PROCUREMENT PLAN (Textual Part) Project information: Dominican Republic, Integrated Social Protection and Promotion Project , P147213 Project Implementation agency: Gabinete de Coordinación de Política Sociales (GCPS) Date of the Procurement Plan: 11/19/2018 Period covered by this Procurement Plan: 18 MONTHS Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. i This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Not Applicable such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Not Applicable When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; “Not Applicable” Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] “Not Applicable” Other Relevant Procurement Information. We have other procedures that we are using that were established in the Operational Manual, for the selection of training providers, under subcomponent 1.3, following the procedures in point 3.19 of the Bank's procurement rules. Likewise, the Operative Manual establishes the contracting of minor works of subcomponent 1.2, where non-governmental organizations (NGOs) will be convened, using an approach of Community Participation in Contracting (PCC or CDD), following the provisions of the Bank's procurement rules. iRules Acquisitions Of Goods, Works And Services Different From The Consultants With Loans Of The IBRD, Ida Credits And Donations By Bank World Borrowers January 2011 Revised In July 2014 PROCUREMENT Dominican Republic : INTEGRATED SOCIAL PROTECTION AND PROMOTION PROJECT PLAN General Information Country: Dominican Republic Bank’s Approval Date of the Original Procurement Plan: 2018-04-24 2019-11-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147213 GPN Date: Project Name: INTEGRATED SOCIAL PROTECTION AND PROMOTION PROJECT Loan / Credit No: IBRD / 84790 Executing Agency(ies):Social Policy Coordination Cabinet WORKS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-GCPS-80213-CW-RFB / (Act. 1.2.2.1.2) Component 1. Integrated Contratación de obras Area-Based Social Solicitud de Single Stage - En IBRD / 84790 Previa Open - National 7,169,295.82 0.00 2018-10-01 2018-10-11 2018-11-26 2019-01-07 2019-02-13 2020-05-01 para la rehabilitación de Protection and Pro-poor ofertas One Envelope ejecución pisos de tierra por Service Delivery cemento de viviendas PSIP5AESPCDD / (Act. 1.2.1.1) Subproyectos Component 1. Integrated Participación de ejecutados por ONG para Area-Based Social la comunidad En la adecuación (pisos de IBRD / 84790 Previa Open - National 3,250,000.00 0.00 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-14 Protection and Pro-poor en las ejecución tierra por cemento) de las Service Delivery adquisiciones viviendas en las provincias seleccionadas PSIP-10-LPI-OC / (Act. 1.2.2.1) Contratación de Component 1. Integrated contratistas privados para Area-Based Social Solicitud de Open - Single Stage - En IBRD / 84790 Previa 3,430,704.00 0.00 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-24 2019-11-20 la rehabilitación de pisos Protection and Pro-poor ofertas International One Envelope ejecución de tierra por cemento de Service Delivery viviendas DO-GCPS-128159-CW- RFQ / (Act. 1.2.2.1) Lote 31- (214 viviendas) - Fase IV "Sustitución de Piso de Component 1. Integrated tierra por pisos de Area-Based Social Solicitud de Single Stage - En IBRD / 84790 Posterior Open - National 319,288.00 0.00 2019-09-07 2019-11-02 2020-04-30 cemento", Provincia: Azua, Protection and Pro-poor cotizaciones One Envelope ejecución Municipios: (Estebania, Service Delivery Las Charcas, Peralta, Pueblo Viejo, Sabana Yegua, Tabara Arriba, Guayabal) DO-GCPS-128162-CW- RFQ / (Act. 1.2.2.1) Lote 32 - (212 viviendas) - Component 1. Integrated Fase IV "Sustitución de Area-Based Social Solicitud de Single Stage - En Piso de tierra por pisos IBRD / 84790 Posterior Open - National 316,304.00 0.00 2019-09-07 2019-11-02 2020-04-30 Protection and Pro-poor cotizaciones One Envelope ejecución de cemento", Provincia: Service Delivery San Juan de la Maguana, Municipios: (El Cercado, Sección, El pinar) DO-GCPS-128163-CW- RFQ / (Act. 1.2.2.1) Lote 33 - (219 viviendas) - Component 1. Integrated Fase IV "Sustitución de Area-Based Social Solicitud de Single Stage - Ejecución Piso de tierra por pisos IBRD / 84790 Posterior Open - National 326,748.00 0.00 2019-09-07 2019-11-02 2020-04-30 Protection and Pro-poor cotizaciones One Envelope pendiente de cemento", Provincia: Service Delivery Elias Piña, Municipios: (Comendador (Urbano y rural), Juan Santiago) GOODS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Integrated PIPPS - 197- 2016 / Area-Based Social Solicitud de Open - Proceso Adquisicion de IBRD / 84790 Previa 60,000.00 38,500.00 Firmado Protection and Pro-poor cotizaciones International Vehiculos Service Delivery Component 2. DO-GCPS-78735-GO-RFB Strengthening of the / (Act. 2.2.1.1.4.5) Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 372.74 0.00 2018-11-04 2018-12-30 2019-06-28 Uniformes de cotizaciones One Envelope pendiente and Support to Targeted Encuestadores Households DO-GCPS-78829-GO-RFB / (Act. 3.2.2.3.2) Component 3. Enhancing Solicitud de Single Stage - Ejecución Adquisición de equipos IBRD / 84790 Equity and Results- Posterior Open - National 200,000.00 0.00 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-07-17 ofertas One Envelope pendiente para la implementación de orientation la segunda fase del SIME DO-GCPS-79030-GO-RFB Component 3. Enhancing Solicitud de Single Stage - Ejecución / (Act. 3.4.2.1.2) Software IBRD / 84790 Equity and Results- Posterior Limited 45,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones One Envelope pendiente y Digitalización orientation DO-GCPS-79035-GO-RFB / (Act. 3.4.2.1.4) Component 3. Enhancing Adquisición de Equipos Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 15,000.00 0.00 2018-10-03 2018-11-28 2019-05-27 para adecuación de Salón cotizaciones One Envelope pendiente orientation de Conferencias UTP, equipos de comunicación. DO-GCPS-79038-GO-RFB Component 3. Enhancing / (Act. 3.4.2.1.5) Aumento Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 100,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 Capacidad de cotizaciones One Envelope pendiente orientation Almacenamientos Servidores DO-GCPS-80975-GO-RFQ Component 3. Enhancing / (Act. 3.4.2.1.1) Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 45,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 Adquisición de Equipos y cotizaciones One Envelope pendiente orientation Software para la UTP Component 2. PSIP-285-LPN-B / (Act. Strengthening of the Solicitud de Single Stage - Ejecución 2.1.3.5) Motocicletas para IBRD / 84790 PROSOLI CCT Program Posterior Open - National 235,238.00 0.00 2017-01-07 2017-03-04 2017-08-31 cotizaciones One Envelope pendiente coordinadores municipales and Support to Targeted Households PSIP-282-CP-B / Component 2. (Act.2.3.5.1.2) Adquirir el Strengthening of the Solicitud de Single Stage - Ejecución Certificado para apoyar el IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,519.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones One Envelope pendiente intercambio de datos de and Support to Targeted la JCE e interoperatividad Households PSIP-87-CP-B / (Act. 3.1.1.1.1) Adquisición de almacenamiento para las Component 3. Enhancing Solicitud de Single Stage - Ejecución bases de datos 1er, 2do, IBRD / 84790 Equity and Results- Posterior Limited 58,906.00 0.00 2016-07-13 2016-09-07 2017-03-06 cotizaciones One Envelope pendiente 3er ESH, Base de datos orientation maestras y adicionales. SIUBEN PSIP-250-CP-B / Component 3. Enhancing Solicitud de Single Stage - Ejecución (Act.3.1.1.1.8) Vestimenta- IBRD / 84790 Equity and Results- Posterior Limited 1,761.00 0.00 2017-01-25 2017-03-22 2017-09-18 cotizaciones One Envelope pendiente Piloto Estudio orientation Page 1 PSIP-286-CP-B / (Act. 3.1.1.2.2.2.1) Adquisicion de equipo para la Component 3. Enhancing Solicitud de Single Stage - Ejecución Preparación y distribución IBRD / 84790 Equity and Results- Posterior Limited 9,561.00 0.00 2017-06-17 2017-08-12 2018-02-08 cotizaciones One Envelope pendiente de la cartografía (420.000 orientation mapas para distribución del trabajo) PSIP-287-CP-B / (Act. Component 3. Enhancing 3.1.1.2.2.2.2) Adquisición Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 1,678.00 0.00 2016-11-26 2017-01-21 2017-07-20 de Equipo Drone para la cotizaciones One Envelope pendiente orientation ejecución del ESH DO-GCPS-97727-GO-RFQ Component 3. Enhancing / (Act. 3.3.9.8) Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 5,884.06 0.00 2019-02-05 2019-04-02 2019-09-29 Readecuación de oficinas cotizaciones One Envelope pendiente orientation del proyecto Cultura Ciudadana. DO-GCPS-78783-GO-RFB / (Act. 2.2.2.3.1) Component 2. Automatización del Strengthening of the mecanismo mediante la Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 38,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 adquisión de tabletas para cotizaciones One Envelope pendiente and Support to Targeted el Feedback de los Households Reportes Comunitarios en los puntos solidarios o colmados DO-GCPS-78788-GO-RFB Component 2. / (Act. 2.2.3.9) Adquisición Strengthening of the Solicitud de Single Stage - Ejecución de Mobiliario y Equipos IBRD / 84790 PROSOLI CCT Program Posterior Limited 2,592.97 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones One Envelope pendiente Informáticos para los and Support to Targeted Reportes Comunitarios. Households PSIP-187-CP-B / (Act. Component 2. 2.1.3.2.3.2.1) Material Strengthening of the Solicitud de Single Stage - Ejecución Gastable para la IBRD / 84790 PROSOLI CCT Program Posterior Limited 15,991.66 0.00 2016-03-21 2016-05-16 2016-11-12 cotizaciones One Envelope pendiente imrpesion de la Ficha del and Support to Targeted levantamiento Households PSIP-313-CP-B / (Act. 2.1.4.3) Adquisición de equipos informáticos para capacitación y operación Component 2. de los Comites Strengthening of the Solicitud de Single Stage - Ejecución Provinciales y Regionales IBRD / 84790 PROSOLI CCT Program Posterior Limited 54,965.49 0.00 2017-05-07 2017-07-02 2017-12-29 cotizaciones One Envelope pendiente en la implementacion and Support to Targeted sobre la estrategia Households Progresando Unidos (Laptop, impresoras, Camaras Digitales, Scanner, Proyectores, etc.) PSIP-296-CP-B / (Act. 2.2.1.1.3) Adquisición de Component 2. Equipos Informáticos para Strengthening of the la expansión de puntos Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 61,294.97 0.00 2016-11-06 2017-01-01 2017-06-30 solidarios (PC, Printers, cotizaciones One Envelope pendiente and Support to Targeted Scanners, UPS y Routers Households para servicios telefónicos y conectividad) Component 2. PSIP-288-CP-B / (Act. Strengthening of the 2.2.1.1.5) Adquisición de Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 12,473.17 0.00 2017-06-12 2017-08-07 2018-02-03 Uniformes para oficiales cotizaciones One Envelope pendiente and Support to Targeted de servicios de PS Households Component 2. PSIP-289-CP-B / (Act. Strengthening of the 2.2.1.1.7) Adquisicion de Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 11,500.12 0.00 2016-11-06 2017-01-01 2017-06-30 mobiliario para los puntos cotizaciones One Envelope pendiente and Support to Targeted solidarios Households PSIP-57-CP-SGO / (Act. Component 2. 2.2.3.2) Material gastable Strengthening of the para para la Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 3,052.98 0.00 2017-06-12 2017-08-07 2018-02-03 Implementacion de los 5 cotizaciones One Envelope pendiente and Support to Targeted ciclos de Reportes Households Comunitarios en las 14 provincias seleccionadas PSIP-194-CP-B / (Act. 2.3.2.2.1) Adquisición de Component 2. equipos de tecnologia Strengthening of the Solicitud de Single Stage - Ejecución (desktop, laptop, IBRD / 84790 PROSOLI CCT Program Posterior Limited 22,784.06 0.00 2017-02-06 2017-04-03 2017-09-30 cotizaciones One Envelope pendiente multimedia, software y and Support to Targeted equipos de backup y Households almacenamiento, Swich) PSIP-193-CD-S / (Act. Component 2. 2.3.2.2.2) Actualizacion de Strengthening of the licencias del sistema de Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 54,841.70 0.00 2017-06-12 2017-08-07 2018-02-03 mensajeria y correo cotizaciones One Envelope pendiente and Support to Targeted electronico para apoyar la Households plataforma Punto Solidario. Component 2. PSIP-74-CP-B / (Act. Strengthening of the 2.3.2.3) Adquisción de Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 16,080.01 0.00 2017-06-12 2017-08-07 2018-02-03 herramientas de seguridad cotizaciones One Envelope pendiente and Support to Targeted (Licencias de Antivirus) Households PSIP-77-CD-B / Component 2. (Act.2.3.5.1) Adquisicion de Strengthening of the Adquisición Ejecución la Base de Datos de IBRD / 84790 PROSOLI CCT Program Previa Direct 15,132.85 0.00 2016-05-13 2016-05-18 2016-06-22 2016-12-19 directa pendiente Ciudadanos de la JCE y and Support to Targeted sus actualizaciones por un Households perido de 4 años PSIP-274-CP-B / (Act. 3.2.3.2) Adquisición Component 3. Enhancing equipo informatico para Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 10,122.57 0.00 2017-06-12 2017-08-07 2018-02-03 implementación del cotizaciones One Envelope pendiente orientation Observatorio de Políticas Sociales PSIP-006-CP-B / (Act. Component 3. Enhancing 3.3.8.5) Equipos de Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 6,823.70 0.00 2017-06-12 2017-08-07 2018-02-03 Cómputos (Computadores cotizaciones One Envelope pendiente orientation de escritorio, Impresoras, UPS) PSIP-005-CP-B / (Act. 3.3.8.6) Materiales y Component 3. Enhancing Suministros (material Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 3,944.81 0.00 2017-06-12 2017-08-07 2018-02-03 gastable de oficina y cotizaciones One Envelope pendiente orientation bultos para cargar material de trabajo) PSIP-004-CP-B / (Act. 3.3.8.8) Adquisición de Component 3. Enhancing Solicitud de Single Stage - Ejecución prendas de vestir IBRD / 84790 Equity and Results- Posterior Limited 1,531.56 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones One Envelope pendiente (Camisetas para personal orientation de documentación) PSIP-015-CP-B / (Act. Component 3. Enhancing Solicitud de Single Stage - Ejecución 3.4.2.1.6) Equipos de IBRD / 84790 Equity and Results- Posterior Limited 60,981.91 0.00 2018-06-20 2018-08-15 2019-02-11 cotizaciones One Envelope pendiente informatíca para la UTP orientation PSIP-016-CP-B / (Act.3.4.2.2) Adquisicion Component 3. Enhancing Solicitud de Single Stage - Ejecución Equipos y mobiliarios de IBRD / 84790 Equity and Results- Posterior Limited 28,526.55 0.00 2018-01-13 2018-03-10 2018-09-06 cotizaciones One Envelope pendiente oficina UTP (varios orientation procesos de adq.) Page 2 PSPI-017-CP-B / (Act.3.4.2.4) Material Component 3. Enhancing Gastable (suministro Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 37,827.03 0.00 2016-06-08 2016-08-03 2017-01-30 operativos oficina, cotizaciones One Envelope pendiente orientation papeleria, carpetas, papel bond, material de oficina) DO-GCPS-77676-GO-RFB Component 2. / (Act. 2.2.1.1.1) Strengthening of the Solicitud de Single Stage - En Adquisición de 2 Unidades IBRD / 84790 PROSOLI CCT Program Posterior Open - National 490,000.00 0.00 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-07-17 ofertas One Envelope ejecución Móviles para Brindar los and Support to Targeted Servicios de Puntos Households Solidarios DO-GCPS-78807-GO-RFB / (Act. 2.3.7.1) Adquisición Component 2. de equipo y servidores Strengthening of the Solicitud de Single Stage - Ejecución para apoyo de bases de IBRD / 84790 PROSOLI CCT Program Posterior Open - National 211,627.93 0.00 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-07-17 ofertas One Envelope pendiente datos intermediarios y and Support to Targeted servicios de web para Households intercambio de data entre aplicaciones DO-GCPS-104154-GO- Component 2. RFQ / (Act. 2.3.8) Strengthening of the Solicitud de Single Stage - Ejecución Adquisición de Licencias IBRD / 84790 PROSOLI CCT Program Posterior Open - National 8,300.00 0.00 2019-04-03 2019-05-05 2019-06-04 cotizaciones One Envelope pendiente para Equipos Informáticos and Support to Targeted para el monitoreo del Households Data Center. DO-GCPS-104192-GO- Component 2. RFQ / (Act. 2.1.3.3.2) Strengthening of the Solicitud de Single Stage - Ejecución Camisetas para IBRD / 84790 PROSOLI CCT Program Posterior Limited 11,118.12 0.00 2019-04-03 2019-05-29 2019-11-25 cotizaciones One Envelope pendiente Supervisores Enlaces and Support to Targeted Progreando Unidos Households DO-GCPS-104885-GO- Component 3. Enhancing Solicitud de Single Stage - Ejecución RFQ / (Act. 3.2.5.4) IBRD / 84790 Equity and Results- Posterior Limited 50,000.00 0.00 2019-04-05 2019-05-31 2019-11-27 cotizaciones One Envelope pendiente Adquisición de Hardware orientation y Software DO-GCPS-104887-GO- Component 3. Enhancing Solicitud de Single Stage - Ejecución RFQ / (Act. 3.2.5.5) IBRD / 84790 Equity and Results- Posterior Limited 2,000.00 0.00 2019-04-05 2019-05-31 2019-11-27 cotizaciones One Envelope pendiente Adquisición de mobiliario orientation de oficina Component 2. DO-GCPS-105069-GO- Strengthening of the RFQ / (Act. 2.2.1.1.7) Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 18,542.18 0.00 2019-05-05 2019-06-30 2019-12-27 Adquisición de mobiliario cotizaciones One Envelope pendiente and Support to Targeted para los puntos solidarios Households Component 2. DO-GCPS-105070-GO- Strengthening of the RFQ / (Act. 2.3.2.2.1) Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 22,000.00 0.00 2019-05-05 2019-06-30 2019-12-27 Adquisición de equipos de cotizaciones One Envelope pendiente and Support to Targeted tecnología Households DO-GCPS-77484-GO-RFB / (Act. 1.3.2.6.5) Equipos y Component 1. Integrated Materiales para las Area-Based Social Solicitud de Single Stage - Ejecución actividades del IBRD / 84790 Posterior Limited 8,494.00 0.00 2018-11-04 2018-12-30 2019-06-28 Protection and Pro-poor cotizaciones One Envelope pendiente Subcomponentes Service Delivery (Adquisición de Tabletas para Supervisión de cursos) DO-GCPS-119186-GO- Component 1. Integrated RFQ / (Act. 1.2.1.9) Area-Based Social Solicitud de Single Stage - Ejecución IBRD / 84790 Posterior Open - National 18,000.00 0.00 2019-06-19 2019-08-14 2020-02-10 Adquisición de Equipos Protection and Pro-poor cotizaciones One Envelope pendiente Informáticos para el Service Delivery Depto. de Infraestructura DO-GCPS-119188-GO- Component 1. Integrated RFQ / (Act. 1.2.1.9 Area-Based Social Solicitud de Single Stage - Ejecución IBRD / 84790 Posterior Open - National 1,800.00 0.00 2019-06-19 2019-08-14 2020-02-10 Adquisición de Laptop Protection and Pro-poor cotizaciones One Envelope pendiente para el Depto. de Service Delivery Infraestructura) DO-GCPS-119190-GO- Component 2. RFQ / (Ac.t. 2.3.8 Strengthening of the Solicitud de Single Stage - Ejecución Adquisición de Switches y IBRD / 84790 PROSOLI CCT Program Posterior Open - National 17,500.00 0.00 2019-06-19 2019-08-14 2020-02-10 cotizaciones One Envelope pendiente Disco Duros para el Data and Support to Targeted Center) Households Component 2. DO-GCPS-80781-GO-RFQ Strengthening of the / (Act. 2.2.1.4) Solicitud de Single Stage - IBRD / 84790 PROSOLI CCT Program Posterior Limited 45,000.00 0.00 Cancelado 2018-11-04 2018-12-30 2019-06-28 Habilitación de Punto cotizaciones One Envelope and Support to Targeted Solidario Households DO-GCPS-98430-GO-RFQ Component 2. / (Act.2.3.7.1.2.3) Strengthening of the Solicitud de Single Stage - Ejecución Adquisición de Licencias IBRD / 84790 PROSOLI CCT Program Posterior Open - National 73,374.00 0.00 2019-03-05 2019-04-30 2019-10-27 cotizaciones One Envelope pendiente y Servidores para el and Support to Targeted Data Center Households DO-GCPS-121823-GO-RFB / (Act. 3.3.17) Adquisición Component 3. Enhancing Solicitud de Single Stage - En de Vehículos para IBRD / 84790 Equity and Results- Posterior Open - National 250,000.00 0.00 2019-07-31 2019-08-10 2019-09-09 2019-10-09 2019-11-13 2020-05-11 ofertas One Envelope ejecución Monitoreo y Evaluación de orientation los Trabajos de campo DO-GCPS-134510-NC- Component 2. RFQ / (Act. 2.3.8) Central Strengthening of the Solicitud de Single Stage - Ejecución Telefónica para el IBRD / 84790 PROSOLI CCT Program Posterior Limited 46,000.00 0.00 2019-10-05 2019-11-30 2020-05-28 cotizaciones One Envelope pendiente Gabinete de Coordinación and Support to Targeted de Política Social Households DO-GCPS-141407-GO- Component 2. RFQ / (Act. 2.2.4.1) Strengthening of the Solicitud de Single Stage - Ejecución Equipos para Talleres de IBRD / 84790 PROSOLI CCT Program Posterior Limited 88,252.00 0.00 2019-11-05 2019-12-31 2020-06-28 cotizaciones One Envelope pendiente Ebanistería para CTC and Support to Targeted Makers Households DO-GCPS-141409-GO- Component 2. RFQ / (Act. 2.2.4.1.1) Strengthening of the Solicitud de Single Stage - Ejecución Equipos y materiales IBRD / 84790 PROSOLI CCT Program Posterior Limited 96,000.00 0.00 2019-11-05 2019-12-31 2020-06-28 cotizaciones One Envelope pendiente Eléctricos para Talleres de and Support to Targeted Robotica para CTC Households Makers Component 2. DO-GCPS-141411-GO- Strengthening of the RFQ / (Act. 2.2.4.1.2) Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 61,000.00 0.00 2019-11-05 2019-12-31 2020-06-28 Equipos para Talleres cotizaciones One Envelope pendiente and Support to Targeted Textil para CTC Makers Households DO-GCPS-144626-GO- Component 3. Enhancing Solicitud de Single Stage - Ejecución RFQ / (Act. 3.3.9.10) IBRD / 84790 Equity and Results- Posterior Limited 1,746.00 0.00 2019-12-04 2020-01-29 2020-07-27 cotizaciones One Envelope pendiente Adquisición de Equipos orientation Tecnológicos DO-GCPS-145729-GO- RFQ / Vestimenta e Component 3. Enhancing Solicitud de Single Stage - Ejecución Identificación para el el IBRD / 84790 Equity and Results- Posterior Limited 2,717.00 0.00 2019-12-04 2020-01-13 2020-07-11 cotizaciones One Envelope pendiente personal del orientation Levantamiento de Reportes Comunitarios NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2. DO-GCPS-78740-NC-RFB Strengthening of the / (Act. 2.2.1.1.4.6) Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,627.24 0.00 2018-11-04 2018-12-30 2019-06-28 Reproducción de cotizaciones One Envelope pendiente and Support to Targeted Materiales Households Page 3 Component 2. DO-GCPS-78750-NC-RFB Strengthening of the Solicitud de Single Stage - Ejecución / (Act. 2.2.1.1.4.10) Mesa IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,587.08 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones One Envelope pendiente de Ayuda and Support to Targeted Households DO-GCPS-78982-NC-RFB / (Act. 3.3.4.4) Component 3. Enhancing Reproducción de Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 37,500.00 0.00 2018-11-04 2018-12-30 2019-06-28 documento de cotizaciones One Envelope pendiente orientation sistematizacion de buenas practicas en la protección social del país DO-GCPS-79020-NC-RFB / (Act. 3.3.9.11) Component 3. Enhancing Contratación de firma Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 12,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 para la realización de un cotizaciones One Envelope pendiente orientation audiovisual educativo para las charlas universitarias DO-GCPS-79029-NC-RFB / (Act. 3.3.9.12) Impresión Component 3. Enhancing Solicitud de Single Stage - Ejecución de volantes, carpetas y IBRD / 84790 Equity and Results- Posterior Limited 10,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones One Envelope pendiente creación del contenido orientation para los mismos PSIP-28-CP-SGO / (Act. 2.1.2.3) Logística para la Component 2. Creación de los Comites Strengthening of the Provinciales y capacitación Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 29,701.00 0.00 2017-06-12 2017-08-07 2018-02-03 de la estrategia cotizaciones One Envelope pendiente and Support to Targeted Progresando Unidos y del Households funcionamiento de los comites PSIP-195-CP-S / (Act. Component 2. 2.1.3.2.2) Diagramacion y Strengthening of the Solicitud de Single Stage - Ejecución Reproduccion de los IBRD / 84790 PROSOLI CCT Program Posterior Limited 55,832.00 0.00 2017-12-09 2018-02-03 2018-08-02 cotizaciones One Envelope pendiente Manuales (material de and Support to Targeted apoyo) Households PSIP-SNC-001 / (Act. 2.1.3.2.3.4.1) Seminario introductorio a equipo Component 2. SENASA (gerentes Strengthening of the Solicitud de Single Stage - Ejecución regionales y encargados de IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,000.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones One Envelope pendiente afiliaciones) y de and Support to Targeted INFOTEP (asesores y Households coordinadores de oficina) a realizarse en 4 regionales Component 2. PSIP-SNC-002 / (Act. Strengthening of the Solicitud de Single Stage - Ejecución 2.1.3.2.3.4.1) Seminario IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,000.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones One Envelope pendiente introductorio para COS and Support to Targeted Households PSIP-37-CP-S / Component 2. (Act.2.1.5.1) Reproduccion Strengthening of the Solicitud de Single Stage - Ejecución de Materiales para cambio IBRD / 84790 PROSOLI CCT Program Posterior Limited 6,400.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones One Envelope pendiente de comportamiento y and Support to Targeted Escuela de Familia Households PSIP-248-CP-SNC / Component 3. Enhancing Solicitud de Single Stage - Ejecución (Act.3.1.1.1.6) Alquiler de IBRD / 84790 Equity and Results- Posterior Limited 4,760.00 0.00 2017-01-25 2017-03-22 2017-09-18 cotizaciones One Envelope pendiente Vehiculos- Piloto Estudio orientation DO-GCPS-97705-NC-RFQ Component 2. / (Act. 2.1.3.1.3) Apoyo al Strengthening of the monitoreo y seguimiento Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 8,099.61 0.00 2019-02-05 2019-03-28 2019-09-24 del cumplimiento de las cotizaciones One Envelope pendiente and Support to Targeted corresponsabilidades de Households salud y educación Component 2. DO-GCPS-80502-NC-RFQ Strengthening of the / (Act. 2.2.1.1.2) Adquisición Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Direct 40,000.00 0.00 2019-07-31 2019-08-05 2019-09-09 2020-03-07 Mantenimiento de las directa pendiente and Support to Targeted Unidades Móviles Households Component 2. DO-GCPS-78747-NC-RFB Strengthening of the Solicitud de Single Stage - Ejecución / (Act. 2.2.1.1.4.8) IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,725.41 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones One Envelope pendiente Alquiler de Vehiculos and Support to Targeted Households PSIP-254-CP-S / (Act. Component 1. Integrated (1.3.1.1.3) Seguro Contra Area-Based Social Solicitud de Single Stage - Ejecución IBRD / 84790 Posterior Limited 20,000.00 0.00 2016-06-06 2016-08-01 2017-01-28 Accidentes a Jovenes Protection and Pro-poor cotizaciones One Envelope pendiente durante la Fase de Service Delivery Pasantia PSIP-CP-SC / (Act. 2.1.3.2.3.3.2) Reproducción de rotafolios de educación Component 2. financiera a ser utilizados Strengthening of the en la capacitación de las Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 8,646.92 0.00 2016-08-27 2016-10-22 2017-04-20 familias beneficiarias de cotizaciones One Envelope pendiente and Support to Targeted la 14 provincias Households priorizadas del proyecto Progresando Unidos. Y notarizacion de documento Component 2. PSIP-45-CP-S / (Act. Strengthening of the 2.2.1.1.8) Materiales Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 3,068.06 0.00 2017-06-06 2017-08-01 2018-01-28 impresos (Brochures, cotizaciones One Envelope pendiente and Support to Targeted letreros) Households PSIP-270-CP-S / (Act. 2.2.3.10) Reproduccion de Component 2. guias, cuestionarios y Strengthening of the Solicitud de Single Stage - Ejecución manuales para la IBRD / 84790 PROSOLI CCT Program Posterior Limited 3,893.57 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones One Envelope pendiente Implementation de los 5 and Support to Targeted ciclos de los Reportes Households Comunitarios PSIP-005-SC / (Act. 3.3.2.4) Asistencia técnica Component 3. Enhancing para la formulación y Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 15,171.77 0.00 2017-06-12 2017-08-07 2018-02-03 seguimiento a la política cotizaciones One Envelope pendiente orientation de reducción de embrazo en adolescentes y desigualdad de género DO-GCPS-87346-NC-RFQ / (Act. 3.3.3.1) Experto para la definición y Component 3. Enhancing aplicación de la Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 8,565.65 0.00 2017-06-12 2017-08-07 2018-02-03 metodología de la cotizaciones One Envelope pendiente orientation construcción de una Política Publica de Vivienda para Grupos Vulnerables. (pago de pasajes y viátios) PSIP-001-SC / (Act. 3.3.9.2) Pago de 8 boletos Component 3. Enhancing aéreos de asesores Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 6,218.58 0.00 2018-08-14 2018-10-09 2019-04-07 internacionales para el cotizaciones One Envelope pendiente orientation diseño de la medición y talleres de transferencia metodológica PSIP-019-CP-SNC / Component 3. Enhancing Solicitud de Single Stage - Ejecución (Act.3.4.2.16) Transporte y IBRD / 84790 Equity and Results- Posterior Limited 5,258.04 0.00 2018-01-13 2018-03-10 2018-09-06 cotizaciones One Envelope pendiente almacenaje orientation Page 4 DO-GCPS-98409-NC-CDD / (Act. 1.3.1.1.1) 3ra.. Contratación de los Component 1. Integrated Participación de Centros Operativos del Area-Based Social la comunidad En Sistema (COS) para IBRD / 84790 Posterior Open - National 2,700,000.00 0.00 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 Protection and Pro-poor en las ejecución capacitación en Service Delivery adquisiciones competencias básicas y habilidades técnicas dirigidos a los jóvenes beneficiarios del Proyecto PSIP-111-PS-CDD / (Act. 1.3.1.1.1) 2da. Contratación de los Component 1. Integrated Participación de Centros Operativos del Area-Based Social la comunidad En Sistema (COS) para IBRD / 84790 Previa Open - National 3,431,183.00 0.00 2017-12-15 2017-12-20 2018-01-31 2018-03-02 2018-04-06 2018-10-03 Protection and Pro-poor en las ejecución capacitación en Service Delivery adquisiciones competencias básicas y habilidades técnicas dirigidos a los jóvenes beneficiarios del Proyecto DO-GCPS-104210-NC- RFQ / Servicios de Alquiler de Vehículos para Component 3. Enhancing Solicitud de Single Stage - Ejecución continuidad del IBRD / 84790 Equity and Results- Posterior Limited 76,800.00 0.00 2019-03-09 2019-03-25 2019-09-21 cotizaciones One Envelope pendiente Levantamiento del 3ESH orientation (Regional Distrito Nacional, Santo Domingo y Este) DO-GCPS-104211-NC- RFQ / Servicios de Alquiler de Vehículos para Component 3. Enhancing Solicitud de Single Stage - Ejecución la realización de la IBRD / 84790 Equity and Results- Posterior Limited 77,200.00 0.00 2019-03-09 2019-03-25 2019-09-21 cotizaciones One Envelope pendiente continuidad del orientation Levantamiento del 3ESH (Regional: Nordeste, Central, Norcentral y Noroeste) DO-GCPS-104212-NC- RFQ / Servicios de Vehículos para la Component 3. Enhancing Solicitud de Single Stage - Ejecución realización de la IBRD / 84790 Equity and Results- Posterior Limited 50,400.00 0.00 2019-03-09 2019-03-25 2019-09-21 cotizaciones One Envelope pendiente continuidad del orientation Levantamiento del 3ESH (Regional: El Valle, Enriquillo y Valdesia) DO-GCPS-104847-NC- Component 3. Enhancing Solicitud de Single Stage - Ejecución RFQ / (Act. 3.2.1.2.4.3.1) IBRD / 84790 Equity and Results- Posterior Limited 43,333.33 0.00 2019-04-05 2019-05-31 2019-11-27 cotizaciones One Envelope pendiente Alquiler de vehículo orientation DO-GCPS-105067-NC- Component 2. RFQ / (Act. 2.2.1.1.5) Strengthening of the Solicitud de Single Stage - Ejecución Adquisición de Uniformes IBRD / 84790 PROSOLI CCT Program Posterior Limited 3,000.00 0.00 2019-05-05 2019-06-30 2019-12-27 cotizaciones One Envelope pendiente para oficiales de servicios and Support to Targeted de PS Households PSIP-11-PS-CDD / (Act. 1.3.1.1.1) 1ra. Contratación de los Centros Operativos Component 1. Integrated Participación de del Sistema (COS) para Area-Based Social la comunidad Ejecución capacitación en IBRD / 84790 Previa Open - National 505,236.83 0.00 2016-06-01 2016-06-06 2016-07-18 2016-08-17 2016-09-21 2017-03-20 Protection and Pro-poor en las pendiente competencias básicas y Service Delivery adquisiciones habilidades técnicas dirigidos a los jóvenes beneficiarios del Proyecto DO-GCPS-116956-NC- Component 2. RFQ / (Act. 2.1.3.6.1) Strengthening of the Capacitación Personal Solicitud de Single Stage - Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 70,000.00 0.00 2019-07-05 2019-08-30 2020-02-26 Operativo de PROSOLI en cotizaciones One Envelope pendiente and Support to Targeted la Estrategia de Cambio Households de Comportamiento en Higiene DO-GCPS-107009-NC-RFB Component 2. / (Act. 2.1.3.6.1) Strengthening of the Capacitación Personal Solicitud de Single Stage - IBRD / 84790 PROSOLI CCT Program Posterior Open - National 100,000.00 0.00 Cancelado 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2020-01-17 Operativo de PROSOLI en ofertas One Envelope and Support to Targeted la Estrategia de Cambio Households de Comportamiento en Higiene DO-GCPS-116959-NC- RFQ / (Act. 3.2.1.2.3) Component 3. Enhancing Levantamiento de Linea Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 100,000.00 0.00 2019-06-05 2019-07-31 2020-01-27 de Base para la cotizaciones One Envelope pendiente orientation Evaluación del Impacto del subcomponente 1.2 (Mejora de Vivienda) DO-GCPS-106709-NC-RFP / (Act. 3.2.1.2.3) Levantamiento de Linea Component 3. Enhancing Pedido de Single Stage - de Base para la IBRD / 84790 Equity and Results- Posterior Open - National 100,000.00 0.00 Cancelado 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2020-01-17 propuestas One Envelope Evaluación del Impacto orientation del subcomponente 1.2 (Mejora de Vivienda) DO-GCPS-116962-NC- RFQ / (Act. 3.2.1.3.2) Component 3. Enhancing Levantamiento de Linea Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 100,000.00 0.00 2019-06-05 2019-07-31 2020-01-27 Base para la Evaluación cotizaciones One Envelope pendiente orientation Subcomponente 1.3 (Capacitación DO-GCPS-106713-NC-RFP / (Act. 3.2.1.3.2) Levantamiento de la Component 3. Enhancing Pedido de Single Stage - Linea Base para la IBRD / 84790 Equity and Results- Posterior Open - National 100,000.00 0.00 Cancelado 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2020-01-17 propuestas One Envelope Evaluación del orientation Subcomponente 1.3 (Capacitación) Component 2. DO-GCPS-119196-NC-DIR Strengthening of the / (Act. 2.2.1.3.1) Curso Adquisición Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Direct 2,600.00 0.00 2019-06-16 2019-06-17 2019-06-27 2019-12-24 Certificación Servicio al directa pendiente and Support to Targeted Cliente Households Component 2. DO-GCPS-119197-NC-DIR Strengthening of the / (Act. 2.3.6.3) Curso Adquisición Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Direct 2,600.00 0.00 2019-06-14 2019-06-15 2019-06-25 2019-12-22 Certificación en Servicio al directa pendiente and Support to Targeted Cliente Households DO-GCPS-119238-NC-DIR Component 3. Enhancing / (Act. 3.3.2.6) Diplomado Adquisición Ejecución IBRD / 84790 Equity and Results- Posterior Direct 2,770.00 0.00 2019-06-14 2019-06-19 2019-07-24 2020-01-20 en Análisis y Diseño de directa pendiente orientation Políticas Públicas DO-GCPS-119441-NC- Component 2. RFQ / (Act. 2.1.2.2.2) Strengthening of the Solicitud de Single Stage - Ejecución Impresiones de Manuales IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,665.00 0.00 2019-11-05 2019-12-31 2020-06-28 cotizaciones One Envelope pendiente para la capacitación de and Support to Targeted los Comités Provinciales y Households Regionales DO-GCPS-77489-NC-RFB / (Act. 2.1.2.2) Diagramación, Revisión e Component 2. Impresión manuales para Strengthening of the Solicitud de Single Stage - la creación de los comités IBRD / 84790 PROSOLI CCT Program Posterior Limited 19,665.00 0.00 Cancelado 2018-11-04 2018-12-30 2019-06-28 cotizaciones One Envelope y capacitación de la and Support to Targeted estrategia Progresando Households Unidos y del funcionamiento de los comités DO-GCPS-121889-NC-DIR Component 2. / (Act. 2.2.1.4) Habilitación Strengthening of the de Punto Solidario en el Adquisición Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Direct 45,000.00 0.00 2019-07-31 2019-08-05 2019-09-09 2020-03-07 Centro de Atención directa pendiente and Support to Targeted Presidencial para el Households Ciudadano, Punto GOB Page 5 DO-GCPS-78787-NC-RFB Component 2. / (Act. 2.2.3.8) Strengthening of the Solicitud de Single Stage - Publicación de los IBRD / 84790 PROSOLI CCT Program Posterior Limited 6,667.00 0.00 Cancelado 2018-11-04 2018-12-30 2019-06-28 cotizaciones One Envelope resultados de los Reportes and Support to Targeted Comunitarios Households DO-GCPS-122288-NC- RFQ / (Act. 3.2.3.3.3) Component 3. Enhancing Solicitud de Single Stage - Ejecución Impresión de Publicaciones IBRD / 84790 Equity and Results- Posterior Open - National 4,700.00 0.00 2019-07-15 2019-09-09 2020-03-07 cotizaciones One Envelope pendiente del Observatorio de orientation Políticas Sociales DO-GCPS-127345-NC- CDD / (Act. 1.3.1.1.1) 4Ta Licitación - Contratación de los Centros Operativos Component 1. Integrated Participación de del Sistema (COS, para la Area-Based Social la comunidad En IBRD / 84790 Previa Open - National 2,670,000.00 0.00 2019-08-15 2019-09-02 2019-10-02 2019-11-01 2019-12-06 2020-06-03 capacitación en Protection and Pro-poor en las ejecución competencias básicas y Service Delivery adquisiciones habilidades técnicas dirigidas a los jóvenes beneficiarios del Proyecto DO-GCPS-133697-NC- RFQ / Alquiler de Vehículos para las Component 3. Enhancing Solicitud de Single Stage - Ejecución actividades del IBRD / 84790 Equity and Results- Posterior Limited 4,685.15 0.00 2019-10-05 2019-11-30 2020-05-28 cotizaciones One Envelope pendiente Levantamiento dela orientation evaluación de Impacto de la Linea de base del subcomponente 1.2 DO-GCPS-145725-NC- Component 3. Enhancing RFQ / Alquiler de Solicitud de Single Stage - Ejecución IBRD / 84790 Equity and Results- Posterior Limited 33,067.16 0.00 2019-12-04 2020-01-29 2020-07-27 vehículos para el cotizaciones One Envelope pendiente orientation Levantamiento de Reportes Comunitarios DO-GCPS-145726-NC-DIR / Seguro de vida y contra Component 3. Enhancing Adquisición Ejecución accidente personal de IBRD / 84790 Equity and Results- Posterior Direct 273.19 0.00 2019-11-29 2019-12-04 2019-12-14 2020-06-11 directa pendiente campo para el orientation Levantamiento de Reportes Comunitarios DO-GCPS-145727-NC- RFQ / Alquiler de GPS Component 3. Enhancing Solicitud de Single Stage - Ejecución para ser utilizados en los IBRD / 84790 Equity and Results- Posterior Limited 410.00 0.00 2019-12-04 2020-01-13 2020-07-11 cotizaciones One Envelope pendiente vehículos para el orientation Levantamiento de Reportes Comunitarios DO-GCPS-145728-NC-DIR / Data para Dispositivos Component 3. Enhancing Adquisición Ejecución móviles para el IBRD / 84790 Equity and Results- Posterior Direct 1,879.00 0.00 2019-11-29 2019-12-04 2019-12-30 2020-06-27 directa pendiente Levantamiento de orientation Reportes Comunitarios CONSULTING FIRMS Activity Reference No. Actual Short List and Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of / Description Component Review Type Method Amount Terms of Reference Draft Request for Technical Proposals Evaluation Report Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual PIPPS-163-2016 / Component 1. Integrated Selección PROCESO DE AGENTE Area-Based Social Open - IBRD / 84790 Previa basada en 197,810.00 197,810.00 Cancelado VERIFICADOR Protection and Pro-poor International calidad INDEPENDIENTE Service Delivery DO-GCPS-78790-CS-QCBS Component 2. / (Act. 2.3.1.2) Strengthening of the Selección Open - Ejecución Contratación de Firma IBRD / 84790 PROSOLI CCT Program Posterior basada en 226,666.67 0.00 2018-09-28 2018-10-19 2018-12-02 2018-12-30 2019-01-29 2019-03-05 2019-04-09 2020-04-08 International pendiente Consultora para mejorar and Support to Targeted calidad y costo la plataforma Punto Households Solidario DO-GCPS-78953-CS-QCBS / (Act. 3.3.2.2.5) Diseño de Component 3. Enhancing Selección la campaña de educación Ejecución IBRD / 84790 Equity and Results- Posterior basada en Open - National 80,000.00 0.00 2018-10-30 2018-11-20 2019-01-03 2019-01-31 2019-03-02 2019-04-06 2019-05-11 2020-05-10 ciudadana par la inclusión pendiente orientation calidad y costo laboral de personas con discapacidad. DO-GCPS-85684-CS-QCBS / (Act. 2.3.2.1) dquisición e Implantación de una solución tipo IVR para Component 2. enviar SMS a los Strengthening of the Selección Ejecución Beneficiarios, realizar IBRD / 84790 PROSOLI CCT Program Posterior basada en Open - National 210,120.00 0.00 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2020-06-10 pendiente encuestas de satisfacción, and Support to Targeted calidad y costo como también permitir Households que los ciudadanos puedan consultar el estatus de sus trámites, quejas, reclamos y solicitudes DO-GCPS-78802-CS-QCBS / (Act. 2.3.6.2) Component 2. Implementar un Sistema Strengthening of the Selección de DataWarehouse para Ejecución IBRD / 84790 PROSOLI CCT Program Posterior basada en Open - National 190,100.00 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-04 2019-06-03 2019-07-08 2019-08-12 2020-08-11 manejo de indicadores y pendiente and Support to Targeted calidad y costo cuadro de mando integral Households basado en la plataforma de intercambio de datos interinstitucional DO-GCPS-80902-CS-QCBS Component 3. Enhancing Selección / (Act. 3.2.1.2.4) Ejecución IBRD / 84790 Equity and Results- Posterior basada en Open - National 307,500.00 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-04 2019-06-03 2019-07-08 2019-08-12 2020-08-11 Realizar la Intervención y pendiente orientation calidad y costo Monitoreo de Intervención PSIP-182-SBCC-SC / Component 3. Enhancing Selección (Act.3.4.3.1) Auditoria IBRD / 84790 Equity and Results- Posterior basada en Open - National 32,051.33 0.00 Bajo Revision 2016-01-03 2016-01-24 2016-03-08 2016-04-05 2016-05-05 2016-06-09 2016-07-14 2017-07-14 financiera externa fondos orientation calidad y costo del Proyecto PSIP-183-SCC-SC / (Act. Component 3. Enhancing Selección 3.4.3.2) Agente Verificador Open - Ejecución IBRD / 84790 Equity and Results- Previa basada en 199,971.00 0.00 2016-01-03 2016-01-24 2016-03-08 2016-04-05 2016-05-05 2016-06-09 2016-07-14 2017-07-14 Indpendiente de los fondos International pendiente orientation calidad y costo componente 1.1 del Proyecto DO-GCPS-117424-CS-CQS / (Act. 3.3.2.9.1) Selección Component 3. Enhancing Consultoría para basada en Ejecución IBRD / 84790 Equity and Results- Posterior Open - National 55,000.00 0.00 2019-05-31 2019-06-21 2019-08-04 2019-09-03 2019-10-08 2020-04-05 Elaboración del Diseño calificaciones de pendiente orientation Curricular para Clases de consultores Competencia comunicativas de Español a Inmigrantes DO-GCPS-117426-CS-CQS / (Act. 3.3.2.9.2) Selección Component 3. Enhancing Consultoría para la basada en Ejecución IBRD / 84790 Equity and Results- Posterior Open - National 55,000.00 0.00 2019-05-31 2019-06-21 2019-08-04 2019-09-03 2019-10-08 2020-04-05 Implementación de Clases calificaciones de pendiente orientation de Competencias consultores Comunicativas de Español a Inmigrantes DO-GCPS-77504-CS-QCBS Component 2. / (Act. 2.1.3.4) Consultoría Strengthening of the Selección para la Revisión de los Open - IBRD / 84790 PROSOLI CCT Program Posterior basada en 35,204.96 0.00 Cancelado 2018-09-28 2018-10-19 2018-12-02 2018-12-30 2019-01-29 2019-03-05 2019-04-09 2020-04-08 procesos transversales y International and Support to Targeted calidad y costo descentralizados de Households PROSOLI DO-GCPS-122267-CS- QCBS / (Act. 3.2.1.3.3) Component 3. Enhancing Selección Ejecución Realizar la Intervención y IBRD / 84790 Equity and Results- Posterior basada en Open - National 241,000.00 0.00 2019-07-31 2019-08-21 2019-10-04 2019-11-01 2019-12-01 2020-01-05 2020-02-09 2021-02-08 pendiente Monitoreo de Intervención orientation calidad y costo Subcomponente 1.3 (Capacitación) Page 6 DO-GCPS-80931-CS-QCBS Component 3. Enhancing Selección / (Act. 3.2.2.3.3) Ejecución IBRD / 84790 Equity and Results- Posterior basada en Open - National 130,000.00 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-04 2019-06-03 2019-07-08 2019-08-12 2020-08-11 Desarrollo de la pendiente orientation calidad y costo Plataforma Informática del SIME DO-GCPS-78799-CS-QCBS / (Act. 2.3.5.3) Component 2. Implantación de un Strengthening of the Selección Sistema de administración Ejecución IBRD / 84790 PROSOLI CCT Program Previa basada en Open - National 586,230.00 0.00 2019-08-22 2019-09-12 2019-10-26 2019-11-23 2019-12-23 2020-01-27 2020-03-02 2021-03-02 de data interinstitucional pendiente and Support to Targeted calidad y costo (SIUBEN, ADESS, Households SENASA, TSS, Prosoli, INFOTEP, MINERD,MSP, MM, DT) INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PIPPS-125-2017 / Component 1. Integrated Recontratacion directa del Area-Based Social Selección directa Personal de la Unidad IBRD / 84790 Previa Direct 0.00 49,734.34 Firmado Protection and Pro-poor de consultores Tecnica del Proyecto Service Delivery (UTP) - Gavino Severino Berroa Component 1. Integrated PIPPS-083-2016 / Area-Based Social Selección directa Recontratacion de IBRD / 84790 Previa Direct 0.00 2,977.13 Cancelado Protection and Pro-poor de consultores Digitadores Service Delivery Component 1. Integrated PIPPS-061-2016 / Area-Based Social Selección directa Recontratacion de Personal IBRD / 84790 Previa Direct 0.00 158,693.42 Firmado Protection and Pro-poor de consultores de la UTP Service Delivery PIPPS-694-2017 / Contratacion directa y Component 3. Enhancing Selección directa recontratacion del personal IBRD / 84790 Equity and Results- Previa Direct 145,659.45 189,769.00 Firmado de consultores de la Unidad Tecnica del orientation Proyecto UTP DO-GCPS-77451-CS-INDV / (Act. 1.3.2.1.5) Consultoría Individual Component 1. Integrated para Adecuación de Area-Based Social Ejecución Cursos de Capacitación de IBRD / 84790 Posterior Individual Open 40,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Protection and Pro-poor pendiente acuerdo a las familias Service Delivery ocupacionales con mayor demanda de capacitacion (en base al estudio de Demanda Laboral) DO-GCPS-77454-CS-INDV / (Act. 1.3.2.5) Consultoría Component 1. Integrated Individual para Revisión y Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 40,000.46 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Adecuación de la Oferta Protection and Pro-poor pendiente Curricular del INFOTEP Service Delivery para grupos vulnerables DO-GCPS-77458-CS-INDV / (Act. 1.3.2.6.2) Component 1. Integrated Consultoría para la Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 20,210.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Implementación de Protection and Pro-poor pendiente Mejoras al sistema Service Delivery Informático de PROSOLI. Modulo Progresando Unidos DO-GCPS-77485-CS-INDV / (Act. 1.3.3.1) Diagnóstico Component 1. Integrated sobre mejores prácticas Area-Based Social Ejecución internacionales autoempleo IBRD / 84790 Posterior Individual Open 35,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Protection and Pro-poor pendiente para la definición de una Service Delivery estrategia de micro emprendimiento DO-GCPS-78713-CS-INDV / (Act. 1.3.2.6.6.1) Asistente Contable 1 Component 1. Integrated para apoyo a la Dirección Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 20,800.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 de Capacitación de Protection and Pro-poor pendiente PROSOLI para gestión de Service Delivery pagos a jóvenes de los Centros Operativos del Sistema (COS) DO-GCPS-78714-CS-INDV / (Act. 1.3.2.6.6.2) Asistente Contable 2 para Component 1. Integrated apoyo a la Dirección de Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 20,800.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Capacitación de PROSOLI Protection and Pro-poor pendiente para gestión de pagos a Service Delivery jóvenes de los Centros Operativos del Sistema (COS) DO-GCPS-78720-CS-INDV / (Act. 1.3.3.2.4) Apoyo Component 1. Integrated Soporte Técnico para Area-Based Social Ejecución Enlace Operativo de Santo IBRD / 84790 Posterior Individual Open 20,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Protection and Pro-poor pendiente Domingo y el Distrito Service Delivery Nacional para la implementación de proceso de capacitación. DO-GCPS-78766-CS-INDV Component 2. / (Act. 2.2.2.2.1) Apoyo Strengthening of the Técnico para la IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 50,000.00 0.00 En ejecución 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-07-22 digitalización y la and Support to Targeted sistematización de data. Households DO-GCPS-78782-CS-INDV Component 2. / (Act. 2.2.2.2.5)Desarrollo Strengthening of the e Implementación Piloto Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 7,500.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 de Reportes Comunitarios pendiente and Support to Targeted vinculados a Puntos Households Solidarios DO-GCPS-78826-CS-INDV / (Act. 3.2.2.1) Component 3. Enhancing Ejecución Actualización del IBRD / 84790 Equity and Results- Posterior Individual Open 50,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 pendiente inventario de los orientation programas de protección social. DO-GCPS-78828-CS-INDV / (Act. 3.2.2.3.1) Diseño Component 3. Enhancing conceptual de la segunda IBRD / 84790 Equity and Results- Posterior Individual Open 40,000.00 0.00 En ejecución 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 fase del SIME (tablero de orientation control, 9 entidades adscritas) DO-GCPS-78833-CS-INDV Component 3. Enhancing / (Act. 3.3.1.1) Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 40,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Fortalecimiento de la pendiente orientation Institucionalidad social. DO-GCPS-78837-CS-INDV / (Act. 3.3.1.2) Facilitador Component 3. Enhancing Ejecución proceso consulta para la IBRD / 84790 Equity and Results- Posterior Individual Open 40,000.00 0.00 2019-02-08 2019-03-29 2019-04-19 2019-05-24 2019-11-20 pendiente reformas en protección orientation social DO-GCPS-78838-CS-INDV / (Act. 3.3.1.3) Consultores Individuales para el Component 3. Enhancing Ejecución fortalecimiento de la IBRD / 84790 Equity and Results- Posterior Individual Open 50,000.00 0.00 2018-10-29 2018-12-17 2019-01-07 2019-02-11 2019-08-10 pendiente implementacion de la orientation estrategia integral de Protección Social. Page 7 DO-GCPS-78839-CS-INDV / (Act. 3.3.1.4) Diseño e Component 3. Enhancing implementación la Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 25,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 plataforma virtual del pendiente orientation inventario nacional de programas sociales DO-GCPS-78967-CS-INDV / (Act. 3.3.2.6) Asistencia Técnica para formulación Component 3. Enhancing y seguimiento de políticas Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 55,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 para cerrar brechas pendiente orientation sociales, desigualdad de genero e iniquidad de derechos humanos. DO-GCPS-78969-CS-CDS Component 3. Enhancing Selección directa Ejecución / (Act. 3.3.2.7) Taller IBRD / 84790 Equity and Results- Previa Direct 45,000.00 0.00 2018-09-28 2018-10-08 2018-12-12 2019-06-10 de consultores pendiente Sobre Teoría de Cambio orientation DO-GCPS-78974-CS-INDV / (Act. 3.3.4.3) Definición de metodología para Component 3. Enhancing Ejecución identificación y IBRD / 84790 Equity and Results- Posterior Individual Open 50,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente sistematización de buenas orientation practicas en la protección social del país DO-GCPS-78994-CS-INDV / (Act. 3.3.9.5) Component 3. Enhancing Ejecución Contratación de IBRD / 84790 Equity and Results- Posterior Individual Open 31,512.61 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente consultoría para orientation implementación de evaluación (sociólogo) DO-GCPS-78996-CS-INDV / (Act. 3.3.9.6) Component 3. Enhancing Ejecución Contratación de IBRD / 84790 Equity and Results- Posterior Individual Open 31,512.60 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente consultoría para orientation implementación de evaluación (psicólogo) DO-GCPS-80719-CS-INDV Component 1. Integrated / (Act. 1.3.2.6.3) Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 24,700.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 Consultoría para la Protection and Pro-poor pendiente Vinculación Empresarial Service Delivery de PROSOLI DO-GCPS-80928-CS-INDV / (Act. 3.2.3.3.4) Component 3. Enhancing Consultoría Individual De Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 20,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 Apoyo Técnico de pendiente orientation Investigación al Observatorio de Políticas Sociales del GCPS DO-GCPS-81089-CS-INDV / (Act. 3.3.2.2.2) Apoyo al Component 3. Enhancing Ejecución desarrollo de políticas IBRD / 84790 Equity and Results- Posterior Individual Open 20,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente sectoriales de la Agenda orientation de Discapacidad PSIP-8-3CV-CI / (Act. 1.2.1.3) Apoyo a la Coordinacion Tecnica del Component 1. Integrated Proyecto de Mejoramiento Area-Based Social Ejecución de Viviendas (cambio piso IBRD / 84790 Previa Individual Limited 113,092.00 0.00 2016-01-01 2016-01-06 2016-01-27 2016-03-02 2016-08-29 Protection and Pro-poor pendiente tierra por cemento) de los Service Delivery Hogares en Extrema Pobreza en la Republica Dominicana PSIP-3CV-CI / (Act.1.2.1.5) Encargados Component 1. Integrated Regionales de Apoyo a la Area-Based Social IBRD / 84790 Previa Individual Open 248,145.00 0.00 En ejecución 2016-01-06 2016-02-24 2016-03-16 2016-04-20 2016-10-17 Unidad de Infraestructura Protection and Pro-poor Social (6 encargados - Service Delivery todos los lotes -empresas y ONGs PSIP-22-3CV-CI / (Act. Component 1. Integrated 1.3.3.2.1) Apoyo Técnico Area-Based Social Ejecución Administrativo a IBRD / 84790 Previa Individual Open 47,265.00 0.00 2016-03-01 2016-04-19 2016-05-10 2016-06-14 2016-12-11 Protection and Pro-poor pendiente PROSOLI para la Service Delivery implementacion del proceso de capacitacion PSIP-257-3CV-CI / (Act. 2.1.2.1) Actualización del Reglamento de Component 2. Funcionamiento de los Strengthening of the Ejecución Comités Regionales y IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 10,011.00 0.00 2015-12-03 2015-12-08 2015-12-29 2016-02-02 2016-07-31 pendiente Municipales del Prosoli y and Support to Targeted Elaboración del Contenido Households de Manuales de Capacitación para los Comités PSIP-186-3CV-CI / (Act. 2.1.3.2.1) Actualización y elaboración del material Component 2. de apoyo y la guía del Strengthening of the facilitador, para la Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 20,000.00 0.00 2016-02-03 2016-02-08 2016-02-29 2016-04-04 2016-10-01 implementación de la pendiente and Support to Targeted capacitación operativa del Households personal de campo en las provincias del Proyecto Progresando Unidos PSIP-192-3CV-CI / (Act. 2.1.3.2.3.3.4) Contratacion Component 2. de 14 digitadores para el Strengthening of the Ejecución Procesamiento de la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 3,231.00 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 pendiente informacion obtenida de la and Support to Targeted ficha y alimentacion de la Households Base de datos PSIP-292-3CV-CI / (Act. 2.1.3.2.4.2) Consultor Component 2. Individual Senior para Strengthening of the Ejecución Monitoreo y Seguimiento IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 20,000.00 0.00 2017-07-03 2017-07-08 2017-07-29 2017-09-02 2018-03-01 pendiente al proceso de Capacitacion and Support to Targeted Operativa al personal de Households Campo Supervisores PSIP-293-3CV-CI / (Act.2.1.3.2.4.3) Consultor Component 2. Individual Junior para Strengthening of the Ejecución Monitoreo y Seguimiento IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 10,000.00 0.00 2017-08-01 2017-08-06 2017-08-27 2017-10-01 2018-03-30 pendiente al proceso de Capacitacion and Support to Targeted Operativa al personal de Households Campo Supervisores PSIP-040-3CV-CI / (Act. 2.2.1.3.2) Implementacion de plataforma de Component 2. educacion virtual para la Strengthening of the Ejecución capacitacion, seguimiento IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 25,000.00 0.00 2017-09-01 2017-09-06 2017-09-27 2017-11-01 2018-04-30 pendiente y desarrollo de habilidades and Support to Targeted de los representantes de Households servicio al cliente, personal soporte de los Puntos Solidarios PSIP-315-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.1.1.1.5) Pago aplicacion IBRD / 84790 Equity and Results- Posterior Individual Limited 7,865.00 0.00 2016-08-26 2016-08-31 2016-09-21 2016-10-26 2017-04-24 pendiente fichas - Piloto Estudio orientation PSIP-276-3CV-CI / (Act. 3.1.1.2.2.4.1) Consultor Component 3. Enhancing para el diseno del Plan IBRD / 84790 Equity and Results- Posterior Individual Limited 2,974.00 0.00 En ejecución 2017-02-20 2017-02-25 2017-03-18 2017-04-22 2017-10-19 de Medios de la Campana orientation de Comunicaciones ESH2017 Page 8 PSIP-227-3CV-CI / (Act. 3.2.3.1.1) Consultoria individual No.1 para el Component 3. Enhancing Ejecución diseño e implementación IBRD / 84790 Equity and Results- Posterior Individual Limited 29,418.00 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 pendiente del portal WEB del orientation Observatorio de Políticas Sociales PSIP-280-CD-CI / (Act.3.3.2.1) Diseño y Component 3. Enhancing Selección directa Ejecución Elaboración del Manual IBRD / 84790 Equity and Results- Previa Direct 43,250.00 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 de consultores pendiente Operativo para el proyecto orientation Progresando Unidos PSIP-025-CD-SC / (Act. 3.3.4.6.1 ) Asesoria Tecnica para la Component 3. Enhancing Implemntacion y Selección directa Ejecución IBRD / 84790 Equity and Results- Previa Direct 5,400.00 0.00 2018-05-01 2018-05-11 2018-07-15 2019-01-11 Configuracion de Dspace de consultores pendiente orientation como Plataforma Tecnologica para la Creacion del Repositorio Institucional (RI) INTEC PSIP-026-3CV-CI / (Act. 3.3.4.6.2) Consultoria Component 3. Enhancing Individual Nacional de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 4,660.00 0.00 2018-06-30 2018-08-18 2018-09-08 2018-10-13 2019-04-11 Apoyo Informatico para el pendiente orientation DIseño e Implementacion del Repositorio Institucioinal PSIP-027-3CV-CI / (Act. 3.3.5.1.1) Consultoría para Component 3. Enhancing el diseño e inventario Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 8,700.00 0.00 2016-06-01 2016-06-06 2016-06-27 2016-08-01 2017-01-28 inicial del Centro de pendiente orientation Documentación de Políticas Sociales PSIP-002-3CV-CI / (Act. Component 3. Enhancing 3.3.9.4) Contratación de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 38,000.00 0.00 2018-08-28 2018-09-02 2018-09-23 2018-10-28 2019-04-26 consultoría para la pendiente orientation aplicación de la línea base. PSIP-199-CD-CI / Component 3. Enhancing Selección directa Ejecución (Act.3.4.1.3) Especialista IBRD / 84790 Equity and Results- Previa Direct 88,274.00 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 de consultores pendiente Financiero orientation PSIP-201-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.7) Consultor en IBRD / 84790 Equity and Results- Previa Direct 43,274.00 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 de consultores pendiente Tecnologia orientation PSIP-208-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.8) Apoyo Logistico de IBRD / 84790 Equity and Results- Previa Direct 13,332.00 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 de consultores pendiente Oficina/Asistente orientation Financiero PSIP-206-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.13) Analista IBRD / 84790 Equity and Results- Previa Direct 43,271.00 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 de consultores pendiente Financiero orientation PSIP-010-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.18) Oficial de IBRD / 84790 Equity and Results- Previa Direct 27,160.00 0.00 2018-04-01 2018-04-11 2018-06-15 2018-12-12 de consultores pendiente Adquisiciones orientation PSIP-013-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.22) Analista IBRD / 84790 Equity and Results- Previa Direct 19,015.00 0.00 2018-01-01 2018-01-11 2018-03-17 2018-09-13 de consultores pendiente Financiero 2 orientation PSIP-008-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.25) Asesora de IBRD / 84790 Equity and Results- Previa Direct 12,474.00 0.00 2018-03-01 2018-03-11 2018-05-15 2018-11-11 de consultores pendiente Adquisiciones BM orientation DO-GCPS-77448-CS-INDV / (Act. 1.3.2.1.4) Component 1. Integrated Consultoría Individual Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 60,000.00 0.00 2018-09-27 2018-11-15 2018-12-06 2019-01-10 2019-07-09 Internacional para Protection and Pro-poor pendiente Asistencia Técnica al Service Delivery INFOTEP para Estudio de Demanda Laboral DO-GCPS-80896-CS-INDV / (Act. 3.2.1.1) Evaluación Component 3. Enhancing Ejecución de Procesos de las IBRD / 84790 Equity and Results- Posterior Individual Open 11,250.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente Intervenciones de la orientation Estrategia territoral DO-GCPS-80724-CS-INDV / (Act. 1.3.3.2.5) Apoyo Component 1. Integrated Soporte Técnico para Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 15,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 Enlace Operativo en la Protection and Pro-poor pendiente Región Sur para la Service Delivery implementación de proceso de capacitacion PSIP-6-3CV-CI / (Act. Component 1. Integrated 1.2.1.2.1) Supervisores de Area-Based Social obra en apoyo a la a IBRD / 84790 Previa Individual Open 128,142.13 0.00 En ejecución 2017-01-06 2017-02-24 2017-03-17 2017-04-21 2017-10-18 Protection and Pro-poor Unidad de Infr. Social (30 Service Delivery supervisores) DO-GCPS-87196-CS-INDV / (Act. 1.3.2.3) Component 1. Integrated Coordinador Técnico para Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 24,870.92 0.00 2016-06-01 2016-07-20 2016-08-10 2016-09-14 2017-03-13 el Monitoreo y Protection and Pro-poor pendiente Seguimiento de las Service Delivery Actividades de capacitación del Subcomponente PSIP-232-3CV-CI / (Act. 1.3.3.2.2) Apoyo Tec. Component 1. Integrated Operativo a PROSOLI Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 15,821.53 0.00 2016-10-11 2016-11-29 2016-12-20 2017-01-24 2017-07-23 para la imp. Del proceso Protection and Pro-poor pendiente de capacitacion en la Service Delivery Regional Sto Dgo y D.N. PSIP-233-3CV-CI / (Act. 1.3.3.2.3) Apoyo Soporte Component 1. Integrated Técnico para Enlace Area-Based Social Ejecución Operativo en las gerencias IBRD / 84790 Posterior Individual Open 16,420.29 0.00 2016-10-11 2016-11-29 2016-12-20 2017-01-24 2017-07-23 Protection and Pro-poor pendiente del INFOTEP de la Service Delivery Regiion Sur para la implementacion del proceso de capacitacion PSIP- 3CV-CI / (Act. Component 2. 2.1.3.1.4) Consultoria Strengthening of the Individual Coordinadora Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 31,158.69 0.00 2017-10-12 2017-10-17 2017-11-07 2017-12-12 2018-06-10 para el Seguimiento de pendiente and Support to Targeted las Operaciones de Households Progresando Unidos Component 2. PSIP-29-3CV-CI / (Act. Strengthening of the 2.2.1.1.4.11) Consultoria Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 8,215.09 0.00 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Analista de Informacion pendiente and Support to Targeted para Punto Solidario Households PSIP-022-3CV-CI / (Act. 2.2.2.1.1) Consultoria Indvidual para el Apoyo Component 2. técnico a la coordinación Strengthening of the Ejecución de Actividades de la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 19,548.47 0.00 2015-12-23 2015-12-28 2016-01-18 2016-02-22 2016-08-20 pendiente Dirección de Vinculación and Support to Targeted Interinstitucional en el Households marco del Proyecto Progresando Unidos Page 9 PSIP-225-3CV-CI / (Act. 2.2.2.2.4) Diseño Component 2. Conceptual y Desarrollo Strengthening of the Ejecución de la Plataforma IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 13,912.28 0.00 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 pendiente Informática para la and Support to Targeted recopilación, análisis y Households publicación de Reportes Comunitarios Digitales. PSIP-56-3CV-CI / (Act. 2.2.3.1) Apoyo Técnico Administrativo -- (Apoyo Component 2. Técnico y Administrativo Strengthening of the Ejecución en Actividades de IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 15,700.00 0.00 2016-06-01 2016-06-06 2016-06-27 2016-08-01 2017-01-28 pendiente Dirección de Vinculación and Support to Targeted Interinstitucional del Households Prosoli en el marco del Proyecto Progresando Unidos) PSIP-58-3CV-CI / (Act. 2.2.3.3) Contratación Component 2. consultores de Campo Strengthening of the para el apoyo técnico a la Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 17,165.77 0.00 2017-06-07 2017-07-26 2017-08-16 2017-09-20 2018-03-19 implementación de los pendiente and Support to Targeted Reportes Comunitarios, Households Distrito Nacional - Santo Domingo PSIP-030-3CV-CI / (Act. 2.3.1.1.1) consultoria para Component 2. elaboracion de Protocolos, Strengthening of the Ejecución Politicas, Convenios y IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 20,576.40 0.00 2016-04-01 2016-05-20 2016-06-10 2016-07-15 2017-01-11 pendiente Colaboracion and Support to Targeted Interinstitucional que Households regiran la Interoperabilidad Component 2. PSIP-71-3CV-CI / (Act. Strengthening of the 2.3.1.3.3) Contratación de Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 28,263.39 0.00 2016-08-01 2016-08-06 2016-08-27 2016-10-01 2017-03-30 consultor administrador de pendiente and Support to Targeted proyectos. Households Component 2. PSIP-71A-3CV-CI / (Act. Strengthening of the 2.3.1.3.4) Contratación de Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 26,313.93 0.00 2017-12-28 2018-01-02 2018-01-23 2018-02-27 2018-08-26 consultor administrador de pendiente and Support to Targeted proyectos. Households PSIP-035-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.1.1.2.2.5.5) Honorarios IBRD / 84790 Equity and Results- Posterior Individual Limited 276,105.50 0.00 2018-01-10 2018-01-15 2018-02-05 2018-03-12 2018-09-08 pendiente personal revisores orientation PSIP-036-3CV-CI / Component 3. Enhancing (Act.3.1.1.2.2.5.6) Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 1,336.24 0.00 2018-01-10 2018-01-15 2018-02-05 2018-03-12 2018-09-08 Honorarios Personal pendiente orientation Encargado Supervisores PSIP-037-3CV-CI / (Act. Component 3. Enhancing 3.1.1.2.2.5.7) Personal de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 54,239.17 0.00 2018-01-10 2018-01-15 2018-02-05 2018-03-12 2018-09-08 Apoyo Administrativo y pendiente orientation Tecnico del 3ESH PSIP-129-3CV-CI / (Act. 3.2.2.3.4) Consultoria Component 3. Enhancing Individual para la Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 34,494.48 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 Optimización el Sistema pendiente orientation Informático del Módulo Operativo del SIME PSIP-228-3CV-CI / (Act. 3.2.3.1.2) Consultoria individual No.2 para el Component 3. Enhancing diseño gráfico de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 15,383.74 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 elementos contenidos en pendiente orientation actividades del Observatorio de Políticas Sociales, así como manejo de las redes sociales PSIP-230-3CV-CI / (Act.3.2.3.3.1) Consultoría individual No.1 Component 3. Enhancing Cualitativa: nacional para Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 24,007.54 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 la implementación y pendiente orientation funcionamiento del Observatorio de Políticas Sociales. PSIP-229-3CV-CI / (Act.3.2.3.3.2) Consultoría individual No.2 Component 3. Enhancing Cuantitativa: nacional Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 23,573.38 0.00 2016-08-22 2016-10-10 2016-10-31 2016-12-05 2017-06-03 para la implementación y pendiente orientation funcionamiento del Observatorio de Políticas Sociales. PSIP-028-3CV-CI / (Act. 3.3.6.1) Analista Component 3. Enhancing Ejecución documental para IBRD / 84790 Equity and Results- Posterior Individual Limited 10,275.82 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 pendiente implementación del centro orientation de documentación de políticas sociales PSIP-001-3CV-CI / (Act. 3.3.9.13) Creacion de Metodologia e Component 3. Enhancing Instrumentos de Actuacion IBRD / 84790 Equity and Results- Posterior Individual Open 39,659.89 38,907.52 Firmado 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-05-11 de las Acciones de orientation Innovacion Institucional del Programa de Prevencion PSIP-198-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.2) Especialista en IBRD / 84790 Equity and Results- Previa Direct 80,256.30 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 de consultores pendiente Adquisiciones orientation PSIP-207-CD-CI / (Act. Component 3. Enhancing 3.4.1.4) Analista de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 45,959.31 0.00 2017-01-01 2017-01-06 2017-01-27 2017-03-03 2017-08-30 Registro y Reportes del pendiente orientation Proyecto (Contador) PSIP-222-3V-CI / Component 3. Enhancing Ejecución (Act.3.4.1.5) Asistente IBRD / 84790 Equity and Results- Posterior Individual Limited 32,000.00 0.00 2017-01-01 2017-01-06 2017-01-27 2017-03-03 2017-08-30 pendiente Financiero del Proyecto orientation PSIP-235-3V-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.6) Analista IBRD / 84790 Equity and Results- Previa Individual Limited 20,712.65 0.00 2017-01-01 2017-01-06 2017-01-27 2017-03-03 2017-08-30 pendiente Adquisiciones 2 orientation Component 3. Enhancing PSIP-202-CD-CI / (Act. Selección directa Ejecución IBRD / 84790 Equity and Results- Posterior Direct 8,057.00 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 3.4.1.9) Conserje de consultores pendiente orientation PSIP-160-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.10) Asistente IBRD / 84790 Equity and Results- Posterior Individual Limited 24,968.77 0.00 2017-01-01 2017-01-06 2017-01-27 2017-03-03 2017-08-30 pendiente Adquisiciones orientation Component 3. Enhancing PSIP-203-CD-CI / (Act. Selección directa Ejecución IBRD / 84790 Equity and Results- Posterior Direct 6,181.00 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 3.4.1.11) Mensajeria de consultores pendiente orientation Component 3. Enhancing PSIP-306-3CV-CI / (Act. Selección directa Ejecución IBRD / 84790 Equity and Results- Posterior Direct 21,043.00 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 3.4.1.14) Chofer UTP de consultores pendiente orientation Page 10 Component 3. Enhancing PSIP-209-3CV-CI / (Act. Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 96,673.37 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 3.4.1.16) Enlace Operativo pendiente orientation PSIP-011-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.19) Analista de IBRD / 84790 Equity and Results- Posterior Individual Limited 13,268.75 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contratos 1 orientation PSIP-012-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.21) Auxiliar de IBRD / 84790 Equity and Results- Posterior Individual Limited 6,697.70 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Gestion de contratos orientation PSIP-0001-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.1) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,592.72 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 1 orientation PSIP-0002-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.2) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,592.72 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 2 orientation PSIP-003-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.3) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,077.82 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 3 orientation PSIP-004-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.4) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,077.82 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 4 orientation PSIP-005-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.5) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,077.82 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 5 orientation PSIP-006-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.6) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,077.82 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 6 orientation PSIP-007-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.24) Asistente Tecnico IBRD / 84790 Equity and Results- Posterior Individual Open 11,825.55 0.00 2018-03-01 2018-04-19 2018-05-10 2018-06-14 2018-12-11 pendiente (a) Coordinador de Enlace orientation PSIP-0009-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.26) Auxiliar de IBRD / 84790 Equity and Results- Posterior Individual Limited 7,961.25 0.00 2018-01-08 2018-01-13 2018-02-03 2018-03-10 2018-09-06 pendiente Adquisiciones orientation DO-GCPS-77507-CS-INDV Component 2. / (Act. 2.1.4.1) Desarrollo Strengthening of the e Implementación del Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 9,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 sistema de seguimiento de pendiente and Support to Targeted comités Municipales y Households Regionales (desarrollo informático) DO-GCPS-102454-CS-CDS / Contratación del personal de campo (pago Component 3. Enhancing Ejecución de ficha a Entrevistadores IBRD / 84790 Equity and Results- Previa Individual Direct 779,377.20 0.00 2019-02-21 2019-03-03 2019-03-24 2019-04-28 2019-10-25 pendiente y Supervisores) de la orientation continuidad del Levantamiento del 3ESH PSIP-7-3CV-CI / (Act. Component 1. Integrated 1.2.1.2.2) Encargados Area-Based Social Ejecución Regionales de Apoyo a la IBRD / 84790 Posterior Individual Open 36,283.55 0.00 2017-01-06 2017-02-24 2017-03-17 2017-04-21 2017-10-18 Protection and Pro-poor pendiente a Unidad de Infr. Social Service Delivery (6 Encargados Regionales) PSIP-581-3CV-CI / (Act. 2.2.3.3) Contratación Component 2. consultores de Campo Strengthening of the Ejecución para el apoyo tecnico a la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 15,736.00 0.00 2018-01-23 2018-01-28 2018-02-18 2018-03-25 2018-09-21 pendiente implementación de los and Support to Targeted Reportes Comunitarios Households Regional El Valle, Enriquillo PSIP-582-3CV-CI / (Act. 2.2.3.3) Contratación Component 2. consultores de Campo Strengthening of the para el apoyo tecnico a la Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 15,735.00 0.00 2018-02-15 2018-04-05 2018-04-26 2018-05-31 2018-11-27 implementación de los pendiente and Support to Targeted Reportes Comunitarios Households Regional Noroeste, Norcentral PSIP-583-3CV-CI / (Act. 2.2.3.3) Contratación Component 2. consultores de Campo Strengthening of the Ejecución para el apoyo tecnico a la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 16,863.00 0.00 2018-09-10 2018-09-15 2018-10-06 2018-11-10 2019-05-09 pendiente implementación de los and Support to Targeted Reportes Comunitarios Households Regional Este, Valdesia Component 3. Enhancing PSIP-2091-3CV-CI / (Act. Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 47,095.00 0.00 2018-06-01 2018-06-06 2018-06-27 2018-08-01 2019-01-28 3.4.1.16) Enlace Operativo pendiente orientation PSIP-021-3CV-CI / (Act. 3.3.8.1) Component 3. Enhancing Ejecución Consultora/Encargada del IBRD / 84790 Equity and Results- Posterior Individual Direct 23,044.02 0.00 2017-06-07 2017-06-17 2017-07-08 2017-08-12 2018-02-08 pendiente Area de Documentación de orientation PROSOLI PSIP-240-CD-CI / Component 3. Enhancing Selección directa Ejecución (Act.3.4.1.12) Asistente IBRD / 84790 Equity and Results- Posterior Direct 42,406.22 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 de consultores pendiente Administrativo orientation DO-GCPS-80704-CS-QCBS Component 1. Integrated / (Act. 1.2.2.2) Area-Based Social Ejecución Supervisión de la IBRD / 84790 Posterior Individual Open 50,198.01 0.00 2019-02-03 2019-03-24 2019-04-14 2019-05-19 2019-11-15 Protection and Pro-poor pendiente rehabilitación de Service Delivery viviendas, cambio de piso de tierra por cemento PSIP-1601-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.10) Asistente IBRD / 84790 Equity and Results- Posterior Individual Limited 16,900.00 0.00 2018-05-14 2018-05-19 2018-06-09 2018-07-14 2019-01-10 pendiente Adquisiciones orientation PSIP-2071-3CV-CI / (Act. Component 3. Enhancing 3.4.1.4) Analista de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 32,772.00 0.00 2018-03-12 2018-03-17 2018-04-07 2018-05-12 2018-11-08 Registro y Reportes del pendiente orientation Proyecto (Contador) PSIP-1981-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.2) Especialista en IBRD / 84790 Equity and Results- Posterior Individual Limited 39,303.00 0.00 2018-04-16 2018-04-21 2018-05-12 2018-06-16 2018-12-13 pendiente Adquisiciones orientation DO-GCPS-78985-CS-INDV / (Act. 3.3.6.2) Gestor de Proyectos Sociales. Component 3. Enhancing Ejecución Asistencias técnicas a ser IBRD / 84790 Equity and Results- Posterior Individual Open 20,800.00 0.00 2018-11-21 2019-01-09 2019-01-30 2019-03-06 2019-09-02 pendiente identificadas para la orientation innovación y creación de nuevas políticas publicas. PSIP-0221-3CV-CI / (Act. 2.2.2.1.1) Consultoria Indvidual para el Apoyo Component 2. técnico a la coordinación Strengthening of the Ejecución de Actividades de la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 22,728.00 0.00 2018-10-23 2018-10-28 2018-11-18 2018-12-23 2019-06-21 pendiente Dirección de Vinculación and Support to Targeted Interinstitucional en el Households marco del Proyecto Progresando Unidos Page 11 PSIP-2281-3CV-CI / (Act. 3.2.3.1.2) Consultoria individual No.2 para el Component 3. Enhancing diseño gráfico de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 30,428.00 0.00 2017-07-24 2017-07-29 2017-08-19 2017-09-23 2018-03-22 elementos contenidos en pendiente orientation actividades del Observatorio de Políticas Sociales, así como manejo de las redes sociales DO-GCPS-789851-CS- INDV / (Act. 3.3.6.2) Especialista para el Analisis y Formulacion de Component 3. Enhancing Ejecución Politicas Publicas en el IBRD / 84790 Equity and Results- Posterior Individual Open 28,600.00 0.00 2018-11-21 2019-01-09 2019-01-30 2019-03-06 2019-09-02 pendiente Sector Social. Asistencias orientation técnicas a ser identificadas para la innovación y creación de nuevas políticas publicas. DO-GCPS-104161-CS- INDV / (Act. 3.2.1.3.3.1) Asistente de Investigación Component 3. Enhancing para el Diseño e Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 29,150.00 0.00 2019-03-29 2019-05-02 2019-05-12 2019-06-07 2019-12-04 Implementación de la pendiente orientation Evaluación de Impacto del subcomponente 1.3 (Capacitación) del Proyecto Progresando Unidos DO-GCPS-104165-CS- INDV / (Act. 3.2.1.2.4.1) Asistente de Investigación para el diseño e Component 3. Enhancing Ejecución implementación de la IBRD / 84790 Equity and Results- Posterior Individual Open 29,150.00 0.00 2019-03-29 2019-05-02 2019-05-12 2019-06-07 2019-12-04 pendiente Evaluación de Impacto al orientation Subcomponente 1.2 (Mejora de Vivienda) del proyecto Progresando Unidos. DO-GCPS-104167-CS- Component 2. INDV / (Act. 2.2.1.3.2) Strengthening of the Ejecución Consultoría Ampliación del IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 12,052.16 0.00 2019-03-29 2019-05-02 2019-05-12 2019-06-07 2019-12-04 pendiente Alcance de la Plataforma and Support to Targeted de Educación Virtual. Households PSIP-13114-3CV-CI / (Act. 1.3.1.1.4) Apoyo Component 1. Integrated Técnico Operativo a Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 15,833.00 0.00 2019-02-11 2019-03-20 2019-03-30 2019-04-25 2019-10-22 PROSOLI para la Protection and Pro-poor pendiente implementación del Service Delivery proceso de Capacitación en la Regional Norcentral. PSIP-13115-3CV-CI / (Act. 1.3.1.1.5) Apoyo Component 1. Integrated Técnico Operativo a Area-Based Social Ejecución PROSOLI para la IBRD / 84790 Posterior Individual Open 15,833.00 0.00 2019-02-11 2019-03-20 2019-03-30 2019-04-25 2019-10-22 Protection and Pro-poor pendiente implementación del Service Delivery proceso de Capacitación en la Regional Distrito Nacional. PSIP-13116-3CV-CI / (Act.1.3.1.1.6) Apoyo Component 1. Integrated Técnico Operativo a Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 15,833.00 0.00 2019-02-11 2019-03-20 2019-03-30 2019-04-25 2019-10-22 PROSOLI para la Protection and Pro-poor pendiente implementación del Service Delivery proceso de Capacitación en la Regional Enriquillo. DO-GCPS-104832-CS- Component 2. INDV / (Act. 2.1.3.6.2) Strengthening of the Consultorías para Apoyo Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 10,000.00 0.00 2019-03-31 2019-04-14 2019-04-29 2019-05-25 2019-11-21 Técnico de Seguimiento a pendiente and Support to Targeted la Implementación del Households Cambio de Comportamiento DO-GCPS-104849-CS- Component 3. Enhancing INDV / (Act. IBRD / 84790 Equity and Results- Posterior Individual Limited 4,950.00 0.00 En ejecución 2019-03-31 2019-04-05 2019-04-26 2019-05-31 2019-11-27 3.2.1.2.4.3.3)contratación orientation de Chofer DO-GCPS-104851-CS- INDV / (Act. 3.2.1.3.3.2) Analista Junior para Component 3. Enhancing Ejecución Gestión de la Evaluación IBRD / 84790 Equity and Results- Posterior Individual Open 20,900.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 pendiente del impacto del Sub- orientation componente 1.3 (Capacitación) del Proyecto Progresando Unidos. DO-GCPS-104853-CS- INDV / (Act. 3.2.2.4.1) Component 3. Enhancing Ejecución Consultoría de apoyo y IBRD / 84790 Equity and Results- Posterior Individual Open 24,750.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 pendiente mantenimiento a la orientation plataforma informática del SIME DO-GCPS-104854-CS- Component 3. Enhancing INDV / (Act. 3.2.2.4.2) IBRD / 84790 Equity and Results- Posterior Individual Open 24,750.00 0.00 En ejecución 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 Analista de Monitoreo orientation DO-GCPS-104855-CS- Component 3. Enhancing INDV / (Act. 3.2.2.4.3) IBRD / 84790 Equity and Results- Posterior Individual Open 22,000.00 0.00 En ejecución 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 Gestora Administrativa de orientation Proyectos Sociales DO-GCPS-104880-CS- Component 3. Enhancing INDV / (Act.3.2.5.1) Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 27,500.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 Consultoría para pendiente orientation elaboración de Manual Operativo DO-GCPS-104882-CS- Component 3. Enhancing INDV / (Act. 3.2.5.2) Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 22,000.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 Consultoría para pendiente orientation elaboración de Agenda Anual de Evaluación DO-GCPS-104883-CS- INDV / (Act. 3.2.5.3) Component 3. Enhancing Ejecución Consultoría de IBRD / 84790 Equity and Results- Posterior Individual Open 20,900.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 pendiente acompañamiento técnico y orientation gestión del Laboratorio de Evidencias DO-GCPS-104900-CS- INDV / (Act. 3.3.6.3) Consultoria Individual de Component 3. Enhancing Ejecución Auxiliar Documental para IBRD / 84790 Equity and Results- Posterior Individual Limited 7,850.00 0.00 2019-03-08 2019-03-13 2019-04-03 2019-05-08 2019-11-04 pendiente el Centro de orientation Documentacion y Repositorio Institucional del GCPS DO-GCPS-105012-CS- INDV / (Act. 3.3.14) Component 3. Enhancing Ejecución Consultoría Seguimiento a IBRD / 84790 Equity and Results- Posterior Individual Open 7,000.00 0.00 2019-04-30 2019-06-03 2019-06-13 2019-07-09 2020-01-05 pendiente la Capacitación Cambio de orientation Comportamiento Senior DO-GCPS-105013-CS- INDV / (Act. 3.3.15) Component 3. Enhancing Ejecución Consultorias Seguimiento IBRD / 84790 Equity and Results- Posterior Individual Open 3,205.00 0.00 2019-04-30 2019-06-03 2019-06-13 2019-07-09 2020-01-05 pendiente a la Capacitación Cambio orientation de Comportamiento Junior. DO-GCPS-105387-CS-CDS Component 2. / (Act. 2.2.1.1.10) Strengthening of the Selección directa Ejecución Realización e Encuestas IBRD / 84790 PROSOLI CCT Program Posterior Direct 4,900.00 0.00 2019-03-11 2019-03-19 2019-04-14 2019-05-14 de consultores pendiente de Satisfacción de los and Support to Targeted Servicios de Punto Households Solidario. Page 12 DO-GCPS-109644-CS-CDS / (Act. 3.2.2.3.3.1) Consultoría Individual Component 3. Enhancing para Acompañar el Selección directa IBRD / 84790 Equity and Results- Posterior Direct 45,000.00 0.00 En ejecución 2019-04-30 2019-05-10 2019-07-14 2020-01-10 Proceso de Implementación de consultores orientation da la 2da. fase del Sistema Integrado de Monitoreo y Evaluación (SIME)". DO-GCPS-116966-CS- INDV / (Act. 2.1.3.7) Consultoría Individual Component 2. Coordinador Operativo Strengthening of the Ejecución para el Enlace de las IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 30,000.00 0.00 2019-05-31 2019-06-05 2019-06-26 2019-07-31 2020-01-27 pendiente operaciones del Proyecto and Support to Targeted Progresando Unidos, Households Provincias Independencia, Barahona, Pedernales y Bahoruco. DO-GCPS-117428-CS- INDV / (Act. 3.3.2.9.3) Component 3. Enhancing Consultoría Individual de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 30,000.00 0.00 2019-05-31 2019-07-19 2019-08-09 2019-09-13 2020-03-11 Monitoreo y Evaluación de pendiente orientation las Clases de Competencia Comunicativa de Español a Inmigrantes DO-GCPS-118056-CS- INDV / (Act. 3.3.2.4.1) Analista para la Component 3. Enhancing Coordinación, monitoreo y IBRD / 84790 Equity and Results- Posterior Individual Open 25,000.00 0.00 En ejecución 2019-07-31 2019-09-18 2019-10-09 2019-11-13 2020-05-11 seguimiento a la orientation implementación del Plan de Reducción de Embarazos en adolescentes. DO-GCPS-119438-CS- INDV / (Act. 2.1.2.2.1) Consultoría para Diseño, Component 2. Revisión y Diagramación Strengthening of the de Manuales para la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 18,000.00 0.00 En ejecución 2019-07-01 2019-07-06 2019-07-27 2019-08-31 2020-02-27 creación de los comités y and Support to Targeted capacitación de la Households estrategia Progresando Unidos y del Funcionamiento de los Comités. DO-GCPS-104843-CS- INDV / (Act. 3.2.1.2.4.2) Analista Junior para Component 3. Enhancing Ejecución Gestión de la Evaluación IBRD / 84790 Equity and Results- Posterior Individual Open 17,100.00 0.00 2019-07-31 2019-09-03 2019-09-13 2019-10-09 2020-04-06 pendiente del Impacto al Sub- orientation Componete 1.2 (Mejora de Vivienda) del Proyecto Progresando Unidos DO-GCPS-121826-CS- INDV / (Act. 3.2.1.2.4.3.5) Monitores Locales para la Component 3. Enhancing Evaluación de impacto del IBRD / 84790 Equity and Results- Posterior Individual Limited 20,900.00 0.00 En ejecución 2019-07-31 2019-08-05 2019-08-26 2019-09-30 2020-03-28 Subcomponente de Mejora orientation de Vivienda del Proyecto Progresando Unidos DO-GCPS-121835-CS- INDV / (Act. 2.2.3.3) Consultoría de Campo Component 2. para el Apoyo Técnico y Strengthening of the Operativo a la Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 16,800.00 0.00 2019-07-31 2019-09-18 2019-10-09 2019-11-13 2020-05-11 Implementación de los pendiente and Support to Targeted Reportes Comunitarios en Households el PROSOLI, Regionales Noroeste y Norcentral (Provincias Santiago y Monte cristi) DO-GCPS-77490-CS-INDV Component 2. / (Act. 2.1.3.1.1) Strengthening of the Consultoría individual de Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 53,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 un Coordinador Operativo pendiente and Support to Targeted para el enlace de las Households operaciones de Progresando Unido DO-GCPS-78768-CS-INDV Component 2. / (Act. 2.2.2.2.2) Analista Strengthening of the Ejecución para aplicación de Minería IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 12,382.56 0.00 2019-07-31 2019-09-18 2019-10-09 2019-11-13 2020-05-11 pendiente de Datos y Comunicación and Support to Targeted Social de Reportes Households Comunitarios DO-GCPS-77488-CS-INDV Component 2. / (Act. 2.1.1.1) Diseño del Strengthening of the instrumento del Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 14,782.44 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 levantamiento de la oferta pendiente and Support to Targeted de servicios y compilación Households de la información. DO-GCPS-80911-CS-INDV / (Act. 3.2.1.3.3) Levantamiento de Linea Component 3. Enhancing de Base para la IBRD / 84790 Equity and Results- Posterior Individual Open 100,000.00 0.00 Cancelado 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 Evaluación del impacto de orientation la estrategia territorial integral del proyecto. DO-GCPS-128164-CS- Component 1. Integrated INDV / (Act. 1.2.2.2) Lote Area-Based Social Ejecución 31, Fase IV "Supervisión IBRD / 84790 Posterior Individual Open 12,996.69 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 Protection and Pro-poor pendiente de pisos de tierra por Service Delivery pisos de cemento", Provincia: Azua DO-GCPS-128165-CS- INDV / (Act. 1.2.2.2) Lote Component 1. Integrated 32, Fase IV "Supervisión Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 12,880.45 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 de pisos de tierra por Protection and Pro-poor pendiente pisos de cemento", Service Delivery Provincia: San Juan de la Maguana DO-GCPS-128167-CS- INDV / (Act. 1.2.2.2) Lote Component 1. Integrated 33, Fase IV "Supervisión Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 13,623.15 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 de pisos de tierra por Protection and Pro-poor pendiente pisos de cemento", Service Delivery Provincia: Elias piña DO-GCPS-128168-CS- INDV / (Act. 3.2.3.6.1) CI- Acompañamiento técnico Component 3. Enhancing en la actualización del IBRD / 84790 Equity and Results- Posterior Individual Open 20,000.00 0.00 En ejecución 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 Plan Estratégico Sectorial orientation para la Inclusión Social y Económica (PEISE) DO-GCPS-78789-CS-INDV / (Act. 2.2.3.11) Consultoría Individual para Sistematización del Component 2. proceso de Strengthening of the Institucionalización de los IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 17,000.00 0.00 En ejecución 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Reportes Comunitarios en and Support to Targeted el PROSOLI y Households contribución de los Planes de Acción a la mejora de los servicios sociales básicos que reciben los hogares". DO-GCPS-133696-CS-CDS / Contratación Directa del Component 3. Enhancing Selección directa Ejecución Personal para la IBRD / 84790 Equity and Results- Previa Direct 16,713.00 0.00 2019-09-30 2019-10-10 2019-12-14 2020-06-11 de consultores pendiente Evaluación de Impacto orientation Linea de Base del sucomponente 1.2 Page 13 DO-GCPS-134186-CS- INDV / (Act. 3.3.6.2.1) Component 3. Enhancing Consultoría Individual IBRD / 84790 Equity and Results- Posterior Individual Open 15,000.00 0.00 En ejecución 2019-09-30 2019-11-18 2019-12-09 2020-01-13 2020-07-11 Analista Gestor /a orientation Administrativo de Proyectos Sociales DO-GCPS-134188-CS- INDV / (Act. 3.3.2.8.1) Consultoría Individual Component 3. Enhancing para la Elaboración del IBRD / 84790 Equity and Results- Posterior Individual Open 25,000.00 0.00 En ejecución 2019-09-30 2019-11-18 2019-12-09 2020-01-13 2020-07-11 Perfil psicosocial de orientation hogares e incidencia de la violencia de Género DO-GCPS-134507-CS- INDV / (Act. 3.3.2.4.2) Consultoría Individual Component 3. Enhancing Asistencia Técnica para IBRD / 84790 Equity and Results- Posterior Individual Open 26,218.10 0.00 En ejecución 2019-09-30 2019-11-18 2019-12-09 2020-01-13 2020-07-11 Monitoreo, seguimiento y orientation evaluación de la política de Reducción de Embarazo en Adolescentes y Desigualdad de Género". DO-GCPS-136071-CS- Component 2. INDV / (Act. 2.3.1.2.2) Strengthening of the Consultoría Individual IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 21,000.00 0.00 En ejecución 2019-09-30 2019-11-18 2019-12-09 2020-01-13 2020-07-11 analista de Sistema de and Support to Targeted Plataforma WEB de Punto Households Solidario DO-GCPS-136069-CS- INDV / (Act. 2.3.8.1) Component 2. Consultoría Individual Strengthening of the Desarrollador para IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 40,000.00 0.00 En ejecución 2019-09-30 2019-11-18 2019-12-09 2020-01-13 2020-07-11 aplicaciones WEB y and Support to Targeted Móviles requeridas en el Households Sistema de Información Progresando con Solidaridad (SIPS) DO-GCPS-136072-CS- Component 3. Enhancing INDV / (Act. 3.1.1.2.7) IBRD / 84790 Equity and Results- Posterior Individual Open 10,000.00 0.00 En ejecución 2019-09-30 2019-11-18 2019-12-09 2020-01-13 2020-07-11 Consultoría Individual orientation para Base de Datos DO-GCPS-139676-CS- INDV / (Act. 2.2.2.2.4) Component 2. Diseño Conceptual y Strengthening of the Desarrollo de la IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 12,000.00 0.00 En ejecución 2019-10-21 2019-11-16 2019-12-07 2020-01-11 2020-07-09 Plataforma Informática and Support to Targeted para la Gestión del Households Proceso de Reportes Comunitarios (RC) DO-GCPS-141388-CS-CDS / (Act. 3.4.3.1) Auditoria Externa del Proyecto, Component 3. Enhancing Selección directa Periodo del 1ro. de enero IBRD / 84790 Equity and Results- Posterior Direct 38,700.00 0.00 En ejecución 2019-10-21 2019-10-28 2019-11-21 2020-12-31 de consultores al 31 de diciembre 2019 orientation y del 1ro. de Enero al 30 de septiembre 2020. DO-GCPS-141403-CS- Component 2. INDV / (Act. 2.3.8.3) Strengthening of the Asistencia Técnica para IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 21,000.00 0.00 En ejecución 2019-10-21 2019-12-09 2019-12-30 2020-02-03 2020-08-01 Desarrollo de aplicaciones and Support to Targeted Móviles Households DO-GCPS-141405-CS- Component 2. INDV / (Act. 2.3.8.4) Strengthening of the Asistencia Técnica para IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 21,000.00 0.00 En ejecución 2019-10-21 2019-12-09 2019-12-30 2020-02-03 2020-08-01 Desarrollo de Aplicaciones and Support to Targeted WEB Households Component 2. DO-GCPS-141406-CS- Strengthening of the INDV / (Act. 2.3.8.5) IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 20,000.00 0.00 En ejecución 2019-10-21 2019-12-09 2019-12-30 2020-02-03 2020-08-01 Gestor de Proyectos TIC. and Support to Targeted Households DO-GCPS-145733-CS- Component 2. INDV / (Act. 2.2.1.5.2) Strengthening of the Ejecución Consultoría Individual IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 18,000.00 0.00 2019-11-29 2019-12-04 2019-12-11 2019-12-28 2020-06-25 pendiente Analista de Proyectos de and Support to Targeted Punto Solidario Households DO-GCPS-145734-CS- Component 2. INDV / (Act. 2.2.1.5.3) Strengthening of the Ejecución Consultoría Individual IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 25,000.00 0.00 2019-11-29 2019-12-04 2019-12-08 2020-01-03 2020-07-01 pendiente Ofial de Atención and Support to Targeted Ciudadano /a de Punto Households Solidario DO-GCPS-145731-CS-CDS / Contratación del personal de campo (pago Component 3. Enhancing Selección directa Ejecución de ficha a Entrevistadores IBRD / 84790 Equity and Results- Posterior Direct 33,292.00 0.00 2019-11-29 2019-12-09 2020-01-23 2020-07-21 de consultores pendiente y Supervisores) para el orientation Levantamiento de Reportes Comunitarios Page 14