The World Bank Report No: ISR15376 Implementation Status & Results Argentina AR APL2 Urban Flood Prevention and Drainage (P093491) Public Disclosure Copy Operation Name: AR APL2 Urban Flood Prevention and Drainage (P093491) Project Stage: Implementation Seq.No: 17 Status: ARCHIVED Archive Date: 02-Aug-2014 Country: Argentina Approval FY: 2006 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Adaptable Program Loan Implementing Agency(ies): Ministry of Federal Planning (UCPyPFE) Key Dates Board Approval Date 06-Jun-2006 Original Closing Date 31-Mar-2011 Planned Mid Term Review Date 28-Nov-2011 Last Archived ISR Date 08-Dec-2013 Effectiveness Date 03-Mar-2008 Revised Closing Date 31-Dec-2014 Actual Mid Term Review Date 30-Nov-2011 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project would help reduce vulnerability of Argentina to flooding, through a mix of physical, institutional and financial measures. It will be the second phase of an APL, planned over the next 7 years. While phase 1 of the program develops a risk management program for the City of Buenos Aires, phase 2 develops a risk management program for six provinces complying with the selection criteria, and undertakes preparation of the future operations. The measures will aim at improving the security of economic assets and persons living in flood-prone areas by constructing defense facilities to reduce future losses due to floods, and by strengthening national and provincial institutions and systems for dealing with future floods. These provinces (Chaco, Corrientes, Misiones, Santa Fe, Formosa and Entre Rios), are located along the two main rivers, the Paran? and Paraguay, constituting the Argentinean region most vulnerable to flooding. The provinces have started to develop a risk management strategy under the current Flood Protection Project (4117-AR), and they succeeded in achieving positive results in risk identification and mitigation. In addition, the provinces will build on the achievements and experience from the City of Buenos Aires in phase1. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Non Structural Measures 2.80 Public Disclosure Copy Emergency Social Interventions 12.50 Development of Key Defense Facilities 52.20 Project Implementation and Administration 2.50 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating NA Page 1 of 6 The World Bank Report No: ISR15376 Implementation Status Overview The project is financing structural and non structural measures in the provinces of Corrientes, Chaco, Santa Fe and Entre Rios to reduce vulnerability of Argentina to flooding. All work contracts have been signed and are expected to be finished before the end of the project (December 31st, 2014). Finished works have benefited 287,000 people (72 percent of the goal), and have made possible to protect 3,680 ha of land against flooding (exceeding the project the goal). The participating provinces have made great progress in Public Disclosure Copy implementing non structural measures. Eight municipalities have published ordinances with information on risk and land uses. Approximately 3.6 million people are now protected by flood risk contingency plans surpassing the PAD target of 2.5 million. Eighteen communication campaigns for municipal stakeholders were carried out. Five monitoring systems of drainage and wastewater effluent quality were implemented. And two provinces are now equipped with contingency plans and have carried out simulations. Finally, the implementation of the resettlement plan in Resistencia is helping 207 families that lived in flood prone areas. Implementation of the Resistencia resettlement plan is considered best practice. Locations Country First Administrative Division Location Planned Actual Argentina Not Entered Wanda Argentina Not Entered Villa Hernandarias Argentina Chaco Resistencia ✔ Argentina Chaco Puerto Vilelas ✔ Argentina Not Entered Provincia de Misiones Not Entered Not Entered Provincia de Misiones ✔ Argentina Not Entered Mercedes Not Entered Not Entered Mercedes ✔ Argentina Corrientes Gobernador Ingeniero Valentin Virasoro ✔ Argentina Not Entered Provincia de Formosa Not Entered Not Entered Provincia de Formosa ✔ Argentina Not Entered Provincia de Entre Ríos Public Disclosure Copy Not Entered Not Entered Provincia de Entre Ríos ✔ ✔ Argentina Not Entered Curuzú Cuatiá Argentina Not Entered Provincia de Corrientes Not Entered Not Entered Provincia de Corrientes ✔ ✔ Argentina Not Entered Bella Vista Argentina Not Entered Barranqueras Page 2 of 6 The World Bank Report No: ISR15376 Country First Administrative Division Location Planned Actual Not Entered Not Entered Barranqueras ✔ Public Disclosure Copy Argentina Not Entered Provincia de Santa Fe Not Entered Not Entered Provincia de Santa Fe ✔ ✔ Argentina Not Entered Provincia del Chaco Not Entered Not Entered Provincia del Chaco ✔ ✔ Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target 1. Area protected by the proposed works in the Text Value 0 3680 3124 ha selected provinces Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 Comments The new revised indicator From finished contracts New target of 3,124 ha was agreed on the restructuring is: agreed in Project "Size of area protected by the Restructuring (March 2011) proposed works in the participating provinces". The new baseline is 2630 2. Municipalities for which land use planning Text Value 0 8 5 includes risk mapping Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 Comments The new revised indicator New target of 5 was agreed in agreed on the restructuring is Project Restructuring (March "Number of Municipalities for 2011) which land use planning includes risk mapping, including identification, location, quantification and Public Disclosure Copy characterization of population" Population with reduced flood vulnerability as a Number Value 0.00 287000.00 400000.00 result of proposed works in participating Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 provinces. Comments From finished contracts. It is A target of 400,000 was expected to benefit more than agreed in Project 460.000 Restructuring (March 2011) Intermediate Results Indicators Page 3 of 6 The World Bank Report No: ISR15376 Indicator Name Core Unit of Measure Baseline Current End Target Number of provinces equipped with Text Value 0 2 4 contingency plans and having carried out Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 Public Disclosure Copy simulations Comments Santa Fe and Entre Rios New target of 4 was agreed in Project Restructuring (March 2011) Municipal ordinances published with Text Value 0 8 5 information on risk and land use in all provincial Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 cities involved by works Comments New target of 5 was agreed in Project Restructuring (March 2011) Population covered by flood-risk contingency Text Value 0 3,594,537 2,500,000 plans. Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 Comments New target of 2,500,000 was agreed in Project Restructuring (March 2011) Population re-housed in safe areas and fully Text Value 0 675 1,800 protected from floods Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 Comments The new revised indicator From people living already in New target of 1,800 was agreed on the restructuring is: finished houses. agreed in Project "Population re-housed in safe Restructuring (March 2011) areas with low flooding risk" Length of drainage network constructed Text Value 0 49077 48,077 m Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 Comments Communication campaings for municipal stake Number Value 0.00 18.00 9.00 holders (indicator agreed on project Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 restructuring March 2011) Comments Public Disclosure Copy Physical works completed Number Value 3.00 5.00 12.00 Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 Comments Due to the imposibility of financing the works in Entre Rios this target will not reach the goal. Ongoing contracts will make the indicator to raise to 9 Page 4 of 6 The World Bank Report No: ISR15376 Monitoring system of drainage and wastewater Number Value 1.00 1.00 2.00 effluent quality (New indicator agreed in project Date 30-Jun-2006 30-Apr-2014 31-Mar-2014 restructuring March 2011) Comments Previous reported value was Public Disclosure Copy a mistake (typo). Data on Financial Performance (as of 14-May-2014) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P093491 IBRD-73820 Effective 06-Jun-2006 08-May-2007 03-Mar-2008 31-Mar-2011 31-Dec-2014 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P093491 IBRD-73820 Effective USD 70.00 70.00 0.00 58.31 11.69 83.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation The extension of the closing date of the Project, from March 30, 2014 to December 31, 2014, was approved by the Bank on November 21, 2013. The extension is allowing to complete three contracts in Chaco, including those related to the resettlement in Resistencia, and one contract in the Province of Santa Fe for the protection of the coastal area of Cayasta. According to the information received during the last supervision mission in May and the closely monitoring it is expected to finish all works before the end of the Project. Page 5 of 6 The World Bank Report No: ISR15376 Restructuring History Level two Approved on 29-Mar-2011, Level two Approved on 01-Oct-2012 Public Disclosure Copy Related Projects There are no related projects. Public Disclosure Copy Page 6 of 6