90135 Procurement Plan for Electrification Works Updated 30/06/2014 (Mahmodia Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Contract Contract Contract Package reference No/ Procurement Bank Preference Bid Document Closing Signing Contract Completion Completion Final Contract SL No District Description of Works Status Commencement Contract Value Name, City, and Country of Contractor Contract No method (Date) Currency Date Value (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Ongoing Completed Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Contract Contract Contract Package reference No/ Procurement Bank Preference Bid Document Closing Signing Contract Completion Completion Final Contract SL No District Description of Works Status Commencement Contract Value Name, City, and Country of Contractor Contract No method (Date) Currency Date Value (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) The High Dam Company for Electrical Planned 1/Oct/09 02-Jan-10 Projects 1/Jan/12 Medium Volt Electrification for 1 Mahmoudia IIIMP/IIS/MAHM/ELM-01-2009 NCB Revised n/a No 12,835,885.00 EGP 1/Sep/13 El Mahmoudia District Actual 18/Mar/09 12/Aug/09 12/Aug/09 23/Aug/09 16/Sep/09 02-Jan-10 The High Dam Company for Electrical Planned 1/Oct/09 01-Feb-10 Projects 01-Jan-12 Low Volt Electrification for El 2 Mahmoudia IIIMP/IIS/MAHM/ELL-02-2009 NCB Revised n/a No 13,415,732.40 EGP 1/Sep/13 Mahmoudia District Actual 18/Mar/09 3/Sep/09 3/Sep/09 1/Oct/09 24/Nov/09 02-Jan-10 Planned Ongoing Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Contract Contract Contract Package reference No/ Procurement Bank Preference Bid Document Closing Signing Contract Completion Completion Final Contract SL No District Description of Works Status Commencement Contract Value Name, City, and Country of Contractor Contract No method (Date) Currency Date Value (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Procurement Plan for Main Canal Rehabilitation Works Updated 30/06/2014 (Mahmodia Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Contract Signing Contract Package reference No/ Procurement Bank Preference Document Closing Contract SL No District Contract No Description of Works method Status Commencement Contract Value Currency Name, City, and Country of Contractor Completion (Date) (Date) (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) Planned 1/Jan/11 1/Feb/11 1/Mar/11 1/Mar/11 1/Apr/11 1/Apr/11 30/Mar/12 IIIMP/MAIN-CANAL/MAHM/2- 1 Mahmoudia Rehabilitate Lock at Km 0+000 NCB Revised Prior No 1/Dec/11 15/Apr/12 30/Jul/12 30/Jul/12 29/Aug/12 13/Sep/12 2,956,300.00 EGP Maher Salah Mohamed Abo Eissa 12/Sep/13 2012 Actual 1/Feb/12 27/Jun/12 30/Jul/12 30/Jul/12 24/Sep/12 8/Oct/12 10/Oct/12 9/Nov/13 Planned 8/Mar/11 8/Apr/11 2/May/11 2/May/11 1/Jun/11 1/Jun/11 30/May/12 IIIMP/MAIN-CANAL/MAHM/3- Remodel Mahmoudia Canal from km 0.7- 2 Mahmoudia NCB Revised Prior No 1/Dec/11 21/Mar/12 21/Mar/12 1/Jul/12 16/Jul/12 5,551,810.00 EGP El Karakat Egyptian Company 15/Jul/13 2012 15.35 Actual 20/Jul/11 17/Feb/12 21/Mar/12 21/Mar/12 18/Jun/12 9/Jul/12 14/Jul/12 15/Sep/13 Planned 10/Mar/11 10/Apr/11 2/May/11 2/May/11 1/Jun/11 1/Jun/11 30/May/12 Abo IIIMP/MAIN-CANAL/MAHM/4- Remodel Mahmoudia Canal from km Lwaa El Hamed Company for 3 NCB Revised Prior No 1/Dec/11 22/Mar/12 22/Mar/12 1/Jul/12 16/Jul/12 8,904,700.00 EGP 15/Jul/13 Hommos 2012 15.350 - 29.930 Contracting Actual 20/Jul/11 17/Feb/12 22/Mar/12 22/Mar/12 27/May/12 7/Jul/12 7/Jul/12 20/Jun/13 Planned 15/Mar/11 15/Apr/11 2/May/11 2/May/11 1/Jun/11 1/Jun/11 30/May/12 Kafr El IIIMP/MAIN-CANAL/MAHM/5- Remodel Mahmoudia Canal from km Shaaban Hamza for Contracting El 4 NCB Revised Prior No 1/Dec/11 24/Mar/12 24/Mar/12 1/Jul/12 16/Jul/12 3,854,000.00 EGP 15/Jul/13 Dawar 2012 29.930 - 42.890 Behera Actual 20/Jul/11 17/Feb/12 24/Mar/12 24/Mar/12 28/May/12 7/Jul/12 7/Jul/12 11/Sep/13 Total completed contracts Ongoing Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Contract Signing Contract Package reference No/ Procurement Bank Preference Document Closing Contract SL No District Contract No Description of Works method Status Commencement Contract Value Currency Name, City, and Country of Contractor Completion (Date) (Date) (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) Remove old swing bridges at km 8.48 Planned 1/Jan/11 1/Feb/11 2/Mar/11 2/Mar/11 1/Apr/11 1/Apr/11 31/Mar/12 Mahmoudia, IIIMP/MAIN-CANAL/MAHM/1- (Ashour), Km 15.53 (Elzawia) and km Lwaa El Hamed Company for 1 Abo NCB Revised Prior No 1/Dec/11 20/Mar/12 20/Mar/12 1/Jul/12 16/Jul/12 1,620,130.00 EGP 15/Jul/13 2012 27.04 (Abo Hommos) and replace with Contracting Hommos pontoon foot bridges Actual 20/Jul/11 17/Feb/12 20/Mar/12 20/Mar/12 27/May/12 7/Jul/12 7/Jul/12 Remodel canal, bored pile protection km Planned 25/Jan/11 25/Feb/11 2/Mar/11 2/Mar/11 1/Apr/11 1/Apr/11 Cooperative society for 24/Jun/12 IIIMP/MAIN-CANAL/MAHM/6- 2 Mahmoudia 0-0.7 and removal of bridge pier and NCB Revised Prior No 7/Dec/12 6/Jan/13 6/Jan/13 29/Mar/13 13/Apr/13 21,541,300.00 EGP Engineering Consultancy- 7/Jul/14 2012 abutments at km 0+500 Damanhour Actual 20/Jul/11 26/Dec/12 28/Jan/13 28/Jan/13 3/May/13 21/May/13 22/May/13 Planned 1/Apr/13 1/Jun/13 2/Jul/13 2/Jul/13 16/Jul/13 7/Aug/13 22/Aug/13 18/Jun/14 Remodel Mahmoudia Canal Downstream Kafr El IIIMP/MAIN-CANAL/MAHM/8A- 3 Kafr EL Dawar Lock A from km 44.77 to NCB Revised Post No 1/Jul/13 16/Jul/13 15/Aug/13 15/Aug/13 10/Jan/14 1/Feb/14 16/Feb/14 1,687,200.00 ElGabry Company for Trading & 13/Dec/14 Dawar 2013 EGP km 52.80 Contracting Actual 12/Mar/13 28/Jul/13 28/Aug/13 28/Aug/13 23/Jan/14 2/Mar/14 5/Mar/14 Total ongoing contracts Planned Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Contract Signing Contract Package reference No/ Procurement Bank Preference Document Closing Contract SL No District Contract No Description of Works method Status Commencement Contract Value Currency Name, City, and Country of Contractor Completion (Date) (Date) (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) Raise, Widen Embankment and Put Planned 1/Jan/11 30/Jan/11 1/Feb/11 1/Feb/11 1/Mar/11 1/Mar/11 29/Jul/11 Mahmoudia, IIIMP/MAIN-CANAL/MAHM/7- Asphalt Layer on Embankment of 1 Abo Hommos 2013 Mahmodia Canal in Different Locations Cancelled Revised Post No 1/Jun/13 16/Jun/13 16/Jul/13 16/Jul/13 30/Jul/13 15/Aug/13 30/Aug/13 Cancelled 29/Aug/14 from Km 5.500 to Km 36.800 Actual Planned 1/Apr/13 1/Jun/13 2/Jul/13 2/Jul/13 16/Jul/13 7/Aug/13 22/Aug/13 18/Jun/14 Remodel Mahmoudia Canal Downstream Kafr El IIIMP/MAIN-CANAL/MAHM/8B- Revised 1/Jul/13 16/Jul/13 15/Aug/13 15/Aug/13 16/Jan/14 7/Feb/14 22/Feb/14 19/Dec/14 2 Kafr EL Dawar Lock B (from km52.800 to NCB Post No Dawar 2014 km 62.00) Actual 12/Mar/13 28/Jul/13 29/Aug/13 29/Aug/13 Retender Actual 5/Jun/14 7/Jul/14 7/Jul/14 Procurement Plan for Branch Canal Rehabilitation Works (Mahmodia Area) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Signing Package reference No/ Procurement Bank Preference Document Closing SL No District Description of Works Status Contract No method (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) Planned 26-Jun-07 21-Jul-07 15-Aug-07 15-Aug-07 08-Sep-07 24-Oct-07 Mesqa Intakes along Direct Mahmoudia 1 Mahmoudia IIIMP/IIS/MAHM/W01-2008 NCB Revised Prior No Right Side Actual 10/Oct/07 09-Feb-08 01-Mar-08 01-Mar-08 17-Apr-08 12-May-08 Planned 26-Jun-07 21-Jul-07 15-Aug-07 15-Aug-07 08-Sep-07 24-Oct-07 Mesqa Intakes along Direct Mahmoudia 2 Mahmoudia IIMP/IIS/MAHM/W02-2008 NCB Revised Prior No Left Side Actual 10-Oct-07 09-Feb-08 01-Mar-08 01-Mar-08 17-Apr-08 12-May-08 Planned 26-Jun-07 21-Jul-07 15-Aug-07 15-Aug-07 08-Sep-07 24-Oct-07 3 Mahmoudia IIIMP/IIS/MAHM/W03-2008 Mesqa Intakes along Hamid Menisi NCB Revised Prior No Actual 10-Oct-07 09-Feb-08 02-Mar-08 02-Mar-08 17-Apr-08 12-May-08 Planned 26-Jun-07 21-Jul-07 15-Aug-07 15-Aug-07 08-Sep-07 24-Oct-07 Mesqa Intakes along Nekla & Sawaki Al- 4 Mahmoudia IIIMP/IIS/MAHM/W05-2008 NCB Revised Prior No Hadid Actual 10-Oct-07 09-Feb-08 02-Mar-08 02-Mar-08 17-Apr-08 12-May-08 Preparation of civil works for ultrasonic flow Planned 15/Feb/11 15/Mar/11 15/Apr/11 15/May/11 5 Various IIMP/IS/MAHM/W07-2011 meters and water levels equipment along El NCB Revised Post No 15/Oct/11 Mahmoudia canal and its Branches Actual 3/Mar/11 18/Apr/11 19/May/11 19/May/11 25/May/11 20/Sep/11 Planned 1/Apr/11 1/May/11 1/Jun/11 1/Jun/11 1/Jul/11 Abo Homoss + Besentway and Other Branch Canals 6 IIIMP/IIS/MAHM/W08/2011 NCB Revised Prior No 15/Mar/12 14/Apr/12 14/Apr/12 1/Jul/12 Kafr El Dawar Rehabilitation Actual 15/May/11 11/Mar/12 11/Apr/12 11/Apr/12 22/May/12 4/Jun/12 Total completed contracts Ongoing Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Signing Package reference No/ Procurement Bank Preference Document Closing SL No District Description of Works Status Contract No method (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) Planned 17/Aug/11 16/Sep/11 16/Oct/11 16/Oct/11 El-Baradi and Other Branch Canals 1 Mahmoudia IIIMP/IIS/MAHM/W09-2013 NCB Revised Post No 15/Sep/12 15/Mar/13 14/Apr/13 14/Apr/13 20/May/13 Rehabilitation Actual 8/Oct/12 26/Feb/13 27/Mar/13 27/Mar/13 30/Apr/13 10/Jun/13 Planned 22/Aug/11 21/Sep/11 21/Oct/11 21/Oct/11 20/Nov/11 Hamd Mensi and its Branches 2 Mahmoudia IIIMP/IIS/MAHM/W10-2013 NCB Revised Post No 1/Oct/12 15/Mar/13 14/Apr/13 14/Apr/13 20/May/13 Rehabilitation Actual 3/Oct/12 26/Feb/13 28/Mar/13 28/Mar/13 10/Jun/13 Total ongoing contracts Planned Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Signing Package reference No/ Procurement Bank Preference Document Closing SL No District Description of Works Status Contract No method (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) Updated 30/06/2014 Contract Contract Contract Completion Commencement Contract Value Name, City, and Country of Contractor Currency (Date) (Date) 29/Aug/08 Adel Abdel Azez El- Shahawy 2,371,475.00 EGP Company 15/May/08 14-Oct-09 29/Aug/08 Adel Abdel Azez El- Shahawy 2,014,300.00 EGP Company 15/May/08 14-Mar-09 29/Aug/08 Adel Abdel Azez El- Shahawy 3,128,525.00 EGP Company 15/May/08 14-Oct-09 29/Aug/08 Adel Abdel Azez El- Shahawy 2,351,875.00 EGP Company 15/May/08 14-Oct-09 21/Nov/11 Al- Mohamadia for Contracting 22/Apr/12 697,510.00 EGP Mahamed Abd El Khalek Amara 20/Sep/11 19/Jun/12 8/Jul/11 1/Aug/13 Sherif Hassan Kheiry&Mohamed 16/Jul/12 6,971,000.00 EGP Fathy Said for Contracting 2/Aug/12 13/Jun/13 Contract Contract Contract Completion Commencement Contract Value Name, City, and Country of Contractor Currency (Date) (Date) 15/Nov/11 13/Nov/12 27/May/13 9,642,000.00 EGP Heraa` Contracting Office 26/May/14 10/Jun/13 20/Nov/11 18/Nov/12 Al Kholy Company for contracting 27/May/13 5,916,980.00 EGP and Engineering Works 26/May/14 10/Jun/13 Contract Contract Contract Completion Commencement Contract Value Name, City, and Country of Contractor Currency (Date) (Date) Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Updated 30/06/2014 Completed Area Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Contract Contract Contract Package reference No/ Procurement Bank Preference Bid Document Closing Signing Contract Name, City, and Country of Completion SL No District Description of Works Status Commencement Contract Value Contract No method Currency Contractor (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Planned 01-Mar-08 19-Mar-08 19-Apr-08 19-Apr-08 19-May-08 04-May-09 9/Jan/10 Meska Improvement Works for Ganabiet 1 Mahmoudia IIIMP/IIS/MAHM/MQ-01-2008 990 NCB Revised Prior No 13-Jul-08 15-May-09 16-Jun-09 16-Jun-09 16-Jul-09 16-Sep-09 4,945,610.00 EGP Heraa` Contracting Office 24/May/10 Hamad Menesi Canal Actual 20-Jul-08 11-May-09 16-Jun-09 16-Jun-09 21-Jul-09 03-Aug-09 22-Aug-09 21-Jun-10 Planned 01-Dec-08 18-Jan-09 18-Feb-09 18-Feb-09 18-Mar-09 22-Apr-09 28/Dec/09 Meska Improvement Works for Swaki Al Al Kholy Company for contracting 2 Mahmoudia IIIMP/IIS/MAHM/MQ-01-2009 969 NCB Revised Prior No 22-Aug-09 5,977,910.00 EGP and Engineering Works 29/Apr/10 Hadid Branch Canal Actual 05-Feb-09 11-May-09 15-Jun-09 15-Jun-09 21-Jul-09 22-Aug-09 22-Aug-09 21/Jun/10 Planned 01-Mar-09 19-Mar-09 19-Apr-09 19-Apr-09 19-May-09 04-Jul-09 11/Mar/10 Meska Improvement Works in Rayah Al-Amro Office for Contracting 3 Mahmoudia IIIMP/IIS/MAHM/MQ-03-2009 824 NCB Revised Prior No 4,929,535.00 EGP Zarkoon Branch Canal Actual 30-Apr-09 06-Jul-09 09-Aug-09 09-Aug-09 19-Aug-09 01-Sep-09 08-Sep-09 21-Jun-10 Planned 04-Aug-09 27-Aug-09 27-Sep-09 27-Sep-09 19-Oct-09 17-Nov-09 Al-Sesy Group for Contracting 25/Jul/10 Meska Improvement Works in Nasry 4 Mahmoudia IIIMP/IIS/MAHM/MQ-04-2009 1,269 NCB Revised Prior No 6,528,043.15 EGP Company Branch Canal Actual 21-Jun-09 06-Jul-09 10-Aug-09 10-Aug-09 19-Aug-09 01-Sep-09 08-Sep-09 07-Jul-10 Planned 01-Nov-09 18-Nov-09 20-Dec-09 20-Dec-09 20-Jan-10 18-Feb-10 26/Oct/10 Meska Improvement Works for Al-Hakim Heraa` Contracting Office 5 Mahmoudia IIIMP/IIS/MAHM/MQ-05-2009 1,295 NCB Revised Prior No 6,079,620.00 EGP 28/Jul/12 Branch Canal Actual 19-Jul-09 03-Sep-09 04-Oct-09 04-Oct-09 29-Oct-09 17-Nov-09 05-Dec-09 4/Mar/13 Planned 01-Mar-10 18-Mar-10 18-Apr-10 18-Apr-10 18-May-10 15-Jun-10 20/Feb/11 Meska Improvement for Nekla Branch Al-Amro Office for Contracting 6 Mahmoudia IIIMP/IIS/MAHM/MQ-06-2009 1,365 NCB Revised Prior No 31-Oct-09 01-Dec-09 01-Dec-09 10-Dec-09 09-Jan-10 6,677,055.00 EGP 16/Sep/10 Canal Right Bank from the Intake to End Actual 03-Aug-09 31-Oct-09 01-Dec-09 01-Dec-09 13-Dec-09 28-Dec-2009 11-Jan-10 10-Nov-10 Meska Improvement Works for Hamad Planned 01-Mar-10 18-Mar-10 18-Apr-10 18-Apr-10 18-May-10 15-Jun-10 Algamea Al-Taawonia Al-Intagia for 20/Feb/11 7 Mahmoudia IIIMP/IIS/MAHM/MQ-07-2009 Menisi Branch Canal Right Bank from 1,257 NCB Revised Prior No 5,365,060.00 EGP modern construction intake to Km 3.030 Actual 13-Aug-09 03-Sep-09 07-Oct-09 07-Oct-09 29-Oct-09 17-Nov-09 05-Dec-09 04-Oct-10 Meska Improvement Works in El-Sant, Planned 03-Jan-10 24-Jan-10 24-Feb-10 24-Feb-10 24-Mar-10 22-Apr-10 28/Dec/10 Heraa` Contracting Office 8 Mahmoudia IIIMP/IIS/MAHM/MQ-08-2009 G. Arimon and Zarkoon Al-Sharkia 1,008 NCB Revised Prior No 5,230,820.00 EGP Branch Canals Actual 13-Aug-09 03-Sep-09 05-Oct-09 05-Oct-09 29-Oct-09 17-Nov-09 05-Dec-09 4/Apr/11 Meska Improvement Works for Hamed Planned 17/Aug/09 1/Oct/09 2/Nov/09 2/Nov/09 12/Dec/09 27/Dec/09 24/Aug/10 Abdalla El Kholy and his partners for 9 Mahmoudia IIIMP/IIS/MAHM/MQ-09-2009 Menisi Branch Canal (2) Left Bank from 1,034 NCB Revised Prior No 01-Nov-09 02-Dec-09 02-Dec-09 10-Dec-09 4,314,345.00 EGP General contracting Km 3.800 to Km 6.365 Actual 16-Sep-09 31-Oct-09 02-Dec-09 02-Dec-09 13-Dec-09 11-Jan-10 26-Jan-10 25-Sep-10 Planned 03-Mar-10 20-Mar-10 21-Apr-10 21-Apr-10 21-May-10 18-Jun-10 23/Feb/11 Meska Improvement Works for Hamad 10 Mahmoudia IIIMP/IIS/MAHM/MQ10-2009 Menisi Branch Canal (3) Right bank from 1,111 NCB Revised Prior No 5,156,555.00 EGP Heraa` Contracting Office Km 3.700 to Km 8.950 Actual 22-Nov-09 26-Dec-09 28-Jan-10 28-Jan-10 16-Feb-10 13-Mar-10 20-Mar-10 19/Apr/11 Planned 01-Oct-09 19-Oct-09 19-Nov-09 19-Nov-09 19-Dec-09 22-Jan-10 29/Sep/10 Meska Improvement Works for El-Awqaf Revised 01-Dec-09 19-Dec-09 19-Jan-10 19-Jan-10 19-Feb-10 22-Mar-10 20-Apr-10 Office of engineer shaban Hamzah 16/Dec/10 11 Mahmoudia IIIMP/IIS/MAHM/MQ11-2009 El-Sharqiya, El-Awqaf El-Gharbiya, Ezab 832 NCB Prior No 3,224,300.00 EGP Ghurab El-Awqaf and Silika branch canals Actual 22-Nov-09 26-Dec-09 27-Jan-10 27-Jan-10 16-Feb-10 15-Mar-10 27/Mar/10 26/Jan/11 Planned 01-Mar-10 18-Mar-10 18-Apr-10 18-Apr-10 18-May-10 15-Jun-10 20/Feb/11 Meska Improvement Works in Nekla Al-Amro Office for Contracting 12 Mahmoudia IIIMP/IIS/MAHM/MQ12-2009 1,580 NCB Revised Prior No 8,436,370.00 EGP Branch Canal - Left Bank Actual 22-Nov-09 26-Dec-09 26-Jan-10 26-Jan-10 16-Feb-10 23-Mar-10 01-Apr-10 30/Jan/11 Planned 15-Mar-08 15-Apr-08 18-May-08 18-May-08 18-Jun-08 18-Aug-08 25/Apr/09 Combined SSD and Mesqa improvement Abdalla El Kholy and his partners for 13 Mahmoudia IIIMP/IIS/MAHM/W06-2008 1,049 NCB Revised Prior No 8,274,495.00 EGP General contracting in G. El-Bably + G. Sharaf + G. El-Baradi Actual 15-Apr-08 10-Sep-08 08-Oct-08 08-Oct-08 06-Nov-08 01-Dec-08 10-Feb-09 07-Dec-09 Total completed contracts Ongoing Area Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Contract Contract Contract Package reference No/ Procurement Bank Preference Bid Document Closing Signing Contract Name, City, and Country of Completion SL No District Description of Works Status Commencement Contract Value Contract No method Currency Contractor (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Meska Improvement Works in G. Planned 01-Mar-10 18-Mar-10 18-Apr-10 18-Apr-10 18-May-10 15-Jun-10 20/Feb/11 Revised Al Kholy Company for contracting 1 Mahmoudia IIIMP/IIS/MAHM/MQ-02-2009 Shebrakhiet, G. Kafr El-Rahmania and Al- 1,317 NCB Prior No 6,188,537.40 EGP and Engineering Works Moorda Branch Canals Actual 30-Apr-09 08-Jul-09 08-Aug-09 08-Aug-09 23/Aug/09 14-Oct-09 15-Oct-09 Total ongoing contracts Planned Area Review by Domestic Preparation of Bid Invitation Bid Bid Opening BER Contract Contract Contract Package reference No/ Procurement Bank Preference Bid Document Closing Signing Contract Name, City, and Country of Completion SL No District Description of Works Status Commencement Contract Value Contract No method Currency Contractor (Date) (fed) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) (Date) Sheet Mesqa Improvement, page 5 of 7 Procurement Plan for Drainage Rehabilitation Works (Mahmodia Area) Updated 30/06/2014 Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Bid Contract Area Domestic Preparation of Bid Bid Invitation Bid Opening Closing Contract Signing Package reference No/ Procurement Preference Document Contract Contract Completion SL No District Description of Works Status BER Contract Value Name, City, and Country of Contractor Contract No method Commencement (Date) Currency (Date) (fed) (yes/no) (Date) (Date) (Date) (Date) (Date) Planned 15-May-07 24-Sep-07 2/Oct/08 1 Abu Hommos IIIMP/EPAD/MAHM/W01-2007 Pitching Abo hommos drain NCB Revised No 2,112,000.00 EGP Mohammed Badawy Mohammed Actual 31-May-07 28-Feb-08 24-Mar-08 24-Mar-08 15-Jul-08 21-Sep-08 21-Sep-08 24/May/11 Planned 15-May-07 24-Sep-07 27/Mar/09 Rehabilitation of civil works for Abo Mohamed Ahmad Mousa El 2 Abu Hommos IIIMP/EPAD/MAHM/W02-2007 NCB Revised No 3,401,750.00 EGP hommos II Sakran Actual 17-Feb-08 28-Feb-08 26-Mar-08 26-Mar-08 15-Jul-08 19-Aug-08 21/Sep/08 20-Mar-10 Planned 15-Sep-08 01-Feb-09 10/Feb/10 Embankment Protection for El-Atf, El- 3 Mahmoudia IIIMP/EPAD/MAHM/W03-2008 NCB Revised No 01-Mar-09 2,610,250.00 EGP Al Phara'na office for Contracting 10/Mar/10 Bably and Omleet Drains Actual 17-Nov-08 17-Jan-09 17-Feb-09 17-Feb-09 24-Mar-09 21-Apr-09 21-Apr-09 28-Dec-09 Planned 01-Dec-10 30/Nov/11 Deepening and Widening of Zawiet ghazal 4 Mahmoudia IIIMP/EPADP/MAHM/W04-2010 NCB Revised No 20-May-10 1/Mar/11 28/Feb/11 1,951,450.00 EGP Eng. Ahmed Hassan Al -Shendy 27/Feb/12 open drain Actual 17-May-10 21-Aug-10 26-Sep-10 26-Sep-10 6/Dec/10 1/Mar/11 1/Mar/11 3/Apr/12 Planned 15-Sep-08 01-Feb-09 5/Aug/10 Rehabilitation of Subsurface Drainage Al - Eman company for 5 Abu Hommos IIIMP/EPAD/MAHM/SSD01- 2009 2,400 NCB Revised No 04-Feb-10 01-Jun-10 5,611,262.40 EGP 3/Dec/11 Networks in Abo Hommos 3 Area contracting Actual 02-Jul-09 23-Aug-09 28-Sep-09 28-Sep-09 30-May-10 1/Jul/10 01-Jul-10 24/Dec/13 Planned 26-Feb-09 13-Dec-09 12/Dec/11 Subsurface Drainage Networks in Abo El-Rashedia Company for General 6 Abu Hommos IIIMP/EPAD/MAHM/SSD02 2009 3,450 NCB Revised No 04-Feb-10 01-Jun-10 8,255,950.00 EGP 30/May/12 Hommos 2 Area Contracting Actual 02-Jul-09 23-Aug-09 27-Sep-09 27-Sep-09 15-Jun-10 11/Jul/10 15/Jul/10 25/Sep/12 Replacement and Rehabilitation of Planned 01-Feb-10 01-Oct-10 01-Sep-10 31/Aug/11 Subsurface Drainage Works in Part of Al- El-Rashedia Company for General 7 Mahmoudia IIIMP/EPADP/MAHM/SSD03-2009 Lawia 1st Command Area of Ryah 1,600 NCB Revised No 13-Dec-09 30-Nov-10 07-Dec-10 3,633,470.00 EGP 6/Dec/11 Contracting Zarkoon 1600 feddan Mahmoudia Command Area Actual 21-Apr-10 10-May-10 10-Jun-10 10-Jun-10 07-Nov-10 15/Dec/10 15/Dec/10 30/Jan/12 Replacement and Rehabilitation of Planned 20-Dec-09 01-Apr-10 5/Jul/11 Abdalla El Kholy and his partners 8 Mahmoudia IIIMP/EPADP/MAHM/SSD04-2010 Subsurface Drainage Works in Al-Atf the 2,500 NCB Revised No 30-Nov-10 07-Dec-10 5,110,485.00 EGP 4/Mar/12 for General contracting 2nd (A) El Mahmoudia Command Area Actual 19-Apr-10 18-May-10 20-Jun-10 20-Jun-10 10-Nov-10 13/Dec/10 13/Dec/10 2/Jul/12 Replacement and Rehabilitation of Planned 20-Dec-09 01-Apr-10 3/Oct/11 Subsurface Drainage Works in Al-Atf the 9 Mahmoudia IIIMP/EPADP/MAHM/SSD05-2010 3,400 NCB Revised No 21-Nov-10 30-Nov-10 6,122,930.50 EGP El Salam for general contracting 23/May/12 2nd (B) 3400 feddan Mahmoudia Command Area Actual 19-Apr-10 18-May-10 22-Jun-10 22-Jun-10 01-Nov-10 13/Nov/10 13/Nov/10 10/Apr/11 Total completed contracts Ongoing Bid Contract Area Domestic Preparation of Bid Bid Invitation Bid Opening Closing Contract Signing Package reference No/ Procurement Preference Document Contract Contract Completion SL No District Description of Works Status BER Contract Value Name, City, and Country of Contractor Contract No method Commencement (Date) Currency (Date) (fed) (yes/no) (Date) (Date) (Date) (Date) (Date) Replacement and Rehabilitation of Planned 17-Mar-10 17-Jun-10 19/Dec/11 Abdalla El Kholy and his partners 1 Mahmoudia IIIMP/EPADP/MAHM/SSD06A/2012 Subsurface Drainage Works in El-Lawia (2)- 1,850 NCB Revised No 15/Jan/11 20/Apr/12 20/May/12 20/May/12 20/Sep/12 5/Oct/12 5,494,539.60 EGP 29/Mar/14 for General contracting A Actual 16/Jan/11 19/May/12 20/Jun/12 20/Jun/12 5/Sep/12 15/Oct/12 15/Oct/12 Replacement and Rehabilitation of Planned 17-Mar-10 17-Jun-10 19/Dec/11 Abdalla El Kholy and his partners 2 Mahmoudia IIIMP/EPADP/MAHM/SSD06B/2012 Subsurface Drainage Works in El-Lawia (2)- 2,320 NCB Revised No 15/Jan/11 20/Apr/12 20/May/12 20/May/12 10/Oct/12 25/Oct/12 6,636,105.00 EGP 18/Apr/14 for General contracting B Actual 16/Jan/11 19/May/12 24/Jun/12 24/Jun/12 8/Aug/12 25/Jul/12 5/Nov/12 Replacement and Rehabilitation of Planned 1/May/12 31/May/12 30/Jun/12 30/Jun/12 30/Jul/12 6/Aug/12 5/Aug/14 Irrigation company for puplic 3 Mahmoudia IIIMP/EPADP/MAHM/SSD8-2012 Subsurface Drainage Works in Zawiet 3,800 NCB Revised No 1/Aug/12 31/Aug/12 31/Aug/12 17/Feb/13 4/Mar/13 9,135,565.75 EGP 3/Mar/15 works ghazal Actual 7/Jun/12 15/Aug/12 30/Sep/12 30/Sep/12 23/Oct/12 20/Mar/13 20/Mar/13 Replacement and Rehabilitation of Planned 10/Dec/11 15/Mar/12 14/Apr/12 14/Apr/12 14/May/12 29/May/12 20/Nov/13 Egyptian Company for Irrigation 4 Mahmoudia IIIMP/EPADP/MAHM/SSD09-A-2012 Subsurface Drainage Works in El Bably 1st 2,650 NCB Revised No 15/Mar/12 14/Apr/12 14/Apr/12 10/Aug/12 25/Aug/12 6,353,400.20 EGP and Drainage 16/Feb/14 (A) Actual 23/Jan/12 6/Mar/12 21/Apr/12 21/Apr/12 15/Aug/12 15/Sep/12 15/Sep/12 Replacement and Rehabilitation of Planned 10/Dec/11 15/Mar/12 14/Apr/12 14/Apr/12 14/May/12 29/May/12 20/Nov/13 Mohamed Lotfy Mahmoud Abo- 5 Mahmoudia IIIMP/EPADP/MAHM/SSD09-B-2012 Subsurface Drainage Works in El Bably 1st 2,200 NCB Revised No 15/Mar/12 14/Apr/12 14/Apr/12 10/Aug/12 25/Aug/12 5,479,414.90 EGP 16/Feb/14 Elnile for contracting (B) Actual 23/Jan/12 6/Mar/12 21/Apr/12 21/Apr/12 15/Aug/12 15/Sep/12 15/Sep/12 Replacement and Rehabilitation of Planned 01-Jan-13 01-Apr-13 8/Apr/13 30/Sep/14 6 Abu Hommos IIIMP/EPADP/MAHM/SSD10-A-2013 Subsurface Drainage Works in Zawiet 2,100 NCB Revised No 10/May/13 18/May/13 17/Jun/13 17/Jun/13 15/Jul/13 1/Aug/13 16/Aug/13 5,718,512.50 EGP Egyptian Real State Company 7/Feb/15 Naem (A) Actual 30/Mar/13 25/Jun/13 24/Jul/13 24/Jul/13 18/Sep/13 7/Oct/13 24/Nov/13 Replacement and Rehabilitation of Planned 01-Jan-13 01-Apr-13 8/Apr/13 30/Sep/14 7 Abu Hommos IIIMP/EPADP/MAHM/SSD10-B-2013 Subsurface Drainage Works in Zawiet 1,900 NCB Revised No 10/May/13 18/May/13 17/Jun/13 17/Jun/13 15/Jul/13 1/Aug/13 16/Aug/13 5,101,300.00 EGP Egyptian Real State Company 7/Feb/15 Naem (B) Actual 30/Mar/13 25/Jun/13 25/Jul/13 25/Jul/13 18/Sep/13 7/Oct/13 25/Nov/13 Replacement and Rehabilitation of Planned 1/Apr/12 1/May/12 31/May/12 31/May/12 30/Jun/12 15/Jul/12 14/Jul/14 8 Mahmoudia IIIMP/EPADP/MAHM/SSD11-2012 Subsurface Drainage Works in Sharaf 3,400 NCB Revised No 1/Oct/12 31/Oct/12 30/Nov/12 30/Nov/12 29/May/13 15/Jun/13 30/Jun/13 9,076,453.20 EGP Abdalla Abd ElKawi ElTokhy 29/Jun/15 drain at Hammad menisi end Actual 5/Sep/12 29/Dec/12 30/Jan/13 30/Jan/13 11/Apr/13 13/Jun/13 15/Jun/13 Replacement and Rehabilitation of Planned 15/May/12 14/Jun/12 14/Jul/12 14/Jul/12 13/Aug/12 28/Aug/12 Cooperetive Society Productivity 19/Feb/14 9 Abu Hommos IIIMP/EPADP/MAHM/SSD12-A-2013 Subsurface Drainage Works in Abo 2,700 NCB Revised No 1/Jul/13 31/Jul/13 30/Aug/13 30/Aug/13 27/Sep/13 14/Oct/13 29/Oct/13 7,035,565.00 EGP for Reconstruction & 22/Apr/15 Hommos 1st (A) Development at Gharbia Actual 30/May/13 4/Aug/13 16/Sep/13 16/Sep/13 22/Oct/13 29/Oct/13 16/Dec/13 Replacement and Rehabilitation of Planned 15/May/12 14/Jun/12 14/Jul/12 14/Jul/12 13/Aug/12 28/Aug/12 19/Feb/14 Mohamed Lotfy Mahmoud Abo- 10 Abu Hommos IIIMP/EPADP/MAHM/SSD12-B-2013 Subsurface Drainage Works in Abo 2,900 NCB Revised No 1/Jul/13 31/Jul/13 30/Aug/13 30/Aug/13 27/Sep/13 14/Oct/13 29/Oct/13 8,234,000.00 EGP 22/Apr/15 Elnile for contracting Hommos 1st (B) Actual 30/May/13 4/Aug/13 19/Sep/13 19/Sep/13 2/Jan/14 2/Jan/14 Planned 1/Sep/12 1/Oct/12 31/Oct/12 31/Oct/12 30/Nov/12 15/Dec/12 8/Jun/14 Replacement and Rehabilitation of Revised 1/Apr/13 15/Mar/13 14/Apr/13 14/Apr/13 4/Jun/13 21/Jun/13 6/Jul/13 28/Dec/14 Abdalla El Kholy and his partners 11 Abu Hommos IIIMP/EPADP/MAHM/SSD13 (A)-2013 Subsurface Drainage Works in Abo El - 1,900 NCB No 5,881,868.00 EGP for General contracting Einen (1) A Actual 24/Dec/12 31/Mar/13 7/May/13 7/May/13 6/18/2013 Cancelled Actual 27/Jun/13 6/Aug/13 8/Sep/13 8/Sep/13 14/Nov/13 1/Feb/14 1/Feb/14 Planned 1/Sep/12 1/Oct/12 31/Oct/12 31/Oct/12 30/Nov/12 15/Dec/12 8/Jun/14 Replacement and Rehabilitation of Revised 1/Apr/13 15/Mar/13 14/Apr/13 14/Apr/13 5/Jun/13 22/Jun/13 7/Jul/13 29/Dec/14 12 Abu Hommos IIIMP/EPADP/MAHM/SSD13 (B)-2013 Subsurface Drainage Works in Abo El - 2,600 NCB No 8,322,225.00 EGP El Salam for general contracting Einen (1) B Actual 24/Dec/12 31/Mar/13 8/May/13 8/May/13 6/18/2013 Cancelled Actual 27/Jun/13 6/Aug/13 10/Sep/13 10/Sep/13 14/Nov/13 1/Feb/14 1/Feb/14 Planned 1/Oct/12 31/Oct/12 30/Nov/12 30/Nov/12 30/Dec/12 14/Jan/13 8/Jul/14 Replacement and Rehabilitation of Revised 1/Oct/13 15/Mar/13 14/Apr/13 14/Apr/13 23/Jun/13 10/Jul/13 25/Jul/13 Irrigation company for puplic 16/Jan/15 13 Abu Hommos IIIMP/EPADP/MAHM/SSD14 A-2013 Subsurface Drainage Works in Abo El - 2,750 NCB No 8,228,815.70 EGP works Einen (2- A) Actual 26/Nov/12 9/Apr/13 26/May/13 26/May/13 6/12/2013 Cancelled Actual 12/Jun/13 4/Aug/13 12/Sep/13 12/Sep/13 12/Jan/14 12/Jan/14 Planned 1/Oct/12 31/Oct/12 30/Nov/12 30/Nov/12 30/Dec/12 14/Jan/13 8/Jul/14 Replacement and Rehabilitation of Revised 1/Oct/13 15/Mar/13 14/Apr/13 14/Apr/13 27/Jun/13 14/Jul/13 29/Jul/13 Cooperetive Society Productivity 20/Jan/15 14 Abu Hommos IIIMP/EPADP/MAHM/SSD14 B-2013 Subsurface Drainage Works in Abo El - 2,200 NCB No 5,597,325.00 EGP of Irrigation Projects & Einen (2-B) Actual 26/Nov/12 9/Apr/13 30/May/13 30/May/13 6/18/2013 Cancelled Architecture Actual 18/Jun/13 4/Aug/13 5/Sep/13 5/Sep/13 5/Jan/14 9/Jan/14 Replacement and Rehabilitation of Planned 1/Nov/12 1/Dec/12 31/Dec/12 31/Dec/12 30/Jan/13 14/Feb/13 8/Aug/14 Irrigation company for puplic 15 Mahmoudia IIIMP/EPADP/MAHM/SSD15-2012 Subsurface Drainage Works in Abo El - 1,400 NCB Revised No 1/Dec/12 31/Dec/12 30/Jan/13 30/Jan/13 15/Mar/13 30/Mar/13 3,811,445.45 EGP 21/Sep/14 works Einen (3) Actual 9/Sep/12 27/Nov/12 1/Jan/13 1/Jan/13 11/Feb/13 15/Apr/13 15/Apr/13 Planned 15/Mar/13 14/Apr/13 14/May/13 14/May/13 13/Jun/13 28/Jun/13 20/Dec/14 Replacement and Rehabilitation of Revised 1/Apr/13 1/May/13 31/May/13 31/May/13 13/Jun/13 30/Jun/13 15/Jul/13 6/Jan/15 16 Abu Hommos IIIMP/EPADP/MAHM/SSD16A-2013 Subsurface Drainage Works in Mahalet 2,150 NCB No 7,119,350.00 EGP El tokhy Company for contracting Keel (2) A Actual 22/Jan/13 10/Apr/13 16/May/13 16/May/13 6/18/2013 Retender Actual 18/Jun/13 6/Aug/13 15/Sep/13 15/Sep/13 14/Nov/13 15/Feb/14 15/Feb/14 Planned 15/Mar/13 14/Apr/13 14/May/13 14/May/13 13/Jun/13 28/Jun/13 20/Dec/14 Replacement and Rehabilitation of Revised 1/Apr/13 1/May/13 31/May/13 31/May/13 16/Jun/13 3/Jul/13 18/Jul/13 9/Jan/15 17 Abu Hommos IIIMP/EPADP/MAHM/SSD16B-2013 Subsurface Drainage Works in Mahalet 2,650 NCB No 8,214,390.35 EGP El tokhy Company for contracting Keel (2) B Actual 22/Jan/13 10/Apr/13 19/May/13 19/May/13 6/18/2013 Retender Actual 18/Jun/13 6/Aug/13 18/Sep/13 18/Sep/13 14/Nov/13 15/Feb/14 15/Feb/14 Replacement and Rehabilitation of Planned 20/Jan/13 19/Feb/13 21/Mar/13 21/Mar/13 20/Apr/13 5/May/13 27/Oct/14 18 Abu Hommos IIIMP/EPADP/MAHM/SSD17A-2013 Subsurface Drainage Works in Waslat El 2,200 NCB Revised No 30/Mar/13 29/Apr/13 29/May/13 29/May/13 26/Jun/13 13/Jul/13 28/Jul/13 6,344,175.00 EGP Egyptian Dredging Company 19/Jan/15 Zeiny (2) A Actual 30/Mar/13 24/Jun/13 28/Jul/13 28/Jul/13 18/Sep/13 28/Dec/13 28/Dec/13 Replacement and Rehabilitation of Planned 20/Mar/13 19/Apr/13 19/May/13 19/May/13 18/Jun/13 3/Jul/13 25/Dec/14 19 Abu Hommos IIIMP/EPADP/MAHM/SSD17B-2013 Subsurface Drainage Works in Waslat El 1,900 NCB Revised No 1/Jun/13 1/Jul/13 1/Jul/13 29/Jul/13 15/Aug/13 30/Aug/13 4,901,795.00 EGP Egyptian Dredging Company 21/Feb/15 Zeiny (2) B Actual 30/Mar/13 24/Jun/13 29/Jul/13 29/Jul/13 18/Sep/13 29/Dec/13 29/Dec/13 Planned 10/Sep/13 10/Oct/13 9/Nov/13 9/Nov/13 9/Dec/13 24/Dec/13 19/Mar/15 Replacement and Rehabilitation of Revised 15/Mar/13 14/Apr/13 14/Apr/13 5/Jun/13 22/Jun/13 7/Jul/13 El-Rashedia Company for General 30/Sep/14 20 Abu Hommos IIIMP/EPADP/MAHM/SSD18A-2013 1,750 NCB No 4,547,450.00 EGP Subsurface Drainage Works in Zeiny (1) A 6/12/2013 Contracting Actual 26/Nov/12 25/Mar/13 8/May/13 8/May/13 Retender Actual 27/Jun/13 4/Aug/13 2/Sep/13 2/Sep/13 2/Jan/14 2/Jan/14 Planned 10/Sep/13 10/Oct/13 9/Nov/13 9/Nov/13 9/Dec/13 24/Dec/13 17/Jun/15 Replacement and Rehabilitation of Revised 15/Mar/13 14/Apr/13 14/Apr/13 9/Jun/13 26/Jun/13 11/Jul/13 2/Jan/15 21 Abu Hommos IIIMP/EPADP/MAHM/SSD18B-2013 2,950 NCB No 8,283,130.75 EGP El tokhy Company for contracting Subsurface Drainage Works in Zeiny (1) B Actual 26/Nov/12 25/Mar/13 12/May/13 12/May/13 6/12/2013 Retender Actual 27/Jun/13 4/Aug/13 9/Sep/13 9/Sep/13 1/Oct/13 9/Jan/14 Planned 18/May/13 17/Jun/13 17/Jul/13 17/Jul/13 16/Aug/13 31/Aug/13 30/Aug/15 Replacement and Rehabilitation of Revised 15/Mar/13 14/Apr/13 14/Apr/13 12/Jun/13 29/Jun/13 14/Jul/13 13/Jul/15 General Company for Land 22 Abu Hommos IIIMP/EPADP/MAHM/SSD19-2013 Subsurface Drainage Works in Mahalet 2,700 NCB No 7,684,870.00 EGP Reclamation Keel (1) Actual 23/Oct/12 10/Apr/13 15/May/13 15/May/13 6/18/2013 Retender Actual 6/Aug/13 11/Sep/13 11/Sep/13 14/Nov/13 1/Feb/14 1/Feb/14 Planned Bid Contract Area Domestic Preparation of Bid Bid Invitation Bid Opening Closing Contract Signing Package reference No/ Procurement Preference Document Contract Contract Completion SL No District Description of Works Status BER Contract Value Name, City, and Country of Contractor Contract No method Commencement (Date) Currency (Date) (fed) (yes/no) (Date) (Date) (Date) (Date) (Date) Planned 01-Jun-10 01-Dec-10 14/May/12 Rehabilitation and Pitching works Revised 1/Jun/14 1/Jul/14 31/Jul/14 31/Jul/14 13/Aug/14 30/Aug/14 6/Sep/14 5/Sep/15 1 Various IIIMP/EPADP/MAHM/W05 NCB No EGP Rahmania & other drains Revised 1/Oct/14 31/Oct/14 30/Nov/14 30/Nov/14 13/Dec/14 30/Dec/14 6/Jan/15 5/Jan/16 Actual Procurement Plan for Miscellaneous Works (Mahmodia Area) Updated 30/06/2014 Arab republic of Egypt EGT-7291: Integrated Irrigation Improvement & Management Project Original:28/2/2008 Completed Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Contract Signing Package reference No/ Bank Preference Document Closing Contract Completion Completion of Completion SL No District Description of Works Status Contract Value Name, City, and Country of Contractor Contract No (Date) Currency Contract (Date) Date (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) Ongoing Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Contract Signing Package reference No/ Bank Preference Document Closing Contract Completion Completion of SL No District Description of Works Status Contract Value Name, City, and Country of Contractor Contract No Currency Contract (Date) (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) Planned Review by Domestic Preparation of Bid Bid Invitation Bid Bid Opening BER Contract Contract Signing Package reference No/ Bank Preference Document Closing Contract Completion Completion of SL No District Description of Works Status Contract Value Name, City, and Country of Contractor Contract No Currency Contract (Date) (Date) (prior/post) (yes/no) (Date) (Date) (Date) (Date) (Date) (Date) Planned 15/Dec/10 15/Jan/11 15/Feb/11 15/Feb/11 15/Mar/11 11/Sep/11 Damanhour/Ka 1 IIIMP/IS/MAHM/MIS-09-2010 Shed for 2.5 bar-PVC Pipe Protection Revised Post No 1/Dec/11 31/Dec/11 30/Jan/12 30/Jan/12 29/Feb/12 EGP 27/Aug/12 fr El Dawar Actual Cancelled