Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Road Asset Management Project (P123961) Vietnam Road Asset Management Project (P123961) EAST ASIA AND PACIFIC | Vietnam | Transport Global Practice | IBRD/IDA | Specific Investment Loan | FY 2014 | Seq No: 2 | ARCHIVED on 20-Jan-2015 | ISR17399 | Implementing Agencies: Project Management Unit No. 3 (PMU3) Key Dates Key Project Dates Board Approval date:12-Dec-2013 Effectiveness Date:11-Apr-2014 Planned Mid Term Review Date:31-Dec-2017 Actual Mid-Term Review Date:28-Nov-2014 Original Closing Date:31-Dec-2020 Revised Closing Date:31-Dec-2020 Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed Project Development Objective (PDO) is to improve the efficiency and sustainability of the national road asset management and maintenance practices performed by the Ministry of Transport on national roads in Vietnam. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component A: Road Asset Management System (RAMS) Development:(Cost $10.00 M) Component B: Road Asset Preservation:(Cost $156.60 M) Component C: Road Asset Improvement:(Cost $133.40 M) Component D: Institutional Strengthening Program:(Cost $1.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Satisfactory  Satisfactory Overall Risk Rating  --  Moderate 1/20/2015 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Road Asset Management Project (P123961) Implementation Status and Key Decisions The project was approved by the Board on December 12, 2013, and the activities under each component are in procurement. Preparation for the Road Asset Management System development, detailed designs for maintenance and improvements of the project roads, and preparation for technical assistance for institutional strengthening program are underway. The Financing Agreement was signed on January 14, 2014, and became effective on April 11, 2014. The next implementation review mission is scheduled in March/April 2015. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  --  Moderate Macroeconomic  --  --  Moderate Sector Strategies and Policies  --  --  Moderate Technical Design of Project or Program  --  --  Substantial Institutional Capacity for Implementation and Sustainability  --  --  Moderate Fiduciary  --  --  Moderate Environment and Social  --  --  Moderate Stakeholders  --  --  Low Other  --  --  -- Overall  --  --  Moderate 1/20/2015 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Road Asset Management Project (P123961) Results Project Development Objective Indicators PHINDPDOTBL  Annual and mid-term (3 years) plans for priority and implementation of national road network maintenance and long-term (10 years) maintenance strategy generated by RAMS (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 PHINDPDOTBL  Data collection: completed for -Road surface conditions for about 2300km road under RRMU No.2 /17,748km highway; - Inventory of about 4700 bridges on the whole national road network. (Yes/No, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value -- -- -- -- Date 31-Dec-2016 -- 03-Dec-2014 31-Dec-2019 PHINDPDOTBL  Improved financing of road maintenance measured by the increased maintenance financing covered by the RMF (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 70.00 70.00 70.00 100.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 PHINDPDOTBL  Expansion of PBC program in national road maintenance (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1700.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 Overall Comments 1/20/2015 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Road Asset Management Project (P123961) Intermediate Results Indicators PHINDIRITBL  Annual condition measurement for national road network (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 17748.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 PHINDIRITBL  PBC maintenance implemented under the project (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 170.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 PHINDIRITBL  Km of roads maintained under the project with traditional input method (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 161.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 PHINDIRITBL  Km of roads improved under the project (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 56.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 1/20/2015 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Road Asset Management Project (P123961) PHINDIRITBL  Annual audit of Road Maintenance Fund published and available for civil society (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 20-Sep-2013 17-Jan-2014 30-Nov-2014 31-Dec-2020 Comments The annual audit report for 2013 expenditure by RMF was released in November 2014. PHINDIRITBL  Roads in good and fair condition as a share of total classified roads (Percentage, Core) Baseline Actual (Previous) Actual (Current) End Target Value 70.00 70.00 70.00 72.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 PHINDIRITBL  Size of the total classified network (Kilometers, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 17748.00 17748.00 17748.00 17748.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 PHINDIRITBL  Percentage of affected households having woman attended consultation activities on compensation/resettlement (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 50.00 50.00 50.00 80.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2017 1/20/2015 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Road Asset Management Project (P123961) PHINDIRITBL  Semi-annual Project Monitoring and Evaluation Report will be submitted to the Bank (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 2.00 14.00 Date 20-Sep-2013 17-Jan-2014 03-Dec-2014 31-Dec-2020 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P123961 IDA-53310 Effective USD 250.00 250.00 0.00 3.50 247.54 1% P123961 TF-15733 Effective USD 1.57 1.57 0.00 0.00 1.57 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P123961 IDA-53310 Effective 12-Dec-2013 14-Jan-2014 11-Apr-2014 31-Dec-2020 31-Dec-2020 P123961 TF-15733 Effective 14-Jan-2014 14-Jan-2014 14-Jan-2014 30-Jun-2016 30-Jun-2016 Cumulative Disbursements 1/20/2015 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Road Asset Management Project (P123961) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 1/20/2015 Page 7 of 7 Public Disclosure Copy