The World Bank Second Power Transmission Project (P146788) REPORT NO.: RES33671 RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF SECOND POWER TRANSMISSION PROJECT APPROVED ON DECEMBER 22, 2014 TO UKRAINE ENERGY & EXTRACTIVES GLOBAL PRACTICE EUROPE AND CENTRAL ASIA REGION Regional Vice President: Cyril E Muller Country Director: Satu Kristiina J. Kahkonen Senior Global Practice Director: Riccardo Puliti Practice Manager/Manager: Sameer Shukla Task Team Leader: Dmytro Glazkov, Koji Nishida The World Bank Second Power Transmission Project (P146788) ABBREVIATIONS AND ACRONYMS MoECI Ministry of Energy, Coal and Industry MoF Ministry of Finance PDO Project Development Objective PIU Project Implementation Unit PTP Power Transmission Project SS Substations UE Ukrenergo WEM Wholesale Electricity Market The World Bank Second Power Transmission Project (P146788) BASIC DATA Product Information Project ID Financing Instrument P146788 Investment Project Financing Original EA Category Current EA Category Partial Assessment (B) Partial Assessment (B) Approval Date Current Closing Date 22-Dec-2014 30-Jun-2020 Organizations Borrower Responsible Agency National Power Company Ukrenergo (UE),Ministry of Ministry of Finance Energy and Coal Industry of Ukraine Project Development Objective (PDO) Original PDO To improve the reliability of power transmission system and support implementation of the Wholesale Electricity Market in Ukraine. OPS_TABLE_PDO_CURRENTPDO Summary Status of Financing Net Ln/Cr/Tf Approval Signing Effectiveness Closing Commitment Disbursed Undisbursed IBRD-84620 22-Dec-2014 10-Feb-2015 09-Jun-2015 30-Jun-2020 330.00 29.88 300.12 TF-17661 22-Dec-2014 10-Feb-2015 09-Jun-2015 30-Jun-2020 48.43 .22 48.21 Policy Waiver(s) Does this restructuring trigger the need for any policy waiver(s)? No The World Bank Second Power Transmission Project (P146788) I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING A. Project Status 1. The Second Power Transmission Project (PTP2) was approved on December 24, 2014 and is a follow up of the Power Transmission Project in Support of the Energy Sector Reform and Development Program closed on June 30, 2016. Despite slow progress during the first two years after effectiveness, PTP2 (the Project) has developed a steady pace since the end of 2017. Since most of the progress is related to preparation of procurement packages, the total disbursement for the Project as of April 2019 is low at 8% (US$30 mln) and is expected to increase later in 2019 with the commencement of construction activities for six substations. Ukrenergo (UE) and the Ministry of Economy and Coal Industry (MoECI) expect that the Project Development Objective continues to be achievable. The Project’s progress towards the PDO is rated Moderately Satisfactory. 2. At the time of restructuring, the implementation progress is rated moderately satisfactory with regards to all the Project’s components. Initially, the infrastructure component - Rehabilitation of substations has been progressing slowly due to lengthy review and approvals carried out by the Cabinet of Ministers (CabMin). However, at the end of 2018 the procedural obstacles have been removed. As a result, MoECI has become the final approval agency for technical documents, which will considerably speed up the formal contract approval process once the bidding process is completed. Construction works for two out of six substations - Sumy and Kremenchug have commenced in December 2018. During the mission in October 2018, the Bank requested MoECI to speed up the design approval process for the remaining 4 substations with the goal of completion of the construction activities by the Project’s original Closing Date, June 30, 2020. Works on the non- infrastructure components has also progressed significantly during 2018. A contract for Balancing Market software was signed in July 2018. The bid opening for SCADA/WAMS package took place on January 31, 2019. Other large IT/software tenders were launched in 2018 and contract signatures for those contracts are expected during 2019. 3. The Project financial management has been consistently rated Moderately Satisfactory for the past two years. The Project complies with the fiduciary requirements and there are no overdue audits. B. Rationale for Restructuring 4. As the Project moved further into implementation stage, the tenders carried out in 2018 for rehabilitation of six substations and installation of power compensation devices generated savings in the amount of US$168 million, mainly due to the following factors: (i) high level of competition among twelve to fifteen bidders per tender package; (ii) actual costs turned out to be much lower than the cost estimates developed during project preparation; (iii) reduction of the cost of the Gas Insulated Switchgear substations due to technology advances; and (iv) devaluation of the local currency (UAH) during the implementation period. The World Bank Second Power Transmission Project (P146788) 5. To utilize the savings, UE, MoECI and Ministry of Finance requested the Bank’s approval to utilize US$108 million for financing of rehabilitation of 15 additional substations under Component 1 of the Project. The scope of the additional works would include modernization and automation of substation equipment – the same activities which were envisaged by the initial scope of the Project with regards to the original six substations. The proposed substations are significantly aged with obsolete equipment and require urgent rehabilitation. The modernization and automation will support the country’s strategic plan to synchronize the Ukrainian power system with the European power system, by adopting European requirements for the substation equipment. The MoF has also requested the World Bank to cancel the remaining US$60 million out of US$168 million savings. The Bank agrees with such a request since such cancelation will increase the overall Project’s value for money, improve the overall disbursement performance of the Project and will reduce the amount of the commitment fees currently paid by the Government of Ukraine. 6. The MoF has also requested extension of the Project’s Closing Date from June 30, 2020 to June 30, 2022. The extension would enable completion of rehabilitation of the additional substations as well as support the establishment of a Wholesale Electricity Market (WEM) in Ukraine, which is delayed compared to the original timeline. 7. Furthermore, to allow for a better flexibility and for using different procurement approaches including fit for purpose principle, the MoF has requested that the Project’s legal agreements to be revised as to allow using the single source procurement method for the selection of consultants. The current versions of the legal agreements require the Project team to obtain a waiver each time there is a need to process procurement packages using the method, as the single source procurement is not included in the legal agreements. At the time of the project’s preparation, all procurement packages were to be procured through ICB or QCBS. This rigid approach is no longer applicable in the context of the new procurement framework, which allows for much more flexible procurement approaches and the Borrower is requesting to adjust the Legal agreements to the requirements of the Bank’s new procurement framework. II. DESCRIPTION OF PROPOSED CHANGES 8. The proposed changes are in line with the Project restructuring request of letter from the MoF dated April 1, 2019 and the letter from UE dated April 8, 2019. The restructuring will not affect the project development objective and no change of the safeguard category is planned. 9. The proposed changes are as follows: (a) cancellation of loan funds in the amount of US$60 million; (b) extension of the Closing Date from June 30, 2020 to June 29, 2022; (c) revision of the Project’s results framework to reflect the addition of 15 substations to the project’s scope of activities and extension of the Closing Date, namely, the following amendments in the PDO indicators and the Intermediate Results Indicators: The World Bank Second Power Transmission Project (P146788) (i) revision of the PDO indicator (1) “number of outages at rehabilitated SS is reduced” to include new SSs in: Kalush, Bohorodchany, Boryslav, Rivne, Ivano-Frankivsk, Kovel, Pivnichnoukrainska, Konotop, Poltava, Loseve, Bilotserkivska, Poliana, Chernihivska, Nizhynska, Slavutych and updating the target values accordingly; (ii) revision of the PDO indicator (2) “decrease in power usage for own needs of Substations which were reconstructed”; (iii) revision of the Intermediate Results Indicator (1) “Implementation progress of SS rehabilitation”; (2) “reduced operating and maintenance costs at the rehabilitated SSs”; and (4) “Energy Not Served reduced by 50%”; Other indicators are amended to reflect the extension of the Closing date. (d) Amending Section III of Schedule 2 to the Loan Agreement to allow for maximum flexibility to the Borrower in the selection of procurement methods for goods, works and non-consulting services and for consulting services. I. SUMMARY OF CHANGES Changed Not Changed Results Framework ✔ Loan Closing Date(s) ✔ Cancellations Proposed ✔ Reallocation between Disbursement Categories ✔ Procurement ✔ Implementing Agency ✔ DDO Status ✔ Project's Development Objectives ✔ Components and Cost ✔ Disbursements Arrangements ✔ Disbursement Estimates ✔ Overall Risk Rating ✔ Safeguard Policies Triggered ✔ EA category ✔ The World Bank Second Power Transmission Project (P146788) Legal Covenants ✔ Institutional Arrangements ✔ Financial Management ✔ APA Reliance ✔ Implementation Schedule ✔ Other Change(s) ✔ Economic and Financial Analysis ✔ Technical Analysis ✔ Social Analysis ✔ Environmental Analysis ✔ IV. DETAILED CHANGE(S) OPS_DETAILEDCHANGES_LOANCLOSING_TABLE LOAN CLOSING DATE(S) Original Revised Proposed Proposed Deadline Ln/Cr/Tf Status Closing Closing(s) Closing for Withdrawal Applications IBRD-84620 Effective 30-Jun-2020 29-Jun-2022 29-Oct-2022 TF-17661 Effective 30-Jun-2020 29-Jun-2022 29-Oct-2022 OPS_DETAILEDCHANGES_CANCELLATIONS_TABLE CANCELLATIONS Value Reason Current Cancellation New Ln/Cr/Tf Status Currency Date of for Amount Amount Amount Cancellation Cancellation BORROWER' S REQUEST IBRD- Disburs 330,000,000.0 270,000,000.0 USD 60,000,000.00 02-Apr-2019 FOR 84620-001 ing 0 0 COUNTRY REASONS BORROWER' S REQUEST TF-17661- Effectiv USD 48,425,000.00 0.00 02-Apr-2019 48,425,000.00 FOR 001 e COUNTRY REASONS The World Bank Second Power Transmission Project (P146788) OPS_DETAILEDCHANGES_REALLOCATION _TABLE REALLOCATION BETWEEN DISBURSEMENT CATEGORIES Financing % Current Allocation Actuals + Committed Proposed Allocation (Type Total) Current Proposed IBRD-84620-001 | Currency: USD iLap Category Sequence No: 1 Current Expenditure Category: GD,CW,Non-CS,CS,TR P 1,2.1,2.3,2.4 326,675,000.00 22,305,295.76 266,675,000.00 100.00 100.00 iLap Category Sequence No: 2 Current Expenditure Category: GD,Non-CS,CS,TR for P.3 2,500,000.00 333,844.64 2,500,000.00 100.00 100.00 iLap Category Sequence No: 4 Current Expenditure Category: Interest Rate Cap or Collar Premium 0.00 0.00 0.00 Total 329,175,000.00 22,639,140.40 269,175,000.00 . The World Bank Second Power Transmission Project (P146788) . Results framework COUNTRY: Ukraine Second Power Transmission Project Project Development Objectives(s) To improve the reliability of power transmission system and support implementation of the Wholesale Electricity Market in Ukraine. Project Development Objective Indicators by Objectives/ Outcomes RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Improve reliability of the power transmission system and support implementation of the WEM Number of outages at rehabilitated SSs is 0.00 0.00 reduced (Number) Action: This indicator has been Revised Sumy (Number) 27.00 27.00 27.00 27.00 27.00 27.00 27.00 7.00 Action: This indicator has been Revised Cherkaska (Number) 12.00 12.00 12.00 12.00 12.00 12.00 12.00 3.00 Action: This indicator has been Revised Novokyivska (Number) 35.00 35.00 35.00 35.00 35.00 35.00 35.00 8.00 Action: This indicator has been Revised Kremenchuk 37.00 37.00 37.00 37.00 37.00 37.00 37.00 9.00 (Number) The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator has been Revised Nyvky (Number) 23.00 23.00 23.00 23.00 23.00 23.00 23.00 5.00 Action: This indicator has been Revised Zhytomyrska 28.00 28.00 28.00 28.00 28.00 28.00 28.00 7.00 (Number) Action: This indicator has been Revised Kalush (Number) 18.00 18.00 18.00 18.00 18.00 4.00 Action: This indicator is New Bohorodchany 15.00 15.00 15.00 15.00 15.00 4.00 (Number) Action: This indicator is New Boryslav (Number) 6.00 6.00 6.00 6.00 6.00 1.00 Action: This indicator is New Rivne (Number) 21.00 21.00 21.00 21.00 21.00 5.00 Action: This indicator is New Ivano-Frankivsk 17.00 17.00 17.00 17.00 17.00 4.00 (Number) The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator is New Kovel (Number) 14.00 14.00 14.00 14.00 14.00 3.00 Action: This indicator is New Pivnichnoukrainska 3.00 3.00 3.00 3.00 3.00 1.00 (Number) Action: This indicator is New Konotop (Number) 6.00 6.00 6.00 6.00 6.00 1.00 Action: This indicator is New Poltava (Number) 22.00 22.00 22.00 22.00 22.00 5.00 Action: This indicator is New Loseve (Number) 26.00 26.00 26.00 26.00 26.00 6.00 Action: This indicator is New Bilotserkivska 25.00 25.00 25.00 25.00 25.00 6.00 (Number) Action: This indicator is New Poliana (Number) 16.00 16.00 16.00 16.00 16.00 4.00 The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator is New Chernihivska 17.00 17.00 17.00 4.00 (Number) Action: This indicator is New Nizhynska (Number) 16.00 16.00 16.00 16.00 16.00 4.00 Action: This indicator is New Slavutych (Number) 15.00 15.00 15.00 15.00 15.00 3.00 Action: This indicator is New Share of electricity traded on bilateral basis and day ahead market in 0.00 0.00 0.00 0.00 40.00 40.00 40.00 50.00 WEM of Ukraine (Percentage) Action: This indicator has been Revised Decrease in power usage for own needs of Substations which were 8,951.00 8,951.00 8,951.00 8,951.00 8,823.00 8,823.00 8,823.00 8,324.00 reconstructed (Megawatt hour(MWh)) Action: This indicator has been Revised The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 North Region SS Kremenchuk, Sumy 3,299.00 3,299.00 3,299.00 3,299.00 3,230.00 3,230.00 3,230.00 3,091.00 (Megawatt hour(MWh)) Action: This indicator has been Revised North Region: SS Pivnichnoukrainska, Konotop, Poltava, 6,647.00 6,647.00 6,647.00 6,647.00 6,647.00 6,647.00 6,647.00 6,189.00 Loseve (Megawatt hour(MWh)) Action: This indicator is New Central Region: SS Bilotserkivska, Poliana, Chernihivska, 5,088.00 5,088.00 5,088.00 5,088.00 5,088.00 5,088.00 5,088.00 4,778.00 Nizhynska, Slavutych (Megawatt hour(MWh)) Action: This indicator has been Revised Central Region: SS Novokyivska, Nyvki, Cherkaska, 3,863.00 3,863.00 3,863.00 3,863.00 3,735.00 3,735.00 3,735.00 3,546.00 Zhytomyrska (Megawatt hour(MWh)) The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator is New Western Region: SS Kalush, Bohorodchany, Boryslav, Rivne, Ivano- 5,414.00 5,414.00 5,414.00 5,414.00 5,414.00 5,414.00 5,414.00 5,132.00 Frankivsk, Kovel (Megawatt hour(MWh)) Action: This indicator is New PDO Table SPACE Intermediate Results Indicators by Components RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Rehabilitation of Transmission Substations (Action: This Component has been Revised) Reduced operating and maintenance costs at the rehabilitated SSs: Novokyivska,Nyvky,Krem enchuk,Zhytomyrsk,Cher 0.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 kaska,Sumy,Kalush,Bohor odchany,Boryslav,Rivne,I vano,Frankivsk,Kovel,Pivn ichnoukrainska etc (Percentage) The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Rationale: The indicator is revised to add additional substations. The final list includes: Action: This indicator has Novokyivska,Nyvky,Kremenchuk,Zhytomyrsk,Cherkaska,Sumy,Kalush,Bohorodchany,Boryslav,Rivne,Ivano,Frankivsk,Kovel,Pivnichnoukrainska,Konotop,Poltava,Lo been Revised seve,Bilotserkivska,Poliana,Chernihivska,Nizhynska,Slavutych Novokyivska 0.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 (Percentage) Action: This indicator is New Nyvky (Percentage) 0.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 Action: This indicator is New Kremenchuk 0.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 (Percentage) Action: This indicator is New Zhytomyrska 0.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 (Percentage) Action: This indicator is New Cherkaska 0.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 (Percentage) Action: This indicator is New Sumy (Percentage) 0.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator is New Kalush (Percentage) 0.00 50.00 Action: This indicator is New Bohorodchany 0.00 50.00 (Percentage) Action: This indicator is New Boryslav (Percentage) 0.00 50.00 Action: This indicator is New Rivne (Percentage) 0.00 50.00 Action: This indicator is New Ivano-Frankivsk 0.00 50.00 (Percentage) Action: This indicator is New Kovel (Percentage) 0.00 50.00 Action: This indicator is New Pivnichnoukrainska 0.00 50.00 (Percentage) The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator is New Konotop (Percentage) 0.00 50.00 Action: This indicator is New Poltava (Percentage) 0.00 50.00 Action: This indicator is New Loseve (Percentage) 0.00 50.00 Action: This indicator is New Bilotserkivska 0.00 50.00 (Percentage) Action: This indicator is New Poliana (Percentage) 0.00 50.00 Action: This indicator is New Chernihivska 0.00 50.00 (Percentage) Action: This indicator is New Nizhynska 0.00 50.00 (Percentage) The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator is New Slavutych 0.00 50.00 (Percentage) Action: This indicator is New Electricity losses per year in the Project area 1.90 1.70 1.70 1.70 1.60 1.60 1.60 1.40 (Percentage) Action: This indicator has been Revised Electricity losses per year in the project 0.00 0.00 0.00 0.00 0.00 0.00 area- Non-Technical (Percentage) Action: This indicator has been Marked for Deletion Electricity losses per year in the project 0.50 0.50 0.50 0.40 0.30 0.20 area- Technical (Percentage) The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator has been Marked for Deletion Total net injected generation (Megawatt 147,200.00 152,880.00 155,820.00 158,760.00 161,700.00 164,640.00 hour(MWh)) Action: This indicator has been Marked for Deletion Implementation progress Works on High of SS Rehabiliation Voltage Unit 110 – in:Novokyyivska,Nivki,Kre Detailed design by 150 kV start/ menchuk,Zhytomyrska,C The works at 110- The works at 110- Works continue on the contractor Contract Signed herkaska,Sumy,Kalush,Bo Bidding Document 150 kV high- 150 kV high- High Voltage Units 0.00 Contract Signed ready and and detailed design horodchany,Boryslav,Riv Ready voltage facilities voltage facilities 330 kV/ Contracts expertise review by the contractor ne,Ivano- continue continue Completed approved ready and Frankivsk,Kovel,Pivnichno expertise review ukrainska,Konotop,Poltav approved a etc (Text) Action: This indicator has been Revised Voltage at bus bars 35kV at the rehabilitated SSs 0.00 0.00 0.00 0.00 0.00 are within operating limits +-5% (Volts) Action: This indicator has been Revised The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Kamianets-Podilska 42.00 42.00 42.00 40.00 40.00 40.00 40.00 36.00 (Volts) Action: This indicator has been Revised Shepetivka (Volts) 41.00 41.00 41.00 40.00 40.00 40.00 40.00 36.00 Action: This indicator has been Revised Kovel (Volts) 40.00 40.00 40.00 39.00 39.00 39.00 39.00 36.00 Action: This indicator has been Revised Novovolynsk (Volts) 40.00 40.00 40.00 39.00 39.00 39.00 39.00 35.00 Action: This indicator has been Revised Lutsk Pivdenna (Volts) 40.00 40.00 40.00 39.00 39.00 39.00 39.00 35.00 Action: This indicator has been Revised Energy Not Served reduced (Gigawatt-hour 0.00 0.00 0.00 0.00 0.00 (GWh)) Action: This indicator has been Revised North Region (Gigawatt-hour 7.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 (GWh)) The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Action: This indicator has been Revised Central Region (Gigawatt-hour 35.00 0.00 0.00 0.00 25.00 25.00 25.00 50.00 (GWh)) Action: This indicator has been Revised West Region 25.00 0.00 0.00 0.00 0.00 0.00 0.00 50.00 (Percentage) Action: This indicator is New Tons of GHG emissions reduced or avoided 0.00 344,199.00 734,427.00 1,000,464.00 1,579,257.00 1,579,257.00 1,579,257.00 2,804,407.00 based on Electricity Savings (Tones/year) Action: This indicator has been Revised Annual energy savings 0.00 1,500.00 8,000.00 47,000.00 220,000.00 220,000.00 220,000.00 430,000.00 (MWh/year) Action: This indicator is New Increased installed RE caapacity in Ukraine ES 0.00 180.00 395.00 500.00 680.00 680.00 680.00 1,100.00 (Megawatt) Action: This indicator is New Electricity Market Enhancement The World Bank Second Power Transmission Project (P146788) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 Bidding Documents Implementation progress Feasibility study Bidding Documents Bidding Documents The contract under The contract under Detailed Design ready, Tender Contract Signed of Smart Grid (Text) completed preparation preparation implementation implementation ready Procedure opened Action: This indicator has been Revised The hardware The hardware Modifications to BM contract is under contract is under Contract Signed for (software)/ implementation implementation Implementation of Feasibility study Contract signed for Bidding Documents Contract Signed for hardware.Software Balancing Market The software is The software is Balancing Market (Text) completed hard and software preparation software Fine-tuned for the Operational / under under launch. Balancing Market implementation implementation Operational Action: This indicator has been Revised Bidding Documents Bidding Documents Contract Signed for ready for ready for hardware. hardware. Implementation progress Feasibility study hardware. Contract Signed for Detailed Design Contract under Contract under Bidding Documents MIS Operational of MIS (Text) completed Bidding Documents software. Completed for implementation implementation ready for software ready for software software. Action: This indicator has been Revised IO Table SPACE The World Bank Second Power Transmission Project (P146788) The World Bank Second Power Transmission Project (P146788)