92174 Procurement Plan Annex: (i) to the Semiannual Procurement Progress Report Latest Clearance by Bank on 05 August 2014 Country: WEST BANK AND GAZA Project: Water Sector Capacity Building to PWA P117443 Category: Goods Schedule Stat. Proc WB NO. Component Description No. of Method Rev Prep. of WB Issue of Bids Evaluation WB Contract Contract Start Comple. Source of Finance Comments Reference submission/ Lots/ packages Prior/ Bidding NO Bidding Openning Report NO Award Sig. Date Date Post Docs Docs Furniture P Prior 13-Feb-11 20-Feb-11 21-Feb-11 9-Mar-11 15-Mar-11 22-Mar-11 25-Mar-11 1-Apr-11 1-Apr-11 G1 3 1 R S IDA A 10-May-11 5-Jun-11 20-Jun-11 28-Jun-11 30-Jun-11 1-Jul-11 15-Jul-11 11-Sep-11 P 13-Feb-11 20-Feb-11 21-Feb-11 9-Mar-11 15-Mar-11 22-Mar-11 25-Mar-11 1-Apr-11 1-Apr-11 Tender was canceled because R some error in specifications / was retenderred G2 3 Office equipment 1 S Prior A Complete, Supplier (Al Bidawi Information 5-Sep-11 10-Sep-11 14-Sep-11 27-Sep-11 4-Oct-11 10-Oct-11 11-Oct-11 11-Oct-11 20-Nov-11 6-Dec-11 IDA Systems, Ramallah) Printing brochures and Awareness P Post 23-Jan-12 30-Jan-12 6-Feb-12 21-Feb-12 N.A 6-Mar-12 8-Mar-12 8-Mar-12 Materials R1 1-Jul-13 NA 8-Jul-13 22-Jul-13 29-Jul-13 NA 5-Aug-13 12-Aug-13 17-Aug-13 30-Sep-13 G3 3 S IDA R2 15-Dec-14 NA 22-Dec-14 5-Jan-15 19-Jan-15 NA 26-Jan-15 29-Jan-15 31-Jan-15 17-Mar-15 A P 19-Jan-12 26-Jan-12 2-Feb-12 25-Feb-12 10-Mar-12 17-Mar-12 20-Mar-12 22-Mar-12 20-Mar-12 Complete, G4 3 Office Equipment Gaza 1 R S Post NA 2-Apr-12 NA 6-May-12 IDA Supplier (Future Information A 20-Mar-12 NA 20-Mar-12 29-Mar-12 9-Apr-12 NA 9-Apr-12 11-Apr-12 11-Apr-12 17-Apr-12 Systems) P 15-Feb-12 22-Feb-12 28-Feb-12 26-Mar-12 15-Apr-12 22-Apr-12 25-Apr-12 27-Apr-12 28-Apr-12 Complete, Surface Software / The Watershed Modeling System (WMS v 8.4), R 20-Mar-13 NA 27-Mar-13 7-Apr-13 14-Apr-13 NA 21-Apr-13 30-May-13 5-Jun-13 31-Jul-13 Hydro-Engineering for A Environmental and Informations G5 2 Groundwater Quality Monitoring 1 S Post IDA System, Aquifer test software, Updated Consultancy (HEC), Ramallah 11-Mar-13 NA 13-Mar-13 28-Mar-13 17-Apr-13 NA 22-May-13 22-May-13 22-May-13 15-Sep-13 version of GMS (v 8.1) P 15-Oct-12 NA 22-Oct-12 5-Nov-12 12-Nov-12 NA 19-Nov-12 22-Nov-12 23-Nov-12 23-Dec-12 Complete, R Supplier (ORJWAN Copnay for G6 3 Printing annual progress report of 2012 1 A S Post IDA Design and Printing, Ramallah) 5-Nov-12 NA 6-Nov-12 25-Nov-12 27-Nov-12 NA 19-Dec-12 19-Dec-12 20-Dec-12 29-Jan-13 P 20-Mar-13 NA 27-Mar-13 7-Apr-13 14-Apr-13 NA 21-Apr-13 30-May-13 5-Jun-13 31-Jul-13 Due to the political situation, R1 1-Dec-13 NA 27-Dec-13 9-Jan-14 17-Jan-14 NA 21/1/2014 28-Jan-14 30-Jan-14 2-Mar-14 procurment is postponed IT Equipment -PWA Gaza Office R2 15-Dec-14 NA 22-Dec-14 5-Jan-15 19-Jan-15 NA 26-Jan-15 29-Jan-15 31-Jan-15 17-Mar-15 G7 3 1 S Post IDA (12 computers & 1 fax) A P 20-Mar-13 NA 27-Mar-13 7-Apr-13 14-Apr-13 NA 21-Apr-13 30-May-13 5-Jun-13 31-Jul-13 Due to the political situation, R1 1-Dec-13 NA 27-Dec-13 9-Jan-14 17-Jan-14 NA 21/1/2014 28-Jan-14 30-Jan-14 2-Mar-14 procurment is postponed Furniture-PWA Gaza Office R2 15-Dec-14 NA 22-Dec-14 5-Jan-15 19-Jan-15 NA 26-Jan-15 29-Jan-15 31-Jan-15 17-Mar-15 G8 3 1 S Post IDA (12 desks & 12 chairs) A Software and leterature on business P 20-Mar-13 NA 27-Mar-13 7-Apr-13 14-Apr-13 NA 21-Apr-13 30-May-13 5-Jun-13 31-Jul-13 Complete, planning; and R Exalt Information & Technical solutions (software and Communication Technologies, A G9 2 internet) to improve internal 2 S Post IDA Ramallah communications; and to facilitate 23-Jun-13 NA 28-Jun-13 11-Jul-13 16-Jul-13 NA 22-Jul-13 22-Jul-13 30-Sep-13 contact between ministerial and regulatory units in Gaza and West P 10-Sep-13 NA 17-Sep-13 30-Sep-13 7-Oct-13 NA 14-Oct-13 21-Oct-13 28-Oct-13 30-Apr-14 Completed, Software for new electronic system for R Gardenia Company for Marketing G10 2 PWA library and on job training and 1 A S Post IDA & Advertising Services, Ramallah capacity building for librarians 5-Sep-13 NA 5-Sep-13 19-Sep-13 26-Sep-13 NA 6-Oct-13 7-Oct-13 7-Oct-13 31-May-14 P 10-Sep-13 NA 17-Sep-13 30-Sep-13 7-Oct-13 NA 14-Oct-13 21-Oct-13 28-Oct-13 30-Apr-14 Complete, Supply and install, Communication/ R BCI, Ramallah G11 2 video conference system and one 1 A S Post SIDA laptop for PIU 9-Oct-13 NA 10-Oct-13 24-Oct-13 3-Nov-13 NA 11-Nov-13 12-Nov-13 12-Nov-13 3-Apr-14 P 24-Oct-13 NA 27-Oct-13 10-Nov-13 17-Nov-13 NA 24-Nov-13 27-Nov-13 29-Nov-13 29-Dec-13 Complete, Furniture for PWA library in the new R Nieroukh Scales Metallic G12 2 building (Special metalic 1 A S Post SIDA Furniture Co., Hebron sheves and tables for three computers) 26-Oct-13 NA 28-Oct-13 1-Dec-13 5-Dec-13 NA 22-Dec-13 30-Dec-13 30-Dec-13 1-Apr-14 P 20-Aug-14 NA 27-Aug-14 17-Sep-14 15-Oct-14 NA 22-Oct-14 25-Oct-14 27-Oct-14 26-Dec-14 New Procurment of Instruments to the R G13 2 Hydro-Monitoring System (West Bank 1 A S Post SIDA only) Gaza is funded from ICRC Procurement Plan Latest Clearance by Bank on 05 August 2014 Country: WEST BANK AND GAZA Project: Water Sector Capacity Building to PWA P117443 Category: Consulting Services No. Compo Description Schedule nent Stat. Select. WB Refere Method Rev Prep. of WB NO REOI ADV. Sub. Of EOIs Short list WB NO Prep. Of WB NO Issue of Sub. Of Tech. Eval. WB NO Open. of Fin. Proposals Invitation for Neg. Neg./ Draft Contract WB NO Contract Signing Start Completion date Source of Finance Comments nce Prior/ TOR RFP RFP/ Invitations Proposals date Post P 2010 Sep-11 28-Sep-10 11-Oct-10 19-Oct-10 8-Nov-10 19-Oct-10 8-Nov-10 9-Nov-10 22-Dec-10 29-Dec-10 14-Jan-11 17-Jan-11 23-Jan-11 30-Jan-11 14-Feb-11 Mar-11 4-Jan-11 28-Feb-14 Complete, R 2010 Oct-10 28-Sep-10 11-Oct-10 19-Oct-10 6-Dec-10 19-Oct-10 6-Dec-10 13-Dec-10 27-Jan-11 27-Feb-11 10-Mar-11 17-Mar-11 20-Mar-11 31-Mar-11 7-Apr-11 15-Apr-11 1-May-11 30-Apr-14 Consultant (ORGUT Consulting SER1 1 TPAT QCBS Prior IDA, AFD & SIDA AB, Sweden in Association with A 1-Oct-10 9-Oct-10 28-Sep-10 19-Oct-10 15-Nov-10 7-Dec-10 15-Nov-10 7-Dec-10 13-Dec-10 27-Jan-11 26-Apr-11 10-May-11 12-May-11 FCG Finish Consulting Group, Finland) P 8-Feb-11 22-Feb-11 NA NA 5-Mar-11 12-Mar-11 NA NA NA NA NA NA NA NA 1-Apr-11 8-Apr-11 9-Apr-11 9-Apr-11 30-Apr-11 Cancelled, to be covered under Contract Management Training R SER8 "Trainers on key priority SER2 2 IC Prior (Cancelled) A topics for PWA managers and staff" P 17-Nov-11 8-Dec-11 NA NA NA NA 7-Dec-11 14-Dec-11 16-Dec-11 15-Jan-12 29-Jan-12 5-Feb-12 12-Feb-12 NA 19-Feb-12 26-Feb-12 28-Feb-12 6-Mar-12 29-May-12 IDA Complete, Assessment of Acquired Regional Consultant (EcoconServ R 19-Jan-12 5-Feb-12 15-Feb-12 22-Feb-12 22-Feb-12 NA 24-Feb-12 10-Mar-12 24-Feb-12 1-Mar-12 NA 7-Mar-12 10-Mar-12 17-Mar-12 18-Mar-12 18-Mar-12 18-Jun-12 Experience on the Wastewater SER3 2 CQS Prior Environmental Solutions, Eygpt Treatment, Reuse and Sludge Management in assocaition with Universal A 21-Nov-12 17-Jan-12 24-Jan-12 9-Feb-12 9-Apr-12 18-Apr-12 19-Apr-12 NA 10-May-12 27/05/2012 NA NA 27-May-12 29-May-12 9-Jun-12 16-Jun-12 17-Sep-12 18-Sep-12 26-May-13 Group, Nablus ) P 2-Apr-12 10-Apr-12 12-Apr-12 28-Apr-12 11-May-12 19-May-12 19-May-12 26-May-12 28-May-12 7-Jun-12 8-Jun-12 15-Jun-12 15-Aug-12 Complete, Training in Management, Business SER4 2 R CQS Post 20-Mar-12 27-Mar-12 30-Mar-12 15-Apr-12 22-Apr-12 27-Apr-12 28-Apr-12 NA 29-Apr-12 16-May-12 25-May-12 2-Jun-12 16-May-12 23-May-12 25-May-12 2-Jun-12 5-Jun-12 10-Jun-12 10-Aug-12 IDA Consultant (General Consulting Planning A 16-Apr-12 NA 5-Mar-12 22-May-12 NA NA 5-Jun-12 NA 6-Jun-12 19-Jun-12 NA 29/06/2012 8-Jul-12 25/07/2012 1-Aug-02 & Training) P 1-Mar-12 8-Mar-12 10-Mar-12 25-Mar-12 5-Apr-12 12-Apr-12 14-Apr-12 NA 15-Apr-12 2-May-12 12-May-12 19-May-12 2-May-12 22-May-12 30-May-12 7-Jun-12 10-Jun-12 25-Jun-12 1-Jun-13 Cancelled. This assignment is R to be conducted by PMT staff 11-Mar-12 17-May-13 4-Apr-12 23-Apr-13 5-Jun-12 7-Jun-12 NA NA 16-Sep-12 because the Consultant "JV of Transboundary Study SER5 2 CQS Prior CEC and Saaf BV" did not (Cancelled) submit the proposal on the 11-Mar-12 17/05/2013 4-Apr-12 23/04/2013 5-Jun-12 6-Jul-12 NA NA 8-Jul-12 deadlien of submision of A 16/09/2012. P 1-Jun-11 15-Jun-11 20-Jun-11 5-Jul-11 15-Jul-11 25-Jul-11 15-Jul-11 25-Jul-11 1-Aug-11 30-Aug-11 15-Sep-11 20-Sep-11 25-Sep-11 28-Sep-11 28-Sep-11 1-Oct-11 15-Oct-11 1-Nov-11 30-Jun-13 This service managed by the IDA R 27-Nov-11 8-Dec-11 13-Dec-11 20-Dec-11 12-Dec-11 20-Jan-12 29-Jan-12 5-Feb-12 12-Feb-12 19-Feb-12 21-Feb-12 21-Feb-12 30-Jun-13 Ministry of Finance A Complete, SER6 3 External Auditor LCS Prior Consultant (Al Wafa Company 27-Nov-11 17-Jan-12 26-Dec-11 17-Jan-12 26-Jan-12 28-Feb-12 26-Mar-12 29-Mar-12 29-Mar-12 30-Apr-12 30-Apr-12 30-Jun-13 for Financiual & Accounting, Ramallah) P 1-Jun-11 15-Jun-11 20-Jun-11 5-Jul-11 15-Jul-11 25-Jul-11 15-Jul-11 25-Jul-11 1-Aug-11 30-Aug-11 15-Sep-11 20-Sep-11 25-Sep-11 28-Sep-11 22-Sep-11 1-Oct-11 15-Oct-11 1-Nov-11 30-Jun-13 Ongoing, Consultant (JV of EcoConServ R1 23-Dec-11 30-Dec-11 NA NA NA NA 6-Jan-12 13-Jan-12 15-Jan-12 14-Feb-12 28-Feb-12 6-Mar-12 13-Mar-12 NA 20-Mar-12 27-Mar-12 29-Mar-12 5-Apr-12 5-May-12 Environmental Solutions-Eygpt, R2 1-Sep-12 15-Sep-12 22-Sep-12 14-Oct-12 24-Oct-12 5-Nov-12 7-Nov-12 NA 8-Nov-12 23-Dec-12 3-Jan-13 10-Jan-13 3-Jan-13 10-Jan-13 12-Jan-13 19-Jan-13 SER7 3 Mid-term evaluation CQS Post IDA Universal Group & House of A Palestinian Expertise for 13-May-12 24-Jun-12 28-Jun-12 11-Jul-12 9-Aug-12 NA 23-Aug-12 NA 4-Sep-12 30-Sep-12 6-Nov-12 NA 30-Sep-12 11-Nov-12 NA 30-Dec-12 31-Dec-12 Consultancies & Studies , Nablus) P 1-May-13 8-May-13 12-May-13 26-May-13 10-Jun-13 17-Jun-13 23-Jun-13 30-Jun-13 4-Jul-13 4-Aug-13 18-Aug-13 25-Aug-13 29-Aug-13 5-Sep-13 10-Sep-13 17-Sep-13 24-Sep-13 1-Oct-13 30-Mar-14 Cancelled. Per Bank's proposal R 15-Sep-13 22-Sep-13 29-Sep-13 13-Oct-13 27-Oct-13 3-Nov-13 10-Nov-13 17-Nov-13 24-Nov-13 22-Dec-13 5-Jan-14 12-Jan-14 19-Jan-14 26-Jan-14 2-Feb-14 9-Feb-14 16-Feb-14 20-Feb-14 20-Aug-14 Training on key priority topics for on September 10, 2013, this SER8 2 A QCBS Prior SIDA PWA managers and staff assignmenet will be carried out by available training centers according to traning fees. P 3-Mar-13 10-Mar-13 12-Mar-13 26-Mar-13 10-Apr-13 NA NA NA NA NA 17-Apr-13 24-Apr-13 NA 27-Apr-13 30-Apr-13 7-May-13 7-May-13 14-May-13 Was done under the GIZ fund Tariff Training -Communication R and suport to PWA SER9 2 Adviser – implementation workshops IC Prior (Cancelled) A P 15-Oct-13 22-Oct-13 29-Oct-13 13-Nov-13 27-Nov-13 3-Dec-13 10-Dec-13 17-Dec-13 24-Dec-13 22-Jan-14 5-Feb-14 12-Feb-14 19-Feb-14 26-Feb-14 2-Mar-14 9-Mar-14 16-Mar-14 18-Mar-14 18-Sep-14 PWA proposed to fund it from NRW status sustainability and tariff 2 R QCBS Prior the Trust Fund SER10 system implementation road map in SIDA Gaza (Cancelled) A P 15-Sep-13 22-Sep-13 29-Sep-13 13-Oct-13 27-Oct-13 3-Nov-13 10-Nov-13 17-Nov-13 24-Nov-13 22-Dec-13 5-Jan-14 12-Jan-14 19-Jan-14 26-Jan-14 2-Feb-14 9-Feb-14 16-Feb-14 20-Feb-14 31-Dec-15 Ongoing, SER11 3 External Audit for 2013-2014 R QCBS Prior IDA Managed by the MoF. A Auditor: Ernst& Young- Middle 24-Oct-13 2-Nov-13 24-Nov-13 27-Nov-13 3-Dec-13 5-Jan-14 26-Jan-14 30-Jan-14 5-Feb-14 27-Feb-14 27-Feb-14 30-Jun-16 East, Ramallah P 28-Aug-14 4-Sep-14 11-Sep-14 2-Oct-14 23-Oct-14 6-Nov-14 23-Oct-14 6-Nov-14 13-Nov-14 18-Dec-14 15-Jan-15 29-Jan-15 5-Feb-15 19-Feb-15 26-Feb-15 5-Mar-15 12-Mar-15 19-Mar-15 16-Aug-15 SER12 1 PWA Water Information System R QCBS Prior SIDA A NATIONAL LEGAL EXPERT TO P 23-Jul-14 30-Jul-14 6-Aug-14 16-Aug-14 30-Aug-14 6-Sep-14 NA NA NA NA NA NA NA 13-Sep-14 17-Sep-14 24-Sep-14 27-Sep-14 1-Oct-14 1-Oct-15 ASSIST PALESTINIAN WATER R AUTHORITY (PWA) IN THE PLANNING A SER13 2 IC Prior SIDA AND IMPLEMENTATION OF LEGAL ACTIVITIES OF THE REFORM 23-Jul-14 14-Aug-14 18-Aug-14 28-Aug-14 PROGRAM P 25-Aug-14 1-Sep-14 8-Sep-14 22-Sep-14 6-Oct-14 13-Oct-14 NA NA NA NA NA NA NA 20-Oct-14 24-Oct-14 NA 31-Oct-14 4-Nov-14 4-Nov-15 SER14 2 Translater for PWA Website R IC Post 12-Oct-14 NA 19-Oct-14 2-Nov-14 9-Nov-14 NA NA NA NA NA NA NA NA 16-Nov-14 20-Nov-14 NA 27-Nov-14 1-Dec-14 1-Dec-15 SIDA A P 25-Aug-14 1-Sep-14 8-Sep-14 6-Oct-14 3-Nov-14 17-Nov-14 3-Nov-14 17-Nov-14 24-Nov-14 5-Jan-15 2-Feb-15 16-Feb-15 23-Feb-15 9-Mar-15 16-Mar-15 23-Mar-15 30-Mar-15 6-Apr-15 2-Dec-15 SER15 1 TPAT (Phase II) R QCBS Prior SIDA_WB A 22-Sep-14 30-Oct-14 National Experts to Develop P 30-Sep-14 9-Oct-14 12-Oct-14 19-Oct-14 2-Nov-14 16-Nov-14 NA NA NA NA NA NA NA 23-Nov-14 30-Nov-14 7-Dec-14 14-Dec-14 21-Dec-14 21-Mar-15 New Palestinian Water Authority (PWA) R SER16 1 IC Prior SIDA_WB Strategic Plan and Implementation A Plan P 8-Dec-14 15-Dec-14 NA NA NA NA NA NA NA NA NA NA NA 22-Dec-14 29-Dec-14 5-Jan-15 8-Jan-15 15-Jan-15 1-Mar-15 New Upgrading the Existing Software at R SER17 2 SS Prior SIDA_WB PWA Human Resources Department A