Sample Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan Original: March, 2014 : Revision: March, 2017 3. Date of General Procurement Notice: April, 2014 4. Period covered by this procurement plan: The procurement period of project covered from year May 1, 2015 to July 31, 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1 NCB (Goods) ; IT and Non-consulting Equivalent and Below US$ Above USD 2 mil. services 1,000,000 2 NCB (Works) Equivalent and Below US$ Above USD 10 mil. 10 million 3 Shopping (Goods) Equivalent and Below US$ None 100,000 4 Shopping (Works) Equivalent and Below US$ None 200,000 2. Prequalification. Bidders for Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P133828 is developed by MoA (for Parts A and C1) and the Guidelines for implementation of activities under parts B and C2 are developed by NAPR 5. Any Other Special Procurement Arrangements: None 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estim Packag Domest Review Comments No. ated es ic by Cost Prefere Bank nce (Prior / (yes/no) Post) US$ millio n Summary of the ICB (Works) 22.4 2 No Prior The first one has been already signed Summary of the NCB (Works) 1.15 1 No Post Summary of the NCB (Goods) 0.75 3 No Post Summary of the ICB (Non- 0.8 2 No Post Consultant Services) Summary of the Shopping 0.4 13 No Post (Goods) Summary of the Shopping (Non- 0.074 1 No Post Consultant Services) Summary of the Direct 0.2 2 Contracting III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods Above US$ (Firms) 1,000,000 2. CQS Applicable for assignments with estimation below USD 300K 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packag Review Comments Assignment Cost es by Bank US$ (Prior / million Post) Summary of number of contracts 3.5 3 Prior that will be let under QCBS Summary of number of contracts 0.51 7 Post LCS, FB, CQS that will be let under other methods Summary of number of contracts 1.01 35 Prior/Post 4 signed contracts were subject that will be let under IC to the Prior reviewer Summary of number of contracts 0.33 11 Prior/Post 9 signed contracts were subject that will be let under SSS to the Prior reviewer PROCUREMENT Georgia : Irrigation and Land Market Development Project PLAN General Information Country: Georgia Bank’s Approval Date of the Original Procurement Plan: 2016-09-15 2020-01-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133828 GPN Date: Project Name: Irrigation and Land Market Development Project Loan / Credit No: IDA / 54560 Executing Agency(ies): Ministry of Agriculture of Georgia WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDIC/CW/ICB/01 / Rehabilitation of Irrigation Scheme Main Canals and Component 1 Irrigation and Open - Single Stage - One IDA / 54560 Prior Request for Bids 0.00 14,623,975.02 Signed Electrical and Mechanical Drainage Improvement International Envelope parts of main canal and headwork IDIC/CW/NCB/01 / Sioni Pending Component 1 Irrigation and Single Stage - One and Algeti Dams Safety IDA / 54560 Post Request for Bids Open - National 1,150,000.00 0.00 Implementati 2017-12-01 2017-12-15 2018-01-14 2018-02-13 2018-03-13 2018-09-09 Drainage Improvement Envelope Works on IDIC/CW/ICB/02 / Rehabilitation of secondary Pending Component 1 Irrigation and Open - Single Stage - One networks for Zeda Ru, Tbisi- IDA / 54560 Prior Request for Bids 19,700,000.00 0.00 Implementati 2018-11-05 2018-11-19 2018-12-31 2019-01-30 2019-02-27 2019-07-27 Drainage Improvement International Envelope Kumisi and Zemo Samgori on Irrigation Schemes GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDIC/G/SH/07 / PPMD Component 3 Project Request for Single Stage - One IDA / 54560 Post Open - National 20,000.00 0.00 Canceled 2018-01-17 2018-02-14 2018-04-15 office Furniture Management Quotations Envelope IDIC/G/SH/08 / Component 3 Project Request for Single Stage - One Environmental Monitoring IDA / 54560 Post Open - National 15,000.00 0.00 Canceled 2018-01-17 2018-02-14 2018-04-15 Management Quotations Envelope Field Equipment IDIC/G/SH/09 / Component 3 Project Request for Single Stage - One Environmental Monitoring IDA / 54560 Post Open - National 5,000.00 0.00 Canceled 2018-01-17 2018-02-14 2018-04-15 Management Quotations Envelope Program IDIC/G/DC/01 / Procurement Component 1 Irrigation and of Agricultural software - IDA / 54560 Post Direct Selection Direct 19,000.00 0.00 Canceled 2017-02-17 2017-02-27 2017-03-11 2017-05-10 Drainage Improvement Sic^2 IDIC/G/SH/10 / Supply of Component 1 Irrigation and Request for Single Stage - One Tachometer for Georgian IDA / 54560 Post Open - National 17,000.00 0.00 Canceled 2017-07-06 2017-08-08 2017-10-07 Drainage Improvement Quotations Envelope Amelioration IDIC/G/SH/13 / Supply of 5 units of off-road small size Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 100,000.00 0.00 Canceled 2017-10-05 2017-10-28 2017-12-27 trucks to the Georgian Drainage Improvement Quotations Envelope Amelioration (GA) Page 1 IDIC/G/NCB/02 / Supply of Component 1 Irrigation and Single Stage - One Machinery and Equipment to IDA / 54560 Post Request for Bids Open - National 450,000.00 80,241.94 Signed 2017-12-04 2017-12-18 2018-01-17 2018-02-16 2018-03-09 2018-06-07 Drainage Improvement Envelope Georgian Amelioration IDIC/G/NCB/03 / PPMD Component 3 Project Single Stage - One IDA / 54560 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2018-01-10 2018-01-24 2018-02-23 2018-03-25 2018-04-22 2018-06-21 Equipment - Vehicles Management Envelope IDIC/G/NCB/01 / Supply of Component 1 Irrigation and Single Stage - One IT equipment to Georgian IDA / 54560 Post Request for Bids Open - National 375,000.00 0.00 Canceled 2017-04-25 2017-05-09 2017-06-08 2017-07-08 2017-07-29 2017-09-27 Drainage Improvement Envelope Amelioration IDIC/G/SH/06 / Supply of IT Office Equipment for Component 3 Project Request for Single Stage - One DPMMU and Amelioration IDA / 54560 Post Open - National 80,000.00 0.00 Canceled 2018-01-17 2018-02-14 2018-04-15 Management Quotations Envelope and Land Management Department of MoA IDIC/G/SH/11 / Supply Echo-sounder and 10 units Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 26,000.00 0.00 Canceled 2017-03-02 2017-04-02 2017-06-01 of Leveling Instrument to Drainage Improvement Quotations Envelope Georgian Amelioration IDIC/G/NCB/02-1 / Supply Component 1 Irrigation and Single Stage - One of Machinery and Equipment IDA / 54560 Post Request for Bids Open - National 357,200.00 0.00 Canceled 2018-02-27 2018-02-27 2018-03-29 2018-04-28 2018-05-19 2018-07-18 Drainage Improvement Envelope to Georgian Amelioration IDIC/G/SH/14 / Supply of 2 units of Off-Road 4X4 Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 48,000.00 44,019.87 Signed 2018-03-28 2018-04-30 2018-07-02 vehicles for Georgian Drainage Improvement Quotations Envelope Amelioration IDIC/G/SH/06-1 / Re- announcement of Supply of IT Office Equipment for Component 3 Project Request for Single Stage - One IDA / 54560 Post Open - National 80,000.00 0.00 Canceled 2018-04-27 2018-05-18 2018-06-17 DPMMU and Amelioration Management Quotations Envelope and Land Management Department of MEPA Under IDIC/G/SH/15 / Supply of Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 17,300.00 0.00 Implementati 2018-11-07 2018-12-28 2019-06-26 GPS Navigators for GA Drainage Improvement Quotations Envelope on IDIC/G/SH/16 / Supply of Component 1 Irrigation and Request for Single Stage - One Printing and Scanning IDA / 54560 Post Open - National 2,300.00 1,705.17 Signed 2018-11-05 2018-12-28 2019-06-26 Drainage Improvement Quotations Envelope Instruments for GA IDIC/G/SH/17 / Supply of Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 4,800.00 2,367.80 Signed 2018-11-05 2018-12-28 2019-06-26 Network Equipment fro GA Drainage Improvement Quotations Envelope IDIC/G/SH/18 / Supply of Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 11,000.00 6,087.28 Signed 2018-11-07 2018-12-28 2019-06-26 Photography Tools for GA Drainage Improvement Quotations Envelope IDIC/G/SH/19 / Supply of Component 1 Irrigation and Request for Single Stage - One Automotive Equipment for IDA / 54560 Post Open - National 46,500.00 12,834.62 Signed 2018-11-07 2018-12-28 2019-06-26 Drainage Improvement Quotations Envelope GA IDIC/G/ICB/01 / Supply of Component 1 Irrigation and Open - Single Stage - One IT equipment for Georgian IDA / 54560 Post Request for Bids 180,000.00 56,110.00 Signed 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-16 2019-08-15 Drainage Improvement International Envelope Amelioration IDIC/G/NCB/04 / Supply of Component 1 Irrigation and Single Stage - One SUV vehicles for Georgian IDA / 54560 Post Request for Bids Open - National 357,200.00 359,300.60 Signed 2018-11-20 2018-11-20 2018-12-20 2019-01-10 2019-02-01 2019-04-02 Drainage Improvement Envelope Amelioration IDIC/G/SH/21 / Unionalls Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 15,000.00 14,668.13 Signed 2019-02-13 2019-03-27 2019-07-25 (Uniforms) for GA Drainage Improvement Quotations Envelope Page 2 IDIC/G/SH/22 / Supply of Component 1 Irrigation and Request for Single Stage - One Printing Equipment to the IDA / 54560 Post Open - National 23,000.00 10,927.76 Signed 2019-03-27 2019-05-07 2019-08-05 Drainage Improvement Quotations Envelope Georgian Amelioration IDIC/G/NCB/01-1 / Supply Component 1 Irrigation and Single Stage - One of IT equipment to Georgian IDA / 54560 Post Request for Bids Open - National 375,000.00 0.00 Canceled 2018-01-29 2018-02-03 2018-03-05 2018-04-04 2018-04-25 2018-07-24 Drainage Improvement Envelope Amelioration IDIC/G/SH/22-1 / Supply of Under Component 1 Irrigation and Request for Single Stage - One Printing Equipment for IDA / 54560 Post Open - National 14,000.00 0.00 Implementati 2019-06-25 2019-08-05 2019-10-04 Drainage Improvement Quotations Envelope Georgian Amelioration on IDIC/G/SH/12 / Supply of 3 units of Automatic Flow Measuring Devices and 15 Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 54,000.00 0.00 Canceled 2018-02-08 2018-03-11 2018-05-10 units of water flow velocity Drainage Improvement Quotations Envelope measurement equipment for Georgian Amelioration (GA) IDIC/G/NCB/05 / Computer Under Component 1 Irrigation and Single Stage - One hardware for Georgian IDA / 54560 Post Request for Bids Open - National 105,000.00 0.00 Implementati 2019-07-09 2019-07-12 2019-08-11 2019-08-26 2019-09-17 2019-12-16 Drainage Improvement Envelope Amelioration on IDIC/G/SH/20 / Automotive Pending Component 1 Irrigation and Request for Single Stage - One and Network Equipment for IDA / 54560 Post Open - National 34,500.00 0.00 Implementati 2019-11-04 2019-12-12 2020-03-11 Drainage Improvement Quotations Envelope GA on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDIC/NCS/NCB/02 / Bathymetric survey for Component 1 Irrigation and Single Stage - One IDA / 54560 Post Request for Bids Open - National 157,000.00 0.00 Canceled 2018-02-12 2018-02-17 2018-03-19 2018-04-18 2018-05-09 2018-11-05 Algeti, Sioni and Tbilisi Drainage Improvement Envelope Reservoirs IDIC/NCS/NCB/01 / Topographic Survey for Tbisi Component 1 Irrigation and Single Stage - One IDA / 54560 Post Request for Bids Open - National 297,040.00 0.00 Canceled 2017-02-27 2017-03-06 2017-03-27 2017-04-10 2017-04-17 2017-08-15 Kumisi, Kvemo Samgori and Drainage Improvement Envelope Zeda Ru Irrigation Schemes IDIC/G/SH/23 / Bathymetric Pending Component 1 Irrigation and Request for Single Stage - One Survey for Algeti and Tbilisi IDA / 54560 Post Open - National 53,000.00 0.00 Implementati 2019-04-22 2019-06-17 2019-12-14 Drainage Improvement Quotations Envelope Reservoirs on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ILMDP/C/QCBS/01-2015 / Consulting Services for Supervision of Civil Works to be implemented under Component 1 Irrigation and Quality And Cost- Open - Irrigation and Land Market IDA / 54560 Prior 1,500,000.00 2,492,473.69 Signed Drainage Improvement Based Selection International Development Project - Irrigation And Drainage Improvement Component (ILMDP) Page 3 IDIC/CS/LCS/02 / GILMDP Component 1 Irrigation and Least Cost Open - Project Financial Audit for IDA / 54560 Post 60,000.00 36,167.00 Signed 2016-11-07 2016-11-17 2016-12-22 2017-01-12 2017-02-11 2017-03-11 2017-03-18 2019-07-31 Drainage Improvement Selection International 2015-2019 fiscal years IDIC/CS/CQS/01 / Strengthening of Designing Consultant Component 1 Irrigation and Capacity and Technical IDA / 54560 Post Qualification Open - National 100,000.00 0.00 Canceled 2017-12-11 2017-12-25 2018-01-15 2018-02-05 2018-02-12 2019-02-12 Drainage Improvement maintenance of Georgian Selection Amelioration IDIC/CS/QCBS/03 / Component 1 Irrigation and Quality And Cost- Open - Institutional Strengthening of IDA / 54560 Prior 1,200,000.00 0.00 Canceled 2017-11-01 2017-11-15 2017-12-13 2018-01-10 2018-02-09 2018-03-02 2018-03-16 2019-09-07 Drainage Improvement Based Selection International Georgian Amelioration Consultant IDIC/CS/CQS/05 / National Component 3 Project IDA / 54560 Post Qualification Open - National 20,000.00 0.00 Canceled 2018-03-01 2018-03-15 2018-04-19 2018-05-03 2018-05-10 2018-11-06 Technical Assistance Management Selection IDIC/CS/CQS/03 / Independent Dam Safety Consultant Assessment and Design and Component 1 Irrigation and Open - IDA / 54560 Post Qualification 220,000.00 257,415.49 Signed 2017-07-31 2017-08-14 2017-09-18 2017-10-09 2017-10-23 2019-02-15 Supervision of Dam Safety Drainage Improvement International Selection Activities for Algeti and Sioni Dams IDIC/CS/CQS/07 / Design Consultant Component 1 Irrigation and Engineering Consultancy IDA / 54560 Post Qualification Open - National 50,000.00 0.00 Canceled 2017-02-27 2017-03-13 2017-04-24 2017-05-08 2017-05-15 2018-02-09 Drainage Improvement Services Selection IDIC/CS/QCBS/02 / Preparation of Detailed Engineering Design and Construction Supervision Component 1 Irrigation and Quality And Cost- Open - IDA / 54560 Prior 4,000,000.00 3,126,284.12 Signed 2017-09-25 2017-10-09 2017-11-13 2017-12-11 2018-01-10 2018-01-31 2018-02-21 2019-08-15 services for Kvemo Samgori, Drainage Improvement Based Selection International Tbisi-Kumisi and Zeda Ru irrigation system's secondary, tertiary and on-farm network IDIC/CS/CQS/08 / Consultant Preparation of Training Component 1 Irrigation and Open - Under IDA / 54560 Post Qualification 40,000.00 0.00 2018-10-01 2018-10-15 2018-10-29 2018-11-14 2018-11-25 2019-12-31 Modules and Conduction of Drainage Improvement International Implementation Selection Training Courses IDIC/CS/LCS/03 / ILMDP Component 1 Irrigation and Least Cost Open - Pending Project Financial Audit for IDA / 54560 Post 60,000.00 0.00 2020-01-22 2020-02-01 2020-03-01 2020-03-16 2020-03-31 2020-04-28 2020-05-18 2021-07-31 Drainage Improvement Selection International Implementation 2019-2021 fiscal years INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual CS/IC/10 / Procurement Component 1 Irrigation and IDA / 54560 Prior Consultant Open 9,000.00 215,392.96 Signed Consultant Drainage Improvement Selection IDIC/CS/IC/03 / Water Individual Resource and Climate Component 1 Irrigation and IDA / 54560 Prior Consultant Open 0.00 42,611.12 Signed Advisor for Institutional Drainage Improvement Selection Strengthening of UASCG Individual IDIC/CS/IC/04 / Agricultural Component 1 Irrigation and IDA / 54560 Prior Consultant Open 60,000.00 43,266.65 Signed Economist Drainage Improvement Selection Page 4 Individual IDIC/CS/IC/05 / Water Component 1 Irrigation and IDA / 54560 Prior Consultant Open 0.00 34,272.44 Signed Resource Legal Advisor Drainage Improvement Selection IDIC/CS/IC/01 / Individual Component 1 Irrigation and Management Operation and IDA / 54560 Prior Consultant Open 60,000.00 55,932.00 Signed Drainage Improvement Maintenance (MOM) Advisor Selection IDIC/CS/SSS/01 / Local-level Component 1 Irrigation and Water Management IDA / 54560 Prior Direct Selection Direct 80,000.00 114,971.33 Completed Drainage Improvement Institutions Advisor IDIC/CS/SSS/04 / Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 18,000.00 102,863.87 Signed Component Director Drainage Improvement IDIC/CS/SSS/05 / Financial Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 17,000.00 100,042.66 Signed Manager Drainage Improvement IDIC/CS/SSS/06 / Component 1 Irrigation and Accountant and IDA / 54560 Prior Direct Selection Direct 13,000.00 78,677.21 Signed Drainage Improvement Disbursement Specialist IDIC/CS/SSS/02 / Irrigation Component 1 Irrigation and Policy Specialist and IDA / 54560 Prior Direct Selection Direct 35,000.00 37,366.67 Signed Drainage Improvement Strategy Team Leader Individual IDIC/CS/IC/14 / Component Component 1 Irrigation and IDA / 54560 Prior Consultant Open 33,000.00 179,102.62 Signed Coordinator Drainage Improvement Selection IDIC/CS/SSS/03 / Component 1 Irrigation and Accounting Software IDA / 54560 Prior Direct Selection Direct 0.00 29,588.38 Signed Drainage Improvement Maintenance Specialist IDIC/CS/SSS/08 / Water Component 1 Irrigation and Resource and Climate IDA / 54560 Prior Direct Selection Direct 20,000.00 23,862.23 Signed Drainage Improvement Advisor IDIC/CS/SSS/09 / Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 55,000.00 55,263.33 Signed Agricultural Economist Drainage Improvement IDIC/CS/SSS/10 / Water Resource Legal advisory Component 1 Irrigation and Under IDA / 54560 Prior Direct Selection Direct 65,000.00 67,587.78 services for Institutional Drainage Improvement Implementation Strengthening of GA IDIC/CS/IC/29 / Designing advisory services for Individual Institutional Strengthening of Component 1 Irrigation and IDA / 54560 Post Consultant Open 100,000.00 45,076.00 Terminated 2016-10-10 2016-11-19 2016-12-03 2016-12-17 2017-12-17 Georgian Amelioration Drainage Improvement Selection (Consultant with international experience) IDIC/CS/SSS/13 / Team Component 1 Irrigation and Leader for finalization of IDA / 54560 Post Direct Selection Direct 20,257.00 20,256.67 Signed 2016-10-24 2016-11-03 2016-11-24 2017-05-23 Drainage Improvement Irrigation Strategy Individual IDIC/CS/IC/17 / PPMD Component 3 Project IDA / 54560 Post Consultant Open 70,000.00 22,675.43 Signed 2017-02-20 2017-03-18 2017-03-25 2017-03-30 2019-07-28 Engineer 2 Management Selection Individual IDIC/CS/IC/21 / Component 3 Project IDA / 54560 Post Consultant Open 20,000.00 0.00 Canceled 2018-01-11 2018-02-13 2018-02-27 2018-03-04 2019-03-04 Environmental Specialist Management Selection Page 5 IDIC/CS/IC/30 / Agricultural Economics advisory services for Institutional Individual Component 1 Irrigation and Strengthening of Georgian IDA / 54560 Post Consultant Open 40,000.00 45,217.60 Signed 2017-02-27 2017-03-30 2017-04-09 2017-04-12 2018-01-07 Drainage Improvement Amelioration (Consultant Selection with international experience) IDIC/CS/IC/32 / Local Individual Consultant for Preparation of Component 1 Irrigation and IDA / 54560 Post Consultant Open 7,500.00 7,069.67 Signed 2017-04-17 2017-05-16 2017-05-23 2017-05-24 2017-08-22 Georgian National Drainage Drainage Improvement Selection Strategy IDIC/CS/IC/33 / Regional Advisor to the Georgian Individual Component 1 Irrigation and Amelioration (GA) for Water IDA / 54560 Post Consultant Open 79,240.00 71,213.00 Signed 2017-09-25 2017-10-24 2017-11-03 2017-11-08 2019-02-01 Drainage Improvement Users Organisations (WUO) Selection strategy development IDIC/CS/IC/34 / Consultant for supervision of implementation of civil works under Batch 1 for Individual Zeda Ru, Kvemo Samgori Component 1 Irrigation and IDA / 54560 Post Consultant Open 12,000.00 13,136.62 Signed 2017-09-25 2017-10-13 2017-10-20 2017-10-21 2018-07-08 and Tbisi-Kumisi Irrigation Drainage Improvement Selection Schemes in compliance with the ESMF and EMPs and consultations for Drainage Strategy IDIC/CS/IC/35 / Team Individual Component 1 Irrigation and Leader for Water Users IDA / 54560 Post Consultant Open 10,435.00 12,785.39 Signed 2018-01-22 2018-02-18 2018-02-23 2018-02-26 2018-08-25 Drainage Improvement Development Support Unit Selection Individual IDIC/CS/IC/36 / Assistant Component 3 Project IDA / 54560 Post Consultant Open 32,283.00 29,117.65 Signed 2018-01-08 2018-01-23 2018-01-26 2018-01-27 2019-07-21 Procurement Consultant Management Selection IDIC/CS/IC/37 / Senior Specialist for irrigation Individual Component 1 Irrigation and engineering, operation and IDA / 54560 Post Consultant Open 9,130.00 6,849.32 Signed 2018-01-22 2018-02-18 2018-02-23 2018-02-26 2018-08-25 Drainage Improvement maintenance of Water Users Selection Development Support Unit IDIC/CS/IC/26 / Preparation Individual Component 1 Irrigation and of Environment Management IDA / 54560 Post Consultant Open 20,000.00 0.00 Canceled 2017-11-15 2017-12-18 2018-01-01 2018-01-06 2018-03-07 Drainage Improvement Plan for Batch 2 Selection IDIC/CS/IC/31 / Complete Individual legislative framework Component 1 Irrigation and IDA / 54560 Post Consultant Open 15,600.00 0.00 Canceled 2017-04-03 2017-05-02 2017-05-12 2017-05-15 2017-07-14 analysis regarding Drainage Improvement Selection agricultural land in Georgia IDIC/CS/SSS/14 / Component 1 Irrigation and Accountant and IDA / 54560 Post Direct Selection Direct 13,000.00 5,378.27 Signed 2018-03-20 2018-03-30 2018-05-06 2018-11-02 Drainage Improvement Disbursement Specialist IDIC/CS/SSS/15 / International Lead- Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 42,300.00 56,679.33 Signed 2018-03-29 2018-04-02 2018-04-09 2018-10-06 Consultant Irrigation and Drainage Improvement Drainage IDIC/CS/IC/39 / Deputy Individual Team leader for Water Component 1 Irrigation and IDA / 54560 Post Consultant Open 8,600.00 7,777.78 Signed 2018-05-16 2018-06-13 2018-06-18 2018-06-21 2018-12-21 Users Development Support Drainage Improvement Selection Unit Page 6 IDIC/CS/IC/40 / Water Individual management Specialist Component 1 Irrigation and IDA / 54560 Post Consultant Open 7,400.00 11,351.35 Signed 2018-05-18 2018-06-23 2018-06-28 2018-07-01 2018-12-31 Water Users Development Drainage Improvement Selection Support Unit IDIC/CS/IC/41 / Regional Individual Team Leader for Water Component 1 Irrigation and IDA / 54560 Post Consultant Open 7,400.00 6,671.61 Signed 2018-05-18 2018-06-23 2018-06-28 2018-07-01 2018-12-31 Users Development Support Drainage Improvement Selection Unit for Tbisi-Kumisi IDIC/CS/IC/42 / Regional Individual Team Leader for Water Component 1 Irrigation and IDA / 54560 Post Consultant Open 7,400.00 6,671.61 Signed 2018-05-18 2018-06-23 2018-06-28 2018-07-01 2018-12-31 Users Development Support Drainage Improvement Selection Unit for Zeda Ru IDIC/CS/IC/43 / Regional Individual Team Leader for Water Component 1 Irrigation and IDA / 54560 Post Consultant Open 7,400.00 6,671.61 Signed 2018-05-18 2018-06-23 2018-06-28 2018-07-01 2018-12-31 Users Development Support Drainage Improvement Selection Unit for Zemo Samgori IDIC/CS/IC/44 / Regional Individual Team Leader for Water Component 1 Irrigation and Under IDA / 54560 Post Consultant Open 7,400.00 0.00 2018-05-18 2018-06-23 2018-06-28 2018-07-01 2018-12-31 Users Development Support Drainage Improvement Implementation Selection Unit for Kvemo Samgori IDIC/CS/SSS/-16 / Water Resource Legal advisory Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 45,000.00 0.00 Canceled 2018-06-19 2018-06-19 2018-06-27 2019-06-27 services for Institutional Drainage Improvement Strengthening of GA IDIC/CS/SSS/-16/1 / Water Resource Legal advisory Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 45,000.00 46,741.10 Signed 2018-06-22 2018-06-22 2018-06-30 2019-06-30 services for Institutional Drainage Improvement Strengthening of GA IDIC/CS/SSS/17 / Local-level Component 1 Irrigation and Water Management IDA / 54560 Post Direct Selection Direct 84,300.00 84,370.00 Signed 2018-09-28 2018-10-05 2018-11-01 2020-01-11 Drainage Improvement Institutions Advisor IDIC/CS/SSS/18 / Training Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 4,000.00 3,915.38 Signed 2019-02-08 2019-02-15 2019-03-22 2019-07-20 Course for GA Drainage Improvement IDIC/CS/SSS/19 / Local Component 1 Irrigation and Environmental and Social IDA / 54560 Post Direct Selection Direct 11,200.00 10,344.83 Signed 2019-04-03 2019-04-07 2019-04-18 2019-12-30 Drainage Improvement Specialist Individual IDIC/CS/IC/38 / Financial Component 1 Irrigation and IDA / 54560 Post Consultant Open 17,000.00 0.00 Canceled 2018-03-25 2018-05-01 2018-05-22 2018-06-26 2018-12-23 Manager Drainage Improvement Selection IDIC/CS/SSS/20 / Mid-term Survey for Irrigation and Component 1 Irrigation and Under IDA / 54560 Post Direct Selection Direct 36,000.00 0.00 2019-11-04 2019-11-10 2019-12-12 2020-06-09 Drainage Improvement Drainage Improvement Implementation Component I Page 7