Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan February 7, 2014. Revision of the Procurement Plan, February 8, 2017 2. Date of General Procurement Notice: Updated April 20, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year June 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 5 million All 2. NCB (Goods) Above US$ 4 million All 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 15 million All 5. ICB and LIB (Non-Consultant Services) Above US$ 5 million All 6. NCB (Non-Consultant Services) Above US$ 4 million All 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan IBRD 8353-BR was approved on January 8, 2014 and revised on December 23, 2015 by the Government of the State of Espirito Santo. Any Other Special Procurement Arrangements: Retroactive Financing - an aggregate amount not to exceed $20,000,000 equivalent may be made for payments made prior to this date but on or after October 1, 2013, for Eligible Expenditures. 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness June 5, 2017 Goods and Works Estimated Review Cost by Bank Comments US$ Description of Assignment million (Prior / Post) SEAMA-1F2 / Aquisição de Equipamentos para o Sistema de Informações Ambiental 4.9 Prior Single CESAN-2B5 / Works at Vila Velha and Cariacica 164 Prior Stage III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2 million All 2. Single Source (Firms) Above US$ 2 million All 3. Individual Above US$ 0.4 million All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $1.5 million equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule Consultant Services Estimated Review Cost by Bank Comments US$ Description of Assignment million (Prior / Post) SEAMA-1F1 / Study and Projects for the development 2.34 Prior of the Environmental Management System. QCBS CESAN-2B1 / Supervision of works and execution of socio-environmental of the sewage systems in nine 2.8 Prior municipalities of the countryside of the State of QCBS - Espirito Santo Initiated CESAN-4A1 / Management of the RMGV Works 18 Prior QCBS - Supervision Program Initiated ARSP-4B1 / Revision and Tariff Restructuring of the 1.8 Prior Sanitation Services and Regulatory Accounting QCBS June 5, 2017 June 5, 2017 PROCUREMENT Brazil : BR Espirito Santo Integrated Sustainable Water Management Project PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2017-02-08 2019-10-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P130682 GPN Date: 2017-04-20 Project Name: BR Espirito Santo Integrated Sustainable Water Management Project Loan / Credit No: IBRD / 83530 Executing Agency(ies): Executive Secretariat of the State of Espirito Santo WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Efficient Water Supply CESAN-2B6 / Contratacao Solicitação de Open - Single Stage - One IBRD / 83530 Services and Increased Prévia 0.00 Cancelado 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Obras de Cariacica Propostas International Envelope Access to Sanitation CESAN-2B3 / Execucao de obras e servicos de Implantacao, Reabilitacao e Efficient Water Supply Ampliacao de Sistemas de Solicitação de Single Stage - One IBRD / 83530 Services and Increased Posterior Open - National 6,059,394.19 Assinado 2017-04-28 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2018-02-14 Esgotamento Sanitario de Propostas Envelope Access to Sanitation Conceicao do Castelo, Divino de Sao Lourenco e Marechal Floriano CESAN-2B4 / Execucao de obras e servicos de Implantacao, Reabilitacao e Efficient Water Supply Solicitação de Single Stage - One Ampliacao de Sistemas de IBRD / 83530 Services and Increased Posterior Open - National 7,582,813.99 Assinado 2017-06-10 2017-06-15 2017-07-27 2017-08-26 2017-09-30 2018-03-29 Propostas Envelope Esgotamento Sanitario de Access to Sanitation Santa Leopoldina e Santa Maria de Jetiba CESAN-3B2 / Construcao Watershed Management and Solicitação de Single Stage - One de equipamentos sociais a IBRD / 83530 Posterior Open - National 0.00 Cancelado 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Restoration of Forest Cover Propostas Envelope margem do Mangarai CESAN-3B6 / Adequacao e recuperacao de Estradas Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-03-15 2017-03-20 2017-05-01 2017-05-31 2017-07-05 2018-01-01 vicinais de terra, com Restoration of Forest Cover Propostas Envelope confeccao de caixas secas CESAN-2B5 / Contratacao Efficient Water Supply Solicitação de Open - Single Stage - One Obras de Vila Velha e IBRD / 83530 Services and Increased Prévia 0.00 Cancelado 2017-05-30 2017-06-04 2017-07-16 2017-08-15 2017-09-19 2018-03-18 Propostas International Envelope Cariacica Access to Sanitation Efficient Water Supply CESAN-2B7 / DBO de Vila Solicitação de Open - Single Stage - One IBRD / 83530 Services and Increased Prévia 0.00 Cancelado 2017-12-18 2018-04-05 2018-04-05 2018-02-07 2018-05-20 2018-06-04 2018-07-09 2024-06-07 Velha. Propostas International Envelope Access to Sanitation Efficient Water Supply CESAN-2B8 / Contratacao Solicitação de Open - Single Stage - One IBRD / 83530 Services and Increased Prévia 0.00 Cancelado 2018-01-15 2018-01-20 2018-03-03 2018-04-02 2018-05-07 2021-04-21 de Obras Cariacica Propostas International Envelope Access to Sanitation CESAN-2B10 / Contratação das Obras de ampliação do Efficient Water Supply sistema de coleta de esgoto Solicitação de Open - Single Stage - One IBRD / 83530 Services and Increased Prévia 47,000,682.26 Assinado 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 2018-11-24 da ETE Bandeirantes para Propostas International Envelope Access to Sanitation Bairros Cariacica e Viana, em dois Lotes. Page 1 Efficient Water Supply CESAN 2 B5 / DBO de Solicitação de Open - IBRD / 83530 Services and Increased Prévia Multi Stage 0.00 Cancelado 2018-04-26 2018-04-26 2018-05-30 2018-04-26 2018-08-08 2018-11-20 2018-12-25 2020-06-17 Vila Velha Propostas International Access to Sanitation Efficient Water Supply Em fase de CESAN-2 B5 / DBO de Solicitação de Open - IBRD / 83530 Services and Increased Prévia Multi Stage 0.00 Implementaçã 2017-11-17 2018-04-23 2018-05-23 2017-12-18 2018-08-08 2018-11-20 2018-12-25 2020-06-17 Vila Velha. Propostas International Access to Sanitation o INCAPER 3B5-4 / Construção de Obras de Em fase de Watershed Management and Solicitação de Single Stage - One Adequação e Recuperação de IBRD / 83530 Posterior Open - National 0.00 Implementaçã 2018-10-10 2018-10-15 2018-11-26 2018-12-26 2019-01-30 2019-07-29 Restoration of Forest Cover Propostas Envelope Estradas Vicinais e o Construção de Caixas Secas DEFESA CIVIL-1H7 / Construção do Centro Integrated Water Solicitação de Single Stage - One Estadual de Gerenciamento IBRD / 83530 Management and Disaster Prévia Open - National 0.00 Cancelado 2018-07-13 2018-07-18 2018-08-29 2018-09-28 2018-11-02 2019-05-01 Propostas Envelope de Risco e Desastre do Risk Management Espírito Santo. SEAMA 1H7 / Construção Integrated Water Em fase de do Centro Estadual de Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Prévia Open - National 0.00 Implementaçã 2018-10-24 2018-11-23 2019-01-04 2019-02-03 2019-03-10 2019-09-06 Gerenciamento de Risco e Propostas Envelope Risk Management o Desastre do Espírito Santo CESAN 2B9 / Execucao de obras e servicos de Implantacao, Reabilitacao e Ampliacao de Sistemas de Efficient Water Supply Em fase de Solicitação de Single Stage - One Esgotamento Sanitario de IBRD / 83530 Services and Increased Prévia Open - National 0.00 Implementaçã 2018-11-09 2018-12-04 2019-01-18 2019-02-17 2019-03-24 2019-09-20 Propostas Envelope Domingos Martins , Distrito Access to Sanitation o de Pedra Menina e Afonso Cláudio (Lote 1) e Castelo (Lote 2) SEAMA-3B6 / Adequacao e recuperacao de Estradas Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-07-31 2017-08-05 2017-09-16 2017-10-16 2017-11-20 2018-05-19 vicinais de terra, com Restoration of Forest Cover Propostas Envelope confeccao de caixas secas SEAMA-3B2 / Construcao Watershed Management and Solicitação de Single Stage - One de equipamentos sociais a IBRD / 83530 Posterior Open - National 0.00 Cancelado 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Restoration of Forest Cover Propostas Envelope margem do Mangarai CESAN-2B2 / Implantacao, Reabilitacao e Ampliacao de Efficient Water Supply Solicitação de Single Stage - One Implementaçã Sistemas de Esgotamento IBRD / 83530 Services and Increased Prévia Open - National 0.00 2016-07-16 2016-07-21 2016-08-06 2016-08-21 2016-08-31 2019-02-17 Propostas Envelope o Pendente Sanitario de Dores do Rio Access to Sanitation Preto, Ibatiba, Irupi e Iuna GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CESAN-2A3 / Aquisicao de Motores Eletricos de Alta Efficient Water Supply Eficiencia para substituicao Solicitação de Single Stage - One IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 de equipamentos diversos na Propostas Envelope Access to Sanitation CESAN (Item 8 Efic Energetica) Page 2 CESAN-2A6 / Aquisicao de Motores Eletricos de Alta Efficient Water Supply Em fase de Eficiencia para substituicao IBRD / 83530 Services and Increased Posterior Leilões eletrônicos Open 0.00 Implementaçã 2017-11-28 2017-12-17 2018-01-21 2018-07-20 de equipamentos diversos na Access to Sanitation o CESAN (Item 8 Efic Energética) DEFESA CIVIL-1H32 / Integrated Water Solicitação de Single Stage - One Aquisicao de equipamentos IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-04-10 2017-04-15 2017-05-27 2017-06-26 2017-07-31 2018-01-27 Propostas Envelope de comunicacao e outros Risk Management SEAMA-1F2 / Aquisicao de Integrated Water Solicitação de Single Stage - One Hardware para o Sistema de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Propostas Envelope Informacoes Ambiental Risk Management SEAMA-1F8 / Aquisicao de Integrated Water Em fase de Hardware para o Sistema de IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Implementaçã 2017-11-28 2017-12-17 2018-01-21 2018-07-20 Informacoes Ambiental Risk Management o DEFESA CIVIL-1H5 / Integrated Water Solicitação de Single Stage - One Aquisicao de estacoes moveis IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-05-20 2017-05-25 2017-07-06 2017-08-05 2017-09-09 2018-03-08 Propostas Envelope de tratamento de agua Risk Management SEAMA-1C1 / Aquisicao de Integrated Water Implementaçã sondas multiparametricas IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 2018-06-04 2018-06-23 2018-07-28 2019-01-24 o Pendente portateis. Risk Management CESAN 2A2 / Serviços de Modernização Efficient Water Supply (Retrofit/Revamp) de Bombas IBRD / 83530 Services and Increased Prévia Aquisição Direta Direct 2,959,180.53 Assinado 2018-07-19 2018-08-15 2018-09-11 2020-10-09 Verticais de Grande Porte Access to Sanitation do Sistema de Produção e Água da RMGV CESAN-2A2 / Reforma ou substituicao das bombas de grande porte da CESAN, Efficient Water Supply Solicitação de Single Stage - One com intuito de recuperacao IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 Propostas Envelope do rendimento eletrico dos Access to Sanitation equipamentos (Item 6 Efic Energetica) AGERH-1C2 / Aquisicao de 03 medidores de vazao para conduto forcado, 01 medidor Integrated Water de vazao para pequenas Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-05-22 2017-05-27 2017-07-08 2017-08-07 2017-09-11 2018-03-10 profundidades, 01 medidor Propostas Envelope Risk Management de vazao para medias e grandes profundidades e 04 sondas multiparametros DEFESA CIVIL-1H31 / Aquisicao de mobiliario para Integrated Water Solicitação de Single Stage - One Coordenadorias Regionais e IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-07-20 2017-09-14 2018-03-13 Cotações Envelope Municipais de Protecao e Risk Management Defesa Civil DEFESA CIVIL-1H321 / Integrated Water Aquisicao de veiculos para IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2017-11-20 2017-12-09 2018-01-13 2018-07-12 combate a incendio florestal Risk Management e outros DEFESA CIVIL-1H322 / Integrated Water Aquisicao de empilhadeira e IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2017-11-23 2017-12-18 2018-01-22 2018-07-21 mini escavadeira Risk Management DEFESA CIVIL-1H323 / Integrated Water Aquisicao de equipamentos IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2017-12-15 2018-01-03 2018-02-07 2018-08-06 para salvamento em Risk Management enchentes e outros Page 3 DEFESA CIVIL-1H6 / Integrated Water Aquisicao de estacoes moveis IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2017-12-05 2017-12-24 2018-01-28 2018-07-27 de tratamento de agua Risk Management SEAMA-1F7 / Aquisicao de Integrated Water Solicitação de Single Stage - One Fibra Ótica para o Sistema IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-07-04 2017-07-09 2017-08-20 2017-09-19 2017-10-24 2018-04-22 Propostas Envelope de Informacoes Ambiental Risk Management CESAN 2A10 / Fornecimento, configuração e implantação de sistema Efficient Water Supply Em fase de Solicitação de Single Stage - One móvel de dados e IBRD / 83530 Services and Increased Posterior Open - National 0.00 Implementaçã 2018-11-09 2018-12-04 2019-01-15 2019-02-14 2019-03-21 2019-09-17 Propostas Envelope planejamento de recursos na Access to Sanitation o manutenção eletromecânica da CESAN. CESAN 1A1 / Efficient Water Supply Em fase de Solicitação de Single Stage - One Monitoramento e Gestão de IBRD / 83530 Services and Increased Posterior Open - National 0.00 Implementaçã 2018-11-20 2018-12-15 2019-01-26 2019-02-25 2019-04-01 2019-09-28 Propostas Envelope Índices Elétricos (MGI). Access to Sanitation o SEAMA 1H31 / Aquisição de mobiliário para Integrated Water Solicitação de Single Stage - One Implementaçã Coordenadorias Regionais e IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2018-10-28 2018-11-12 2018-12-24 2019-01-23 2019-02-27 2019-08-26 Propostas Envelope o Pendente Municipais de Proteção e Risk Management Defesa Civil SEAMA 1H321 / Aquisicao Integrated Water Solicitação de Single Stage - One Implementaçã de veiculos para combate a IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2018-12-15 2018-12-30 2019-02-10 2019-03-12 2019-04-16 2019-10-13 Propostas Envelope o Pendente incendio florestal e outros Risk Management SEAMA 1H322 / Aquisicao Integrated Water Solicitação de Single Stage - One Implementaçã de empilhadeira e mini IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2018-10-28 2018-11-12 2018-12-24 2019-01-23 2019-02-27 2019-08-26 Propostas Envelope o Pendente escavadeira Risk Management SEAMA 1H323 / Aquisicao Integrated Water de equipamentos para Solicitação de Single Stage - One Implementaçã IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2018-10-28 2018-11-12 2018-12-24 2019-01-23 2019-02-27 2019-08-26 salvamento em enchentes e Propostas Envelope o Pendente Risk Management outros SEAMA 1H324 / Aquisição de Veículo do Tipo Integrated Water Solicitação de Single Stage - One Implementaçã Plataforma para transporte IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2018-12-21 2019-01-15 2019-02-26 2019-03-28 2019-05-02 2019-10-29 Propostas Envelope o Pendente de máquinas, equipamentos Risk Management e autossocorro de viaturas SEAMA-1F6 / Aquisicao de Integrated Water Solicitação de Single Stage - One Software para o Sistema de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-07-09 2017-09-03 2018-03-02 Cotações Envelope Informacoes Ambiental Risk Management SEAMA 1H10 / Estações Meteorológicas - Aquisição de 32 plataformas de coleta de Integrated Water Solicitação de Single Stage - One Implementaçã dados para complementar a IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2019-03-29 2019-05-18 2019-06-17 2019-07-17 2019-08-21 2019-11-19 Propostas Envelope o Pendente rede de monitoramento Risk Management meteorológica do Espirito Santo SEAMA-1H325 / Aquisição de 09 (nove) veículos Auto Bomba Tanque e Salvamento Integrated Water (ABTS) para fortalecer a Solicitação de Single Stage - One Implementaçã IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2019-04-02 2019-05-17 2019-06-16 2019-07-01 2019-08-05 2020-02-01 capacidade de resposta a Propostas Envelope o Pendente Risk Management desastre do Corpo de Bombeiros Militar do Espírito Santo. Page 4 CESAN 2A11 / Modernização e Ampliação Efficient Water Supply Solicitação de Single Stage - One da Telemetria, Telecomando IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2019-04-01 2019-04-16 2019-05-28 2019-06-27 2019-08-01 2020-07-26 Propostas Envelope e Centro de Controle Access to Sanitation Operacional. SEAMA 1H6 / Aquisição de Integrated Water Solicitação de Single Stage - One estações móveis de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-10-28 2018-11-17 2018-12-29 2019-01-28 2019-03-04 2019-08-31 Propostas Envelope tratamento de água Risk Management CESAN 4C7 / Aquisição de Project Management, Solicitação de Single Stage - One Implementaçã computadores para a gestão IBRD / 83530 Supervision and Posterior Open - National 0.00 2019-09-10 2019-10-25 2019-11-24 Cotações Envelope o Pendente do Projeto Institutional Strengthening SEAMA 1F7 / Implantação de infraestrutura de cabeamento óptico e Integrated Water telefônico, bem como de IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2018-10-30 2018-11-24 2018-12-13 2019-01-17 2019-07-16 implantação, com Risk Management fornecimento de equipamentos e acessórios de rede Wireless NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SEAMA-1D2 / Servicos de levantamento de batimetria Integrated Water Solicitação de Single Stage - One e medicao de ondas e IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-04-23 Propostas Envelope correntes da Costa do Risk Management Espirito Santo CESAN-3B1 / Elaboracao e Implementacao do Plano de Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Comunicacao Social do Restoration of Forest Cover Propostas Envelope Mangarai Project Management, CESAN-4C5 / Auditoria Solicitação de Single Stage - One IBRD / 83530 Supervision and Posterior Open - National 17,774.95 Assinado 2017-11-20 2018-01-15 2020-12-30 Externa do Projeto Cotações Envelope Institutional Strengthening CESAN-4C2 / Contratacao Project Management, Solicitação de Single Stage - One de modernizacao do Sistema IBRD / 83530 Supervision and Posterior Open - National 0.00 Cancelado 2017-02-10 2017-02-15 2017-03-29 2017-04-28 2017-06-02 2017-11-29 Propostas Envelope SAFFI Institutional Strengthening CESAN-4C6 / Contratacao Project Management, de modernizacao do Sistema IBRD / 83530 Supervision and Posterior Leilões eletrônicos Open 455,837.41 Assinado 2017-12-10 2017-12-29 2018-02-02 2020-01-23 SAFFI Institutional Strengthening SEAMA-3B7 / Assistencia Watershed Management and Solicitação de Open - Single Stage - One Tecnica Rural - ATER IBRD / 83530 Posterior 0.00 Cancelado 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 Restoration of Forest Cover Propostas International Envelope Mangarai. DEFESA CIVIL-1H21 / Integrated Water Solicitação de Single Stage - One Aquisicao de passagens IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-08-20 2018-10-15 2019-04-13 Cotações Envelope aereas Risk Management Integrated Water DEFESA CIVIL-1H22 / IBRD / 83530 Management and Disaster Posterior Aquisição Direta Direct 0.00 Cancelado 2018-08-06 2018-08-11 2018-09-15 2019-03-14 Inscricoes Risk Management Page 5 SEAMA-3B10 / Servicos de Monitoramento Ambiental em Bacias de Controle e Watershed Management and Contribuicao de Sedimentos IBRD / 83530 Posterior Leilões eletrônicos Open 0.00 Cancelado 2018-06-15 2018-06-20 2018-07-09 2018-08-13 2019-02-09 Restoration of Forest Cover por Estradas Vicinais nao Pavimentadas na Bacia do Rio Mangarai. INCAPER-3B5-1 / Monitoramento Ambiental da Em fase de Bacia do Mangaraí e em Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - National 0.00 Implementaçã 2018-11-12 2018-12-07 2019-01-18 2019-02-17 2019-03-24 2019-09-20 Bacias de Controle e Restoration of Forest Cover Propostas Envelope o Contribuição de Sedimentos por Estradas Vicinais SEAMA 1H12 / Serviços especializados para Integrated Water Solicitação de Single Stage - One Implementaçã Implantação e customização IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2018-12-21 2019-01-15 2019-02-26 2019-03-28 2019-05-02 2019-10-29 Propostas Envelope o Pendente do sistema Terra MA2 - Risk Management Alerta - ES. SEAMA 3A4 / Capacitação e Treinamento em Ações de Gestão de Mananciais e Watershed Management and Implementaçã Restauração Florestal - IBRD / 83530 Posterior Aquisição Direta Direct 0.00 2018-10-29 2018-11-13 2018-12-18 2019-06-16 Restoration of Forest Cover o Pendente Aquisição de Inscrições para o 5ª Congresso Brasileiro de Reflorestamento SEAMA-1D3 / Servicos de levantamento de batimetria Integrated Water e medicao de ondas e IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2018-02-08 2018-03-25 2018-04-29 2018-10-26 correntes da costa do Risk Management Espirito Santo SEAMA 1H11 / Instalação Integrated Water Solicitação de Single Stage - One Implementaçã das Estações Meteorológicas IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2019-07-25 2019-09-13 2019-10-13 2019-11-02 2019-11-30 2020-02-28 Propostas Envelope o Pendente - Alerta - ES. Risk Management SEAMA 1H13 / Inscrição no curso "Structural Collapse Specialist - Instructor Led Training", a ser realizado na Integrated Water Em fase de Texas A&M Enginnering IBRD / 83530 Management and Disaster Posterior Aquisição Direta Direct 0.00 Implementaçã 2019-03-20 2019-05-04 2019-06-18 2019-07-23 Extension Service (TEEX) - Risk Management o USA, para 02 (dois) oficiais bombeiros militares. Realização em Set/2019. SEAMA 1H14 / Inscrição no curso "EOC Operations and Planning for All Harzards", Escola Maryland Integrated Water Em fase de Fire and Rescue Institute IBRD / 83530 Management and Disaster Posterior Aquisição Direta Direct 0.00 Implementaçã 2019-03-20 2019-05-04 2019-06-18 2019-07-23 (MFRI) - USA - para 08 Risk Management o (oito) oficiais bombeiros militares. Realização em Out/2019. SEAMA-1C4 / Aquisição e Integrated Water Solicitação de Single Stage - One Implementaçã instalação de estações IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2019-07-25 2019-09-13 2019-11-02 2019-12-02 2020-01-06 2020-12-01 Propostas Envelope o Pendente hidrológicas automáticas. Risk Management SEAMA-3A3 / Assistencia Watershed Management and Solicitação de Open - Single Stage - One IBRD / 83530 Posterior 0.00 Cancelado 2017-09-20 2017-09-25 2017-11-06 2017-12-06 2018-01-10 2018-07-09 Tecnica Rural - ATER Restoration of Forest Cover Propostas International Envelope Page 6 SEAMA 1H1 / Desenvolvimento do Sistema Integrado de Proteção e Integrated Water Defesa Civil (Lote 1) e Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-11-30 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2019-10-08 Desenvolvimento do sistema Propostas Envelope Risk Management de Integração de Dados Didometereológicos do ES (Lote 2) SEAMA-1F3 / Capacitacao Integrated Water Solicitação de Single Stage - One em Gestao Ambiental e de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-08-17 2018-08-22 2018-10-03 2018-11-02 2018-12-07 2019-06-05 Propostas Envelope Recursos Hidricos Risk Management SEAMA-3A2 / Elaboracao e Implementacao do Plano de Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-07-17 2017-07-22 2017-09-02 2017-10-02 2017-11-06 2018-05-05 Comunicacao Social do Restoration of Forest Cover Propostas Envelope Reflorestar SEAMA 1H15 / Aquisição de passagens aéreas, incluindo reserva, emissão e marcação de bilhetes em vôos nacionais e Integrated Water Em fase de Solicitação de Single Stage - One internacionais para USA - IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Implementaçã 2019-05-25 2019-07-20 2019-08-19 Cotações Envelope Treinamento e visita técnica Risk Management o na Texas Enginnering Extension Service e no Maryland Fire and Recue Institute. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARSP-4B1 / Revisao e Project Management, Seleção Baseada Reestruturacao Tarifaria dos Open - IBRD / 83530 Supervision and Prévia na Qualidade e 1,495,227.64 Assinado 2017-04-10 2017-05-01 2017-06-14 2017-07-12 2017-08-11 2017-09-15 2017-10-20 2018-10-20 Servicos de Saneamento e International Institutional Strengthening Custo Contabilidade Regulatoria SEDURB-1G1 / Elaboracao de Estudos e Integrated Water Seleção Baseada Open - Desenvolvimento Plano IBRD / 83530 Management and Disaster Posterior na Qualidade e 0.00 Cancelado 2017-09-20 2017-10-11 2017-11-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2019-04-01 International Diretor de Aguas Urbanas Risk Management Custo da RMGV - Fase 1 CESAN-4A1 / Project Management, Seleção Baseada Gerenciamento do Programa Open - Em fase de IBRD / 83530 Supervision and Prévia na Qualidade e 0.00 2017-04-15 2017-05-06 2017-06-19 2017-07-17 2017-08-16 2017-09-20 2017-10-25 2018-10-25 e Supervisao de Obras International Implementação Institutional Strengthening Custo RMGV SEAMA-3A1 / Contratacao de Servicos de Aperfeicoamento do Sistema Seleção Baseada Watershed Management and Implementação de Gestao Tecnica e IBRD / 83530 Posterior na Qualidade e Open - National 0.00 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-12-25 Restoration of Forest Cover Pendente Financeira do Programa Custo Reflorestar - PORTAL REFLORESTAR AGERH-1C1 / Projeto executivo de microlocalizacao (Identificacao dos pontos e Integrated Water Seleção Baseada referenciais de niveis), Teste IBRD / 83530 Management and Disaster Posterior nas Qualificações Open - National 0.00 Cancelado 2017-06-05 2017-08-26 2017-10-09 2017-11-08 2017-12-13 2018-06-11 de Intensidade de sinais Risk Management dos Consultores GSM, anuencia de instalacao e croqui de estrutura de fixacao (50 ptos) Page 7 CESAN-3B4 / Avaliacao Seleção Baseada Socioambiental da Bacia e Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-05-15 2017-06-05 2017-07-19 2017-08-16 2017-09-15 2017-10-20 2017-11-24 2018-11-24 Monitoramento de Impacto Restoration of Forest Cover Custo de Resultados INCAPER-3B5 / Elaboracao Seleção Baseada de Diagnostico Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-12-25 Socioeconomico de 800 Restoration of Forest Cover Custo propriedades rurais Project Management, CESAN-4C1 / Auditoria Seleção Baseada IBRD / 83530 Supervision and Posterior Open - National 0.00 Cancelado 2017-05-22 2017-06-12 2017-07-26 2017-08-23 2017-09-22 2017-10-27 2017-12-01 2018-05-30 Externa do Projeto no Menor Custo Institutional Strengthening SEDURB-1G2 / Elaboracao Integrated Water Seleção Baseada Em fase de do Plano Diretor de Aguas IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 2018-02-08 2018-03-08 2018-05-21 2018-06-18 2018-07-18 2018-08-22 2018-09-26 2019-09-26 Implementação Urbanas da RMGV Risk Management Custo CESAN-2B1 / Supervisao de obras e execucao de Servicos Socioambientais dos Efficient Water Supply Seleção Baseada Open - Sistemas de Esgotamento IBRD / 83530 Services and Increased Prévia na Qualidade e 0.00 Cancelado 2017-05-22 2017-06-12 2017-07-26 2017-08-23 2017-09-22 2017-10-27 2017-12-01 2018-12-01 International Sanitario em 09 (nove) Access to Sanitation Custo municipios do interior do Espirito Santo CESAN-2A1 / 1a. Etapa do Plano Diretor de Conservacao de Energia Efficient Water Supply Seleção Baseada Eletrica para Sistemas de IBRD / 83530 Services and Increased Posterior na Qualidade e Open - National 0.00 Cancelado 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 Coleta e Tratamento de Access to Sanitation Custo Esgoto da CESAN no Espirito Santo (Item 10 Efic Energetica) INCAPER-3B5-3 / Supervisão de Obras de Watershed Management and Seleção Baseada Implementação Adequação e Recuperação de IBRD / 83530 Posterior Open - National 0.00 2018-11-30 2018-12-21 2019-02-09 2019-03-09 2019-04-08 2019-05-13 2019-06-17 2019-12-14 Restoration of Forest Cover no Menor Custo Pendente Estradas Vicinais e Construção de Caixas Secas SEAMA 1H8 / Serviços de Supervisão dos Projetos e Integrated Water Obras de Implantação do Seleção Baseada Em fase de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2018-12-20 2019-01-10 2019-02-23 2019-03-23 2019-04-22 2019-05-27 2019-07-01 2019-12-28 Centro Estadual de no Menor Custo Implementação Risk Management Gerenciamento de Riscos e Desastres (CEGRD). SEAMA-1F9 / Serviços de consultoria especializada para realização de levantamentos de requisitos Integrated Water Seleção Baseada Em fase de e as respectivas contagens IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 2019-03-11 2019-04-08 2019-06-07 2019-07-05 2019-08-04 2019-09-08 2019-10-13 2020-01-11 Implementação estimadas em pontos de Risk Management Custo função de sistemas de informação da SEMA/IEMA/AGERH SEAMA-1D1 / Determinacao Integrated Water Seleção Baseada da variacao temporal da IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2017-06-16 2017-07-07 2017-08-20 2017-09-17 2017-10-17 2017-11-21 2017-12-26 2018-12-26 linha de costa do Espirito Risk Management Custo Santo SEAMA-3B4 / Avaliacao Seleção Baseada Socioambiental da Bacia e Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2018-03-15 2018-04-05 2018-05-19 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 Monitoramento de Impacto Restoration of Forest Cover Custo de Resultados Page 8 INCAPER-3B1 / Consultoria técnica especializada em Educação Ambiental e Seleção Baseada Mobilização Social com Watershed Management and Em fase de IBRD / 83530 Posterior na Qualidade e Open - National 0.00 2019-03-11 2019-04-01 2019-05-31 2019-06-28 2019-07-28 2019-09-01 2019-10-06 2020-12-29 enfoque no empoderamento Restoration of Forest Cover Implementação Custo feminino, no âmbito do Projeto Piloto do Rio Mangaraí. INCAPER-3B5-2 / Gestão da Terra, Educação Seleção Baseada Watershed Management and Open - Ambiental e Mobilização IBRD / 83530 Prévia na Qualidade e 0.00 Cancelado 2018-10-30 2018-11-20 2019-01-14 2019-02-11 2019-03-13 2019-04-17 2019-05-22 2020-05-21 Restoration of Forest Cover International Social com enfoque no Custo empoderamento feminino SEAMA-3B9 / Contratação de consultoria técnica Seleção Baseada especializada em Mobilização Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2018-01-30 2018-02-20 2018-04-05 2018-05-03 2018-06-02 2018-07-07 2018-08-11 2019-08-11 Social e Educação Ambiental Restoration of Forest Cover Custo no âmbito do Projeto Piloto Mangaraí SEAMA-1C3 / Microlocalização em campo para instalação de estações hidrológicas automáticas com Integrated Water Seleção Baseada seus respectivos lances de Em fase de IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 2019-03-11 2019-04-01 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-06-07 réguas linimétricas e Implementação Risk Management Custo referenciais de nível, incluindo levantamento topo- batimétrico e elaboração de projetos construtivos. SEAMA-1C1-2 / Consultoria Integrated Water Seleção Baseada para Microlocalização de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-10-28 2018-11-18 2019-01-01 2019-01-29 2019-02-28 2019-04-04 2019-05-09 2019-11-05 no Menor Custo Estações Hidrológicas Risk Management SEAMA-1C2 / Projeto executivo de microlocalizacao (Identificacao dos pontos e Integrated Water Seleção Baseada referenciais de niveis), Teste IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2018-07-25 2018-08-15 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2020-02-03 de Intensidade de sinais Risk Management Custo GSM, anuencia de instalacao e croqui de estrutura de fixacao (50 ptos). SEAMA-1F10 / Desenvolver sistema de informações integrado ao Geobases - Serviços técnicos de Integrated Water Seleção Baseada Em fase de parametrização, construção IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 2019-03-11 2019-04-01 2019-06-15 2019-07-13 2019-08-12 2019-09-16 2019-10-21 2020-10-20 Implementação de navegadores geográficos, Risk Management Custo documentação e transferência de conhecimento para o Geobases SEAMA 1H4 / Integrated Water Seleção Baseada Desenvolvimento do Geobases IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2018-10-01 2018-10-22 2018-12-05 2019-01-02 2019-02-01 2019-03-08 2019-04-12 2020-04-11 2.0. Risk Management Custo SEAMA-1F5 / Modelagem Integrated Water Seleção Baseada Institucional da Agencia IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2017-09-20 2017-10-11 2017-11-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2019-04-01 Ambiental Risk Management Custo SEAMA-3B11 / Elaboracao de estudos de aplicacao das Seleção Baseada Watershed Management and metodologias e ferramentas IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2018-07-10 2018-07-31 2018-09-13 2018-10-11 2018-11-10 2018-12-15 2019-01-19 2020-01-19 Restoration of Forest Cover do Sistema de Modelagem Custo Costeira - SMC Brasil. Page 9 SEAMA-3B5 / Elaboracao Seleção Baseada de Diagnostico Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-09-15 2017-10-06 2017-11-19 2017-12-17 2018-01-16 2018-02-20 2018-03-27 2019-03-27 Socioeconomico de 800 Restoration of Forest Cover Custo propriedades rurais SEAMA-3B8 / Assistencia Seleção Baseada Watershed Management and Tecnica Rural - ATER IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-11-14 2017-12-05 2018-01-18 2018-02-15 2018-03-17 2018-04-21 2018-05-26 2019-05-26 Restoration of Forest Cover MangaraI Custo SEAMA 1H5 / Integrated Water Seleção Baseada Desenvolvimento do sistema Em fase de IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-06-21 de Integração de Dados Implementação Risk Management Custo Hidrometereológicos do ES CESAN-2B12 / Supervisão de Obras e Execução de Efficient Water Supply Serviços Socioambientais de Seleção Baseada Open - IBRD / 83530 Services and Increased Prévia 0.00 Cancelado 2018-09-17 2018-10-08 2018-11-21 2018-12-19 2019-01-18 2019-02-22 2019-03-29 2019-09-25 Sistemas de Esgotamento no Menor Custo International Access to Sanitation Sanitário em Municípios do Interior do Estado. SEAMA-1H3 / Integrated Water Seleção Baseada Desenvolvimento do Sistema Em fase de IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-06-21 Integrado de Proteção e Implementação Risk Management Custo Defesa Civil. SEAMA 1H3 / Integrated Water Desenvolvimento do Sistema Seleção Baseada IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2019-05-10 2019-05-31 2019-08-04 2019-09-01 2019-10-01 2019-10-31 2019-12-05 2020-05-03 Integrado de Proteção e na Qualidade Risk Management Defesa Civil SEAMA-1F1 / Integrated Water Seleção Baseada Desenvolvimento de Sistemas Open - IBRD / 83530 Management and Disaster Prévia na Qualidade e 0.00 Cancelado 2019-12-02 2019-12-23 2020-02-01 2020-02-29 2020-03-30 2020-05-04 2020-06-08 2021-04-04 Finalísticos de Gestão International Risk Management Custo Ambiental. CESAN 2A7 / Plano Efficient Water Supply Seleção Baseada Diretor de Conservação de IBRD / 83530 Services and Increased Posterior na Qualidade e Open - National 0.00 Cancelado 2018-09-17 2018-10-08 2018-11-21 2018-12-19 2019-01-18 2019-02-22 2019-03-29 2020-03-28 Energia - PDCE - 2º Etapa. Access to Sanitation Custo CESAN 4A3 / Servicos de Supervisao de Obras de Project Management, Seleção Baseada Open - Esgotamento Sanitario da IBRD / 83530 Supervision and Prévia 0.00 Cancelado 2018-07-30 2018-08-20 2018-10-03 2018-10-31 2018-11-30 2019-01-04 2019-02-08 2019-08-07 no Menor Custo International RMGV, no Município de Vila Institutional Strengthening Velha. CESAN 4A2 / Servicos de Supervisao de Obras de Project Management, Esgotamento Sanitario de Seleção Baseada Open - IBRD / 83530 Supervision and Prévia 0.00 Cancelado 2018-07-25 2018-08-15 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2019-08-02 Cariacica - ETE no Menor Custo International Institutional Strengthening Bandeirantes (Bairros Cariacica e Viana) CESAN 4A4 / Serviços de Supervisão de Obras de Project Management, Seleção Baseada Open - Implementação Esgotamento Sanitário da IBRD / 83530 Supervision and Prévia 0.00 2019-10-02 2019-10-02 2019-10-31 2019-12-15 2020-01-14 2020-02-09 2020-03-02 2023-06-15 no Menor Custo International Pendente RMGV, Município de Vila Institutional Strengthening Velha CESAN 4A5 / Supervisão Project Management, de Obras de Esgotamento Seleção Baseada Open - Implementação IBRD / 83530 Supervision and Prévia 0.00 2019-10-01 2019-10-22 2019-12-05 2020-01-02 2020-02-01 2020-03-07 2020-04-11 2023-07-25 Sanitário de Cariacica e no Menor Custo International Pendente Institutional Strengthening Bairros Viana na RMGV INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Page 10 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CESAN-4C4 / Contratacao Project Management, de profissional para servicos Implementação IBRD / 83530 Supervision and Posterior Individual Open 0.00 2017-03-15 2017-05-03 2017-05-24 2017-06-28 2017-12-25 de traducao para apoio ao Pendente Institutional Strengthening Projeto AGERH-1E1 / Contratacao de Hidrogeologo para Integrated Water elaboracao de TDR e IBRD / 83530 Management and Disaster Posterior Individual Open 0.00 Cancelado 2017-05-22 2017-07-10 2017-07-31 2017-09-04 2018-03-03 acompanhamento dos Risk Management trabalhos do Levantamento. CESAN-4C3 / Contratacao Project Management, de um especialista em Em fase de IBRD / 83530 Supervision and Posterior Individual Open 0.00 2017-12-08 2017-12-13 2018-01-03 2018-01-08 2018-04-08 licitacoes para apoio ao Implementação Institutional Strengthening Projeto SEAMA-1E1 / Contratação de Hidrogeólogo para elaboração de Termo de Integrated Water Referência para a Execução Em fase de IBRD / 83530 Management and Disaster Posterior Individual Open 0.00 2018-01-30 2018-03-20 2018-04-10 2018-05-15 2018-11-11 do Levantamento e Implementação Risk Management Sistematização de dados e de estudos Hidrogeológico do ES SEAMA-1F4 / Elaboracao de Termo de Referencia para Integrated Water o desenho da Modelagem IBRD / 83530 Management and Disaster Posterior Individual Open 0.00 Cancelado 2017-06-20 2017-08-08 2017-08-29 2017-10-03 2018-04-01 Institucional da Agencia Risk Management Ambiental SEAMA 1H9 / Profissional para apoiar a Defesa Civil no gerenciamento, análise de projeto e supervisão das Integrated Water obras do Centro de IBRD / 83530 Management and Disaster Posterior Individual Open 0.00 Cancelado 2018-10-29 2018-12-17 2019-01-07 2019-02-11 2019-08-10 Gerenciamento de Risco e Risk Management outras atividades do Programa de execução do Órgão. SEAMA-3A5 / Compilação de dados sobre sistemas de abastecimento e de reservação de água Watershed Management and Em fase de IBRD / 83530 Posterior Individual Open 0.00 2019-03-13 2019-05-01 2019-05-22 2019-06-26 2019-10-13 localizados nas bacias do Restoration of Forest Cover Implementação Doce, São Mateus e Itaúnas (Regiao Norte) - Programa Reflorestar SEAMA-3A6 / Compilação de dados sobre sistemas de abastecimento e de reservação de água localizados nas bacias do Watershed Management and Em fase de IBRD / 83530 Posterior Individual Open 0.00 2019-03-13 2019-05-01 2019-05-22 2019-06-26 2019-10-18 Riacho, Reis Magos, Santa Restoration of Forest Cover Implementação Maria da Vitória, Jucu, Guarapari, Benevente, Rio Novo, Itabapoana, Itapemirim (Região Sul) - Reflorestar SEAMA 3A7 / Dimensionamento das áreas de intervenção e dos efeitos da mudança do uso da terra Watershed Management and Em fase de sobre a qualidade da água IBRD / 83530 Posterior Individual Open 0.00 2019-03-28 2019-05-16 2019-06-06 2019-07-11 2020-02-21 Restoration of Forest Cover Implementação em microbacias que fornecem água para ETA's e em 51 microbacias que captam água que abastece reservatório. Page 11 SEDURB-1G3 / Contratação de especialista em aquisições Project Management, nas diretrizes de agencias IBRD / 83530 Supervision and Posterior Individual Direct 0.00 Cancelado 2018-10-02 2018-10-12 2018-11-02 2018-12-07 2019-06-05 multilaterais com domínio no Institutional Strengthening idioma Ingles. CESAN 4C9 / Profissional Project Management, para apoio técnico Em fase de IBRD / 83530 Supervision and Posterior Individual Open 0.00 2019-08-30 2019-09-07 2019-09-10 2019-09-25 2021-04-30 administrativo à Gestão do Implementação Institutional Strengthening Projeto CESAN 4C10 / Profissional Project Management, para apoio de engenharia a Em fase de IBRD / 83530 Supervision and Posterior Individual Open 0.00 2019-08-30 2019-09-09 2019-09-12 2019-09-27 2021-04-30 Unidade de Gestão do Implementação Institutional Strengthening Projeto CESAN 4C11 / Profissional Project Management, para apoio a gestao Em fase de IBRD / 83530 Supervision and Posterior Individual Open 0.00 2019-08-30 2019-09-07 2019-09-10 2019-09-25 2021-04-30 financeira do Projeto Implementação Institutional Strengthening (Controller). CESAN 4C12 / Profissional Project Management, Implementação para apoio a gestão contábil IBRD / 83530 Supervision and Posterior Individual Open 0.00 2019-09-06 2019-09-14 2019-09-17 2019-10-02 2021-04-30 Pendente do Projeto Institutional Strengthening CESAN 4C13 / Profissional para apoio a Unidade de Project Management, Implementação Gerenciamento do Projeto IBRD / 83530 Supervision and Posterior Individual Open 0.00 2019-09-20 2019-09-28 2019-10-01 2019-10-16 2021-04-30 Pendente nos serviços de supervisão Institutional Strengthening ambiental CESAN 4C14 / Profissional para apoio a Unidade de Project Management, Implementação Gerenciamento do Projeto IBRD / 83530 Supervision and Posterior Individual Open 0.00 2019-09-20 2019-09-28 2019-10-01 2019-10-16 2021-04-30 Pendente nos serviços de supervisão Institutional Strengthening social CESAN 4C8 / Especialista Project Management, em aquisições para apoio ao IBRD / 83530 Supervision and Prévia Individual Open 0.00 Cancelado 2019-09-10 2019-09-18 2019-09-21 2019-10-06 2021-04-30 Projeto Institutional Strengthening CESAN 4D1 / Treinamento e transferência de Project Management, Seleção Direta de Implementação conhecimentos técnicos sobre IBRD / 83530 Supervision and Posterior Direct 0.00 2019-10-01 2019-10-06 2019-11-05 2020-04-03 Consultores Pendente Concessões e Parcerias Institutional Strengthening Público-Privadas CESAN-4C8 / Especialista Project Management, Seleção Direta de em aquisição para apoio à IBRD / 83530 Supervision and Prévia Direct 0.00 Em Análise 2019-10-01 2019-10-11 2019-11-05 2021-04-30 Consultores gestão do Projeto Institutional Strengthening Page 12