PROCUREMENT PLAN (Textual Part) Project information: Burkina Faso Local Government Support Project - P162742 Project Implementation agency: Unité de Coordination du Programme d’Appui aux Collectivités Territoriales Date of the Procurement Plan: 23 September 2017 Period covered by this Procurement Plan: 13 September to 31 December 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in LOI N° 039-2016/AN portant règlementation générale de la commande publique, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Burkina Faso : Local Government Support Project PLAN General Information Country: Burkina Faso Banks Approval Date of the Original Procurement Plan: 2017-10-19 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-04-11 Project ID: P120517 GPN Date: Project Name: Local Government Support Project Loan / Credit No: IDA / H7360, IDA / D2240 Executing Agency(ies): Unite de Coordination du Programme d Appui aux Collectivites Territoriales WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PACT-56415-CW-RFQ / Travaux d'aménagement des locaux des bureaux de Component 4: Project Request for Single Stage - One Pending IDA / D2240 Post Limited 121,540.00 0.00 2018-06-14 2018-08-16 2018-10-15 SP/AMBF, de l'UCP/PACT, management and evaluation Quotations Envelope Implementation pavage et construction de trois boxes métalliques GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PACT-29596-GO-RFB / Component 4: Project Single Stage - One Matériel informatique et péri- IDA / H7360 Post Request for Bids Open - National 100,000.00 76,767.38 Signed 2017-11-15 2017-11-29 2017-11-20 2017-11-30 2017-12-20 2017-12-28 2017-12-31 2018-01-19 2018-01-24 2018-02-26 2018-03-25 management and evaluation Envelope informatique BF-PACT-29716-GO-RFQ / Component 4: Project Request for Single Stage - One Fournitures de bureau, de IDA / H7360 Post Limited 10,000.00 41,700.25 Signed 2017-11-20 2017-11-09 2017-12-29 2018-01-02 2018-01-29 2018-01-10 management and evaluation Quotations Envelope consommables informatiques BF-PACT-29722-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / H7360 Post Limited 25,000.00 79,274.32 Signed 2017-11-20 2017-11-17 2017-12-21 2018-01-18 2018-01-21 Matériel et mobilier de bureau management and evaluation Quotations Envelope BF-PACT-29717-GO-RFB / Component 4: Project Single Stage - One IDA / H7360 Post Request for Bids Open - National 300,000.00 229,035.44 Signed 2017-11-15 2017-11-29 2017-11-20 2017-11-30 2017-12-20 2017-12-15 2017-12-27 2018-01-22 2018-01-24 2018-03-02 2018-04-24 Matériel roulant management and evaluation Envelope BF-PACT-29723-GO-DIR / Component 4: Project Under Fourniture de services IDA / H7360 Post Direct Selection Direct 300,000.00 0.00 2018-01-15 2018-03-16 2018-01-29 2018-03-16 2018-02-19 2018-02-26 management and evaluation Implementation dassurance BF-PACT-56330-GO-RFQ / Component 3 - Improving Acquisition de mobiliers de accountability linkages between Request for Single Stage - One Pending IDA / D2240 Post Limited 19,000.00 0.00 2018-06-20 2018-08-22 2018-09-21 bureau pour le compte de local level policy makers and Quotations Envelope Implementation lAMBF et de lUCP/PACT citizens BF-PACT-56307-GO-RFQ / Edition de divers documents pour Component 1 - Establishing the la DGCT, de nouveaux foundations of robust Request for Single Stage - One Pending é entiels de la décentralisation IDA / D2240 réfr Post Limited 63,000.00 0.00 2018-07-14 2018-09-01 2018-10-16 administrative and fiscal Quotations Envelope Implementation pour le SP/CONAD et d é ition de intergovernmental institutions divers documents pour lUCP/PACT BF-PACT-56351-GO-RFQ / Acquisition de fournitures de Component 4: Project Request for Single Stage - One Pending IDA / D2240 Post Limited 20,000.00 0.00 2018-11-04 2018-12-23 2019-01-22 bureau pour le compte de management and evaluation Quotations Envelope Implementation lUCP/PACT NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PACT-56336-NC-DIR / Acquisition Tom 2 PRO et Component 4: Project Pending IDA / D2240 Post Direct Selection Direct 40,000.00 0.00 2018-04-15 2018-04-30 2018-07-04 2018-09-02 migration et acquisition dun management and evaluation Implementation logiciel de paie CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PACT-29760-CS-QCBS / Component 4: Project Quality And Cost- Under Audit financier et comptable de IDA / H7360 Post Open - National 90,000.00 0.00 2018-03-10 2017-11-30 2018-03-15 2017-12-07 2018-04-03 2018-01-16 2018-05-08 2018-05-13 2018-06-04 2018-06-28 2019-03-01 management and evaluation Based Selection Implementation trois exercices BF-PACT-29763-CS-QCBS / Component 4: Project Quality And Cost- Under Audit des marchés des IDA / H7360 Post Open - National 150,000.00 0.00 2018-01-10 2017-11-20 2018-01-15 2017-11-30 2018-02-06 2018-01-09 2018-03-15 2018-02-26 2018-03-22 2018-03-15 2018-04-15 2018-05-13 2018-06-27 management and evaluation Based Selection Implementation communes pour cinq exercices Component 3 - Improving BF-PACT-29746-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2018-01-26 2017-12-04 2017-12-04 2018-01-03 2018-02-23 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Plateau Central citizens Component 3 - Improving BF-PACT-29732-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2018-02-13 2017-12-04 2017-12-04 2018-01-03 2018-02-22 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Centre citizens Page 1 Component 3 - Improving BF-PACT-29749-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2018-01-26 2017-12-04 2017-12-04 2018-01-03 2018-02-21 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Centre Est citizens Component 3 - Improving BF-PACT-29734-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C du IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2017-12-04 2018-01-03 2018-02-23 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation Centre Ouest citizens Component 3 - Improving BF-PACT-29728-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2018-02-13 2017-12-04 2017-12-04 2018-01-03 2018-02-22 2018-02-02 2018-02-16 2018-04-01 2018-04-29 2019-04-29 local level policy makers and Based Selection Implementation région du Sud-Ouest citizens Component 3 - Improving BF-PACT-29726-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2018-02-08 2017-12-04 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région des Hauts-Bassins citizens Component 3 - Improving BF-PACT-29736-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2017-12-04 2018-01-03 2018-02-23 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région de lEst citizens Component 3 - Improving BF-PACT-29729-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2017-12-04 2018-01-03 2018-02-27 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Sahel citizens Component 3 - Improving BF-PACT-29730-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2018-02-27 2017-12-04 2017-12-04 2018-01-03 2018-02-27 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Boucle du Mouhoun citizens Component 3 - Improving BF-PACT-29747-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2017-12-04 2018-01-03 2018-02-23 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Centre Sud citizens Component 3 - Improving BF-PACT-29737-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2018-02-13 2017-12-04 2017-12-04 2018-01-03 2018-02-23 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Centre Nord citizens Component 3 - Improving BF-PACT-29743-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2017-12-04 2018-01-03 2018-02-22 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région des Cascades citizens Component 3 - Improving BF-PACT-29745-CS-CQS / Mise accountability linkages between Quality And Cost- Under en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2018-02-13 2017-12-04 2017-12-04 2018-01-03 2018-02-27 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Nord citizens BF-PACT-56343-CS-QCBS / Component 1 - Establishing the Etude sur les potentialités foundations of robust Quality And Cost- Pending IDA / D2240 Post Open - National 40,000.00 0.00 2018-06-30 2018-07-21 2018-08-19 2018-09-16 2018-10-16 2018-11-20 2018-12-25 2019-03-25 financières non fiscales des administrative and fiscal Based Selection Implementation Collectivités Locales (DGTCP) intergovernmental institutions BF-PACT-56393-CS-QCBS / Audit organisationnel et Component 1 - Establishing the fonctionnel de la DGCT en lien foundations of robust Quality And Cost- Pending IDA / D2240 Post Open - National 40,000.00 0.00 2018-07-05 2018-07-26 2018-09-08 2018-10-06 2018-11-05 2018-12-10 2019-01-14 2019-04-14 é entiels de avec les nouveaux réfr administrative and fiscal Based Selection Implementation la décentralisation assorti d'un intergovernmental institutions plan stratégique BF-PACT-56378-CS-QCBS / Component 3 - Improving Etude pour la collecte de accountability linkages between Quality And Cost- Pending données et suivi externe de IDA / D2240 Post Open - National 124,000.00 0.00 2018-09-30 2018-10-21 2018-12-04 2019-01-01 2019-01-31 2019-03-07 2019-04-11 2019-10-08 local level policy makers and Based Selection Implementation lapproche organisation citizens communautaire de base (OCB) BF-PACT-56367-CS-QCBS / Component 3 - Improving Recrutement d'un organisme accountability linkages between Quality And Cost- Pending IDA / D2240 Post Open - National 436,410.00 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-03 2018-09-02 2018-10-07 2018-11-11 2019-11-11 pour la mise en Suvre de la sous local level policy makers and Based Selection Implementation composante C.4 citizens BF-PACT-56180-CS-CQS / Consultant Recrutement dun cabinet de Component 4: Project Pending IDA / D2240 Post Qualification Open - National 10,000.00 0.00 2018-04-10 2018-04-24 2018-05-22 2018-06-05 2018-07-10 2018-07-25 recrutement du personnel management and evaluation Implementation Selection complémentaire de lUCP/PACT BF-PACT-56155-CS-CQS / Recrutement d'un consultant Consultant Component 4: Project Pending pour la collecte de données IDA / D2240 Post Qualification Open - National 80,170.00 0.00 2018-06-06 2018-06-20 2018-08-03 2018-08-17 2018-09-21 2018-11-20 management and evaluation Implementation finales au niveau citoyen dans la Selection région du Sahel INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PACT-29766-CS-INDV / Component 4: Project Individual Consultant Relecture, suivi et hébergement IDA / H7360 Post Limited 5,000.00 4,802.71 Signed 2017-11-05 2017-11-10 2017-11-10 2017-11-13 2017-11-20 2018-01-09 2017-12-14 2018-01-26 2018-01-14 management and evaluation Selection du site web du PACT BF-PACT-29770-CS-INDV / Component 4: Project Individual Consultant Elaboration dune base de IDA / H7360 Post Limited 5,000.00 4,364.45 Signed 2017-10-20 2017-11-16 2017-10-25 2017-11-22 2017-11-05 2018-01-09 2017-11-27 2018-01-26 2017-12-27 management and evaluation Selection données BF-PACT-29815-CS-INDV / Audits municipaux et Assistance Component 2 - Strengthening Individual Consultant à lélaboration des Plans de IDA / H7360 capacity of municipalities to Post Limited 55,000.00 22,634.16 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Selection Développements Institutionnels manage local development (PDI) de 11 communes Page 2 BF-PACT-29816-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,895.89 Signed 2017-11-25 2017-11-08 2017-11-30 2017-12-21 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 1) BF-PACT-29789-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 37,429.71 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 2) BF-PACT-29790-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,133.48 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 3) BF-PACT-29779-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 40,344.23 Signed 2017-11-25 2017-11-08 2017-11-30 2017-12-21 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 4) BF-PACT-29817-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,344.24 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 5) BF-PACT-29795-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,753.13 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 6) BF-PACT-29799-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 37,747.70 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 7) BF-PACT-29787-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,346.28 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 8) BF-PACT-29791-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 40,334.67 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 9) BF-PACT-29809-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 37,429.71 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 10) BF-PACT-29793-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,075.89 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 11) BF-PACT-29797-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 40,025.77 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 12) BF-PACT-29796-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 39,852.29 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 13) BF-PACT-29813-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,888.86 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 14) BF-PACT-29792-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,346.09 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 15) BF-PACT-29785-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,378.15 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2017-12-29 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 16) Page 3 BF-PACT-29802-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 38,291.59 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 17) BF-PACT-29788-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 39,681.98 Signed 2017-11-25 2017-11-08 2017-11-30 2017-12-21 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 18) BF-PACT-29804-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 44,054.48 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 19) BF-PACT-29805-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 37,492.56 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 20) BF-PACT-29818-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 41,890.56 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 21) BF-PACT-29812-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 22,574.64 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 22) BF-PACT-29806-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 22,530.77 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 23) BF-PACT-29798-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 22,310.52 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 24) BF-PACT-29814-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 22,573.70 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 25) BF-PACT-29808-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 22,187.27 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 26) BF-PACT-29781-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 22,152.79 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-13 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 27) BF-PACT-29807-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 22,153.18 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 28) BF-PACT-29794-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 22,585.63 Signed 2017-11-25 2017-11-08 2017-11-30 2017-12-21 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 29) BF-PACT-29753-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 23,293.57 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 30) BF-PACT-29786-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 20,624.60 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-05 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 31) BF-PACT-29800-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 20,722.77 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 32) Page 4 BF-PACT-29811-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 23,293.95 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 33) BF-PACT-29801-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant IDA / H7360 capacity of municipalities to Post Limited 50,000.00 23,158.71 Signed 2017-11-25 2017-11-08 2017-11-30 2018-01-15 2017-12-14 2018-01-12 2018-01-28 2018-01-26 2018-03-14 Développements Institutionnels Selection manage local development (PDI) de 10 communes (groupe 34) Component 3 - Improving BF-PACT-29819-CS-CDS / accountability linkages between Under Collecte de données finales du IDA / H7360 Post Direct Selection Direct - National 153,507.00 0.00 2017-09-18 2017-09-18 2017-10-11 2017-09-19 2017-10-30 2018-01-28 local level policy makers and Implementation Projet au niveau citoyen citizens BF-PACT-56421-CS-INDV / Consultant pour la formation des Component 1 - Establishing the membres de la gouvernance foundations of robust Individual Consultant Pending administrative et locale et les IDA / D2240 Post Limited 40,000.00 0.00 2018-05-30 2018-06-04 2018-06-25 2018-07-30 2018-08-29 administrative and fiscal Selection Implementation membres des GTS (MATD & intergovernmental institutions MINEFID) en planification et suivi é aluation v BF-PACT-56340-CS-INDV / Consultant pour la formation des Component 1 - Establishing the membres du réseau sur les foundations of robust Individual Consultant Pending IDA / D2240 Post Limited 14,560.00 0.00 2018-05-20 2018-06-04 2018-07-04 2018-08-08 2018-08-23 politiques de décentralisation et administrative and fiscal Selection Implementation les problèmes m é ergents intergovernmental institutions (RPDDL) BF-PACT-56153-CS-INDV / Component 1 - Establishing the Conception dun logiciel de foundations of robust Individual Consultant Pending IDA / D2240 Post Limited 12,000.00 0.00 2018-06-01 2018-06-15 2018-07-06 2018-08-10 2018-10-09 gestion des effectifs des administrative and fiscal Selection Implementation collectivités territoriales (DGFPT) intergovernmental institutions BF-PACT-56326-CS-INDV / Component 1 - Establishing the Elaboration dune base de foundations of robust Individual Consultant Pending IDA / D2240 Post Limited 40,000.00 0.00 2018-06-01 2018-06-15 2018-07-15 2018-08-19 2018-10-18 données pour le SNSE (SP administrative and fiscal Selection Implementation CONAD) intergovernmental institutions BF-PACT-56160-CS-INDV / Elaboration dune base de é encé données géo réfr couplée Component 4: Project Individual Consultant Pending IDA / D2240 Post Limited 12,000.00 0.00 2018-05-10 2018-05-24 2018-06-14 2018-07-19 2018-09-02 avec un logiciel de cartographie management and evaluation Selection Implementation et formation des utilisateurs (UCP/PACT) Page 5