Republic Of Yemen Water Sector Support Program WSSP Procurement Plan of WSSP Compiled 2009 - 2016 I. General 1. Project Information Project Name: Water Setor Support Program Country: Republic of Yemen Project ID: P 107037 Loan/Credit Numbers: IDA Grant No. H449 RY 2. Bank's approval date of Procurement Plan Original: Revision 1: Add new revisions 17/4/2012 3. Date of General Procurement Notice September 16, 2009 UN Development Business issue # 758 II. Goods, Work and Non-Consulting Services Thresholds 1. Prior Review Threshold. Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Unlike the case in IDA credit agreemens,the tresholds of contract amounts were indicted only in proc plan for 2009 as attachment 3 of agrred minutes of the IDA grant agreement and some information was incomplete as shown in the comments. Prior Review Threshold 1a. Procurement Category (USD) Comments Goods 500,000 As mentioned in attachment 3 Works 5,000,000 As mentioned in attachment 3 Non-Consultant Services N/A Include all categories authorized by the loan agreement Procurement Method 1b. Procurement Method Threshold (USD) Comments ICB (Goods) As shown confirmed on 20/1/2010 500,000 NCB (Goods) >50000 As Confirmed on 20/1/2010 Shopping (Goods) 50,000 ICB (Works) >5,000,000 NCB (Works) 5,000,000 As mentioned in attachment 3 Shopping works 200,000 ICB (Non-Consultant Services) N/A Include all methods authorized by the loan agreement 2. Prequalification. Bidders for _________ shall be prequlified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. NA 3. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): Refer to the relevant CDD project implementation document approved by the Bank 4. Reference to (if any) Project Operational/Procurement Manual: ??????? 5. Any Other Special Procurement Arrangements: [ncluding advance procurement and retroactive financing, if applicable 6. Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" sheet III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Threshold 1a. Procurement Category (USD) Comments Consulting Firms (Competitive) 200,000 Consulting Firms (Sole Source) All Individual Consultants (Competitive) 50,000 As mentioned in attachment 3 Individual Consultants (Sole Source) All SS contracts As mentioned in attachment 3 Include all categories authorized by the loan agreement Procurement Method 1b. Procurement Method Threshold (USD) Comments QCBS According to guidlunes and 200000 and more HTC QCB less than 200000 FCS less than 200000 LCS less than 200000 CQS less than 200000 Consulting Firms (Competitive) 200,000 Consulting Firms (Sole Source) All Individual Consultants (Competitive) 50,000 As mentioned in attachment 3 Individual Consultants (Sole Source) All ICB (Non-Consultant Services) NA Include all methods authorized by the loan agreement 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Note: OPCPR list of ceilings can be found here:http://go.worldbank.org/MKXO98RY40 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] NA 4. Consultancy Assignments with Selection Methods and Time Schedule: See attached "Consulting Services" sheet IV. Implementing Agency Capacity Building Activities with Time Schedule: See attached "Capacity Building" sheet P107037 Updated Republic of Yemen Water Sector Support Program (WSSP) Procurement Plan for Goods & Works for Part C - WSSP for Year 2009 - 2012 Canceled activities Red raws Green cells for completed contracts white Red cells for canceled cells for under implementation contracts contracts WSSP - GARWSP procurement plan 2010 - 2016 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned 08/G/RWSS/WSSP/09 Procurement of pipes and Goods Prior NCB 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Mahaweet 15-Dec-09 2-Jan-10 G.Irr.Cooperative 14-Apr-10 Actual 14-Jun-09 15-Jun-09 14-Jul-09 8-Aug-09 13-Aug-09 20-Dec-09 1-Feb-10 23-Mar-10 285,763.00 US $ Sanaa, Yemen 21-Jun-10 285,763.00 285,763.00 Completed Planned 05/G/RWSS/WSSP/09 Procurement of pipes and Goods Prior NCB 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in saada 15-Dec-09 2-Jan-10 Heskan Co. 14-Apr-10 Actual 14-Jun-09 15-Jun-09 14-Jul-09 10-Aug-09 15-Aug-09 15-Dec-09 1-Feb-10 20-Mar-10 278,522.00 US $ Sanaa, Yemen 18-Jun-10 278,522.00 278,522.00 Completed Planned 16/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in lahj 15-Dec-09 2-Jan-10 G.Irr.Cooperative 14-Apr-10 Actual 14-Jun-09 15-Jun-09 10-Sep-09 25-Sep-09 30-Sep-09 4-Oct-09 1-Feb-10 24-Mar-10 136,998.68 US $ Sanaa, Yemen 22-Jun-10 136,998.68 136,998.68 Completed Planned 03/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Haja 15-Dec-09 2-Jan-10 G.Irr.Cooperative 14-Apr-10 Actual 14-Jun-09 15-Jun-09 3-Jul-09 26-Jul-09 1-Aug-09 15-Feb-10 1-Feb-10 26-Mar-10 371,021.73 US $ Sanaa, Yemen 24-Jun-10 285,763.00 285,763.00 Completed Planned 05/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Sanaa 15-Dec-09 2-Jan-10 G.Irr.Cooperative 14-Apr-10 Actual 14-Jun-09 15-Jun-09 6-Jul-09 30-Jul-09 5-Aug-09 15-Aug-09 1-Feb-10 24-Mar-10 137,093.39 US $ Sanaa, Yemen 22-Jun-10 137,093.39 137,093.39 Completed Planned 01/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Mareb 15-Dec-09 2-Jan-10 National trading 14-Apr-10 Actual 14-Jun-09 15-Jun-09 28-Jun-09 24-Jul-09 29-Jul-09 8-Oct-09 1-Feb-10 10-Jan-10 76,920.00 US $ Co.Sanaa, Yemen 10-Apr-10 76,920.00 76,920.00 Completed Planned 01/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Shabwa 15-Dec-09 2-Jan-10 G.Irr.Cooperative 14-Apr-10 Actual 14-Jun-09 15-Jun-09 4-Jul-09 30-Jul-09 5-Aug-09 23-Aug-09 1-Feb-10 23-Mar-10 336,631.75 US $ Sanaa, Yemen 21-Jun-10 336,631.75 336,631.75 Completed Planned 04/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 G.Irr.C & Green 30-Oct-09 Revised fittings in Hudaida 15-Dec-09 2-Jan-10 Land Sanaa, 14-Apr-10 Actual 14-Jun-09 15-Jun-09 15-Jul-09 10-Aug-09 15-Aug-09 19-Aug-09 1-Feb-10 20-Mar-10 303,265.00 US $ Yemen 18-Jun-10 303,265.00 303,265.00 Completed Planned 05/G/RWSS/WSSP/09 Procurement of pumps and Goods Prior NCB 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 Al-Abrag & Abu 30-Sep-09 Revised accessories in Hudaida 15-Dec-09 2-Jan-10 Alregal Co Sanaa, 14-Apr-10 Actual 14-Jun-09 15-Jun-09 15-Jul-09 10-Aug-09 10-Aug-09 1-Oct-09 1-Feb-10 25-Mar-10 90,232.00 US $ Yemen 23-Jun-10 90,232.00 90,232.00 Completed Planned 06/G/RWSS/WSSP/09 Procurement of pumps and Goods Prior NCB 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 30-Sep-09 Revised accessories in saada 9-Jan-10 23-Jan-10 6-Feb-10 27-Feb-10 31/0531-5-2010/2010 Al-Sunidar trading Actual 14-Jun-09 15-Jun-09 15-Dec-09 10-Jan-10 15-Jan-10 1-Feb-10 1-Feb-10 9-Mar-10 155,958.00 US $ Sanaa, Yemen 7-Jun-10 155,958.00 155,958.00 Completed Planned 17/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 14-Apr-10 Revised accessories in lahj Abu Alrgal Sanaa, Actual 14-Jun-09 15-Jun-09 29-Jun-09 22-Jul-09 27-Jul-09 10-Aug-09 1-Feb-10 10-Jan-10 24,772.44 US $ Yemen 10-Apr-10 24,772.44 24,772.44 Completed Planned 04/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 14-Apr-10 Revised accessories in Haja Abu Alrgal Sanaa, Actual 14-Jun-09 15-Jun-09 3-Jul-09 25-Jul-09 1-Aug-09 8-Aug-09 1-Feb-10 27-Feb-10 62,086.00 US $ Yemen 28-May-10 62,086.00 12,413.60 Completed Planned 04/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 Al-Abrag & Abu 14-Apr-10 Revised accessories in Sanaa Alregal Co Sanaa, Actual 14-Jun-09 15-Jun-09 6-Jul-09 30-Jul-09 5-Aug-09 15-Aug-09 15-Sep-09 23-Dec-09 172,941.00 US $ Yemen 23-Mar-10 172,941.00 172,941.00 Completed Planned 02/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 14-Apr-10 Revised accessories in Mareb Al-Sunidar trading Actual 14-Jun-09 15-Jun-09 28-Jun-09 24-Jul-09 29-Jul-09 8-Aug-09 1-Feb-10 10-Jan-10 104,045.00 US $ Sanaa, Yemen 10-Apr-10 104,045.00 104,045.00 Completed Planned 02/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 Al-Abrag & Abu 14-Apr-10 Revised accessories in Shabwa Alregal Co Sanaa, Actual 14-Jun-09 15-Jun-09 4-Jul-09 30-Jul-09 5-Aug-09 20-Aug-09 20-Feb-10 131,956.00 US $ Yemen 21-May-10 131,956.00 131,956.00 Completed Rashad ALhaj 4/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 1/ MAH Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Heskan Co. Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Mahaweet Post NCB 1-Sep-10 1-Oct-10 1-Oct-10 20-Oct-10 15-Nov-10 22-Dec-10 Sanaa, Yemen Actual ‫Ù?علي‬ 1-Feb-10 28-Mar-10 28-Mar-10 29-Aug-10 22-Sep-10 306,876.09 21-Dec-10 306,876.09 23,322.58 Completed Planned ‫مقترح‬ 1/ SAD Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in saada Post NCB 7-May-10 7-Jun-10 7-Jun-10 25-Jun-10 2-Oct-10 Heskan Co. 15-Jan-11 Actual ‫Ù?علي‬ 1-Feb-10 7-Jun-10 7-Jul-10 7-Jul-10 19-Jul-10 28-Jul-10 153,257.30 US $ Sanaa, Yemen 26-Oct-10 153,257.30 11,647.55 Completed Planned ‫مقترح‬ 1/ LAH Procurement of pipes and Goods post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in lahj G.Irr.Cooperative 20-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 18-Feb-10 17-Mar-10 22-Mar-10 1-Apr-10 16-Jun-10 527,180.63 US $ Sanaa, Yemen 14-Sep-10 527,180.63 40,065.73 Completed Planned ‫مقترح‬ 1/ SAN Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Sanaa Post NCB 23-Jun-10 23-Jul-10 23-Jul-10 15-Aug-10 17-Oct-10 G.Irr.Cooperative 25-Dec-10 Actual ‫Ù?علي‬ 1-Feb-10 20-Mar-10 14-Apr-10 19-Apr-10 2-Oct-10 30-Oct-10 477,229.70 US $ Sanaa, Yemen 28-Jan-11 477,229.70 36,269.46 Completed Planned ‫مقترح‬ 1/ MAR /G/RWSS/ Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 H.Al-Hbabi 29-Sep-10 Revised ‫متوقع‬ WSSP/10 fittings in Mareb Post NCB 1-May-10 1-Jun-10 1-Jun-10 5-Oct-10 15-Oct-10 corp. Sanaa, 30-Dec-10 Actual ‫Ù?علي‬ 1-Feb-10 12-May-10 7-Jun-10 12-Jun-10 15-Jul-10 2-Aug-10 82,831.00 US $ Yemen 12-Jan-11 82,831.00 6,295.16 Completed Planned ‫مقترح‬ 1/ SHB Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 AL Almeen + National Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Shabwa Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Company for Sponge 25-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 28-Feb-10 29-Mar-10 4-Apr-10 19-Jun-10 23-Jun-10 397,148.00 US $ & Plastic Industry 21-Sep-10 397,148.00 30,183.25 Completed Planned ‫مقترح‬ 1/ HUD Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 G.Irr.Cooperative Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings for two contracts in 25-Dec-10 + alshahab co. Actual ‫Ù?علي‬ Hudaida 1-Feb-10 7-Mar-10 2-Apr-10 7-Apr-10 24-Jul-10 25-Aug-10 612,856.99 US $ Sanaa, Yemen 23-Nov-10 612,856.99 46,577.13 Completed Planned ‫مقترح‬ 1/ TAZ Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 abo fras 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in taiz org.Sanaa, 30-Nov-10 577,454.66 Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 5-Apr-10 10-Apr-10 24-Jul-10 31-Aug-10 579,515.23 US $ Yemen 29-Nov-10 43,886.54 Completed Planned ‫مقترح‬ 1/ ABN Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Abyan Post NCB 15-Apr-10 15-May-10 15-May-10 15-Jun-10 7-Jul-10 Mass Trading 29-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 28-Apr-10 20-May-10 25-May-10 20-Jun-10 21-Aug-10 384,000.00 US $ Sanaa, Yemen 19-Nov-10 384,000.00 29,184.00 Completed Planned ‫مقترح‬ 1/ HAD Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in moklla Post NCB 15-Apr-10 15-May-10 15-May-10 15-Jun-10 7-Jul-10 20-Nov-10 H.Al-Hbabi Actual ‫Ù?علي‬ 1-Feb-10 20-Apr-10 19-May-10 24-May-10 14-Aug-10 4-Sep-10 US $ 3-Dec-10 Planned ‫مقترح‬ Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 509,074.83 corp. Sanaa, 29-Sep-10 509,074.83 38,689.69 1/ HAD Procurement of pipes and Goods Revised ‫متوقع‬ Post NCB 15-Apr-10 15-May-10 15-May-10 15-Jun-10 7-Jul-10 Yemen 20-Nov-10 /G/RWSS/WSSP/10 fittings in saioon Actual ‫Ù?علي‬ 1-Feb-10 20-Apr-10 19-May-10 24-May-10 14-Aug-10 4-Sep-10 US $ 3-Dec-10 Completed Planned ‫مقترح‬ 1/ JWF Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 National 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in al-jowf Post NCB 25-May-10 20-Jun-10 25-Jun-10 15-Jul-10 15-Oct-10 Company for 15-Dec-10 Completed Actual ‫Ù?علي‬ 1-Feb-10 1-Jun-10 30-Jun-10 30-Jul-10 24-Jul-10 30-Aug-10 7,614.00 US $ Sponge & 28-Nov-10 7,614.00 578.66 Planned ‫مقترح‬ 1/ BYD Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 H.Al-Hbabi 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in al-bedhaa corp. Sanaa, 1-Sep-10 Completed Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 3-May-10 29-May-10 542,716.00 US $ Yemen 27-Aug-10 542,716.00 41,246.42 Planned ‫مقترح‬ 1/ DHL /G/RWSS/ Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 fittings in aldhale Mass Trading 1-Sep-10 Completed Actual ‫Ù?علي‬ 1-Feb-10 21-Feb-10 16-Mar-10 21-Mar-10 3-May-10 30-May-10 238,600.00 US $ Sanaa, Yemen 28-Aug-10 238,600.00 18,133.60 Planned ‫مقترح‬ 1/ AMR Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 H.Al-Hbabi 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in amran Post NCB 20-May-10 15-Jun-10 20-Jun-10 10-Jul-10 30-Jul-10 corp. Sanaa, 15-Nov-10 Completed Actual ‫Ù?علي‬ 1-Feb-10 28-May-10 21-Jun-10 27-Jun-10 24-Jul-10 15-Aug-10 476,475.50 US $ Yemen 20-Nov-10 476,475.50 36,212.14 Planned ‫مقترح‬ 1/ RYM Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 H.Al-Hbabi 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in ryimah corp. Sanaa, Completed Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 3-May-10 31-May-10 421,630.28 US $ Yemen 29-Sep-10 421,630.28 32,043.90 Planned ‫مقترح‬ 1/ MAH Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 National 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in al-mahra 15-Oct-10 30-Oct-10 Company for 30-Jan-11 Completed Actual ‫Ù?علي‬ 1-Feb-10 9-May-10 1-Jun-10 6-Jun-10 18-Jun-10 17-Jul-10 85,418.00 Sponge & 15-Jan-11 85,418.00 6,491.77 Planned ‫مقترح‬ 1/ DHM Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 H.Al-Hbabi 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in thamar Post NCB 5-Mar-10 1-Apr-10 5-Apr-10 5-May-10 7-Jun-10 corp. Sanaa, 29-Sep-10 Completed Actual ‫Ù?علي‬ 1-Feb-10 1-Mar-10 25-Mar-10 31-Mar-10 3-May-10 1-Jun-10 492,896.73 US $ Yemen 29-Sep-10 492,896.73 37,460.15 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Mahaweet Post NCB 1-Jul-10 25-Jul-10 30-Jul-10 15-Aug-10 1-Sep-10 10-Nov-10 119636.62 Completed Actual ‫Ù?علي‬ 1-Feb-10 3-Aug-10 2-Sep-10 2-Sep-10 1-Oct-10 30-Oct-10 124,055.00 US $ 29-Sep-10 9,092.38 Planned ‫مقترح‬ * 2/ SAD Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Al sonidar 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in saada Post NCB 1-Apr-10 25-Apr-10 30-Apr-10 1-Jun-10 10-Aug-10 trading Sanaa, 10-Oct-10 128970 Completed Actual ‫Ù?علي‬ 1-Feb-10 3-Apr-10 1-May-01 5-May-01 23-May-10 17-Jul-10 128,970.00 US $ Yemen 29-Sep-10 17,390.51 Planned ‫مقترح‬ 2/ LAH Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Abu Alregal Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in lahj Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 15-Aug-10 Completed Sanaa, Yemen Actual ‫Ù?علي‬ 1-Feb-10 18-Feb-10 15-Mar-10 20-Mar-10 2-Apr-10 25-Apr-10 120,886.00 US $ 29-Sep-10 120022 9,121.67 Planned ‫مقترح‬ 2/ HAJ Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Al 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Haja Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 abrag&Abureg 15-Aug-10 Completed Actual ‫Ù?علي‬ 1-Feb-10 22-Feb-10 17-Mar-10 23-Mar-10 1-Apr-10 16-May-10 179,035.00 US $ al&alwatary 29-Sep-10 178256.77 20,305.23 Planned ‫مقترح‬ 2/ SAN Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ Post NCB 23-Jun-10 23-Jul-10 23-Jul-10 10-Aug-10 30-Aug-10 Alabrag&Abur 30-Oct-10 Completed /G/RWSS/WSSP/10 accessories for (18)contracts 781514.99 egal&alwatary Actual ‫Ù?علي‬ in Sanaa 1-Feb-10 7-Mar-10 1-Apr-10 5-Apr-10 19-Jun-10 19-Jul-10 788,401.22 US $ 16-Nov-10 76,533.18 Planned ‫مقترح‬ 2/ MAR /G/RWSS/ Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag&alwat Revised ‫متوقع‬ WSSP/10 accessories for (15)contracts 20-Aug-10 339352.1 Completed ary&Asonidar Actual ‫Ù?علي‬ in Mareb 1-Feb-10 3-Mar-10 28-Mar-10 3-Apr-10 3-May-10 5-Jun-10 338,888.00 US $ 3-Sep-10 25,790.76 Planned ‫مقترح‬ 2/ SHB Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag&Abur Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Shabwa Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 25-Aug-10 Completed egal&Alwatary Actual ‫Ù?علي‬ 1-Feb-10 28-Feb-10 28-Mar-10 4-Apr-10 20-Apr-10 12-Jun-10 269,159.00 US $ 29-Sep-10 269,159.00 20,456.08 Planned ‫مقترح‬ 2/ HUD Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag&Abur Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Hudaida Post NCB 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 15-Aug-10 248213.57 Completed egal&alwatary Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 1-Apr-10 7-Apr-10 3-May-10 5-Jun-10 249,066.00 US $ 3-Sep-10 28,094.24 Rashad ALhaj 5/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ *** 2/ TAZ Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag&Also 29-Sep-10 revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (20)contracts 9-Jun-10 9-Jul-10 9-Jul-10 1-Aug-10 20-Aug-10 nidar& Ali 30-Jan-11 406344.89 Completed Actual ‫Ù?علي‬ in taez 1-Feb-10 7-Mar-10 5-Apr-10 10-Apr-00 15-May-10 4-Oct-10 595,059.94 US $ Alsonidar 20-May-11 54,387.45 Planned ‫مقترح‬ 2/ IBB Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ Post NCB Alabrag&alwat 15-Sep-10 Completed /G/RWSS/WSSP/10 accessories for (22)contracts 698567 ary&Asonidar Actual ‫Ù?علي‬ in Ibb 1-Feb-10 3-Mar-10 30-Mar-10 3-Apr-10 8-May-10 29-May-10 685,000.00 US $ 27-Aug-10 53,091.09 Planned ‫مقترح‬ 2/ ABN Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Abyan Post NCB 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 197761 Completed Company Actual ‫Ù?علي‬ 1-Feb-10 5-Mar-10 30-Mar-10 5-Apr-10 18-Apr-10 15-May-10 200,400.00 US $ 13-Aug-10 15,029.84 Planned ‫مقترح‬ 2/ HAD Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag&Ason Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in moklla Post NCB 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 149,953.00 149,953.00 Completed idar Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 1-Apr-10 7-Apr-10 21-Apr-10 5-Jun-10 US $ 3-Sep-10 11,396.43 Planned ‫مقترح‬ 2/ HAD Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag&Ason Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in saioon Post NCB 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 128366.25 128,366.25 Completed idar Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 1-Apr-10 7-Apr-10 21-Apr-10 5-Jun-10 US $ 3-Sep-10 9,755.84 Planned ‫مقترح‬ 2/ BYD Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in al-bedhaa Post NCB 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 Alabrag 1-Jul-10 Completed Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 20-Apr-10 9-May-10 120,500.00 US $ 7-Aug-10 120,500.00 9,158.00 Planned ‫مقترح‬ 2/ DHL /G/RWSS/ Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag&Ason Revised ‫متوقع‬ WSSP/10 accessories in aldhale Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 Completed idar Actual ‫Ù?علي‬ 1-Feb-10 21-Feb-10 16-Mar-10 21-Mar-10 4-Apr-10 23-Apr-10 149,149.00 US $ 22-Jul-10 152953.52 11,624.47 Planned ‫مقترح‬ 2/ AMR Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag&Ason Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (9) contracts Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 Completed idar Actual ‫Ù?علي‬ in amran 1-Feb-10 23-Feb-10 18-Mar-10 23-Mar-10 10-Apr-10 18-Apr-10 328137.15 US $ 17-Jul-10 328,137.15 24,938.42 Planned ‫مقترح‬ 2/ RYM Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag&Ason Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (9) contracts in Post NCB 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 369873.01 Completed idar Actual ‫Ù?علي‬ ryimah 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 3-May-10 29-May-10 US $ 27-Aug-10 369,873.01 28,110.35 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in al-mahra Alabrag&M.als Completed Actual ‫Ù?علي‬ 1-Feb-10 24-Mar-10 19-Apr-10 24-Apr-10 10-May-10 29-May-10 99,993.00 US $ hraf 27-Aug-10 100,192.00 7,614.59 Planned ‫مقترح‬ 2/ DHM Procurement of pumps and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 /G/RWSS/WSSP/10 accessories for (28)contracts Alabrag&Abur Revised ‫متوقع‬ Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 Completed in thamar ega Actual ‫Ù?علي‬ 1-Feb-10 3-Mar-10 25-Mar-10 31-Mar-10 15-May-10 16-Jun-10 872,056.00 US $ 14-Sep-10 870,056.00 66,124.26 Planned ‫مقترح‬ **1/HQ /G/RWSS/ Goods of Tools and materials Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 laboratory in HQ 1-Sep-10 30-Sep-10 30-Sep-10 15-Oct-10 30-Oct-10 23-Jan-11 250,438.00 Completed Actual ‫Ù?علي‬ 1-Feb-10 18-Aug-10 18-Sep-10 18-Sep-10 15-Oct-10 25-Oct-10 254,424.00 US $ ‫بيتا يمن‬ 12-Jan-11 19,033.29 Rashad ALhaj 6/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 1/ DHL /G/RWSS/ Procurement of pipes and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ WSSP/11 fittings in aldhale Completed Actual ‫Ù?علي‬ 30-Jan-11 26-Jan-11 26-Feb-11 26-Feb-11 2-Mar-11 4-Apr-11 444,989.50 US $ H.A.Al-Hbabi 15-Dec-12 444,989.50 33,813.92 Planned ‫مقترح‬ 1/ RYM Procurement of pipes and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 fittings in ryimah Completed Actual ‫Ù?علي‬ 25-Jan-11 3-Feb-11 5-Mar-11 5-Mar-11 6-May-11 26-May-11 356,315.00 US $ H.Al-Hbabi 15-Dec-12 356,315.00 27,079.96 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories for contracts in Alabrag&M.als 24-Sep-11 Completed Actual ‫Ù?علي‬ Mahaweet 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 19-Mar-11 27-Apr-11 111,023.51 us $ hraf 23-Jan-13 111,023.51 22,923.59 Planned ‫مقترح‬ 2/ DHL /G/RWSS/ Procurement of pumps and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ WSSP/11 accessories in aldhale Completed Actual ‫Ù?علي‬ 30-Jan-11 26-Jan-11 26-Feb-11 26-Feb-11 2-Mar-11 20-Apr-11 161,356.52 US $ Aburegal tradingSanaa, Yemen 12-Jul-11 159,717.50 19,669.60 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories in Al-mahra 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 28-Nov-12 Completed Actual ‫Ù?علي‬ 30-Jan-11 2-Feb-11 5-Mar-11 5-Mar-11 16-Mar-11 9-May-12 147,800.00 US $ Alabrag Co. 5-Jul-12 147,800.00 29,560.00 Planned ‫مقترح‬ 2/ SAN Procurement of pumps and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 Abudallh A. 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories for (Al qatisha -Algeel 21-Jun-13 21-Jul-13 21-Jul-13 15-Aug-13 30-Aug-13 Asonidar 28-Nov-13 78,410.95 78,410.95 Completed Actual ‫Ù?علي‬ Naham-Bait Bos-bait Aldeeb- 30-Jan-11 26-Jun-13 27-Jul-13 27-Jul-13 15-Sep-13 10-Oct-13 224,429.52 us 20-Mar-14 Planned ‫مقترح‬ 2/ HUD Procurement of pumps and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ Post NCB 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 Alabrag&alwat 28-Nov-12 255,755.65 Completed /G/RWSS/WSSP/11 accessories for (11)contracts Actual ‫Ù?علي‬ 25-Jan-11 19-Dec-12 221,261.05 us ary 16-Jan-13 44,587.35 in Hudaida Planned ‫مقترح‬ 2/ HAD Procurement of pumps and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories in Hadramout 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 28-Nov-12 109,500.00 Completed Actual ‫Ù?علي‬ 15-Feb-11 19-Jul-12 28-Aug-12 28-Aug-12 19-Sep-12 30-Sep-12 109,500.00 us Alabrag Co. 24-Oct-12 21,900.00 Planned ‫مقترح‬ 2/ RYM Procurement of pumps and Goods Post NCB 25-Jan-11 12-Feb-11 14-Mar-11 14-Mar-11 29-Mar-11 16-Apr-11 16-Jul-11 Revised ‫متوقع‬ 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 ‫محالت الشاطبى‬ 28-Nov-12 212,958.95 Completed /G/RWSS/WSSP/11 accessories in Ryimah Actual ‫Ù?علي‬ 25-Jan-11 7-Jul-12 7-Aug-12 7-Aug-12 25-Aug-12 17-Nov-12 212,576.74 us ‫التجاريه‬ 26-Feb-13 43,912.65 Planned ‫مقترح‬ 2/ AMR Procurement of pumps and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ 21-Jan-12 20-Feb-12 20-Feb-12 16-Mar-12 21-Jun-12 Alabrag Co. 19-Sep-12 Completed /G/RWSS/WSSP/11 accessories in amran Actual ‫Ù?علي‬ 25-Jan-11 9-Jul-12 11-Aug-12 11-Aug-12 9-Dec-12 64,000.00 us Sanaa-Yemen 30-Dec-12 64,000.00 12,800.00 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB 25-Jan-13 5-Feb-13 7-Mar-13 7-Mar-13 22-Mar-13 9-Apr-13 9-Jul-13 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/13 accessories for Alsheeny in Al- Alabrag Co. the payment under Actual ‫Ù?علي‬ mahra 30-Jan-13 10-May-13 8-Jun-13 8-Jun-13 26-Jun-13 26-Jun-13 38,800.00 us Sanaa-Yemen 16-Apr-14 processing Planned ‫مقترح‬ 2/ MAR /G/RWSS/ Procurement of pumps and Goods Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ 2-Jan-13 1-Feb-13 1-Feb-13 26-Feb-13 13-Mar-13 Alabrag Co. 11-Jun-13 Completed WSSP/11 accessories in Mareb Actual ‫Ù?علي‬ 5-Feb-11 17-Apr-13 15-May-13 15-May-13 1-Jun-13 8-Jul-13 53,800.00 us Sanaa-Yemen 20-Feb-14 53,800.00 53,800.00 Planned ‫مقترح‬ 4/ Supply of pumping unit for Good Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/G/RWSS/WSSP/ (hajreen ) - Taiz Ali Alsonidar Completed Actual ‫Ù?علي‬ 13 21-Jul-13 21-Aug-13 21-Aug-13 46,500.00 us Sanaa-Yemen 7-Aug-14 46,500.00 46,500.00 Planned ‫مقترح‬ 4/ Supply of pumping unit Good Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/G/RWSS/WSSP/ for(Daba ) - Taiz Ali Alsonidar Completed Actual ‫Ù?علي‬ 13 21-Jul-13 21-Aug-13 21-Aug-13 37,500.00 us Sanaa-Yemen 7-Aug-14 37,500.00 37,500.00 Planned ‫مقترح‬ 4/ Supply of pumping unit for Good Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/G/RWSS/WSSP/ (Alsafeh ) - Taiz Ali Alsonidar Completed Actual ‫Ù?علي‬ 13 21-Jul-13 21-Aug-13 21-Aug-13 9-Oct-13 34,746.91 us Sanaa-Yemen 7-Aug-14 34,746.91 34,746.91 Planned ‫مقترح‬ Procurement of FM system Goods post NS 15-Sep-12 21-Sep-12 5-Oct-12 5-Oct-12 15-Oct-12 2-Nov-12 Completed and Revised ‫متوقع‬ HQ/WSSP/G/NS/12/1 the payment under Actual ‫Ù?علي‬ 5-Sep-12 5-Oct-12 5-Oct-12 16-Oct-12 20,206.00 US Otober 2014 processing Planned ‫مقترح‬ 1/ Supply and installation of Goods Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Completed and Revised ‫متوقع‬ TAZ/G/RWSS/WSSP/ pumping unit for (Aldhaabob) 3-Aug-14 2-Sep-14 2-Sep-14 27-Sep-14 12-Oct-14 10-Jan-15 the payment under Actual ‫Ù?علي‬ 14 in Taiz 1-Sep-14 30-Sep-14 30-Sep-14 22-Oct-14 11-Nov-14 37,500.00 US 31-Dec-14 processing Total of completed Goods contracts 17,437,202.59 16,947,491.81 4,035,815.59 Planned ‫مقترح‬ Post NCB 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 Natco 21-Nov-12 3/ HQ Procurement of Emergency Goods Revised ‫متوقع‬ 11-Jan-13 11-Jan-13 5-Feb-13 Campany 288,439.19 288,439.19 completed /G/RWSS/WSSP/12 Computers & accessories& Actual ‫Ù?علي‬ 12-Dec-12 20-Jan-13 20-Jan-13 9-Oct-13 294,413.69 us Sanaa-Yemen 6-Jun-14 copy machine ,…. in HQ Natco Planned ‫مقترح‬ 3/ HQ Procurement of Emergency Goods Post NCB 31-Mar-12 1-Jan-13 31-Jan-13 31-Jan-13 15-Feb-13 5-Mar-13 3-Jun-13 Revised ‫متوقع‬ Campany completed /G/RWSS/WSSP/13 copy machine ,…. in HQ Actual ‫Ù?علي‬ 17-Jan-13 20-Feb-13 20-Feb-13 20-May-13 27,144.00 us Sanaa-Yemen 6-Jun-14 Planned ‫مقترح‬ 4/ HQ Procurement of Emergency Goods Post NCB 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ 3-Aug-14 2-Sep-14 2-Sep-14 27-Sep-14 12-Oct-14 Ardh Hemiar 18-Feb-15 completed /G/RWSS/WSSP/12 Office Furniture in HQ Actual ‫Ù?علي‬ 17-May-14 17-Jun-14 17-Jun-14 17-Nov-14 20-Dec-14 110,970.00 us Sanaa-Yemen Total of completed 432,527.69 288,439.19 288,439.19 Planned ‫مقترح‬ emergancy 2/ MAHcontracts Procurement of pumps and Goods Post NCB 25-Jan-11 1-Jan-15 31-Jan-15 31-Jan-15 15-Feb-15 5-Mar-15 4-Jun-15 Revised ‫متوقع‬ /G/RWSS/WSSP/15 accessories for Al gafara & Actual ‫Ù?علي‬ Al wahoaha contracts in Planned ‫مقترح‬ 4/ HQ Procurement of Stationaries Goods Post NCB 31-Mar-12 4-May-12 3-Jun-12 3-Jun-12 18-Jun-12 6-Jul-12 4-Oct-12 Revised ‫متوقع‬ 8-Dec-14 7-Jan-15 7-Jan-15 1-Feb-15 16-Feb-15 /G/RWSS/WSSP/14 in HQ Actual ‫Ù?علي‬ 23-Dec-14 28-Jan-15 28-Jan-15 Planned ‫مقترح‬ 1/ HQ Procurement of Emergency lab Goods Post NCB 31-Mar-12 4-May-12 3-Jun-12 3-Jun-12 18-Jun-12 6-Jul-12 4-Oct-12 Revised ‫متوقع‬ 8-Dec-14 7-Jan-15 7-Jan-15 1-Feb-15 16-Feb-15 /G/RWSS/WSSP/12 equipments in HQ Actual ‫Ù?علي‬ Planned ‫مقترح‬ 2/ HQ Procurement of Emergency Goods Post NCB 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ 8-Dec-14 7-Jan-15 7-Jan-15 1-Feb-15 16-Feb-15 /G/RWSS/WSSP/12 Survey equipments in HQ Actual ‫Ù?علي‬ 23-Dec-14 28-Jan-15 28-Jan-15 Planned ‫مقترح‬ 3/ HQ Procurement of Emergency Goods Post NCB 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ 8-Dec-14 7-Jan-15 7-Jan-15 1-Feb-15 16-Feb-15 /G/RWSS/WSSP/12 water resources equipments in Actual ‫Ù?علي‬ 23-Dec-14 28-Jan-15 28-Jan-15 HQ Planned ‫مقترح‬ 1/ HAJ Procurement of pipes and Goods Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Haja Prior ICB 5-Oct-10 10-Oct-10 20-Oct-10 2-Dec-10 2-Dec-10 21-Jan-11 5-Feb-11 21-Feb-11 22-May-11 Actual ‫Ù?علي‬ 5-Oct-10 17-Oct-10 14-Nov-10 27-Dec-10 27-Dec-10 1-Mar-11 29-Mar-11 18-Jun-12 1,344,345.97 under termination Rashad ALhaj 7/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned 07- Various Water & Sanitation Civil Works Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 26-Aug-10 1-Sep-10 30-Dec-10 Revised 3/CW/RWSS/WSSP/0 Works alradyah in Hudaida Prior NCB 10-Oct-10 16-Oct-10 15-Nov-10 15-Nov-10 29-Nov-10 8-Jan-11 24-Jan-11 25-Mar-11 Completed Actual 9 1-Aug-10 31-Oct-10 10-Nov-10 11-Dec-10 11-Dec-10 25-Dec-10 7-Feb-11 9-Feb-11 44,094.40 US $ Qaid Al malky ‫ قايد المالكي‬20-Jul-11 27,208.80 27,208.80 Planned 01- Various Water & Sanitation Civil Works Prior NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 26-Aug-10 1-Sep-10 Hady ‫هادي هاديان‬ 30-Dec-10 Revised 2/CW/RWSS/WSSP/0 Works al alqar in Ma'reb Prior NS 17-May-10 5-Oct-10 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 4-Jan-11 20-Jan-11 ,Hadyan Sanaa 15-May-11 Completed Actual 9 1-Oct-10 25-Oct-10 25-Oct-10 9-Nov-10 9-Nov-10 20-Dec-10 5-Jan-11 15-Jan-11 4,031.67 US $ Yemen 11-May-11 4,031.67 4,031.67 Planned 01- Various Water & Sanitation Civil Works Prior NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 Hady ‫هادي هاديان‬ 30-Dec-10 Revised 1/CW/RWSS/WSSP/0 Works qasha albared in Ma'reb Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 ,Hadyan Sanaa 15-Mar-11 Completed Actual 9 1-Oct-10 26-Oct-10 9-Nov-10 9-Nov-10 1-Dec-10 28-Dec-10 15,318.67 US $ Yemen 16-May-11 14,652.02 14,505.50 Planned 01- Various Water & Sanitation Civil Works Prior NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 Hady ‫هادي هاديان‬ 30-Dec-10 Revised 3/CW/RWSS/WSSP/0 Works alaeer wahshan in Ma'reb Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 ,Hadyan Sanaa 14-Jan-11 Completed Actual 9 1-Oct-10 26-Oct-10 9-Nov-10 9-Nov-10 1-Dec-10 28-Dec-10 4,823.76 US $ Yemen 2-Feb-11 4,808.18 4,615.85 Planned 01- Various Water & Sanitation Civil Works Prior NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 Hady ‫هادي هاديان‬ 30-Dec-10 Revised 4/CW/RWSS/WSSP/0 Works algafynah in Ma'reb Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 ,Hadyan Sanaa 15-Mar-11 Completed Actual 9 1-Oct-10 26-Oct-10 9-Nov-10 9-Nov-10 1-Dec-10 28-Dec-10 22,741.82 US $ Yemen 20-Jul-11 20,917.36 20,080.66 Planned 01- Various Water & Sanitation Civil Works Prior NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 Hady ‫هادي هاديان‬ 30-Dec-10 Revised 5/CW/RWSS/WSSP/0 Works goa alaber in Ma'reb Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 ,Hadyan Sanaa 26-Feb-11 Completed Actual 9 1-Oct-10 26-Oct-10 9-Nov-10 9-Nov-10 1-Dec-10 28-Dec-10 9,923.81 US $ Yemen ‫ناصر ناصر الموهبي‬ 30-Jan-11 8,914.85 8,201.67 Planned 04/CW/RWSS/WSSP/ Various Water & Sanitation Civil Works Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 Naser Al 30-Dec-10 Revised 09 Works in Sana'a Post NCB 1-Mar-10 N/A 25-Mar-10 25-Apr-10 15-May-10 15-Jun-10 moheby Sanaa 25-Feb-11 Completed Actual 3-Mar-10 2-Apr-10 2-May-10 2-May-10 1-Jun-10 4-Sep-10 46,929.38 US $ Yemen 07/20/2011 46,866.44 45,413.95 ‫مبارك الزرقه‬ Planned 07- Various Water & Sanitation Civil Works Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 Mubarak Al 30-Dec-10 Revised 1/CW/RWSS/WSSP/0 Works almdman in Hudaida Post NCB 17-May-10 N/A 11-Oct-10 10-Nov-10 10-Nov-10 18-Nov-10 10-Jan-11 Zurqa Sanaa 12-Mar-11 Completed Actual 9 1-Nov-10 10-Nov-10 11-Dec-10 11-Dec-10 25-Dec-10 11-Jan-11 63,037.12 US $ Yemen 20-Jul-11 63,034.33 60,512.97 Various Water & Sanitation Civil Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 Mubarak Al 30-Dec-10 Planned 07- Works Works deer ali in Hudaida Zurqa Sanaa- Revised 2/CW/RWSS/WSSP/0 Post NCB 17-May-10 N/A 9-Oct-10 10-Nov-10 10-Nov-10 18-Nov-10 10-Jan-11 Yemen ‫مبارك‬ 12-Mar-11 Completed Actual 9 1-Nov-10 10-Nov-10 11-Dec-10 11-Dec-10 25-Dec-10 11-Jan-11 41,228.84 US $ ‫الزرقه‬ 20-Jul-11 38,292.84 36,761.13 Planned 07- Various Water & Sanitation Civil Works Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 ‫ناصر صالح االغبري‬ 30-Dec-10 Revised 4/CW/RWSS/WSSP/0 Works alfash in Hudaida Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 Naser Al 20-Feb-11 Completed Actual 9 10-Oct-10 11-Nov-10 25-Nov-10 25-Nov-10 10-Dec-10 22-Dec-10 27,621.00 US $ Ghabari ‫جواد االصبحي‬ 20-Jul-11 26,910.80 26,910.80 Planned 07- Various Water & Sanitation Civil Works Post NCB 10-Jun-09 24-Jun-09 29-Jun-09 29-Jul-09 12-Aug-09 1-Sep-10 Gawad Al 30-Dec-10 Revised 5/CW/RWSS/WSSP/0 Works alzaher in Hudaida Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 1-Jan-11 -Asbahy Sanaa 5-Mar-11 Completed Actual 9 10-Oct-10 11-Nov-10 25-Nov-10 25-Nov-10 16-Dec-10 4-Jan-11 30,611.70 US $ Yemen ‫جواد االصبحي‬ 20-Jul-11 14,973.26 14,973.26 Planned 07- Various Water & Sanitation Civil Works Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 Gawad Al 30-Dec-10 Revised 6/CW/RWSS/WSSP/0 Works alhomra in Hudaida Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 1-Jan-11 -Asbahy Sanaa 5-Mar-11 Completed Actual 9 1-Nov-10 11-Nov-10 25-Nov-10 25-Nov-10 16-Dec-10 4-Jan-11 17,746.40 US $ Yemen 20-Jul-11 8,261.60 8,261.60 Planned 08- Various Water & Sanitation Civil Works Post NCB 10-Jun-09 24-Jun-09 29-Jun-09 29-Jul-09 12-Aug-09 1-Sep-10 ‫شوقى عبد سعيد‬ 30-Dec-10 Revised 1/CW/RWSS/WSSP/0 Works alsameesn in Lahj Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 Shawqi Abdo 4-Feb-11 Completed Actual 9 25-Oct-10 27-Oct-10 13-Nov-10 13-Nov-10 23-Nov-10 6-Dec-10 20,337.00 US $ Saeed 20-Dec-13 16,972.80 16,972.80 Planned 08- Various Water & Sanitation Civil Works Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 ‫علي محمد‬ 30-Dec-10 Revised 2/CW/RWSS/WSSP/0 Works daqm in Lahj Post NS 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 .A ‫عبدالرب‬ 13-Feb-11 Completed Actual 9 25-Oct-10 13-Nov-10 29-Nov-10 29-Nov-10 9-Dec-10 15-Dec-10 36,071.00 US $ Abdulrab 20-Dec-13 13,714.20 8,538.12 Rashad ALhaj 8/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 4-1/MAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani zeed in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 ‫محمد رزق خذيÙ?‬ 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 48,101.00 US $ M. Hudhaif 06/24/2012 28,238.40 2,146.12 Completed Planned ‫مقترح‬ 4-2/MAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫نضال العودي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almarm in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 Nedal Al 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 6,581.50 US $ Awdy 2-May-11 6,451.50 530.32 Completed Planned ‫مقترح‬ 4-3/MAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫نضال العودي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almrmeeda in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 Nedal Al 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 1,738.00 US $ Awdy 24-Apr-11 1,738.00 142.86 Completed Planned ‫مقترح‬ 4-4/MAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works anbar in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 ‫علي محمد حرمل‬ 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 15,701.00 US $ A. Harmal 06/24/2012 14,915.95 1,133.61 Completed Planned ‫مقترح‬ 4-5/MAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫نضال العودي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani alashal in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 Nedal Al 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 11,544.00 US $ Awdy 06/24/2012 10,325.00 6,445.20 Completed Planned ‫مقترح‬ 4-1/ LAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫ناصر صالح االغبري‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alhagr in lahj Post NS 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 Naser Al 14-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 13-Nov-10 29-Nov-10 29-Nov-10 1-Dec-10 15-Dec-10 43,837.00 US $ Ghabari 07/04/2012 37,099.59 4,878.23 Completed Planned ‫مقترح‬ 4-2/ LAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫نشوان ناجى‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works boran in lahj Post NS 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 ‫محسن‬ 5-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 27-Oct-10 13-Nov-10 13-Nov-10 20-Nov-10 6-Dec-10 50,272.00 US $ ‫سعيد‬ ‫شوقى عبد‬ Nashwan 07/04/2012 47,167.66 4,595.06 Completed Planned ‫مقترح‬ 4-3/ LAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Shawqi 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alsameen2 in lahj Post NCB 11-Oct-10 10-Nov-10 10-Nov-10 25-Nov-10 5-Dec-10 Saeed 11-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 1-Nov-10 1-Dec-10 1-Dec-10 3-Dec-10 12-Dec-10 57,216.00 US $ Sanaa 07/04/2012 54,557.64 3,293.36 Completed Planned ‫مقترح‬ 4-4/ LAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫ناصر صالح االغبري‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works ama'een in lahj Post NS 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 Naser Al 14-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 13-Nov-10 29-Nov-10 29-Nov-10 1-Dec-10 15-Dec-10 37,428.00 US $ Ghabari 07/04/2012 32,826.30 5,307.78 Completed Planned ‫مقترح‬ 4-5/ LAH Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫ناصر صالح االغبري‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works aljamrk in lahj Post NS 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 Naser Al 14-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 13-Nov-10 29-Nov-10 29-Nov-10 1-Dec-10 15-Dec-10 52,989.00 US $ Ghabari 07/04/2012 23,117.73 9,125.19 Completed Planned ‫مقترح‬ 4-2/SAN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫صالح ابو Ù?نة‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works khadar in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 Saleh Abu 24-Jun-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 25-Apr-11 9,388.60 US $ Fana Sanaa 09/19/2011 7,679.03 583.60 Completed Planned ‫مقترح‬ 4-3/SAN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫احمد علي مهدي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works algadeer in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 A. a. Mahdi 12-Jul-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 13-Apr-11 25,509.72 US $ Sanaa 27-Jun-11 26,902.96 3,721.10 Completed Planned ‫مقترح‬ 4-5/SAN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Al ‫مكتب القايÙ?ي‬ 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works algeerf in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 dubai Office 14-May-11 the payment under Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 23-May-11 7,702.14 US $ Sanaa 12/12/2012 processing Planned ‫مقترح‬ 4-12/ SAN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Al ‫مكتب القايÙ?ي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alsahman in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 Qaify office 16-Jun-11 Completed Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 17-Apr-11 16,720.65 US $ Sanaa 09/19/2011 15,887.55 2,327.18 Planned ‫مقترح‬ 4-13/ SAN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Al ‫مكتب القايÙ?ي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bashar in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 Qaify office 16-Jun-11 Completed Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 17-Apr-11 8,095.79 US $ Sanaa 15-May-13 7,688.04 1,531.97 Planned ‫مقترح‬ 4-14/ SAN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Saleh Abu 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alhagar in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 Fana Sanaa- 24-Jun-11 the payment under Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 25-Apr-11 8,090.75 US $ Yemen‫صالح‬ 22-Jun-11 processing Rashad ALhaj 9/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 4-3/ MAR /G/RWSS/ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫مانع حجالن‬ 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works rahb al haglan in Mareb Post NS 1-Jan-11 5-Jan-11 19-Jan-11 19-Jan-11 29-Jan-11 14-Feb-11 Manea 15-Apr-11 Completed Actual ‫Ù?علي‬ 20-Jan-11 5-Jan-11 18-Jan-11 18-Jan-11 25-Jan-11 5-Feb-11 18,197.00 US $ Haglan 07/01/2011 13,460.99 2,692.20 Planned ‫مقترح‬ 4-3/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Naser Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkadsh in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 Mohby 24-Apr-11 Revised1 2-Apr-12 16-Apr-12 16-Apr-12 24-Apr-12 10-May-12 Sanaa- 9-Jul-12 Completed Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 14,431.33 US $ Yemen‫ناصر‬ 4-Jul-12 8,383.44 1,676.69 Planned ‫مقترح‬ 4-4/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫عبدالوهاب‬ 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani abeedan in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 A. Al ‫القريضي‬ 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 4-May-11 7,704.60 US $ Qaridhy 06/17/2012 processing Planned ‫مقترح‬ 4-5/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫احمد علي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works aldol &alkhansr in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 A. Al ‫البيضاني‬ 24-Apr-11 Completed Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 7-Mar-11 29,468.69 US $ Baidani Naser Al 9-Aug-12 22,141.76 1,682.77 Planned ‫مقترح‬ 4-6/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Mohby Sanaa- 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alaza'az in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 Yemen‫ناصر‬ 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 5,910.67 US $ ‫الموهبى‬ 6-May-12 processing Planned ‫مقترح‬ 4-7/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫باسم محمد غالب‬ 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works heeb alasabah in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 Qasim Ghalib 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 16-Apr-11 5,985.80 US $ Sanaa Yemen 10-Aug-11 processing Planned ‫مقترح‬ 4-11/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alqreesha in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 16-Apr-11 6,526.02 US $ ‫باسم محمد غالب‬ 08/10/2011 processing Naser Al Planned ‫مقترح‬ 4-12/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Mohby Sanaa- 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alsha'aby in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 Yemen‫ناصر‬ 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 3,724.99 US $ ‫الموهبى‬ 06/18/2012 processing Planned ‫مقترح‬ 4-1/ BYD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫علي هادي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works abiy in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 A. Al ‫الزعكري‬ 6-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 11,708.80 US $ Zukry Sanaa 10-Aug-12 15,599.11 1,185.53 Rashad ALhaj 10/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 4-2/ BYD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 .A.H ‫علي هادي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alshraf in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 Al Zukry 6-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 10,249.50 US $ -Sanaa 10-Aug-12 13,654.95 1,037.78 Planned ‫مقترح‬ 4-3/ BYD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 .A.H ‫علي هادي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almagleen in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 Al Zukry 6-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 6,498.50 US $ -Sanaa 10-Aug-12 8,657.66 657.98 Planned ‫مقترح‬ 4-4/ BYD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 .A.H ‫علي هادي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works al alsalal in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 Al Zukry 6-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 19,878.60 US $ -Sanaa 10-Aug-12 26,483.36 2,012.74 Planned ‫مقترح‬ 4-5/ BYD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 .A.H ‫علي هادي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almakla in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 Al Zukry 6-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 26,546.90 US $ -Sanaa 10-Aug-12 24,879.05 1,890.81 Planned ‫مقترح‬ 4-6/ BYD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 .A.H ‫علي هادي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkhaf in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 Al Zukry 6-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 19,430.60 US $ -Sanaa 10-Aug-12 21,337.84 1,621.68 Planned ‫مقترح‬ 4-7/ BYD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 .A.H ‫علي هادي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almcehar in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 Al Zukry 6-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 17,450.90 US $ .A.H-Sanaa ‫علي هادي‬ 9-Jul-12 16,354.52 1,242.94 Planned ‫مقترح‬ 4-8/ BYD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Al Zukry 30-Dec-10 /G/RWSS/WSSP/10 Works mahaba in al-bedhaa Revised ‫متوقع‬ Post NCB 11-Oct-10 10-Nov-10 10-Nov-10 3-Jan-11 19-Jan-11 -Sanaa 21-Mar-11 Completed Actual ‫Ù?علي‬ 20-Nov-10 26-Nov-10 26-Dec-10 26-Dec-10 3-Jan-11 10-Jan-11 49,376.26 US $ ‫الزعكري‬Yemen 9-Jul-12 52,781.60 7,684.17 Planned ‫مقترح‬ 4-1/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫أحمد‬ 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works alkadam in aldhale Post NS 19-Dec-10 1-Jan-11 1-Jan-11 7-Jan-11 23-Jan-11 ‫محمداحمدالطامي‬ 23-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 22,384.00 US $ A. Al Tamy 27-Jul-11 22,384.00 1,839.94 Planned ‫مقترح‬ 4-2/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫أحمد‬ 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works al-lakmah in aldhale Post NS 9-Oct-10 1-Jan-11 3-Jan-11 7-Jan-11 23-Jan-11 ‫محمداحمدالطامي‬ 23-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 17,607.00 US $ A. Al Tamy Samid Hameed 23-Mar-12 17,607.00 1,447.25 Planned ‫مقترح‬ 4-3/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Sanaa- 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works hagalan in aldhale Post NS 9-Oct-10 1-Jan-11 3-Jan-11 7-Jan-11 23-Jan-11 Yemen‫صامد حميد‬ 23-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 13,846.00 US $ ‫عبد اهلل محم‬ 5-May-12 13,829.00 1,136.69 Samid Hameed Planned ‫مقترح‬ 4-4/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Sanaa- 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works algaboba in aldhale Post NS 9-Oct-10 1-Jan-11 3-Jan-11 7-Jan-11 23-Jan-11 Yemen‫صامد حميد‬ 23-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 17,456.00 US $ ‫عبد اهلل محم‬ 05/09/2012 17,456.00 1,434.91 Samid Hameed Planned ‫مقترح‬ 4-5/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Sanaa- 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works altreera in aldhale Post NS 9-Oct-10 1-Jan-11 3-Jan-11 7-Jan-11 23-Jan-11 Yemen‫صامد حميد‬ 23-Mar-11 Completed Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 17,707.00 US $ ‫عبد اهلل محم‬ 06/02/2012 17,055.60 3,553.20 Planned ‫مقترح‬ 4-1/ AMR Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫هادى حمود يحي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works algadm in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 Hady Laswar 2-May-11 Completed Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 18,935.05 US $ Sanaa=Yeme 11/19/2011 7,619.81 1,518.38 Planned ‫مقترح‬ 4-2/ AMR Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫هادى حمود يحي‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alaqeely in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 Hady Laswar 2-May-11 Completed Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 14,059.81 US $ Sanaa=Yeme 11/19/2011 11,126.86 2,217.22 Planned ‫مقترح‬ 4-4/ AMR Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Alian Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alswadeen in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 Abidy Sanaa- 2-May-11 Completed Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 23-Mar-11 11,918.93 US $ Yemen‫عليان‬ 07/27/2011 5037.97 382.89 Planned ‫مقترح‬ 4-7/ AMR Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Alian Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works beet alman in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 Abidy Sanaa- 2-May-11 Completed Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 5,332.94 US $ Yemen‫عليان‬ 11/06/2011 3,540.86 708.17 Planned ‫مقترح‬ 4-1/ RYM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Qaid Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almahamal in ryimah Post NS 30-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 Mohby 1-Jun-11 Completed Actual ‫Ù?علي‬ 30-Jan-11 12-Feb-11 26-Feb-11 26-Feb-11 15-Mar-11 2-Apr-11 16,091.33 US $ Amran- 08/28/2012 9,672.63 2,803.93 Planned ‫مقترح‬ 4-2/ RYM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Qaid Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works wadi seer in ryimah Post NS 30-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 Mohby 1-Jun-11 Completed Actual ‫Ù?علي‬ 30-Jan-11 12-Feb-11 26-Feb-11 26-Feb-11 15-Mar-11 2-Apr-11 15,217.61 US $ Amran- 03/17/2012 9,203.49 2,791.87 Planned ‫مقترح‬ 4-4/ RYM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Qaid Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works asfal mzar in ryimah Post NS 30-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 Mohby 1-Jun-11 Completed Actual ‫Ù?علي‬ 30-Jan-11 12-Feb-11 26-Feb-11 26-Feb-11 15-Mar-11 2-Apr-11 17,855.24 US $ Amran- 03/19/2012 11,304.53 3,353.25 Planned ‫مقترح‬ 4-2/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Yahya Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alhmr in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 Sanabany 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 2,385.51 US $ Dhamar- 02/07/2011 2,493.95 498.79 Planned ‫مقترح‬ 4-3/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Yahya Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani ahmed in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 Sanabany 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 4,637.02 US $ Dhamar- 12-Nov-13 5,436.70 1,087.33 Planned ‫مقترح‬ 4-4/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫عبدالسالم‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works yafah in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 A.Salam Al 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 5,691.68 US $ Sarary 07/04/2012 3,207.26 1,255.06 Planned ‫مقترح‬ 4-5/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫عبدالسالم‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works wathan in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 A.Salam Al 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 3,850.47 US $ Sarary 10/01/2011 3,660.51 732.10 Planned ‫مقترح‬ Various Water & Sanitation Civil Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Gamam 30-Dec-10 4-6/ DHM Works Works rabat amran in thamar Contracting Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Completed Dhamar- Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 1,729.00 US $ Yemen‫مكتب جمام‬ 10/01/2011 1,533.64 116.56 Planned ‫مقترح‬ Various Water & Sanitation Civil Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Gamam 30-Dec-10 4-7/ DHM Works Works ftayl in thamar Contracting Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Completed Dhamar- Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 2,192.00 US $ Yemen‫مكتب جمام‬ 10/01/2011 2,050.09 155.81 Planned ‫مقترح‬ 4-8/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Yahya Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works hagrah sabeel in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 Sanabany 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 4,635.89 US $ Dhamar- 03/28/2012 3,114.74 622.95 Planned ‫مقترح‬ 4-9/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 ‫عبدالسالم‬ 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works altalha in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 A.Salam Al 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 2,810.75 US $ Sarary 06/25/2012 1,763.00 638.98 Rashad ALhaj 11/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** ‫مؤسسة الجزيرة‬ Planned ‫مقترح‬ 4-10/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 .AlGazira Corp 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkmeem in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 -Dhamar 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 1,840.61 ‫الخضراء‬Yemen 06/17/2011 1406.18 281.24 Planned ‫مقترح‬ Various Water & Sanitation Civil Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Gamam 30-Dec-10 4-11/ DHM Works Works almatahn in thamar Contracting Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Completed Dhamar- Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 4,142.00 US $ ‫الجزيرة‬ Yemen ‫جمام‬ ‫مكتب‬ ‫مؤسسة‬ 06/17/2011 3,937.85 299.28 Planned ‫مقترح‬ 4-12/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 .AlGazira Corp 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works ahlal in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 -Dhamar 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 1,792.64 US $ ‫الخضراء‬Yemen 06/11/2011 1704.112 340.82 Planned ‫مقترح‬ 4-13/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Eadah Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alshmah in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 Malky Amran- 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 6-Feb-11 4,342.67 US $ Yemen ‫عيضة‬ 04/26/2011 3879.62 775.92 Rashad ALhaj 12/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 4-14/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alsanam in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 21-Mar-11 1,845.40 US $ 04/26/2011 Planned ‫مقترح‬ 4-15/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Yahya Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works zaragah in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 Sanabany 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 4,039.89 US $ Dhamar- 05/17/2011 2894.85 951.57 Planned ‫مقترح‬ 4-16/ DHM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works kalba alaqar in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Completed Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 5,058.04 US $ 07/02/2011 Planned ‫مقترح‬ 3/ SAD works of tank in saada Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 + ‫مطري عيبان‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 30-Aug-10 Matary Ayan 15-Feb-11 71,003.31 Completed Actual ‫Ù?علي‬ 1-Feb-10 3-Apr-10 1-May-10 5-May-10 24-Jun-10 25-Jul-10 70,938.93 US $ -Saada 06/28/2012 5,813.33 Planned ‫مقترح‬ 3/ MAR /G/RWSS/ works of tank in Mareb Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Manea Aglan 29-Sep-10 Revised ‫متوقع‬ WSSP/10 Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 Mareb- Completed Actual ‫Ù?علي‬ 1-Feb-10 3-Mar-10 28-Mar-10 3-Apr-10 25-Apr-10 10-May-10 36,564.95 US $ Yemen‫مانع‬ 07/24/2012 35,425.27 980.47 Planned ‫مقترح‬ 3/ SHB works of tank in Shabwa Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫مكتب محمد‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 ‫الزعتري ومكتب‬ 1-Mar-11 Completed Actual ‫Ù?علي‬ 1-Feb-10 28-Feb-10 28-Mar-10 4-Apr-10 27-Apr-00 5-Jun-10 77,454.67 US $ ‫حسن دحنان‬ 12-Dec-13 75,452.98 8,052.15 Planned ‫مقترح‬ 3/ TAZ works of tank in taez Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 ‫مبارك الزرقه‬ Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB 1-Mar-11 63,093.03 Completed ‫وعبدالحق عماد‬ Actual ‫Ù?علي‬ 1-Feb-10 8-Mar-10 5-Apr-10 10-Apr-10 10-May-10 29-May-10 64,376.17 US $ 06/17/2012 5,184.63 Planned ‫مقترح‬ 3/ ABN works of tank in Abyan Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB 1-Mar-10 25-Mar-10 30-Mar-10 3-May-10 7-Jun-10 1-Mar-11 27,976.32 Completed Actual ‫Ù?علي‬ 1-Feb-10 25-Mar-10 19-Apr-10 24-Apr-10 20-Oct-10 26,779.67 US $ 14-Mar-11 2,383.42 Planned ‫مقترح‬ 3/ HAD works of tank in moklla Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB 1-Mar-10 25-Mar-10 30-Mar-10 3-May-10 7-Jun-10 ‫عوض السومحي‬ 1-Mar-11 66,991.84 Completed Actual ‫Ù?علي‬ 1-Feb-10 22-Mar-10 15-Apr-10 21-Apr-10 10-May-10 27-May-10 113,032.24 US $ 04/16/2012 7,807.25 Planned ‫مقترح‬ 3/ DHL /G/RWSS/ works of tank in aldhale Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 ‫Ù?ضل محمد مساعد‬ 67,041.81 Completed Actual ‫Ù?علي‬ 1-Feb-10 21-Feb-10 16-Mar-10 21-Mar-10 4-Apr-10 27-Apr-10 68,405.19 US $ 1-Nov-10 5,468.28 Planned ‫مقترح‬ 3/ AMR works of tank in amran Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫علي القصاري‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 ‫&هادي حمود‬ 1-Mar-11 Completed Actual ‫Ù?علي‬ 1-Feb-10 1-Mar-10 26-Mar-10 31-Mar-10 10-May-10 29/05&1/8/2010 448,694.77 US $ ‫الصور&حنيني‬ 10/04/2011 477,144.69 37,052.14 Planned ‫مقترح‬ 3/ RYM works of tank in ryimah Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 ‫قائد محمد علي‬ Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB 1-Mar-10 25-Mar-10 30-Mar-10 3-May-10 7-Jun-10 1-Mar-11 243,758.61 20,032.50 Completed ‫المالكي‬ Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 3-May-10 28-Jul-10 242,690.42 US $ 03/21/2012 Planned ‫مقترح‬ 3/ MAH works of tank in al-mahra Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 ‫صالح ابو زيد و‬ Revised ‫متوقع‬ /G/RWSS/WSSP/10 1-Mar-11 17,155.68 Completed ‫محمد بن الشرÙ?‬ Actual ‫Ù?علي‬ 1-Feb-10 18-Apr-10 18-May-10 18-May-10 25-May-10 9-Jun-10 18,852.00 US $ 03/21/2012 1,303.83 Planned ‫مقترح‬ 3/ HQ works ofBuildings in al-jowf Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 ‫يوسÙ? الصنعاني‬ 18-Jul-11 73,897.04 Completed Actual ‫Ù?علي‬ 1-Feb-10 9-Apr-10 19-May-10 24-May-10 1-Jul-10 18-Jul-10 271,684.74 US $ 19-Jul-12 5,913.15 Planned ‫مقترح‬ 3/ IBB /G/RWSS/ works of tank in Ibb Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 1-Mar-11 88,609.03 Completed Actual ‫Ù?علي‬ 1-Feb-10 1-Mar-10 25-Mar-10 30-Mar-10 18-Apr-10 11-May-10 91,021.12 US $ 12/25/2011 90,804.30 Planned ‫مقترح‬ 3/HAJ /G/RWSS/ works of tank in Haja Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫القدمي للمقاوالت‬ 29-Sep-10 Revised ‫متوقع‬ WSSP/10 ‫و احمد قاسم‬ 1-Mar-11 67,175.91 Completed Actual ‫Ù?علي‬ 1-Feb-10 22-Feb-10 17-Mar-10 23-Mar-10 20-Apr-10 12-May-10 71,152.06 US $ ‫المالكي‬ 05/20/2012 7,843.68 Planned ‫مقترح‬ 3/DHM /G/RWSS/ works of tank in thamar Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 1-Mar-11 11,596.66 Completed Actual ‫Ù?علي‬ 1-Feb-10 1-Jun-10 25-Jun-10 30-Jun-10 1-May-10 31-May-10 11,583.79 US $ ‫عبدالخالق المعانسي‬ 05/20/2012 837.33 Planned ‫مقترح‬ 3/LAH /G/RWSS/ works of tank in lahj Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 1-Mar-11 15,479.10 Completed Actual ‫Ù?علي‬ 1-Feb-10 18-Feb-10 15-Mar-10 20-Mar-10 2-Apr-10 25-Apr-10 54,335.28 US $ ‫جلوي عبداهلل ناصر‬ 03/06/2012 3,095.82 Planned ‫مقترح‬ 3/SAN /G/RWSS/ works of tank in sanaa Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫Ù?ارع العويري‬ 29-Sep-10 Revised ‫متوقع‬ WSSP/10 ‫ومطري Ù‚Ù?ري‬ 1-Mar-11 71,610.46 Completed Actual ‫Ù?علي‬ 5-Mar-10 1-Feb-10 20-Mar-10 14-Apr-10 19-Apr-10 24-May-10 13-Jul-10 71,726.62 US $ ‫عيبان‬ 01/01/2012 3,835.58 Planned ‫مقترح‬ 3/BYD /G/RWSS/ works of tank in al-bedhaa Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 ‫علي هادي‬ 1-Mar-11 63,557.50 Completed Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 20-Apr-10 26-Apr-10 62,560.75 US $ ‫الزعكري‬ 15-Mar-12 6,131.29 Planned ‫مقترح‬ 5/ TAZ works of wells in taez Works Post NCB 6-Feb-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 ‫مهدي راشد أبو‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 ‫علي Ùˆ علي غالب‬ 170,625.27 Completed Actual ‫Ù?علي‬ 5-Mar-10 8-Mar-10 5-Apr-10 10-Apr-10 19-May-10 9-Jun-10 200,849.37 US $ ‫الحنمي‬ 15-Jan-11 12,967.52 Rashad ALhaj 13/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ * 5/SAN /G/RWSS/ works of wells in sanaa Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 Post NCB 1-Mar-11 395,531.42 Completed Actual ‫Ù?علي‬ 5-Apr-10 22-Apr-10 15-Apr-10 21-Apr-10 26-May-10 30-Jun-10 313,010.91 US $ 1-Apr-11 30,060.39 Planned ‫مقترح‬ 5/ AMR works of wells for (13) Works Post NCB 6-Feb-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 contracts in amran 1-Mar-11 565,242.05 Completed Actual ‫Ù?علي‬ 5-Mar-10 1-Mar-10 26-Mar-10 31-Mar-10 12-May-10 20/6&9/8/2010 639,105.58 US $ 14-Jan-11 42,958.40 Planned ‫مقترح‬ 5/ HAD works of wells in moklla Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 15-Aug-10 9-Oct-10 2-Feb-11 69,068.88 Completed Actual ‫Ù?علي‬ 5-Apr-10 28-Apr-10 18-May-10 23-May-10 28-Aug-10 3-Oct-10 85,763.89 US $ ‫اسحاق للتجارة‬ 1-Jan-11 5,249.23 Planned ‫مقترح‬ 5/ SAD works of wells Alsaoad Faroa Works Post NCB 6-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 10-Aug-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 in saada Post NCB 1-Jan-11 17-Jan-11 18-Mar-11 Canceled Actual ‫Ù?علي‬ 5-Aug-10 1-Sep-10 1-Oct-10 1-Oct-10 2-Jan-11 15-Jan-11 65,500.00 US $ 07/18/2012 Planned ‫مقترح‬ 5/ MAH works of wells in Mahaweet Works Post NCB 30-May-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NS 9-Oct-10 18-Oct-10 18-Oct-10 5-Oct-10 15-Oct-10 ‫سلطان يحيى‬ 1-Feb-11 17,835.18 Completed Actual ‫Ù?علي‬ 5-Aug-10 1-Oct-10 11-Oct-10 11-Oct-10 19-Oct-10 3-Nov-10 43,256.31 US $ ‫السلطان‬ 07/13/2011 1,996.65 Planned ‫مقترح‬ 5/ MAH works of wells in al-mahra Works Post NCB 6-Feb-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 ‫باسعد للمقاوالت‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 15-Aug-10 30-Aug-10 1-Mar-11 38,720.00 Completed Actual ‫Ù?علي‬ 5-Apr-10 9-Jun-10 2-Jul-10 6-Jul-10 1-Aug-10 18-Aug-10 109,815.00 US $ 07/13/2011 2,942.72 Planned ‫مقترح‬ 5/ JWF works of wells in al-jowf Works Post NCB 6-Feb-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 ‫علي هادي العكص‬ 29-Sep-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 NS 20-Aug-10 1-Mar-11 137,734.00 Completed Actual ‫Ù?علي‬ 5-Apr-10 9-May-10 4-Jun-10 9-Jun-10 24-Jul-10 11-Aug-10 188,932.90 US $ 12/30/2012 11,924.96 Planned ‫مقترح‬ 3/ TAZ Civil Works of tank Alsaleef- Works Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ ‫مبارك احمد يحي‬ 11-Aug-11 51,329.13 10,333.78 Completed /CW/RWSS/WSSP/11 Almashkeeb-Alrod Alrabya in Actual ‫Ù?علي‬ 28-Jan-11 31-Jan-11 5-Mar-11 5-Mar-11 15-Apr-11 13-May-11 58,428.74 US $ ‫الزرقه‬ 2-May-12 taez Planned ‫مقترح‬ 3/ LAH Civil Works of tank Works Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Algamrak -Algadra in lahj Completed Actual ‫Ù?علي‬ 30-Jan-11 8-Feb-11 12-Mar-11 12-Mar-11 8-Apr-11 22-Apr-11 84,410.00 US $ 14-Mar-13 66,496.85 13,299.97 Planned ‫مقترح‬ 3/ DHL /CW/RWSS/ Civil Works of tank in Works Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ WSSP/11 aldhale Completed Actual ‫Ù?علي‬ 30-Jan-11 26-Jan-11 26-Feb-11 26-Feb-11 2-Mar-11 3-Mar-11 118,988.79 US $ ‫Ù?ضل محمد مساعد‬ 10-Apr-11 116,403.23 9,498.25 Planned ‫مقترح‬ 3/ AMR Civil Works of tank watar- Works Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Aldhabar-Alhagar- Alrahaba2- Completed Actual ‫Ù?علي‬ 25-Jan-11 30-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 14-May-11 298,276.06 US $ 174,730.65 37,296.28 Alsabain in amran Rashad ALhaj 14/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 4/ SAD Civil Works of Wells in saada Works Post NCB 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ ‫Ù?يصل زابن‬ 30-Mar-00 141,542.58 16,456.61 Completed /CW/RWSS/WSSP/11 Actual ‫Ù?علي‬ 20-Feb-11 27-Feb-11 27-Mar-11 27-Mar-11 4-Apr-11 4-May-11 153,488.00 US $ ‫البورعى‬ 8-Jul-11 Planned ‫مقترح‬ 4/ LAH Civil Works of Wells in lahj Works Post NCB 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ ‫على ابو بكر‬ Completed /CW/RWSS/WSSP/11 Actual ‫Ù?علي‬ 30-Jan-11 8-Feb-11 12-Mar-11 12-Mar-11 22-Mar-11 25-May-11 184,092.00 US $ ‫السليمانى‬ 30-Aug-12 49,361.92 19,140.88 Planned ‫مقترح‬ 4/ HAD Civil Works of Wells in Works Post NCB 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ ‫اسحاق للتجارة‬ 11,244.62 854.59 Completed /CW/RWSS/WSSP/11 Hadramout Actual ‫Ù?علي‬ 30-Jan-11 7-Feb-11 7-Mar-11 7-Mar-11 14-Mar-11 4-Apr-11 49,532.71 US $ ‫والحÙ?ريات‬ 30-Aug-12 Planned ‫مقترح‬ Post NCB 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 Union 8-Jul-11 7/ AMR Civil Works Hangar of in Works Revised ‫متوقع‬ Contracting 19-Jan-12 Completed /G/RWSS/WSSP/11 amran Actual ‫Ù?علي‬ 24-Apr-11 23-May-11 23-May-11 20-Jun-11 23-Jul-11 133,700.27 US$ Company 14-Feb-14 58,187.10 58,187.10 Planned ‫مقترح‬ 4/ AMR Civil Works of Wells in Works Post NCB 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 amran 30-Mar-00 Completed Actual ‫Ù?علي‬ 25-Jan-11 28-Jan-11 26-Feb-11 26-Feb-11 15-Jun-11 15-Jul-11 142,970.00 US $ ‫يحي صالح المÙ?زر‬ 10/01/2011 144,116.64 45,186.95 Planned ‫مقترح‬ 3/ RYM Civil Works of tank in Works Post NCB 25-Jan-11 12-Feb-11 14-Mar-11 14-Mar-11 29-Mar-11 16-Apr-11 16-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 ryimah ‫احمد قاسم المالكى‬ 55,314.21 Completed Actual ‫Ù?علي‬ 30-Jan-11 3-Feb-11 5-Mar-11 5-Mar-11 20-Mar-11 9-Apr-11 86,280.37 US $ ‫والطميس والحميدي‬ 1-Aug-12 13,121.34 Planned 02/CW/RWSS/WSSP/ Various Water & Sanitation Civil Works Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 09 Works in Alshafal Mahaweet Post NCB 1-Jan-11 N/A 5-Feb-11 7-Mar-11 7-Mar-11 15-Mar-11 31-Mar-11 29-Jun-11 Completed Actual 20-Jan-11 6-Feb-11 8-Mar-11 8-Mar-11 22-Mar-11 30-Mar-11 73,873.00 US $ ‫ظال عبد القادر العودي‬ 43,394.40 43,394.40 Planned ‫مقترح‬ 4-2/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works al'ameer in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 16-Apr-11 3,155.79 US $ 14-Jan-14 processing Planned ‫مقترح‬ 4-8/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani msan in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 22-Jun-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 23-Apr-11 5,232.93 US $ 14-Mar-14 processing Planned ‫مقترح‬ 4-9/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkhabal in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 1-Jul-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 26,648.79 US $ 14-May-14 processing Planned ‫مقترح‬ 4-10/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works mayala in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 4-May-11 2,668.13 US $ 14-Aug-14 processing Planned ‫مقترح‬ 4-13/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkadra qadas in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 8,528.02 US $ 14-Aug-14 processing Planned ‫مقترح‬ 4-14/ TAZ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Completed and Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alshareera in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 the payment under Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 23-Apr-11 18,624.38 US $ 14-Aug-14 processing Planned ‫مقترح‬ 4-9/ AMR Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani abd in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 ‫احمد علي عبده‬ 2-May-11 Completed Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 17,686.97 US $ ‫جهالن‬ 27-Aug-13 17,373.63 17,373.63 Planned ‫مقترح‬ 4-3/ RYM Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Naser Al 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani asd&reem in ryimah Post NCB 30-Jan-11 12-Feb-11 14-Mar-11 14-Mar-11 22-Mar-11 7-Apr-11 Mohby 28-Sep-11 Completed Actual ‫Ù?علي‬ 30-Jan-11 27-Mar-11 26-Apr-11 26-Apr-11 15-May-11 31-May-11 193,467.72 US $ Sanaa- 129,550.69 74,652.97 Planned ‫مقترح‬ 4-12/ SAN Various Water & Sanitation Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Civil Works bani walid,in Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 Completed 35,899.48 Revised2 Sanaa 21-Jun-12 5-Jul-12 5-Jul-12 15-Jul-12 31-Jul-12 ‫محمد على محمد‬ 29-Sep-12 Actual ‫Ù?علي‬ 27-Feb-11 3-Oct-12 9-Oct-12 9-Oct-12 26-Dec-12 US $ ‫الصبارى‬ 28-Apr-13 24,524.79 4,904.96 Planned ‫مقترح‬ 5-1/ DHL /G/RWSS/ Various Water & Sanitation Works Post NS 1-Aug-11 15-Aug-11 30-Aug-11 30-Aug-11 7-Sep-11 17-Sep-11 16-Nov-11 Completed Revised ‫متوقع‬ WSSP/11 Civil Works al kharbah Post NS 20-Jan-12 21-Jun-12 5-Jul-12 5-Jul-12 15-Jul-12 31-Jul-12 9-Oct-12 140,794.51 shoki'a -Sarar shoki'a- Actual ‫Ù?علي‬ Almarasa-Alrabat in Aldhale 7-Oct-12 us ‫احمد محمد الطامى‬ 16-Dec-12 62013.11 12,402.62 Planned ‫مقترح‬ 4-1/ AMR Various Water & Sanitation Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Completed Revised ‫متوقع‬ /CW/RWSS/WSSP/13 Civil Works in Alakeely in Post NS 1-Jan-11 15-Jan-11 14-Jan-00 14-Jan-00 24-Jan-00 9-Feb-00 9-Apr-00 Revised2 Amran 21-Jan-13 4-Feb-13 4-Feb-13 14-Feb-13 1-Mar-13 30-Apr-13 Actual ‫Ù?علي‬ 15-Jan-11 20-Feb-13 13,684.68 us ‫محمود الجالل‬ 8-Apr-13 12,815.95 2,563.19 Completed Planned ‫مقترح‬ 4-2/ AMR Various Water & Sanitation Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/13 Civil Works Beet Alman in Post NS 1-Jan-11 15-Jan-11 14-Jan-00 14-Jan-00 24-Jan-00 9-Feb-00 9-Apr-00 Revised2 Amran 21-Jan-13 4-Feb-13 4-Feb-13 14-Feb-13 2-Mar-13 ‫حنين حميد محمد‬ 1-May-13 Completed Actual ‫Ù?علي‬ 15-Jan-11 10-Feb-13 6,812.79 us ‫الذرحانى‬ 19-May-13 6,026.20 1,205.24 Planned ‫مقترح‬ 4-2/ AMR Various Water & Sanitation Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/13 Civil Works bani abd in Post NS 1-Jan-11 15-Jan-11 14-Jan-00 14-Jan-00 24-Jan-00 9-Feb-00 9-Apr-00 Completed Revised2 Amran 21-Jan-13 4-Feb-13 4-Feb-13 14-Feb-13 2-Mar-13 ‫احمد علي عبده‬ 1-May-13 Actual ‫Ù?علي‬ 15-Jan-11 10-Feb-13 13,690.60 us ‫جهالن‬ 27-Aug-13 12,829.22 12,829.22 Planned ‫مقترح‬ 5-1/ RYM Various Water & Sanitation Works Post NCB 1-Aug-11 15-Aug-11 14-Sep-11 14-Sep-11 22-Sep-11 9-Oct-11 8-Dec-11 Completed Revised ‫متوقع‬ /G/RWSS/WSSP/11 Civil Works mahalat wadi Post NCB 20-Jan-12 21-Jan-13 20-Feb-13 20-Feb-13 2-Mar-13 18-Mar-13 ‫مؤسسه على حسين‬ 12-Apr-14 Actual ‫Ù?علي‬ alzanam in Ryimah 17-Apr-13 18-May-13 18-May-13 1-Jun-13 1-Jun-13 86,840.00 us ‫الحديقى‬ Naser Al 67,792.97 29,678.93 Planned ‫مقترح‬ 5-2/ RYM Various Water & Sanitation Works Post NCB 1-Aug-11 15-Aug-11 14-Sep-11 14-Sep-11 22-Sep-11 9-Oct-11 Mohby Sanaa- 8-Dec-11 Completed Revised ‫متوقع‬ /G/RWSS/WSSP/11 Civil Works alkabah in Post NCB 20-Jan-12 21-Jan-13 20-Feb-13 20-Feb-13 2-Mar-13 18-Mar-13 Yemen‫ناصر‬ 12-Apr-14 Actual ‫Ù?علي‬ Ryimah 17-Apr-13 18-May-13 18-May-13 15-Jun-13 1-Jul-13 231,608.47 us ‫الموهبى‬ 207,926.40 207,926.40 Rashad ALhaj 15/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 7/ Construction of turn key WS Works Post NCB 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 16-Apr-00 Completed Revised ‫متوقع‬ HAJ/CW/RWSS/WSS system in (al danay) in Hajah 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 ‫عبدالرحمن محسن‬ 12-Apr-14 Actual ‫Ù?علي‬ P/11 15-Apr-11 18-Aug-12 16-Sep-12 16-Sep-12 12-Dec-12 336,825.35 us ‫سالب‬ 30662.83 30,662.83 Planned ‫مقترح‬ 8/ Construction of turn key WS Works Post NCB 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 16-Apr-00 Completed Revised ‫متوقع‬ HAJ/CW/RWSS/WSS system in Alhadhan in Hajah 21-Jun-13 21-Jul-13 21-Jul-13 15-Aug-13 30-Aug-13 28-Nov-13 Actual ‫Ù?علي‬ P/11 15-Apr-11 18-Aug-12 16-Sep-12 16-Sep-12 12-Dec-12 253,572.10 us ‫عبدالرزاق الوادعي‬ 20-Dec-13 238231.16 238,231.16 Planned ‫مقترح‬ 6/ Civil Works & Sanitation Works Post NCB 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 Cooperative 16-Apr-00 Completed Revised ‫متوقع‬ IBB/CW/RWSS/WSSP &Pumps-pipes (al maseel) in 20-May-13 19-Jun-13 19-Jun-13 14-Jul-13 29-Jul-13 Association of 25-Apr-14 332,661.40 Actual ‫Ù?علي‬ /11 IBB 15-Apr-11 30-Jul-13 1-Sep-13 1-Sep-13 24-Nov-13 597,882.90 us public 332661.4 Planned ‫مقترح‬ 7/ Civil Works & Sanitation Works Post NCB 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 Cooperative 16-Apr-00 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP &Pumps-pipes (almoueh) in 20-May-13 19-Jun-13 19-Jun-13 14-Jul-13 29-Jul-13 Association of 25-Apr-14 107,914.00 Actual ‫Ù?علي‬ /11 IBB 15-Apr-11 30-Jul-13 1-Sep-13 1-Sep-13 27-Oct-13 578,134.05 us public 107914 Completed Planned ‫مقترح‬ 2/ Construction of (Al mesher) Works Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP turn key WS system in Ibb 99,316.93 Completed Actual ‫Ù?علي‬ /13 30-Mar-13 185,295.36 us ‫احمد علي مهدي‬ 20-Dec-13 99316.93 Planned ‫مقترح‬ 3/ Construction of (Al ‫) الوزيرة‬ Works Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP turn key WS system in Ibb 384,458.46 Completed Actual ‫Ù?علي‬ /13 30-Mar-13 396,508.45 us ‫احمد علي مهدي‬ 20-Dec-13 384,458.46 Planned ‫مقترح‬ 1/ Construction of (Al lasaan) Works Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ AMR/CW/RWSS/WSS turn key WS system in Amran Badr Allden 119,459.70 Completed Actual ‫Ù?علي‬ P/13 21-Jun-13 20-Jul-13 20-Jul-13 232,014.50 us Company 30-Nov-14 119,459.70 Planned ‫مقترح‬ 1/ Construction of (almashkib) Works Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 Sabah 1-Aug-13 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS turn key WS system() - Taiz Foundation 77,778.18 Completed Actual ‫Ù?علي‬ P/13 21-Jul-13 21-Aug-13 21-Aug-13 8-Oct-13 204,725.00 us Construction 30-Nov-14 77,778.18 Planned ‫مقترح‬ 2/ Construction of (Asleef) turn Works Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 Sabah 1-Aug-13 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS key WS system - Taiz Foundation 73,123.73 Completed Actual ‫Ù?علي‬ P/13 21-Jul-13 21-Aug-13 21-Aug-13 8-Oct-13 157,961.00 us Construction 30-Nov-14 73,123.73 Planned ‫مقترح‬ 3/ Construction of (Mahoal Works Post NCB 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 Sabah 1-Aug-13 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS Alala'a) turn key WS system Foundation 80,163.87 Completed Actual ‫Ù?علي‬ P/13 - Taiz 21-Jul-13 21-Aug-13 21-Aug-13 8-Oct-13 166,966.00 us Construction 30-Nov-14 80,163.87 Planned ‫مقترح‬ 5-1/SAD Various Water & Sanitation Works Post NS 1-Aug-11 15-Aug-11 30-Aug-11 30-Aug-11 7-Sep-11 17-Sep-11 16-Nov-11 ‫عبدالقدوس علي‬ Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Civil Works falla in Saada Post NCB 15-May-12 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 10-Apr-14 16,135.05 Completed Actual ‫Ù?علي‬ 8-Jan-14 9-Feb-14 9-Feb-14 27-Mar-14 29,990.40 US ‫الغزي‬ 16,135.05 Planned ‫مقترح‬ *4/ HQ works ofBuildings in al mahra Works Post NCB 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 ‫مؤسسة التميمي‬ 18-Jul-14 174,930.70 Completed Actual ‫Ù?علي‬ 1-Feb-10 9-Apr-10 19-May-10 24-May-10 1-Jul-10 31-Jul-10 368,792.55 US $ 16,502.68 Planned ‫مقترح‬ 5-4/SAD Various Water & Sanitation Works Post NS 1-Aug-11 15-Aug-11 30-Aug-11 30-Aug-11 7-Sep-11 17-Sep-11 16-Nov-11 Completed and Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Civil Works Aldarb bani Post NCB 15-May-12 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 ‫مجمع الهاشمي‬ 10-Apr-14 the payment under Actual ‫Ù?علي‬ Aoier in Saada 8-Jan-14 9-Feb-14 9-Feb-14 14,701.90 US ‫التجاري‬ 12-Dec-14 processing Planned ‫مقترح‬ 4-11/ SAN Various Water & Sanitation Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Civil Works , algaraa, bani Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 45,198.60 Completed Revised2 shadad in Sanaa 21-Jun-12 5-Jul-12 5-Jul-12 15-Jul-12 31-Jul-12 29-Sep-12 Actual ‫Ù?علي‬ 27-Feb-11 3-Oct-12 9-Oct-12 9-Oct-12 30-Oct-12 ‫مكتب القائيÙ?ي‬ 12-Dec-14 28,858.03 5,771.61 Total cost of completed Works contracts 10,483,964.04 7,179,203.40 2,930,205.67 completed Planned ‫مقترح‬ 6/ HQ Civil Works of Emergency Works Post NCB 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ /CW/RWSS/WSSP/12 Rehabilitation of GARWSP 13-Apr-13 145,525.50 145,525.50 Actual ‫Ù?علي‬ HQ buildings in 8-May-12 10-Jun-12 10-Jun-12 15-Oct-12 291,731.00 us ‫مؤسسة النهضة‬ completed Planned ‫مقترح‬ 7/ HQ Civil Works of Emergency Works Post NCB 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ /CW/RWSS/WSSP/12 Sanaa branch’s buildings 21-Jan-14 20-Feb-14 20-Feb-14 17-Mar-14 1-Apr-14 6-Nov-15 Actual ‫Ù?علي‬ NA NA 3-Mar-14 9-Apr-14 9-Apr-14 3-Nov-14 NA 11-Nov-14 408,863.50 US Total cost of completed Works contracts 700,594.50 145,525.50 145,525.50 copmpleted Planned ‫مقترح‬ 4-14/ SAN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Qaid Al Malky 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works Alhamra in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 Sanaa- 24-Jun-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 25-Apr-11 13,317.76 US $ Yemen‫قائد المالكي‬ Completed Planned ‫مقترح‬ 4-5/ AMR Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alafry in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 2-May-11 Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 9,266.82 US $ Planned ‫مقترح‬ 3/ MAH Civil Works of tank of Beat Works Post NCB 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 Saleh Matar 9-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Alshoishy in Mahaweet Mahweet- 24-Sep-11 Actual ‫Ù?علي‬ 30-Jan-11 6-Feb-11 8-Mar-11 8-Mar-11 28-Mar-11 17-Apr-11 43,338.79 US $ Yemen ‫صالح‬ Planned ‫مقترح‬ Post NS 1-Aug-11 15-Aug-11 30-Aug-11 30-Aug-11 7-Sep-11 17-Sep-11 ‫عبد اهلل علي‬ 16-Nov-11 5-3/SAD Various Water & Sanitation Works Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Civil Works wadi kona in Post NCB 15-May-12 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 A. Al 10-Apr-14 Actual ‫Ù?علي‬ Saada 8-Jan-14 9-Feb-14 9-Feb-14 44,727.50 US Qumaly Planned ‫مقترح‬ 5-2/SAD Various Water & Sanitation Works Post NS 1-Aug-11 15-Aug-11 30-Aug-11 30-Aug-11 7-Sep-11 17-Sep-11 ‫مجمع الهاشمي‬ 16-Nov-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/14 Civil Works alkhashab & Post NCB 15-May-12 3-Aug-14 17-Aug-14 17-Aug-14 27-Aug-14 12-Sep-14 Al Hashmy 21-Nov-14 Actual ‫Ù?علي‬ Sahar Alkara in Saada 8-Nov-14 86,533.30 US -Trading Sada Planned ‫مقترح‬ 4-3/ AMR Various Water & Sanitation Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Qaid Al 30-Dec-10 Revised2 /CW/RWSS/WSSP/10 Civil Works Alsaoadeen in 3-Aug-14 17-Aug-14 17-Aug-14 27-Aug-14 12-Sep-14 Mohby 11-Nov-14 Actual ‫Ù?علي‬ Amran 15-Jan-11 3-Oct-14 15,331.78 US Amran- Planned ‫مقترح‬ 4-5/ HAJ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 Qaid Al 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works Shaleelh in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 Malky Sanaa- 2-Aug-11 Revised2 1-Apr-12 8-Sep-14 8-Oct-14 8-Oct-14 16-Oct-14 1-Nov-14 Yemen‫قائد‬ 24-May-15 Actual ‫Ù?علي‬ NA NA 16-10-2014 16-11-2014 16-11-2014 12-Jan-14 25-Dec-14 224,372.45 US ‫المالكي‬ Rashad ALhaj 16/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned 03/CW/RWSS/WSSP/ Construction of Various Water & Works Post NCB 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 09 Sanitation Civil Works Raba Post NS 1-Jan-11 N/A 8-Jan-11 7-Feb-11 15-Feb-11 3-Mar-11 1-Jun-11 Revised2 Masod in Haja 8-Jan-15 23-Jan-15 23-Jan-15 31-Jan-15 16-Feb-15 17-May-15 Actual 15-Jan-11 Planned ‫مقترح‬ 4-1/ HAJ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works bani gamal in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 8-Jan-15 8-Jan-15 7-Feb-15 7-Feb-15 15-Feb-15 3-Mar-15 2-May-15 Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4-2/ HAJ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works altowr in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 8-Jan-15 8-Jan-15 7-Feb-15 7-Feb-15 15-Feb-15 3-Mar-15 2-May-15 Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4-3/ HAJ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works bani Mshata'a in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 8-Jan-15 8-Jan-15 7-Feb-15 7-Feb-15 15-Feb-15 3-Mar-15 2-May-15 Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4-4/ HAJ Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works bani faeed in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 8-Jan-15 8-Jan-15 7-Feb-15 7-Feb-15 15-Feb-15 3-Mar-15 2-May-15 Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4-11/ SAN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works hara ala'atzaz, alareen, Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 Revised2 al-ladan,and alfars in Sanaa 8-Jan-15 22-Jan-15 22-Jan-15 1-Feb-15 17-Feb-15 18-Apr-15 Actual ‫Ù?علي‬ 27-Feb-11 Rashad ALhaj 17/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Planned ‫مقترح‬ 4-1/ ABN Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works alrhaba in Abyan Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Revised2 Post NS 8-Jan-15 22-Jan-15 22-Jan-15 1-Feb-15 17-Feb-15 18-Apr-15 Actual ‫Ù?علي‬ 20-Jan-11 Planned ‫مقترح‬ 4-1/ HAD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works that altareek-Tabk Hazar Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Revised2 in Moklla Post NS 8-Jan-15 22-Jan-15 22-Jan-15 1-Feb-15 17-Feb-15 18-Apr-15 Actual ‫Ù?علي‬ 20-Jan-11 Planned ‫مقترح‬ 4-1/ JWF Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫ متوقع‬/CW/RWSS/WSSP/10 Works in Al kharba al-jowf Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Revised2 8-Jan-15 22-Jan-15 22-Jan-15 1-Feb-15 17-Feb-15 18-Apr-15 Actual ‫Ù?علي‬ 20-Jan-11 Planned ‫مقترح‬ 4-1/ MAH Construction of schames in Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Shamhot Al-mahra Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 Revised2 Post NS 8-Jan-15 8-Jan-15 22-Jan-15 22-Jan-15 30-Jan-15 15-Feb-15 16-Apr-15 Actual ‫Ù?علي‬ 12-Jun-12 Planned ‫مقترح‬ 2/ Construction of schames for Works Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP (Bani Ali-Sahamar-Garf Almolad- 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ Habalat samara -Gamash- /14 Tabeeha-Ras Albalad) in Ibb Planned ‫مقترح‬ 2/ Construction of Garana in Works Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS Taiz 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ P/14 Planned ‫مقترح‬ 1/ Construction of Dalwan in Works Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ AMR/CW/RWSS/WSS Amran 8-Dec-14 7-Jan-15 7-Jan-15 1-Feb-15 16-Feb-15 Actual ‫Ù?علي‬ P/14 8-Dec-14 1-Jan-15 6-Jan-15 Planned ‫مقترح‬ 1/ Construction of Hawgeer Alshrah Works Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ LAH/CW/RWSS/WSS WS system in Lahjj 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ P/14 Planned ‫مقترح‬ 1/ Construction of (Bani Mansuor) Works Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ SAN/CW/RWSS/WSS WS system in Sanaa 8-Jan-15 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ P/14 Planned ‫مقترح‬ 1/ Construction of (Alkabah) turn Works Post NCB 21-Jun-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ HAJ/CW/RWSS/WSS key WS system - Haja 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ P/14 Planned ‫مقترح‬ 2/ Construction of (Alkharh bani Works Post NCB 21-Jun-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ SAN/CW/RWSS/WSS sowar) Turn key WS system - 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ Sana'a P/14 Planned ‫مقترح‬ 1/ Construction of (Nokhan) turn Works Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ SHB/CW/RWSS/WSS key WS system in Shabwa 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ P/14 Planned ‫مقترح‬ 2/ Construction of (Makhar) turn Works Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ SHB/CW/RWSS/WSS key WS system in Shabwa 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ P/14 Planned ‫مقترح‬ 1/ Construction of (Beet Aladeeb) Works Post NCB 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP turn key WS system in Ibb 8-Jan-15 7-Feb-15 7-Feb-15 4-Mar-15 19-Mar-15 Actual ‫Ù?علي‬ /14 Total cost of planned - - 436,888.40 - - - Works contracts Planned ‫مقترح‬ 4-2/ HAD Various Water & Sanitation Civil Works Post NCB 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works moshah in Saioon Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Revised2 Post NS 3-Aug-14 17-Aug-14 17-Aug-14 27-Aug-14 12-Sep-14 11-Nov-14 Actual ‫Ù?علي‬ 20-Jan-11 Canceled Planned ‫مقترح‬ 6/ Civil Works & Sanitation Works Post NCB 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 16-Apr-00 HAJ/CW/RWSS/WSS &Pumps-pipes(jabal al adbae) Revised ‫متوقع‬ in Hajah 21-Jun-13 21-Jul-13 21-Jul-13 15-Aug-13 30-Aug-13 28-Nov-13 Actual ‫Ù?علي‬ P/11 15-Apr-11 Canceled Rashad ALhaj 18/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Rashad ALhaj 19/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Rashad ALhaj 20/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Rashad ALhaj 21/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Rashad ALhaj 22/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Rashad ALhaj 23/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Rashad ALhaj 24/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Rashad ALhaj 25/35 Bank’s No Bank’s No Review Preparation Contract Objection to Bid Goods/ Objection to Name, City, and by Bank Method of of Bid Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract Completion of total Expenditure Package/ Reference No. Description of Goods Works/ Bidding Contract Value Currency No. Country of Contract (Date) incurred to Date Exp. From IDA share (Prior/ Selection Document (Date) (Date) (Date) Decision Report and Signed (Date) Contractor NCS Document Post) (Date) (Date) Contract Award (Date)** (Date)** Rashad ALhaj 26/35 Republic of Yemen Water Sector Support Program (WSSP) Consultancy services 2010 - 2016 In some contracts, one or more of these approvals may be ** Applicable in case of Bank's prior review contained in one Bank communication. Name, City, No No Objection by No Objection by and Country RFP Final Review Type of TOR/Shortlis No Objection Objection Proposal the Bank to the the Bank of SL Method Advertising Draft to be No Objection Services Expenses SL Package/ Reference by Bank Consultant t to be from Bank for from Bank RFP Issued Submission Technical (Technical/ Contract Contract Contract Contract Contractor No. Description of Services of for Short forwarded to from Bank for Completion Incurred No. No. (Prior/ (Firm/ Finalised Shortlist for Final (Date) Deadline Evaluation #Combined/ Draft Signed (Date) Value Currency No. (incl. Zip CS Selection listing (Date) the Bank TOR (Date)** (Date) to Date Post) Individual) (Date) (Date)** RFP (Date) Report Contract/ Final Code if US) (Date) (Date)** (Date)** Contract) (Date)** 35 ‫استشاري لتقييم تجربة الهيئة‬ ‫ومشروع المياه والصرÙ?‬ Prior Individual IC Planned 1-Aug-10 15-Aug-10 15-Sep-10 15-Sep-10 20-Sep-10 shoat term ‫الصحي الريÙ?ي‬ 2 01/G/RWSS/WSSP/10 17940.00 US$ Dr.Ali Qasam Sanaa Yemen 17940.00 Revised consultant for Assessment 19-Feb-11 GARWSP and RWSSP Actual Methods 24-Jul-10 25-Sep-10 NA 20-Dec-10 NA NA NA NA NA NA 21-Dec-10 19-Mar-11 27/35 Republic of Yemen Water Sector Support Program (WSSP) Plan of Capacity Building Activities (GARWSP) SL Estimated Completion No. Expected Outcome/ Activity Description Duration Start Date Date Comments Training of trainers to conduct courses on Social 2 2 weeks 15-Jun-11 02/28/2011 ‫تدريب مدربين للتحÙ?يز االجتماعي‬ 02/28/2011 Completed Mobilization. Training of trainers to conduct training courses in ‫تدريب مدربين لتدريب الÙ?روع‬ GARWSP Branches and upon request of otherr 06/01/2011 1 9 weeks 1-Jun-11 ‫والجهات االخرى‬ 06/01/2011 Completed stakeholders. Training courses in advance accounting for 5 13 Weeks 17-Jun-11 02/26/2011 ‫المحاسبة ÙˆÙ?قا للمعايير الدولية‬ 02/26/2011 Completed GARWSP Financial Staff. Advance couse in M&E and GARWSP staff ‫االساليب الحديثة Ù?ÙŠ المتابعة‬ 05/21/2011 7 performance assessment 11 Weeks 14-Aug-11 ‫وتقويم االداء‬ 05/21/2011 Completed Training course on the use of GIS in GARWSP ‫دورة تدريبية علمية متخصصة‬ 02/05/2011 8 interventions at thre field level. 9 Weeks 3-May-11 ‫Ù?ÙŠ نظم المعلومات الجغراÙ?ية‬ 02/05/2011 Completed 9 Advance Specialized course in Project Management 9 weeks 1-Jan-11 01/15/2011 ‫دورة احتراÙ?ية Ù?ÙŠ ادارة المشاريع‬ 01/15/2011 Completed Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 1 Projects ( IN Sana'a) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 2 Projects ( In Taiz) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة تعز‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 3 Projects ( In IBB) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة اب‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 4 Projects ( In Hodiedah) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة الحديد‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 5 Projects ( In Abyen) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة ابين‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 6 Projects ( In Hajah) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة حجة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 7 Projects ( In Dhamar) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة `ذمار‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 8 Projects ( In Lahj) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة لحج‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 9 Projects ( In al dhalea) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 10 Projects ( In Amran) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 11 Projects ( In Hadramout) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 12 Projects ( In Albaida) 1 weeks 15-Apr-15 ‫للمشاريع المياه البيضاء‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 13 Projects ( In Mareb) 1 weeks 15-Apr-15 ‫للمشاريع المياه مارب‬ Republic of Yemen Water Sector Support Program (WSSP) Plan of Capacity Building Activities (GARWSP) SL Estimated Completion No. Expected Outcome/ Activity Description Duration Start Date Date Comments Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 14 Projects ( In sa'ada) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة صعدة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 15 Projects ( In Raima) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة ريمة‬ ‫تحÙ?يز وتدريب اللجان المشغلة‬ Training of Operating committees of Rural Drinking ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ 16 Projects ( In Al mahweet) 1 weeks 15-Apr-15 ‫المحويت‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 17 Projects ( In Shapoa) 1 weeks 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة شبوة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 18 Projects ( In Al mahra'a) 1 weeks 15-Apr-15 ‫للمشاريع المياهÙ?ÙŠ محاÙ?ظة المهرة‬ ‫تحÙ?يز وتدريب اللجان المشغلة‬ Training of Operating committees of Rural Drinking ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ 19 Projects ( In al-jouf) 1 weeks 15-Apr-15 ‫الجوÙ?‬ Republic of Yemen Water Sector Support Program (WSSP) Plan of Capacity Building Activities (GARWSP) SL Estimated Completion No. Expected Outcome/ Activity Description Duration Start Date Date Comments Preparation and Printing of Training Materials ‫اعداد واخراج مواد التدريبية‬ pertinent to GARWSP mandate for conducting ‫تتواÙ?Ù‚ مع مهام وانشطه الهيئة‬ training courses both at central and GARWSP 1 21 Weeks 15-Apr-15 ‫للتدريب والÙ?روع واالخرين عليه‬ Branches. Advance course on updating electronic systems at ‫تقييم االنضمة االلكترونية(النظام‬ 3 GARWSP HQ 8 weeks 15-Apr-15 )‫ نظام السكرتاريه‬+ ‫المالي‬ ‫تنصيب االنظمة االلكترونية‬ Instalation of Electronic Systems in GARWSP )‫نظام السكرتارية‬+‫(النظام المالي‬ branches (FMS+ Folow up pocesses of applications) 4 6 Weeks 15-Apr-15 ‫Ù?ÙŠ الÙ?روع (ميداني‬ Prepare a manual on GARWSP approaches and ‫اعداد الكتاب الشامل لوتائق‬ 5 methodologies 28 Weeks 15-Apr-15 ‫منهجية الهيئة‬ Preapre materials and presentations to be used in ‫استعراض منهجية الهيئة للجهات‬ workshops in the water sector on the mandate of ‫االخرى‬ 6 GARWSP 20 Weeks 15-Apr-15 Evaluation of conducteed training programs( 2009- -2009 ‫تقييم الخطط التدريبية‬ 7 2010) ‫م‬2010 The estimated cost below covers both consultancy srevices and transport allowance and nutrition, residence for trainees Training of trainers for the training of Rural Drinking ‫تدريب مدربين لتدريب لجان‬ 3 Water Projects Committees 11weeks 3-Jun-12 24-Jul-12 ‫جمعيات المشاريع‬ Training course in Project manangement and ‫ادراة المشاريع ودراسة الجدوى‬ 6 physability studies. 15 Weeks 20-Jul-12 30-Oct-12 ‫(المÙ?اهيم والقضايا االجتماعية‬ 4 Training Courses in English language 15-Aug-15 Republic of Yemen Water Sector Support Program (WSSP) Plan of Capacity Building Activities (GARWSP) SL Estimated Completion No. Expected Outcome/ Activity Description Duration Start Date Date Comments Plan 2011 Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 1 Projects ( IN Sana'a) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 2 Projects ( In Taiz) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة تعز‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 4 Projects ( In Hodiedah) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة الحديد‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 8 Projects ( In Lahj) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة لحج‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 9 Projects ( In al dhalea) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 10 Projects ( In Amran) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 11 Projects ( In Hadramout) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 14 Projects ( In sa'ada) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة صعدة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 15 Projects ( In Raima) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة ريمة‬ Republic of Yemen Water Sector Support Program (WSSP) Plan of Capacity Building Activities (GARWSP) SL Estimated Completion No. Expected Outcome/ Activity Description Duration Start Date Date Comments Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 17 Projects ( In Shabwa) one week 15-Apr-15 ‫للمشاريع المياه Ù?ÙŠ محاÙ?ظة شبوة‬ Training of Operating committees of Rural Drinking ‫تحÙ?يز وتدريب اللجان المشغلة‬ 18 Projects ( In Al mahra'a) one week 15-Apr-15 ‫للمشاريع المياهÙ?ÙŠ محاÙ?ظة المهرة‬ Local training program for staff Training Subject Cost 0 Preparation of different operational manuals 13636 13636 0 English language training courses 13636 13636 0 Accounting (intl. standard) 28000 28000 0 Project management 28000 28000 0 Monitoring and evaluation 23455 23455 Republic of Yemen Water Sector Support Program (WSSP) Plan of Capacity Building Activities (GARWSP) SL Estimated Completion Expected No. Different courses Activity Outcome/ technical Description (Evaluation and Duration Start Date Date Comments installation of electonic systems, GIS systems and 0 profesional management 44180 44180 Training on plans and budgets preparation 9000 - Use of the new financial and accounting systems 18000 - Procurement procedures 18000 - Design and Selection of pumping units 42418 - Technical Supervision of wells drilling . 9000 - Using new software’s in designs of water systems 14455 - Water quality monitoring 9728 - Wells testing and logging 22545 - Use of GIS in wells data base 9000 - Wells drilling techniques 9000 - Design of water harvesting systems 13545 - Artificial Well recharging 9000 - Operation and maintenance of pumping units 9000 - Computer and software courses 16800 - Environmental impact assessment 9000 Charactarastics of Ground water and movement of underground water 9000 Cost of supervising and monitoring 13509 Total 391907 0 Total contracted Value Component Total allocated budget from IDA Total Planned cost* s Item Total contracted Value some contracts financed 7.6% and 20% from IDA , the Goods remaining contracts financed 100% from IDA 17,437,203 some contracts financed 7.6% and 20% from IDA , the Works 10,483,964 remaining contracts financed 100% from IDA W&G Emergency Finance 100% from IDA 1,133,122 Consultancy services Finance 100% from IDA 61,440 Training Operating Cost total 22,000,000 29,115,729 Includes other financers (GOY and EKN) **about USD 6,000,000 of this amount is under contracting processes Total contracted Value Total incurred from IDA Remaining Planned Unplanned amounts Cost** IDA share ALL IDA share 16,947,492 4,035,816 #REF! 4,525,526 6,447,482 7,179,203 2,930,206 #REF! #REF! 1,022,152 433,965 433,965 61,440 42,190 42,190 #REF! 16,124 16,124- 239,150 239,150- 12,056,601 24,602,850 7,697,450 #REF! #REF! g processes