The World Bank Report No: ISR7431 Implementation Status & Results Mexico Sustainable Rural Development (P106261) Public Disclosure Copy Operation Name: Sustainable Rural Development (P106261) Project Stage: Implementation Seq.No: 8 Status: ARCHIVED Archive Date: 01-Jul-2012 Country: Mexico Approval FY: 2009 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Specific Investment Loan Implementing Agency(ies): SAGARPA/FIRCO Key Dates Board Approval Date 24-Feb-2009 Original Closing Date 31-Dec-2013 Planned Mid Term Review Date 11-Jun-2012 Last Archived ISR Date 28-Dec-2011 Effectiveness Date 29-Jan-2010 Revised Closing Date 31-Dec-2013 Actual Mid Term Review Date 11-Jun-2012 Project Development Objectives Sustainable Rural Development (P106261) Project Development Objective (from Project Appraisal Document) The project development objective is to promote the adoption of environmentally sustainable technologies in agri-businesses. Has the Project Development Objective been changed since Board Approval of the Program? Yes No Sustainable Rural Development (P108766) Global Environmental Objective (from Project Appraisal Document) The global environment objective is to contribute to the goals of the National Strategy on Climate Change by reducing GHG (CO2) emission through the adoption of emission-reduction technologies and the support to the implementation of the President#s Special Program for Climate Change (PECC), with special reference to the improved environmental sustainability of small and medium-scale agri-business. Has the Global Environmental Objective been changed since Board Approval of the Program? Yes No Public Disclosure Copy Component(s) Component Name Component Cost Investments in environmentally sustainable technologies in agri-business 151.04 Investment and Production Support Services 10.91 Institutional Strengthening 3.59 Project Management, Monitoring and Evaluation 2.45 Overall Ratings Previous Rating Current Rating Page 1 of 7 The World Bank Report No: ISR7431 Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Progress towards achievement of GEO Satisfactory Satisfactory Public Disclosure Copy Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating Implementation Status Overview A World Bank mission to the Sustainable Rural Development Project took place in Mexico City from June 4 to 12, 2012. The main objective of this mission was to conduct the Mid Term Review of the project, focusing overall progress to date, including technical, operational and administrative aspects of project implementation. Through a detailed assessment of the status of the project, combined with the review of the reports prepared by both FIRCO's PIU and two independent consultants, the mission concluded that the project has made considerable progress towards meeting its objectives and targets, thus contributing to the overall improvement of agro-environmental conditions of beneficiary producers and agro- industries. The mission also discussed with FIRCO representatives a series of opportunities for further enhancement of project results, mainly related to the effective utilization of GEF resources. Locations Country First Administrative Division Location Planned Actual Mexico Not Entered Estado de Yucatan Mexico Not Entered Estado de Veracruz-Llave Mexico Not Entered Estado de Nuevo Leon Mexico Not Entered Estado de Sonora Mexico Not Entered Estado de Michoacan de Ocampo Mexico Not Entered Estado de Jalisco Mexico Not Entered Estado de Guanajuato Mexico Not Entered Estado de Durango Mexico Not Entered Estado de Coahuila de Zaragoza Public Disclosure Copy Mexico Not Entered Estado de Chihuahua Results Project Development Objective Indicators Page 2 of 7 The World Bank Report No: ISR7431 Indicator Name Core Unit of Measure Baseline Current End Target Number of small and medium-sized agri- Text Value 0 466 919 businesses adopting environmentally Date 19-Jan-2009 11-Jun-2012 31-Dec-2013 Public Disclosure Copy sustainable technologies (renewable energy, Comments energy efficient technologies, sustainable waste management or biomass conversion) Global Environmental Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Tons of CO2 equivalent avoided Text Value 0 770,000 770,000 Date 19-Jan-2009 11-Jun-2012 31-Dec-2013 Comments SAGARPA is successfully formulating climate Text Value SAGARPA/ FIRCO staff Department of Bioeconomy The Climate Change unit is change mitigation and adaptation policies and participate in training events actively engages in climate functioning programs in the agricultural sector and change related activities monitoring their implementation Date 19-Jan-2009 11-Jun-2012 31-Dec-2012 Comments Dept of Bioeconomy expected to strengthen SAGARPA's engagement in climate change issues Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of MWH energy is produced by Text Value 0 17,256 MWh and 9,163 tons 92,510 MWh and 588,413 biomass and corresponding tons of CO2 e tons emissions avoided Date 19-Jan-2009 11-Jun-2012 31-Dec-2013 Comments Number of agri-business employees/ Text Value 0 0 930 processors has participated in training events Date 19-Jan-2009 11-Jun-2012 31-Dec-2012 Public Disclosure Copy organized by the project Comments Number of energy efficiency and /or renewable Text Value 0 466 919 energy sub-projects received technical Date 19-Jan-2009 11-Jun-2012 31-Dec-2013 assistance on energy efficiency and/or Comments renewable energy technologies during implementation Page 3 of 7 The World Bank Report No: ISR7431 Number of pilot projects carried out to Text Value 0 0 4 demonstrate and validate other technological Date 19-Jan-2009 11-Jun-2012 31-Dec-2011 innovations that could be proposed under the Comments project Public Disclosure Copy A unit within SAGARPA is established to Text Value No Unit 1 The unit is established and support and/or to formulate, implement and functioning monitor Climate Change mitigation and Date 19-Jan-2009 11-Jun-2012 31-Dec-2010 adaptationpolicies and programs in agriculture Comments Commission for the PECC sector Number of Inter-ministerial workshops Text Value 0 4 6 promoting collaboration and knowledge sharing Date 19-Jan-2009 11-Jun-2012 31-Dec-2013 on climate change activities related to the Comments project carried out Number of SAGARPA/FIRCO staff that Text Value 0 147 280 participated in training events organized by the Date 19-Jan-2009 11-Jun-2012 31-Dec-2011 project Comments Quarterly physical and financial status reports Text Value Reports submitted to the Bank 4 Reports submitted to the Bank prepared and submitted to the Bank Date 19-Jan-2009 11-Jun-2012 31-Dec-2013 Comments Semi-annual documents on lessons learned Text Value Reports submitted to the Bank 4 Reports submitted to the Bank and policy implications are prepared. To Date 19-Jan-2009 11-Jun-2012 31-Dec-2013 coincide with supervision missions Comments Planning process followed as defined in the Text Value AIP prepared and submitted AIP prepared and submitted Operations Manual describing when and how to the Bank to the Bank Annual Implementation Plans (AIP) and Date 19-Jan-2009 26-Nov-2010 31-Dec-2013 quarterly and monthly plans prepared based on Comments Project Implementation Plan Number of agri-businesses having adopted low Text Value 0 At least 141 energy efficiency, carbon intensity technologies 300 biomass energy, 329 Public Disclosure Copy solar thermal, 109 PV system and 40 biomass electricity generator sub-projects. Date 19-Jan-2009 15-Dec-2011 31-Dec-2013 Comments Number of KWh of energy saved from adoption Text Value 0 22,58M KWh, 26,703 tons of energy efficient technologies and Date 19-Jan-2009 15-Dec-2011 31-Dec-2013 corresponding tons of avoided CO2 e Comments emissions Page 4 of 7 The World Bank Report No: ISR7431 Number of MWH energy is produced by Text Value 0 69,930 MWH, 561,710 tons biomass and corresponding tons of CO2 e Date 19-Jan-2009 15-Dec-2011 31-Dec-2013 emissions avoided Comments Public Disclosure Copy Number of agri-business employees/ Text Value 0 930 processors has participated in training events Date 19-Jan-2009 15-Dec-2011 31-Dec-2012 organized by the project Comments Number of energy efficiency and /or renewable Text Value 0 919 energy sub-projects received technical Date 19-Jan-2009 15-Dec-2011 31-Dec-2013 assistance on energy efficiency and/or Comments renewable energy technologies during implementation Number of pilot projects carried out to Text Value 0 4 demonstrate and validate other technological Date 19-Jan-2009 15-Dec-2011 31-Dec-2011 innovations that could be proposed under the Comments project A unit within SAGARPA is established to Text Value No Unit The unit is established and support and/or to formulate, implement and functioning monitor Climate Change mitigation and Date 19-Jan-2009 15-Dec-2011 31-Dec-2010 adaptationpolicies and programs in agriculture Comments sector Number of Inter-ministerial workshops Text Value 0 6 promoting collaboration and knowledge sharing Date 19-Jan-2009 15-Dec-2011 31-Dec-2013 on climate change activities related to the Comments project carried out Number of SAGARPA/FIRCO staff that Text Value 0 280 participated in training events organized by the Date 19-Jan-2009 15-Dec-2011 31-Dec-2011 project Comments Quarterly physical and financial status reports Text Value Reports submitted to the Bank Reports submitted to the Bank prepared and submitted to the Bank Public Disclosure Copy Date 19-Jan-2009 15-Dec-2011 31-Dec-2013 Comments Semi-annual documents on lessons learned Text Value Reports submitted to the Bank Reports submitted to the Bank and policy implications are prepared. To Date 19-Jan-2009 15-Dec-2011 31-Dec-2013 coincide with supervision missions Comments Page 5 of 7 The World Bank Report No: ISR7431 Planning process followed as defined in the Text Value AIP prepared and submitted AIP prepared and submitted Operations Manual describing when and how to the Bank to the Bank Annual Implementation Plans (AIP) and Date 19-Jan-2009 15-Dec-2011 31-Dec-2013 quarterly and monthly plans prepared based on Public Disclosure Copy Comments Project Implementation Plan Data on Financial Performance (as of 12-Jun-2012) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P106261 IBRD-76520 Effective 24-Feb-2009 14-May-2009 29-Jan-2010 31-Dec-2013 31-Dec-2013 P108766 TF-93134 Effective 14-May-2009 14-May-2009 08-Feb-2010 31-Dec-2013 31-Dec-2013 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P106261 IBRD-76520 Effective USD 50.00 50.00 0.00 22.05 27.95 44.00 P108766 TF-93134 Effective USD 10.50 10.50 0.00 1.37 9.13 13.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation None Page 6 of 7 The World Bank Report No: ISR7431 Restructuring History There has been no restructuring to date. Public Disclosure Copy Related Projects P108766-Sustainable Rural Development, P130623-Sustainable Rural Development Additional Financing Public Disclosure Copy Page 7 of 7