The World Bank Implementation Status & Results Report Freetown Emergency Recovery Project (P166075) Freetown Emergency Recovery Project (P166075) AFRICA | Sierra Leone | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 2 | ARCHIVED on 13-Dec-2018 | ISR35179 | Implementing Agencies: Ministry of Finance and Economic Development (MoFED), Ministry of Finance and Economic Development (MoFED) Key Dates Key Project Dates Bank Approval Date: 22-Feb-2018 Effectiveness Date: 13-Apr-2018 Planned Mid Term Review Date: 28-Oct-2019 Actual Mid-Term Review Date: -- Original Closing Date: 28-Feb-2021 Revised Closing Date: 28-Feb-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to rehabilitate selected critical infrastructure and to strengthen government capacity for managing disaster risk. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Rehabilitation of Public Infrastructure and Slope Stabilization:(Cost $7.84 M) Component 2: Strengthening institutional capacity:(Cost $1.80 M) Component 3: Project Management:(Cost $1.90 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Overall, the FERP is progressing well and disbursement is 23% in its first six months of implementation. This is driven by the urgent earthworks under Component 1.1., carried out by UNOPS. The other two works components are procuring the design consultancies under Components 1.2 and 1.3. Component 2 is moving ahead with an Emergency Preparedness and Response Capacity Needs Assessment, which will inform institutional capacity strengthening requirements in disaster risk management. 12/13/2018 Page 1 of 5 The World Bank Implementation Status & Results Report Freetown Emergency Recovery Project (P166075) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Substantial Substantial Substantial Other -- -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Rehabilitate critical infrastructure IN00598471 ►Number of beneficiaries with restored or improved access to service delivery infrastructure (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 34,000-44,000 Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 IN00598479 Female beneficiaries with restored or improved access to service delivery infrastructure (Text, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40-50% IN00598472 ►Number of population protected by the slope stabilization works (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 400-600 Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 IN00598480 Female beneficiaries protected by slope stabilization works (Text, Custom Supplement) 12/13/2018 Page 2 of 5 The World Bank Implementation Status & Results Report Freetown Emergency Recovery Project (P166075) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40-50% Strengthen government capacity for managing disaster risk IN00598435 ►Disaster preparedness and contingency plan developed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No 0.00 No Yes Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 Overall Comments PDO The number of people protected from slope stabilization works is being calculated and will be included in the next ISR. Intermediate Results Indicators by Components Component 1: Rehabilitation of Public Infrastructure and Slope Stabilization IN00598473 ►Number of bridges reconstructed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4-6 Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 IN00598476 ►Length of roads rehabilitated (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4-6 km Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 IN00598477 ►Number of Kilometers of water piping installed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 42-55 km Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 Component 2: Strengthening institutional capacity IN00598475 12/13/2018 Page 3 of 5 The World Bank Implementation Status & Results Report Freetown Emergency Recovery Project (P166075) ►Number of individuals engaged in community disaster risk awareness and preparedness activities (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3,400-4,400 Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 IN00598482 Percentage of women engaged in community disaster risk awareness and preparedness activities (Text, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40-50% IN00598474 ►Number of Government Officials trained in disaster preparedness and management (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15-20 Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 IN00598481 Female Government Officials trained in disaster preparedness and management (Text, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20-30% Component 3: Project Management IN00598478 ►Percentage of Greivances Addressed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80-100% Date 01-Mar-2018 25-May-2018 01-Nov-2018 26-Feb-2021 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P166075 IDA-D2750 Effective USD 10.00 10.00 0.00 2.29 7.67 23% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date 12/13/2018 Page 4 of 5 The World Bank Implementation Status & Results Report Freetown Emergency Recovery Project (P166075) P166075 IDA-D2750 Effective 22-Feb-2018 26-Mar-2018 13-Apr-2018 28-Feb-2021 28-Feb-2021 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/13/2018 Page 5 of 5