Rural & Urban Access Improvement Project (P160359) Procurement Plan Country: Nicaragua Region: LATIN AMERICA AND CARIBBEAN Approval Date: 06-Mar-2017 July 9, 2010 PROCUREMENT Nicaragua : Rural and Urban Access Improvement Project PLAN General Information Country: Nicaragua Bank’s Approval Date of the Original Procurement Plan: 2017-06-08 2020-02-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160359 GPN Date: 2017-06-19 Project Name: Rural and Urban Access Improvement Project Loan / Credit No: IDA / 59640, IDA / 59630, IDA / 62010 Executing Agency(ies): Ministry of Transport and Infrastructure WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NI-MTI-16136-CW-FCA / Participación de Component 1: Road Adoquinado camino Granada IDA / 59630 Posterior la comunidad en Direct 288,000.00 673,235.50 Firmado 2018-02-02 2018-02-07 2018-03-14 2018-09-10 Infrastructure Improvement - Malacatoya MCA 1 las adquisiciones NI-MTI-17805-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 673,759.26 Firmado 2017-10-30 2017-11-03 2017-12-08 2018-06-06 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 01. NI-MTI-17808-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 673,758.14 Firmado 2018-01-10 2018-01-15 2018-02-19 2018-08-17 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 02. NI-MTI-17810-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 673,742.49 Firmado 2017-10-30 2017-11-03 2017-12-08 2018-06-06 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 03. NI-MTI-17811-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 673,751.71 Firmado 2018-01-08 2018-01-12 2018-02-16 2018-08-15 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 04. NI-MTI-17821-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 673,740.37 Firmado 2018-01-10 2018-01-15 2018-02-19 2018-08-17 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 05. NI-MTI-17827-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 673,758.44 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 06. NI-MTI-17829-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 657,371.01 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 07. NI-MTI-17831-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 653,132.03 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 08. Page 1 NI-MTI-17833-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 656,913.13 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 09. NI-MTI-17836-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 670,749.69 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 10. NI-MTI-17837-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 667,292.90 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 11. NI-MTI-17839-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 660,800.40 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 12. NI-MTI-17841-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 644,426.91 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 13. NI-MTI-17843-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 605,797.48 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 14. NI-MTI-17846-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 563,563.68 Firmado 2018-02-02 2018-02-07 2018-03-14 2018-09-10 Infrastructure Improvement Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 15. NI-MTI-17847-CW-DIR / Adoquinado del Camino La Participación de Component 1: Road Ejecución Libertad - San Pedro de IDA / 59630 Posterior la comunidad en Direct 182,400.00 0.00 2018-02-02 2018-02-07 2018-03-14 2018-09-10 Infrastructure Improvement pendiente Lóvago Modulo Comunitario las adquisiciones de Adoquinado MCA N°. 16. NI-MTI-17616-CW-FCA / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 644,090.29 Firmado 2017-11-30 2017-12-05 2018-01-09 2018-07-09 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 2 NI-MTI-17614-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 648,147.69 Firmado 2017-11-30 2017-12-05 2018-01-09 2018-07-09 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 3 NI-MTI-17617-CW-FCA / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 656,062.24 Firmado 2017-10-30 2017-11-03 2017-12-08 2018-06-06 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 4 NI-MTI-17619-CW-FCA / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 648,807.51 Firmado 2017-10-30 2017-11-03 2017-12-08 2018-06-06 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 5 Page 2 NI-MTI-17621-CW-FCA / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 630,540.20 Firmado 2017-09-25 2017-09-29 2017-11-03 2018-05-02 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 6 NI-MTI-17622-CW-FCA / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 592,062.13 Firmado 2017-10-31 2017-11-06 2017-12-11 2018-06-09 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 7 NI-MTI-17624-CW-FCA / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 601,300.46 Firmado 2017-10-30 2017-11-03 2017-12-08 2018-06-06 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 8 NI-MTI-17799-CW-FCA / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 613,208.63 Firmado 2017-11-30 2017-12-05 2018-01-09 2018-07-09 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 9 NI-MTI-17800-CW-FCA / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 288,000.00 651,745.20 Firmado 2017-11-30 2017-12-05 2018-01-09 2018-07-09 Granada - Malacatoya MCA Infrastructure Improvement las adquisiciones 10 NI-MTI-17801-CW-FCA / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 539,277.70 Firmado 2017-11-30 2017-12-05 2018-01-09 2018-07-09 Infrastructure Improvement Corn Island MCA 1 las adquisiciones NI-MTI-17802-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 573,201.83 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 1 NI-MTI-17803-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 540,412.20 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 2 NI-MTI-17817-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 551,418.60 Firmado 2018-01-10 2018-01-15 2018-02-19 2018-08-17 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 5 NI-MTI-17818-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 547,901.00 Firmado 2018-01-10 2018-01-15 2018-02-19 2018-08-17 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 6 NI-MTI-17819-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 574,104.07 Firmado 2018-01-10 2018-01-15 2018-02-19 2018-08-17 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 7 NI-MTI-17824-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 570,828.36 Firmado 2018-01-10 2018-01-15 2018-02-19 2018-08-17 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 8 NI-MTI-17825-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 574,534.03 Firmado 2018-01-10 2018-01-15 2018-02-19 2018-08-17 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 9 NI-MTI-17826-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 575,173.06 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 10 Page 3 NI-MTI-17828-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,753.55 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 1 las adquisiciones NI-MTI-17830-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,741.30 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 2 las adquisiciones NI-MTI-17832-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,755.02 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 3 las adquisiciones NI-MTI-17834-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,740.20 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 4 las adquisiciones NI-MTI-17835-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,743.18 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 5 las adquisiciones NI-MTI-17838-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,760.45 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 6 las adquisiciones NI-MTI-17840-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,748.35 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 7 las adquisiciones NI-MTI-17842-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,746.41 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 8 las adquisiciones NI-MTI-17844-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 669,641.64 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 9 las adquisiciones NI-MTI-17845-CW-DIR / Participación de Component 1: Road Adoquinado Camino Camino IDA / 59630 Posterior la comunidad en Direct 168,000.00 673,585.35 Firmado 2018-02-01 2018-02-06 2018-03-13 2018-09-10 Infrastructure Improvement Cárdenas - Colón MCA 10 las adquisiciones NI-MTI-16128-CW-RFB / Mejoramiento de la Component 1: Road Solicitud de Open - Single Stage - One IDA / 59640 Previa 10,960,000.00 14,635,357.17 Firmado 2017-08-14 2017-08-28 2017-10-12 2017-10-23 2017-11-13 2019-05-07 Carretera La Garita - Infrastructure Improvement ofertas International Envelope Empalme Tipitapa NI-MTI-17567-CW-RFB / Mejoramiento de la carretera Component 1: Road Solicitud de Open - Single Stage - One IDA / 59640 Previa 16,530,000.00 26,614,759.13 Firmado 2017-08-02 2017-08-07 2017-09-18 2017-10-18 2017-11-22 2018-05-21 Ciudad Sandino - Mateare Infrastructure Improvement ofertas International Envelope (11.81 Km) NI-MTI-17570-CW-RFB / Component 1: Road Solicitud de Single Stage - One Movimiento de tierra para el IDA / 59640 Posterior Open - National 270,000.00 0.00 Cancelado 2018-03-01 2018-03-06 2018-04-17 2018-05-17 2018-06-21 2018-12-18 Infrastructure Improvement ofertas Envelope camino Corn Island NI-MTI-29189-CW-CDD / Participación de Adoquinado Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 168,000.00 540,959.40 Firmado 2017-11-07 2017-11-27 2017-12-18 2018-06-15 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 11 NI-MTI-29190-CW-CDD / Participación de Adoquinado Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 168,000.00 522,596.34 Firmado 2017-11-07 2017-11-13 2017-12-19 2018-06-18 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 12 Page 4 NI-MTI-17809-CW-DIR / Participación de Adoquinado Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 547,535.25 Firmado 2017-10-30 2017-11-03 2017-12-12 2018-06-10 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 4 NI-MTI-22746-CW-DIR / Component 1: Road Adquisición Ejecución Movimiento de tierra para el IDA / 59640 Previa Direct 270,000.00 0.00 2017-11-07 2017-11-13 2017-12-22 2018-06-20 Infrastructure Improvement directa pendiente camino Corn Island NI-MTI-17572-CW-RFB / Movimiento de tierra para el Component 1: Road Solicitud de Single Stage - One IDA / 59640 Posterior Open - National 2,880,000.00 2,531,481.60 Firmado 2017-12-13 2017-12-19 2018-01-23 2018-02-22 2018-03-29 2018-09-25 camino Macuelizo - Santa Infrastructure Improvement ofertas Envelope María NI-MTI-17577-CW-RFB / Movimiento de tierra para el Component 1: Road Solicitud de Single Stage - One camino La Libertad - San IDA / 59640 Posterior Open - National 2,097,600.00 0.00 En ejecución 2017-11-15 2017-11-20 2018-01-02 2018-02-02 2018-03-12 2018-09-10 Infrastructure Improvement ofertas Envelope Pedro de Lóvago MCA N°. 8- 15 NI-MTI-17575-CW-RFB / Component 1: Road Solicitud de Single Stage - One Movimiento de tierra para el IDA / 59640 Posterior Open - National 3,000,000.00 0.00 En ejecución 2017-11-15 2017-11-21 2018-01-02 2018-02-01 2018-03-08 2018-09-04 Infrastructure Improvement ofertas Envelope camino Cárdenas - Colón NI-MTI-17568-CW-RFB / Movimiento de tierra para el Component 1: Road Solicitud de Single Stage - One camino Granada - IDA / 59640 Posterior Open - National 1,860,000.00 0.00 En ejecución 2017-11-15 2017-11-21 2018-01-02 2018-02-01 2018-03-08 2018-09-04 Infrastructure Improvement ofertas Envelope Malacatoya MCA N° del 1- 10 NI-MTI-17576-CW-RFB / Movimiento de tierra para el Component 1: Road Solicitud de Single Stage - One camino La Libertad - San IDA / 59640 Posterior Open - National 2,097,600.00 0.00 En ejecución 2017-11-15 2017-11-20 2018-01-01 2018-02-01 2018-03-09 2018-09-05 Infrastructure Improvement ofertas Envelope Pedro de Lóvago MCA N°. 1- 7 NI-MTI-17806-CW-DIR / Participación de Adoquinado Camino Camino Component 1: Road IDA / 59630 Posterior la comunidad en Direct 174,000.00 554,042.89 Firmado 2017-11-30 2017-12-05 2018-01-15 2018-07-13 Macuelizo - Santa María Infrastructure Improvement las adquisiciones MCA 3 NI-MTI-95203-CW-RFB / Mejoramiento del camino Component 1: Road Solicitud de Open - Single Stage - One IDA / 62010 Previa 19,750,820.00 0.00 En ejecución 2019-01-16 2019-01-21 2019-03-04 2019-04-03 2019-05-08 2019-11-04 Macuelizo-Santa María Fase Infrastructure Improvement ofertas International Envelope II (19.05 km) NI-MTI-17578-CW-RFB / Obras de adaptación de Component 1: Road Solicitud de Single Stage - One IDA / 59640 Posterior Open - National 3,000,000.00 0.00 Cancelado 2018-04-02 2018-04-06 2018-05-18 2018-06-18 2018-07-23 2019-01-19 puntos vulnerables de la red Infrastructure Improvement ofertas Envelope vial a cambio climático NI-MTI-100886-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 570,530.05 575,321.12 Firmado 2019-02-15 2019-02-20 2019-03-27 2019-09-23 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 5 NI-MTI-100916-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 570,932.51 575,726.96 Firmado 2019-02-15 2019-02-20 2019-03-27 2019-09-23 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 9 NI-MTI-101507-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 533,393.03 526,808.46 Firmado 2019-02-25 2019-03-02 2019-04-06 2019-10-03 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 15 Page 5 NI-MTI-101508-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 532,320.39 525,592.46 Firmado 2019-02-25 2019-03-02 2019-04-06 2019-10-03 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 16 NI-MTI-101425-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 543,940.81 537,226.04 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 1 NI-MTI-100909-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 571,238.24 576,035.26 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 7 NI-MTI-101429-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 545,395.53 538,662.79 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 2 NI-MTI-101438-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 548,139.85 541,373.24 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 3 NI-MTI-101491-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 542,569.63 535,871.79 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 5 NI-MTI-101490-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 543,793.46 537,080.50 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 4 NI-MTI-101493-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 543,419.01 536,710.67 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 6 NI-MTI-101495-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 543,893.09 537,178.91 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 7 NI-MTI-101498-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 543,755.80 537,043.31 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 8 NI-MTI-101499-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 547,676.98 540,916.08 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 9 NI-MTI-101501-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 545,552.83 538,818.15 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 10 NI-MTI-101502-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 547,686.44 540,925.43 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 11 NI-MTI-101503-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 546,282.78 539,539.10 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 12 Page 6 NI-MTI-101504-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 546,799.29 540,049.23 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 13 NI-MTI-101505-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 547,471.45 540,713.09 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Cárdenas-Colón Fase III Infrastructure Improvement las adquisiciones MCA 14 NI-MTI-100903-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 570,578.39 575,369.87 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 6 NI-MTI-100876-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 571,005.48 575,800.55 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 2 NI-MTI-100880-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 569,970.40 574,756.77 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 4 NI-MTI-100873-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 570,539.61 575,330.76 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 1 NI-MTI-100878-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 569,559.61 574,342.54 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 3 NI-MTI-100913-CW-CDD / Participación de Mejoramiento del camino Component 1: Road IDA / 62010 Posterior la comunidad en Direct 571,284.47 576,081.88 Firmado 2019-03-18 2019-03-19 2019-04-23 2019-10-20 Granada-Malacatoya Fase III Infrastructure Improvement las adquisiciones MCA 8 NI-MTI-135202-CW-RFB / Movimiento de Tierra para Component 1: Road Solicitud de Single Stage - One Ejecución IDA / 62010 Posterior Open - National 1,509,000.02 0.00 2019-09-30 2019-10-05 2019-11-16 2019-12-16 2020-01-20 2020-07-18 el Mejoramiento del camino Infrastructure Improvement ofertas Envelope pendiente Granada-Malacatoya Fase III. NI-MTI-135205-CW-RFB / Movimiento de tierra para el Component 1: Road Solicitud de Single Stage - One IDA / 62010 Posterior Open - National 4,672,904.91 0.00 Cancelado 2019-09-30 2019-10-05 2019-11-16 2019-12-16 2020-01-20 2020-07-18 Mejoramiento del camino Infrastructure Improvement ofertas Envelope Cárdenas -Colón Fase III NI-MTI-99806-CW-RFB / Obras de adaptación a cambio climático de los Component 1: Road Solicitud de Single Stage - One IDA / 59630 Posterior Open - National 506,797.49 0.00 Cancelado 2019-02-18 2019-02-23 2019-04-06 2019-05-06 2019-06-10 2019-12-07 puntos vulnerables en el Infrastructure Improvement ofertas Envelope tramo Empalme El Cuá-El Carmen: Llorona # 2. NI-MTI-99809-CW-RFB / Obras de adaptación a Component 1: Road Solicitud de Single Stage - One cambio climático de los IDA / 59630 Posterior Open - National 1,871,622.05 0.00 Cancelado 2019-02-18 2019-02-23 2019-04-06 2019-05-06 2019-06-10 2019-12-07 Infrastructure Improvement ofertas Envelope puntos vulnerables en el Puente Miraflores. Page 7 NI-MTI-99810-CW-RFB / Obras de adaptación a cambio climático de los puntos vulnerables en el Component 1: Road Solicitud de Single Stage - One IDA / 59630 Posterior Open - National 1,792,155.73 0.00 Cancelado 2019-02-18 2019-02-23 2019-04-06 2019-05-06 2019-06-10 2019-12-07 tramo Estelí-Condega: Infrastructure Improvement ofertas Envelope Kukamonga, Fase 1: Punto # 1 y Punto #2, Fase 2: Punto #3 y Punto #4. NI-MTI-99813-CW-RFB / Obras de adaptación a cambio climático de los Component 1: Road Solicitud de Single Stage - One IDA / 59630 Posterior Open - National 856,073.80 0.00 Cancelado 2019-02-18 2019-02-23 2019-04-06 2019-05-06 2019-06-10 2019-12-07 puntos vulnerables en el Infrastructure Improvement ofertas Envelope tramo Ranchería-Villa 15 de Julio. NI-MTI-155012-CW-RFB / Construcción de obras de adaptación al cambio Component 1: Road Solicitud de Open - Single Stage - One Ejecución IDA / 59630 Previa 7,626,971.60 0.00 2020-04-06 2020-04-11 2020-05-23 2020-06-22 2020-07-27 2021-01-23 climático en tramos Infrastructure Improvement ofertas International Envelope pendiente vulnerables de la red vial nacional NI-MTI-155894-CW-RFB / Construcción de obras de Solicitud de Open - Single Stage - One Ejecución IDA / 59640 Component 2: Road Safety Previa 6,500,000.00 0.00 2020-06-08 2020-06-13 2020-07-25 2020-08-24 2020-09-28 2021-03-27 Seguridad Vial en las ofertas International Envelope pendiente carreteras de Nicaragua NI-MTI-156830-CW-RFB / Movimiento de tierra para el Mejoramiento del camino Component 1: Road Solicitud de Single Stage - One Ejecución IDA / 62010 Posterior Open - National 1,866,107.72 0.00 2020-02-03 2020-02-08 2020-03-21 2020-04-20 2020-05-25 2020-11-21 Cárdenas-Colón Fase III Infrastructure Improvement ofertas Envelope pendiente (Segunda Convocatoria) Tramo I. NI-MTI-156831-CW-RFB / Movimiento de tierra para el Mejoramiento del camino Component 1: Road Solicitud de Single Stage - One Ejecución IDA / 62010 Posterior Open - National 2,003,619.85 0.00 2020-02-03 2020-02-08 2020-03-21 2020-04-20 2020-05-25 2020-11-21 Cárdenas-Colón Fase III Infrastructure Improvement ofertas Envelope pendiente (Segunda Convocatoria) Tramo II. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NI-MTI-17611-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One Ejecución colocados en el sitio para el IDA / 59640 Posterior Open - National 420,000.00 0.00 2017-10-13 2017-10-18 2017-11-29 2017-12-29 2018-02-02 2018-08-01 Infrastructure Improvement ofertas Envelope pendiente camino Granada - Malacatoya Sección 3 NI-MTI-17613-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One Ejecución IDA / 59640 Posterior Open - National 162,000.00 0.00 2018-03-21 2018-03-26 2018-05-07 2018-06-06 2018-07-11 2019-01-07 colocados en el sitio para el Infrastructure Improvement ofertas Envelope pendiente camino Corn Island NI-MTI-17620-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 460,000.00 0.00 En ejecución 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 Infrastructure Improvement ofertas Envelope camino Macuelizo - Santa María Sección 3 Page 8 NI-MTI-17630-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One Ejecución colocados en el sitio para el IDA / 59640 Posterior Open - National 401,280.00 0.00 2018-05-02 2018-05-07 2018-06-18 2018-07-18 2018-08-22 2019-02-18 Infrastructure Improvement ofertas Envelope pendiente camino La Libertad - San Pedro de Lóvago Sección 3 NI-MTI-17631-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One Ejecución colocados en el sitio para el IDA / 59640 Posterior Open - National 401,280.00 0.00 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 Infrastructure Improvement ofertas Envelope pendiente camino La Libertad - San Pedro de Lóvago Sección 4 NI-MTI-17633-GO-RFB / Compra de los radares y Solicitud de Single Stage - One Ejecución IDA / 59640 Component 2: Road Safety Posterior Open - National 50,000.00 0.00 2018-06-04 2018-06-08 2018-07-20 2018-08-20 2018-09-24 2019-03-23 alcoholímetros para la ofertas Envelope pendiente Policía NI-MTI-17632-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One Ejecución colocados en el sitio para el IDA / 59640 Posterior Open - National 401,280.00 0.00 2017-10-10 2017-10-16 2017-11-27 2017-12-27 2018-01-31 2018-07-30 Infrastructure Improvement ofertas Envelope pendiente camino La Libertad - San Pedro de Lóvago Sección 5 NI-MTI-17623-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 440,000.00 671,413.67 En ejecución 2017-11-27 2017-12-04 2018-01-15 2018-02-14 2018-03-21 2018-09-17 Infrastructure Improvement ofertas Envelope camino Cárdenas - Colón Sección 1 NI-MTI-17618-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 460,000.00 0.00 En ejecución 2017-12-04 2017-12-09 2018-01-22 2018-02-21 2018-03-28 2018-09-24 Infrastructure Improvement ofertas Envelope camino Macuelizo - Santa María Sección 2 NI-MTI-17592-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 42,000.00 592,855.04 Firmado 2017-11-27 2017-12-04 2018-01-15 2018-02-14 2018-03-21 2018-09-17 Infrastructure Improvement ofertas Envelope camino Granada - Malacatoya Sección 1 NI-MTI-17615-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 460,000.00 0.00 En ejecución 2017-11-27 2017-12-04 2018-01-15 2018-02-14 2018-03-21 2018-09-17 Infrastructure Improvement ofertas Envelope camino Macuelizo - Santa María Sección 1 NI-MTI-17625-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 440,000.00 0.00 Cancelado 2017-12-04 2017-12-11 2018-01-22 2018-02-21 2018-03-28 2018-09-24 Infrastructure Improvement ofertas Envelope camino Cárdenas - Colón Sección 2 NI-MTI-17628-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 401,280.00 584,129.13 Firmado 2017-11-27 2017-12-01 2018-01-12 2018-02-12 2018-03-19 2018-09-14 Infrastructure Improvement ofertas Envelope camino La Libertad - San Pedro de Lóvago Sección 1 NI-MTI-79072-GO-RFB / Adquisición de adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio de las IDA / 59630 Previa Open - National 644,086.71 0.00 En ejecución 2018-09-20 2018-09-25 2018-11-06 2018-12-06 2019-01-10 2019-07-09 Infrastructure Improvement ofertas Envelope obras del Proyecto Cárdenas- Colón Fase II. NI-MTI-17629-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 401,280.00 0.00 Cancelado 2017-12-04 2017-12-11 2018-01-22 2018-02-22 2018-03-29 2018-09-25 Infrastructure Improvement ofertas Envelope camino La Libertad - San Pedro de Lóvago Sección 2 Page 9 NI-MTI-17610-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 420,000.00 0.00 Cancelado 2017-12-04 2017-12-11 2018-01-22 2018-02-21 2018-03-28 2018-09-24 Infrastructure Improvement ofertas Envelope camino Granada - Malacatoya Sección 2 NI-MTI-17627-GO-RFB / Compra de Adoquines Component 1: Road Solicitud de Single Stage - One colocados en el sitio para el IDA / 59640 Posterior Open - National 440,000.00 0.00 Cancelado 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 Infrastructure Improvement ofertas Envelope camino Cárdenas - Colón Sección 3 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NI-MTI-17636-CS-QCBS / Supervisión para el Component 1: Road Selección basada Open - Mejoramiento de la IDA / 59640 Previa 420,000.00 724,578.80 Firmado 2017-07-04 2017-07-25 2017-09-06 2017-10-04 2017-11-03 2017-12-08 2018-01-15 2019-01-15 Infrastructure Improvement en calidad y costo International Carretera Granada - Malacatoya. NI-MTI-17638-CS-QCBS / Supervisión para el Component 1: Road Selección basada Open - IDA / 59640 Previa 420,000.00 459,674.97 Firmado 2017-06-22 2017-07-13 2017-08-25 2017-09-22 2017-10-23 2017-11-27 2018-01-03 2019-01-03 Mejoramiento del Camino Infrastructure Improvement en calidad y costo International Macuelizo - Santa María NI-MTI-17641-CS-QCBS / Supervisión para el Component 1: Road Selección basada Open - Mejoramiento del Camino La IDA / 59640 Previa 638,400.00 474,503.65 Firmado 2017-07-06 2017-07-27 2017-09-08 2017-10-06 2017-11-06 2017-12-11 2018-01-15 2019-01-15 Infrastructure Improvement en calidad y costo International Libertad - San Pedro de Lóvago NI-MTI-17642-CS-QCBS / Preparación de estudios Selección basada Open - IDA / 59640 Component 2: Road Safety Posterior 230,000.00 0.00 Cancelado 2018-05-02 2018-05-23 2018-07-06 2018-08-03 2018-09-03 2018-10-08 2018-11-12 2019-11-12 técnicos para tratar puntos en calidad y costo International peligrosos de seguridad vial NI-MTI-17643-CS-QCBS / Component 3: Institutional Fortalecimiento de la Selección basada Open - Ejecución IDA / 59640 Strengthening and Posterior 300,000.00 0.00 2018-04-02 2018-04-23 2018-06-06 2018-07-04 2018-08-03 2018-09-07 2018-10-12 2019-10-12 capacidad de M&E y la en calidad y costo International pendiente Implementation Support calidad de datos estadísticos NI-MTI-17645-CS-QCBS / Component 3: Institutional Consultoría para preparar Selección basada Open - IDA / 59640 Strengthening and Posterior 300,000.00 0.00 Cancelado 2018-02-12 2018-03-05 2018-04-18 2018-05-16 2018-06-15 2018-07-20 2018-08-24 2019-08-24 auditoría administrativa en calidad y costo International Implementation Support financiera del proyecto NI-MTI-17650-CS-CQS / Component 3: Institutional Selección basada Apoyo a la implementación Ejecución IDA / 59640 Strengthening and Posterior en calificaciones Open - National 50,000.00 0.00 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 de actividades de pendiente Implementation Support de consultores participación ciudadana NI-MTI-16138-CS-QCBS / Supervisión Mejoramiento de Component 1: Road Selección basada Open - IDA / 59640 Previa 986,400.00 753,247.40 Firmado 2017-06-12 2017-06-30 2017-07-17 2017-09-07 2017-09-22 2017-10-12 2017-10-26 2019-06-18 la Carretera La Garita - Infrastructure Improvement en calidad y costo International Empalme Tipitapa Page 10 NI-MTI-17634-CS-QCBS / Supervisión para el Component 1: Road Selección basada Open - Mejoramiento de la IDA / 59640 Previa 1,487,700.00 1,051,723.00 Rescindido 2017-07-03 2017-07-20 2017-09-02 2017-09-30 2017-10-30 2017-12-04 2018-01-08 2019-01-08 Infrastructure Improvement en calidad y costo International Carretera Las Piedrecitas - (km 6+830)-Mateare NI-MTI-17639-CS-QCBS / Supervisión para el Component 1: Road Selección basada Open - IDA / 59640 Previa 420,000.00 1,024,441.14 Firmado 2017-07-05 2017-07-27 2017-09-08 2017-10-06 2017-11-07 2017-12-12 2018-01-16 2019-01-16 Mejoramiento del Camino Infrastructure Improvement en calidad y costo International Cárdenas - Colón NI-MTI-19378-CS-CQS / Línea de Base para la Component 3: Institutional Selección basada Open - Evaluación de Impacto del IDA / 59640 Strengthening and Posterior 300,000.00 210,150.60 Firmado 2017-07-14 2017-08-16 2017-10-20 2017-11-17 2017-12-18 2018-01-22 2018-02-26 2019-02-26 en calidad y costo International Proyecto de Mejoramiento de Implementation Support Acceso Rural y Urbano NI-MTI-23521-CS-CQS / Component 3: Institutional Selección basada Consultor de Apoyo Técnico IDA / 59640 Strengthening and Posterior en calificaciones Open - National 60,000.00 0.00 Cancelado 2017-08-03 2017-08-24 2017-10-06 2017-11-06 2017-12-11 2018-06-08 Estadístico en Monitoreo y Implementation Support de consultores Evaluación Component 3: Institutional Selección basada NI-MTI-17646-CS-CQS / IDA / 59640 Strengthening and Previa en calificaciones Open - National 150,000.00 0.00 Cancelado 2018-02-09 2018-03-02 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Especialista Adquisiciones Implementation Support de consultores NI-MTI-17649-CS-CQS / Component 3: Institutional Selección basada Fortalecimiento de la Ejecución IDA / 59640 Strengthening and Posterior en calificaciones Open - National 50,000.00 0.00 2018-02-08 2018-03-01 2018-04-16 2018-05-16 2018-06-20 2018-12-17 participación de mujeres en pendiente Implementation Support de consultores las obras Component 3: Institutional NI-MTI-40803-CS-INDV / Selección basada IDA / 59630 Strengthening and Posterior Open - National 100,000.00 0.00 Cancelado 2018-06-21 2018-07-12 2018-08-25 2018-09-22 2018-10-22 2018-11-26 2018-12-31 2019-12-31 Encuestas deBeneficiarios en calidad y costo Implementation Support NI-MTI-44267-CS-QCBS / Preparación de Estudios Selección basada Open - IDA / 59640 Component 2: Road Safety Previa 500,000.00 355,387.05 Firmado 2018-02-05 2018-02-26 2018-04-16 2018-05-14 2018-06-13 2018-07-18 2018-08-23 2019-08-23 Técnicos para tratar Puntos en calidad y costo International Peligrosos de Seguridad Vial NI-MTI-64111-CS-QCBS / Supervisión para el Mejoramiento de la Component 1: Road Selección basada Open - IDA / 59640 Previa 1,487,700.00 574,337.26 Firmado 2018-06-11 2018-06-25 2018-07-10 2018-08-22 2018-09-06 2018-10-11 2018-11-11 2019-11-11 Carretera Ciudad Sandino- Infrastructure Improvement en calidad y costo International Mateare (11.81 km), Segunda Convocatoria. NI-MTI-76772-CS-QCBS / Supervisión del Mejoramiento Component 1: Road Selección basada del camino Granada- IDA / 62010 Posterior Open - National 377,650.00 0.00 Cancelado 2018-09-04 2018-09-25 2018-11-08 2018-12-06 2019-01-05 2019-02-09 2019-03-16 2020-03-15 Infrastructure Improvement en calidad y costo Malacatoya Fase III (8.30 km) NI-MTI-76773-CS-QCBS / Supervisión para el Component 1: Road Selección basada Open - Mejoramiento del Camino IDA / 62010 Previa 655,473.00 0.00 Cancelado 2018-09-04 2018-09-25 2018-11-08 2018-12-06 2019-01-05 2019-02-09 2019-03-16 2020-03-15 Infrastructure Improvement en calidad y costo International Cárdenas-Colón Fase III (13.72 km) NI-MTI-76775-CS-QCBS / Supervisión del Mejoramiento Component 1: Road Selección basada Open - IDA / 62010 Previa 1,382,557.00 717,926.14 Firmado 2018-09-04 2018-09-25 2018-11-08 2018-12-06 2019-01-05 2019-02-09 2019-03-16 2020-03-15 del Camino Macuelizo-Santa Infrastructure Improvement en calidad y costo International María Fase II (19.05 km) NI-MTI-94795-CS-QCBS / Component 3: Institutional Selección basada Servicios de Consultoría para IDA / 59630 Strengthening and Posterior Open - National 100,000.00 81,360.40 Firmado 2019-01-14 2019-02-04 2019-03-20 2019-04-17 2019-05-17 2019-06-21 2019-07-26 2020-07-25 en calidad y costo Encuestas de Beneficiarios Implementation Support Page 11 NI-MTI-94798-CS-LCS / Consultoría para preparar Auditoría Administrativa Component 3: Institutional Selección basada Open - Financiera del Proyecto IDA / 59630 Strengthening and Posterior 300,000.00 68,005.00 Firmado 2019-01-14 2019-02-04 2019-03-20 2019-04-17 2019-05-17 2019-06-21 2019-07-26 2020-01-22 en el menor costo International Mejoramiento de Acceso Implementation Support Rural y Urbano y su Financiamiento Adicional. NI-MTI-99177-CS-QCBS / Servicios de Consultoría para el desarrollo de un ¨Estudio Component 3: Institutional Selección basada Open - de demanda servida en el IDA / 59630 Strengthening and Posterior 365,152.00 0.00 En ejecución 2019-02-08 2019-03-01 2019-04-14 2019-05-12 2019-06-11 2019-07-16 2019-08-20 2020-08-19 en calidad y costo International Sistema de Transporte Implementation Support intermunicipal público de pasajeros de Nicaragua¨. NI-MTI-17651-CS-CDS / Selección basada Capacitación en "Gestión de Open - IDA / 59640 Component 2: Road Safety Posterior en calificaciones 15,000.00 0.00 Cancelado 2018-06-14 2018-07-05 2018-08-18 2018-09-17 2018-10-22 2019-04-20 la Seguridad Vial en la International de consultores Carreteras" NI-MTI-99795-CS-QCBS / Component 3: Institutional Consultoría para la creación Selección basada Open - IDA / 59630 Strengthening and Posterior 250,000.00 0.00 En ejecución 2019-02-11 2019-03-04 2019-04-17 2019-05-15 2019-06-14 2019-07-19 2019-08-23 2020-08-22 del Sistema de Estadísticas en calidad y costo International Implementation Support de Transporte (SET). NI-MTI-17647-CS-CQS / Fortalecimiento de la Component 3: Institutional Selección basada capacidad de salvaguardas IDA / 59640 Strengthening and Posterior Open - National 170,000.00 0.00 Cancelado 2018-02-08 2018-03-01 2018-04-16 2018-05-14 2018-06-15 2018-07-20 2018-08-24 2019-08-23 en calidad y costo ambientales y sociales de la Implementation Support UGA NI-MTI-103998-CS-CQS / Selección basada Capacitación en Gestión de Open - IDA / 59640 Component 2: Road Safety Posterior en calificaciones 15,000.00 0.00 En ejecución 2019-03-18 2019-04-08 2019-05-22 2019-06-21 2019-07-26 2020-01-22 la seguridad vial en las International de consultores carreteras. NI-MTI-147798-CS-QCBS / Consultoría para la Component 3: Institutional Selección basada Open - Ejecución preparación de los Estudios IDA / 59630 Strengthening and Previa 778,560.00 0.00 2020-03-02 2020-03-23 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-09-11 en calidad y costo International pendiente y Diseños de Proyectos de Implementation Support Infraestructura Vial NI-MTI-17637-CS-QCBS / Supervisión Externa de las Component 1: Road Selección basada Open - IDA / 59640 Posterior 420,000.00 0.00 Cancelado 2018-05-16 2018-06-06 2018-07-21 2018-08-18 2018-09-17 2018-10-22 2018-11-26 2019-11-26 obras del camino Corn Infrastructure Improvement en calidad y costo International Island INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NI-MTI-23997-CS-INDV / Component 3: Institutional Consultor de Apoyo Técnico IDA / 59630 Strengthening and Posterior Individual Open 60,000.00 57,000.00 Firmado 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-18 Estadístico en Monitoreo y Implementation Support Evaluación Component 3: Institutional NI-MTI-47814-CS-CDS / Selección directa IDA / 59630 Strengthening and Previa Direct 36,000.00 0.00 En ejecución 2018-02-06 2018-02-07 2018-03-08 2020-03-07 Especialista en Adquisiciones de consultores Implementation Support Component 3: Institutional NI-MTI-83869-CS-INDV / IDA / 59630 Strengthening and Posterior Individual Open 20,000.00 20,000.00 Firmado 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 Consultor Especialista Social Implementation Support Page 12 NI-MTI-99452-CS-INDV / Capacitación en ¨Gestión de IDA / 59640 Component 2: Road Safety Posterior Individual Open 15,000.00 0.00 Cancelado 2019-02-08 2019-03-29 2019-04-19 2019-05-24 2019-11-20 la Seguridad Vial en las carreteras¨. Page 13