The World Bank Report No: ISR8293 Implementation Status & Results Costa Rica Umbrella Project for Renewable Energy Sources (El Cote - Smal-Scale Hydro Power Plant). (P076421) Public Disclosure Copy Operation Name: Umbrella Project for Renewable Energy Sources (El Cote - Project Stage: Implementation Seq.No: 5 Status: ARCHIVED Archive Date: 19-Nov-2012 Smal-Scale Hydro Power Plant). (P076421) Country: Costa Rica Approval FY: 2003 Product Line: Carbon Offset Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: UNIDENTIFIED Implementing Agency(ies): Compania Nacional de Fuerza y Luz S.A (CNFL) Key Dates Board Approval Date 03-Dec-2002 Original Closing Date 31-Dec-2013 Last Archived ISR Date 07-Aug-2011 Effectiveness Date 03-Dec-2002 Revised Closing Date 31-Dec-2013 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Implementation Status Overview The project was successfully constructed and is now generating electricity in excess of original target. The project is registered with the United Nations Framework Convention on Climate Change (UNFCCC) and generating ERs. To date, two CER (certified emission reduction) issuances have taken place. Locations Country First Administrative Division Location Planned Actual Costa Rica Not Entered Vara Blanca Costa Rica Not Entered Cantón de Tilarán Public Disclosure Copy Costa Rica Not Entered Cantón de Santa Cruz Costa Rica Not Entered Poasito Costa Rica Not Entered Heredia Costa Rica Not Entered Provincia de Guanacaste Costa Rica Provincia de Guanacaste Provincia de Guanacaste ✔ Costa Rica Not Entered Lago Cote Page 1 of 2 The World Bank Report No: ISR8293 Country First Administrative Division Location Planned Actual Costa Rica Not Entered Laguna de Arenal Public Disclosure Copy Costa Rica Provincia de Alajuela Provincia de Alajuela ✔ Key Decisions Regarding Implementation None Related Projects There are no related projects. Public Disclosure Copy Page 2 of 2