Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Logistics Statistical System (P158817) Vietnam Logistics Statistical System (P158817) EAST ASIA AND PACIFIC | Vietnam | Macroeconomics, Trade and Investment Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2017 | Seq No: 3 | ARCHIVED on 04-Jun-2019 | ISR36123 | Implementing Agencies: Ministry of Transport, Transport Development and Strategy Institute Key Dates Key Project Dates Bank Approval Date:12-Sep-2016 Effectiveness Date:26-Sep-2017 Original Closing Date:26-Sep-2019 Revised Closing Date:26-Sep-2019 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective of this project is to establish a logistics statistical system to support strategic planning, evidence-based policy making, and monitoring the implementation of policies related to logistics in Vietnam. This would be achieved through the establishment of a national system for collecting, processing and publishing logistics statistics on an annual basis in Vietnam. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Implementation Status and Key Decisions The Grant was approved by Bank management on September 12, 2016 and the grant agreement only became effective a year later on September 26, 2017 due to internal procedures within the government. A framework agreement was signed in early 2018 between the World Bank and the OECD for OECD to provide technical assistance to TDSI in implementing the project. An international consultant based in the region was also engaged directly by the Bank to provide direct technical support to TDSI and ensure close technical support. 6/4/2019 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Logistics Statistical System (P158817) Delays in starting to implementing the project and delays in timely implementation of agreed activities has led to slippages in completing activities under the workplan and this is likely to result in some activities not being completed before the scheduled closing date of September 26, 2019. Some progress has recently been observed both in terms of procurement and disbursement.Disbursement to date has amounted to USD 70,000 or 14 percent of the total cost and it is expected that by September 26, the scheduled closing date of the grant agreement, approximately 70 percent of the grant will be disbursed . However, it is likely that activities including the analysis of the data to be collected and the building of the database may go beyond the current closing date of September 26, 2019. Thus, the client, Ministry of Transport, has requested for an extension of the closing date to June 30, 2020 to ensure that the project development objective and full deliverables will be achieved (a formal letter of request has been received). The client has already commenced engagement with MPI and SBV on extending the project to June 30, 2020. The task team will work closely with the client to monitor this process. A project implementation support mission was conducted by a joint team of World Bank and OECD/ITF staff between May 13-14, 2019 to provide technical support for the VLSS pilot survey, support TDSI to finalize agreed deliverables to ensure full compliance with the VLSS project objectives, and discuss and agree on timelines for the completion of all outstanding activities under the project. A Management Letter, with agreed actions and next steps will be sent to the client shortly. Risks Overall Risk Rating Risk Category Rating at Approval Previous Rating Current Rating Overall  --  Moderate  Substantial Comments Despite the progress made, the project is facing higher risk of timely completion if the closing date can't be extended. The team therefore change the risk rating from moderate in the previous ISR to substantial. Results Project Development Objective Indicators PHINDPDOTBL Indicator One: Reference to VLSS in Government policy and strategy documents (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 2.00 5.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 6/4/2019 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Logistics Statistical System (P158817) PHINDPDOTBL Two: Definition of indicators and guidelines for the collection, processing, and reporting of annual trade logistics data Indicator (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 1.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 PHINDPDOTBL Indicator Three: Pilot comprehensive logistics survey report with processed data (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 PHINDPDOTBL Indicator Four: Published pilot annual report on logistics statistics based on the survey result (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 03-Jul-2017 -- -- 02-Jul-2019 PHINDPDOTBL Indicator Five: Enhanced capacity within the MOT for collecting and reporting trade logistics data (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 Overall Comments Intermediate Results Indicators 6/4/2019 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Logistics Statistical System (P158817) PHINDIRITBL Intermediate Result Indicator One - Component 1: A set of indicators and their definition (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 1.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 PHINDIRITBL IntermediateResult Indicator Two - Component 1: Guidelines for collecting, processing, and reporting on annual logistics data; (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 PHINDIRITBL Intermediate Result Indicator Three - Component 1: Survey design (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 1.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 PHINDIRITBL Intermediate Result Indicator Four - Component 2: Validated Survey design (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 1.00 1.00 Date 03-Jul-2017 -- 31-May-2019 04-Sep-2018 6/4/2019 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Logistics Statistical System (P158817) PHINDIRITBL Intermediate Result Indicator Five - Component 2: Sampling and field test (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 1.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 PHINDIRITBL Intermediate Result Indicator Six - Component 2: Conduct of comprehensive survey (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 PHINDIRITBL Intermediate Result Indicator Seven - Component 2: Survey result and draft anual report (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 PHINDIRITBL Intermediate Result Indicator Eight - Component 3: Published pilot annual report and lessons learned (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 6/4/2019 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Logistics Statistical System (P158817) PHINDIRITBL IntermediateResult Indicator Nine - Component 3: Final guidelines for collecting, processing, and reporting on annual logistics data (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 03-Jul-2017 -- 31-May-2019 26-Sep-2019 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P158817 TF-A4566 Effective USD 0.50 0.50 0.00 0.07 0.43 14% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P158817 TF-A4566 Effective 12-Sep-2017 26-Sep-2017 26-Sep-2017 26-Sep-2019 26-Sep-2019 Cumulative Disbursements 6/4/2019 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Vietnam Logistics Statistical System (P158817) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/4/2019 Page 7 of 7 Public Disclosure Copy