Public Disclosure Copy The World Bank Implementation Status & Results Report Guangxi Rural Poverty Alleviation Pilot Project (P153892) Guangxi Rural Poverty Alleviation Pilot Project (P153892) EAST ASIA AND PACIFIC | China | Agriculture Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 1 | ARCHIVED on 27-Apr-2017 | ISR27640 | Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:21-Dec-2016 Effectiveness Date:-- Planned Mid Term Review Date:-- Actual Mid-Term Review Date:-- Original Closing Date:30-Jun-2023 Revised Closing Date:30-Jun-2023 Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to increase income generation opportunities through demonstration of value chain development models in the project counties. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Improvement of Pro-Poor Value Chains:(Cost $90.22 M) Public Infrastructure and Services:(Cost $62.79 M) Enhancing Investments in Poor Areas:(Cost $10.41 M) Project Management, Monitoring and Evaluation:(Cost $10.83 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  --  Satisfactory Overall Implementation Progress (IP)  --  Satisfactory Overall Risk Rating  --  Moderate 4/27/2017 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guangxi Rural Poverty Alleviation Pilot Project (P153892) Implementation Status and Key Decisions The project is waiting for the effectiveness after the Loan Agreement was signed on 27 February 2017. Project Management Offices are considered ready to start up project activities when the effectiveness is expected for 26 May, 2017. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Low  --  Low Macroeconomic  Moderate  --  Moderate Sector Strategies and Policies  Moderate  --  Moderate Technical Design of Project or Program  Substantial  --  Substantial Institutional Capacity for Implementation and Sustainability  Substantial  --  Substantial Fiduciary  Substantial  --  Substantial Environment and Social  Moderate  --  Moderate Stakeholders  Moderate  --  Moderate Other  --  --  -- Overall  Moderate  --  Moderate Results Project Development Objective Indicators PHINDPDOTBL  Number of project-supported cooperatives making profit (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDPDOTBL  Number of acknowledged certificates and brand names obtained under the project (Number of product certificates) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 4/27/2017 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guangxi Rural Poverty Alleviation Pilot Project (P153892) Value 0.00 -- 0.00 40.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDPDOTBL  Number of registered GI and brand certificates (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5.00 PHINDPDOTBL  Farmers reached with agricultural assets and services provided by the project (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 15,000.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDPDOTBL  % female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40.00 PHINDPDOTBL  % poor in the cooperatives (Percentage, Custom Supplement) 4/27/2017 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guangxi Rural Poverty Alleviation Pilot Project (P153892) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 60.00 Overall Comments The Project is waiting to its effectiveness. No project activities have started yet. Hence, all indicators are 0 at this stage. Intermediate Results Indicators PHINDIRITBL  Number of cooperatives that have received Cooperative Development Fund (cumulative) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDIRITBL  Cooperative management effectiveness (METT) (Score) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDIRITBL  Cooperative members who adopt innovative marketing practices (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 4/27/2017 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guangxi Rural Poverty Alleviation Pilot Project (P153892) PHINDIRITBL  Customers satisfied with the rural infrastructure services provided by the project (Percentage of male customers) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 70.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDIRITBL  Percentage of female customers (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 70.00 PHINDIRITBL  Number of value chains for which risk management plans were developed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 8.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDIRITBL  Project management improvement actions triggered by grievances/complaints (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 4/27/2017 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guangxi Rural Poverty Alleviation Pilot Project (P153892) PHINDIRITBL  Customers satisfied with the services provided by Business Incubation Center (Percentage of male customers) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 70.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDIRITBL  Percentage of female customers (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 70.00 PHINDIRITBL  Households in project areas covered by credit rating (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 38,000.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 PHINDIRITBL  Learning Workshops and Conferences (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 4/27/2017 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guangxi Rural Poverty Alleviation Pilot Project (P153892) PHINDIRITBL  Project-related publications produced (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Date 22-Dec-2016 -- 10-Apr-2017 31-Dec-2022 Overall Comments The project is waiting for its effectiveness. No project activities have started hence all indicators are 0 at this stage. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed Not P153892 IBRD-86700 USD 100.00 100.00 0.00 0.00 100.00 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P153892 IBRD-86700 21-Dec-2016 -- -- 30-Jun-2023 30-Jun-2023 Effective Cumulative Disbursements 4/27/2017 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guangxi Rural Poverty Alleviation Pilot Project (P153892) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 4/27/2017 Page 8 of 8 Public Disclosure Copy