PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive Bidding 1. 3M and above All contracts (ICB) (Goods) National Competitive Bidding (NCB) 2. less than 3M 2M and above (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated: May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 LN 8421 PH Procurement Plan Updated June 2018 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Ref. No. Description g ent Comments US$1= Source nce by Bank Opening Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review Threshold No. Selection Method Method Threshold US$ US$ 1. Competitive Methods 0.3M & above (may be used for also less 1m and above (QCBS, QBS, FBS) (Firms) than 0.3M) 2. Competitive Method CQS less than 0.3M None (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to justification Firms: 1M and above; Individuals) in accordance with paras. 3.9 and 5.4 Individuals 0.3M and respectively of Consultant Guidelines at above. the Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref. Description of Estimated Cost (USD Funding Procuring Expected Bid Comme Selection Method No. Contract Package million) Source Agency Opening Date nts Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 million) LP/GoP Selection US$1,042,75 Single Source Luzon A ( Php59.152 million) LP/GoP Selection US$1,042,75 Single Source Luzon B ( Php48.614 million) LP/GoP Selection US$1,042,75 Single Source Visaya ( Php29.612 million) LP/GoP Selection US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: LN 8421 PH Procurement Plan Updated June 2018 ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2017-11-03 2019-09-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 84210, IBRD / 88160 Executing Agency(ies): Department of Agriculture WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IFB No. 0185-N-2015 / Supply and Delivery of Forty (40) units Pick-up Truck, Double Cab, 4X4 Component 1: Local and Single Stage - One IBRD / 84210 Prior Request for Bids Open - National 0.00 1,261,350.14 Signed DED (Lot 1) and Six (6) National Level Planning Envelope units Van, DED (Lot 2) for Philippine Rural Development Project PRDP-IS-NPCO-090-GOODS- Pending Component 4: Project Request for Single Stage - One 001-2019 / IBRD / 88160 Post Open - National 3,773.58 0.00 Implementati 2019-01-06 2019-03-03 2019-08-30 Implementation Support Quotations Envelope Cabinet/Shelves/Rack on PRDP-IS-NPCO-091-GOODS- Pending Component 4: Project Request for Single Stage - One 001-2019 / Baggage IBRD / 88160 Post Open - National 9,433.96 0.00 Implementati 2019-01-06 2019-03-03 2019-08-30 Implementation Support Quotations Envelope Protective Carrier for Vehicle on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAS No. 0076-N / Consultancy Services for the Component 1: Local and Fixed Budget Open - Conduct of Value Chain IBRD / 84210 Prior 371,145.98 371,145.91 Signed National Level Planning Selection International Analysis of Agriculture and Fisheries Commodities Page 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IS-NPCO-IB-001-000- Component 4: Project 2018-AF / Alternate IBRD / 84210 Post Direct Selection Direct 9,882.35 19,451.95 Signed 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Component Head PRDP-IS-NPCO-IB-002-000- Component 4: Project 2018-AF / Roads and Bridge IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Specialist PRDP-IS-NPCO-IB-003-001- Component 4: Project 2018-AF / Roads IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-NPCO-IB-003-002- Component 4: Project 2018-AF / Roads IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-NPCO-IB-003-003- Component 4: Project 2018-AF / Roads IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-NPCO-IB-003-004- Component 4: Project 2018-AF / Roads IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-NPCO-IB-003-005- Component 4: Project 2018-AF / Roads IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-NPCO-IB-003-006- Component 4: Project 2018-AF / Roads IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-NPCO-IB-003-007- Component 4: Project 2018-AF / Roads IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-NPCO-IB-004-001- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-IB-004-002- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-IB-004-003- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-OPD-001- Component 4: Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 000-2018-AF / Legal Officer Implementation Support PRDP-IS-NPCO-OPD-002- Component 4: Project 001-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-OPD-002- Component 4: Project 002-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate Page 2 PRDP-IS-NPCO-DPD-001- Component 4: Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 000-2018-AF / Legal Officer Implementation Support PRDP-IS-NPCO-DPD-002- Component 4: Project 000-2018-AF / Compliance IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer PRDP-IS-NPCO-DPD-003- Component 4: Project 000-2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Assistant PRDP-IS-NPCO-001-000- Component 4: Project 2018-AF / I-Support IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Alternate Unit Head PRDP-IS-NPCO-ADM-001- Component 4: Project 001-2018-AF / Admin Officer IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support III PRDP-IS-NPCO-ADM-001- Component 4: Project 002-2018-AF / Admin Officer IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support III PRDP-IS-NPCO-ADM-002- Component 4: Project 001-2018-AF / Admin Officer IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I / Personnel Officer PRDP-IS-NPCO-ADM-002- 002-2018-AF / Admin Officer Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 I / Property and Supply Implementation Support Officer PRDP-IS-NPCO-ADM-003- Individual Component 4: Project 000-2018-AF / Administrative IBRD / 84210 Post Consultant Direct 3,529.41 0.00 Canceled 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 Implementation Support Assistant / Staff Selection Individual PRDP-IS-NPCO-ADM-004- Component 4: Project IBRD / 84210 Post Consultant Direct 3,529.41 0.00 Canceled 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 001-2018-AF / Cash Clerk Implementation Support Selection Individual PRDP-IS-NPCO-ADM-004- Component 4: Project IBRD / 84210 Post Consultant Direct 3,529.41 0.00 Canceled 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 002-2018-AF / Cash Clerk Implementation Support Selection PRDP-IS-NPCO-ADM-005- Component 4: Project 001-2018-AF / Chauffeur / IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Driver PRDP-IS-NPCO-ADM-005- Component 4: Project 002-2018-AF / Chauffeur / IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Driver PRDP-IS-NPCO-ADM-005- Component 4: Project 003-2018-AF / Chauffeur / IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Driver PRDP-IS-NPCO-ADM-005- Component 4: Project 004-2018-AF / Chauffeur / IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Driver PRDP-IS-NPCO-ADM-005- Component 4: Project 005-2018-AF / Chauffeur / IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Driver Page 3 PRDP-IS-NPCO-ADM-005- Component 4: Project 006-2018-AF / Chauffeur / IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Driver PRDP-IS-NPCO-ADM-005- Individual Component 4: Project 007-2018-AF / Chauffeur / IBRD / 84210 Post Consultant Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 Implementation Support Driver Selection PRDP-IS-NPCO-ADM-005- Individual Component 4: Project 008-2018-AF / Chauffeur / IBRD / 84210 Post Consultant Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 Implementation Support Driver Selection PRDP-IS-NPCO-ADM-006- Component 4: Project 000-2018-AF / Messengerial IBRD / 84210 Post Direct Selection Direct 2,541.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Staff PRDP-IS-NPCO-ADM-007- Component 4: Project IBRD / 84210 Post Direct Selection Direct 2,117.65 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 000-2018-AF / Utility Worker Implementation Support PRDP-IS-NPCO-FIN-001-000- Component 4: Project 2018-AF / LGU Finance / IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Alternate Unit Head PRDP-IS-NPCO-FIN-002-000- Component 4: Project 2018-AF / Finance Analyst IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support III PRDP-IS-NPCO-FIN-003-000- Component 4: Project 2018-AF / Finance Analyst IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support II PRDP-IS-NPCO-FIN-004-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Finance Analyst I Implementation Support PRDP-IS-NPCO-FIN-005-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-ACC-001- Component 4: Project 001-2018-AF / Financial IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Analyst I PRDP-IS-NPCO-ACC-001- Component 4: Project 002-2018-AF / Financial IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Analyst I PRDP-IS-NPCO-ACC-001- Component 4: Project 003-2018-AF / Financial IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Analyst I PRDP-IS-NPCO-BUD-001- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 001-2018-AF / Budget Implementation Support Analyst I PRDP-IS-NPCO-BUD-001- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 002-2018-AF / Budget Implementation Support Analyst I PRDP-IS-NPCO-PRO-001- Component 4: Project 000-2018-AF / Alternate Unit IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Head PRDP-IS-NPCO-PRO-002- Component 4: Project 001-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Specialist Page 4 PRDP-IS-NPCO-PRO-002- Component 4: Project 002-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Specialist PRDP-IS-NPCO-PRO-003- Component 4: Project 001-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer PRDP-IS-NPCO-PRO-003- Component 4: Project 002-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer PRDP-IS-NPCO-PRO-003- Component 4: Project 003-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer PRDP-IS-NPCO-PRO-004- Component 4: Project 001-2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Procurement Officer PRDP-IS-NPCO-PRO-004- Component 4: Project 002-2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Procurement Officer PRDP-IS-NPCO-PRO-005- Component 4: Project 001-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-PRO-005- Component 4: Project 002-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-MAE-001- Component 4: Project 000-2018-AF / M&E Unit IBRD / 84210 Post Direct Selection Direct 10,588.24 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Head PRDP-IS-NPCO-MAE-002- Component 4: Project 000-2018-AF / M&E IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Alternate Unit Head PRDP-IS-NPCO-MAE-003- Component 4: Project 001-2018-AF / M&E IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Specialist PRDP-IS-NPCO-MAE-003- Component 4: Project 002-2018-AF / M&E IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Specialist PRDP-IS-NPCO-MAE-004- Component 4: Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 000-2018-AF / M&E Officer Implementation Support PRDP-IS-NPCO-MAE-005- Component 4: Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 000-2018-AF / MIS Officer Implementation Support PRDP-IS-NPCO-MAE-006- Component 4: Project 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-SES-001-000- Component 4: Project 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Safeguards Specialist PRDP-IS-NPCO-SES-002-000- Component 4: Project 2018-AF / Social Safeguard IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Specialist Page 5 PRDP-IS-NPCO-SES-003-000- Component 4: Project 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Safeguards Officer PRDP-IS-NPCO-SES-004-000- Component 4: Project 2018-AF / Social Safeguard IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer PRDP-IS-NPCO-SES-005-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-GGU-001- 000-2018-AF / Geomapping Component 4: Project IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 and Governance Alternate Implementation Support Unit Head PRDP-IS-NPCO-GGU-002- Component 4: Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 000-2018-AF / GIS Data Implementation Support Officer PRDP-IS-NPCO-GGU-003- Component 4: Project 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-INF-001-000- Component 4: Project 2018-AF / Web IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Administrator PRDP-IS-NPCO-INF-002-000- Component 4: Project 2018-AF / Graphics / Layout IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Artist PRDP-IS-NPCO-INF-003-001- Component 4: Project 2018-AF / Photographer / IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Videographer PRDP-IS-NPCO-INF-003-002- Component 4: Project 2018-AF / Photographer / IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Videographer PRDP-IS-NPCO-INF-004-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-ECO-001- Component 4: Project 000-2018-AF / Economics IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Alternate Unit Head PRDP-IS-NPCO-ECO-002- Component 4: Project 001-2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Economist PRDP-IS-NPCO-ECO-002- Component 4: Project 002-2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Economist PRDP-IS-NPCO-ECO-003- Component 4: Project 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-GEF-001- Component 4: Project 000-2018-AF / GEF NRM IBRD / 84210 Post Direct Selection Direct 10,588.24 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Unit Head Page 6 PRDP-IS-NPCO-GEF-002- Component 4: Project 000-2018-AF / GEF NRM IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer PRDP-IS-NPCO-GEF-003- Component 4: Project 001-2018-AF / Regional GEF IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support NRM Officer PRDP-IS-NPCO-GEF-003- Component 4: Project 002-2018-AF / Regional GEF IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support NRM Officer PRDP-IS-NPCO-GEF-004- Component 4: Project 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-NPCO-001-IB-001- Individual Component 4: Project Pending 2019-AF / Alternate IBRD / 88160 Post Consultant Direct 20,377.36 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Component Head Selection PRDP-IS-NPCO-002-IB-002- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 14,943.40 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Specialist Selection PRDP-IS-NPCO-003-IB-003- Individual Component 4: Project Pending 2019-AF / Roads IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-004-IB-004- Individual Component 4: Project Pending 2019-AF / Roads IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-005-IB-005- Individual Component 4: Project Pending 2019-AF / Roads IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-006-IB-006- Individual Component 4: Project Pending 2019-AF / Roads IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-007-IB-007- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 9,509.43 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-NPCO-008-ISP-001- Individual Component 4: Project Pending 2019-AF / I-Support IBRD / 88160 Post Consultant Direct 20,377.36 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Alternate Unit Head Selection Individual PRDP-IS-NPCO-012-OPD- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 16,301.89 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 001-2019-AF / Legal Officer Implementation Support Implementation Selection PRDP-IS-NPCO-013-OPD- Individual Component 4: Project Pending 002-2019-AF / Administrative IBRD / 88160 Post Consultant Open 9,509.43 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer II Selection PRDP-IS-NPCO-014-OPD- Individual Component 4: Project Pending 003-2019-AF / Administrative IBRD / 88160 Post Consultant Open 7,471.70 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer I Selection PRDP-IS-NPCO-015-DPD- Individual Component 4: Project Pending 001-2019-AF / Senior Project IBRD / 88160 Post Consultant Open 12,226.42 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Development Specialist Selection Page 7 PRDP-IS-NPCO-016-DPD- Individual Component 4: Project Pending 002-2019-AF / Administrative IBRD / 88160 Post Consultant Open 7,924.53 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer II Selection PRDP-IS-NPCO-017-DPD- Individual Component 4: Project Pending 003-2019-AF / Administrative IBRD / 88160 Post Consultant Open 7,924.53 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer II Selection PRDP-IS-NPCO-019-DPD- Individual Component 4: Project Pending 005-2019-AF / Senior IBRD / 88160 Post Consultant Open 14,943.40 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Economist Selection Individual PRDP-IS-NPCO-020-DPD- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 006-2019-AF / Economist Implementation Support Implementation Selection Individual PRDP-IS-NPCO-021-DPD- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,509.43 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 007-2019-AF / Economist Implementation Support Implementation Selection PRDP-IS-NPCO-022-ADM- Individual Component 4: Project Pending 001-2019-AF / Supply & IBRD / 88160 Post Consultant Direct 10,867.92 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Property Officer Selection PRDP-IS-NPCO-023-ADM- Individual Component 4: Project Pending 002-2019-AF / Administrative IBRD / 88160 Post Consultant Direct 10,867.92 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer III Selection PRDP-IS-NPCO-024-ADM- Individual Component 4: Project Pending 003-2019-AF / Administrative IBRD / 88160 Post Consultant Direct 9,509.43 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer III Selection PRDP-IS-NPCO-025-ADM- Individual Component 4: Project Pending 004-2019-AF / Administrative IBRD / 88160 Post Consultant Open 6,792.45 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer II Selection PRDP-IS-NPCO-039-GGU- Individual 001-2019-AF / Geomapping Component 4: Project Pending IBRD / 88160 Post Consultant Direct 19,018.87 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 & Governance Alternate Implementation Support Implementation Selection Unit Head Individual PRDP-IS-NPCO-040-GGU- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 002-2019-AF / GIS Officer Implementation Support Implementation Selection PRDP-IS-NPCO-041-FIN-001- Individual Component 4: Project Pending 2019-AF / Alternate Unit IBRD / 88160 Post Consultant Direct 19,018.87 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Head Selection PRDP-IS-NPCO-042-FIN-002- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-04-01 2019-04-11 2019-05-02 2019-06-06 2019-12-03 Implementation Support Implementation II Selection PRDP-IS-NPCO-043-FIN-003- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Open 12,452.83 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation II Selection PRDP-IS-NPCO-044-FIN-004- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Open 12,452.83 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation II Selection PRDP-IS-NPCO-045-ACT-001- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 12,226.42 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation I Selection Page 8 PRDP-IS-NPCO-046-ACT-002- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 12,226.42 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation I Selection PRDP-IS-NPCO-047-ACT-003- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 12,226.42 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation I Selection PRDP-IS-NPCO-048-BUD- Individual Component 4: Project Pending 001-2019-AF / Budget IBRD / 88160 Post Consultant Direct 12,226.42 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Analyst Selection PRDP-IS-NPCO-049-BUD- Individual Component 4: Project Pending 002-2019-AF / Budget IBRD / 88160 Post Consultant Direct 12,226.42 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Analyst Selection PRDP-IS-NPCO-050-BUD- Individual Component 4: Project Pending 003-2019-AF / Budget IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst Selection PRDP-IS-NPCO-051-PRO- Individual Component 4: Project Pending 001-2019-AF / Alternate Unit IBRD / 88160 Post Consultant Direct 19,018.87 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Head Selection PRDP-IS-NPCO-052-PRO- Individual Component 4: Project Pending 002-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 14,943.40 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Specialist Selection PRDP-IS-NPCO-053-PRO- Individual Component 4: Project Pending 003-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer Selection PRDP-IS-NPCO-054-PRO- Individual Component 4: Project Pending 004-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer Selection PRDP-IS-NPCO-055-PRO-00- Individual Component 4: Project Pending 2019-AF / Associate IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Procurement Officer Selection PRDP-IS-NPCO-056-MNE- Individual Component 4: Project Pending 001-2019-AF / Monitoring & IBRD / 88160 Post Consultant Direct 20,377.36 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Evaluation Unit Head Selection PRDP-IS-NPCO-057-MNE- Individual Component 4: Project Pending 002-2019-AF / Monitoring & IBRD / 88160 Post Consultant Direct 19,018.87 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Evaluation Alternate Head Selection Individual PRDP-IS-NPCO-058-MNE- Component 4: Project Pending IBRD / 88160 Post Consultant Open 3,735.85 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 003-2019-AF / MIS Specialist Implementation Support Implementation Selection PRDP-IS-NPCO-059-MNE- Individual Component 4: Project Pending 004-2019-AF / Monitoring & IBRD / 88160 Post Consultant Direct 14,943.40 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Evaluation Specialist Selection PRDP-IS-NPCO-060-MNE- Individual Component 4: Project Pending 005-2019-AF / Monitoring & IBRD / 88160 Post Consultant Open 12,226.42 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Evaluation Officer Selection PRDP-IS-NPCO-061-SES-001- Individual 2019-AF / Social & Component 4: Project Pending IBRD / 88160 Post Consultant Direct 14,943.40 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Environment Safeguards Implementation Support Implementation Selection Specialist Page 9 PRDP-IS-NPCO-062-SES-002- Individual 2019-AF / Social & Component 4: Project Pending IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Environment Safeguards Implementation Support Implementation Selection Officer PRDP-IS-NPCO-063-SES-003- Individual 2019-AF / Social & Component 4: Project Pending IBRD / 88160 Post Consultant Direct 13,584.91 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Environment Safeguards Implementation Support Implementation Selection Officer PRDP-IS-NPCO-064-SES-004- Individual 2019-AF / Associate Social & Component 4: Project Pending IBRD / 88160 Post Consultant Open 12,226.42 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Environment Safeguards Implementation Support Implementation Selection Officer PRDP-IS-NPCO-065-ICE-001- Individual Component 4: Project Pending 2019-AF / Information IBRD / 88160 Post Consultant Open 14,943.40 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Specialist Selection Individual PRDP-IS-NPCO-066-ICE-002- Component 4: Project Pending IBRD / 88160 Post Consultant Open 12,226.42 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 2019-AF / Writer Implementation Support Implementation Selection PRDP-IS-NPCO-067-ICE-003- Individual Component 4: Project Pending 2019-AF / Media Production IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NPCO-068-R00-001- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Specialist Selection PRDP-IS-NPCO-069-R00-002- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Specialist Selection PRDP-IS-NPCO-070-R00-003- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-071-R00-004- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-072-R00-005- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-073-R00-006- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-074-R00-007- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-075-R00-008- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-076-R00-009- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-077-R00-010- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection Page 10 PRDP-IS-NPCO-078-R00-011- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-079-R00-012- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-080-R00-013- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NPCO-081-R00-001- Individual 2019-AF / Web-based Component 4: Project Pending IBRD / 88160 Post Consultant Open 15,094.34 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Financial Management Implementation Support Implementation Selection System PRDP-IS-NPCO-082-OPD- Individual Component 4: Project Pending 004-2019-AF / Compliance IBRD / 88160 Post Consultant Direct 3,735.85 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer Selection PRDP-IS-NPCO-083-OPD- Individual Component 4: Project Pending 005-2019-AF / Project IBRD / 88160 Post Consultant Direct 2,377.36 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-06-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NPCO-084-OPD- Individual Component 4: Project Pending 006-2019-AF / Project IBRD / 88160 Post Consultant Direct 2,377.36 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-NPCO-085-PRO- Individual Component 4: Project Pending 006-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 3,396.23 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-03-17 Implementation Support Implementation Officer Selection PRDP-IS-NPCO-086-PRO- Individual Component 4: Project Pending 007-2019-AF / Associate IBRD / 88160 Post Consultant Direct 3,056.60 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Procurement Officer Selection PRDP-IS-NPCO-087-ICE-004- Individual Component 4: Project Pending 2019-AF / Graphic and Lay IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-03-17 Implementation Support Implementation out Artist Selection PRDP-IS-NPCO-088-FIN-005- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 2,377.36 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection Page 11