-C-23 d'animation technologique dans les sites 0,03 1 nouvellement aménagés Summary of number of contracts that will be let 1,43 131 Post under Individual Consultant individuel en appui à l'équipe 19-C-3 0,01 1 Passation des Marchés Review by Estimated Cost Ref. No. Description of Assignment Packages Bank Comments US$ million (Prior / Post) Consultant pour l'évaluation d'impact de la 20-C-3 0,05 1 première phase du PIC2 Consultant pour le diagnostic statistique des 21-C-3 entreprises et des emplois dans les Régions 0,02 1 d'intervention du PIC 22-C-1 Recrutement d'un Assistant de Programme 0,02 1 Recrutement de formateur sur " la gestion des 23-C-21 archives, technique de communication, technique 0,01 1 d'accueil" Recrutement de formateur sur le SIG, 24-C-21 0,01 1 bureautique Recrutement de formateur sur la notion de voirie 25-C-21 /règlementation sur 0,01 1 l'Habitat/hygiène/propreté/assainissement Recrutement d'un CI pour l'Etude-Bilan des 26-C-21 expériences pilotes "Marché contrôlé cacao" dans 0,01 1 la Zone Sambirano Recrutement d'un assistant technique en appui à 27-C-21 la Région Atsimo Andrefana (profil SIGiste, 0,02 1 gestion base des données, coordination des PTF) Recrutement d'un CI pour la formation des AT 28-C-21 sur le modèle alliant la gouvernance et le 0,02 1 développement économique local Recrutement d'un CI pour l'étude et la mise en 29-C-21 œuvre des fiscalités touristiques et les taxations 0,03 1 liées aux filières soutenues Etude de la Remise à niveau et de renforcement 30-C-22 du système d'approvisionnement en Eau Potable 0,10 1 de la ville d'Ambanja Assistance technique pour l'amélioration de la performance commerciale et le développement 31-C-23 0,06 1 des produits dérivés dans les parcs MNP (spécialiste merchandising) Recrutement d'un Assistant technique pour la 32-C-24 gestion d’une pépinière moderne de cacao - 0,00 1 station FOFIFA à Ambanja Recrutement d'un Assistant technique auprès du FOFIFA pour la gestion financière, 33-C-24 0,01 1 administrative et comptable d’un programme de production et de vente de plants de cacao Assistance technique de niveau international pour 34-C-24 accompagner le projet à l'identification d'autres 0,06 1 filières à appuyer dans le cadre du PIC 2.2 Consultant individuel de niveau international 35-C-24 pour une assistance technique au FOFIFA sur la 0,06 1 production de plants de cacao certifiés Recrutement d'un consultant individuel national 36-C-24 pour le Secrétariat Exécutif du Conseil National 0,01 1 du Cacao Etudes, contrôle et surveillance des travaux de 37-C-24 réhabilitation de bâtiments pour le centre de 0,03 1 contrôle du cacao à Ambanja Assistance Technique pour la mise en place d'un 38-C-24 projet pilote sur la production de Patchouli et sur 0,03 1 les filières huiles essentielles Etude de faisabilité pour la mise en place d’une 39-C-24 unité de conditionnement et traitement de produit 0,05 1 horticole (baies roses et fruits) pour FD Recrutement de techniciens d'encadrement des 40-C-24 0,05 5 producteurs de baie rose et filières associées Review by Estimated Cost Ref. No. Description of Assignment Packages Bank Comments US$ million (Prior / Post) Recrutement d'un assistant technique socio 41-C-24 organisateur pour les filières baie rose et 0,02 1 associées Étude agro-socio-économique des systèmes de production pour identifier des modèles 42-C-24 d’exploitation et incluant la promotion 0,05 1 d’entreprises rurales de travaux ou de services (préparation PIC2.2) Recrutement d'un Consultant pour le poste de 43-C-24 Secrétaire Exécutif du Conseil Interprofessionnel 0,02 1 du Coton Recrutement d'un assistant technique pour le 44-C-24 suivi technique du Conseil Interprofessionnel du 0,01 1 Coton Assistant technique de niveau international pour 45-C-24 0,05 1 la formation des formateurs en BCI (filière coton) Etude préalable sur l’accès à l’irrigation à travers des techniques innovantes (volet aménagement 46-C-24 0,01 1 hydro-agricole et exploitation des ressources souterraines) Assistance technique pour un projet pilote sur la 47-C-24 production Pois du Cap dans la Région Atsimo 0,03 1 Andrefana Assistance Technique pour un appui juridique à l'amélioration du cadre réglementaire des filières 48-C-24 0,03 1 complémentaires (aquaculture, huiles essentielles…) Recrutement de 26 techniciens d’encadrement en 49-C-24 0,08 26 algoculture villageoise Recrutement de 08 techniciens d’encadrement en 50-C-24 0,03 8 holothurie Recrutement de 11 socio organisateurs en 51-C-24 0,03 11 aquaculture villageoise Assistance technique pour la mise en œuvre du 52-C-1 programme d'accompagnement des PME dans les 0,08 1 trois régions (6 consultants nationaux) Recrutement de formateurs/experts pour la formation des professions judiciaires (magistrats, 53-C-1 avocats, arbitres, médiateurs), des professions du 0,10 6 chiffre (experts-comptables) ( 6 consultants internationaux) Recrutement de formateurs/experts nationaux pour la formation des professions judiciaires 54-C-1 (magistrats, avocats, arbitres, médiateurs), des 0,07 23 professions du chiffre (experts-comptables) ( 23 consultants nationaux) Assistance technique pour la formation et l'appui au renforcement de la coopération entre le 55-C-1 0,04 2 tribunal et le CAMM (02 consultants internationaux) Formateurs pour élaborer et mettre en œuvre un programme de formation (perfectionnement) pour 56-C-23 0,04 6 les guides agréés par le MinTour dans les deux régions (6 contrats) Formateurs pour le renforcement de capacités des gestionnaires de sites et des prestataires de 57-C-23 0,04 6 service dans les sites aménagés (Jardin de la Mer, Montagne des Français) (6 contrats) Review by Estimated Cost Ref. No. Description of Assignment Packages Bank Comments US$ million (Prior / Post) Assistance technique pour l'élaboration de la stratégie d'appui à l'artisanat dans les deux 58-C-23 régions (analyse filières, choix des dilières, 0,01 1 ciblage des bénéficiaires, plans d'actions,..) (consultant individiduel national) Assistance technique pour la formation technique 59-C-23 des artisans dans les filières sélectionnés 0,04 6 (plusieurs consultants nationaux) Recrutement d'un designer pour appuyer les 60-C-23 artisans dans le développement de produits pour 0,04 1 les touristes (consultant international) Summary of number of contracts that will be let 0,13 6 post under SSS Etude d'Identification et de mobilisation d'une 61-C-22 0,05 1 nouvelle source d'eau pour la ville de Diégo Renouvellement des contrats des 4 AT 62-C-24 0,07 4 Agribusiness dans les pôles Renouvellement du contrat de l'AT en gestion de 63-C-24 0,01 1 base des données et contrôle du Conseil Coton Summary of number of contracts that will be let 0,13 15 post under SSS or individual Renouvellement contrats des 2 AT gouvernance 64-C-21 locale urbaine Diana (si évaluation satisfaisante: 0,02 2 SSS, sinon SCI) Renouvellement contrats des 2 AT gouvernance 65-C-21 locale urbaine Atsimo Andrefana (si évaluation 0,02 2 satisfaisante: SSS, sinon SCI) Renouvellement contrat de l'AT gouvernance 66-C-21 locale urbaine Anosy (si évaluation satisfaisante: 0,01 1 SSS, sinon SCI) Renouvellement contrats des 4 AT OCAI Diana 67-C-21 0,02 4 (si évaluation satisfaisante: SSS, sinon SCI) Renouvellement contrats des 2 AT OCAI Anosy 68-C-21 0,01 2 (si évaluation satisfaisante: SSS, sinon SCI) Renouvellement contrats des 3 AT OCAI 69-C-21 Atsimo Andrefana (si évaluation satisfaisante: 0,01 3 SSS, sinon SCI) Renouvellement du contrat du Coordonnateur 70-C-31 Régional du PIC à Diana (si évaluation 0,04 1 satisfaisante: SSS, sinon SCI) IV. Training activities Review by Estimated Cost Ref. No. Description of Assignment Packages Bank Comments US$ million (Prior / Post) Formation du personnel clé du Projet en Fiduciaire (comptabilité, administration, 71 passation des marchés, audit), Infrastructures, 0,04 9 Post Gouvernance locale, Tourisme, Agribusiness, Gestion de Projet etc… V. List of tentative activities to be carried out in 2017 but for which confirmation will be made at a later stage: Review by Estimated Cost Ref. No. Description of Assignment Packages Bank Comments US$ million (Prior / Post) Review by Estimated Cost Ref. No. Description of Assignment Packages Bank Comments US$ million (Prior / Post) Summary of number of contracts that will be let 0 0 under QCBS Summary of number of contracts that will be let 0 0 under CQS Summary of number of contracts that will be let 0,025 2 under Individual Assistance technique pour la formation et l'appui au renforcement de la coopération entre le 0,025 2 Post tribunal et le CAMM (2 consultants internationaux) Summary of number of contracts that will be let 0,075 2 under SSS Assistance technique pour le suivi et la mise en 0,06 1 Post œuvre des réformes sur la justice commerciale Extension du contrat relatif au développement du 0,015 1 Post logiciel de la chaîne commerciale Summary of number of contracts that will be let 0 0 under SSS or individual PROCUREMENT Madagascar : Integrated Growth Poles and Corridor Project 2 PLAN General Information Country: Madagascar Bank’s Approval Date of the Original Procurement Plan: 2017-08-03 2019-07-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P113971 GPN Date: Project Name: Integrated Growth Poles and Corridor Project 2 Loan / Credit No: IDA / 55640 Executing Agency(ies): Integrated Growth Poles and Corridor Project 2 WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 5-T-21-PIC2-17 / Travaux de renforcement, sécurisation Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 10,122.23 Achevé 2017-08-07 2017-10-02 2018-03-31 et protection des guichets Envelope uniques de Diégo 6-T-21-PIC2-17 / Travaux de renforcement, sécurisation Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 8,943.27 Achevé 2017-08-07 2017-10-02 2018-03-31 et protection des guichets Envelope uniques de Ambanja 7 A-T-21-PIC2-17 / Travaux de réhabilitation des bureaux de 02 communes Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 47,548.73 Achevé 2017-07-29 2017-09-23 2018-03-22 Antanimena - Envelope Ambohimahavelon - Atsimo Andrefana (vague 3) 7 C-T-21-PIC2-17 / Travaux de réhabilitation des bureaux Single Stage - One de 02 communes IDA / 55640 A posteriori Demande de prix Limited 30,656.84 Signé 2017-07-29 2017-09-23 2018-03-22 Envelope Antafiambotry Ambalahonko DIANA (vague 3) 7 D-T-21-PIC2-17 / Travaux de réhabilitation des bureaux de 02 communes Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 43,178.89 Achevé 2017-07-29 2017-09-23 2018-03-22 Antsakoamanondro Envelope Ambohimena Diana (vague 3) 7 E-T-21-PIC2-17 / Travaux de réhabilitation des bureaux Single Stage - One de 02 communes Mantaly IDA / 55640 A posteriori Demande de prix Limited 57,004.49 Signé 2017-07-29 2017-09-23 2018-03-22 Envelope Antsohombondrona Diana (vague 3) 7 F - T-21-PIC2-17 / Travaux de réhabilitation Single Stage - One des bureaux de 02 IDA / 55640 A posteriori Demande de prix Limited 45,079.32 Signé 2017-07-29 2017-09-23 2018-03-22 Envelope communes Tanandava Sampona Anosy (vague 3) 11-T-1-PIC2-17 / Travaux Single Stage - One de réhabilitation des locaux IDA / 55640 A posteriori Demande de prix Limited 14,812.29 Achevé 2017-09-20 2017-11-15 2018-05-14 Envelope du centre d'affaires Diégo 2-T-23-PIC2-17  / Travaux Single Stage - One d'aménagement du Tsingy IDA / 55640 A posteriori Appel d'offres Open - National 553,028.98 Signé 2018-01-30 2018-02-04 2018-03-06 2018-04-05 2018-04-21 2018-12-17 Envelope Rouge à Diana Page 1 8-A-T-21-PIC2-17  / Travaux de réhabilitation Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 38,748.74 Signé 2017-12-05 2018-01-14 2018-05-14 des 02 bureaux communes Envelope région Anosy 8-B-T-21-PIC2-17  / Travaux de réhabilitation Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 32,904.60 Achevé 2017-12-05 2018-01-14 2018-05-14 des 02 bureaux communes Envelope Atsimo Andrefana 8-C-T-21-PIC2-17  / Travaux de réhabilitation Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 47,918.34 Achevé 2017-12-05 2018-01-14 2018-05-14 des bureaux communes Envelope Atsimo Andrefana 8-D-T-21-PIC2-17  / Single Stage - One Travaux de réhabilitation IDA / 55640 A posteriori Demande de prix Limited 41,635.34 Signé 2017-12-05 2018-01-14 2018-05-14 Envelope des bureaux communes DIANA 8-E-T-21-PIC2-17  / Single Stage - One Travaux de réhabilitation IDA / 55640 A posteriori Demande de prix Limited 22,658.82 Signé 2017-12-05 2018-01-14 2018-05-14 Envelope des bureaux communes (Anosy) 8-F-T-21-PIC2-17  / Single Stage - One Travaux de réhabilitation IDA / 55640 A posteriori Demande de prix Limited 40,175.33 Signé 2017-12-05 2018-01-14 2018-05-14 Envelope des bureaux communes (Anosy) 8-G-T-21-PIC2-17 / Travaux de réhabilitation des bureaux Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 47,140.59 Achevé 2017-12-05 2018-01-14 2018-05-14 communes (Atsimo Envelope Andrefana) 8-H-T-21-PIC2-17 / Travaux Single Stage - One de réhabilitation des bureaux IDA / 55640 A posteriori Demande de prix Limited 31,616.02 Signé 2017-12-05 2018-01-14 2018-05-14 Envelope communes (Diana) 8-I-T-21-PIC2-17 / Travaux Single Stage - One de réhabilitation des bureaux IDA / 55640 A posteriori Demande de prix Limited 39,158.28 Signé 2017-12-05 2018-01-14 2018-05-14 Envelope communes (Diana) 8-J-T-21-PIC2-17 / Travaux Single Stage - One de réhabilitation des bureaux IDA / 55640 A posteriori Demande de prix Limited 24,590.21 Signé 2017-12-05 2018-01-14 2018-05-14 Envelope communes (Diana) 8-K-T-21-PIC2-17 / Travaux Single Stage - One de réhabilitation des bureaux IDA / 55640 A posteriori Demande de prix Limited 56,891.69 Résilié 2017-12-05 2018-01-14 2018-05-14 Envelope communes (Diana) 10 A-T-23-PIC2-17 / Petits Single Stage - One travaux d'embellissement IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-02-27 2018-04-24 2018-08-22 Envelope touristique ville Tuléar 10 B-T-23-PIC2-17 / Petits Single Stage - One travaux d'embellissement IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-02-28 2018-04-25 2018-08-23 Envelope touristique ville de Diégo 9 B-T-21-PIC2-17 / Travaux d'assainissement et Single Stage - One d'embellissement communes IDA / 55640 A posteriori Demande de prix Limited 129,415.16 Signé 2018-03-27 2018-05-22 2018-11-18 Envelope pilotes Belalanda/Mangily (pôles touristiques) 9 C-T-21-PIC2-17 / Travaux d'assainissement et Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 99,400.73 Signé 2018-03-27 2018-05-22 2018-11-18 d'embellissement commune Envelope Ramena (pôle touristique) Page 2 8-L-T-21-PIC2-17  / Single Stage - One Travaux de réhabilitation IDA / 55640 A posteriori Demande de prix Limited 35,535.73 Achevé 2017-12-05 2018-01-14 2018-05-14 Envelope des bureaux communes (ANOSY) 8-M-T-21-PIC2-17  / Travaux de réhabilitation Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 16,649.14 Signé 2017-12-05 2018-01-14 2018-05-14 des bureaux communes Envelope (ANOSY) 8-N-T-21-PIC2-17  / Travaux de réhabilitation Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 50,522.39 Signé 2017-12-05 2018-01-14 2018-05-14 des bureaux communes Envelope (ANOSY) 10 C-T-23-PIC2-17 / Petits Single Stage - One travaux d'embellissement IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-04-29 2018-06-24 2018-10-22 Envelope touristique ville Diego 10 D-T-23-PIC2-17 / Petits Single Stage - One travaux d'embellissement IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-04-29 2018-06-24 2018-10-22 Envelope touristique ville Tuléar 4-T-24-PIC2-17 / Travaux de réhabilitation de bâtiment Single Stage - Two IDA / 55640 A posteriori Appel d'offres Open - National 0.00 Annulé 2017-09-20 2017-09-25 2017-11-06 2018-01-19 2018-02-23 2018-08-22 pour le centre de contrôle Envelope du cacao à Ambanja 04-T-24-PIC2-17 / Travaux de réhabilitation de bâtiment Single Stage - One IDA / 55640 A posteriori Appel d'offres Open - National 69,504.15 Achevé 2017-11-26 2017-12-01 2017-12-31 2018-01-30 2018-02-28 2018-06-28 pour le centre de contrôle Envelope du cacao à Ambanja 15-T-22-PIC2-17 / Travaux Single Stage - One de réhabilitation de voiries IDA / 55640 A posteriori Appel d'offres Open - National 1,240,840.96 Signé 2018-03-15 2018-03-22 2018-04-21 2018-05-06 2018-06-10 2018-09-08 Envelope urbaines de Diego 7 B-T-21-PIC2-17 / Travaux de réhabilitation des bureaux Single Stage - One de 02 communes Ankareara IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2017-07-29 2017-09-23 2018-03-22 Envelope Andranobory Anosy (vague 3) 7 G-T-21-PIC2-17 / Travaux de réhabilitation des bureaux Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2017-07-29 2017-09-23 2018-03-22 commune Amboasary Anosy Envelope (vague 3) 13-T-23-PIC2-17 / Travaux d'aménagement et de construction d'infrastructures Single Stage - One IDA / 55640 A posteriori Appel d'offres Open - National 0.00 Annulé 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 2019-02-16 de visite et de services Envelope touristiques - Montagne d'Ambre - Diégo. 14-T-23-PIC2-17 / Petits travaux d'amélioration des Single Stage - One infrastructures de visites IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-04-05 2018-05-31 2018-11-27 Envelope touristiques - Tsimanapetsotsa-Tuléar. 3-T-23-PIC2-17  / Travaux Single Stage - One d'aménagement de la Mer IDA / 55640 A posteriori Appel d'offres Open - National 0.00 Annulé 2018-02-28 2018-03-05 2018-04-04 2018-04-19 2018-04-29 2018-12-25 Envelope d'Emeraude à Diana Page 3 9 D-T-21-PIC2-18 / Travaux Single Stage - One d'appui à l'adduction d'eau IDA / 55640 A posteriori Demande de prix Limited 125,992.02 Signé 2018-11-04 2018-12-30 2019-06-28 Envelope potable commune Anakao 12 A-T-23-PIC2-18 / Petits travaux d'embellissement et Single Stage - One d'aménagement pour l'accueil IDA / 55640 A posteriori Appel d'offres Open - National 455,198.13 Signé 2018-10-30 2018-11-04 2018-12-16 2019-01-15 2019-02-19 2019-08-18 Envelope et visites touristiques - Nosy Ve -Tuléar 12-T-23-PIC2-17 / Petits travaux d'embellissement et Single Stage - One d'aménagement pour l'accueil IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-03-05 2018-04-30 2018-10-27 Envelope et visites touristiques - Nosy Ve -Tuléar. 01-T-22-PIC2-17 / Travaux de construction d’un réservoir d’eau et pose de Single Stage - One IDA / 55640 A posteriori Appel d'offres Open - National 2,573,750.86 Signé 2017-05-20 2017-05-24 2017-06-23 2017-07-13 2017-07-25 2018-03-22 conduites dans la ville de Envelope Toliara – région Sud-Ouest - Madagascar 9 A-T-21-PIC2-17 / Travaux Single Stage - One En cours d'embellissement commune IDA / 55640 A posteriori Demande de prix Limited 0.00 2018-11-16 2019-01-11 2019-04-11 Envelope d'exécution Anakao (pôle touristique) 9 E-T-21-PIC2-18 / Travaux Single Stage - One d'asssainissement de la IDA / 55640 A posteriori Appel d'offres Open - National 0.00 Annulé 2019-01-05 2019-01-10 2019-02-21 2019-03-23 2019-04-27 2019-10-24 Envelope Commune Anakao 222-T2 / Travaux de renforcement et de rehabilitation du systeme Open - Single Stage - One IDA / 55640 A priori Appel d'offres 4,936,676.87 Signé 2016-07-08 2016-07-29 2016-09-13 2016-10-04 2016-11-03 2017-12-28 d’alimentation en eau International Envelope potable de la ville de diego – region diana - madagascar 222-T1 / Travaux de renforcement et de rehabilitation du systeme Open - Single Stage - One d’alimentation en eau IDA / 55640 A priori Appel d'offres 3,194,107.43 Signé 2016-06-23 2016-07-12 2016-08-25 2016-09-23 2016-10-03 2017-09-28 International Envelope potable de la ville de toliara – region sud ouest - madagascar GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 8-F-24-PIC2-17 / Acquisition Single Stage - One de semences de qualité de IDA / 55640 A posteriori Demande de prix Limited 4,285.71 Achevé 2017-10-30 2017-12-25 2018-06-23 Envelope pois de cap 04-F-23-PIC2-17 / Fourniture d'équipements et matériels divers (mobiliers de bureau, bureautiques, Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 18,258.17 Achevé 2017-09-04 2017-10-30 2018-04-28 informatiques, outils Envelope d'animation technologique, équipements et accessoires divers...) Page 4 Passation de 18-F-3-PIC2-17 / Acquisition marchés auprès En attente IDA / 55640 A posteriori Direct 0.00 2017-08-06 2017-08-11 2017-09-15 2018-03-14 04 véhicules via UNOPS des agences de d'exécution l'ONU 2-F-21-PIC2-17  / Fournitures et Equipements Single Stage - One des Régions et STD pour IDA / 55640 A posteriori Demande de prix Limited 19,885.56 Achevé 2018-04-04 2018-05-10 2018-08-08 Envelope opérationnaliser les pôles SIG SITEF 3 B-F-21-PIC2-17 / Fourniture de matériels et d'équipements dans le cadre Single Stage - One En attente de l'assainissement et IDA / 55640 A posteriori Demande de prix Limited 0.00 2018-02-25 2018-04-22 2018-07-21 Envelope d'exécution l'embellissement de commune touristique pilote Belalanda/Mangily 3 C-F-21-PIC2-17 / Fourniture de matériels et d'équipements dans le cadre Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 10,116.44 Achevé 2018-04-15 2018-06-10 2018-09-08 de l'assainissement et Envelope l'embellissement de commune touristique pilote Ramena 01-F-24-PIC2-17 / Acquisition de matériels et équipements pour la mise en Single Stage - Two place de culture de stevia IDA / 55640 A posteriori Appel d'offres Open - National 0.00 Annulé 2017-08-23 2017-08-28 2017-10-09 2017-12-22 2018-01-26 2018-07-25 Envelope pour 20 ha pilotes (achats multiples: kits pompe d'irrigation solaire, plants) 6-F-24-PIC2-17 / Acquisition Single Stage - One d'équipements pour le centre IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2017-09-25 2017-11-20 2018-05-19 Envelope de contrôle de cacao 6 A-F-24-PIC2-17 / Aquisition d'équipements Single Stage - One informatiques pour le centre IDA / 55640 A posteriori Demande de prix Limited 2,868.14 Achevé 2018-01-29 2018-03-26 2018-06-24 Envelope de contrôle de cacao Ambanja 6 B-F-24-PIC2-17 / Aquisition d'équipements Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 1,765.59 Achevé 2018-02-16 2018-04-13 2018-06-12 mobilier pour le centre de Envelope contrôle de cacao Ambanja 7-F-24-PIC2-17 / achat d'équipements dans le cadre du renforcement des Single Stage - One capacités techniques des IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2017-10-03 2017-11-28 2018-05-27 Envelope préparateurs de cacao (bacs de fermentation, aires de séchage, etc) 7 A-F-24-PIC2-17 / Achat d'équipements dans le cadre du renforcement des Single Stage - One capacités techniques des IDA / 55640 A posteriori Demande de prix Limited 84,218.58 Signé 2018-02-18 2018-04-15 2018-10-12 Envelope préparateurs de cacao (Bacs de fermentation et aire de sechage) 7 B-F-24-PIC2-17 / Achat d'équipements dans le cadre du renforcement des Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 348.82 Résilié 2018-01-30 2018-03-27 2018-05-26 capacités techniques des Envelope préparateurs de cacao (divers équipements) Page 5 22-F-24-PIC2-17 / FOURNITURE DES EQUIPEMENTS AGRICOLES POUR LES Single Stage - One IDA / 55640 A posteriori Appel d'offres Open - National 118,450.08 Achevé 2017-12-20 2017-12-25 2018-01-24 2018-02-13 2018-02-23 2018-05-24 PRODUCTEURS DE COTON Envelope DANS LA REGION ATSIMO ANDREFANA (PULVERISATEUR, EPI) 19-B-F-24-PIC2-17 / Acquisition d'équipements et fournitures pour les filières Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 16,759.80 Achevé 2018-03-20 2018-05-04 2018-07-03 associées (patchoulli, miel, Envelope pois de cap, baie rose...) - Vague 2 19-C-F-24-PIC2-17 / Acquisition d'équipements et fournitures pour les filières Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 22,438.35 Achevé 2018-04-21 2018-05-21 2018-07-20 associées (patchoulli, miel, Envelope pois de cap, baie rose...) - Vague 3 19-D-F-24-PIC2-17 / Acquisition d'équipements et fournitures pour les filières Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-05-20 2018-06-20 2018-08-19 associées (patchoulli, miel, Envelope pois de cap, baie rose...) - Vague 4 19-E-F-24-PIC2-17 / Acquisition d'équipements et fournitures pour les filières Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-06-20 2018-07-20 2018-09-18 associées (patchoulli, miel, Envelope pois de cap, baie rose...) - Vague 5 5-F-24-PIC2-17 / Achat d'équipement et matériels Single Stage - One pour l'holothuriculture IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2017-08-01 2017-09-26 2018-03-25 Envelope (enclos, tour de guet, aire de cuisson) 19-A-F-24-PIC2-17 / Acquisition d'équipements et fournitures pour les filières Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 31,610.81 Signé 2018-02-20 2018-03-29 2018-05-28 associées (patchoulli, miel, Envelope pois de cap, baie rose...) - Vague 1 20-F-24-PIC2-17 / Acquisition de petits Single Stage - One équipements pour le contrôle IDA / 55640 A posteriori Demande de prix Limited 9,906.03 Signé 2018-04-20 2018-05-15 2018-11-11 Envelope de pesticide in situ à Atsimo Andrefana 23-F-23-PIC2-17 / Fourniture d'équipements Open - Single Stage - One IDA / 55640 A posteriori Appel d'offres 617,612.72 Signé 2018-05-30 2018-06-04 2018-07-04 2018-07-24 2018-08-14 2018-11-12 pour les aéroports de Tuléar International Envelope et Fort-Dauphin 21-F-21-PIC2-17 / Acquisition de petits Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 21,115.01 Achevé 2018-03-20 2018-05-15 2018-11-11 équipements pour la collecte Envelope des déchets dans les pôles Page 6 22-A-F-24-PIC2-17 / FOURNITURE DES EQUIPEMENTS AGRICOLES POUR LES Single Stage - One IDA / 55640 A posteriori Appel d'offres Open - National 54,613.44 Achevé 2018-02-21 2018-02-26 2018-04-02 2018-04-12 2018-05-11 2018-09-08 PRODUCTEURS DE COTON Envelope DANS LA REGION ATSIMO ANDREFANA (EPI) - RELANCE 26 A -F-1-PIC2-18 / Acquisition de matériels et Single Stage - One équipements informatiques IDA / 55640 A posteriori Demande de prix Limited 16,411.35 Achevé 2018-05-27 2018-06-16 2018-07-16 Envelope pour Confédération Tourisme et pour OCSIF 26 B -F-1-PIC2-18 / Acquisition de mobiliers de bureau , matériel de bureau Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 10,531.12 Achevé 2018-05-27 2018-06-16 2018-07-16 et bureautique pour Envelope Confédération Tourisme et pour OCSIF 14-F-24-PIC2-17 / Achat d'équipements et de matériels pour l'algoculture Single Stage - One (corde, piquets, flotteurs, IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2017-08-28 2017-10-23 2018-04-21 Envelope table de séchage, barque, fournitures pour magasin de stockage) 13 A -F-1-PIC2-17 / fourniture d'équipements et production de supports de communication dans le cadre Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2017-12-18 2018-02-12 2018-08-11 de la participation à des Envelope évènements nationaux et internationaux (achats multiples) 10-F-23 / Acquisition de matériels, équipements et fournitures pour la mise en Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-01-29 2018-03-26 2018-09-22 place du centre d'information Envelope et de documentation pour les guides 01 A-F-24-PIC2-17 / Acquisition de matériels et équipements Kit de sechage Single Stage - One IDA / 55640 A posteriori Appel d'offres Open - National 0.00 Annulé 2018-04-15 2018-04-20 2018-05-20 2018-06-19 2018-07-18 2018-09-16 pour la mise en place de Envelope culture de stevia pour 20 ha pilotes 3 A-F-21-PIC2-17 / Fourniture de matériels et d'équipements dans le cadre Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2018-03-19 2018-05-14 2018-08-12 de l'assainissement et Envelope l'embellissement de commune touristique pilote Anakao 9-F-1-PIC2-17 / Acquisition de matériels, mobiliers, matériels informatiques, équipements et accessoires Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 0.00 Annulé 2017-08-20 2017-10-15 2018-04-13 pour les centres Envelope d'affaires/CCI dans les régions et le Ministère de la Justice Page 7 01 B-F-24-PIC2-17 / Fournitures et Installation d'équipements solaires et d'équipements électromécaniques pour une Single Stage - One IDA / 55640 A posteriori Appel d'offres Open - National 578,841.96 Signé 2018-04-30 2018-05-05 2018-06-04 2018-07-04 2018-08-02 2018-10-01 (01) station de pompage Envelope d'une irrigation agricole par aspersion a canon - analamapisampy et antanimieva (en 02 lots) 027-F-21-PIC2-18 / Fournitures d'équipements et matériels divers pour CNC Single Stage - One et FOFIFA Ambanja IDA / 55640 A posteriori Demande de prix Limited 11,967.95 Signé 2019-02-03 2019-03-31 2019-05-30 Envelope (mobiliers de bureau, bureautique, équipements et accessoires, outillages, ...) 028-F-22-PIC2-19 / Single Stage - One Fournitures de petit IDA / 55640 A posteriori Demande de prix Limited 4,009.66 Achevé 2019-03-10 2019-03-30 2019-04-29 Envelope équipement pour AEP Diégo 029-F-22-PIC2-19 / Fourniture de tuyaux et Single Stage - One En attente IDA / 55640 A posteriori Demande de prix Limited 0.00 2019-06-25 2019-07-08 2019-08-07 accessoires de branchements Envelope d'exécution pour l’AEP DIEGO 031-F-22-PIC2-19 / Fourniture d’équipements Single Stage - One En attente IDA / 55640 A posteriori Demande de prix Limited 0.00 2019-06-28 2019-07-15 2019-09-13 pour forage et pompage Envelope d'exécution AEP Tuléar 032-F-21-PIC2-19 / Passation de Acquisition d’orthophoto 30 En attente IDA / 55640 A posteriori marché de gré à Direct 0.00 2019-06-23 2019-06-28 2019-07-02 2019-08-01 cm de résolution 2019 pour d'exécution gré Nosy Be 033-F-21-PIC2-19 / Acquisition de tablettes et Single Stage - One En attente IDA / 55640 A posteriori Demande de prix Limited 0.00 2019-06-28 2019-07-08 2019-07-13 de GPS pour enquêtes Envelope d'exécution foncières NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 15-F-21-PIC2-17 / Fourniture de services pour la saisie et le traitement Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 36,417.32 Achevé 2018-02-20 2018-04-17 2018-10-14 des données fiscales des Envelope communes rurales de la Région Diana 16-F-21-PIC2-17 / Fourniture de services pour la saisie et le traitement Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 59,479.39 Achevé 2018-02-20 2018-04-17 2018-10-14 des données fiscales des Envelope communes rurales dans la Région Atsimo Andrefana 17-F-21-PIC2-17 / Fourniture de services pour la saisie et le traitement Single Stage - One IDA / 55640 A posteriori Demande de prix Limited 31,786.98 Achevé 2018-02-20 2018-04-17 2018-10-14 des données fiscales des Envelope communes rurales dans la Région Anosy Page 8 25-F-23-PIC2-18 / Passation de Acquisition de données IDA / 55640 A posteriori marché de gré à Direct 119,302.64 Signé 2018-05-15 2018-05-20 2018-06-24 2019-06-24 statistiques sur le trafic gré aérien touristique 24-F-3-PIC2-2018 / Analyse Passation de de résidus de pesticides IDA / 55640 A posteriori marché de gré à Direct 28,000.00 Signé 2018-05-01 2018-05-06 2018-05-16 2018-11-12 culture Coton Toliara  gré 030-F-21-PIC2-19 / Passation de Enquêtes sur Nosy Be dans En attente IDA / 55640 A posteriori marché de gré à Direct 0.00 2019-06-23 2019-06-28 2019-07-05 2019-09-13 le cadre de l’ASA Foncier d'exécution gré Urbain avec ONG SAGE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 17-C-23-PIC2-17 / Passation de Formation en communication marchés auprès En cours IDA / 55640 A priori Direct 0.00 2017-10-08 2018-04-06 de crise auprès du Conseil des agences de d'exécution du Tourisme l'ONU 18-C-23-PIC2-17 / Consultance pour le Sélection fondée développement d'outils sur les IDA / 55640 A posteriori Open - National 0.00 Annulé 2017-07-25 2017-08-15 2017-09-28 2017-10-28 2017-12-02 2018-05-31 d'animation technologique qualifications des dans les sites nouvellement consultants aménagés 93-C-22-PIC2-17 / Contrôle Sélection fondée et surveillance des Travaux IDA / 55640 A posteriori sur la qualité et Open - National 41,408.92 Signé 2018-01-15 2018-01-29 2018-02-27 2018-03-29 2018-04-13 2018-04-25 2018-05-30 2018-08-28 de réhabilitation de voiries le coût urbaines de Diego 86-C-23-PIC2-17 / Agence Sélection fondée internationale de relations sur les Open - publiques spécialiste du IDA / 55640 A posteriori 107,899.69 Signé 2017-12-30 2018-02-08 2018-03-12 2018-03-22 2018-04-16 2018-10-13 qualifications des International tourisme sur les marchés consultants européens 85-C-23-PIC2-17 / Agence Sélection fondée internationale de relations sur les Open - publiques spécialiste du IDA / 55640 A posteriori 12,483.81 Achevé 2018-01-08 2018-02-08 2018-02-28 2018-03-15 2018-04-04 2018-05-04 qualifications des International tourisme sur les marchés consultants anglophones 97-C-31-PIC2-17 / Préparation des documents Sélection fondée cadre de sauvegardes et sur les IDA / 55640 A posteriori Open - National 61,691.68 Achevé 2018-02-25 2018-03-12 2018-03-27 2018-04-01 2018-04-23 2018-10-20 études d'impacts sociaux et qualifications des environnementaux pour le consultants PIC2-2 101-C-23-PIC2-2018 / Assistance technique pour Sélection fondée l'amélioration de la sur les Open - performance commerciale et IDA / 55640 A posteriori 0.00 Annulé 2018-05-15 2018-06-05 2018-07-19 2018-08-18 2018-09-11 2019-05-09 qualifications des International le développement des consultants produits dérivés dans les parcs MNP INDIVIDUAL CONSULTANTS Page 9