Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: November 2015]: Revision 1 of Updated Procurement Plan, August 2016] 2. Date of General Procurement Notice: January, 2016 3. Period covered by this procurement plan: The procurement period of project covered from December 2017 to December 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of procurement Substantial risk Works (including turnkey, supply & installation of plant and 10.000.000USD equipment, and PPP) Goods, information technology and non-consulting services 2.000.000USD 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P147674 issued by PRAPS-BF 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domesti Review Comments No. Cost c by Bank US$ Preferen (Prior / million ce Post) (yes/no) Summary of the NCB 7.6 7 No Post (Works) Summary of the NCB 1.6 6 No Post (Goods) Summary of the RfQ 0.2 2 No Post (Works) January 10, 2018 Summary of the RfQ 0.5 9 No Post (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of procurement Substantial risk Consultants: firms 1.000.000USD Consultants: individuals 300.000USD 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.8 8 post number of contracts that will be let under QCBS, FBBS, LCBS Summary of 3 39 Post CQS, number of Individual contracts that consultant will be let under other methods January 10, 2018 PROCUREMENT Western Africa : Regional Sahel Pastoralism Support Project PLAN General Information Country: Western Africa Banks Approval Date of the Original Procurement Plan: 2018-01-15 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-03-08 Project ID: P147674 GPN Date: Project Name: Regional Sahel Pastoralism Support Project Loan / Credit No: IDA / 56510, IDA / 56520, IDA / D0650, IDA / D0640, IDA / 56490, IDA / 56500, IDA / D0660 Executing Agency(ies): Regional Sahel Pastoralism Support Project - Niger, Regional Sahel Pastoralism Support Project - Chad, Regional Sahel Pastoralism Support Project - Senegal, Inter-State Committee against Drought in the Sahel, Regional Sahel Pastoralism Support Project - Burkina Faso, Regional Sahel Pastoralism Support Project - Mali, Regional Sahel Pastoralism Support Project - Mauritania WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7788-CW-RFB / Travaux de constructions Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 bureaux DGSV & rehabilitation Envelope Implementation batiment UCP NE-PRAPS-NE-7808-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-03-25 2017-05-20 2017-07-19 Institutional Support Quotations Envelope Implementation Dosso NE-PRAPS-NE-7962-CW-RFQ / Project Management and Request for Single Stage - One Pending Rehabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-15 2017-06-10 2017-08-09 Institutional Support Quotations Envelope Implementation Tillaberi NE-PRAPS-NE-7963-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-15 2017-06-10 2017-08-09 Institutional Support Quotations Envelope Implementation Agadez NE-PRAPS-NE-7964-CW-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-04-22 2017-06-17 2017-08-16 Réhabilitation bureau d'Agadez Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7966-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-22 2017-06-17 2017-08-16 Institutional Support Quotations Envelope Implementation Maradi NE-PRAPS-NE-7968-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-17 2017-06-12 2017-08-11 Institutional Support Quotations Envelope Implementation Zinder NE-PRAPS-NE-7969-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-25 2017-06-20 2017-08-19 Institutional Support Quotations Envelope Implementation Diffa NE-PRAPS-NE-7970-CW-RFQ / Request for Single Stage - One Pending Construction de 15 postes IDA / 56510 Animal Health Improvement Post Open - National 0.00 2017-05-27 2017-07-22 2018-01-18 Quotations Envelope Implementation é inaires départementaux vétr PRAPS-SN-05-TX / Recrutement d'une entreprise pour la construction et la réhabilitation Natural Resource Management Single Stage - Two Pending des forages pastoraux q é uipés IDA / 56520 Post Request for Bids Open - National 0.00 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 2018-07-21 Enhancement Envelope Implementation de château d'eau, d'abreuvoirs et de moyens d'exhaure en zone 2 (KF et TC) TD-PRAPS-TD-9579-CW-RFQ / Natural Resource Management Request for Single Stage - One Pending Réhabilitation des tronçons de IDA / D0650 Post Limited 0.00 2017-03-15 2017-05-10 2017-11-06 Enhancement Quotations Envelope Implementation balises TD-PRAPS-TD-9637-CW-RFB / Construction de 4 marchés à Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 0.00 2017-07-17 2017-07-22 2017-09-02 2017-10-02 2017-11-06 2018-05-05 bétail et de 2 postes de sortie Envelope Implementation frontaliers TD-PRAPS-TD-9638-CW-RFB / Natural Resource Management Single Stage - One Pending IDA / D0650 Post Request for Bids Open - National 0.00 2017-07-20 2017-07-25 2017-09-05 2017-10-05 2017-11-09 2018-05-08 Aménagement de 20 mares Enhancement Envelope Implementation TD-PRAPS-TD-9641-CW-RFB / Natural Resource Management Single Stage - One Pending Aménagement de 150 kilomètres IDA / D0650 Post Request for Bids Open - National 0.00 2017-07-20 2017-07-25 2017-09-05 2017-10-05 2017-11-09 2018-05-08 Enhancement Envelope Implementation de tronçons balisés TD-PRAPS-TD-9644-CW-RFQ / Request for Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Limited 0.00 2017-10-07 2017-12-02 2018-05-31 Forage des postes de sortie Quotations Envelope Implementation TD-PRAPS-TD-9645-CW-RFB / Single Stage - One Pending Construction et réhabilitation des IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2018-03-19 Envelope Implementation postes de vaccination TD-PRAPS-TD-9648-CW-RFB / Single Stage - One Pending Construction réhabilitation et IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 0.00 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Envelope Implementation é uipement de 12 forages q 01-T/PRAPS / réhabiliter clôture Project Management and Request for Single Stage - One IDA / 56490 Post Limited 18,108.92 Signed 2017-05-03 2017-06-05 2017-06-21 2017-08-16 2017-08-20 antenne de Fada Institutional Support Quotations Envelope REF 8 / Construction dans la Request for Single Stage - One Pending zone agro-écologique du Mali IDA / 56500 Market Access Facilitation Post Open - National 0.00 2017-06-06 2017-08-01 2018-01-28 Quotations Envelope Implementation Nord Est NE-PRAPS-NE-23108-CW-RFB Project Management and Single Stage - One Pending IDA / 56510 Post Request for Bids Open - National 0.00 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-14 / Construction des locaux Institutional Support Envelope Implementation 119 / Construction de 15 postes Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 é inaires départementaux vétr Envelope Implementation 120 / Contruction de 10 postes Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Limited 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 communaux frontaliers Envelope Implementation 121 / Finalisation de 4 puits Natural Resource Management Request for Single Stage - One Pending pastoraux à Dosso IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation (PAAPSSP/CTB) 122 / Fonçage de 4puits Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pastoaraux Tahoua (PAAPSSP) Enhancement Quotations Envelope Implementation 123 / Réhabilitation de 3 puits Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Dosso (PAAPSSP) Enhancement Quotations Envelope Implementation 124 / Rehabilitation batiment Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 DGPIA Enhancement Quotations Envelope Implementation 125 / Constructiondes 2 centres Request for Single Stage - One Pending IDA / 56510 Market Access Facilitation Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 de collecte de lait Quotations Envelope Implementation 126 / Construction/réhabilitation Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-02-13 2018-02-18 2018-04-01 2018-05-01 2018-06-05 2018-12-02 des marchés à bétail Envelope Implementation 127 / Réalisation d'une station de pompage dans la commune Natural Resource Management Single Stage - One Pending de N'Guimi dans la région de IDA / 56510 Post Request for Bids Open - National 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 Enhancement Envelope Implementation Diffa dans le cadre de programme d'urgrncr Diffa 2017 128 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tchinta 129 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tassara Page 1 130 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bermo 131 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Korgom 132 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Ollélewa 133 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tenhiya 134 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tanout 135 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Magaria 136 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bandé 137 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bouné 138 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Alakos 139 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gamou 140 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gouré 141 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Guidiguir 142 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kéllé 143 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Takaya 144 / Réhabilitation des puits Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Quotations Envelope Implementation Gudimouni 145 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Moa 146 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kanya Wamé 147 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation deTesker 148 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gueskérou 149 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Chétimari 150 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Guigmi 151 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kablewa 152 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Foulatari 153 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Guel Beyli 154 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Gourti 155 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Djeladjo 156 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Fillingué 157 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation deTchintaborak 158 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Ingall 159 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Ingall 160 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Bermo 161 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Tchinta 162 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Abala 163 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune deTenhiya Page 2 164 / Réhabilitation des stations de pompage/forages pastoraux Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 dans la commune deTesker (site Enhancement Quotations Envelope Implementation de Tesker et Aborak) REF 1 / Réhabilitation de 19 Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2017-11-22 2017-11-27 2018-01-08 2018-02-07 2018-03-14 2018-09-10 batiments Enhancement Envelope Implementation ML-PRAPS-ML-33832-CW-RFQ / Travaux d'aménagement et de gestion des pistes et des gîtes Natural Resource Management Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-10-30 2017-12-25 2018-06-23 d'étapes dans les cercles de Enhancement Quotations Envelope Implementation Koutiala et Yorosso (région de Sikasso) ML-PRAPS-ML-33835-CW-RFQ Natural Resource Management Request for Single Stage - One Pending / Travaux d'aménagement de 3 IDA / 56500 Post Limited 0.00 2017-11-14 2018-01-09 2018-07-08 Enhancement Quotations Envelope Implementation périmètres pastoraux ML-PRAPS-ML-34689-CW-RFB Single Stage - One Pending / Réhabilitation dans la zone IDA / 56500 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-03-31 2018-04-05 2018-05-17 2018-06-16 2018-07-21 2019-01-17 Envelope Implementation Delta central ML-PRAPS-ML-34760-CW-RFQ / Construction dans la zone agro- Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 0.00 2017-11-13 2018-01-08 2018-07-07 é ologique du Delta central de 7 c Quotations Envelope Implementation magasins MR-PRAPS-MR -35029-CW- RFB / construction en 2 lots de 7 Single Stage - One Pending IDA / D0660 Market Access Facilitation Post Request for Bids Open - National 0.00 2017-12-28 2018-01-02 2018-02-13 2018-03-15 2018-04-19 2018-10-16 marchés a bétail dans plusieurs Envelope Implementation wilayas MR-PRAPS-MR -35030-CW- RFQ / réalisation d un puit Natural Resource Management Request for Single Stage - One Pending pastoral dans la localité de IDA / D0660 Post Open - National 0.00 2018-01-01 2018-02-26 2018-08-25 Enhancement Quotations Envelope Implementation teguelwezza commune de Kankossa 02-T/MOD1 / Réalisation de 111 forages pastoraux solaires et Natural Resource Management Single Stage - One Under IDA / 56490 Post Request for Bids Open - National 0.00 2017-12-04 2017-10-31 2017-12-18 2018-01-17 2017-12-15 2018-02-16 2018-04-01 2018-07-30 manuels dans les 6 régions du Enhancement Envelope Implementation PRAPS 05-T/MOD1 / Réalisation de 30 Natural Resource Management Single Stage - One Pending boulis et surcreusement de 5 IDA / 56490 Post Request for Bids Open - National 0.00 2018-09-28 2018-10-12 2018-11-11 2018-12-11 2019-01-24 2019-07-23 Enhancement Envelope Implementation mares 07-T/MOD1 / Construction de 9 Request for Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Limited 0.00 2019-02-10 2019-04-16 2019-08-14 é inaires cabinets vétr Quotations Envelope Implementation 09-T/MOD1 / Travaux de construction de 6 postes Single Stage - One Pending é inaires et 30 parcs de vétr IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-12-04 2017-12-18 2018-01-17 2018-02-16 2018-04-01 2018-07-30 Envelope Implementation vaccination dans les 6 régions du PRAPS-BF 06-T/MOD1 / Single Stage - One Pending construction/réhabilitation et IDA / 56490 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-10-31 2018-11-14 2018-12-14 2019-01-13 2019-02-26 2019-07-26 Envelope Implementation é uipement d'UTL et CCL q PRAPS-SN-01-TX / Réalisation Single Stage - Two Pending des travaux de construction de IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-03-02 2018-03-07 2018-04-18 2018-05-03 2018-06-17 2018-09-15 Envelope Implementation 15 parcs a vaccination PRAPS-SN-02-TX-2018 / Réalisation des travaux de Request for Single Stage - One Pending IDA / 56520 Animal Health Improvement Post Limited 0.00 2018-05-02 2018-06-27 2018-12-24 construction d'incinérateurs au Quotations Envelope Implementation niveau des 8 SDEL PRAPS-SN-03-TX-2018 / Réalisation des travaux de confection et de pose de bornes Natural Resource Management Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2018-05-16 2018-07-11 2019-01-07 pour la matérialisation des Enhancement Quotations Envelope Implementation couloirs de transhumance Payar - Kahène PRAPS-SN-04-TX-2018 / Réalisation des travaux de construction et la réhabilitation Natural Resource Management Single Stage - Two Pending des forages pastoraux q é uipés IDA / 56520 Post Request for Bids Open - National 0.00 2018-01-17 2018-01-22 2018-03-05 2018-04-04 2018-05-09 2019-01-04 Enhancement Envelope Implementation de château d'eau, d'abreuvoirs et de moyens d'exhaure en zone 1 (SL, MT, LG) PRAPS-SN-05-TX-2018 / Réalisation des travaux Natural Resource Management Single Stage - Two Pending IDA / 56520 Post Request for Bids Open - National 0.00 2018-05-25 2018-05-30 2018-07-11 2018-08-10 2018-09-14 2019-01-12 d'aménagement de mares Enhancement Envelope Implementation pastorales PRAPS-SN-06-TX-2018 / Réalisation des travaux de Single Stage - Two Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-05-11 2018-05-16 2018-06-27 2018-07-27 2018-08-31 2018-12-29 réhabilitation de 85 km de pistes Envelope Implementation rurales PRAPS-SN-07-TX-2018 / Réalisation des travaux de Single Stage - Two Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-02-09 2018-02-14 2018-03-28 2018-04-27 2018-06-01 2018-09-29 construction de huit (08) Envelope Implementation marchés à bétail PRAPS-SN-08-TX-2018 / Single Stage - Two Pending Réalisation des travaux de IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-01-26 2018-01-31 2018-03-14 2018-04-13 2018-05-18 2018-11-14 Envelope Implementation construction des unités laitières T02 MR PRAPS 2017 / Construction et rehabilitation en Single Stage - One Pending 2 de 9 postes de santé et la IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-04-10 2017-04-14 2017-05-19 2017-06-18 2017-11-14 2018-11-30 Envelope Implementation rehabilitation de 10 autres dans 7 wilayas T01 MR PRAPS / Construction Single Stage - One Pending et réhabilitation des locaux de la IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-03-30 2017-04-09 2017-05-11 2017-06-10 2018-01-30 2018-08-28 Envelope Implementation DSV PRAPS-SN-09-TX-2018 / Project Management and Request for Single Stage - One Under Travaux de réaménagement des IDA / 56520 Post Limited 0.00 2018-01-22 2018-03-19 2018-04-03 Institutional Support Quotations Envelope Implementation bureaux du PRAPS MR-PRAPS-MR -45323-CW- RFB / Construction de 73 parcs Single Stage - One Pending IDA / D0660 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-04-25 2018-04-30 2018-06-11 2018-07-11 2018-08-15 2018-11-13 de vaccination dans plusieurs Envelope Implementation wilayas MR-PRAPS-MR -45327-CW- RFB / Construction en 2 lots de Single Stage - One Pending IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-05-25 2018-05-30 2018-07-11 2018-09-14 2019-03-13 10 aires d abattage améliorées Envelope Implementation dans plusieurs wilayas BF-PRAPS-BF-45749-CW-RFB Project Management and Single Stage - One Pending / Construction du siège du IDA / 56490 Post Request for Bids Open - National 0.00 2017-06-19 2017-06-24 2017-07-24 2017-08-23 2017-09-27 2018-09-22 Institutional Support Envelope Implementation PRAPS-BF ML-PRAPS-ML-46040-CW-RFQ / Réalisation des travaux Natural Resource Management Request for Single Stage - One Pending d'aménagement de 02 mares IDA / 56500 Post Limited 0.00 2018-03-17 2018-05-12 2018-11-08 Enhancement Quotations Envelope Implementation dans la zone d'intervention du Projet ML-PRAPS-ML-46041-CW-RFQ / Travaux de réhabilitation des Natural Resource Management Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2018-03-10 2018-05-05 2018-11-01 infrastructures hydrauliques Enhancement Quotations Envelope Implementation d'accès à l'eau Page 3 ML-PRAPS-ML-46042-CW-RFB / Réhabilitation de 03 marchés à bétail, construction et é uipement de 02 marchés à q bétail, construction de 05 aires Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2018-05-07 2018-05-12 2018-06-23 2018-07-23 2018-08-27 2019-02-23 d'abattage, 03 té als de Enhancement Envelope Implementation boucherie, 10 magasins d'aliment bétail et 05 pistes d'accès aux marchés à bétail dans le Mali Nord Est PRAPS-SN-02-TX / Recrutement d'une entreprise pour les travaux Natural Resource Management Request for Single Stage - One Pending de construction de clôtures de IDA / 56520 Post Limited 0.00 2018-02-12 2018-04-09 2018-05-24 Enhancement Quotations Envelope Implementation pépinières communautaires (10 pépinières de 1/4 ha) PRAPS-SN-12-TX-2018 / Recrutement d'une entreprise pour la réalisation de clôture de Natural Resource Management Single Stage - One Pending IDA / 56520 Post Request for Bids Open - National 0.00 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2018-12-01 mise en défens sur 200 ha (Dept Enhancement Envelope Implementation Linguère, Kanel, Bakel, Koumpentoum et Koungheul) PRAPS-SN-10-TX-2018 / Recrutement d'une entreprise Single Stage - Two Pending pour la construction et ou la IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2019-01-30 Envelope Implementation réhabilitation de mise aux normes d'aires d'abattage PRAPS-SN-11-TX-2018 / Recrutement d'une entreprise pour la réalisation des travaux de Single Stage - Two Pending construction de Magasins de IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2018-10-02 Envelope Implementation Stockage et de Vente d'Aliment de Bétail (4 de 100T et 5 de 50 tonnes) ML-PRAPS-ML-48029-CW-RFB Natural Resource Management Single Stage - One Pending / Equipements et infrastructures IDA / 56500 Post Request for Bids Open - National 0.00 2018-02-15 2018-02-20 2018-04-03 2018-06-07 2018-12-04 Enhancement Envelope Implementation d'abreuvement de forages ML-PRAPS-ML-48031-CW-RFB Natural Resource Management Single Stage - One Pending / Travaux de 11 forages grand IDA / 56500 Post Request for Bids Open - National 0.00 2018-06-12 2018-06-17 2018-07-29 2018-10-02 2019-03-31 Enhancement Envelope Implementation débit et 14 forages simples ML-PRAPS-ML-47899-CW-RFB / Travaux de réhabilitation de 5 Single Stage - One Pending é inaires, 5 SLPIA, 6 IDA / 56500 secteurs vétr Animal Health Improvement Post Request for Bids Open - National 0.00 2018-02-19 2018-02-24 2018-04-07 2018-05-07 2018-06-11 2018-12-08 Envelope Implementation Postes frontaliers, 1 Poste de contrôle frontalier et 15 UAPIA ML-PRAPS-ML-47901-CW-RFB Single Stage - One Pending / Travaux de construction de 31 IDA / 56500 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-03-08 2018-03-13 2018-04-24 2018-05-24 2018-06-28 2018-12-25 Envelope Implementation Parcs de vaccination ML-PRAPS-ML-47903-CW-RFB / Réalisation du balisage de 245 km de pistes et gîtes d'étapes dans les cercles de Bankass et Natural Resource Management Single Stage - One Pending Koro (région de Mopti) et de 545 IDA / 56500 Post Request for Bids Open - National 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Enhancement Envelope Implementation km de pistes et gîtes d'étapes dans les cercles de Ténenkou et Niono (régions de Mopti et de Ségou) ML-PRAPS-ML-47905-CW-RFB / Réalisation de 14 Systèmes Hydrauliques Pastorales (SHPA) Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2018-04-12 2018-04-17 2018-05-29 2018-06-28 2018-08-02 2019-01-29 dans les régions de Ségou, Enhancement Envelope Implementation Mopti, Tombouctou, Gao et Ménaka ML-PRAPS-ML-47907-CW-RFB / Réalisation des travaux de 11 mini Systèmes Hydraulique Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2018-04-17 2018-04-22 2018-06-03 2018-07-03 2018-08-07 2019-02-03 Pastorales (SHPA) dans les Enhancement Envelope Implementation gites d'étapes des régions de Sikasso, Ségou, Mopti ML-PRAPS-ML-48014-CW-RFB / Réalisation des travaux de 23 forages dont les sites seront Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2018-02-07 2018-02-12 2018-03-26 2018-04-25 2018-05-30 2018-11-26 déterminés à l'issu de la Enhancement Envelope Implementation validation des résultats de l'inventaire des points d'eau ML-PRAPS-ML-48011-CW-RFQ / Réhabilitation de trois bureaux Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2018-02-28 2018-04-25 2018-10-22 pour les antennes régionales à Institutional Support Quotations Envelope Implementation (Kayes, Mopti, Gao) TD-PRAPS-TD-9573-CW-RFB / Single Stage - One Pending Construction de 30 parcs de IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-03-26 2018-03-31 2018-05-12 2018-07-16 2019-01-12 Envelope Implementation vaccination TD-PRAPS-TD-9582-CW-RFB / Natural Resource Management Single Stage - One Pending Construction de la première IDA / D0650 Post Request for Bids Limited 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Enhancement Envelope Implementation tranche des puits pastoraux TD-PRAPS-TD-9585-CW-RFB / Construction de 12 marchés à Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 bétail et de 5 postes de sortie Envelope Implementation frontaliers BF-PRAPS-BF-49891-CW-RFB / Réhabilitation 10 postes é inaires et 04 marchés à vétr Animal Health Improvement Single Stage - One Pending IDA / 56490 Post Request for Bids Open - National 0.00 2018-05-15 2018-05-29 2018-06-28 2018-07-19 2018-08-23 2018-12-21 bétail dans les régions de Market Access Facilitation Envelope Implementation l'antenne de Bobo-Dioulasso et de Fada N'Gourma 04-T/MOD1 / Construction 10 marchés à bétail et Single Stage - One Pending IDA / 56490 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-07-02 2018-07-16 2018-08-15 2018-09-14 2018-10-28 2019-03-27 construction/réhabilitation 10 Envelope Implementation aires d'abattage. 08-T/MOD2 / Sécurisation d'aires de pâture intervilageoise, Natural Resource Management Single Stage - One Pending de délimitation/balisage d'aires IDA / 56490 Post Request for Bids Open - National 0.00 2018-10-31 2018-11-14 2018-12-14 2019-01-13 2019-02-26 2019-07-26 Enhancement Envelope Implementation de repôs, d'aménagement de pistes à bétail 03-T/MOD1 / Réhabilitation de é inaires dans la 08 postes vétr région du Sahel (Arbinda, Banh, Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-05-01 2018-05-15 2018-06-14 2018-07-14 2018-08-27 2018-12-25 Baraboulé, Déou, Mansila, Envelope Implementation Marcoye, Nansoumbou, Tankougoumadié) BF-PRAPS-BF-51569-CW-RFB Single Stage - One Pending / Construction de 08 Postes IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-06-12 2018-06-19 2018-07-19 2018-08-02 2018-08-30 2018-12-28 Envelope Implementation é inaires vétr GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7631-GO-RFB / Project Management and Single Stage - One Pending IDA / 56510 Post Request for Bids Open - National 0.00 2017-02-23 2017-02-28 2017-04-11 2017-05-11 2017-06-15 2017-12-12 Acquisition matériel informatique Institutional Support Envelope Implementation NE-PRAPS-NE-7652-GO-RFQ / Production de certificat Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-03-05 2017-04-30 2017-05-10 international de transhumance de Quotations Envelope Implementation la CEDEAO Page 4 NE-PRAPS-NE-7653-GO-RFQ / Request for Single Stage - One Pending Fourniture et installation de IDA / 56510 Market Access Facilitation Post Limited 0.00 2017-03-10 2017-05-05 2017-07-04 Quotations Envelope Implementation Panneau Solaire pour la DGPIA NE-PRAPS-NE-7654-GO-RFQ / Project Management and Request for Single Stage - One Pending Confection des Panneaux et IDA / 56510 Post Limited 0.00 2017-03-25 2017-05-20 2017-07-19 Institutional Support Quotations Envelope Implementation totems lumineux à Niamey NE-PRAPS-NE-7655-GO-RFQ / Productions des outils de collecte de données sur les Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-03-10 2017-05-05 2017-06-04 statistiques d'élevage ( Institutional Support Quotations Envelope Implementation commercialisation de bétail etc....) NE-PRAPS-NE-7658-GO-RFQ / Realisation, conception d'un Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-04-08 2017-06-03 2017-07-03 compendium sur deux ans de Institutional Support Quotations Envelope Implementation mise en RN en Suvre du PRAPS NE-PRAPS-NE-7659-GO-RFQ / impression d'un compendium sur Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-04-22 2017-06-17 2017-07-07 deux ans de mise en RN en Institutional Support Quotations Envelope Implementation Suvre du PRAPS NE-PRAPS-NE-7660-GO-RFQ / Edition et diffusion des outils et Project Management and Request for Single Stage - One Pending manuels de sensibilisation sur IDA / 56510 Post Limited 0.00 2017-05-02 2017-06-27 2017-07-27 Institutional Support Quotations Envelope Implementation les maladies prioritaires et les maladies emergentes du betail NE-PRAPS-NE-7662-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2018-04-16 Telephone et flotte PRAPS Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7663-GO-RFQ / Project Management and Request for Single Stage - One Pending Fonctionnement véhicules et IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2017-10-18 Institutional Support Quotations Envelope Implementation motos (carburant,entretien,...) NE-PRAPS-NE-7664-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2017-02-24 2017-04-21 2018-04-16 Fourniture et produit d'entretien Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7667-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2018-04-16 Consommable bureau, journaux Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7670-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2017-06-20 Edition journal du PRAPS Institutional Support Quotations Envelope Implementation TD-PRAPS-TD-8494-GO-RFB / Project Management and Single Stage - One Pending Acquisition d'un groupe IDA / D0650 Prior Request for Bids Limited 0.00 2017-07-01 2017-07-06 2017-08-17 2017-09-16 2017-10-21 2018-04-19 Institutional Support Envelope Implementation é ectrogène l pour l'UCP TD-PRAPS-TD-8497-GO-RFB / Single Stage - One Pending Acquisition de 4 000 000 de IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-07-01 2017-07-06 2017-08-17 2017-09-16 2017-10-21 2018-04-19 Envelope Implementation doses de vaccin PPR PRAPS-SN-01-F / Acquisition Single Stage - Two Pending IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-03-13 2017-03-18 2017-04-29 2017-05-14 2017-06-13 2017-07-13 de Vaccins PPCB, PPR et FVR Envelope Implementation BF-CILSS-8938-GO-RFQ / Impression de divers documents Project Management and Request for Single Stage - One Pending (notes des ETP-2, fiches IDA / D0640 Post Limited 0.00 2017-06-20 2017-08-15 2017-09-14 Institutional Support Quotations Envelope Implementation techniques, notes de plaidoyer, guide routier, plaquettes) PRAPS-SN-02-F / Acquisition de kit de diagnostic de Single Stage - Two Pending IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-03-06 2017-03-11 2017-04-15 2017-05-15 2017-06-19 2017-08-03 laboratoire (PPR et FVR) et de Envelope Implementation matériel d'intervention PRAPS-SN-03-F / Recrutement d'un prestataire pour la confection de supports Animal Health Improvement Request for Single Stage - One Pending promotionnels (agendas, polos, IDA / 56520 Project Management and Post Limited 0.00 2017-03-11 2017-04-28 2017-05-28 Quotations Envelope Implementation pagnes, etc.) et Support de Institutional Support Communication (JML, JNE, autre com) PRAPS-SN-04-F / Acquisition Natural Resource Management Request for Single Stage - One Pending de 8 motos pour l'animation des IDA / 56520 Post Limited 0.00 2017-03-18 2017-05-07 2017-06-21 Enhancement Quotations Envelope Implementation UP PRAPS-SN-05-F / Acquisition de matériel de lutte contre les Natural Resource Management Request for Single Stage - One Pending feux de brousse en vue de IDA / 56520 Post Limited 0.00 2017-07-29 2017-09-17 2017-11-01 Enhancement Quotations Envelope Implementation l'équipement de 30 comités de lutte contre les feux de brousse PRAPS-SN-06-F / Acquisition Natural Resource Management Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2017-06-17 2017-08-12 2017-11-10 de motofaucheuses Enhancement Quotations Envelope Implementation PRAPS-SN-07-F / Acquisition de fournitures de bureau, de consommables informatiques et Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2017-03-11 2017-04-30 2018-04-30 de Produits d'entretien de locaux Institutional Support Quotations Envelope Implementation administratifs et de petits matériels et outillages PRAPS-SN-09-F / Services de Project Management and Request for Single Stage - One Pending confection d'habillement pour le IDA / 56520 Post Limited 0.00 2017-03-25 2017-05-14 2017-06-14 Institutional Support Quotations Envelope Implementation personnel de service PRAPS-SN-11-F / Acquisition Project Management and Request for Single Stage - One Pending d'équipements de IDA / 56520 Post Limited 0.00 2017-03-11 2017-04-30 2017-06-15 Institutional Support Quotations Envelope Implementation Communication BF-CILSS-9090-GO-RFQ / Produire des dé itions de fin Project Management and Request for Single Stage - One IDA / D0640 Post Limited 7,364.49 Signed 2017-12-01 2017-10-12 2017-12-30 2017-12-01 2018-01-13 d'année (calendriers, Institutional Support Quotations Envelope plannings...) BF-CILSS-9091-GO-RFQ / Project Management and Request for Single Stage - One Acquisition de deux IDA / D0640 Post Limited 5,197.74 Signed 2018-03-05 2018-01-25 2018-04-09 2018-02-14 2018-04-19 Institutional Support Quotations Envelope rétroprojecteurs BF-CILSS-9092-GO-DIR / Project Management and Request for Single Stage - One Pending Acquisition de matériel de bureau IDA / D0640 Post Limited 0.00 2018-03-09 2018-04-09 2018-04-19 Institutional Support Quotations Envelope Implementation complémentaire BF-CILSS-9093-GO-RFQ / Project Management and Request for Single Stage - One Pending Acquisition de fournitures de IDA / D0640 Post Limited 0.00 2018-04-07 2018-05-12 2018-05-22 Institutional Support Quotations Envelope Implementation bureau PRAPS-SN-12-F / Achat de Mobilier (archivage et salon pour Project Management and Request for Single Stage - One Pending bureau coordonnateur et bureau IDA / 56520 Post Limited 0.00 2017-04-08 2017-05-28 2017-06-27 Institutional Support Quotations Envelope Implementation assistant sauvegarde environnemental et social) PRAPS-SN-13-F / Acquisition Project Management and Request for Single Stage - One Pending de Groupes Electrogènes UCP et IDA / 56520 Post Limited 0.00 2017-03-18 2017-05-07 2017-08-05 Institutional Support Quotations Envelope Implementation antennes PRAPS-SN-14-F / Acquisition Single Stage - One Pending é les en cas de crise de céra IDA / 56520 Pastoral Crisis Management Prior Request for Bids Open - National 0.00 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 2018-03-28 Envelope Implementation pastorale TD-PRAPS-TD-9182-GO-RFQ / Equipement de la salle des Project Management and Request for Single Stage - One Pending réunions du Ministère de IDA / D0650 Post Limited 0.00 2017-04-19 2017-06-14 2017-12-11 Institutional Support Quotations Envelope Implementation l'Elevage et des Productions Animales Page 5 TD-PRAPS-TD-9999-GO-RFB / Project Management and Single Stage - One Pending Acquistion de 17 véhicules Tout IDA / D0650 Prior Request for Bids Open - International 0.00 2016-07-04 2016-07-09 2016-08-20 2016-09-19 2016-10-24 2017-04-22 Institutional Support Envelope Implementation Terrain et de 176 motocyclettes TD-PRAPS-TD-9998-GO-RFB / Project Management and Single Stage - One Pending Acqusitions des matériels IDA / D0650 Post Request for Bids Open - National 0.00 2016-07-21 2016-07-26 2016-09-06 2016-10-06 2016-11-10 2017-05-09 Institutional Support Envelope Implementation informatiques TD-PRAPS-TD-9990-GO-RFB / Single Stage - One Pending Acquistion de 3 000 000 de IDA / D0650 Animal Health Improvement Post Request for Bids Limited 0.00 2016-07-21 2016-07-26 2016-09-06 2016-10-06 2016-11-10 2017-05-09 Envelope Implementation doses de vaccins PPCB 03-F/PRAPS / Acquérir 3 Single Stage - One é ectrogènes au profit groupes l IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 54,364.57 Signed 2017-04-03 2017-04-11 2017-04-08 2017-05-08 2017-05-24 2017-05-29 2017-05-24 2017-07-03 2017-10-13 2017-09-01 Envelope des antennes du PRAPS-BF 02-F/PRAPS / Duplication en Project Management and Request for Single Stage - One 1000 exemplaires la version IDA / 56490 Post Limited 2,739.84 Signed 2018-01-31 2018-01-25 2018-03-28 2018-02-28 2018-04-27 Institutional Support Quotations Envelope adaptée du guide genre Natural Resource Management 14-F/PRAPS / Fournitures et Enhancement Request for Single Stage - One Under consommables de bureau et IDA / 56490 Post Limited 0.00 2018-01-20 2017-12-29 2018-02-24 2018-03-26 Project Management and Quotations Envelope Implementation informatiques Institutional Support 15-F/PRAPS / Mobilier de Project Management and Request for Single Stage - One Pending IDA / 56490 Post Limited 0.00 2018-10-22 2018-12-10 2019-02-08 bureau Institutional Support Quotations Envelope Implementation 13-F/PRAPS / Dispositif de Project Management and Request for Single Stage - One Under vidéoconférence au profit de IDA / 56490 Post Limited 0.00 2018-05-30 2017-12-18 2018-07-18 2018-09-16 Institutional Support Quotations Envelope Implementation l'UCP 12-F/PRAPS / 200 kits outils Request for Single Stage - One Pending pour observatoire par les relais IDA / 56490 Pastoral Crisis Management Post Limited 0.00 2019-06-24 2019-08-19 2019-10-18 Quotations Envelope Implementation de veille 10-F/PRAPS / Support de Single Stage - One Pending communication/formation adapté IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2019-10-30 2019-11-04 2019-12-04 2020-01-03 2020-02-07 2020-04-07 Envelope Implementation é eveurs aux l 09-F/PRAPS / 1 véhicule 4x4 Project Management and Request for Single Stage - One Pending station wagon et 2 véhicules 4x4 IDA / 56490 Post Limited 0.00 2019-10-28 2019-12-23 2020-02-21 Institutional Support Quotations Envelope Implementation pick-up double cabine 05-F/PRAPS / Equiper Single Stage - One l'opérateur spécialisé (VSF-B) en IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 65,012.05 Completed 2016-01-08 2016-12-14 2016-01-22 2016-02-21 2017-01-24 2016-03-22 2017-02-13 2016-04-26 2017-06-23 2016-06-25 2017-08-25 Envelope véhicule 06-F/PRAPS / Production des Affiches et, dépliants (conception de 2 maquettes et impression de 2500 affiches et dépliants), Request for Single Stage - One IDA / 56490 Animal Health Improvement Post Limited 9,123.65 Completed 2017-05-26 2017-06-15 2017-07-21 2017-07-20 2017-08-20 2017-10-03 concevoir et produire des Quotations Envelope supports 'boites à images sur la santé animale et sur la conduite du troupeau REF 11 / Equipements et Project Management and Request for Single Stage - One Pending mobiliers de bureau pour les IDA / 56500 Post Limited 0.00 2017-04-09 2017-06-04 2017-12-01 Institutional Support Quotations Envelope Implementation antennes régionales du Projet REF 12 / Achat d'un véhicule Request for Single Stage - One Pending spécialement q é uipé pour les IDA / 56500 Animal Health Improvement Post Limited 0.00 2017-02-28 2017-04-25 2017-10-22 Quotations Envelope Implementation interventions d'urgence REF 13 / Moquettes, rideaux et Project Management and Request for Single Stage - One Pending accessoires pour l'Unité de IDA / 56500 Post Limited 0.00 2017-05-21 2017-07-16 2018-01-12 Institutional Support Quotations Envelope Implementation Coordination du Projet REF 14 / Matériels Project Management and Request for Single Stage - One Pending informatiques pour les antennes IDA / 56500 Post Open - National 0.00 2017-04-09 2017-06-04 2017-12-01 Institutional Support Quotations Envelope Implementation régionales REF 16 / Acquisition de 80 Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-03-22 2017-05-17 2017-11-13 smartphones Institutional Support Quotations Envelope Implementation REF 17 / Equipements de travail Request for Single Stage - One Pending pour les enquêteurs et les IDA / 56500 Market Access Facilitation Post Limited 0.00 2017-03-14 2017-05-09 2017-11-05 Quotations Envelope Implementation contrôleurs REF 19 / kit de semences Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 0.00 2017-03-25 2017-05-20 2017-11-16 é uipements fourragères et petits q Quotations Envelope Implementation Request for Single Stage - One Pending é inaires REF 22 / Trousses vétr IDA / 56500 Animal Health Improvement Post Limited 0.00 2017-03-30 2017-05-25 2017-11-21 Quotations Envelope Implementation REF 23 / 40 ordinateurs Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-04-14 2017-06-09 2017-12-06 portables et disques externes Institutional Support Quotations Envelope Implementation REF 25 / Ordinateur portable et accessoires, imprimante Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-05-16 2017-07-11 2018-01-07 multifonction, photocopieuse et Institutional Support Quotations Envelope Implementation onduleur du PADEL-M NE-PRAPS-NE-23097-GO-RFQ Request for Single Stage - One Pending / Acquisition des kits de IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-09-01 2017-10-27 2018-04-25 Quotations Envelope Implementation vaccination NE-PRAPS-NE-23100-GO-RFQ Request for Single Stage - One Pending / Equipements des 2 centres de IDA / 56510 Market Access Facilitation Post Limited 0.00 2017-10-20 2017-12-15 2018-06-13 Quotations Envelope Implementation collecte de lait NE-PRAPS-NE-23249-GO-RFQ Request for Single Stage - One Pending / Son de blé (1100 tonnes) région IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation de Tahoua avec depot sur site NE-PRAPS-NE-7610-GO-RFB / Project Management and Single Stage - One Pending Acquisition matériel roulant ( 26 IDA / 56510 Post Request for Bids Open - International 0.00 2017-02-27 2017-03-04 2017-04-15 2017-05-15 2017-06-19 2017-09-02 Institutional Support Envelope Implementation véhicules et 42 Moto) NE-PRAPS-NE-7640-GO-RFQ / Request for Single Stage - One Pending Equipement Vétr é inaire IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-02-28 2017-04-25 2017-06-24 Quotations Envelope Implementation (matériels froid) NE-PRAPS-NE-7641-GO-RFQ / Equipements Vétr é inaires Request for Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-03-05 2017-04-30 2017-06-29 (Matériels de Prélvè ement et Kits Quotations Envelope Implementation de diagnostic ) NE-PRAPS-NE-23326-GO-RFQ / Tourteaux de graine (300 Request for Single Stage - One Pending tonnes) région de Tahoua ( IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation tonnes)de coton avec depot sur site NE-PRAPS-NE-23347-GO-RFQ / Fourniture des produits Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 é inaires et complexes vétr Quotations Envelope Implementation minéraux pour la DGPIA NE-PRAPS-NE-23327-GO-RFQ Request for Single Stage - One Pending / Son de blé région (1100 t) de IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation Zinder avec depot sur site NE-PRAPS-NE-23328-GO-RFQ / Tourteaux de graine de coton Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 (300t) région de Zinder avec Quotations Envelope Implementation depot sur site Page 6 NE-PRAPS-NE-23330-GO-RFQ Request for Single Stage - One Pending / Son de blé région deDiffa (600) IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23333-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Diffa ( 200 tonnes)de coton avec Quotations Envelope Implementation depot sur site NE-PRAPS-NE-23335-GO-RFQ Request for Single Stage - One Under / Son de blé région de Maradi IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (1000 tonnes) avec depot sur site NE-PRAPS-NE-23336-GO-RFQ / Tourteaux de graine région Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 deMaradi ( 200 tonnes)de coton Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23337-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Tillaberi IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (1000 tonnes) avec depot sur site NE-PRAPS-NE-23338-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Tillaberi ( 250 tonnes)de coton Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23339-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Dosso IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (800 tonnes) avec depot sur site NE-PRAPS-NE-23340-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Dosso ( 150 tonnes)de coton Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23341-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Niamey IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (400 tonnes) avec depot sur site NE-PRAPS-NE-23343-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Niamey ( 250 tonnes)de coton Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23344-GO-RFQ / Son de blé région de Agadez ( Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 1000 tonnes)de coton avec depot Quotations Envelope Implementation sur site NE-PRAPS-NE-23345-GO-RFQ / Tourteau de graine de coton Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 région d'Agadez (300 tonnes) Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23045-GO-RFB Project Management and Single Stage - One Pending / Aquisition materiel informatique IDA / 56510 Post Request for Bids Open - National 0.00 2017-07-31 2017-08-05 2017-09-16 2017-10-16 2017-11-20 2018-05-19 Institutional Support Envelope Implementation et de communication 1 / Acquisition materiel roulant Project Management and Single Stage - One Pending IDA / 56510 Prior Request for Bids Open - International 0.00 2016-12-02 2016-12-07 2017-01-18 2017-02-17 2017-03-24 2017-09-20 (26véhicules et 50 Motos) Institutional Support Envelope Implementation 5 / Acquisition de vaccins et Request for Single Stage - One Pending diluants PPCB et diluants (6000 IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-11-06 2018-01-01 2018-06-30 Quotations Envelope Implementation 000 doses) 6 / Edition guide ingénierie Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 sociale Enhancement Quotations Envelope Implementation 7 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tanout Enhancement Quotations Envelope Implementation 8 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Belbedji IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gangara 9 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Kantche Enhancement Quotations Envelope Implementation 10 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Takaya Enhancement Quotations Envelope Implementation 11 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Magaria IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Doungas 12 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Gouré Enhancement Quotations Envelope Implementation 13 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Boune Enhancement Quotations Envelope Implementation 14 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tesker Enhancement Quotations Envelope Implementation 15 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Agadez IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Aderbissanet 16 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de INGAL Enhancement Quotations Envelope Implementation 17 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tchiro-Arlit Enhancement Quotations Envelope Implementation 18 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Iférouane Enhancement Quotations Envelope Implementation 19 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de INATES Enhancement Quotations Envelope Implementation 20 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de say Enhancement Quotations Envelope Implementation 21 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Téra Enhancement Quotations Envelope Implementation 22 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tondikiwindi Enhancement Quotations Envelope Implementation 23 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Filingué Enhancement Quotations Envelope Implementation 24 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Bankilare Enhancement Quotations Envelope Implementation 25 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Guidan IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Roumdji Madaroumfa 26 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Mayayi Enhancement Quotations Envelope Implementation 27 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Dakoro Bermo Enhancement Quotations Envelope Implementation Page 7 28 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tchinta-Konni Enhancement Quotations Envelope Implementation 29 / Acquisition matériel aratoire Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Abalak Quotations Envelope Implementation 30 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Bagaroua Enhancement Quotations Envelope Implementation 31 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tassara Enhancement Quotations Envelope Implementation 32 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Matankari Enhancement Quotations Envelope Implementation 33 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Dogon kirya IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kieche 34 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Falmey-Boboy Enhancement Quotations Envelope Implementation 35 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Diffa Enhancement Quotations Envelope Implementation 36 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Mainé Enhancement Quotations Envelope Implementation 37 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 pour les sites de Goudoumaria Enhancement Quotations Envelope Implementation 38 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région D'Agagez Enhancement Quotations Envelope Implementation 39 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-07 2018-03-04 2018-08-31 2 pour la région De Diffa Enhancement Quotations Envelope Implementation 40 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Dosso Enhancement Quotations Envelope Implementation 41 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Maradi Enhancement Quotations Envelope Implementation 42 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Tahoua Enhancement Quotations Envelope Implementation 43 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Tillaberi Enhancement Quotations Envelope Implementation 44 / Achat semence espèce 1,2 Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 et 3 pour la région De Zinder Enhancement Quotations Envelope Implementation 46 / Acquisition et installation du Natural Resource Management Request for Single Stage - One Pending système de securité ( alarme IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation incendie et vidéo surveillance) 47 / Achat matériel de collecte Request for Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-10-25 2017-12-20 2018-06-18 pour la DGSV Quotations Envelope Implementation 48 / Acquisition materiels Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-27 2017-12-22 2018-06-20 d'archivage electronique Institutional Support Quotations Envelope Implementation 49 / Acquisition de logiciel pour Request for Single Stage - One Pending 5 postes ( Arc Gis logicel R et IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-10-27 2017-12-22 2018-06-20 Quotations Envelope Implementation SPSS) 50 / Acquisition matériel Natural Resource Management Request for Single Stage - One Pending informatique et mobilier de IDA / 56510 Post Limited 0.00 2017-10-27 2017-12-22 2018-06-20 Enhancement Quotations Envelope Implementation bureau pour les 5 postes OSV NE-PRAPS-NE-30649-GO-RFQ Request for Single Stage - One Pending / Acquisition des kits de IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-10-22 2017-12-17 2018-06-15 Quotations Envelope Implementation vaccination NE-PRAPS-NE-30651-GO-RFQ / Réalisation de film sur la place Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-15 2017-12-10 2018-06-08 des femmes et des jeune dans le Institutional Support Quotations Envelope Implementation pastoralisme REF 20 / Un ordinateur, 1 imprimante et photocopieur, 2 Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-03-24 2017-03-24 2017-03-24 bureaux, une armoire, fournitures Institutional Support Quotations Envelope Implementation de bureau ML-PRAPS-ML-31420-GO-RFB Single Stage - One Pending / Acquisition et Transport IDA / 56500 Pastoral Crisis Management Post Request for Bids Open - National 0.00 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 Envelope Implementation d'aliment bétail NE-PRAPS-NE-30638-GO-DIR / Pending Acquisition de vaccins et diluants IDA / 56510 Animal Health Improvement Prior Direct Selection Direct 0.00 2017-11-09 2017-11-14 2017-12-16 2018-06-14 Implementation PPR (15 000 000 doses) NE-PRAPS-NE-34367-GO-RFQ Request for Single Stage - One Pending / Mise en place des incinérateurs IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-12-05 2018-01-30 2018-07-29 Quotations Envelope Implementation pour la gestion des déchets NE-PRAPS-NE-34385-GO-RFQ Request for Single Stage - One Pending / Acquisition /construction des IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-11-11 2018-01-06 2018-07-05 Quotations Envelope Implementation parcs mobiles pour bovins 01-F/MOD1 / Equipement 111 Natural Resource Management Single Stage - One Pending forages solaires et manuels dans IDA / 56490 Post Request for Bids Open - National 0.00 2018-09-28 2018-10-19 2018-11-18 2018-12-09 2019-01-22 2019-05-22 Enhancement Envelope Implementation les régions du PRAPS-BF 17-F/PRAPS / Edition des manuels par compilation des Natural Resource Management Request for Single Stage - One Pending différentes règlementations IDA / 56490 Post Limited 0.00 2018-10-01 2018-11-26 2019-01-25 Enhancement Quotations Envelope Implementation existantes dans le domaine du pastoralisme MR-PRAPS-MR -43177-GO-DIR / Acquisition de médicaments Pending IDA / D0660 Pastoral Crisis Management Prior Direct Selection Direct 0.00 2018-01-29 2018-02-03 2018-03-10 2018-09-06 é inaires vétr pour le plan Implementation d'urgence. Animal Health Improvement 04-F/PRAPS / Acquisition de Natural Resource Management Request for Single Stage - One IDA / 56490 Post Limited 59,620.75 Completed 2017-04-07 2017-05-22 2017-06-18 2017-07-21 2017-08-02 2017-10-27 165 tablettes Enhancement Quotations Envelope Market Access Facilitation F03 MR PRAPS 2017 / Acquisition d'équipements et Single Stage - Two Pending matériel de laboratoire de IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Envelope Implementation contrôle médicaments au profit du ONARDEL F01 MR PRAPS 2017 / Acquisition de 3 000 000 doses Pending IDA / D0660 Animal Health Improvement Prior Direct Selection Direct 0.00 2017-05-15 2017-05-30 2017-07-25 2017-10-23 de vaccins pour la campagne Implementation 2017/2018 PRAPS-SN-01-F-2018 / Acquisition de matériel de froid Request for Single Stage - One Pending IDA / 56520 Animal Health Improvement Post Limited 0.00 2018-02-21 2018-04-18 2018-06-02 complémentaire pour les services Quotations Envelope Implementation é inaires vétr Page 8 PRAPS-SN-02-F-2018 / Single Stage - Two Pending Acquisition de vaccins (PPCB, IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-02-02 2018-02-07 2018-03-21 2018-07-08 2018-10-06 Envelope Implementation PPR et FVR) PRAPS-SN-03-F-2018 / Recrutement d'un prestataire Animal Health Improvement Request for Single Stage - One Pending pour la confection de supports IDA / 56520 Project Management and Post Limited 0.00 2018-04-12 2018-06-07 2018-09-05 Quotations Envelope Implementation promotionnels (agendas, polos, Institutional Support etc.) PRAPS-SN-05-F-2018 / Fourniture et Installation Single Stage - Two Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-02-24 2018-03-01 2018-04-12 2018-07-30 2018-10-28 d'équipements des centres de Envelope Implementation collectes, laiteries et fromagerie PRAPS-SN-07-F-2018 / Acquisition de groupes Project Management and Request for Single Stage - One Under IDA / 56520 Post Limited 0.00 2018-02-14 2018-04-11 2018-07-10 é ectrogènes pour les antennes l Institutional Support Quotations Envelope Implementation du PRAPS PRAPS-SN-08-F-2018 / Project Management and Request for Single Stage - One Pending Acquisition de mobilier IDA / 56520 Post Limited 0.00 2018-03-08 2018-05-03 2018-07-02 Institutional Support Quotations Envelope Implementation d'archivage PRAPS-SN-09-F-2018 / Acquisition de matériel Project Management and Request for Single Stage - One Pending informatique pour CONACILSS et IDA / 56520 Post Limited 0.00 2018-01-29 2018-03-26 2018-05-25 Institutional Support Quotations Envelope Implementation PRAPS ainsi que d'un kit de suivi environnement BF-CILSS-44411-GO-RFQ / Renouvellement de licence de la Project Management and Request for Single Stage - One IDA / D0640 Post Limited 7,492.24 Signed 2018-01-28 2018-01-23 2018-03-11 2018-02-14 2018-03-21 passerelle du système visio Institutional Support Quotations Envelope conférence BF-CILSS-44413-GO-RFQ / Project Management and Request for Single Stage - One Under Mise à jour de l'autocommutateur IDA / D0640 Post Limited 0.00 2018-01-29 2018-01-26 2018-03-05 2018-03-15 Institutional Support Quotations Envelope Implementation du CILSS BF-PRAPS-BF-44618-GO-RFB / Aliments de bétail pour approvisionner des magasins en stocks durgence (30 000 tonnes Single Stage - One Under IDA / 56490 Pastoral Crisis Management Prior Request for Bids Open - International 0.00 2018-02-15 2018-02-13 2018-03-01 2018-04-12 2018-04-26 2018-06-09 2018-08-08 aliment bétail) pour distribution Envelope Implementation SECNSA et SP-CVEL, DGEAP pour réponse à la contingence sécheresse BF-PRAPS-BF-44630-GO-RFB / Acquisition et transport sur sites de vivres pour distribution pour é Boutiques vente à prix modér/ Single Stage - One Under témoins SP CVEL pour IDA / 56490 Pastoral Crisis Management Prior Request for Bids Limited 0.00 2018-02-15 2018-03-05 2018-02-20 2018-04-03 2018-04-17 2018-05-31 2018-07-30 Envelope Implementation assistance aux sinistrés en réponse à la contingence conflits entre exploitants /scénaris de pire cas/DGEAP 07-F/PRAPS / Equipement Animal Health Improvement informatique, ordinateurs, 31 kits Project Management and solaires, 31 refrigérateurs ,31 Institutional Support Single Stage - One congelateur ,62 glacière, IDA / 56490 Pastoral Crisis Management Post Request for Bids Open - National 370,326.86 Signed 2017-04-19 2017-07-17 2017-04-24 2017-06-05 2017-09-04 2017-07-05 2017-09-13 2017-08-09 2017-12-18 2017-11-07 Envelope 124bouteilles de gaz, 35 Natural Resource Management smatphones, 35 power Bank, 50 Enhancement copteurs, qé uip. communicaion Market Access Facilitation 11-F/PRAPS / 100 Kits outils Request for Single Stage - One Under pour observatoire par les relais IDA / 56490 Pastoral Crisis Management Post Limited 0.00 2017-06-20 2017-05-22 2017-08-15 2017-10-14 Quotations Envelope Implementation de veille 08-F/PRAPS / 31 kits solaires - Request for Single Stage - One Pending acquisition, pose et installation IDA / 56490 Animal Health Improvement Post Limited 0.00 2017-11-15 2018-01-26 2018-03-12 Quotations Envelope Implementation de MOF-REF-1 / Acquisition de 43 Request for Single Stage - One motos au profit de la DGSV et de IDA / 56490 Animal Health Improvement Post Limited 94,702.76 Completed 2017-09-10 2017-09-05 2017-11-14 2017-10-30 2017-12-29 2017-12-28 Quotations Envelope VSF-B BF-PRAPS-BF-45936-GO-RFQ / 43 motos au profit des structures déconcentrées de collectes de Request for Single Stage - One Pending IDA / 56490 Pastoral Crisis Management Post Limited 0.00 2018-05-19 2018-07-23 2018-09-21 données dans le cadre de la Quotations Envelope Implementation composante 4 (gestion des crises) BF-PRAPS-BF-45948-GO-RFB / 375 kits pour insertion socio- Single Stage - One Pending IDA / 56490 Pastoral Crisis Management Post Request for Bids Open - National 0.00 2018-04-18 2018-04-23 2018-05-23 2018-06-13 2018-07-27 2018-09-25 professionnelle de la 1ère Envelope Implementation cohorte (C4) BF-PRAPS-BF-45979-GO-RFQ / Request for Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Limited 0.00 2018-03-26 2018-05-21 2018-07-20 Matériel de vaccination Quotations Envelope Implementation BF-PRAPS-BF-45989-GO-RFB / Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-03-14 2018-04-04 2018-05-04 2018-05-25 2018-07-08 2018-09-06 Vaccins contre la PPR Envelope Implementation BF-PRAPS-BF-46005-GO-RFQ / Project Management and Request for Single Stage - One Pending Confection de goodies (publicité IDA / 56490 Post Limited 0.00 2018-02-26 2018-04-02 2018-05-02 Institutional Support Quotations Envelope Implementation par l'objet) BF-PRAPS-BF-46009-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56490 Post Limited 0.00 2018-06-17 2018-08-12 2019-02-08 Activité hors médias Institutional Support Quotations Envelope Implementation ML-PRAPS-ML-46243-GO-RFQ / Acquisition des semences, de boutures et d'éclats de souches é de diverses espèces/variéts Natural Resource Management Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2018-03-30 2018-05-25 2018-11-21 d'herbacées et de ligneuses pour Enhancement Quotations Envelope Implementation les travaux de restauration des pâturages exondés et des bourgoutières ML-PRAPS-ML-46244-GO-RFQ / Acquisition de 11 Kiosques et Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 0.00 2018-09-30 2018-11-25 2019-05-24 11 kits pour la transformation de Quotations Envelope Implementation la viande ML-PRAPS-ML-46245-GO-RFQ / Acquisition de 11 tricycles Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 0.00 2018-10-13 2018-12-08 2019-06-06 motorisés pour le transport de la Quotations Envelope Implementation viande ML-PRAPS-ML-46327-GO-RFQ / Acquisition de 72 Smartphones Project Management and Request for Single Stage - One Pending pour la collecte et la remontée de IDA / 56500 Post Limited 0.00 2018-02-23 2018-04-20 2018-10-17 Institutional Support Quotations Envelope Implementation é enciée l'information géo réfr pour 31 cercles et 10 régions PRAPS-SN-04-F-2018 / Natural Resource Management Pending Acquisition de 4 motos pour IDA / 56520 Post Direct Selection Direct 0.00 2018-03-03 2018-03-08 2018-04-12 2018-06-11 Enhancement Implementation l'animation des UP PRAPS-SN-10-F-2018 / Acquisition de divers fournitures sous fore de contrats-cadres en Single Stage - One Pending trois lots separes Lot 1 produits IDA / 56520 Pastoral Crisis Management Post Request for Bids Open - National 0.00 2018-02-07 2018-02-12 2018-03-26 2018-04-25 2018-05-30 2019-05-30 Envelope Implementation veterinaires Lot 2 aliment de betail et Lot 3 betail ovins et caprins MR-PRAPS-MR -48640-GO- Single Stage - One Pending RFB / Acquisition d'un camion IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2018-11-03 Envelope Implementation frigorifique Page 9 MR-PRAPS-MR -48643-GO- RFB / Acquisition d'équipements Single Stage - One Pending IDA / D0660 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-05-15 2018-05-20 2018-06-19 2018-07-04 2018-08-03 2018-09-02 informatiques et bureautiques Envelope Implementation pour la composante 3 MR-PRAPS-MR -48646-GO- Request for Single Stage - One Pending RFQ / Acquisition de materiel de IDA / D0660 Animal Health Improvement Post Open - National 0.00 2018-04-21 2018-06-12 2018-07-02 Quotations Envelope Implementation prelevement MR-PRAPS-MR -48647-GO- RFQ / Acquisition de Kits ELISA Request for Single Stage - One Pending PPR pour le monitoring et Kits IDA / D0660 Animal Health Improvement Post Open - National 0.00 2018-04-04 2018-05-30 2018-11-26 Quotations Envelope Implementation ELISA PPCB pour l'enquête de prévalence MR-PRAPS-MR -48652-GO- Project Management and Request for Single Stage - One Pending RFQ / Acquisition du logiciel MS IDA / D0660 Post Open - National 0.00 2018-04-23 2018-06-04 2018-06-19 Institutional Support Quotations Envelope Implementation project MR-PRAPS-MR -48657-GO- Project Management and Request for Single Stage - One Pending IDA / D0660 Post Open - National 0.00 2018-04-21 2018-05-21 2018-05-31 RFQ / Acquisition de 20 GPS Institutional Support Quotations Envelope Implementation ML-PRAPS-ML-48894-GO-RFB / Acquisition de véhicules (4 Station wagon, 5 Pickups) Project Management and Single Stage - One Pending complémentaires pour améliorer IDA / 56500 Post Request for Bids Open - National 0.00 2018-03-12 2018-03-17 2018-04-28 2018-05-28 2018-07-02 2018-12-29 Institutional Support Envelope Implementation la mobilité des services techniques (DNSV, DNPIA) et de l'UCP MR-PRAPS-MR -48977-GO- Request for Single Stage - One Pending RFQ / carnets à souches pour le IDA / D0660 Animal Health Improvement Post Open - National 0.00 2018-05-26 2018-07-12 2018-08-11 Quotations Envelope Implementation suivi sanitaire TD-PRAPS-TD-49619-GO-DIR / Pending Acquisition de 15 millions de IDA / D0650 Animal Health Improvement Prior Direct Selection Direct 0.00 2018-06-10 2018-06-15 2018-07-20 2019-01-16 Implementation doses de vaccin contre la PPR BF-PRAPS-BF-44635-GO-DIR / Achat et transport sur sites de é inaires d'intervention produit vétr Pending IDA / 56490 Pastoral Crisis Management Post Direct Selection Direct 0.00 2018-02-15 2018-02-20 2018-04-07 2018-06-06 en réponse à la contingence Implementation é izooties/scénario du p pire/DGSV TD-PRAPS-TD-50122-GO-DIR / Pending Acquisition de six millions de IDA / D0650 Animal Health Improvement Prior Direct Selection Direct 0.00 2018-06-01 2018-06-06 2018-07-11 2019-01-07 Implementation doses de vaccin contre la PPCB TD-PRAPS-TD-50137-GO-RFB / Project Management and Single Stage - One Pending Acquisition de 28 véhicules et IDA / D0650 Post Request for Bids Open - National 0.00 2018-04-04 2018-04-09 2018-05-21 2018-06-20 2018-07-25 2019-01-21 Institutional Support Envelope Implementation 176 motos TD-PRAPS-TD-50145-GO-RFQ / Acquisition des matériels et Request for Single Stage - One Pending IDA / D0650 Animal Health Improvement Post Limited 0.00 2018-04-15 2018-06-10 2018-12-07 chaine de froid et une chambre Quotations Envelope Implementation négative TD-PRAPS-TD-50430-GO-RFQ / Acquisition des groupes Project Management and Request for Single Stage - One Pending IDA / D0640 Post Limited 0.00 2018-03-25 2018-05-20 2018-11-16 é ectrogènes pour les antennes l Institutional Support Quotations Envelope Implementation régionales du PRAPS TD-PRAPS-TD-50439-GO-RFQ / Acquisition des qé uipements Request for Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Limited 0.00 2018-04-15 2018-06-10 2018-12-07 SIM Bétail (1 véhicule et 20 Quotations Envelope Implementation motos) TD-PRAPS-TD-50445-GO-RFB / é uipements Acquisition des q Natural Resource Management Single Stage - One Pending IDA / D0650 Post Request for Bids Limited 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 UAF en matériels de travail et Enhancement Envelope Implementation fournitures de bureau TD-PRAPS-TD-50451-GO-RFQ / Acquisition des matériels de Natural Resource Management Request for Single Stage - One Pending IDA / D0640 Post Limited 0.00 2018-04-04 2018-05-30 2018-11-26 travail de la Division d'Ingénierie Enhancement Quotations Envelope Implementation de Formation de NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7661-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2018-04-16 Internet Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7665-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-25 2017-04-22 2018-04-17 Assurance véhicule Institutional Support Quotations Envelope Implementation PRAPS-SN-10-F / Acquisition Project Management and Pending du logiciel MS Project et IDA / 56520 Prior Direct Selection Direct 0.00 2017-03-13 2017-03-18 2017-04-22 2017-05-22 Institutional Support Implementation formation des utilisateurs PRAPS-SN-08-F / Services d'entretiens et de maintenance Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2016-12-30 2017-01-17 2018-01-17 du matériel informatique, du site Institutional Support Quotations Envelope Implementation web du PRAPS REF 28 / Appui à la production Natural Resource Management Request for Single Stage - One Pending des cartes des couloirs de IDA / 56500 Post Limited 0.00 2017-04-16 2017-06-11 2017-12-08 Enhancement Quotations Envelope Implementation transhumance REF 29 / Développement dune Project Management and Request for Single Stage - One Pending page Facebook et dune page IDA / 56500 Post Limited 0.00 2017-06-17 2017-08-12 2018-02-08 Institutional Support Quotations Envelope Implementation YouTube REF 30 / Conception et Project Management and Request for Single Stage - One Pending réalisation dun clip vidéo pour le IDA / 56500 Post Limited 0.00 2017-04-15 2017-06-10 2017-12-07 Institutional Support Quotations Envelope Implementation PRAPS NE-PRAPS-NE-7669-NC-DIR / Project Management and Pending IDA / 56510 Post Direct Selection Direct 0.00 2017-02-19 2017-02-24 2017-03-31 2018-03-26 Location Bureaux UCP/PRAPS Institutional Support Implementation NE-PRAPS-NE-7642-NC-DIR / Etablissement de 7 conventions Project Management and Pending IDA / 56510 Post Direct Selection Direct 0.00 2017-02-28 2017-03-05 2017-04-09 2017-10-06 avec les média locaux pour la Institutional Support Implementation vulgarisation des textes ML-PRAPS-ML-34772-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-11-05 2017-12-31 2018-06-29 Diffusion de messages Institutional Support Quotations Envelope Implementation MR-PRAPS-MR -43178-NC-RFQ / Logistique (Transport, Single Stage - One Pending manutention et entreposage de IDA / D0660 Pastoral Crisis Management Post Request for Bids Open - National 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 Envelope Implementation l'aliment de bétail) pour le plan d'urgence. PRAPS-SN-06-F-2018 / Recrutement d'un prestataire Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2018-03-19 2018-05-14 2019-05-14 pour la police d'assurance santé Institutional Support Quotations Envelope Implementation des agents du PRAPS ML-PRAPS-ML-47132-NC-RFQ / Conception, radialisation et diffusion des supports de communication sur les activités Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2018-02-24 2018-04-21 2018-10-18 et les acquis du PRAPS- ML par Institutional Support Quotations Envelope Implementation : affichage, audio et audiovisuel, (film, sketchs, affiches, panneaux) Page 10 REF 27 / Production des Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-05-15 2017-07-10 2018-01-06 supports de vulgarisation Institutional Support Quotations Envelope Implementation MR-PRAPS-MR -48649-NC-RFQ / Edition de 1000 brochures du Natural Resource Management Request for Single Stage - One Pending IDA / D0660 Post Open - National 0.00 2018-05-20 2018-07-11 2018-08-25 Code pastoral en arabe/Français Enhancement Quotations Envelope Implementation et en langues nationales MR-PRAPS-MR -48650-NC-RFQ / Conception, dé ition et duplication de supports imprimés Natural Resource Management Request for Single Stage - One Pending IDA / D0660 Post Open - National 0.00 2018-05-20 2018-07-06 2018-07-21 et scriptovisuels de Enhancement Quotations Envelope Implementation communication pour la composante 2 MR-PRAPS-MR -48654-NC-RFB / Acquisition de matériels de visibilité et de supports Project Management and Single Stage - One Pending IDA / D0660 Post Request for Bids Open - National 0.00 2018-04-19 2018-04-24 2018-05-09 2018-05-24 2018-06-13 2018-07-13 communication variés (imprimés Institutional Support Envelope Implementation et scriptovisuels) pour l'UC PRAPS/Partenaires MR-PRAPS-MR -48970-NC-RFQ Project Management and Request for Single Stage - One Pending / Production d'un film IDA / D0660 Post Limited 0.00 2018-05-15 2018-06-25 2018-07-25 Institutional Support Quotations Envelope Implementation documentaire MR-PRAPS-MR -48971-NC-RFQ / Diffusion d'Émissions, de microprogrammes radio et Project Management and Request for Single Stage - One Pending productions médiatiques c é rites IDA / D0660 Post Limited 0.00 2018-05-20 2018-06-26 2018-07-26 Institutional Support Quotations Envelope Implementation de vulgarisation du code pastoral et des thématiques essentielles sur la GRN 03-S/PRAPS / Assurance Project Management and Request for Single Stage - One IDA / 56490 Post Limited 0.00 Canceled 2017-04-22 2017-06-10 2017-07-16 maladie Institutional Support Quotations Envelope BF-PRAPS-BF-49968-NC-DIR / Project Management and Assurance maladie du personnel IDA / 56490 Post Direct Selection Direct 39,313.98 Signed 2017-06-01 2017-07-12 2017-06-08 2017-07-19 2017-07-22 2017-08-07 2018-07-22 Institutional Support du PRAPS-BF CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7700-CS-CQS / Multiples Conventions avec les opérateurs privés pour l'organisation des usagers de Consultant parcours(ingénerie sociale, Project Management and Pending IDA / 56510 Prior Qualification Open - National 0.00 2017-02-20 2017-03-13 2017-04-26 2017-05-26 2017-06-30 2018-06-25 aménagements pastoraux et Institutional Support Implementation Selection hydraulique pastorale ds les 7 régions avec une vingtaine d' ONG au niveau de Vingt sept zones NE-PRAPS-NE-7766-CS-CQS / Appui à la mise en place d'un Consultant disposititif adapté Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-03-13 2017-04-03 2017-05-17 2017-06-16 2017-07-21 2017-09-19 d'approvisionnement et de Implementation Selection distribution d'aliments bétail en cas de crise pastorale NE-PRAPS-NE-7769-CS-CQS / Consultant Elaboration d'un document Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-03-23 2017-04-13 2017-05-27 2017-06-26 2017-07-31 2017-08-30 d'evaluation d'une activité en Implementation Selection situation de crises pastorales PRAPS-SN-12-PI / Sélection d'un consultant individuel pour Consultant Pending l'étude de capitalisation des IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 0.00 2016-11-29 2017-02-09 2017-03-26 2017-04-25 2017-06-09 2017-10-07 Implementation activités de la cellule de lutte Selection contre le vol de bétail PRAPS-SN-04-PI / Sélection d'un cabinet pour l'étude sur les Consultant initiatives en cours pour la mise Natural Resource Management Pending IDA / 56520 Post Qualification Open - National 0.00 2017-03-27 2017-04-17 2017-05-31 2017-06-30 2017-08-04 2018-01-01 en place de pares feux dans le Enhancement Implementation Selection cadre de la lutte contre les feux de brousses PRAPS-SN-06-PI / Sélection é udes d'un cabinet pour les t Consultant Pending techniques en vue de la IDA / 56520 Market Access Facilitation Post Qualification Open - National 0.00 2017-05-02 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2017-12-08 Implementation réhabilitation de 50 km de pistes Selection rurales PRAPS-SN-10-PI / Sélection Consultant Pending d'un cabinet pour les services IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-08-28 2017-09-18 2017-11-01 2017-12-01 2018-01-05 2018-05-05 Implementation d'évaluation d'impact OSB Selection TD-PRAPS-TD-9404-CS-QBS / Recrutement d'un consultant Project Management and Quality Based Pending IDA / D0650 Post Open - National 0.00 2017-03-23 2017-04-13 2017-05-27 2017-06-24 2017-07-24 2017-08-23 2017-09-27 2018-09-27 pour les travaux de réhabilitation Institutional Support Selection Implementation des locaux de l'UCP 19-C/MODSIEGE / MOD pour la Consultant Project Management and Pending construction du siège de l'UCP IDA / 56490 Post Qualification Open - National 0.00 2017-03-09 2017-03-30 2017-04-27 2017-05-11 2017-06-08 2018-09-01 Institutional Support Implementation PRAPS Selection 43-C/PRAPS / Capitalisation Consultant des connaissances endogènes Pending IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 0.00 2019-11-28 2019-12-12 2020-01-09 2020-01-23 2020-02-20 2020-03-21 sur les indicateurs de crise en Implementation Selection pastoralisme 07-C/PRAPS / Evaluation de Consultant l'intégration du pastoralisme dans Pending IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-06-23 2017-07-14 2017-08-11 2017-08-25 2017-09-22 2017-10-22 les instruments de gestion des Implementation Selection crises au Burkina Faso 37-C/PRAPS / Etude offre de formation professionnelle en lien avec le pastoralisme au profit des jeunes et capitalisation des Consultant Under activités connexes autour des IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-06-16 2017-05-26 2017-07-07 2017-08-04 2017-06-17 2017-08-18 2017-07-21 2017-09-22 2017-09-22 Implementation infrastructures d'élevage, des Selection AGR l é igibles dans le PRAPS en relation avec le genre et les technologies adapté 46-C/PRAPS / Elaboration Consultant Natural Resource Management Pending é entiel technique des réfr IDA / 56490 Post Qualification Open - National 0.00 2019-11-29 2019-12-20 2020-01-17 2020-01-31 2020-02-28 2020-03-29 Enhancement Implementation infrastructures pastorales Selection REF 38 / Etudes pour 15 Consultant Natural Resource Management Pending schémas d'aménagement de IDA / 56500 Post Qualification Open - National 0.00 2017-04-18 2017-05-09 2017-06-22 2017-07-22 2017-08-26 2018-02-22 Enhancement Implementation terroirs Selection Consultant REF 39 / Contrôle -surveillance Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2017-03-14 2017-04-04 2017-05-18 2017-06-17 2017-07-22 2018-01-18 des travaux daménagement Implementation Selection REF 40 / Evaluation des Natural Resource Management Quality And Cost- Pending IDA / 56500 Post Open - National 0.00 2017-05-03 2017-05-24 2017-07-07 2017-08-04 2017-09-03 2017-10-08 2017-11-12 2018-11-12 superficies de pâturages Enhancement Based Selection Implementation Consultant é udes REF 42 / Réalisation des t Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-10 2017-05-31 2017-07-14 2017-08-13 2017-09-17 2018-03-16 géophysiques Enhancement Implementation Selection é udes REF 44 / Réalisation des t Natural Resource Management Quality And Cost- Pending IDA / 56500 Post Open - National 0.00 2017-05-04 2017-05-25 2017-07-08 2017-08-05 2017-09-04 2017-10-09 2017-11-13 2018-11-13 techniques Enhancement Based Selection Implementation Page 11 REF 45 / Contrôle -surveillance Consultant Pending é uipements des travaux et q IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2017-04-25 2017-05-16 2017-06-29 2017-07-29 2017-09-02 2018-03-01 Implementation d'abreuvement Selection Consultant REF 46 / Contrôle des travaux Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-18 2017-06-08 2017-07-22 2017-08-21 2017-09-25 2018-03-24 dans la zone mali NORD- EST Enhancement Implementation Selection Consultant REF 63 / Mise en place dun Pending IDA / 56500 Animal Health Improvement Post Qualification Open - National 0.00 2017-05-02 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2018-03-08 fonds de roulement vaccins Implementation Selection Consultant REF 73 / Etudes d'identification Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 des travaux daménagement Enhancement Implementation Selection Consultant REF 74 / Aménagement dans Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 la zone Centre du Mali Enhancement Implementation Selection REF 75 / Aménagement et Consultant Natural Resource Management Pending gestion durable des IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 Enhancement Implementation bourgoutières Selection REF 76 / Aménagement et gestion durable des Consultant Natural Resource Management Pending bourgoutières dans les régions IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 Enhancement Implementation de Tombouctou et de Gao Selection (régions du Nord-Mali) Consultant REF 78 / Réalisation des pare- Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-06-22 2017-07-13 2017-08-26 2017-09-25 2017-10-30 2018-04-28 feu de sécurisation Enhancement Implementation Selection Consultant REF 80 / Mise en place dun Pending IDA / 56500 Animal Health Improvement Post Qualification Open - National 0.00 2017-04-17 2017-05-08 2017-06-21 2017-07-21 2017-08-25 2018-02-21 fonds de roulement vaccins Implementation Selection NE-PRAPS-NE-7774-CS-CQS / Recrutement d'un bureau d'étude Consultant é ude, conception et suivi pour t Pending IDA / 56510 Animal Health Improvement Post Qualification Open - National 0.00 2017-03-22 2017-04-12 2017-05-26 2017-06-25 2017-07-30 2019-01-21 de travaux de construction de la Implementation Selection DGSV et Réhabilitation bureau UCP NE-PRAPS-NE-7779-CS-CQS / Recrutement d'un bureau Consultant d'études pour etude,conception Pending IDA / 56510 Animal Health Improvement Post Qualification Open - National 0.00 2017-02-21 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2018-12-23 et contrôle des 15 postes Implementation Selection départementaux et des 10 postes communauxfrontaliers* NE-PRAPS-NE-7702-CS-CQS / Consultant Convention de prestation avec un Natural Resource Management Pending IDA / 56510 Post Qualification Open - National 0.00 2017-04-02 2017-04-23 2017-06-06 2017-07-06 2017-08-10 2018-08-05 Bureau pour organisation des Enhancement Implementation Selection usagers de parcours 53 / Recrutemnt d'un bureau Consultant d'étude pour Appui aux initiatives Natural Resource Management Pending IDA / 56510 Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 communautaires à travers les Enhancement Implementation Selection CEP 58 / Identification, accords sociaux, géo réfré ence et Consultant Project Management and Pending préparation des DAO pour les IDA / 56510 Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Institutional Support Implementation travaux de balisage en 2018 des Selection couloirs de passage 65 / Convention de prestation Consultant Project Management and Pending avec un bureau pour organisation IDA / 56510 Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Institutional Support Implementation des usagers de parcours Selection 66 / Multiples Conventions avec les opérateurs privés pour l'organisation des usagers de parcours(ingénerie sociale, Consultant Pending aménagements pastoraux et IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation hydraulique pastorale ds les 7 Selection régions avec une vingtaine d' ONG au niveau de Vingt sept zones 68 / Recrutement d'un consultant firme pour Consultant Pending l'Elaboration d'un document IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation d'evaluation d'une activité en Selection situation de crises pastorales 80 / Recrutement d'un bureau Consultant d'étude pour t é ude, conception et Project Management and Under IDA / 56510 Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 suivi et contôle de batiment du Institutional Support Implementation Selection Projet 84 / Recrutement des ONG/OPEL pour le démarrage Consultant Pending du processus des accords partis IDA / 56510 Market Access Facilitation Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation pour la construction/réhabilitation Selection des marchés 85 / Recrutement d'un bureau d'études pour etude,conception Consultant Pending et contrôle des 15 postes IDA / 56510 Animal Health Improvement Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation départementaux et des 10 Selection postes communauxfrontaliers* Consultant 86 / Etude sur l'institution de Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 SVPP Implementation Selection 91 / Recrutement dun bureau detude pour Etudes de Consultant Pending faisabilité, préparation DAO, suivi IDA / 56520 Market Access Facilitation Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation et contrôle des quatorze centres Selection de collecte de lait 97 / recrutement dun bureau d'études pour la réalisation des etudes techniques et elaboration Quality And Cost- Pending IDA / 56510 Market Access Facilitation Post Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 des DAO relatifs a la Based Selection Implementation construction/rehabilitation des 29 marchés à bétail NE-PRAPS-NE-30657-CS-LCS / Recrutement d'un bureau d'étude pour etudes,suivi et contrôle des Project Management and Pending travaux de Réhabilitation du IDA / 56510 Post Least Cost Selection Open - National 0.00 2017-09-30 2017-10-21 2017-12-04 2018-01-01 2018-01-31 2018-03-07 2018-04-11 2018-10-08 Institutional Support Implementation batiment de la DGPIA et les locaux devant abriter les antennes régionales du PRAPS REF 47 / Recrutement de consultant chargé des t é udes Consultant Pending techniques pour la réalisation IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2017-05-19 2017-06-09 2017-07-23 2017-08-22 2017-09-26 2018-03-25 Implementation des Travaux dans la zone DELTA Selection CENTRAL ML-PRAPS-ML-31460-CS-CQS / RECRUTEMENT D'UNE ONG POUR LA CONDUITE DES Consultant Project Management and Pending ACTIVITÉS DE SAUVEGARDES IDA / 56500 Post Qualification Open - National 0.00 2017-10-25 2017-11-15 2017-12-29 2018-01-28 2018-03-04 2018-08-31 Institutional Support Implementation SOCIALES AUTOUR DES Selection INFRASTRUCTURES DU PRAPS Page 12 ML-PRAPS-ML-33294-CS-CQS Consultant / Recrutement de consultant pour Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 la réalisation des Travaux de Enhancement Implementation Selection sécurisation 18-C/PRAPS / Recrutement d'un opérateur en alphabétisation Consultant Under pour la formation des membres IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2017-11-13 2017-10-02 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 Implementation des OP de la région de la Boucle Selection du Mouhoun 17-C/PRAPS / Recrutement d'un Consultant opérateur en alphabétisation Under IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2017-11-13 2017-10-02 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 pour la formation des membres Implementation Selection des OP de la région de l'Est 16-C/PRAPS / Recrutement d'un Consultant opérateur en alphabétisation Pending IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2017-11-13 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 pour la formation des membres Implementation Selection des OP de la région du Nord 03-C/MOD1 / Suivi-contrôle des travaux de construction de 5 Consultant Under é inaires et 30 parcs IDA / 56490 postes vétr Animal Health Improvement Post Qualification Open - National 0.00 2017-12-02 2018-01-15 2017-12-16 2018-01-20 2018-02-10 2018-03-17 2018-08-14 Implementation de vaccination dans les 6 régions Selection du PRAPS-BF 04-C/MOD1 / Maîtrise d'Suvre travaux de réalisation de 111 Consultant Natural Resource Management Under forages pastoraux solaires et IDA / 56490 Post Qualification Open - National 0.00 2017-12-29 2018-01-15 2018-01-19 2018-03-04 2018-04-03 2018-05-08 2018-10-05 Enhancement Implementation manuels dans les 6 régions du Selection PRAPS 05-C/MOD1 / Suivi-contrôle Consultant Pending travaux de réhabilitation de 25 IDA / 56490 Animal Health Improvement Post Qualification Open - National 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2018-12-20 Implementation é inaires postes vétr Selection 06-C/MOD1 / Etude/suivi 15 Pending marchés et 10 aires d'abattage à IDA / 56490 Market Access Facilitation Post Least Cost Selection Open - National 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-01 2018-08-31 2018-10-05 2018-11-09 2019-04-08 Implementation construire et à réhabiliter Consultant 02-C/MOD1 / Etude/suivi 30 Natural Resource Management Under IDA / 56490 Post Qualification Open - National 0.00 2018-09-21 2017-12-27 2018-10-12 2018-01-30 2018-11-25 2018-12-25 2019-01-29 2019-07-28 boulis et5 mares Enhancement Implementation Selection 08-C/MOD1 / Etude/suivi Quality And Cost- Under UTL/CCL à construire et IDA / 56490 Market Access Facilitation Post Open - National 0.00 2018-08-21 2017-05-29 2018-09-11 2018-10-25 2018-11-22 2017-10-06 2018-12-22 2017-10-06 2019-01-26 2017-10-06 2019-03-02 2019-07-30 Based Selection Implementation réhabiliter 11-C/MOD2 / Etudes s et suivi- contrôle Travaux de sécurisation de 25 aires de pâture inter- villageoise, de délimitation/balisage de 60 aires Natural Resource Management Quality And Cost- Pending IDA / 56490 Post Open - National 0.00 2018-08-22 2018-09-12 2018-10-26 2018-11-23 2018-12-23 2019-01-27 2019-03-03 2019-07-31 de repos, d'aménagement de 1 Enhancement Based Selection Implementation 000 km de pistes à bétail, et de récupération de 10 000 ha de terres dégradées par ONG/associatio 10-C/MOD1 / Etudes environnementales et sociales Quality And Cost- Pending IDA / 56490 Animal Health Improvement Post Open - National 0.00 2018-08-21 2018-09-11 2018-10-25 2018-11-22 2018-12-22 2019-01-26 2019-03-02 2019-06-30 UTL/CCL à construire et à Based Selection Implementation réhabiliter 01-C/MOD1 / Etude Consultant Natural Resource Management Pending environnemental et sociale 30 IDA / 56490 Post Qualification Open - National 0.00 2018-08-21 2018-09-11 2018-10-25 2018-11-24 2018-12-29 2019-05-28 Enhancement Implementation boulis et 5 mares Selection 41-C/MOD1 / Etudes environnementales et sociales 15 Consultant marchés à bétail et 10 aires Pending IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-05-14 2018-06-04 2018-07-18 2018-08-17 2018-09-21 2019-03-20 d'abattage à construire et Implementation Selection réhabiliter dans les régions d'intervention du PRAPS-BF 42-C/MOD1 / Etude environnementales et sociales 9 Quality And Cost- Pending é inaires privés à cabinets vétr IDA / 56490 Animal Health Improvement Post Open - National 0.00 2018-07-17 2018-08-07 2018-09-20 2018-10-18 2018-11-17 2018-12-22 2019-01-26 2019-07-25 Based Selection Implementation construire dans les régions d'intervention du PRAPS-BF 43-C/MOD1 / Etudes/suivi 9 é inaires privés à cabinets vétr Quality And Cost- Pending IDA / 56490 Animal Health Improvement Post Open - National 0.00 2018-05-14 2018-05-28 2018-07-02 2018-07-16 2018-07-30 2018-08-18 2018-09-22 2019-03-21 construire dans les régions Based Selection Implementation d'intervention du PRAPS-BF PRAPS-SN-09-PI / Sélection de consultant pour le développement Consultant Under de modules sur les crises IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 0.00 2016-12-07 2016-12-07 2017-02-04 2017-03-10 2017-04-10 2017-03-30 2017-05-31 2017-08-29 Implementation pastorales (SIGEL) et formation Selection des utilisateurs C11 MR PRAPS 2017 / Recrutement d'un prestataire de Consultant service (3) pour l'animation Natural Resource Management Pending IDA / D0660 Post Qualification Open - National 0.00 2017-04-15 2017-04-25 2017-05-25 2017-06-04 2017-06-19 2017-09-17 pastorale des UEP 5 & 6 partie Enhancement Implementation Selection Gorgol, Tagant, partie Brakna, Trarza, et Inchiri). PRAPS-SN-02-PI-2018 / Sélection d'un consultant responsable du processus de Natural Resource Management Fixed Budget Pending é aluation participatif de la suivi v IDA / 56520 Post Open - National 0.00 2018-03-06 2018-03-27 2018-05-10 2018-06-07 2018-07-07 2018-08-11 2018-09-15 2019-09-15 Enhancement Selection Implementation mise en Suvre des plans de gestion et organisation des ateliers d'évaluation 21-C/PRAPS / Evaluation des Consultant performances du PRAPS et de la Project Management and Under IDA / 56490 Post Qualification Open - National 0.00 2017-01-27 2017-01-30 2017-02-17 2017-04-02 2017-03-27 2017-05-02 2017-04-19 2017-06-22 2017-08-03 responsable de la formulation du Institutional Support Implementation Selection PADEL-B Project Management and Quality And Cost- Pending 35-C/PRAPS / Auditeur externe IDA / 56490 Post Open - National 0.00 2019-04-15 2019-05-06 2019-06-10 2019-06-24 2019-07-15 2019-08-19 2019-10-02 2022-10-01 Institutional Support Based Selection Implementation Consultant MOF-REF-2 / Réalisation film Project Management and Pending IDA / 56490 Post Qualification Open - National 0.00 2016-06-09 2016-06-30 2016-08-13 2016-09-12 2016-10-17 2017-04-15 documentaire et spots Institutional Support Implementation Selection MR-PRAPS-MR -45322-CS- QCBS / Suivi des travaux de Quality And Cost- Pending construction de 73 parcs de IDA / D0660 Animal Health Improvement Post Open - National 0.00 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2018-11-25 Based Selection Implementation vaccination dans plusieurs localités du pays MR-PRAPS-MR -45329-CS- QCBS / Suivi des travaux de Quality And Cost- Pending construction de 10 aires d IDA / D0660 Market Access Facilitation Post Open - National 0.00 2018-06-15 2018-07-06 2018-08-19 2018-09-16 2018-10-16 2018-11-20 2018-12-25 2019-06-23 Based Selection Implementation abattage améliorées dans plusieurs wilayas MR-PRAPS-MR -45331-CS- QCBS / Suivi des travaux de Quality And Cost- Pending IDA / D0660 Market Access Facilitation Post Open - National 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-16 2018-09-15 2018-10-20 2018-11-24 2019-07-22 construction de 7 marchés dans Based Selection Implementation plusieurs wilayas BF-PRAPS-BF-45594-CS-CQS / Opérateur en alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP dans la Selection région des Cascades Page 13 BF-PRAPS-BF-45599-CS-CQS / Opérateur en alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP de la Selection région des Hauts Bassins BF-PRAPS-BF-45604-CS-CQS / Opérateur en Alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP de la Selection région du Sahel MOF-REF-11 / Animal Health Improvement ONG/Association pour réaliser Pastoral Crisis Management Consultant Under l'ingénierie sociale du PRAPS IDA / 56490 Natural Resource Management Post Qualification Open - National 0.00 2016-08-02 2017-10-02 2016-08-23 2016-10-06 2016-11-05 2017-01-03 2017-07-02 Implementation dans l'antenne de Fada Enhancement Selection N'Gourma (Région de l'Est) Market Access Facilitation MOF-REF-12 / Animal Health Improvement ONG/Association pour réaliser Pastoral Crisis Management Consultant Pending l'ingénierie sociale du PRAPS IDA / 56490 Natural Resource Management Post Qualification Open - National 0.00 2016-08-02 2016-08-23 2016-10-06 2016-11-05 2017-01-03 2017-07-02 Implementation dans l'antenne de Dori (régions Enhancement Selection du Sahel et du Nord) Market Access Facilitation MOF-REF-13 / ONG/association Animal Health Improvement pour l'ingénierie sociale du Pastoral Crisis Management Consultant PRAPS-BF dans l'antenne de Under IDA / 56490 Natural Resource Management Post Qualification Open - National 0.00 2016-08-02 2016-08-01 2016-08-23 2016-10-06 2016-11-05 2017-01-03 2017-07-02 Bobo-Dioulasso (régions des Implementation Enhancement Selection Hauts-Bassins, de la Boucle du Market Access Facilitation Mouhoun et des Cascades) 32-C/MOD1 / Etudes Quality And Cost- environnementales et sociales 9 IDA / 56490 Animal Health Improvement Post Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-08-24 Based Selection é inaires cabinets vétr 09-C/MOD1 / Etudes/suivi 9 Quality And Cost- é inaires à cabinets vétr IDA / 56490 Animal Health Improvement Post Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-08-24 Based Selection construction BF-PRAPS-BF-45926-CS-CQS / Consultant Project Management and Pending Suivi-contrôle de la construction IDA / 56490 Post Qualification Open - National 0.00 2017-06-26 2017-07-17 2017-08-14 2017-08-28 2017-10-02 2018-09-27 Institutional Support Implementation du siège du PRAPS-BF Selection BF-PRAPS-BF-46011-CS-CQS / Consultant Plan d'aménagement et de Natural Resource Management Pending IDA / 56490 Post Qualification Open - National 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2018-10-06 gestion (PAG) de la zone Enhancement Implementation Selection pastorale de Barani (48 924 ha) BF-PRAPS-BF-46012-CS-CQS / Plan d'aménagement et de Consultant Natural Resource Management Pending gestion (PAG) de la zone IDA / 56490 Post Qualification Open - National 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2018-10-06 Enhancement Implementation pastorale de Sondré Est (16 459 Selection ha) ML-PRAPS-ML-46328-CS-CQS / Réalisation d'une té ude pour Consultant l'évaluation des superficies et de Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-03 2018-09-07 2019-03-06 la qualité des pâturages dans les Implementation Selection zones du Sahel Occidental, du Delta Central et du Mali Nord-Est ML-PRAPS-ML-46378-CS-CQS / Recrutement d'une ONG pour l'Appui au renforcement de Consultant capacité des membres des Pending IDA / 56500 Pastoral Crisis Management Post Qualification Open - National 0.00 2018-05-14 2018-06-04 2018-07-18 2018-08-17 2018-09-21 2019-03-20 organisations pastorales sur la Implementation Selection vie associative, l'exploitation et la maintenance des infrastructures pastorales ML-PRAPS-ML-46542-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux Consultant Natural Resource Management Pending d'aménagement de 4110 IDA / 56500 Post Qualification Open - National 0.00 2018-08-14 2018-09-04 2018-10-18 2018-11-17 2018-12-22 2019-06-20 Enhancement Implementation hectares de bourgoutières dans Selection les Régions de Ségou, Mopti, Tombouctou et Gao ML-PRAPS-ML-46560-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux 300 Consultant Natural Resource Management Pending km de pare- feu autour des IDA / 56500 Post Qualification Open - National 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Enhancement Implementation zones de pâturages dans les Selection cercles de Bankass, Douentza et Youwarou (région de Mopti) ML-PRAPS-ML-46561-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux 330 Consultant km de pare- feu autour des Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 zones de pâturages dans les Enhancement Implementation Selection cercles de Gao, Ansongo (région de Gao) et Niono (région de Ségou) ML-PRAPS-ML-47112-CS-CQS Consultant Natural Resource Management Pending / Etude géophysique IDA / 56500 Post Qualification Open - National 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-27 2018-08-31 2019-02-27 Enhancement Implementation d'implantation de 23 forages Selection ML-PRAPS-ML-46757-CS-CQS Consultant Natural Resource Management Pending / Etude géophysique IDA / 56500 Post Qualification Open - National 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-27 2018-08-31 2019-02-27 Enhancement Implementation d'implantation de 23 forages Selection BF-CILSS-46764-CS-CQS / Consultant Etude sur l'utilisation de Pending IDA / D0640 Pastoral Crisis Management Post Qualification Open - International 0.00 2018-03-08 2018-03-29 2018-05-12 2018-05-26 2018-06-16 2018-10-14 l'approche proxy calorique avec Implementation Selection les produits de l'élevage ML-PRAPS-ML-46972-CS-CQS Consultant / Etudes complémentaires de la Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2018-05-22 2018-06-12 2018-07-26 2018-08-25 2018-09-29 2019-03-28 Stratégie Nationale d'hydraulique Enhancement Implementation Selection Pastorale ML-PRAPS-ML-46974-CS-CQS / Surveillance des travaux pour Consultant Pending les infrastructures marchandes et IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2018-05-29 2018-06-19 2018-08-02 2018-09-01 2018-10-06 2019-04-04 Implementation des magasins d'aliments bétail Selection dans la zone du Mali Nord Est ML-PRAPS-ML-47095-CS-CQS Consultant / Appui à l'élaboration des plans Pending IDA / 56500 Pastoral Crisis Management Post Qualification Open - National 0.00 2018-04-18 2018-05-09 2018-06-22 2018-07-22 2018-08-26 2019-02-22 de contingence communaux par Implementation Selection un bureau Consultant REF 41 / Contrôle -surveillance Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2017-03-16 2017-04-06 2017-05-20 2017-06-19 2017-07-24 2018-01-20 des travaux Implementation Selection MR-PRAPS-MR -48817-CS- Consultant CQS / Assistance Technique Pending IDA / D0660 Animal Health Improvement Post Qualification Open - National 0.00 2018-05-15 2018-06-05 2018-07-19 2018-07-29 2018-08-23 2018-10-07 pour opérationnalisation du Implementation Selection dispositif de la composante 1 MR-PRAPS-MR -48818-CS- CQS / Assistance technique Consultant Pending pour la rédaction d'un manuel de IDA / D0660 Animal Health Improvement Post Qualification Open - National 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-27 2018-08-31 2018-10-15 Implementation procédures de la réglementation Selection existante MR-PRAPS-MR -48825-CS- Consultant CQS / Recrutement d'un Pending IDA / D0660 Market Access Facilitation Post Qualification Open - National 0.00 2018-05-21 2018-06-11 2018-07-25 2018-08-04 2018-08-24 2018-09-23 assistant technique pour Implementation Selection l'opérationnalisation de la FNE MR-PRAPS-MR -48831-CS- Consultant CQS / Recrutement d'un Pending IDA / D0660 Pastoral Crisis Management Post Qualification Open - National 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-07 2018-07-27 2018-08-26 consultant pour la finalisation et Implementation Selection la mise sur pied du SI Page 14 MR-PRAPS-MR -48840-CS- Consultant CQS / Bureau d'études pour Project Management and Pending IDA / D0660 Post Qualification Open - National 0.00 2018-05-15 2018-05-30 2018-07-13 2018-07-23 2018-08-23 2018-09-22 former le personnel du ME en Institutional Support Implementation Selection bureautique et informatique MR-PRAPS-MR -48841-CS- CQS / Screening et Evaluation Consultant Project Management and Pending impact environnementale et IDA / D0660 Post Qualification Open - National 0.00 2018-05-15 2018-05-30 2018-07-13 2018-07-23 2018-08-12 2018-09-26 Institutional Support Implementation social pour 73 parcs de Selection vaccination. . MR-PRAPS-MR -48842-CS- CQS / Evaluation impact Consultant Project Management and Pending environnemental pour fonçage IDA / D0660 Post Qualification Open - National 0.00 2018-04-20 2018-05-11 2018-06-24 2018-07-24 2018-08-28 2018-09-27 Institutional Support Implementation de 18 forages (TDRs et NIES) et Selection 11 puits. MR-PRAPS-MR -48844-CS- Consultant CQS / Evaluation Project Management and Pending IDA / D0660 Post Qualification Open - National 0.00 2018-05-07 2018-05-28 2018-07-11 2018-07-26 2018-08-15 2018-09-14 environnementale de 7 marchés Institutional Support Implementation Selection à bétail et 2 aires de repos MR-PRAPS-MR -48965-CS- Consultant CQS / Evaluation impact Project Management and Pending IDA / D0660 Post Qualification Open - National 0.00 2018-05-15 2018-06-05 2018-07-19 2018-07-29 2018-08-18 2018-09-17 environnementale pour fonçage Institutional Support Implementation Selection de 12 forages (TDRs et NIES) Consultant 40-C/PRAPS / Etude sur les IDA / 56490 Animal Health Improvement Post Qualification Open - National 0.00 Canceled 2017-03-31 2017-04-14 2017-05-05 2017-05-12 2017-06-16 2017-07-16 mandats sanitaires Selection TD-PRAPS-TD-50597-CS-QCBS / Recrutement d'un ingénieur Quality And Cost- Pending conseil pour la supervision et IDA / D0650 Market Access Facilitation Prior Open - National 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 Based Selection Implementation contrôle des infrastructures pastorales INDIVIDUAL CONSULTANTS Page 15