The World Bank Implementation Status & Results Report Saramacca Canal System Rehabilitation Project (P165973) Saramacca Canal System Rehabilitation Project (P165973) LATIN AMERICA AND CARIBBEAN | Suriname | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 1 | ARCHIVED on 01-May-2019 | ISR36820 | Implementing Agencies: Ministry of Finance (MoF), Ministry of Public Works, Transport and Communication (MoPWTC) Key Dates Key Project Dates Bank Approval Date: 14-Feb-2019 Effectiveness Date: -- Planned Mid Term Review Date: -- Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2024 Revised Closing Date: 31-Dec-2024 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to reduce flood risk for the people and assets in the greater Paramaribo area and improve the operation of the Saramacca Canal System. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Improving the Drainage Infrastructure:(Cost $29.00 M) Strengthening the Saramacca Canal System:(Cost $3.00 M) Providing a Contingent Emergency Response:(Cost $0.41 M) Supporting Project Management and Implementation:(Cost $2.50 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Satisfactory Overall Risk Rating -- Substantial Implementation Status and Key Decisions The project was approved by the World Bank Board of Directors on February 14, 2019. The Government and the World Bank team are working together towards a prompt declaration of effectiveness of the project. As soon as the project is declared effective, a project launch will be organized in Suriname. 5/1/2019 Page 1 of 6 The World Bank Implementation Status & Results Report Saramacca Canal System Rehabilitation Project (P165973) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial -- Substantial Macroeconomic Substantial -- Substantial Sector Strategies and Policies Moderate -- Moderate Technical Design of Project or Program Moderate -- Moderate Institutional Capacity for Implementation and Sustainability High -- High Fiduciary High -- High Environment and Social Substantial -- Substantial Stakeholders Moderate -- Moderate Other Moderate -- Moderate Overall Substantial -- Substantial Results PDO Indicators by Objectives / Outcomes Reduce flood risk for the people living in the Greater Paramaribo area IN00695506 ►Number of people benefitting from reduced flood risk for a 10-year return period. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 57,000.00 Date 14-Feb-2019 -- 24-Apr-2019 31-Dec-2024 Number of people benefiting from reduced flood risk in relation to the number of working flood gates for a Comments: specific return period (10-year return period). IN00695508 Number of female beneficiaries benefitting from reduced flood risk for a 10-year return period. (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Improve the operation of the Saramacca Canal System for flood risk management and navigation IN00695475 ►Introduction of a risk-based maintenance system for the drainage of the Saramacca Canal System (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target 5/1/2019 Page 2 of 6 The World Bank Implementation Status & Results Report Saramacca Canal System Rehabilitation Project (P165973) Value No -- No Yes Date 14-Feb-2019 -- 24-Apr-2019 31-Dec-2024 Comments: Baseline: Non-integrated, mechanical, partially operational system. IN00695507 ►Increased flood forecast lead time for the Saramacca Canal System (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value -12.00 -- 12.00 4.00 Date 14-Feb-2019 -- 24-Apr-2019 31-Dec-2024 Just-in-time or post-flood event management with a delay of up to 12 hours for release of water due to Comments: nonfunctioning gate and sluice operation and tidal conditions Intermediate Results Indicators by Components Improving the Drainage Infrastructure IN00695509 ►Engineering design completed for the works for the improved capacity of the Saramacca Canal to discharge water into the Suriname and Saramacca Rivers (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 14-Feb-2019 -- 24-Apr-2019 31-Dec-2024 The engineering design, including the bill of quantities and the bidding documents, for the improvements Comments: of the main infrastructure of the Saramacca canal are finalized IN00695511 ►Improved capacity of the Saramacca Canal to discharge water into the Suriname and Saramacca Rivers (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 38.00 -- 38.00 100.00 Date 25-Jul-2018 -- 24-Apr-2019 31-Dec-2024 Baseline is 38 percent: Based on the average of Suriname River side -(a) one working lock gate out of two (50 percent operational capacity) and (b) three working sluice gates out of five (60 percent operational Comments: capacity); Saramacca River side -(a) one working lock gate out of two (50 percent operational capacity) and (b) zero working sluice gates out of four (0 percent operational capacity). IN00695513 ►Improved functioning of the Saramacca Canal for navigation (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 2.00 -- 2.00 12.00 Date 25-Jul-2018 -- 24-Apr-2019 31-Dec-2024 Comments: Number of hours that the canal operates for navigation IN00695514 5/1/2019 Page 3 of 6 The World Bank Implementation Status & Results Report Saramacca Canal System Rehabilitation Project (P165973) ►Area with increased drainage capacity for a 10-year return period (Square kilometer(km2), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 70.00 Date 25-Jul-2018 -- 24-Apr-2019 31-Dec-2024 Number of square kilometers with increased drainage capacity for a 10-year return period in the Comments: Saramacca Canal catchment area IN00695515 ►Number of engaging information events on the implementation of the activities to improve the Saramacca Canal conveyance (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5.00 Date 14-Feb-2019 -- 24-Apr-2019 31-Dec-2024 The preparation of the events and campaigns will considerer venues, timing, and discussion dynamics that effectively enable the participation of both women and men. Given the ample diversity of Suriname’s Comments: citizens’ origin, the approach will also be mindful of the needed adjustments to encourage participation from all backgrounds. IN00695516 ►Number of beneficiaries consulted on the proposed project designs, associated environmental and social impacts, and envisaged mitigation measures (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 200.00 Date 14-Sep-2018 -- 24-Apr-2019 31-Dec-2023 The preparation of the events and campaigns will considerer venues, timing, and discussion dynamics that effectively enable the participation of both women and men. Given the ample diversity of Suriname’s Comments: citizens’ origin, the approach will also be mindful of the needed adjustments to encourage participation IN00695517 from all backgrounds. Number of female beneficiaries consulted on the proposed project designs (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 IN00695518 ►Secondary and Tertiary canal system baseline and prioritization for pilot works developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 14-Feb-2019 -- 24-Apr-2019 31-Dec-2024 Secondary and Tertiary canal system baseline and prioritization criteria for pilot works are collected and Comments: defined IN00695519 ►Interventions for the selected pilot works to improve localized drainage completed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes 5/1/2019 Page 4 of 6 The World Bank Implementation Status & Results Report Saramacca Canal System Rehabilitation Project (P165973) Date 14-Feb-2019 -- 24-Apr-2019 31-Dec-2024 Interventions for the selected pilot works to improve localized drainage are completed based on the Comments: prioritization criteria defined Strengthening the Saramacca Canal Water Management System IN00695510 ►Updated guidelines and operational procedures for managing flood control and navigation of the Saramacca Canal drainage system (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 14-Feb-2019 -- 24-Apr-2019 31-Dec-2024 Guidelines and operational procedures for managing the Saramacca Canal drainage system will be Comments: updated reflecting the overall improvements of project financed infrastructure and capacity for flood control and navigation IN00695512 ►Endorsement of the feasibility study toward the establishment of a Saramacca Canal System management platform (or similar mechanism responsible) for the system sustainability (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 25-Jul-2018 -- 24-Apr-2019 31-Dec-2024 Feasibility study toward the establishment of a Saramacca Canal System management platform (or similar Comments: mechanism responsible) for the system sustainability Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Not P165973 IBRD-89240 USD 35.00 35.00 0.00 0.00 35.00 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P165973 IBRD-89240 14-Feb-2019 11-Apr-2019 -- 31-Dec-2024 31-Dec-2024 Effective Cumulative Disbursements 5/1/2019 Page 5 of 6 The World Bank Implementation Status & Results Report Saramacca Canal System Rehabilitation Project (P165973) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/1/2019 Page 6 of 6