Document of The World Bank Report No: 74072-KG RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND VILLAGE INVESTMENT PROJECT CREDIT (46570-KG) GRANT (H2500- KG) GRANT (H5190-KG) BOARD APPROVAL: NOVEMBER 3, 2009 TO THE KYRGYZ REPUBLIC NOVEMBER 30, 2012 Regional Vice President: Philippe H. Le Houerou Country Director: Saroj Kumar Jha Sector Manager / Director: Elisabeth Huybens Task Team Leader: Aly Zulficar Rahim 2 SECOND VILLAGE INVESTMENT PROJECT P098949 CREDIT (46570-KG) GRANT (H2500- KG) GRANT (H5190-KG) Restructuring Paper 1. The closing date for Second Village Investment Project, Credit 46570-KG (original financing) and Second Village Investment Project Additional Financing, Grant H2500- KG, and Grant H5190 - KG, will be extended from December 31, 2012 to June 29, 2013, following the formal letter from the Government of Kyrgyzstan dated November 8, 2012, requesting extension of the project’s closing date. No other changes are proposed. 2. The Project Development Objective (PDO) continues to be achievable and could be realized by the proposed extension of the closing date based on renewed commitment of the Ministry of Finance and of the implementing agency, ARIS. 3. Project implementation has been and continues to be satisfactory. The project has reached each of the 475 aiyl okrugs (local municipalities) in the country and has gained strong recognition amongst the rural population. More than 70,900 local government officials and community members have been trained in principles of budgeting and planning, and 1,698 villages have gained access to improved social and economic infrastructure. Approximately 2.3 million people have benefited directly from the completion of about 6000 micro-projects. 4. The proposed extension is necessary to enable the implementing agency to continue with structural remediation works required for technically complex infrastructure built before 2009 by this project and its predecessor (Village Investment Project). The extension requested will accommodate ongoing remediation works as well as technical designs for works which are due to continue under the proposed Second Additional Financing, which will close the unanticipated financing gap resulting from an underestimate of the cost of works to remedy the structural deficiencies. The Board date for the Second Additional Financing is December 20, 2012 and the Project Paper proposes a closing date of October 31, 2014. 5. The team is pleased to confirm that the Recipient has in place an action plan to complete the project. More specifically, a preliminary assessment of works needed has been produced by an engineering firm and a procurement plan has been prepared. The team also confirms that there are no outstanding audit reports and that previous audit reports were found satisfactory. 6. This will be the second extension of the (first) Additional Financing. The approval of a first Additional Financing set a closing date of December 31, 2011. The first extension to December 31, 2012 was approved through restructuring in June 2011. 3