Ayeyarwady Integrated River Basin Management (AIRBM) Project Procurement Plan I. GENERAL 1. Project information a. Country/Borrower: Myanmar b. Project Implementing Agency: Ministry of Transport (Directorate for Water Resources and Improvement of River Systems) 2. Bank’s approval Date of the procurement Plan a. Original Plan: October 24, 2014 b. Revised Plan September 7, 2015 c. Revised Plan: November 11, 2015 d. Revised Plan: February 26, 2016 e. Revised Plan: August 4, 2016 f. Revised Plan: November 28, 2016 g. Revised Plan: March 21, 2017 3. Date of General Procurement Notice: a. Date : 18 February 2015 II. Type of Procurement. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Market Approaches Thresholds Prior Review Procurement International National-Open National RFQ Comments Threshold (Shopping) Works (Including USD 3m and Less than US$3m Less than Recommended to US$ 2 mil. turnkey supply and above US$1m advertise for 7 days for installation of plant RFQ above USD and equipment) 50,000. Goods, information USD 1m and Less than US$1m Less than Recommended to US$ 1 mil. technology and above US$0.5m advertise for 7 days for non-consulting RFQ above USD services 50,000. Consultants USD 0.1m and Less than Not applicable CQS method may be US$ 0.3 mil. (Firms) above US$0.1m used up to USD 500,000. Use of full RFP mandatory for CQS above USD 300,000. Limits on market approaches do not apply to individual consultants. Consultant US$ 0.2 mil. (Individuals) 1 PROCUREMENT Myanmar : Ayeyarwady Integrated River Basin Management Project PLAN General Information Country: Myanmar Bank’s Approval Date of the Original Procurement Plan: 2016-08-24 2019-07-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146482 GPN Date: Project Name: Ayeyarwady Integrated River Basin Management Project Loan / Credit No: IDA / 55590 Executing Agency(ies): Directorate Of Water Resources and Improvement of River Systems WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CW2-1 / Meeting Room Request for Single Stage - One Upgrade, DMH Yangon IDA / 55590 Post Open - National 47,524.58 Completed 2017-03-05 2017-04-30 2017-10-27 Quotations Envelope Office CW1-1-2 / Demolition of Request for Single Stage - One IDA / 55590 Post Open - National 2,603.61 Signed 2016-01-05 2016-03-01 2016-08-28 DWIR Building Quotations Envelope CW1-1-3 / Renovation of Request for Single Stage - One IDA / 55590 Post Open - National 85,639.39 Signed 2016-02-05 2016-04-01 2016-09-28 DWIR Building Quotations Envelope CW1-3 / PMU Building Car IDA / 55590 Post Direct Selection Direct 2,667.14 Signed 2017-09-30 2017-09-30 2017-10-21 2017-11-30 Parking CW3-1-5A / DWIR Micro- Project in Bagan, Nyaung U IDA / 55590 Post Force Account Direct 114,265.00 Signed 2016-04-01 2016-04-01 2016-04-01 2016-04-01 Groynes CW3-1-5B / DWIR Micro- Project in Bagan, Nyaung U IDA / 55590 Post Force Account Direct 246,000.00 Signed 2016-04-01 2016-04-01 2016-04-01 2016-04-01 Dredging CW3-1-5C / DWIR Micro- Project in Bagan, Nyaung U IDA / 55590 Post Force Account Direct 264,000.00 Signed 2016-04-07 2016-04-07 2016-04-07 2016-04-07 Dredging CW3-1-5D / DWIR Micro- IDA / 55590 Post Force Account Direct 246,000.00 Signed 2016-04-07 2016-04-07 2016-04-07 2016-04-07 Project, Pakkoku Dredging CW3-1-5E / DWIR Micro- IDA / 55590 Post Force Account Direct 236,836.00 Signed 2016-05-30 2016-05-30 2016-05-30 2016-05-30 Project, Pakkoku Dredging Pending CW3-1-5F / DWIR Micro- IDA / 55590 Post Force Account Direct 0.00 Implementati 2017-02-02 2017-02-02 2017-02-02 2017-02-02 Project, Mandalay Dredging on Pending CW3-1-5G / DWIR Micro- IDA / 55590 Post Force Account Direct 0.00 Implementati 2017-06-02 2017-06-02 2017-06-02 2017-06-02 Project, Mandalay Dredging on CW1-1-1REVISED / PMU Request for Single Stage - One IDA / 55590 Post Open - National 1,188,755.48 Completed 2017-09-30 2017-09-30 2017-09-30 Building Quotations Envelope Open - Single Stage - One CW1-1-1 / PMU Building IDA / 55590 Prior Request for Bids 0.00 Canceled 2017-12-31 2017-12-31 2017-12-31 2017-12-31 2018-01-21 2018-07-20 International Envelope CW3-2 / Renovation of Request for Single Stage - One IDA / 55590 Post Open - National 26,346.44 Completed 2018-01-03 2018-02-28 2018-08-27 DWIR Mandalay Office Quotations Envelope Page 1 CW3-1 / River Bank Request for Single Stage - One IDA / 55590 Post Open - National 825,216.13 Signed 2018-02-15 2018-04-12 2018-10-09 Protection for Sub Project 1 Quotations Envelope Under CW3-1-5H / Micro Project IDA / 55590 Post Force Account Direct 0.00 Implementati 2018-02-28 2018-02-28 2018-02-28 2018-02-28 in Nyaung Oo on Under CW3-1-5I / Micro Project in IDA / 55590 Post Force Account Direct 0.00 Implementati 2018-02-28 2018-02-28 2018-02-28 2018-02-28 Pakkoku on CW3-3 / Hydraulic Single Stage - One IDA / 55590 Prior Request for Bids Open - National 2,185,602.77 Signed 2018-04-12 2018-04-17 2018-05-17 2018-06-16 2018-07-21 2019-01-17 Structure for Sub Project 1 Envelope CW1-2 / Municipal Water Supply Connection and Tank IDA / 55590 Post Direct Selection Direct 2,672.59 Signed 2018-09-30 2018-10-05 2018-11-09 2019-05-08 for PMU Building CW2-2 / Refurbishment/renovation of the 5 regional support Under Request for Single Stage - One centers (in Kalewa, IDA / 55590 Post Open - National 0.00 Implementati 2018-12-20 2019-02-14 2019-08-13 Quotations Envelope Mandalay, Mawlamyaing, on Pathein, Myintkyina) and the MHEWC (in NPT) CW3-1-5 J / Microproject Pending for Aung Pan Chaung to Sin IDA / 55590 Post Force Account Direct 0.00 Implementati 2018-01-30 2018-01-30 2018-01-30 2018-01-30 Min Waterway (Balaba) on CW1-5 / Construction of Open - Single Stage - One Under NWRC HQ and HIC IDA / 55590 Prior Request for Bids 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 International Envelope Review Building GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G1-4-2 / DWIR Office Request for Single Stage - One IDA / 55590 Post Limited 40,168.21 Completed 2016-02-06 2016-04-02 2016-09-29 Equipment ( Yangon Office) Quotations Envelope G1-8 / Office Request for Single Stage - One Upgrade/Maintenance : WiFi IDA / 55590 Post Limited 6,057.12 Completed 2016-07-06 2016-08-31 2017-02-27 Quotations Envelope Installation at DWIR G2-2 / ADCP Flow meters Request for Single Stage - One IDA / 55590 Post Limited 175,000.00 Completed 2016-12-06 2017-01-31 2017-07-30 and associated equipment Quotations Envelope Request for Single Stage - One G1-9 / Vehicles IDA / 55590 Prior Open - National 168,803.98 Completed 2016-11-07 2017-01-18 2017-07-17 Quotations Envelope G3-1 / Speed Request for Open - Single Stage - One Boats/Hydrographic Survey IDA / 55590 Prior 225,500.00 Completed 2016-12-06 2017-01-31 2017-07-30 Quotations International Envelope Boats G3-2 / Topo-Hydrographic survey equipment, satellite Request for Single Stage - One images and maps, including IDA / 55590 Prior Open - National 789,237.00 Signed 2016-10-06 2016-12-19 2017-06-17 Quotations Envelope installation of equipment and training in surveying Page 2 G3-3 / Supply and Delivery Open - Single Stage - One IDA / 55590 Prior Request for Bids 1,716,855.12 Signed 2017-01-01 2017-01-06 2017-02-17 2017-03-19 2017-04-23 2017-10-20 of Aids to Navigation International Envelope G3-4 / Multifunctional and Open - Single Stage - One IDA / 55590 Prior Request for Bids 2,100,000.00 Signed 2017-02-01 2017-02-06 2017-03-20 2017-04-19 2017-05-24 2017-11-20 Buoy Handling vessel International Envelope G3-5 / Amphibious multi- Open - Single Stage - One IDA / 55590 Prior Request for Bids 1,551,999.00 Signed 2017-02-01 2017-02-06 2017-03-20 2017-04-19 2017-05-24 2017-11-20 purpose dredger International Envelope G3-6 / WiFi Connection to Request for Single Stage - One IDA / 55590 Post Open - National 4,081.86 Signed 2017-04-05 2017-05-31 2017-11-27 DWIR Mandalay Office Quotations Envelope G3-7 / Office Furniture for Request for Single Stage - One IDA / 55590 Post Open - National 4,681.14 Completed 2017-04-05 2017-05-31 2017-11-27 DWIR Mandalay Office Quotations Envelope G1-10 / PMU Data Request for Single Stage - One Network Infrastructure - IDA / 55590 Post Open - National 75,587.62 Completed 2017-02-15 2017-04-12 2017-10-09 Quotations Envelope Hardware and Software G1-4-3 / DWIR Office Request for Single Stage - One IDA / 55590 Post Open - National 27,389.42 Completed 2016-02-28 2016-06-03 2016-07-31 Furniture for Yangon Office Quotations Envelope Request for Single Stage - One G1-6 / Accounting Software IDA / 55590 Post Open - National 16,871.81 Signed 2016-02-26 2016-06-06 2016-07-06 Quotations Envelope G1-7 / Fiber Cable Installation and Transmission for Data IDA / 55590 Post Direct Selection Direct 2,049.12 Signed 2016-06-01 2016-06-01 2016-06-16 2016-06-16 Network for PMU and DWIR Office G2-1-1 / DMH Office Request for Single Stage - One Equipment for Nay Pyi Taw IDA / 55590 Post Open - National 20,143.35 Completed 2016-01-30 2016-03-31 2016-03-31 Quotations Envelope and Yangon Office G2-1-4 / DMH Office Request for Single Stage - One Furniture for Nay Pyi Taw IDA / 55590 Post Open - National 14,876.87 Signed 2016-02-28 2016-06-03 2016-07-29 Quotations Envelope and Yangon Office Request for Single Stage - One G2-1-3 / Generators IDA / 55590 Post Open - National 26,757.13 Signed 2016-06-07 2017-02-07 2017-03-31 Quotations Envelope G1-11 / Server Desktop and Request for Single Stage - One IDA / 55590 Post Open - National 16,086.97 Signed 2017-09-05 2017-10-31 2018-04-29 Accessories for PMU Office Quotations Envelope G2-1 / Fiber Cable Installation and Request for Single Stage - One Transmission for Data IDA / 55590 Post Open - National 18,339.34 Completed 2017-03-05 2017-04-30 2017-10-27 Quotations Envelope Network for DMH Office in NayPyiTaw G1-12 / Office Furniture for Request for Single Stage - One interim NWRC HQ/HIC IDA / 55590 Post Open - National 9,335.80 Signed 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Building G1-13 / Office Equipment Request for Single Stage - One for interim NWRC HQ/HIC IDA / 55590 Post Open - National 7,738.91 Signed 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Building G1-14 / Data Network Under Cabling, Sever, Desktop and Request for Single Stage - One IDA / 55590 Post Open - National 0.00 Implementati 2018-02-06 2018-04-03 2018-09-30 Accessories for interim Quotations Envelope on NWRC HQ/HIC Building Page 3 G1-15 / Internet Connection for interim NWRC HQ/HIC IDA / 55590 Post Direct Selection Direct 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-09-09 Building G3-9 / Hydraulic Structures Single Stage - One IDA / 55590 Prior Request for Bids Open - National 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-16 2018-12-21 2019-06-19 for Sub Project 1 Envelope G1-16 / Furniture for PMU Request for Single Stage - One IDA / 55590 Post Open - National 91,351.46 Signed 2018-09-06 2018-11-01 2019-04-30 Building Quotations Envelope G1-17 / Equipment for Request for Single Stage - One IDA / 55590 Post Open - National 21,155.96 Signed 2018-09-06 2018-11-01 2019-04-30 PMU Building Quotations Envelope G2-3 / Upper-air Radio Open - Single Stage - One IDA / 55590 Prior Request for Bids 0.00 Canceled 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 2019-05-20 Sounding Equipment International Envelope G2-4 / Automatic Weather Open - Single Stage - One Under stations and associated IDA / 55590 Prior Request for Bids 0.00 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 2019-05-20 International Envelope Review equipment G2-5 / Calibration lab Under Request for Single Stage - One equipment and Electronic IDA / 55590 Post Open - National 0.00 Implementati 2018-08-06 2018-10-01 2019-03-30 Quotations Envelope test equipment on G2-6 / River monitoring Open - Single Stage - One IDA / 55590 Prior Request for Bids 0.00 Canceled 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 2019-05-20 equipment International Envelope G2-8 / Supply and Request for Single Stage - One installation of river level IDA / 55590 Post Open - National 107,397.39 Signed 2018-08-06 2018-10-01 2019-03-30 Quotations Envelope monitoring stage boards G3-11 / Supply and Open - Single Stage - One Delivery of 2 Fast Transit IDA / 55590 Prior Request for Bids 0.00 Canceled 2018-10-01 2018-10-06 2018-11-17 2018-12-17 2019-01-21 2019-07-20 International Envelope Buoy Handling Vessel G3-12 / Two Cutter Suction Under Open - Single Stage - One Dredgers and Ancillary IDA / 55590 Prior Request for Bids 0.00 Implementati 2018-10-01 2018-10-06 2018-11-17 2018-12-17 2019-01-21 2019-07-20 International Envelope Equipment on G3-14 / Three Aluminium Request for Open - Single Stage - One IDA / 55590 Post 753,420.00 Signed 2018-09-05 2018-10-31 2019-04-29 Hydrographic Survey Boats Quotations International Envelope G3-10A / Supply and Request for Single Stage - One Delivery of Acoustic Doppler IDA / 55590 Post Open - National 175,000.00 Signed 2018-09-08 2018-11-03 2019-05-02 Quotations Envelope Current Profiler G3-10REVISED / Supply and Delivery of Topo- Hydrographic Survey Request for Open - Single Stage - One IDA / 55590 Post 614,890.00 Signed 2018-09-08 2018-11-03 2019-05-02 Equipment for the Stretch Quotations International Envelope Between Nyaung Oo and Yangon G2-3REVISED / Upper Air Request for Open - Single Stage - One IDA / 55590 Post 0.00 Canceled 2018-09-08 2018-11-03 2019-05-02 Radio Sounding Equipment Quotations International Envelope Under G2-7 / River Survey Boats- Request for Single Stage - One IDA / 55590 Post Open - National 0.00 Implementati 2018-09-19 2018-11-14 2019-05-13 3 Units Quotations Envelope on G2-3REVISED-FINAL / Under Open - Single Stage - One Upper Air Radio Sounding IDA / 55590 Post Request for Bids 0.00 Implementati 2018-09-30 2018-10-05 2018-11-16 2018-12-16 2019-01-20 2019-07-19 International Envelope Equipment on Page 4 Under G2-6REVISED / River Request for Open - Single Stage - One IDA / 55590 Post 0.00 Implementati 2018-10-10 2018-12-05 2019-06-03 Monitoring Equipment Quotations International Envelope on G2-10 / Automatic water Open - Single Stage - One IDA / 55590 Prior Request for Bids 0.00 Canceled 2018-11-30 2018-12-05 2019-01-16 2019-02-15 2019-03-22 2019-09-18 level recording Equipment International Envelope G2-11 / Forecaster Under Workstations, Printers and Request for Single Stage - One IDA / 55590 Post Open - National 0.00 Implementati 2018-12-06 2019-01-31 2019-07-30 Automated Desktop Quotations Envelope on Deployment System G2-12 / Special furniture Under for the Forecast Operations Request for Single Stage - One IDA / 55590 Post Open - National 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 Centre and 5 regional Quotations Envelope on support centers G2-14 / Cloud computing Pending and other equipment to Request for Single Stage - One IDA / 55590 Post Open - National 0.00 Implementati 2018-12-06 2019-01-31 2019-07-30 provide resilience to DMH Quotations Envelope on systems, Yangon G2-15 / NPT Datacentre and Forecast Operations Open - Single Stage - One IDA / 55590 Prior Request for Bids 0.00 Canceled 2018-12-01 2018-12-06 2019-01-17 2019-02-16 2019-03-23 2019-09-19 Centre renovation,equipment International Envelope and related-services Pending G2-19 / Data Hub Server IDA / 55590 Post Direct Selection Direct 0.00 Implementati 2018-11-30 2018-12-05 2019-01-09 2019-07-08 with Harddrives and UPS on G2-20 / NPT-MDY-YGN Pending Request for Single Stage - One Internet capacity Upgrade IDA / 55590 Post Open - National 0.00 Implementati 2018-12-06 2019-01-31 2019-07-30 Quotations Envelope with Redundancy on G2-9 / Vehicles, 4WD Pick- Request for Single Stage - One IDA / 55590 Post Open - National 0.00 Canceled 2018-12-05 2019-01-30 2019-07-29 up, 3.nos Quotations Envelope Under G1-18 / Internet Bandwidth IDA / 55590 Post Direct Selection Direct 0.00 Implementati 2018-12-17 2018-12-22 2019-01-26 2019-07-25 Upgrading in PMU Building on G2-13 / NPT Data centre Under and Forecast Operations Open - Single Stage - One IDA / 55590 Prior Request for Bids 0.00 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2019-10-08 Centre set up and backend International Envelope on ICT infrastructure G2-10REVISED / Automatic Under Open - Single Stage - One Water Level Recording IDA / 55590 Post Request for Bids 0.00 Implementati 2019-01-18 2019-01-23 2019-03-06 2019-04-05 2019-05-10 2019-11-06 International Envelope Equipment (AWLR) on G3-11REVISED / Supply Under Open - Single Stage - One and Delivery of Fast Transit IDA / 55590 Prior Request for Bids 0.00 Implementati 2019-05-28 2019-06-02 2019-07-14 2019-08-13 2019-09-17 2020-03-15 International Envelope Buoy Handling Vessels on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S1-1 / PMU Website Request for Single Stage - One IDA / 55590 Post Open - National 714.55 Signed 2016-11-23 2016-12-07 2017-06-05 Developer Quotations Envelope Page 5 Under S3-1 / Hydrographic Survey IDA / 55590 Post Force Account Direct 0.00 Implementati 2017-01-31 2017-01-31 2017-01-31 2017-01-31 Stretch 1 on S2-1 / Flow Surveys and IDA / 55590 Post Force Account Direct 59,700.00 Signed 2016-09-30 2016-09-30 2016-09-30 2016-09-30 Rating Review S2-2REVISED / Topographic Request for Single Stage - One Survey Firm to Support IDA / 55590 Post Open - National 49,400.64 Signed 2017-05-30 2017-07-25 2018-01-21 Quotations Envelope Flow Survey S2-2 / Topographic Survey Request for Single Stage - One Firm to Support Flow IDA / 55590 Post Open - National 0.00 Canceled 2017-03-05 2017-04-30 2017-10-27 Quotations Envelope Survey S3-2 / Installation of Aids IDA / 55590 Post Force Account Direct 132,510.08 Signed 2017-12-31 2017-12-31 2017-12-31 2017-12-31 to Navigation S2-3 / River Surveys and Very High Resolution Request for Single Stage - One Satellite Data for Central IDA / 55590 Post Open - National 131,334.71 Signed 2018-08-06 2018-10-01 2019-03-30 Quotations Envelope and Upper Myanmar (4 areas) S3-3 / Conducting the Under Hydrographic Survey Request for Single Stage - One IDA / 55590 Post Open - National 1,053,000.00 Implementati 2018-08-06 2018-10-01 2019-03-30 between Nyaung U and Quotations Envelope on Yangon S3-5 / Installation of Benchmarks from Nyaung U IDA / 55590 Prior Force Account Direct 0.00 Canceled 2018-08-06 2018-08-06 2018-08-06 2018-08-06 to Yangon S3-5REVISED / Installation of Benchmarks from Nyaung IDA / 55590 Post Force Account Direct 40,029.87 Signed 2018-09-14 2018-09-14 2018-09-14 2018-09-14 Oo to Yangon Under S2-4 / WMO agreement IDA / 55590 Prior Direct Selection Direct 0.00 Implementati 2018-12-15 2018-12-20 2019-01-24 2019-07-23 on S1-2 / Development of Pending Request for Single Stage - One Myanmar Official Water IDA / 55590 Post Open - National 0.00 Implementati 2019-08-20 2019-10-15 2019-12-14 Quotations Envelope Portal on S3-6 / Installation of Aids Pending to Navigation (Nyaung Oo to IDA / 55590 Post Force Account Direct 0.00 Implementati 2020-03-30 2020-04-04 2020-05-09 2020-11-05 Yangon) on S3-4 / Additional surveys Request for Single Stage - One under the Engineering Study IDA / 55590 Post Open - National 0.00 Canceled 2018-09-06 2018-11-01 2019-04-30 Quotations Envelope for Stretch 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1.4-21 / Design and Consultant Open - Construction Supervision of IDA / 55590 Prior Qualification 78,170.00 Completed International DWIR Building Selection Page 6 C1-17 / Ayeyarwady Master Quality And Cost- Open - Plan and Decision Support IDA / 55590 Prior 7,833,571.61 Signed 2016-10-24 2016-11-14 2016-12-28 2017-01-25 2017-02-24 2017-03-31 2017-05-05 2018-05-05 Based Selection International System C2-2 / DMH System Quality And Cost- Open - IDA / 55590 Prior 3,522,146.73 Signed 2016-11-16 2016-12-07 2017-01-20 2017-02-17 2017-03-19 2017-04-23 2017-05-28 2018-05-28 Integrator Based Selection International C3-3 / ESIA/SEA/EMP Consultant Open - Supervision for Subproject 1 IDA / 55590 Prior Qualification 416,368.00 Signed 2016-04-27 2016-05-18 2016-08-24 2016-11-30 2017-01-04 2017-07-03 International and Stretch 1 Selection C1-12 / SOB Package 2: Consultant Open - Groundwater and data IDA / 55590 Prior Qualification 227,553.00 Signed 2016-05-10 2016-06-21 2016-07-26 2016-11-25 2016-12-30 2017-06-28 International management Selection Consultant C1-13 / SOB Package 3: Open - IDA / 55590 Prior Qualification 237,567.45 Signed 2016-05-10 2016-06-21 2016-07-26 2016-11-25 2016-12-30 2017-06-28 Sediments & geomorphology International Selection Consultant C1-14 / SOB Package 4: Open - IDA / 55590 Prior Qualification 269,945.38 Signed 2016-05-10 2016-06-21 2016-10-14 2016-12-30 2017-02-03 2017-08-02 Biodiversity & Fisheries International Selection C1-15 / SOB Package 5: Consultant Open - Sectoral development and IDA / 55590 Prior Qualification 245,680.00 Signed 2016-05-10 2016-06-21 2016-07-26 2016-11-25 2016-12-30 2017-06-28 International macroeconomics Selection C1-16 / SOB Package 6: Consultant Open - 3D Mapping and local IDA / 55590 Prior Qualification 344,425.00 Signed 2016-05-10 2016-06-21 2016-07-26 2016-11-25 2016-12-30 2017-06-28 International consultations Selection C1-19REVISED / Quality And Cost- Open - HIC/NWRC Building Design IDA / 55590 Prior 1,533,487.90 Signed 2017-05-25 2017-06-15 2017-07-29 2017-08-26 2017-09-25 2017-10-30 2017-12-04 2018-12-04 Based Selection International and Construction Supervision C3-13 / Feasibility Study, Engineering design, Capacity Quality And Cost- Open - IDA / 55590 Prior 2,445,385.26 Signed 2017-08-31 2017-09-21 2017-11-04 2017-12-02 2018-01-01 2018-02-05 2018-03-12 2019-03-12 Building and Construction Based Selection International Supervision for Stretch1 C3-14 / ESIA,ESMP and Quality And Cost- Open - ARAPs Implementation IDA / 55590 Prior 817,075.00 Signed 2017-08-31 2017-09-21 2017-11-04 2017-12-02 2018-01-01 2018-02-05 2018-03-12 2019-03-12 Based Selection International Support for Stretch 1 C1-19 / Architectural and Engineering Design and Quality And Cost- Open - IDA / 55590 Prior 0.00 Canceled 2017-03-31 2017-04-21 2017-06-04 2017-07-02 2017-08-01 2017-09-05 2017-10-10 2018-10-10 Construction Supervision of Based Selection International the NWRC HQ/HIC C2-8 / Design and Construction Supervision of Consultant New Building in NPT and IDA / 55590 Post Qualification Open - National 183,573.00 Signed 2018-04-01 2018-04-22 2018-06-05 2018-07-05 2018-08-09 2019-02-05 Renovation of Buildings in Selection NPT and Yangon C2-9 / Impact Based Forecasting Pilots and Flood Quality And Cost- Open - Hazard Mapping in the IDA / 55590 Prior 0.00 Under Review 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 Based Selection International Chindwin and Central Ayeyarwady Basin, Myanmar C2-11 / ACAS Coordination Consultant Open - Under and Development of Agro IDA / 55590 Prior Qualification 0.00 2018-08-20 2018-09-10 2018-10-24 2018-11-23 2018-12-28 2019-06-26 International Implementation Meteorological Products Selection Page 7 C2-24 / Update of the Myanmar Climate Change Consultant Alliance documentation with Pending IDA / 55590 Post Qualification Open - National 0.00 2018-12-01 2018-12-22 2019-02-04 2019-03-06 2019-04-10 2019-10-07 new outputs from DMH on Implementation Selection climate trends and projections C3-17 / Formulation of the Navigation Strategy and Quality And Cost- Open - IDA / 55590 Prior 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 Action Plan, including Fleet Based Selection International Optimization C1-32 / Feasibility Study Quality And Cost- Open - Pending on Navigation Enhancement IDA / 55590 Post 0.00 2019-03-29 2019-04-19 2019-06-02 2019-06-30 2019-07-30 2019-09-03 2019-10-08 2020-10-07 Based Selection International Implementation Work for Stretch 2 C1-33 / ESIA and ESMP Consultancy Service for Consultant Open - Pending Feasibility Study on IDA / 55590 Post Qualification 0.00 2019-03-29 2019-04-19 2019-06-02 2019-07-02 2019-08-06 2020-02-02 International Implementation Navigation Enhancement Selection Work For Stretch 2 C3-17REVISED / Formulation of the Resource Consultant Open - Under Management and Operation IDA / 55590 Post Qualification 0.00 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 International Implementation Plan for Ayeyarwady Selection Navigation - RMOP C1-35 / Yangon Region Quality And Cost- Open - Pending IWRM Project Feasibility IDA / 55590 Post 0.00 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection International Implementation Study INDIVIDUAL CONSULTANTS Page 8