The World Bank Report No: ISR13580 Implementation Status & Results Haiti HT Emergency Bridge Reconst & Vulnerab Reduction Project (P114292) Public Disclosure Copy Operation Name: HT Emergency Bridge Reconst & Vulnerab Reduction Project Project Stage: Implementation Seq.No: 11 Status: ARCHIVED Archive Date: 24-Feb-2014 (P114292) Country: Haiti Approval FY: 2009 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Emergency Recovery Loan Implementing Agency(ies): Key Dates Board Approval Date 18-Nov-2008 Original Closing Date 30-Jun-2013 Planned Mid Term Review Date 14-Jun-2013 Last Archived ISR Date 01-Dec-2013 Effectiveness Date 31-Mar-2009 Revised Closing Date 31-Mar-2015 Actual Mid Term Review Date 14-Jun-2013 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project's development objective is to i) restore access on selected ciritical point of the Haitian transportation system and ii) support vulnerability reduction by stregthening the Haitian National Disaster Risk Management System. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Implementing a Program of Bridge Reconstruction 7.20 Improving the resilience of transport infrastructure 5.30 Strengthening Transport System Asset Management 2.50 Strengthening the Haitian National Disaster Risk Management System 4.90 Contingencies 0.00 Public Disclosure Copy Implementing a Program of Bridge Reconstruction 7.20 Improving the resilience of transport infrastructure 5.30 Strengthening Transport System Asset Management 2.50 Strengthening the Haitian National Disaster Risk Management System 4.90 Contingencies 0.00 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Page 1 of 6 The World Bank Report No: ISR13580 Previous Rating Current Rating Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Moderate Public Disclosure Copy Implementation Status Overview *This ISR is being updated with the sole purpose of including a CSI indicator in the Results Framework in compliance with the corporate mandate" . No other changes are being made. Locations Country First Administrative Division Location Planned Actual Haiti Departement du Sud Zanglais Haiti Departement de la Grand'Anse Riviere la Voldrogue Haiti Departement du Sud Torbeck Haiti Departement de l'Ouest Tabarre Haiti Departement de l'Ouest Etang Saumatre Haiti Departement de l'Ouest Etang Saumatre Haiti Departement du Sud Saint-Louis du Sud Haiti Departement de la Grand'Anse Riviere des Roseaux Haiti Departement de l'Ouest Montrouis Haiti Departement du Centre Mirebalais Haiti Not Entered Republic of Haiti Haiti Departement de l'Ouest Riviere Grise Public Disclosure Copy Haiti Departement du Sud-Est Riviere de la Gosseline Haiti Departement de l'Artibonite Gonaives Haiti Departement du Sud-Est Riviere Gauche Haiti Departement de l'Ouest Ganthier Haiti Departement du Sud Fonfrede Haiti Departement de l'Artibonite Ennery Page 2 of 6 The World Bank Report No: ISR13580 Country First Administrative Division Location Planned Actual Haiti Departement de l'Ouest Croix des Missions Public Disclosure Copy Haiti Departement de l'Ouest Croix des Bouquets Haiti Grand#Anse Chalon ✔ Haiti Departement du Sud Les Cayes Haiti Departement du Sud Cavaillon Haiti Departement de l'Ouest Riviere Bretelle Haiti Departement du Sud Aquin Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Disaster Risk Management Units within key Text Value 0 2 ministries are operational and sustainable, with Date 31-Mar-2009 07-Oct-2013 31-Mar-2015 adequate resources and staffing Comments Unit in place, but to be fully operational activity plan has to be developed MTPTC bridge management and asset Text Value 0 Bridge management & asset mangement unit is operational and sustainable, management unit operational with adequate resources and staffing within MPTPC Date 31-Mar-2009 07-Oct-2013 31-Mar-2015 Comments The bridge asset management unit is in place The unit has completed a national bridge inventory and Public Disclosure Copy entered the collected information in the bridge management asset tool developed with the help of an international expert and young engineers hired and trained under this project. Activity plan to be developed as well as bridge management policy a Page 3 of 6 The World Bank Report No: ISR13580 Roads rehabilitated, Non-rural Kilometers Value 0.00 150.00 Date 31-Mar-2009 07-Oct-2013 Comments Public Disclosure Copy Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target (1)Bridge inventory completed and up to date; Text Value 0 3 (2) Constitution of an effective crisis Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 management unit in MTPTC; (3)Constitution of Comments a bridge management unit in MTPTC Number of bridges rebuilt with satisfactory Number Value 0.00 0.00 1.00 technical standards Date 31-Mar-2009 07-Oct-2013 31-Mar-2015 Comments Construction of bridge on river la theme on going 10 emergency bridges purchased Number Value 0.00 10.00 10.00 Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 Comments Number of bridges and road sections that have Number Value 0.00 12.00 8.00 been repaired or consolidated with satisfactory Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 technical standards Comments MTPTC is considering new operations as there is remaining funds on the compenent Bridge Inventory Completed and up to date Yes/No Value No No Yes Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 Comments Constitution of an effective crisis management Yes/No Value No Yes Yes and vulnerability reduction unit in MTPTC Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 Public Disclosure Copy Comments Constitution of a bridge management unit in Yes/No Value No Yes Yes MTPTC Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 Comments Constitution of a bridge management unit in Yes/No Value No Yes Yes MTPTC Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 Comments Page 4 of 6 The World Bank Report No: ISR13580 Number of Emergency Management and Number Value 0.00 1.00 2.00 Vulnerability Reduction Units (EM-VRU) Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 created/reinforced and operational within line Comments ministriesand within their departmental Public Disclosure Copy directorates before the project. Transversal development strategies and Number Value 0.00 4.00 6.00 instruments developed by CIAT, established Date 31-Mar-2009 04-Oct-2013 31-Mar-2015 and in place before end of project Comments Data on Financial Performance (as of 05-Feb-2014) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P114292 IDA-H4320 Effective 18-Nov-2008 12-Feb-2009 31-Mar-2009 30-Jun-2013 31-Mar-2015 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P114292 IDA-H4320 Effective XDR 12.80 12.80 0.00 9.14 3.66 71.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation Page 5 of 6 The World Bank Report No: ISR13580 *This ISR is being updated with the sole purpose of including a CSI indicator in the Results Framework in compliance with the corporate mandate" . No other changes are being made. Public Disclosure Copy Restructuring History Level two Approved on 19-Apr-2011, Level two Approved on 03-Jun-2013 Related Projects There are no related projects. Public Disclosure Copy Page 6 of 6