The World Bank Report No: ISR5441 Implementation Status & Results China Xi'an Sustainable Urban Transport Project (P092631) Public Disclosure Copy Operation Name: Xi'an Sustainable Urban Transport Project (P092631) Project Stage: Implementation Seq.No: 4 Status: ARCHIVED Archive Date: Country: China Approval FY: 2008 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 24-Jun-2008 Original Closing Date 30-Jun-2015 Planned Mid Term Review Date 01-Apr-2012 Last Archived ISR Date 27-Jun-2011 Effectiveness Date 24-Dec-2008 Revised Closing Date 30-Jun-2015 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Road Network (RN) 75.49 Public Transport (PT) 24.65 Traffic Management (TM) 14.93 Air Quality Management (AQM) 10.56 Cultural Heritage (CH) 21.62 Institutional Development (ID) 2.75 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status Overview Page 1 of 3 The World Bank Report No: ISR5441 The progress of the Xi'an Sustainable Urban Transport Project towards the achievement of its development objective, as determined by the Bank team during its October 16-21, 2011 review, is satisfactory: -Most road sections are either under procurement, construction, or already completed. -The designs for the bus priority corridors are soon to be procured (under the GEF Grant). Public Disclosure Copy -A large number of Traffic Management activities are underway - some already completed. -The Air Quality Management Component is showing good progress, and the Motor Vehicle Emission Control Plan Study has commenced. -The Cultural Heritage Component is underway. -The Institutional Development Component is well advanced, with several studies already completed. The Project likely is likely to achieve its development objectives by the planned loan closing date (December 2015). Locations Country First Administrative Division Location Planned Actual Not Entered Not Entered Not Entered Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Value Date Comments Data on Financial Performance (as of 13-May-2011) Financial Agreement(s) Key Dates Project Loan No. Status Approval Date Signing Date Effectiveness Date Closing Date P092631 IBRD-75580 Effective 24-Jun-2008 29-Sep-2008 24-Dec-2008 30-Jun-2015 Disbursements (in Millions) Public Disclosure Copy Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P092631 IBRD-75580 Effective USD 150.00 150.00 0.00 27.40 122.60 Disbursement Graph Page 2 of 3 The World Bank Report No: ISR5441 Public Disclosure Copy Key Decisions Regarding Implementation To review the progress of implementation and take necessary adjustment, a project mid-term review mission will visit Xi'an in March / April 2012. Interim visits by Bank team members will be made on an as-needed basis. Restructuring History Related Projects There are no related projects. Public Disclosure Copy Page 3 of 3