1 BIHAR PANCHYAT STRENGTHENING PROJECT PROCUREMENT PLAN FOR 18 MONTHS I. General 1. Project information: Project Name: : Bihar Panchayat Strengthening Project Country : India Project Code : P102627 Implementing agency for this Procurement Plan : Bihar Gram Swaraj Yojana Society 2. Bank’s approval Date of the procurement Plan Procurement Plan dated : Revision 1 : Revision 2 : Approved by the Bank : on 3. Date of General Procurement Notice: 4. Period covered by this : 18 months II. Goods and Works and Non-consulting services. 1 a) Procurement Methods and Thresholds Method of Threshold Category Procurement (US$ Equivalent) ICB > 40,000,000 Works NCB Up to 40,000,000 Shopping Up to 100,000 ICB > 3,000,000 NCB 100,000 to 3,000,000 Goods and non-consulting services Shopping Up to 100,000 Direct Subject to 3.7 of the guidelines 1 b) Prior Review Threshold - Works : First two contracts irrespective of value and all contracts exceeding US$ 5,000,000. - Goods : First two contracts irrespective of value and all contracts exceeding US$ 500,000 - Direct Contracting: All contracts estimated to cost more than US$ 10,000 2. Pre-qualification. Not Applicable 1 2 3. Reference to (if any) Project Operational/Procurement Manual: BGSYS has prepared a Procurement Manual and agreed with the Bank. All the contracts issued under the project will follow the World Bank’s Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011. In case of any inconsistency between the Procurement Manual or Bihar Government Procurement Procedures and the Bank Guidelines, the latter shall prevail. 4. Any Other Special Procurement Arrangements: A. National Competitive Bidding (NCB) method for procurement and goods and works as per the above value thresholds will be conducted in accordance with paragraph 3.3 and 3.4 of the World Bank Procurement Guidelines and the following provisions:  Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding;  Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids;  No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state owned enterprises, small scale enterprises or enterprises from any given state;  Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/ Employer).  Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project;  Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures. Framework Agreements using DGS&D rate contracts can be used to procure goods up to NCB threshold subject to incorporation of right to audit and Fraud & Corruption clauses.  Two or three envelope system will not be used (except when using e-Procurement system assessed and agreed by the Bank);  No negotiations are conducted even with the lowest evaluated responsive bidders.  Foreign bidders shall not be precluded from bidding. 5. Procurement Packages with Methods and Time Schedule – 2 3 Refer Table - 1 for Works & Goods and Table - 2 for Consulting Services. III. Selection of Consultants 1 a) Selection Methods and Thresholds Method of Procurement Threshold (US$ Equivalent) (a) Quality cum cost Based Selection No threshold (b) Quality Based Selection No threshold (c) Selection Made Under a Fixed Budget No threshold (d) Least Cost Selection No threshold (e) Selection Based on Consultant’s < 300,000 Qualifications (f) Single Source Selection As per Consultant Guidelines Para 3.8 to 3.11 (g) Selection of Individual Consultants As per Consultant Guidelines Para 5.1 to 5.6 1 b) Prior Review Threshold  Consultancy Services: > US$ 200,000 equivalent for firms; and > US$ 100,000 equivalent for individuals  All single source selections of value exceeding US $ 10,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Reference to (if any) Project Operational/ Procurement Manual: BGSYS has prepared the Project Procurement Manual and agreed with the Bank. All the contracts issued under the project will follow the “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011. In case of any inconsistency between the Procurement Manual or Bihar Government Procurement Procedures and the Bank Guidelines, the latter shall prevail. 3 4 Reallocation of Project Funds by Component Non Consult New As per the ancy Allocatio procurem Balance Allocatio services n (INR in ent plan Amount Project Components n (USD in (on Lakhs) (Amount (INR in Million) DAVP (Rs.66 = in Rs Lakhs) Rate 1USD) Lakh) Contrac t) Component 1: 65 42900 33700 9200 1.(a) Construction of Panchayat Sarkar Bhawans. 50 33000 33000 0 1.(b) Functional Panchayats-DLI based 15 9900 700 9200 Component 2: Capacity Building 32.5 21450 9310 900 11240 for Panchayati Raj Institutions 2.1 PRI Institutional Strengthening 29.7 19602 9280 10322 2.1 (a) Core Institutional Capacity 6.7 4422 1825 2597 2.1 (b) Community Engagement 5 3300 1200 2100 2.1 (c) Communications and Mass Media 8 5280 3105 900 1275 2.1 (d) Building GP FM capacity 10 6600 3150 3450 2.2 PRI Capacity development 2.8 1848 30 1818 (sanitation, drinking water) Component 3: Strengthen the capacity to manage 7.5 4950 3950 1000 decentralization (state wise) (Dropped) Component 4 0 0 0 0 : Panchayat Performance Grants Component 5: Project 15 9900 2465 7435 Management Total Project Funding 120 79200 50325 28875 4 5 PROCUREMENT SCHEDULE FOR CONSULTANCY FOR 18 MONTHS COUNTRY : INDIA BORROWER : GOVERNMENT OF INDIA PROJECT : BIHAR PANCHAYAT STRENGTHENING PROJECT DATED : September 20, 2016. [The plan has been prepared by breaking the format in 2 parts: Table-1A & Table- 1B] TABLE – 1A Estimated Procure Pack Method of Procureme Estimate Cost (Lakhs ment age Description Procureme nt d Cost in Instanc No. nt Authority (Lakhs in USD)(1USD es INR) = Rs.66) 1 2 3 4 5 6 7 Third Party Quality BH/BP Audit of the SP/C- Construction of 330 QCBS BGSYS 1 100 1.52 001 PSBs under the Project Third party audit for the BH/BP evaluation of 330 SP/C- functional gram QCBS BGSYS 1 300 4.56 002 panchayat Environment BH/BP Management Plan SP/C- Preparation and QCBS BGSYS 1 300 4.56 003 Monitoring for 330 PSBs Selection of Hiring of Individual BH/BP Individual Consultants - SP/C- Panchayat Facilitation Consultants BGSYS 10 125 1.89 004 (10 Experts individuals) BH/BP CQS after Citizens' Engagement SP/C- Platform approval by BGSYS 1 400 6.06 005 the Bank Integrated Mobile Van Awareness Camaign BH/BP for the Pallate basis on SP/C- two Project Panchayats QCBS BGSYS 1 1200 10.61 006 Districts - Integrated Information Delivery System Development of the Scripts for the Audio BH/BP Selection of and Audio-Visual SP/C- Materials to be Individual BGSYS 1 100 1.52 007 Consultants Produced for Awareness Generation 5 6 Estimated Procure Pack Method of Procureme Estimate Cost (Lakhs ment age Description Procureme nt d Cost in Instanc No. nt Authority (Lakhs in USD)(1USD es INR) = Rs.66) 1 2 3 4 5 6 7 Designs for Training / Awareness Generation Materials including BH/BP Content Generation SP/C- and Ready to Print QCBS BGSYS 1 250 3.03 008 Designs of Monthly Newsletters in the Print Formats BH/BP Production of Audio SP/C- Jingles & Fictional QCBS BGSYS 1 125 1.89 009 Radio Serials BH/BP Production of a Series SP/C- of Two Short Films QCBS BGSYS 1 700 9.09 010 Hiring of Experienced BH/BP Professional for Selection of SP/C- Training of Local Individual BGSYS 1 30 0.45 011 Cultural Troupes for Consultants Street Plays Selection of BH/BP Individual Economist Individual SP/C- with expertise in Public Consultants (3 BGSYS 3 75 1.14 012 Finance individuals consultants) Hiring of 800 BH/BP Accountants for Hand- SP/C- Holding Support to the QCBS BGSYS 1 3,000 45.45 013 GPs under 12 Project Districts Three Individual Consultants for Developing the Code of Selection of Ethics for the Water- Individuals BH/BP Sanitation Programs for Consultants (3 SP/C- Bihar & Do's & Don'ts individuals BGSYS 3 30 0.45 014 for Community with consultants) respect to Water- /CQS- Firm Sanitation Program Implementation / Management BH/BP PMU for State Wide SP/C- PFM Roll Out CQS BGSYS Multiple 400 6.06 015 BH/BP SSS after PFM Software for the SP/C- GPs approval of BGSYS 1 50 0.76 016 Bank 6 7 Estimated Procure Pack Method of Procureme Estimate Cost (Lakhs ment age Description Procureme nt d Cost in Instanc No. nt Authority (Lakhs in USD)(1USD es INR) = Rs.66) 1 2 3 4 5 6 7 BH/BP Statutory Financial SP/C- Audit Support for the QCBS BGSYS 1 800 12.12 017 Project GPs BH/BP Accounting Support for SP/C- the Project GPs QCBS BGSYS 1 1,000 15.15 018 Accountant for Hand- BH/BP Holding Support to GPs SP/C- for the Rest of the 26 QCBS BGSYS 1 1,200 18.18 019 Non-Project Districts in Bihar BH/BP SSS after PMU for e-Panchayat SP/C- Implementation approval of BGSYS 1 500 7.58 020 Bank BH/BP Base Line & End Line SP/C- Surveys for Measuring QCBS BGSYS 1 125 1.89 021 Progress BH/BP Internal Audit for the SP/C- BGSYS Project CQ (Firms) BGSYS 1 8 0.12 022 Management Units BH/BP Statutory Audit to SP/C- BGSYS Project CQ (Firms) BGSYS 1 5 0.08 023 Implementation Units BH/BP HR agency for SP/C- Recruitment QCBS BGSYS 1 175 2.65 024 BH/BP Selection of SP/C- Admin Consultant Individuals BGSYS 1 50 0.76 025 Consultants Individual Consultant BH/BP Selection of for Support to the SP/C- Procurement Unit of Individuals BGSYS 1 20 0.30 026 Consultants BGSYS BH/BP Integrated Web Portal SP/C- for BGSYS CQS BGSYS 1 125 1.89 027 BH/BP Hiring of HR Support SP/C- Agency QCBS BGSYS 1 130 1.97 028 7 8 PROCUREMENT SCHEDULE FOR GOODS FOR 18 MONTHS COUNTRY : INDIA BORROWER : GOVERNMENT OF INDIA PROJECT : BIHAR PANCHAYAT STRENGTHENING PROJECT DATED : September 20, 2016. [The plan has been prepared by breaking the format in 2 parts: Table-2A & Table- 2B] TABLE – 2A Estimate d Cost Method Procure Procure Estim (Lakhs Packag of ment ment ated Description in e No. Procurem Authorit Instanc Cost USD)(1U ent y es (Lakhs SD = in INR) Rs.66) 1 2 3 4 5 6 7 Pilot on Information Seeking Behavior BH/BPSP/ of the Citizens with Information NCB BGSYS 1 300 4.55 G-001 Kiosks Printing of training modules for BH/BPSP/ Capacity Building for Core NCB BGSYS 1 400 6.06 G-002 Institutional Strengthening (Induction) Printing of training modules for BH/BPSP/ Capacity Building Program under NCB BGSYS 1 300 4.55 G-003 Water-Sanitation Printing of training modules for BH/BPSP/ Capacity Building for Core NCB BGSYS 1 300 4.55 G-004 Institutional Strengthening (Refresher) BH/BPSP/ Printing of Pamphlets / Posters / NCB BGSYS 1 200 3.03 G-005 Primers/ Banner for State Events Monthly Printing and Circulation of BH/BPSP/ Newsletters in the Newspaper format NCB BGSYS 1 600 9.09 G-006 for the GPs BH/BPSP/ Wall Paintings on the Aims & Objects NCB BGSYS 1 150 2.27 G-007 of the Project BH/BPSP/ Hoadings, Kiosk and Wallwrap on the NCB BGSYS 1 200 3.03 G-008 Aims & Objects of the Project Print IEC material for integrated BH/BPSP/ mobile complain in two pilot districts NCB BGSYS 1 500 7.58 G-009 and rest of the 10 project districts State Level Awareness Competitions BH/BPSP/ on Promotion of the Objectives of the NCB BGSYS 1 100 1.52 G-010 Project (Non-Consultancy Services) BH/BPSP/ Project POPs , Calendar, Danglers, NCB BGSYS 1 150 2.27 G-011 Posters, Gift Items, Sinages BH/BPSP/ Printing Training modules on NCB BGSYS 1 75 1.14 G-012 Panchayat Financial Management BH/BPSP/ National Office Furniture for DPMUs BGSYS 1 60 0.91 G-013 Shopping 8 9 Estimate d Cost Method Procure Procure Estim (Lakhs Packag of ment ment ated Description in e No. Procurem Authorit Instanc Cost USD)(1U ent y es (Lakhs SD = in INR) Rs.66) 1 2 3 4 5 6 7 BH/BPSP/ Office Furniture for BPMUs NCB BGSYS 1 612 9.27 G-014 BH/BPSP/ National Power Back-Up System for SPMU BGSYS 1 15 0.23 G-015 Shopping BH/BPSP/ Power Back-Up System for DPMUs & NCB BGSYS 1 110 1.67 G-016 BPMUs BH/BPSP/ Laptops for DPMUs & BPMUs Level NCB BGSYS 1 350 5.30 G-017 Positions BH/BPSP/ Desktops for SPMUs, DPMUs & National BGSYS 1 30 0.45 G-018 BPMUs Shopping Mini-Laptops/Tablet for Community BH/BPSP/ Resource Persons (Field Staff tagged NCB BGSYS 1 160 2.42 G-019 with BPMUs) BH/BPSP/ National Printers for DPMUs & BPMUs BGSYS 1 50 0.76 G-020 Shopping BH/BPSP/ National Colour Printers for DPMUs BGSYS 1 30 0.45 G-021 Shopping BH/BPSP/ Procurement of Consumables and National BGSYS 1 40 0.61 G-022 Stationery Items Shopping BH/BPSP/ Housekeeping services (Non- National BGSYS 1 10 0.15 G-023 Consultancy Services) Shopping MS Office Licence for the Desktops / BH/BPSP/ Laptops/Mini-laptop/Tablet at SPMU, NCB BGSYS 1 300 4.55 G-024 DPMUs, BPMUs & CRPs (Gram Panchayat Project Coordinators) 9 10 PROCUREMENT SCHEDULE FOR CONSULTANCY FOR 18 MONTHS [The plan has been prepared by breaking the format in 2 parts: Table-1A & Table-1B] Date : September 20, 2016. TABLE – 1B Contract Value (inclusive of Technical Evaluation (Date) Bank/internal for combined **Prior Review/Post review **WBR No. (only in case of Bank/internal no objection Lakhs (INR) (incl. of taxes) Short listing of EOI (Date) Description of the Activity Evaluation / draft contract Advertising for EOI (Date) Services to be Completed Nationality & Zip Code, if Proposal Submission by for Technical Evaluation Methods of Selection @ Exp. Incurred to Date in Bank/Internal Authority Estimated Cost (INR in **RFP Final Draft to be Contract signing Date Name of Consultant / all applicable taxes) Name of the activity No Objection from RFP Issued (Date) No objection by bidders (Date) PP/R1/R2/R3 prior review) Package No. Sub Approved Co Com Lakhs) Sl. No. (Date). (Date) Comp USA ToR mp ment onent one s nt 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Third Party 30 SN Quality Audit Hiring of Consultancy Services of a firm for P Pri 11/14/ 12/29 1/13/2 1/23/2 1/28/ 2/27/2 3/9/2 3/24/ 4/8/2 4/15/2 Co BH/ Octobe 100 QCBS Jha of the third party quality monitoring of the Comp P or 2016 /2016 017 017 2017 017 017 2017 017 017 mpo BPS r 2016 (SPM 1 Construction construction of 330 Panchayat Sarkar Bhawan onent- nent P/C- - of 330 PSBs Construction under the Project (Phase wise) – 1 - 001 R Finan under the Comp 1 (a): Construction of PSBs 1(a) ce) Project A Third party 15 P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 SN audit for the Octobe 300 QCBS Co BH/ P or 2016 /2016 2016 17 2017 017 2017 017 2017 017 Jha evaluation of The Third Party auditor shall be responsible for Comp r 2016 mpo BPS (SPM 2 330 time to time visit the sites with pre-determined onent- R nent P/C- - functional purposes and submit reports accordingly 1 - 002 Finan gram A 1(b) ce) panchayat Mrina Environment 15 l P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 Management Octobe 300 QCBS Co Sisod BH/ Implementation of environment management P or 2016 /2016 2016 17 2017 017 2017 017 2017 017 Plan Comp r 2016 mpo ia BPS framework (EMF) and natural resource and 3 Preparation onent- nent (SPM P/C- resettlement policy framework (RPF) for and 1 R - -HR 003 construction of 330 panchayat sarkar bhawans Monitoring 1(b) & for 330 PSBs Admi A n) Component 1 (Consultancy Services) Proposed Expenditure as per the Procurement 700 Plan Select ion of Hiring of Panchayat Facilitation Experts for Individ Hiring of Policy Guidance (Acts, Rules & Manuals) / 30 ual Co P Pri 11/14/ 12/9/ 12/19/ 12/24/ 12/29 1/28/2 2/7/2 2/17/ 3/4/2 3/11/2 Om BH/ Individual Development and/or Upgradation Panchayat Octobe 125 Consu mpo Comp P or 2016 2016 2016 2016 /2016 017 017 2017 017 017 Prak BPS Consultants - Financial Management Rules & Manuals with r 2016 ltants nent 4 onent- ash P/C- Panchayat Subsequent Development of Training Modules (10 - 2 (SPM 004 Facilitation for Panchayat Finance Management Program / individ 2.1( - CB) Experts Development of Case Studies / Success uals) a) Stories/Background Materials - (10 individuals) R A Use of technologies for recording social audit CQS Shar Co reports of the vigilance committees, sharing after ad BH/ 01 mpo Citizens' knowledge, expression of point of view with the Comp P appro Pri 10/16/ 10/31 11/10/ 11/15/ 11/20 12/5/2 12/15 12/25 1/9/2 1/16/2 Kum BPS Octobe 400 nent 5 Engagement provision restricted to Panchayati Raj & Rural onent- P val by or 2016 /2016 2016 2016 /2016 016 /2016 /2016 017 017 ar P/C- r 2016 - Platform Development Departments, Govt. of Bihar for 2 the (PM- 005 2.1( the 12 Project Districts. The platform shall Bank IT) & a) facilitate to and fro flow of accurate and precise Om 10 11 Contract Value (inclusive of Technical Evaluation (Date) Bank/internal for combined **Prior Review/Post review **WBR No. (only in case of Bank/internal no objection Lakhs (INR) (incl. of taxes) Short listing of EOI (Date) Description of the Activity Evaluation / draft contract Advertising for EOI (Date) Services to be Completed Nationality & Zip Code, if Proposal Submission by for Technical Evaluation Methods of Selection @ Exp. Incurred to Date in Bank/Internal Authority Estimated Cost (INR in **RFP Final Draft to be Contract signing Date Name of Consultant / all applicable taxes) Name of the activity No Objection from RFP Issued (Date) No objection by bidders (Date) PP/R1/R2/R3 prior review) Package No. Sub Approved Co Com Lakhs) Sl. No. (Date). (Date) Comp USA ToR mp ment onent one s nt 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 information for meaningful citizens' Prak engagement. Under this activity the Society ash shall establish a call center manned with R (SPM appropriate number of experts and human - I/C- resources with technical know-how for the M&E) center to function effectively. This activity shall be outsourced. This shall include development of Mobile Apps for panchayat with necessary software solution to maintain the back-end A activities at the state level call center. The package shall also include the MIS for the ongoing project related programs Mobile Awareness Campaign & On Ground activation of BPSP with the help of Trained 15 Cultural Troupes, Narrowcasting of Audio P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 Octobe 1200 QCBS Jingles & Fictional Serials during the Interlude P or 2016 /2016 2016 17 2017 017 2017 017 2017 017 r 2016 & Screening of Fictional Films under Comp. 2.1(b) -Civic Engagement [The prime focus of the activities shall be to indulge with audiences through structures set of abundant information R on subjects related to participatory planning, Integrated right & entitlements of the individuals & groups, Mobile Van collective decision making & collective action Visha Awareness against collective responsibilities / l Campaign for accountabilities as responsible citizens, Co Sing the Piloted BH/ prioritization of the communities needs through mpo h basis on two Comp BPS engagement of the citizens in logical dialogues nent (SPM 6 Project onent- P/C- and discussions leading to consensus - in the - - Panchayats 2 006 end leaving citizens with inquisitive minds 2.1( Com Districts - forever, thereafter] (For Piloted basis on b) muni Integrated projected panchayats district). This activity catio Information shall be preceded by a Pre-Cursor to Create n) Delivery A Buzz & Necessary Enthusiasm for the System Upcoming Awareness Program for the Gram Panchayats. The Precursor Team shall be Moving in a Branded Four Wheeler Ahead of the Integrated Mobile Van Working to Create Ripples & Inquisitiveness. The Precursor Team shall handover the baton to the Integrated Mobile Van over a period of a day on the 1st Day, before moving ahead to the next Panchayat. Development Selection of Individual Consultant for Select Co of the Scripts Development of Scripts for the Radio Jingles & ion of Om BH/ 15 mpo for the Audio Fictional Radio Serials (Awareness Generation Comp P Individ Po 10/30/ 11/24 12/4/2 12/9/2 12/14 1/13/2 1/23/ 2/2/2 2/17/ 2/24/2 Prak BPS Octobe 100 nent 7 and Audio- Materials including 150 Radio Jingles 130 onent- P ual st 2016 /2016 016 016 /2016 017 2017 017 2017 017 ash P/C- r 2016 - Visual Episodes of Duration of 27 - 30 Minutes of 2 Consu (SPM 007 2.1 Materials to Fictional-Motivational Radio Serials), Two ltants - CB) © be Produced Short Films (Scripts for Motivational-Fictional 11 12 Contract Value (inclusive of Technical Evaluation (Date) Bank/internal for combined **Prior Review/Post review **WBR No. (only in case of Bank/internal no objection Lakhs (INR) (incl. of taxes) Short listing of EOI (Date) Description of the Activity Evaluation / draft contract Advertising for EOI (Date) Services to be Completed Nationality & Zip Code, if Proposal Submission by for Technical Evaluation Methods of Selection @ Exp. Incurred to Date in Bank/Internal Authority Estimated Cost (INR in **RFP Final Draft to be Contract signing Date Name of Consultant / all applicable taxes) Name of the activity No Objection from RFP Issued (Date) No objection by bidders (Date) PP/R1/R2/R3 prior review) Package No. Sub Approved Co Com Lakhs) Sl. No. (Date). (Date) Comp USA ToR mp ment onent one s nt 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 for Short Films of 1 Hour Duration) on Subjects Awareness including Participatory Planning Processes, Generation Collective Decision Making Processes, R Identifying & Fixing Priorities following Democratic Principles of Consistent Public Dialogues & Discussions, Citizens' Engagement in Planning, Implementing & Monitoring the Development Projects, Importance of Understanding the Power vested A in Collective Efforts, Whole Hearted Participation in the Constitutional Bodies - "Gram Sabhas & Ward Sabhas" Designs for 15 P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 Training / Octobe 250 QCBS P or 2016 /2016 2016 17 2017 017 2017 017 2017 017 Awareness r 2016 Visha Generation l Materials R Co Sing Hiring of Consultancy Services for BH/ including mpo h Development of Designs for Training Modules, Comp BPS Content nent (SPM 8 IEC Materials & Monthly Newsletters for Print onent- P/C- Generation - - Formats under Comp 2.1 (c) - Communication 2 008 and Ready to 2.1 Com and Mass media. 1/23/2 4/24/ 2/3/20 24/5/2 4/13/ 5/11/2 10/14 11/9/ Print Designs A © muni of Monthly 014 2014 15 015 2015 015 /2015 2015 catio Newsletters n) in the Print Formats Hiring of Consultancy Services for Production of Radio Jingles & Fictional Radio Serials in 15 P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 Visha Accordance with the Scripts with an Aim & Octobe 125 QCBS P or 2016 /2016 2016 17 2017 017 2017 017 2017 017 l Object of Providing the Citizens with r 2016 Co Sing Necessary Information on their Rights, BH/ Production of mpo h Entitlements, Responsibilities as Citizens, Comp BPS Audio Jingles R nent (SPM 9 Importance of Participatory Planning & onent- P/C- & Fictional - - Requirements for Collective Actions for 2 009 Radio Serials 2.1 Com Necessary Changes in the Appalling, Diabolic © muni & Distraughtly Status Quo, Imminent 1/23/2 4/24/ 2/3/20 24/5/2 4/13/ 5/11/2 10/14 11/9/ catio Requirements for In Practice Administrative & A 014 2014 15 015 2015 015 /2015 2015 n) Fiscal Decentralization, et al under comp 2.1 (c) - Communication and Mass Media. Hiring of Consultancy Services for Production Visha of a Series of two Motivational-Fictional Short 15 l Film(s) in Accordance with the Scripts with an P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 Co Sing Octobe 700 QCBS BH/ Production of Aim & Object of Providing the Citizens with P or 2016 /2016 2016 17 2017 017 2017 017 2017 017 mpo h Comp r 2016 BPS a Series of Necessary Information on their Rights, nent (SPM 10 onent- P/C- Two Short Entitlements, Responsibilities as Citizens, - - 2 010 Films Importance of Participatory Planning & 2.1 Com Requirements for Collective Actions for Much © muni Required Changes in the Appalling, Diabolic, catio Distraughtly, Grim & Gruesome Social n) 12 13 Contract Value (inclusive of Technical Evaluation (Date) Bank/internal for combined **Prior Review/Post review **WBR No. (only in case of Bank/internal no objection Lakhs (INR) (incl. of taxes) Short listing of EOI (Date) Description of the Activity Evaluation / draft contract Advertising for EOI (Date) Services to be Completed Nationality & Zip Code, if Proposal Submission by for Technical Evaluation Methods of Selection @ Exp. Incurred to Date in Bank/Internal Authority Estimated Cost (INR in **RFP Final Draft to be Contract signing Date Name of Consultant / all applicable taxes) Name of the activity No Objection from RFP Issued (Date) No objection by bidders (Date) PP/R1/R2/R3 prior review) Package No. Sub Approved Co Com Lakhs) Sl. No. (Date). (Date) Comp USA ToR mp ment onent one s nt 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Situation, that, off late has become Self- Resistant and Averse in a way that the very thinking of any change is looked at Scornfully. R The devilish Status Quo is now nearly treated as Sacrosanct, Imminent Requirements for In- Practice Administrative & Fiscal Decentralization, et al as a Step-by-Step Guide for the Rural Audiences on Righteous Action 1/23/2 4/24/ 2/3/20 12/17/ 5/25/ Required for a nearly Synonym to Golden A 014 2014 15 2015 2016 Dawn (Communication people for participating Planning) under comp 2.1 (c) - Communication and Mass media. Hiring of Experienced Professional Performing Select Art Troupe from Institution Like National School ion of 15 of Drama, New Delhi or equivalent for P Individ Po 10/30/ 11/24 12/4/2 12/9/2 12/14 1/13/2 1/23/ 2/2/2 2/17/ 2/24/2 Octobe 30 necessary research for Developing Scripts for P ual st 2016 /2016 016 016 /2016 017 2017 017 2017 017 r 2016 Visha Plays & Accordingly Training the Locally Consu Hiring of l Identified Cultural Troupes on Subjects like ltants Experienced Co Sing Collective Action through Participation for BH/ Professional mpo h Raising Voice Collectively in Public Forums & Comp BPS for Training R nent (SPM 11 PRIs Meeting, especially in Gram Sabhas & onent- P/C- of Local - - Ward Sabhas, as the Most Potent Tool for 2 011 Cultural 2.1 Com Creating the Required Pressure on the System Troupes for © muni to Yield to the Individual & Collective Rights, Street Plays catio Participatory Planning as a Tool for Addressing 1/23/2 4/24/ 2/3/20 12/17/ 5/25/ n) the Local Needs including the Demonstration A of the Processes for Participatory Planning & 014 2014 15 2015 2016 Prioritization of Need Comp . 2.1 (c) - Communication and Mass Media. Consultancy Services of 3 individuals Select consultants with expertise in Public Finance to ion of act as Panchayat Finance Coordinator for Individ assisting the state through the Society in ual developing understanding on Investments Vs. 15 Consu P Po 10/30/ 11/24 12/4/2 12/9/2 12/14 1/13/2 1/23/ 2/2/2 2/17/ 2/24/2 Co SN Individual Outcomes, Smoothening Fund Flow Octobe 75 ltants BH/ P st 2016 /2016 016 016 /2016 017 2017 017 2017 017 mpo Jha Economist Mechanism, Conduct Studies on Diversification Comp r 2016 (3 BPS nent (SPM 12 with expertise of Fund Usages & Subsequent Gross onent- individ P/C- - - in Public Resultants, Socio-Economic Impacts of the 2 uals 012 2.1( Finan Finance Grant-in-Aids from the Centre & State to the consul d) ce) GPs (Development of Social Capitals, tants) Economic Advancements, Community Assets R Creation & Usages, Sustainability Factors for the Positive Changes at the Levels of GPs, et A al) Hiring of 800 Services of qualified manpower (accountants) Co Shar BH/ 15 Accountants for panchayat financial management (software Comp P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 mpo ad BPS Octobe 3,000 QCBS 13 for Hand- based) in the 12 project districts with 1 for onent- P or 2016 /2016 2016 17 2017 017 2017 017 2017 017 nent Kum P/C- r 2016 Holding every 4 GPs for a period of 24 months 2 - ar 013 Support to @Rs.15,000/- per month = 800 accountants X 2.1( (PM- 13 14 Contract Value (inclusive of Technical Evaluation (Date) Bank/internal for combined **Prior Review/Post review **WBR No. (only in case of Bank/internal no objection Lakhs (INR) (incl. of taxes) Short listing of EOI (Date) Description of the Activity Evaluation / draft contract Advertising for EOI (Date) Services to be Completed Nationality & Zip Code, if Proposal Submission by for Technical Evaluation Methods of Selection @ Exp. Incurred to Date in Bank/Internal Authority Estimated Cost (INR in **RFP Final Draft to be Contract signing Date Name of Consultant / all applicable taxes) Name of the activity No Objection from RFP Issued (Date) No objection by bidders (Date) PP/R1/R2/R3 prior review) Package No. Sub Approved Co Com Lakhs) Sl. No. (Date). (Date) Comp USA ToR mp ment onent one s nt 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 the GPs 24 months X Rs.15,000/- per month = d) IT) & under 12 Rs.28,80,00,000/- Om Project R Prak Districts ash (SPM - I/C- M&E) SN A Jha (SPM - Finan ce) Three Select Individual ion of Consultants Individ for uals Developing Consu 15 the Code of ltants Hiring of short term Individual Consultant / P Decem Po 12/30/ 1/24/ 2/3/20 2/8/20 2/13/ 3/15/2 3/25/ 4/4/2 4/19/ 4/26/2 Ethics for the 30 (3 Specialist to provide assistance on Developing P ber st 2016 2017 17 17 2017 017 2017 017 2017 017 Water- individ Community Training Materials for Water- 2016 Om BH/ Sanitation uals Co Sanitation Program understanding and Hard- Comp Prak BPS Programs for consul mpo 14 Hitting Information for the Communities' onent- ash P/C- Bihar & Do's tants) nent Understanding with respect to Water-Sanitation 2 (SPM 014 & Don'ts for /CQS- -2.2 Program Implementation, and Business Code - CB) Community Firm for the Program Implementation & with respect Management Units at the State & Districts R to Water- Sanitation Program Implementati A on / Management Component 2 (Consultancy Services) Proposed Expenditure as per the Procurement 5,385 Plan Project Management Unit at the SPMU for the SN PMU for roll out & monitoring of the PFM Program. The Jha State Wide consultancy service provider shall provide the 15 (SPM BH/ PFM Roll Out services of financial experts and IT experts for P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 Co - Comp P Octobe 400 CQS or 2016 /2016 2016 17 2017 017 2017 017 2017 017 BPS (IT expert , managing PFM related services and civil r 2016 mpo Finan 15 onent- P/C- Financial engineers for support of third party quality audit nent ce), 3 015 expert and , training programs for elected representatives -3 Rupa Civil (Mukhiya, Upmukhiya & Panchayat Secretary), Shre engineer) accountants to be hired under the project for e R GPs support, contract management for (PM- 14 15 Contract Value (inclusive of Technical Evaluation (Date) Bank/internal for combined **Prior Review/Post review **WBR No. (only in case of Bank/internal no objection Lakhs (INR) (incl. of taxes) Short listing of EOI (Date) Description of the Activity Evaluation / draft contract Advertising for EOI (Date) Services to be Completed Nationality & Zip Code, if Proposal Submission by for Technical Evaluation Methods of Selection @ Exp. Incurred to Date in Bank/Internal Authority Estimated Cost (INR in **RFP Final Draft to be Contract signing Date Name of Consultant / all applicable taxes) Name of the activity No Objection from RFP Issued (Date) No objection by bidders (Date) PP/R1/R2/R3 prior review) Package No. Sub Approved Co Com Lakhs) Sl. No. (Date). (Date) Comp USA ToR mp ment onent one s nt 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 consultancy firms for assisting panchayats in Acco maintaining the books of accounts, statutory untin financial audit, software based accounting and g- its state wide roll out, capacity building on use CB) of the PFM software including troubleshooting & A & onsite support as may be required). Om Prak ash (SPM -CB) SSS SN 01 after Jha P Novem Pri 10/16/ 10/31 11/10/ 11/15/ 11/20 12/5/2 12/15 12/25 1/9/2 1/16/2 50 appro (SPM P ber or 2016 /2016 2016 2016 /2016 016 /2016 /2016 017 017 val of - 2016 BH/ Bank Co Finan PFM Software for the Accounting and Financial Comp BPS mpo ce) & 16 Software for Management System for the Panchayats in onent- P/C- R nent Shar the GPs Bihar. 3 016 -3 ad Kum ar A (PM- IT) Hiring of Firm(s) for Annual Audit Coverage for 01 all the Panchayats of the 12 Project Districts SN Statutory P Decem Pri 12/16/ 1/30/ 2/14/2 2/24/2 3/1/2 3/31/2 4/10/ 4/25/ 5/10/ 5/17/2 BH/ (Phase wise)-Selection of multiple agency for 800 QCBS Co Jha Financial Comp P ber or 2017 2018 018 018 018 018 2018 2018 2018 018 BPS performing task in multiple districts mpo (SPM 17 Audit Support onent- 2017 P/C- (@Rs.5000/- Per Panchayat Per year for 5 nent - for the 3 017 Years, 3191 GPs in 12 Project District) = 3191 R -3 Finan Project GPs GPs X 5 Years X Rs.5000/- per annum = ce) Rs.7,97,75,000/= A Providing Assistance to the all Panchayats in 30 P Pri 11/14/ 12/29 1/13/2 1/23/2 1/28/ 2/27/2 3/9/2 3/24/ 4/8/2 4/15/2 the 12 Project Districts in Preparing and Octobe 1,000 QCBS P or 2016 /2016 017 017 2017 017 017 2017 017 017 SN Maintaining their Books of Accounts (Phase r 2016 BH/ Accounting Co Jha wise)-Selection of multiple agency for Comp R BPS Support for mpo (SPM 18 performing task in multiple districts onent- P/C- the Project nent - (@Rs.6000/- Per Panchayat Per year for 5 3 018 GPs -3 Finan Years, 3191 panchayats in 12 Project District) A ce) = 3191 GPs X 5 Years X Rs.6000/- per annum = Rs.9,57,30,000/- Accountant Services of qualified manpower for the 30 SN P Pri 11/14/ 12/29 1/13/2 1/23/2 1/28/ 2/27/2 3/9/2 3/24/ 4/8/2 4/15/2 for Hand- panchayat financial management (software Octobe 1,200 QCBS Jha P or 2016 /2016 017 017 2017 017 017 2017 017 017 Holding based) including hand-holding support for a r 2016 (SPM BH/ Support to period of 12 months. Each of the accountants Co - Comp BPS GPs for the shall be responsible to help a minimum of 8 R mpo Finan 19 onent- P/C- Rest of the panchayats for assisting develop in-house nent ce), 3 019 26 Non- capacity for panchayat financial management. -3 Rupa Project This assistance shall be applicable for the Shre A Districts in remaining 26 districts (38 Districts - 12 Project e Bihar Districts) with 5200 Gram Panchayats. The (PM- 15 16 Contract Value (inclusive of Technical Evaluation (Date) Bank/internal for combined **Prior Review/Post review **WBR No. (only in case of Bank/internal no objection Lakhs (INR) (incl. of taxes) Short listing of EOI (Date) Description of the Activity Evaluation / draft contract Advertising for EOI (Date) Services to be Completed Nationality & Zip Code, if Proposal Submission by for Technical Evaluation Methods of Selection @ Exp. Incurred to Date in Bank/Internal Authority Estimated Cost (INR in **RFP Final Draft to be Contract signing Date Name of Consultant / all applicable taxes) Name of the activity No Objection from RFP Issued (Date) No objection by bidders (Date) PP/R1/R2/R3 prior review) Package No. Sub Approved Co Com Lakhs) Sl. No. (Date). (Date) Comp USA ToR mp ment onent one s nt 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 total financial implication shall thus be = 650 Acco accountants X 12 months X Rs.15000/- per untin month = Rs.11,70,00,000/- g- CB) & Om Prak ash (SPM -CB) SSS SN 01 after Jha P Novem Pri 11/16/ 12/1/ 12/11/ 12/16/ 12/21 1/5/20 1/15/ 1/25/ 2/9/2 2/16/2 The Selected Agency shall be responsible for 500 appro (SPM P ber or 2016 2016 2016 2016 /2016 17 2017 2017 017 017 establishing Project Management Unit at the val of - 2016 BH/ PMU for e- SPMU for the roll out & monitoring of the e- Bank Co Finan Comp BPS Panchayat Panchayat Program. The consultancy service mpo ce) & 20 onent- P/C- Implementati provider shall provide the services of financial R nent Shar 3 020 on experts and IT experts for managing e- -3 ad Panchayat Implementation and its integration Kum with PFM software. ar A (PM- IT) Component 3 (Consultancy Services) Proposed Expenditure as per the Procurement 3,950 Plan 15 P Pri 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 Om Base Line & Octobe 125 QCBS BH/ Hiring services of survey agency for data P or 2016 /2016 2016 17 2017 017 2017 017 2017 017 Co Prak End Line Comp r 2016 BPS collection for Base Line & End-line Studies in mpo ash 21 Surveys for onent- P/C- accordance with the Results Framework for R nent (SPM Measuring 4 021 BPSP including Report writing . -4 - Progress A M&E) Internal Audit 30 CQ SN Hiring of CA firm for statutory audit of BGSYS P Po 11/14/ 11/29 12/9/2 12/14/ 12/19 1/3/20 1/13/ 1/23/ 2/7/2 2/14/2 BH/ for the Octobe 8 (Firms Co Jha Management Units (SPMU & DPMUs) - The Comp P st 2016 /2016 016 2016 /2016 17 2017 2017 017 017 BPS BGSYS r 2016 ) mpo (SPM 22 lowest accounting unit under the project shall onent- R P/C- Project nent - be the DPMUs (@rs.30000 for 12 district and 1 4 022 Management -4 Finan SPMU unit per annum) A Units ce) Statutory 01 SN CQ BH/ Audit to P Decem Po 12/16/ 12/31 1/10/2 1/15/2 1/20/ 2/4/20 2/14/ 2/24/ 3/11/ 3/18/2 Co Jha Hiring of CA (Individual Consultants) for Comp 5 (Firms BPS BGSYS P ber st 2016 /2016 017 017 2017 17 2017 2017 2017 017 mpo (SPM 23 Statutory Audit for BGSYS SPMU & DPMUs onent- ) P/C- Project 2016 nent - (12,500 per unit per year) 4 023 Implementati R -4 Finan on Units A ce) BH/ 15 Co Mrina HR agency Comp P Po 10/30/ 12/14 12/29/ 1/8/20 1/13/ 2/12/2 2/22/ 3/9/2 3/24/ 3/31/2 BPS Hiring of HR agency for staff recruitment Octobe 175 QCBS mpo l 24 for onent- P st 2016 /2016 2016 17 2017 017 2017 017 2017 017 P/C- against approx 1500 positions in BGSYS r 2016 nent Sisod Recruitment 4 024 R -4 ia 16 17 Contract Value (inclusive of Technical Evaluation (Date) Bank/internal for combined **Prior Review/Post review **WBR No. (only in case of Bank/internal no objection Lakhs (INR) (incl. of taxes) Short listing of EOI (Date) Description of the Activity Evaluation / draft contract Advertising for EOI (Date) Services to be Completed Nationality & Zip Code, if Proposal Submission by for Technical Evaluation Methods of Selection @ Exp. Incurred to Date in Bank/Internal Authority Estimated Cost (INR in **RFP Final Draft to be Contract signing Date Name of Consultant / all applicable taxes) Name of the activity No Objection from RFP Issued (Date) No objection by bidders (Date) PP/R1/R2/R3 prior review) Package No. Sub Approved Co Com Lakhs) Sl. No. (Date). (Date) Comp USA ToR mp ment onent one s nt 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 (SPM -HR A & Admi n) Select Mrina 15 ion of l P Novem Individ Po 11/30/ 12/25 1/4/20 1/9/20 1/14/ 2/13/2 2/23/ 3/5/2 3/20/ 3/27/2 Sisod BH/ 50 Co Hiring of short term Individual Consultants / Comp P ber uals st 2016 /2016 17 17 2017 017 2017 017 2017 017 ia BPS Admin mpo 25 Specialists for assistance to Admin units of onent- 2016 Consu (SPM P/C- Consultant nent BGSYS 4 ltants -HR 025 -4 R & Admi A n) Select Jaide Individual ion of o 15 Consultant P Individ Po 10/30/ 11/24 12/4/2 12/9/2 12/14 1/13/2 1/23/ 2/2/2 2/17/ 2/24/2 Sinh BH/ Octobe 20 Co for Support to Hiring of short term consultants/Specialists to Comp P uals st 2016 /2016 016 016 /2016 017 2017 017 2017 017 a BPS r 2016 mpo 26 the provide assistance of Procurement to support onent- Consu (SPM P/C- nent Procurement the respective units of BGSYS 4 ltants - 026 -4 Unit of R Proc BGSYS urem A ent) 01 Shar P Po 3/16/2 3/31/ 4/10/2 4/15/2 4/20/ 5/5/20 5/15/ 5/25/ 6/9/2 6/16/2 CS March 125 CQS ad P st 016 2016 016 016 2016 16 2016 2016 016 016 M 2016 Kum tech R ar nolo BH/ Development and Management of Integrated Co (PM- Integrated Comp 130 gies BPS Web Portal that includes HR – MIS, Training – mpo IT) & 27 Web Portal onent- 392 Pvt. P/C- MIS, Online Biometric Attendance, etc. for the nent Om for BGSYS 4 04 60 Ltd./ 027 Society 3/15/2 3/18/ 3/21/2 3/29/2 3/29/ 4/26/2 5/2/2 5/5/2 5/5/2 5/19/2 -4 Prak A March Indi 016 2016 016 016 2016 016 016 016 016 016 ash 2016 a/80 (SPM 000 - I/C- 1 M&E) 01 Mrina P Novem Pri 11/16/ 12/31 1/15/2 1/25/2 1/30/ 3/1/20 3/11/ 3/26/ 4/10/ 4/17/2 l 130 QCBS P ber or 2016 /2016 017 017 2017 17 2017 2017 2017 017 Sisod BH/ Co Hiring of HR Pay Roll & Performance Management of the Comp 2016 ia BPS mpo 28 Support BGSYS Staff at all levels (1575 employee for onent- R (SPM P/C- nent Agency 18 Month- @ Rs.450 Per person per month) 4 -HR 028 -4 & A Admi n) Component 4 (Consultancy Services) Proposed Expenditure as per the Procurement 643 Plan 17 18 18 19 PROCUREMENT SCHEDULE FOR GOODS FOR 18 MONTHS [The plan has been prepared by breaking the format in 2 parts: Table-1A & Table-1B] Date : September 20, 2016. TABLE – 2B Bids Contractor/Nationality & Code in case applicable taxes)(INR in Method of Procurement (Rs in Lakhs) (inclusive Contract Signed (Date) Exp. Incur-red to Date Contract Award (Date) Date of completion of Description of Goods Objection to Bidding Value (INR in lakhs) Bid evaluation Date Estimated Contract Prior Review/ Post Document (Date)** Preparation of Bid Name of the activity Bank/Internal No. Document (Date) Bank/internal No (inclusive of all of prior review) Contract Value PP/A/R1/R2/R3 Opened on (Date) of taxes/ Price Comments/Sub Invitation (Date) Package No. Components escalation) Comments Comments objection Contract ZIP (only Name of Review Lakhs) SL No. (LoA) **WBR No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 October Vishal 11/14/2 12/4/2 1/3/20 1/18/2 1/28/ 2/17/ 2/24/2 PP 300 NCB Prior 25, 016 016 17 017 2017 2017 017 Singh Pilot on Information 2016 (SPM- BH/BP Public Information Kiosk For 100 Com Comp Seeking Behavior of the R Communic 1 SP/G- Panchayats to be made Functional pone onent- Citizens with Information ation) & 001 on Pilot Basis nt-2 2.1(a) Kiosks Sharad A Kumar (PM-IT) Printing of training October 11/14/2 12/4/2 1/3/20 1/18/2 1/28/ 2/17/ 2/24/2 modules for Capacity PP 400 NCB Prior 25, 016 016 17 017 2017 2017 017 BH/BP Printing of Training Modules under Com Comp Om Building for Core 2016 2 SP/G- Capacity Building Program pone onent- Prakash Institutional R 002 (Induction) nt-2 2.1(a) (SPM- CB) Strengthening (Induction) A Printing of Training Modules under Novemb Printing of training 11/21/2 12/11/ 1/10/2 1/25/2 2/4/2 2/24/ 3/3/20 BH/BP Capacity Building Program Com PP 300 NCB Prior er 1, 016 2016 017 017 017 2017 17 Comp Om modules for Capacity 2016 3 SP/G- (Capacity Development under pone onent- Prakash Building Program under 003 Water - Sanitation in12 Project nt-2 R 2.1(a) (SPM- CB) Water-Sanitation Districts) A Printing of training April 15, 5/5/201 5/25/2 6/24/2 7/9/20 7/19/ 8/8/2 8/15/2 PP 300 NCB Prior 7 017 017 17 2017 017 017 modules for Capacity 2017 BH/BP Printing of Training Modules under Com Comp Om Building for Core R 4 SP/G- Capacity Building Program pone onent- Prakash Institutional 004 (Refresher) nt-2 2.1(a) (SPM- CB) Strengthening A (Refresher) Printing of awareness generation January 2/4/201 2/24/2 3/26/2 4/10/2 4/20/ 5/10/ 5/17/2 materials on the importance of PP 200 NCB Prior 15, 7 017 017 017 2017 2017 017 participatory planning, participatory 2017 planning processes, collective Vishal BH/BP Printing of Pamphlets / participation in the meeting of gram Com Comp Singh 5 SP/G- Posters / Primers/ sabhas & ward sabhas, collective pone R onent- (SPM- 005 Banner for State Events decision making processes, nt-2 2.1© Communic achievements under the project, ation) etc. for the state sponsored events during the course of the project A duration Printing of Monthly newsletter as prepared for Awareness Generation August 11/1 Monthly Printing and 9/4/201 9/24/2 10/24/ 11/8/2 12/8/ 12/15/ Vishal Program and delivery of the same PP 600 NCB Prior 15, 6 016 2016 016 8/20 2016 2016 BH/BP Circulation of Com 2016 16 Comp Singh up to the level of block 6 SP/G- Newsletters in the pone onent- (SPM- headquarters from where the copies 006 Newspaper format for nt-2 R 2.1© Communic shall be picked up by the authorized the GPs ation) 19 representative by the Head of the A Gram Panchayats for distribution in 20 Bids Contractor/Nationality & Code in case applicable taxes)(INR in Method of Procurement (Rs in Lakhs) (inclusive Contract Signed (Date) Exp. Incur-red to Date Contract Award (Date) Date of completion of Description of Goods Objection to Bidding Value (INR in lakhs) Bid evaluation Date Estimated Contract Prior Review/ Post Document (Date)** Preparation of Bid Name of the activity Bank/Internal No. Document (Date) Bank/internal No (inclusive of all of prior review) Contract Value PP/A/R1/R2/R3 Opened on (Date) of taxes/ Price Comments/Sub Invitation (Date) Package No. Components escalation) Comments Comments objection Contract ZIP (only Name of Review Lakhs) SL No. (LoA) **WBR No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Panchayats .( 20 Pc X Rs. 15 X 8391 Panchayats X 30 Month) Wall Painting of 5 Important August 11/1 9/4/201 9/24/2 10/24/ 11/8/2 12/8/ 12/15/ Location in the Project Panchayats PP 150 NCB Post 15, 6 016 2016 016 8/20 2016 2016 (Each wall painting of 200 sq. ft.). 2016 16 The subject addressed through this Vishal intervention shall be importance of R BH/BP Wall Paintings on the Com Comp Singh participatory planning, participatory 7 SP/G- Aims & Objects of the pone onent- (SPM- planning processes, collective 007 Project nt-2 2.1© Communic participation in the meeting of gram ation) sabhas & ward sabhas, collective decision making processes, rights / A entitlements / responsibilities of citizen, etc. -Component 2.1 © August 11/1 9/4/201 9/24/2 10/24/ 11/8/2 12/8/ 12/15/ PP 200 NCB Post 15, 6 016 2016 016 8/20 2016 2016 2016 16 It is important to keep people Vishal BH/BP Hoadings, Kiosk and reminding of the priorities under the Com Comp Singh 8 SP/G- Wallwrap on the Aims & Panchayati Raj System. The best pone R onent- (SPM- 008 Objects of the Project ways of doing it is hoarding, nt-2 2.1© Communic wallwraps & information kiosks ation) A August 11/1 9/4/201 9/24/2 10/24/ 11/8/2 12/8/ 12/15/ PP 500 NCB Prior 15, 6 016 2016 016 8/20 2016 2016 2016 16 Print IEC material for Vishal Printing of Information education BH/BP integrated mobile Com Comp Singh and communication material for the R 9 SP/G- complain in two pilot pone onent- (SPM- distribution in the Panchayats for 12 009 districts and rest of the nt-2 2.1© Communic project districts 10 project districts ation) A August 11/1 9/4/201 9/24/2 10/24/ 11/8/2 12/8/ 12/15/ PP 100 NCB Post 15, 6 016 2016 016 8/20 2016 2016 State Level Awareness 2016 16 Vishal Competitions on Marathon, Cycle Competitions BH/BP Com Comp Singh Promotion of the tagged with State Level National / R 10 SP/G- pone onent- (SPM- Objectives of the Project International Festivals twice a year 010 nt-2 2.1© Communic (Non-Consultancy on outsourced arrangements ation) Services) A These are important tools for Novemb 12/15/2 1/4/20 2/3/20 2/18/2 2/28/ 3/20/ 3/27/2 creating brand out of the PP 150 NCB Post er 25, 016 17 17 017 2017 2017 017 Vishal Project POPs , 2016 BH/BP commitments from the project to the Com Comp Singh Calendar, Danglers, 11 SP/G- people. These tools directly / pone R onent- (SPM- Posters, Gift Items, 011 indirectly helps people remain nt-2 2.1(d) Communic Sinages aware of the Project Aims & ation) Objects. A 20 21 Bids Contractor/Nationality & Code in case applicable taxes)(INR in Method of Procurement (Rs in Lakhs) (inclusive Contract Signed (Date) Exp. Incur-red to Date Contract Award (Date) Date of completion of Description of Goods Objection to Bidding Value (INR in lakhs) Bid evaluation Date Estimated Contract Prior Review/ Post Document (Date)** Preparation of Bid Name of the activity Bank/Internal No. Document (Date) Bank/internal No (inclusive of all of prior review) Contract Value PP/A/R1/R2/R3 Opened on (Date) of taxes/ Price Comments/Sub Invitation (Date) Package No. Components escalation) Comments Comments objection Contract ZIP (only Name of Review Lakhs) SL No. (LoA) **WBR No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Printing of Training Modules on Novemb Panchayat Financial Management 12/15/2 1/4/20 2/3/20 2/18/2 2/28/ 3/20/ 3/27/2 PP 75 NCB Post er 25, 016 17 17 017 2017 2017 017 in Accordance with the Budget, 2016 Accounts & Audit Manual of the BH/BP Printing Training State @ Rs.250/- for the Intensive Com R Comp Om 12 SP/G- modules on Panchayat Training of Mukhiya, Up-Mukhiya & pone onent- Prakash 012 Financial Management Panchayat Secretary for the Block nt-2 2.1(d) (SPM- CB) Training Program (8191 Panchayat X 3 + 1450 Accountant + 3377 A Additional for the District & Block Level Officials) Component -2 (Goods) Proposed Expenditure as per the Procurement Plan 3275 Nation Novemb 12/1 al 11/16/2 11/24/ 12/2/2 12/3/2 12/8/ 12/22/ Mrinal BH/BP Purchase of Office Furniture & Com PP 60 Post er 1, 016 2016 016 016 2016 5/20 2016 Comp Office Furniture for Shoppi 16 Sisodia 13 SP/G- Fixtures for 12 District Units (5 lakh pone 2016 onent- DPMUs ng (SPM -HR 013 per District) nt-4 4 R & Admin) A Februar 2/21/20 3/13/2 4/12/2 4/27/2 5/7/2 5/27/ 6/3/20 Mrinal BH/BP Purchase of Office Furniture & Com PP 612 NCB Prior y 1, 17 017 017 017 017 2017 17 Comp Office Furniture for 2017 Sisodia 14 SP/G- Fixtures for 204 Block Units (3 Lakh pone onent- BPMUs (SPM -HR 014 per block) nt-4 R 4 & Admin) A Nation Septem 10/2 10/2 al 9/30/20 10/8/2 10/16/ 10/17/ 11/5/2 Mrinal BH/BP Purchase of Power Back Up Com PP 15 Post ber 15, 16 016 2016 2016 2/20 9/20 016 Comp Power Back-Up System Shoppi 16 16 Sisodia 15 SP/G- System for State Management pone 2016 onent- for SPMU ng (SPM -HR 015 Units nt-4 4 R & Admin) A Februar Purchase of Power Back Up 2/21/20 3/12/2 4/11/2 4/26/2 5/6/2 5/26/ 6/2/20 Mrinal BH/BP Com PP 110 NCB Prior y 1, 16 016 016 016 016 2016 16 Comp Power Back-Up System System for 12 District and 204 2016 Sisodia 16 SP/G- pone onent- for DPMUs & BPMUs Blocks management Units (50 (SPM -HR 016 nt-4 R 4 Thousand per unit) & Admin) A Decemb Mrinal 1/4/201 1/24/2 2/23/2 3/10/2 3/20/ 4/9/2 4/16/2 PP 350 NCB Prior er 15, 7 017 017 017 2017 017 017 Sisodia Purchase of 647-Laptops District & BH/BP Com 2016 Comp (SPM -HR Laptops for DPMUs & Block Units Against 647 sanction 17 SP/G- pone R onent- & Admin) & BPMUs Level Positions positions in BGSYS (@ 55 017 nt-4 4 Sharad thousand per post) A Kumar (PM-IT) Nation Mrinal Decemb al 12/30/2 1/7/20 1/15/2 1/16/2 1/21/ 1/28/ 2/4/20 Sisodia PP 30 Post er 15, 016 17 017 017 2017 2017 17 BH/BP Purchase of 56- Desktops for Com Shoppi Comp (SPM -HR Desktops for SPMUs, 2016 18 SP/G- BGSYS Management Unit (@ 53 pone ng onent- & Admin) & DPMUs & BPMUs 018 thousand per Position) nt-4 R 4 Sharad Kumar A (PM-IT) 21 22 Bids Contractor/Nationality & Code in case applicable taxes)(INR in Method of Procurement (Rs in Lakhs) (inclusive Contract Signed (Date) Exp. Incur-red to Date Contract Award (Date) Date of completion of Description of Goods Objection to Bidding Value (INR in lakhs) Bid evaluation Date Estimated Contract Prior Review/ Post Document (Date)** Preparation of Bid Name of the activity Bank/Internal No. Document (Date) Bank/internal No (inclusive of all of prior review) Contract Value PP/A/R1/R2/R3 Opened on (Date) of taxes/ Price Comments/Sub Invitation (Date) Package No. Components escalation) Comments Comments objection Contract ZIP (only Name of Review Lakhs) SL No. (LoA) **WBR No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Decemb Mrinal 1/4/201 1/24/2 2/23/2 3/10/2 3/20/ 4/9/2 4/16/2 PP 160 NCB Prior er 15, 7 017 017 017 2017 017 017 Sisodia Mini-Laptops/Tablet for BH/BP Purchase of Mini Laptop/Tablet for Com 2016 Comp (SPM -HR Community Resource 19 SP/G- 797 CRP (@ 20 Thousand per pone R onent- & Admin) & Persons (Field Staff 019 Position) nt-4 4 Sharad tagged with BPMUs) A Kumar (PM-IT) Nation Mrinal Februar al 2/16/20 2/24/2 3/4/20 3/5/20 3/10/ 3/17/ 3/24/2 Sisodia PP 50 Post y 1, 17 017 17 17 2017 2017 017 BH/BP Purchase of 216- Printers for Block Com Shoppi Comp (SPM -HR Printers for DPMUs & 2017 20 SP/G- and District Units (@ 23 Thousand pone ng onent- & Admin) & BPMUs 020 Per unit) nt-4 R 4 Sharad Kumar A (PM-IT) Nation Mrinal March al 3/30/20 4/7/20 4/15/2 4/16/2 4/21/ 4/28/ 5/5/20 Sisodia PP 30 Post 15, 17 17 017 017 2017 2017 17 BH/BP Com Shoppi Comp (SPM -HR Colour Printers for Purchase of 12- Printers for District 2017 21 SP/G- pone ng onent- & Admin) & DPMUs Units (@2.5 lakh per unit) 021 nt-4 R 4 Sharad Kumar A (PM-IT) Nation 11/1 al October 10/16/2 10/24/ 11/1/2 11/2/2 11/7/ 11/21/ Mrinal BH/BP Procurement of Stationery Item, Housekeeping Com PP 40 Post 016 2016 016 016 2016 4/20 2016 Comp Shoppi 1, 2016 16 Sisodia 22 SP/G- Consumables and Items and computer peripherals pone ng onent- (SPM -HR 022 Stationery Items items for SPMU office Patna nt-4 4 R & Admin) A Nation 11/1 al October 10/16/2 10/24/ 11/1/2 11/2/2 11/7/ 11/21/ Mrinal BH/BP Housekeeping services Housekeeping services (Non- Com PP 10 Post 016 2016 016 016 2016 4/20 2016 Comp Shoppi 1, 2016 16 Sisodia 23 SP/G- (Non-Consultancy Consultancy Services) for SPMU pone ng onent- (SPM -HR 023 Services) office Patna nt-4 4 R & Admin) A MS Office Licence for Decemb Mrinal the Desktops / 1/4/201 1/24/2 2/23/2 3/10/2 3/20/ 4/9/2 4/16/2 Sisodia PP 300 NCB Prior er 15, 7 017 017 017 2017 017 017 BH/BP Laptops/Mini- Purchase of 1500 -MS Office for Com 2016 Comp (SPM -HR 24 SP/G- laptop/Tablet at SPMU, State, District & Block Units (@ 20 pone onent- & Admin) & 024 DPMUs, BPMUs & Thousand per systems) nt-4 R 4 Sharad CRPs (Gram Panchayat A Kumar Project Coordinators) (PM-IT) Component -4 (Goods) Proposed Expenditure per the Procurement Plan 1767 22 23 Table -3 PROCUREMENT PLAN FOR Non Consultancy(DAVP Rate) [BIHAR PANCHAYAT STRENGTHENING PROJECT] WB LOAN No. 5160/IN Procuremen PP/A/R1/R2/ Component Preparation Description Description Value (INR Document Estimated Method of Comments Comments of Goods of Goods Contract Package in lakhs) Review/ Review SL No. of Bid (Date) Prior Post No. R3 t 1 2 3 4 5 6 7 8 9 10 23 24 Direct December 15, PP 500 Contracting Post Broadcast of Radio Jingles on Radio at Broadcast of Radio Jingles on Radio at 2016 (DAVP) BPSP/N Directorate of Audio-Visual Publicity Rates Directorate of Audio-Visual Publicity Rates Component Component Vishal Singh (SPM- 1 C-001 determined by the Ministry of determined by the Ministry of Broadcasting, -2 R -2 Communication) Broadcasting, Govt. of India Govt. of India (for a year) A Direct December 15, PP 150 Contracting Post Broadcast of Fictional Radio Serial on Broadcast of Fictional Radio Serial on Radio at 2016 (DAVP) BPSP/N Radio at Directorate of Audio-Visual Directorate of Audio-Visual Publicity Rates Component Component Vishal Singh (SPM- 2 C-002 Publicity Rates determined by the Ministry determined by the Ministry of Broadcasting, -2 R -2 Communication) of Broadcasting, Govt. of India Govt. of India (for a year) A Direct December 15, PP 250 Contracting Post Phase-1,Broadcast of short films 2016 BPSP/N Phase-1,Broadcast of short films interviews, Component (DAVP) Component Vishal Singh (SPM- 3 interviews, discussions on local TV C-003 discussions on local TV channels (for a year) -2 R -2 Communication) channels A Component -2 (Non-Consultancy) Proposed Expenditure as per the Procurement Plan 900 PROCUREMENT SCHEDULE FOR WORKS FOR 18 MONTHS 23 24 COUNTRY : INDIA BORROWER : GOVERNMENT OF INDIA PROJECT : BIHAR PANCHAYAT STRENGTHENING PROJECT DATED : September 20, 2016. Note:- 330 Panchayat Sarkar Bhawans are to be treated as separate packages TABLE – 4 PROCUREMENT PLAN FOR WORKS [BIHAR PANCHAYAT STRENGTHENING PROJECT] WB LOAN No. 5160/IN Bids nality & ZIP Code (only in case of (inclusive of all Contractor/Natio Document (Start Contract Value Contract Signed sent to IPRD for Contract Award Contract Award Contract Value decided (Date) Preparation of Bid Evaluation PP/A/R1/R2/R3 review) Description of document Works/ Goods completion of Contract/EOT Invitation (Last Procurement Package No. Objection to Objection to **WBR No. applicable publication (Rs. Lakhs) Bank's No. Bank's No. Comments Method of Document Estimated submission) approved Opened on Name of (Date)** (Date)** ICB/NCB Bidding of Review taxes) SL No. (Date) Date for Date) (Date) Bid Date prior Bid 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Febr 100 Nove Janua Decem Decem Januar Januar uary BPSP/ P each mber ry February 2, Construction of Panchayat Sarkar Bhawan- 1 to 75 (in ______ NCB Post N/A ber 1, ber 31, y 1, y 26, N/A ______ ______ N/A 2, W- P total 1, 2016 2016 2017 16, 2017 2017 201 1 001 - Gram Panchayat _________ in Block of _______District ) There 7500 2016 2017 8 075 shall be 75 Packages for Each of the Panchayat Sarkar Bhawans R A 100 April Januar January March March Marc March BPSP/ P each April 4, 4, Construction of Panchayat Sarkar Bhawan- 76 to150 (in ______ P total NCB Post y 1, N/A 31, 2, 3, h 18, 28, N/A 2017 ______ ______ N/A 201 W- 2017 2017 2017 2017 2017 2017 2 076- Panchayat _________Block in _______District ) There shall be 75 7500 8 150 Packages for Each of the Panchayat Sarkar Bhawans R A 100 June March March April May May May BPSP/ P each June 2, 2, Construction of Panchayat Sarkar Bhawan- 151 to 225 (in P total NCB Post 1, N/A 31, 30, 1, 16, 26, N/A 2017 ______ ______ N/A 201 W- 2017 2017 2017 2017 2017 2017 3 151- ______ Panchayat _________Block in _______District ) There shall 7500 8 226 be 75 Packages for Each of the Panchayat Sarkar Bhawans R A 100 July April May June June June BPSP/ P each May 1, July 3, 3, Construction of Panchayat Sarkar Bhawan- 226 to 330 (in P total NCB Post 1, N/A 2017 31, 1, 16, 26, N/A 2017 ______ ______ N/A 201 W- 2017 2017 2017 2017 2017 4 226- ______ Panchayat _________Block in _______District ) There shall 10500 8 330 be 105 Packages for Each of the Panchayat Sarkar Bhawans R A Dec Co Nove Nove Nove Nove Novem emb P Shopp mber mber mber mber November mp BPSP/ 30 Post N/A NA ber 11, N/A ______ ______ N/A er 6, P ing 1, 2016 12, 15, 18, 21, 2016 201 one 5 W- Refurbishment of SPMU 2016 2016 2016 2016 nt-4 331 6 R A Nov Octo Nove emb Co Octob Octobe Octob P Shopp ber mber November er mp BPSP/ 25 Post er 15, N/A NA r 25, er 26, N/A ______ ______ N/A P ing 2016 2016 2016 29, 1, 4, 2016 11, one 6 W- Electrical works of SPMU 2016 2016 201 nt-4 332 6 R A 24 25 25 PROCUREMENT India : India - Bihar Panchayat Strengthening Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-11-13 2018-12-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P102627 GPN Date: Project Name: India - Bihar Panchayat Strengthening Project Loan / Credit No: IDA / 51600 Executing Agency(ies):Local Area Engineering Organization WORKS Bid Evaluation Activity Reference No. Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BH/BPSP/WB-006 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Bargaon Panchayat in IDA / 51600 Post Request for Bids Open - National 358,618.81 Signed 2017-11-07 2017-11-12 2017-12-17 2018-01-30 2018-02-19 2019-02-19 Envelope Block Silao & (ii) Shabait Panchayat in Block Silao. BH/BPSP/WB-003 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (ii) Doiya Panchayat in IDA / 51600 Post Request for Bids Open - National 368,664.05 Signed 2017-11-07 2017-11-12 2017-12-22 2018-01-12 2018-02-07 2019-02-21 Envelope Block Noorsarai & (ii) Meyar Panchayat in Block Noorsarai. BH/BPSP/WB-005 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Gajipur Panchayat in IDA / 51600 Post Request for Bids Open - National 368,053.15 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Giriyak & (ii) Jiyar Panchayat in Block Asthawan. BH/BPSP/WB-004 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Ajaipur Panchayat in IDA / 51600 Post Request for Bids Open - National 367,780.29 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Noorsarai & (ii) Amba Panchayat in Block Rahui. BH/BPSP/WB-002 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Devra Panchayat in IDA / 51600 Post Request for Bids Open - National 383,198.70 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Naubatpur & (ii) Habaspur Goona Panchayat in Block Bikram. BH/BPSP/WB-001 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Kosut Panchayat in IDA / 51600 Post Request for Bids Open - National 39,483.61 Signed 2017-11-07 2017-11-07 2017-11-29 2018-01-20 2018-02-24 2018-08-23 Envelope Block Dhanarua & (ii) Vijaypura Panchayat in Block Dhanarua. BH/BPSP/WB-007 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Ghostama Panchayat in IDA / 51600 Post Request for Bids Open - National 339,003.14 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Silao & (ii) Gorma Panchayat in Block Silao. BH/BPSP/WB-008 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)    Meghi Nagwan IDA / 51600 Post Request for Bids Open - National 36,182.47 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Panchayat in Block Biharsharif & (ii) Bara Panchayat in Block Ben. BH/BPSP/WB-009 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Aant Panchayat in Block IDA / 51600 Post Request for Bids Open - National 388,721.64 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Ben & (ii) Ben Panchayat in Block Ben. BH/BPSP/WB-010 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Lodipur Panchayat in IDA / 51600 Post Request for Bids Open - National 391,079.07 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Rajgir & (ii) Akauna Panchayat in Block Ben. BH/BPSP/WB-011 / Construction of Panchayat Sarkar Bhawan in (i) Damodarpur Baldha Single Stage - Two IDA / 51600 Post Request for Bids Open - National 367,957.53 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Panchayat in Block Envelope Nagarnausa & (ii) Kachhiyava Panchayat in Block Nagarnausa. BH/BPSP/WB-012 / Construction of Panchayat Sarkar Bhawan in Under Single Stage - Two (i) Shivnagar Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Parvalpur & ion (ii) Chousanda Panchayat in Block Parvalpur. BH/BPSP/WB-013 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Pillich Panchayat in IDA / 51600 Post Request for Bids Open - National 343,985.10 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Parvalpur & (ii) Asta Panchayat in Block Tharthari. BH/BPSP/WB-014 / Construction of Panchayat Sarkar Bhawan in (i) Juniyar Panchayat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Block Hilsa & Envelope (ii) Daniyava Pendapur- Panchayat in Block Eakangarsarai. Page 1 BH/BPSP/WB-016 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Rupauli Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Hanuman Nagar &(ii) Sanahpur Panchayat in Block Singhwara. BH/BPSP/WB-017 / Construction of Panchayat Sarkar Bhawan in (i) Murho Panchayat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 412,231.85 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Block Madhepura & Envelope (ii) Sakarpura Betauna Panchayat in Block Madhepura. BH/BPSP/WB-018 / Construction of Panchayat Sarkar Bhawan in (i) Aourahi Eakpraha Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 421,816.10 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Gamahriya & (ii) Bhatarandha Parmanandapur Panchayat in Block Ghailadh. BH/BPSP/WB-019 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Paina Panchayat in IDA / 51600 Post Request for Bids Open - National 401,744.48 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 Envelope Block Chousa & (ii) Ghosai Parmanandapur Panchayat in Block Chousa. BH/BPSP/WB-020 / Construction of Panchayat Sarkar Bhawan in (i) Arai Single Stage - Two IDA / 51600 Post Request for Bids Open - National 339,938.18 Signed 2017-11-07 2017-11-12 2017-12-24 2018-03-08 2018-04-12 2018-10-09 panchyat in Block Envelope Daudnagar & (ii) Karsaon Panchyat in Block Obra BH/BPSP/WB-021 / Construction of Panchayat Sarkar Bhawan in (i) Ora Single Stage - Two Panchyat in Block IDA / 51600 Post Request for Bids Open - National 344,102.77 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Aurangabad & (ii) Ibrahimpur Panchyat in Block Aurangabad BH/BPSP/WB-022 / Construction of Panchayat Sarkar Bhawan in (i) Kerka Single Stage - Two IDA / 51600 Post Request for Bids Open - National 362,128.66 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Panchyat in Block Envelope Navinagar & (ii) Tengra Panchyat in Block Baroon BH/BPSP/WB-023 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 411,680.73 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Salaiya Panchyat in Block Envelope Madanpur & (ii) Nima Ajan Panchyat in Block Madanpur BH/BPSP/WB-025 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 337,348.36 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Hathiyara Panchyat in Envelope Block Goh & (ii) Purhara Panchyat in Block Haspura BH/BPSP/WB-026 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Udavantnagar Panchyat in IDA / 51600 Post Request for Bids Open - National 379,121.36 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Block Udvantnagar & (ii)Kasap Panchyat in Block Udvantnagar BH/BPSP/WB-027 / Construction of Panchayat Sarkar Bhawan in (i) Asni Single Stage - Two Panchyat in Block IDA / 51600 Post Request for Bids Open - National 402,898.08 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Udvantnagar & (ii) Sonpura Panchyat in Block Udvantnagar BH/BPSP/WB-028 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Korthu west Panchyat in IDA / 51600 Post Request for Bids Open - National 369,765.80 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Block Ghansyampur & (ii) Harinagar Panchyat in Block Kusheshwar Asthan BH/BPSP/WB-029 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Harhachcha Panchyat in IDA / 51600 Post Request for Bids Open - National 416,286.78 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Block Baheri & (ii) Pokharbhinda Panchyat in Block Tardih BH/BPSP/WB-030 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Chilonee Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Pratapganj & (ii) Koriapatti west Panchyat in Block Triveniganj BH/BPSP/WB-031 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Maheshua Panchyat in IDA / 51600 Post Request for Bids Open - National 404,844.22 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Block Triveniganj & (ii) Lotuana south Panchyat in Block Triveniganj BH/BPSP/WB-032 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 389,693.56 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Dinapatti Panchyat in Block Envelope Pipara & (ii) Tulaptti south Panchyat in Block Pipara. BH/BPSP/WB-033 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Thuthi Panchyat in Block IDA / 51600 Post Request for Bids Open - National 385,027.87 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Chhatapur & (ii) Laxmipur Khunti Panchyat in Block Chhatapur Page 2 BH/BPSP/WB-034 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Kathara Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Chhatapur & (ii) Bhimpur Panchyat in Block Chhatapur BH/BPSP/WB-035 / Construction of Panchayat Sarkar Bhawan in (i) Champanagar Panchyat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 400,630.59 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Block Raghopur & (ii) Envelope Chithi Hanumann nagar Panchyat in Block saragadh Bhaptiyahi BH/BPSP/WB-036 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Maura Jharkha Panchyat in IDA / 51600 Post Request for Bids Open - National 386,931.58 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Block Sankarpur & (ii) Tamot persa Panchyat in Block Murliganj BH/BPSP/WB-037 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 390,112.06 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Jeetapur Panchyat in Envelope Block Murliganj & (ii) Haripurkala Panchyat in Block Murliganj BH/BPSP/WB-038 / Construction of Panchayat Sarkar Bhawan in (i) Belari Under Single Stage - Two Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope kumarkhand & (ii) ion Bishanpur Koilahi Panchyat in Block kumarkhand BH/BPSP/WB-039 / Construction of Panchayat Sarkar Bhawan in (i) Madhukar chak Panchyat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 391,886.77 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Block Bihariganj & (ii) Envelope Barahi Aanandpura Panchyat in Block Udakishunganj BH/BPSP/WB-040 / Construction of Panchayat Sarkar Bhawan in (i) Pipra Single Stage - Two Jagdish Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Envelope Bihiya & (ii) Goudadh Rudranagar Panchyat in Block Bihiya BH/BPSP/WB-041 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 312,230.80 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Shivpur Panchyat in Block Envelope Bihiya & (ii) Tiyar Panchyat in Block Bihiya BH/BPSP/WB-042 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 320,269.37 Signed 2017-11-08 2017-11-13 2017-12-25 2018-03-09 2018-04-13 2018-10-10 Panwari Panchyat in Block Envelope Tarari & (ii) Imadpur Panchyat in Block Tarari BH/BPSP/WB-015 / "Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i) Sonki Panchayat in IDA / 51600 Post Request for Bids Open - National 369,024.94 Signed 2017-11-09 2017-11-14 2017-12-26 2018-03-10 2018-04-14 2018-10-11 Envelope Block Darbhanga Sadar & (ii) Chhotaipatti Panchayat in Block Darbhanga Sadar. BH/BPSP/WB-024 / Construction of Panchayat Sarkar Bhawan in (i) Kerap Single Stage - Two IDA / 51600 Post Request for Bids Open - National 332,299.33 Signed 2017-11-09 2017-11-14 2017-12-26 2018-03-10 2018-04-14 2018-10-11 Panchyat in Block rafiganj Envelope & (ii) Dadhpi Panchyat in Block Goh BH/BPSP/WB-043 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Ladaniya Panchyat in Block IDA / 51600 Post Request for Bids Open - National 413,315.96 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Envelope Laukahi & (ii) Majhuara Panchyat in Block Khutauna BH/BPSP/WB-044 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Satghara Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Envelope Rajnagar & (ii) Koilakh Panchyat in Block Rajnagar BH/BPSP/WB-045 / Construction of Panchayat Sarkar Bhawan in (i) Bagar Single Stage - Two IDA / 51600 Post Request for Bids Open - National 322,925.38 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Panchyat in Block Tarari & Envelope (ii) Andhari Panchyat in Block Sahar BH/BPSP/WB-046 / Construction of Panchayat Sarkar Bhawan in (i) Kajar Single Stage - Two IDA / 51600 Post Request for Bids Open - National 337,018.96 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Panchyat in Block Shahpur Envelope & (ii) Basauna Panchyat in Block Jagdishpur BH/BPSP/WB-047 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Bampali Panchyat in Block IDA / 51600 Post Request for Bids Open - National 383,163.94 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Envelope Udavantnagar & (ii) Nawadaben Panchyat in Block Udavantnagar BH/BPSP/WB-048 / Construction of Panchayat Sarkar Bhawan in (i) Purvi Single Stage - Two IDA / 51600 Post Request for Bids Open - National 353,686.17 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Babura Panchyat in Block Envelope Barhara & (ii) Daulatpur Panchyat in Block Koilwar BH/BPSP/WB-049 / Construction of Panchayat Sarkar Bhawan in (i) Farna Single Stage - Two IDA / 51600 Post Request for Bids Open - National 343,474.27 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Panchyat in Block Barhara Envelope & (ii) Gundi Panchyat in Block Barhara Page 3 BH/BPSP/WB-050 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Basantpur Panchyat in IDA / 51600 Post Request for Bids Open - National 322,662.05 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Envelope Block Ara sadar & (ii) Balua Panchyat in Block Barhara BH/BPSP/WB-051 / Construction of Panchayat Sarkar Bhawan in (i)Baruna Single Stage - Two IDA / 51600 Post Request for Bids Open - National 385,773.49 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 Panchyat in Block Agiawan Envelope & (ii) Nonaur Panchyat in Block Agiawan BH/BPSP/WB-052 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 365,050.81 Signed 2017-11-14 2017-11-19 2017-12-31 2018-03-15 2018-04-19 2018-10-16 (i)Garhani Panchyat in Envelope Block Garhani & (ii) Echari Panchyat in Block Garhani BH/BPSP/WB-053 / Construction of Panchayat Sarkar Bhawan in (i)Lagma Single Stage - Two IDA / 51600 Post Request for Bids Open - National 420,643.26 Signed 2017-11-23 2017-11-28 2018-01-09 2018-03-24 2018-04-28 2018-10-25 Panchyat in Block Sonversa Envelope & (ii) Mahua Panchyat in Block Sonversa BH/BPSP/WB-054 / Construction of Panchayat Sarkar Bhawan in (i)Baith Single Stage - Two IDA / 51600 Post Request for Bids Open - National 395,554.07 Signed 2017-11-23 2017-11-28 2018-01-09 2018-03-24 2018-04-28 2018-10-25 Panchyat in Block Sonversa Envelope & (ii) Mora Kopa Panchyat in Block Sonversa BH/BPSP/WB-055 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Mubarakpur Panchyat in IDA / 51600 Post Request for Bids Open - National 358,484.19 Signed 2017-11-23 2017-11-28 2018-01-09 2018-03-24 2018-04-28 2018-10-25 Envelope Block Salkhua & (ii) Kabira Panchyat in Block Salkhua BH/BPSP/WB-056 / Construction of Panchayat Under Sarkar Bhawan in (i)Hareba Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2017-11-23 2017-11-28 2018-01-09 2018-03-24 2018-04-28 2018-10-25 Panchyat in Block Salkhua Envelope ion & (ii) Chanan Panchyat in Block Salkhua BH/BPSP/WB-057 / Construction of Panchayat Sarkar Bhawan in (i)Kap Single Stage - Two Pachami Panchyat in Block IDA / 51600 Post Request for Bids Open - National 375,270.15 Signed 2017-11-23 2017-11-28 2018-01-09 2018-03-24 2018-04-28 2018-10-25 Envelope Saur Bazar & (ii) Gamharia Panchyat in Block Saur Bazar BH/BPSP/WB-058 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Sahuria Pachami IDA / 51600 Post Request for Bids Open - National 395,522.76 Signed 2017-11-23 2017-11-28 2018-01-09 2018-03-24 2018-04-28 2018-10-25 Envelope Panchyat in Block Saur Bazar & (ii) Chandaur Purbi Panchyat in Block Saur Bazar BH/BPSP/WB-059 / Construction of Panchayat Sarkar Bhawan in (i)Neema Single Stage - Two IDA / 51600 Post Request for Bids Open - National 367,978.25 Signed 2017-12-01 2017-12-06 2018-01-17 2018-04-01 2018-05-06 2018-11-02 Panchayat in Block Dobhi Envelope & (ii) Kurmawa Panchayat in Block Dobhi BH/BPSP/WB-060 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Ghoraghat Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-12-01 2017-12-06 2018-01-17 2018-04-01 2018-05-06 2018-11-02 Envelope Block Dobhi & (ii) Bhalua Panchayat in Block Barachatti BH/BPSP/WB-061 / Construction of Panchayat Sarkar Bhawan in (i)Korap Single Stage - Two IDA / 51600 Post Request for Bids Open - National 310,513.96 Signed 2017-12-01 2017-12-06 2018-01-17 2018-04-01 2018-05-06 2018-11-02 Panchayat in Block Konch Envelope & (ii) Kawar Panchayat in Block Konch BH/BPSP/WB-062 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Narawat Panchayat in IDA / 51600 Post Request for Bids Open - National 330,457.87 Signed 2017-12-01 2017-12-06 2018-01-17 2018-04-01 2018-05-06 2018-11-02 Envelope Block Atari & (ii)Panari Panchayat in Block Belaganj BH/BPSP/WB-063 / Construction of Panchayat Sarkar Bhawan in (i)Alam Single Stage - Two Nagar Utari Panchayat in IDA / 51600 Post Request for Bids Open - National 387,487.30 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Block Alam Nagar & (ii)Parmanandpur Panchayat in Block Murliganj BH/BPSP/WB-064 / Construction of Panchayat Sarkar Bhawan in (i)Tengaraha Pariyahi Single Stage - Two IDA / 51600 Post Request for Bids Open - National 390,267.44 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Panchayat in Block Envelope Kumarkhand & (ii)Jeevachhpur Panchayat in Block Gamhariya BH/BPSP/WB-065 / Construction of Panchayat Sarkar Bhawan in (i)Pipra Single Stage - Two Karauti Panchayat in IDA / 51600 Post Request for Bids Open - National 399,217.59 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Block Udakisunganj & (ii)Gopalpur Panchayat in Block Udakisunganj BH/BPSP/WB-066 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Chirauri Panchayat in IDA / 51600 Post Request for Bids Open - National 408,389.57 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Block Chausa & (ii)Laualagan East Panchayat in Block Chausa BH/BPSP/WB-067 / Construction of Panchayat Sarkar Bhawan in (i)Nardah Single Stage - Two IDA / 51600 Post Request for Bids Open - National 780,170.96 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Panchayat in Block Envelope Purainee & (ii)Durgapur Panchayat in Block Purainee Page 4 BH/BPSP/WB-068 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Jeerava Madhailee IDA / 51600 Post Request for Bids Open - National 395,773.87 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Panchayat in Block Shankarpur & (ii)Sonvarsha Panchayat in Block Shankarpur BH/BPSP/WB-069 / Construction of Panchayat Sarkar Bhawan in (i)Tetrah Single Stage - Two Panchayat in Block Akodhi IDA / 51600 Post Request for Bids Open - National 318,464.11 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Gola & (ii)Bagha Khoh Panchayat in Block Akodhi Gola BH/BPSP/WB-070 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 340,493.08 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 (i)Chitouli Panchayat in Envelope Block Tilauthu & (ii)Sewahi Panchayat in Block Tilauthu BH/BPSP/WB-071 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Akashee Panchayat in IDA / 51600 Post Request for Bids Open - National 361,471.52 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Block Sasaram & (ii)Rohtas Garh Panchayat in Block Rohtas BH/BPSP/WB-072 / Construction of Panchayat Sarkar Bhawan in (i)Reriya Single Stage - Two IDA / 51600 Post Request for Bids Open - National 359,467.67 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Panchayat in Block Kochas Envelope & (ii)Karup Panchayat in Block Shivsagar BH/BPSP/WB-073 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Karhara Panchayat in IDA / 51600 Post Request for Bids Open - National 385,536.75 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Block Benipatti & (ii)Tyonth Panchayat in Block Benipatti BH/BPSP/WB-074 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Taraiya Panchayat in IDA / 51600 Post Request for Bids Open - National 377,583.91 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Block Madhawapur & (ii)Pirokhar Panchayat in Block Madhawapur BH/BPSP/WB-075 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Sidhapa Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-12-05 2017-12-10 2018-01-21 2018-04-05 2018-05-10 2018-11-06 Envelope Block Ladaniya & (ii)Chatra Gobrarua North Panchayat in Block Khajauli BH/BPSP/WB-076 / Construction of Panchayat Sarkar Bhawan in (i)Chatra Gobraura South Panchayat Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 in Block Khajauli & Envelope (ii)Chandradih Maharajpur Panchayat in Block Khajauli BH/BPSP/WB-077 / Construction of Panchayat Sarkar Bhawan in (i)Shri Single Stage - Two Khinda Panchayat in Block IDA / 51600 Post Request for Bids Open - National 319,692.32 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Nokha & (ii)Chandi English Panchayat in Block Sanjhouli BH/BPSP/WB-078 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)NonharPanchayat in Block IDA / 51600 Post Request for Bids Open - National 334,953.82 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 Envelope Bikramganj & (ii)Manpur Panchayat in Block Bikramganj BH/BPSP/WB-079 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 337,935.82 Signed 2017-12-04 2017-12-09 2018-01-20 2018-04-04 2018-05-09 2018-11-05 (i)lilwachh Panchayat in Envelope Block Dinara & (ii)Dawath Maharajpur Panchayat in Block Dawath BH/BPSP/WB-080 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 346,077.69 Signed 2017-12-05 2017-12-10 2018-01-21 2018-04-05 2018-05-10 2018-11-06 (i)Dhamni Panchayat in Envelope Block Barun & (ii)Dhangai Panchayat in Block Barun BH/BPSP/WB-081 / Construction of Panchayat Sarkar Bhawan in Under Single Stage - Two (i)Bishanpur Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2017-12-19 2017-12-24 2018-02-04 2018-04-19 2018-05-24 2018-11-20 Envelope Block Patarghat & ion (ii)Pastpar Panchayat in Block Patarghat BH/BPSP/WB-082 / Construction of Panchayat Sarkar Bhawan in Under Single Stage - Two (i)Dhabauli Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2017-12-19 2017-12-24 2018-02-04 2018-04-19 2018-05-24 2018-11-20 Envelope Block Patarghat & ion (ii)Sirwar-Birwar Panchayat in Block Mahishi BH/BPSP/WB-083 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Bardaha panchayat in IDA / 51600 Post Request for Bids Open - National 3,445,597.21 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Islampur & (ii)Telhara Panchayat in Block Eakangarsarai BH/BPSP/WB-084 / Construction of Panchayat Sarkar Bhawan in (i)Murho Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 403,261.38 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Madhepura & (ii)Sakarpura Betauna Panchayat in Block Madhepura BH/BPSP/WB-085 / Construction of Panchayat Sarkar Bhawan in (i)Paina Single Stage - Two IDA / 51600 Post Request for Bids Open - National 400,874.17 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchayat in Block Chousa Envelope & (ii)Ghosai Parmanandapur Panchayat in Blockchousa Page 5 BH/BPSP/WB-086 / Construction of Panchayat Sarkar Bhawan in (i)Maura Single Stage - Two Gharkaha Panchayat in IDA / 51600 Post Request for Bids Open - National 388,267.68 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Sankarpur & (ii)Tamot Parsa Panchayat in Block Murliganj BH/BPSP/WB-087 / Construction of Panchayat Sarkar Bhawan in (i)Jeetapur Panchayat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 397,417.72 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Block Murliganj & Envelope (ii)Haripurkala south Panchayat in Block Murliganj BH/BPSP/WB-088 / Construction of Panchayat Sarkar Bhawan in (i)Madhurkarchak Panchayat Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 in Block Thvahariganj & (ii) Envelope Barahi Aanudapura Raketee Panchayat in Block Udakishunganj BH/BPSP/WB-089 / Construction of Panchayat Sarkar Bhawan in (i) Arai Single Stage - Two IDA / 51600 Post Request for Bids Open - National 338,768.40 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 panchyat in Block Envelope Daudnagar & (ii) Karsaon Panchyat in Block Obra BH/BPSP/WB-090 / Construction of Panchayat Sarkar Bhawan in (i) Ora Single Stage - Two Panchyat in Block IDA / 51600 Post Request for Bids Open - National 342,175.77 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Aurangabad & (ii) Ibrahimpur Panchyat in Block Aurangabad BH/BPSP/WB-091 / Construction of Panchayat Sarkar Bhawan in (i) Kerka Single Stage - Two IDA / 51600 Post Request for Bids Open - National 357,617.08 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchyat in Block Envelope Navinagar & (ii) Tengra Panchyat in Block Barun BH/BPSP/WB-092 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Salaiya Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Madanpur & (ii) Neema Aanjan Panchyat in Block Madanpur BH/BPSP/WB-093 / Construction of Panchayat Sarkar Bhawan in (i) Kerap Single Stage - Two IDA / 51600 Post Request for Bids Open - National 333,446.78 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchyat in Block rafiganj Envelope & (ii) Dadhapee Panchyat in Block Goh BH/BPSP/WB-094 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Chilauni Panchyat in Block IDA / 51600 Post Request for Bids Open - National 393,497.16 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Pratapganj & (ii) Koriyapatti Panchyat in Block Triveniganj BH/BPSP/WB-095 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Kathara Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Chhatapur & (ii) Laxmipur Khunti Panchyat in Block Chhatapur BH/BPSP/WB-096 / Construction of Panchayat Sarkar Bhawan in (i)Mouri Single Stage - Two Piyarpur Panchyat in Block IDA / 51600 Post Request for Bids Open - National 365,421.36 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Paliganj & (ii) Akbarpur Geepur Khunti Panchyat in Block Paliganj BH/BPSP/WB-097 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 362,542.33 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Merapatouna Panchyat in Envelope Block Paliganj & (ii) dahiya Panchyat in Block Paliganj BH/BPSP/WB-098 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Bherhariya siyarampur IDA / 51600 Post Request for Bids Open - National 327,508.77 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Panchyat in Block Paliganj & (ii) Mhabalipur Panchyat in Block Paliganj BH/BPSP/WB-099 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 349,519.08 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Sadikpur Panchyat in Block Envelope Maner & (ii) Balua Khunti Panchyat in Block maner. BH/BPSP/WB-100 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Shrichandpura Panchyat IDA / 51600 Post Request for Bids Open - National 368,427.08 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope in Block Bihta & (ii) Lakhna Purvi Panchyat in Block Punpun BH/BPSP/WB-101 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Hathiyakand Panchyat in IDA / 51600 Post Request for Bids Open - National 367,255.98 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Danapur & (ii) Purani Panapur Panchyat in Block Danapur BH/BPSP/WB-102 / Construction of Panchayat Sarkar Bhawan in (i)Gobindpur Bairahi Single Stage - Two IDA / 51600 Post Request for Bids Open - National 375,820.94 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchyat in Block Envelope Dhanarua & (ii) Sihee Khunti Panchyat in Block Dulhin Bazar Page 6 BH/BPSP/WB-103 / Construction of Panchayat Sarkar Bhawan in (i)Kosut Single Stage - Two IDA / 51600 Post Request for Bids Open - National 378,758.76 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchyat in Block Envelope Dhanarua & (ii) Vijaypura Panchyat in Block Dhanarua BH/BPSP/WB-104 / Construction of Panchayat Sarkar Bhawan in (i)Damodarpur Baldaha Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchyat in Block Envelope Nagarnausa & (ii) Kachhiyava Panchyat in Block Nagarnausa BH/BPSP/WB-105 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 358,830.10 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 (i)Juniyar Panchyat in Block Envelope Hilsa & (ii) Daniyava Panchyat in Block Ekangarsarai BH/BPSP/WB-106 / Construction of Panchayat Sarkar Bhawan in (i)Pipra Single Stage - Two jagdishpur Panchyat in IDA / 51600 Post Request for Bids Open - National 349,353.20 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Bihiya & (ii) Eyar Panchyat in Block Jagdishpur BH/BPSP/WB-107 / Construction of Panchayat Sarkar Bhawan in (i)Rahua Single Stage - Two East Panchyat in Block IDA / 51600 Post Request for Bids Open - National 384,156.85 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Warisnagar & (ii) Dahibahi Panchyat in Block Shivajinagar Nagar BH/BPSP/WB-108 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Alampur Kodaria IDA / 51600 Post Request for Bids Open - National 394,817.90 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Panchyat in Block Bibhutipur & (ii) Kalayanpur Panchyat in Block Bibhutipur BH/BPSP/WB-109 / Construction of Panchayat Sarkar Bhawan in (i)Tabhka Panchyat in Block Single Stage - Two IDA / 51600 Post Request for Bids Open - National 407,837.30 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Bibhutipur & (ii) Envelope Mahammadpur Sakara Panchyat in Block Bibhutipur BH/BPSP/WB-110 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Mustafapur Panchyat in IDA / 51600 Post Request for Bids Open - National 395,739.05 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Bibhutipur & (ii) Kerai Panchyat in Block Bibhutipur BH/BPSP/WB-111 / Construction of Panchayat Sarkar Bhawan in (i)Thar Single Stage - Two IDA / 51600 Post Request for Bids Open - National 377,767.13 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Basariya Panchyat in Block Envelope Rosera & (ii) Sonupur Uttar Panchyat in Block Rosera BH/BPSP/WB-112 / Construction of Panchayat Sarkar Bhawan in (i)Rahua Single Stage - Two IDA / 51600 Post Request for Bids Open - National 379,672.60 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchyat in Block Rosera & Envelope (ii) Bhiraha Purab Panchyat in Block Rosera BH/BPSP/WB-113 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Mohnagar Paschim Panchyat IDA / 51600 Post Request for Bids Open - National 410,439.60 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope in Block Rosera & (ii) Chakthat Paschim Panchyat in Block Rosera BH/BPSP/WB-114 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Mahesua Panchyat in IDA / 51600 Post Request for Bids Open - National 404,844.22 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Triveniganj & (ii) Latauna South Panchyat in Block Triveniganj BH/BPSP/WB-115 / Construction of Panchayat Sarkar Bhawan in (i) Champanagar Panchyat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Block Raghopur & (ii) Envelope Chhitahi Hanuman Nagar Panchyat in Block Saraigarh Bhaptiyahi BH/BPSP/WB-116 / Construction of Panchayat Sarkar Bhawan in (i)Korthu Single Stage - Two west Panchyat in Block IDA / 51600 Post Request for Bids Open - National 368,714.27 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Ghansyampur & (ii) Harinagar Panchyat in Block Kusheshwarsathan BH/BPSP/WB-117 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Harhachcha Panchyat in IDA / 51600 Post Request for Bids Open - National 412,037.75 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Baheri & (ii) Pokharbinda Panchyat in Block Tardih BH/BPSP/WB-118 / Construction of Panchayat Sarkar Bhawan in (i)Barna Panchyat in Block Single Stage - Two IDA / 51600 Post Request for Bids Open - National 420,905.06 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Kusheshwarsathan & (ii) Envelope Mahisaut Sakara Panchyat in Block Kusheshwarsathan East BH/BPSP/WB-119 / Construction of Panchayat Sarkar Bhawan in Under Single Stage - Two (i)Bishahariya Panchyat in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Kusheshwarsathan & ion (ii) Aurahee Panchyat in Block Kusheshwarsathan Page 7 BH/BPSP/WB-120 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Bhadahar Panchyat in IDA / 51600 Post Request for Bids Open - National 40,875.14 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Kusheshwarsathan & (ii) Ramaulee Panchyat in Block Benipur BH/BPSP/WB-121 / Construction of Panchayat Sarkar Bhawan in (i)Batho Single Stage - Two IDA / 51600 Post Request for Bids Open - National 404,451.64 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Radhiyam Panchyat in Envelope Block Benipur & (ii) Atahar South Panchyat in Block Baheri BH/BPSP/WB-122 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Baghaunee Panchyat in IDA / 51600 Post Request for Bids Open - National 405,405.55 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Baheri & (ii) dhanaulee Panchyat in Block Baheri BH/BPSP/WB-123 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Ghorghat Panchyat in Block IDA / 51600 Post Request for Bids Open - National 363,956.86 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Dobhi & (ii) Bhalua Panchyat in Block Barachatti BH/BPSP/WB-124 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Lagma Panchyat in Block Envelope Sonversa & (ii) Mahua Panchyat in Block Sonversa BH/BPSP/WB-125 / Construction of Panchayat Sarkar Bhawan in (i) Baith Single Stage - Two IDA / 51600 Post Request for Bids Open - National 396,919.94 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Musahri Panchyat in Block Envelope Sonversa & (ii) Morakopa Panchyat in Block Sonversa BH/BPSP/WB-126 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 402,472.12 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Mubarakpur Panchyat in Envelope Block Salkhua & (ii) Kabira Panchyat in Block Salkhua BH/BPSP/WB-127 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Hareba Panchyat in Block Envelope Salkhua & (ii) Chanan Panchyat in Block Salkhua BH/BPSP/WB-128 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Sahuria Pachmi Panchyat in IDA / 51600 Post Request for Bids Open - National 396,888.52 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Saur bazar & (ii) Chandaur Purbi Panchyat in Block Saur bazar BH/BPSP/WB-129 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Dhabauli Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Patarghat & (ii) Sirwar- birwar Panchyat in Block Mahishi BH/BPSP/WB-130 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Chilauni Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Pratapganj & (ii) Koriyapatti Panchyat in Block Triveniganj BH/BPSP/WB-131 / Construction of Panchayat Sarkar Bhawan in (i) Kathara Panchyat in Block Single Stage - Two IDA / 51600 Post Request for Bids Open - National 395,885.39 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Chhatapur & (ii) Envelope Lakshamipur Khunti Panchyat in Block Chhatapur BH/BPSP/WB-132 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 349,519.07 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Sadikpur Panchayat in Envelope Block Maner & (ii) Balua Panchayat in Block Maner BH/BPSP/WB-133 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Karhara Panchayat in Block IDA / 51600 Post Request for Bids Open - National 384,210.07 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Benipatti & (ii) Tyonth Panchayat in Block Benipatti BH/BPSP/WB-134 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Taraiya Panchayat in Block IDA / 51600 Post Request for Bids Open - National 244,531.38 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Madhawapur & (ii)Pirokhar Panchayat in Block Madhawapur BH/BPSP/WB-135 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Sidhapa Panchayat in Block IDA / 51600 Post Request for Bids Open - National 439,909.82 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Ladaniya & (ii) Chatra Gobraura North Panchayat in Block Khajauli BH/BPSP/WB-136 / Construction of Panchayat Sarkar Bhawan in (i) Chatra Gobraura South Single Stage - Two IDA / 51600 Post Request for Bids Open - National 431,327.46 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchayat in Block Khajauli Envelope & (ii) chandradih Maharajpur Panchayat in Block Khajauli BH/BPSP/WB-137 / Construction of Panchayat Sarkar Bhawan in (i) Kerka Single Stage - Two IDA / 51600 Post Request for Bids Open - National 356,386.47 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchayat in Block Envelope Navinagar & (ii) Tengra Panchayat in Block Barun Page 8 BH/BPSP/WB-138 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 362,307.44 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 (i)Kharkani Panchayat in Envelope Block Deo & (ii) Basdiha Panchayat in Block Deo BH/BPSP/WB-139 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Pouthu Panchayat in Block IDA / 51600 Post Request for Bids Open - National 363,338.37 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Rafiganj & (ii) Karma Panchayat in Block Daudnagar BH/BPSP/WB-140 / Construction of Panchayat Sarkar Bhawan in (i) Pipra Single Stage - Two IDA / 51600 Post Request for Bids Open - National 329,807.29 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Panchayat in Block Envelope Kutumba & (ii) Ankorha Panchayat in Block Navinagar BH/BPSP/WB-141 / Construction of Panchayat Sarkar Bhawan in (i) Chikna Panchayat in Block Single Stage - Two IDA / 51600 Post Request for Bids Open - National 424,001.08 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Ghoghardiha & (ii) Envelope Brahmpur Bathnaha Panchayat in Block Ghoghardiha BH/BPSP/WB-142 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Dharmdiha Panchayat in IDA / 51600 Post Request for Bids Open - National 381,675.14 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block phulparas & (ii) Phulparas Panchayat in Block Phulparas BH/BPSP/WB-143 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Parashi Purvi Panchayat in IDA / 51600 Post Request for Bids Open - National 216,988.31 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Khutauna & (ii) Bathnaha Panchayat in Block Phulparas BH/BPSP/WB-144 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Sathghara Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Block Rajnagar & (ii) Gour Andhra Panchayat in Block Andhrathadi BH/BPSP/WB-145 / Construction of Panchayat Sarkar Bhawan in (i) Bath Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 407,305.14 Signed 2018-03-29 2018-04-03 2018-05-15 2018-07-28 2018-09-01 2019-02-28 Envelope Madhepur & (ii) Mahinathpur Panchayat in Block Jhanjharpur BH/BPSP/WB-146 / Construction of Panchayat Sarkar Bhawan in (i)Madhukarchak Panchayat Single Stage - Two IDA / 51600 Post Request for Bids Open - National 396,830.69 Signed 2018-04-03 2018-04-08 2018-05-20 2018-08-02 2018-09-06 2019-03-05 in Block Bihariganj & (ii) Envelope Barahi Aanandpura Panchayat in Block Udkishunganj BH/BPSP/WB-147 / Construction of Panchayat Sarkar Bhawan in (i)Sonki Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 363,274.29 Signed 2018-04-03 2018-04-08 2018-05-20 2018-08-02 2018-09-06 2019-03-05 Envelope Darbhanga sadar & (ii) Chhotaipatti Panchayat in Block Darbhanga Sadar BH/BPSP/WB-148 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Rupauli Panchayat in IDA / 51600 Post Request for Bids Open - National 406,533.73 Signed 2018-04-03 2018-04-08 2018-05-20 2018-08-02 2018-09-06 2019-03-05 Envelope Block Hanuman Nagar & (ii) Sanahpur Panchayat in Block Singhwara BH/BPSP/WB-149 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Rahimabad Panchayat in IDA / 51600 Post Request for Bids Open - National 372,364.93 Signed 2018-04-03 2018-04-08 2018-05-20 2018-08-02 2018-09-06 2019-03-05 Envelope Block Tajpur & (ii) Fatehpur Wala Panchayat in Block Tajpur BH/BPSP/WB-150 / Construction of Panchayat Sarkar Bhawan in (i) Single Stage - Two Gadhsisai Panchayat in IDA / 51600 Post Request for Bids Open - National 407,997.71 Signed 2018-04-03 2018-04-08 2018-05-20 2018-08-02 2018-09-06 2019-03-05 Envelope Block VidyaPatinagar & (ii) Songar Panchayat in Block Morwa BH/BPSP/WB-151 / Construction of Panchayat Sarkar Bhawan in (i)Ilra Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 343,039.80 Signed 2018-04-03 2018-04-08 2018-05-20 2018-08-02 2018-09-06 2019-03-05 Envelope Bodhgaya & (ii) Atia Panchayat in Block Bodhgaya BH/BPSP/WB-152 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 (i)Sadullahpur Panchayat in Envelope Block Bisfi & (ii) Bisfi Panchayat in Block Bisfi BH/BPSP/WB-153 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 (i)Bishaul Panchayat in Envelope Block Harlakhi & (ii) Pipraun Panchayat in Block Harlakhi BH/BPSP/WB-154 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Sonamati Panchayat in IDA / 51600 Post Request for Bids Open - National 449,711.53 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Babubarhi & (ii) Pucharukhi Panchayat in Block Babubarhi Page 9 BH/BPSP/WB-155 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 382,168.56 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 (i)Gangapur Panchayat in Envelope Block Pusa & (ii) Kabuliram Panchayat in Block Pusa BH/BPSP/WB-156 / Construction of Panchayat Sarkar Bhawan in (i)Darba Single Stage - Two IDA / 51600 Post Request for Bids Open - National 368,909.43 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Panchayat in Block Patori Envelope & (ii) Sirdilpur Panchayat in Block Patori BH/BPSP/WB-157 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Shiwasinghpur Panchayat IDA / 51600 Post Request for Bids Open - National 368,909.43 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope in Block Mohiuddinnagar & (ii) Adharpur Panchayat in Block Tajpur BH/BPSP/WB-158 / Construction of Panchayat Sarkar Bhawan in (i)Diwari Single Stage - Two IDA / 51600 Post Request for Bids Open - National 407,741.79 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Panchayat in Block Kahra Envelope & (ii) Patuaha Panchayat in Block Kahara BH/BPSP/WB-159 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Tariyama Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Simiri bakhtiyarpur & (ii) Khamauti Panchayat in Block Simiri bakhtiyarpur BH/BPSP/WB-160 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 406,892.06 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 (i)Balhapatti Panchayat in Envelope Block Kahra & (ii) Uteshra Panchayat in Block Salkhua BH/BPSP/WB-161 / Construction of Panchayat Sarkar Bhawan in (i)Sonwai Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 360,156.24 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Dhanarua & (ii) Dhanarua Panchayat in Block Dhanarua BH/BPSP/WB-162 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Bhadoura Panchayat in IDA / 51600 Post Request for Bids Open - National 370,890.86 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Masurahi & (ii) Chapour Panchayat in Block Masurahi BH/BPSP/WB-163 / Construction of Panchayat Sarkar Bhawan in (i)Sarari Single Stage - Two IDA / 51600 Post Request for Bids Open - National 373,085.87 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Panchayat in Block Envelope Danapur & (ii) Lakhani Bigha Panchayat in Block Danapur BH/BPSP/WB-164 / Construction of Panchayat Sarkar Bhawan in (i)Ahiyapur Single Stage - Two IDA / 51600 Post Request for Bids Open - National 344,050.69 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 GyaspurPanchayat in Block Envelope Maner & (ii) Doulatpur Simiri Panchayat in Block Bihta BH/BPSP/WB-165 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 348,890.50 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 (i)Amhara Panchayat in Envelope Block Bihta & (ii) Birdhour Nispura Panchayat in Block Bikram BH/BPSP/WB-166 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Nadhari Kodahari IDA / 51600 Post Request for Bids Open - National 357,900.48 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Panchayat in Block Paliganj & (ii)Khanpura Panchayat in Block Paliganj BH/BPSP/WB-167 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Chorsua Panchayat in IDA / 51600 Post Request for Bids Open - National 396,235.14 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Gariyak & (ii) Pawa Panchayat in Block Biharsarif BH/BPSP/WB-168 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Gazadharpur Panchayat in IDA / 51600 Post Request for Bids Open - National 357,933.49 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Tankuppa & (ii) North LodhwayPanchayat in Block Fatehpur BH/BPSP/WB-169 / Construction of Panchayat Sarkar Bhawan in (i)Shree Single Stage - Two Rampur Panchayat in Block IDA / 51600 Post Request for Bids Open - National 373,130.81 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Sherghati & (ii) Dubhal Panchayat in Block Imamganj BH/BPSP/WB-170 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Ghoswari Panchayat in IDA / 51600 Post Request for Bids Open - National 356,673.39 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Bakhtiyarpur & (ii) Mekra Panchayat in Block Mokama BH/BPSP/WB-171 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in (i)Marchi IDA / 51600 Post Request for Bids Open - National 182,887.88 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Panchayat in Block Patna Sadar . BH/BPSP/WB-172 / Construction of Panchayat Under Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope (i)Sahabeh Panchayat in ion Block Dulhin Bazar Page 10 BH/BPSP/WB-173 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Ekangadih Panchayat in IDA / 51600 Post Request for Bids Open - National 351,118.33 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Ekangarsarai & (ii) Parthu Panchayat in Block Ekengarsarai BH/BPSP/WB-174 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 174,581.44 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope (i)Nahusha Panchayat in Block Harnaut BH/BPSP/WB-175 / Construction of Panchayat Sarkar Bhawan in (i)Dara Single Stage - Two IDA / 51600 Post Request for Bids Open - National 340,798.84 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Nagar Panchayat in Block Envelope Nauhatta & (ii) Chitaw Panchayat in Block Kochas BH/BPSP/WB-176 / Construction of Panchayat Sarkar Bhawan in (i)Kajh Single Stage - Two IDA / 51600 Post Request for Bids Open - National 346,971.32 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Panchayat in Block Gurua Envelope & (ii) Pakri Panchayat in Block Gurua BH/BPSP/WB-177 / Construction of Panchayat Sarkar Bhawan in (i)Gurua Single Stage - Two IDA / 51600 Post Request for Bids Open - National 345,444.12 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Panchayat in Block Gurua Envelope & (ii) Manda Panchayat in Block Gurua BH/BPSP/WB-178 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Hathiyawan Panchayat in IDA / 51600 Post Request for Bids Open - National 345,710.83 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Khizarsarai & (ii) Nanauk Panchayat in Block Manpur BH/BPSP/WB-179 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 332,464.44 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 (i)Kurmawa Panchayat in Envelope Block Konch & (ii) Chabura Panchayat in Block Konch BH/BPSP/WB-180 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 311,091.18 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 (i)Gauharpur Panchayat in Envelope Block Konch & (ii) Dihura Panchayat in Block Tekari BH/BPSP/WB-181 / Construction of Panchayat Sarkar Bhawan in (i)Sonki Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 362,241.22 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Darbhanga Sadar & (ii) Chhotaipatti Panchayat in Block Darbhanga Sadar BH/BPSP/WB-183 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Majhgama Panchayat in IDA / 51600 Post Request for Bids Open - National 409,724.46 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Keoti & (ii) Karwa Taryani Panchayat in Block Jale BH/BPSP/WB-184 / Construction of Panchayat Sarkar Bhawan in (i)Harpur Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 395,188.80 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Singhwara & (ii) Bharathi Panchayat in Block Singhwara BH/BPSP/WB-185 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 214,519.70 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope (i)Godhaila Panchayat in Block Hanuman Nagar BH/BPSP/WB-186 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Paridah Panchayat in IDA / 51600 Post Request for Bids Open - National 391,750.16 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Hasanpur & (ii) Hasanpur Panchayat in Block Hasanpur BH/BPSP/WB-187 / Construction of Panchayat Sarkar Bhawan in (i)Chaita Single Stage - Two Uttari Panchayat in Block IDA / 51600 Post Request for Bids Open - National 412,651.56 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Ujiyarpur & (ii) Lohangeer Panchayat in Block Ujiyarpur BH/BPSP/WB-188 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 196,358.56 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope (i)Ganwpur Panchayat in Block Ujiyarpur BH/BPSP/WB-189 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 210,779.40 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope (i)Arajpur Paschim Panchayat in Block Chausa BH/BPSP/WB-190 / Construction of Panchayat Sarkar Bhawan in (i)Khopaiti Tuniyahi Single Stage - Two IDA / 51600 Post Request for Bids Open - National 418,935.85 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Panchayat in Block Envelope Madhepura & (ii) Kodihar Tarawe Panchayat in Block Gamharia BH/BPSP/WB-191 / Construction of Panchayat Sarkar Bhawan in (i)Kolhai Under Single Stage - Two Patti Dumariya Panchayat IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope in Block Muraliganj & (ii) ion Puraini Panchayat in Block Kumarkhand Page 11 BH/BPSP/WB-192 / Construction of Panchayat Sarkar Bhawan in (i)Fulaut Single Stage - Two Purvi Panchayat in Block IDA / 51600 Post Request for Bids Open - National 423,183.63 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Chousa & (ii) Fulaut Paschim Panchayat in Block Chausa BH/BPSP/WB-193 / Construction of Panchayat Sarkar Bhawan in Pending Single Stage - Two (i)Khursandi Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Puraini & (ii) Bidi ion Ranpal Panchayat in Block Udakishanganj BH/BPSP/WB-194 / Construction of Panchayat Under Sarkar Bhawan in (i)Aurai Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Panchayat in Block Puraini Envelope ion & (ii) Ganeshpur Panchayat in Block Puraini BH/BPSP/WB-196 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in (i)Paroha IDA / 51600 Post Request for Bids Open - National 201,687.73 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Panchayat in Block Biharsarif BH/BPSP/WB-197 / Construction of Panchayat Pending Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope (i)Amartha Panchayat in ion Block Karakat BH/BPSP/WB-198 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Laxmipur Panchayat in IDA / 51600 Post Request for Bids Open - National 408,652.43 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Rahika & (ii) Shambhuar Panchayat in Block Rahika BH/BPSP/WB-199 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Basopatti Panchayat in IDA / 51600 Post Request for Bids Open - National 406,522.66 Signed 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Basopatti & (ii) Narar West Panchayat in Block Kaluahi BH/BPSP/WB-200 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Parashi Purvi Panchayat in Block Khutauna BH/BPSP/WB-201 / Construction of Panchayat Single Stage - Two IDA / 51600 Post Request for Bids Open - National 190,880.33 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Sarkar Bhawan in (i)Bind Envelope Panchayat in Block Bind BH/BPSP/WB-202 / Construction of Panchayat Sarkar Bhawan in (i)Gaur Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 406,108.70 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Andhrathadi & (ii) Baihat Panchayat in Block Lakhnaur BH/BPSP/WB-203 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 198,949.35 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Virshingpur Panchayat in Block Kalyanpur BH/BPSP/WB-204 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 405,191.26 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 (i)Mahinam Panchayat in Envelope Block Benipur & (ii) Ganesh Panchayat in Block Benipur BH/BPSP/WB-205 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Chhatwan Panchayat in IDA / 51600 Post Request for Bids Open - National 315,256.36 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Block Bodhgaya & (ii) Paluhar Panchayat in Block Tekari BH/BPSP/WB-206 / Construction of Panchayat Sarkar Bhawan in (i)Chaita Single Stage - Two IDA / 51600 Post Request for Bids Open - National 337,872.44 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Panchayat in Block Tekari Envelope & (ii) Makhdumpur Panchayat in Block Tekari BH/BPSP/WB-207 / Construction of Panchayat Sarkar Bhawan in (i)Gudru Single Stage - Two IDA / 51600 Post Request for Bids Open - National 346,359.65 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Panchayat in Block Gudru Envelope & (ii) Malpa Panchayat in Block Gudru BH/BPSP/WB-208 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 388,170.20 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 (i)Saduiiahpur Panchayat in Envelope Block Bisfi & (ii) Bisfi Panchayat in Block Bisfi BH/BPSP/WB-209 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 417,248.22 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 (i)Bishaul Panchayat in Envelope Block Harlakhi & (ii) Pipraun Panchayat in Block Harlakhi BH/BPSP/WB-210 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 198,411.65 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Mirzapur Panchayat in Block Hayaghat BH/BPSP/WB-211 / Construction of Panchayat Sarkar Bhawan in (i)Baital Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 350,259.43 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Bankebazar & (ii) Barheta Panchayat in Block Bankebazar Page 12 BH/BPSP/WB-212 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Guriyawa Panchayat in IDA / 51600 Post Request for Bids Open - National 347,887.19 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Block Mohanpur & (ii) Matihani Panchayat in Block Mohanpur BH/BPSP/WB-213 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 184,134.94 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Bhetaura Panchayat in Block Tankuppa BH/BPSP/WB-214 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Ganwpur Panchayat in Block Ujiyarpur BH/BPSP/WB-215 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 420,259.81 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Kodihar Tarawe Panchayat in Block Gamharia BH/BPSP/WB-216 / Construction of Panchayat Pending Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Sargawan Panchayat in ion Block Deo BH/BPSP/WB-217 / Construction of Panchayat Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 183,948.66 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Harpurbarheta Panchayat in Block sarairanjan BH/BPSP/WB-219 / Construction of Panchayat Under Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Lakchminiya Panchayat ion in Block Ladania BH/BPSP/WB-218 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Piperdih Panchayat in IDA / 51600 Post Request for Bids Open - National 363,837.12 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Block Nahutta & (ii) Baknaura Panchayat in Block Rohtas BH/BPSP/WB-220 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Piperdih Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Block Nahutta & (ii) Baknaura Panchayat in Block Rohtas BH/BPSP/WB-221 / Construction of Panchayat Sarkar Bhawan in (i)Tumba Single Stage - Two IDA / 51600 Post Request for Bids Open - National 338,564.74 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Panchayat in Block Rohtas Envelope & (ii) Telkap Panchayat in Block Rohtas BH/BPSP/WB-222 / Construction of Panchayat Sarkar Bhawan in (i)Bhaluri Single Stage - Two IDA / 51600 Post Request for Bids Open - National 342,630.83 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Panchayat in Block Dehri & Envelope (ii) Baligaon Panchayat in Block Akodhigola BH/BPSP/WB-223 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Darigawn Panchayat in IDA / 51600 Post Request for Bids Open - National 342,703.93 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Block Sasaram & (ii) Dhankadh Panchayat in Block Sasaram BH/BPSP/WB-224 / Construction of Panchayat Sarkar Bhawan in Single Stage - Two (i)Yadunathpur Panchayat in IDA / 51600 Post Request for Bids Open - National 348,016.98 Signed 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope Block Nohatta & (ii) Ulibnahi Panchayat in Block Nohatta BH/BPSP/WB-225 / Construction of Panchayat Pending Single Stage - Two Sarkar Bhawan in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-31 2018-09-05 2018-10-17 2018-12-30 2019-02-03 2019-08-02 Envelope (i)Andauli Panchayat in ion Block Kishanpur BH/BPSP/C-226 / Construction of Panchayat Pending Single Stage - Two Sarkar Bhawans in (1) IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-20 2018-11-25 2019-01-06 2019-03-21 2019-04-25 2019-10-22 Envelope Bachchi in Block Baheri (ii) ion Majhaulia in Block Hayaghat BH/BPSP/WB-182 / Construction of Panchayat Sarkar Bhawan in (i) Barna Pending Single Stage - Two Panchayat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-20 2018-11-25 2019-01-06 2019-03-21 2019-04-25 2019-10-22 Envelope Kusheswarshtan & (ii) ion Mahisaut Panchayat in Block Kusheswarshtan BH/BPSP/WB-195 / Construction of Panchayat Sarkar Bhawan in Pending Single Stage - Two (i)Samadhpura Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 Envelope Block Baheri (ii) Kurso ion Machhaita Panchayat in block tardih BH/BPSP/WB-227 / Construction of Panchayat Sarkar Bhawan in (i) Pending Single Stage - Two Kahamauti Panchayat in IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Envelope Simri Bakhtiyarpur Block ion (ii) Tariyama Panchayat in Simri Bakhtiyarpur BH/BPSP/WB-228 / Construction of Panchayat Sarkar Bhawan in (i) Pending Shobhan Panchayat in Block Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Khanpur (ii) Bihshanpur Envelope ion Abhi in Block Khanpur in District Samastipur Rosera Division Page 13 BH/BPSP/WB-229 / Construction of Panchayat Sarkar Bhawan in (i) Pending Single Stage - Two Tumba Panchayat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Envelope Rohtas (ii) Telkap ion Panchayat in Block Rohtas in District Rohtas Division Sasaram BH/BPSP/WB-230 / Construction of Panchayat Sarkar Bhawan in (i) Pending Bhaluari Panchayat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Block Dehri (ii) Baligaon Envelope ion Panchayat Block Akodhi Gola in District Rohtas Sasaram Division BH/BPSP/WB-231 / Construction of Panchayat Sarkar Bhawan in (i) Pending Darigawan Panchayat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Block Sasarami (ii) Envelope ion Dhankadh Panchayat Block Sasaram in District Rohtas Sasaram Division BH/BPSP/WB-232 / Construction of Panchayat Sarkar Bhawan in (i) Pending yadunathpur Panchayat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Block Nohatta (ii) Ulhibnahi Envelope ion Panchayat BlockNohatta in District Rohtas Sasaram Division BH/BPSP/WB-233 / Construction of Panchayat Sarkar Bhawan in (i) Pending Guriyawa Panchayat in Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Block Mohanpur (ii) Envelope ion Matihani Panchayat Block Mohanpur in District Gaya Sherghati Division BH/BPSP/WB-234 / Construction of Panchayat Pending Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Thengha Panchayat in Block Envelope ion Tardih District Darbhanga Benipur Division BH/BPSP/WB-235 / Construction of Panchayat Pending Sarkar Bhawan in (i) Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Chaita Dakshini Panchayat Envelope ion in Block ujiyarpur District Samastipur Rosera Division BH/BPSP/WB-236 / Construction of Panchayat Sarkar Bhawan in (i) Behat Pending shouth Panchayat in Block Single Stage - Two IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Lakhnaur & (ii) Gour Envelope ion Andhra Panchayat in Block Andhrathadi " BH/BPSP/WB-237 / Construction of Panchayat Sarkar Bhawan in (i) Pending Single Stage - Two Thuthi Panchyat in Block IDA / 51600 Post Request for Bids Open - National 0.00 Implementat 2018-11-26 2018-12-01 2019-01-12 2019-03-27 2019-05-01 2019-10-28 Envelope Chhatapur & (ii) Bhimpur ion Panchyat in Block Chhatapur GOODS Bid Evaluation Activity Reference No. Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. Short List and Opening of Combined Loan / Credit Market Contract Type Actual Amount Process Expression of Request for Evaluation of / Description Component Review Type Method Terms of Reference Draft Request for Technical Proposals Evaluation Report Signed Contract Contract Completion No. Approach (US$) Status Interest Notice Proposals as Issued Technical Proposal Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Page 14