The World Bank Report No: ISR10020 Implementation Status & Results China ZhangHu Railway (P122319) Public Disclosure Copy Operation Name: ZhangHu Railway (P122319) Project Stage: Implementation Seq.No: 3 Status: ARCHIVED Archive Date: 16-May-2013 Country: China Approval FY: 2012 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 15-Mar-2012 Original Closing Date 30-Jun-2018 Planned Mid Term Review Date Last Archived ISR Date 12-Nov-2012 Effectiveness Date 03-Aug-2012 Revised Closing Date 30-Jun-2018 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective of the proposed project is to improve accessibility and mobility by responding to existing and anticipated transport demand along the Hohhot-Zhangjiakou (to Beijing) corridor through the provision of additional railway capacity and reduction of transport time for passengers and freight. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost ZhangHu Railway Line 199.50 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Public Disclosure Copy Overall Risk Rating Moderate Moderate Implementation Status Overview The Bank and the government counterparts held the project launch on March 27 - 28 2013 to establish a common understanding between the stakeholders on the principle of successful implementation. The environmental and social safeguards teams have been selected andthey started the preparation works. As for the contractor for the civil works and supervision companies, the implementing agency and the tendering company are preparing to start the selection process. The civil works funded by the Bank are expected to commence by August 2013 as planned. No major issue related to the achievement of the Project Development Objective was noted. Locations Page 1 of 4 The World Bank Report No: ISR10020 Country First Administrative Division Location Planned Actual China Inner Mongolia Inner Mongolia Autonomous Region ✔ Public Disclosure Copy Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of train pairs operating per day on the Number Value 25.00 ZhangHu Railway line Date 28-Mar-2013 31-Dec-2018 Comments N/A The project implementation Taken as first full year of has not yet begun. operation. As this is a new line, achievement of the objective cannot begin to be measured until the line is open to traffic. Number of passengers travelling on the Text Value 9 ZhangHu Railway line (millions) Date 28-Mar-2013 31-Dec-2018 Comments N/A The project implementation Taken as first full year of has not yet begun. operation. As this is a new line, achievement of the objective cannot begin to be measured until the line is open to traffic. Reduced transit time for passengers travelling Minutes Value 411.00 100.00 between Zhangjiakou and Huhehaote Date 28-Mar-2013 31-Dec-2018 Comments The project implementation Taken as first full year of has not yet begun. operation. As this is a new line, achievement of the objective cannot begin to be measured until the line is Public Disclosure Copy open to traffic. Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Completion rate of civil works (cumulative) Percentage Value 0.00 0.00 100.00 Date 31-Dec-2010 28-Mar-2013 31-Dec-2017 Comments The project implementation has not yet begun. Page 2 of 4 The World Bank Report No: ISR10020 Delivery of Bank financed goods Percentage Value 0.00 0.00 100.00 Date 31-Dec-2010 28-Mar-2013 31-Dec-2017 Comments The project implementation Public Disclosure Copy has not yet begun. Data on Financial Performance (as of 03-Aug-2012) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P122319 IBRD-81310 Effective 15-Mar-2012 18-May-2012 03-Aug-2012 30-Jun-2018 30-Jun-2018 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P122319 IBRD-81310 Effective USD 200.00 200.00 0.00 0.50 199.50 0.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation The next supervision mission will take place in October 2013 when the construction works have commenced. Restructuring History Page 3 of 4 The World Bank Report No: ISR10020 There has been no restructuring to date. Related Projects Public Disclosure Copy There are no related projects. Public Disclosure Copy Page 4 of 4