Procurement Plan Guangdong Agricultural Pollution Control Project I. General 1. Bank’s approval Date of the procurement Plan [original: April 13,2016; 1st Revision: June 12,2016; 2nd Revision: February 10, 2017;3rd Revision: July 12,2017; 4th Revision: January 2, 2018;5th Revision: March 21, 2018;6th Revision: April 25, 2018;7th Revision: June 7, 2018 ] 2. Date of General Procurement Notice: Feb. 12, 2014 3. Period covered by this procurement plan: 2014-2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 10 million 2. NCB (Goods) Above US$ 2million 3. ICB (Works) Above US$ 40 million 4. NCB (Works) Above US$ 10 million 5. ICB(Non-Consultant Services) Above US$ 10 million 6. NCB(Non-Consultant Services) Above US$ 2million 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation Manual approved by the Bank] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by Guangdong Agricultural Pollution Control PMO 5. Any Other Special Procurement Arrangements: N/A 6. Summary of the Procurement Packages planned 1 2 3 4 5 6 7 Ref. Description Estima Packages Domest Review Comments No. ted ic Prefere by Bank Cost nce (Prior / Post) US$ (yes/no) million Summary of the 0 0 ICB (Works) Summary of the 0 0 ICB (Goods) Summary of the 2.095 2 all belong NCB (Works) to Post rebidding review Summary of the 0 0 all belong Shopping(Works) to Post review Summary of the 0 0 NCB (Goods) Summary of the 0 0 ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 1 million 2. Single Source (Firms) Above US$ 1 million 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0 0 number of contracts that will be let under QCBS Summary of 0 0 CQS number of contracts that will be let under other methods PROCUREMENT China : China Guangdong Agricultural Pollution Control PLAN General Information Country: China Banks Approval Date of the Original Procurement Plan: 2017-08-08 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-06-09 Project ID: P127775 GPN Date: Project Name: China Guangdong Agricultural Pollution Control Loan / Credit No: IBRD / 83110 Executing Agency(ies): Guangdong Department of Agriculture WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management Bid No.: 0724-1400A08040 / Environmentally Friendly Crop Livestock waste management Production systems of 4 pig farms in Livestock Waste Management Single Stage - One Huizhou City(2 digesters of which IBRD / 83110 (LWM) Prior Request for Bids Open - National N 858,200.00 986,559.66 Signed 2014-07-13 2014-08-08 Envelope are Integrated Digestion Tank, Monitoring and Evaluation the rest 2 are up-stream (M&E), Capacity Development digesters) and Knowledge Management (KM) Project Management Environmentally Friendly Crop Bid No.: 0724-1400A08N0309 / Production Thye First NCB Works : Works Livestock Waste Management of the Livestock Waste Single Stage - One IBRD / 83110 (LWM) Prior Request for Bids Open - National N 1,990,000.00 1,754,556.52 Signed 2014-06-03 2014-07-08 Management Systems of the Envelope Monitoring and Evaluation Five Pig Farms in Huizhou (M&E), Capacity Development Municipality and Knowledge Management (KM) GDAPC-EPC-HY1802 / Physical construction works of system Livestock Waste Management Request for Single Stage - One IBRD / 83110 Post Limited 350,000.00 0.00 Canceled 2018-04-05 2018-05-31 2018-12-31 improvement of Baojin breeding (LWM) Quotations Envelope farm in Heyuan GDAPC-EPC-ZQZJ / Livestock waste management systems of Livestock Waste Management Request for Single Stage - One Under IBRD / 83110 Post Limited 310,000.00 0.00 2018-05-05 2018-04-27 2018-07-14 2019-03-31 Zhongjian pig farm in Zhaoqing (LWM) Quotations Envelope Implementation Municipality- EPC GDAPC-EPC-LDFY / Livestock waste management systems of Livestock Waste Management Request for Single Stage - One Under IBRD / 83110 Post Limited 474,680.00 0.00 2018-05-05 2018-04-27 2018-07-14 2019-03-31 Fangyuan pig farm in Luoding (LWM) Quotations Envelope Implementation City - EPC GPAPC-EPC-ZJKDT / Livestock waste management systems of Livestock Waste Management Single Stage - One IBRD / 83110 Post Request for Bids Open - National 791,140.00 0.00 Canceled 2018-04-10 2018-04-25 2018-04-15 2018-05-01 2018-05-27 2018-05-29 2018-06-06 2018-05-29 2018-07-20 2019-04-30 Kedatan pig farm in Zhanjiang (LWM) Envelope Municipality- EPC GDAPC-EPC-ZQMY / Livestock waste management systems of Livestock Waste Management Single Stage - One IBRD / 83110 Post Request for Bids Open - National 1,186,000.00 0.00 Canceled 2018-04-10 2018-04-25 2018-04-15 2018-05-01 2018-05-27 2018-05-29 2018-06-06 2018-05-29 2018-07-20 2019-04-30 Meiyi pig farm in Zhaoqing (LWM) Envelope Municipality- EPC GDAPC-EPC-HY1801 / Physical construction works of system Livestock Waste Management Request for Single Stage - One Under IBRD / 83110 Post Limited 400,000.00 0.00 2018-04-25 2018-04-12 2018-07-04 2018-12-31 improvement of Guangnan (LWM) Quotations Envelope Implementation breeding farm in Heyuan GDAPC-EPC-ZJYH1801 / Livestock waste management Livestock Waste Management Single Stage - One Pending systems of 2 pig farms of IBRD / 83110 Post Request for Bids Open - National 1,428,500.00 0.00 2018-04-30 2018-05-07 2018-06-21 2018-07-21 2018-09-01 2019-12-31 (LWM) Envelope Implementation Zhanjiang- No.1 Tuzhu Farm -- EPC (Jiaoyiling, Ma'an'nan) GDAPC-EPC-ZJYH1802 / Livestock waste management Livestock Waste Management Single Stage - One Pending systems of 2 pig farms of IBRD / 83110 Post Request for Bids Open - National 1,428,500.00 0.00 2018-04-30 2018-05-07 2018-06-26 2018-07-26 2018-09-06 2019-12-31 (LWM) Envelope Implementation Zhanjiang- No.1 Tuzhu Farm -- EPC (Qilian,Shitouling) GDAPC-EPC-HZ17 / Livestock waste management systems of Livestock Waste Management Request for Single Stage - One Under IBRD / 83110 Post Limited 475,000.00 0.00 2018-05-05 2018-05-14 2018-07-14 2019-03-31 Aigefei pig farm in Huizhou (LWM) Quotations Envelope Implementation Municipality - EPC GDAPC-EPC-HZB1 / Physical construction works of system Livestock Waste Management Single Stage - One Under improvement of 4 breeding IBRD / 83110 Post Request for Bids Open - National 795,000.00 0.00 2018-04-20 2018-04-02 2018-04-25 2018-04-11 2018-06-09 2018-07-09 2018-08-20 2019-06-30 (LWM) Envelope Implementation farms of the 1st batch in Huizhou(rebidding) GPAPC-EPC-ZJKDT-2 / Livest ock waste management syst ems of Kedatan pig farm in Z IBRD / 83110 Livestock Waste Management Post Request for Bids Open - National Single Stage - One 795,000.00 0.00 Pending 2018-06-15 2018-06-20 2018-08-01 2018-08-08 2018-09-21 2019-09-30 (LWM) Envelope Implementation hanjiang Municipality- EPC(r ebidding) GDAPC-EPC-ZQMY-2 / Livestock waste management Livestock Waste Management Single Stage - One Pending systems of Meiyi pig farm in IBRD / 83110 Post Request for Bids Open - National 1,300,000.00 0.00 2018-06-20 2018-06-25 2018-08-06 2018-08-13 2018-09-26 2019-10-31 (LWM) Envelope Implementation Zhaoqing Municipality- EPC(rebidding) GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Project Management Environmentally Friendly Crop Production GDAPC-EA-G1405 / Publicity Livestock Waste Management boards of the project sites of the Request for IBRD / 83110 (LWM) Prior Open - International N 100,000.00 95,683.75 Signed 2015-01-16 first year (crop farms, villagers Quotations Monitoring and Evaluation committees and breeding farms) (M&E), Capacity Development and Knowledge Management (KM) Project Management Environmentally Friendly Crop Production Bid No.: 0724-1400A08N0966 / Livestock Waste Management Single Stage - One Solar insecticidal lamps and IBRD / 83110 (LWM) Prior Request for Bids Open - National N 129,200.00 119,144.07 Signed 2016-05-05 2014-08-15 Envelope sticky boards Monitoring and Evaluation (M&E), Capacity Development and Knowledge Management (KM) GDAPC-G1710 / Equipment f or Longchuan Dongrui organi c fertilzer plant(The contract Livestock Waste Management Request for Single Stage - One IBRD / 83110 Post Limited 440,000.00 428,877.60 Signed 2018-04-04 2018-03-15 2018-05-30 2018-04-02 2018-12-31 was not procured in Y2017 an (LWM) Quotations Envelope d procurement was postpone d to Y2018) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Monitoring and Evaluation GDAPC-NC1801 / Agent for (M&E), Capacity Development Request for Single Stage - One Farmer' Training in Y2018 IBRD / 83110 Post Limited 485,000.00 350,566.44 Signed 2018-03-15 2018-03-08 2018-04-18 2018-03-30 2018-12-31 and Knowledge Management Quotations Envelope (Eastern area of Guangdong) (KM) GDAPC-NC1802 / Agent for Monitoring and Evaluation Farmer' Training in (M&E), Capacity Development Request for Single Stage - One IBRD / 83110 Post Limited 485,000.00 272,341.13 Signed 2018-03-15 2018-03-08 2018-04-20 2018-03-30 2018-12-31 Y2018(Western area of and Knowledge Management Quotations Envelope Guangdong) (KM) GDAPC-NC1803 / Agent for international training to Australia- Monitoring and Evaluation CA Technical Training(20 (M&E), Capacity Development Request for Single Stage - One Pending IBRD / 83110 Post Limited 185,000.00 0.00 2018-07-20 2018-09-12 2019-05-13 persons, 21 days, costs for air and Knowledge Management Quotations Envelope Implementation tickets and Visa are not included (KM) ) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management Environmentally Friendly Crop 0724-1510A08W0283/GDAPC- Production CS1404 / Environment Monitoring Livestock Waste Management Quality Based and Consultation Services for IBRD / 83110 (LWM) Prior Open - International N 1,105,000.00 911,307.76 Signed 2016-01-07 2016-01-08 Selection Livestock Waste Management Monitoring and Evaluation Demonstration (M&E), Capacity Development and Knowledge Management (KM) Project Management Environmentally Friendly Crop Production Livestock Waste Management Consultant 0724-1410A08W3362/GDAPC- IBRD / 83110 (LWM) Prior Qualification Open - International N 266,700.00 250,430.43 Signed 2015-08-20 2015-08-25 CS1414 / PMP Monitoring Monitoring and Evaluation Selection (M&E), Capacity Development and Knowledge Management (KM) Project Management Environmentally Friendly Crop Production GDAPC-CS1502 / Environment Livestock Waste Management Monitoring Consultation Services Quality Based IBRD / 83110 (LWM) Prior Open - International N 1,700,000.00 1,450,212.39 Signed 2016-10-24 2016-10-27 for Fertilizer Reduction and Selection Monitoring and Evaluation Pollution Control Demonstration (M&E), Capacity Development and Knowledge Management (KM) Consultant GDAPC-CS1807 / Geological Livestock Waste Management Pending IBRD / 83110 Post Qualification Open - National 290,000.00 0.00 2018-08-15 2018-09-05 2018-10-12 2018-11-11 2018-12-16 2019-11-07 exploration unit for project farms (LWM) Implementation Selection Monitoring and Evaluation GDAPC-CS1805 / Determination Consultant (M&E), Capacity Development Pending of utilization rate of pesticides in IBRD / 83110 Post Qualification Open - National 80,000.00 0.00 2018-06-15 2018-07-06 2018-08-19 2018-09-18 2018-10-23 2019-12-31 and Knowledge Management Implementation project areas Selection (KM) Monitoring and Evaluation GDAPC-CS1806 / Determination Consultant (M&E), Capacity Development Pending of utilization rate of fertilizer in IBRD / 83110 Post Qualification Open - National 80,000.00 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-23 2018-10-28 2019-12-31 and Knowledge Management Implementation project areas Selection (KM) GDAPC-CS1704 / Pilot study on Monitoring and Evaluation comprehensive control of non- Consultant (M&E), Capacity Development Under point source pollution and IBRD / 83110 Post Qualification Open - National 298,000.00 0.00 2018-07-15 2018-05-21 2018-08-05 2018-05-23 2018-09-18 2018-10-18 2018-11-22 2020-12-31 and Knowledge Management Implementation upgrading of industrial chain in Selection (KM) small area (For rice) Page 2 GDAPC-CS1706 / Pilot study on Monitoring and Evaluation comprehensive control of non- Consultant (M&E), Capacity Development Under point source pollution and IBRD / 83110 Post Qualification Open - National 298,000.00 0.00 2018-07-15 2018-05-21 2018-08-05 2018-05-23 2018-09-18 2018-10-18 2018-11-22 2020-12-31 and Knowledge Management Implementation upgrading of industrial chain in Selection (KM) small area (For vegetable) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3