The World Bank Report No: ISR15492 Implementation Status & Results Uruguay Strengthening Capacity for Improving Environmental Compliance and Promoting Cleaner Production in the Industrial Sector (P129749) 0 o Operation Name: Strengthening Capacity for Improving Environmental Project Stage: Implementation Seq.No: 2 Status: ARCHIVED Archive Date: 16-Aug-2014 Compliance and Promoting Cleaner Production in the (n Industrial Sector (P129749) 0 Country: Uruguay Approval FY: 2012 n Product Line: Institutional Development Fund Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: - Implementing Agency(ies): 0- Key Dates Board Approval Date 01-Mar-2012 Original Closing Date 12-Dec-2015 Planned Mid Term Review Date 22-Aug-2014 Last Archived ISR Date 20-Mar-2013 Effectiveness Date 12-Dec-2012 Revised Closing Date 12-Dec-2015 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from IDF Proposal) The overall development objective of this grant is to undertake activities that will seek to build capacity of the National Agency for Environment (DINAMA-Direccion Nacional de Medio Ambiente) to promote cleaner production, and improve environmental compliance inthe industrial sector (particularly in small and medium enterprises) in Uruguay. Has the Project Development Objective been changed since Board Approval of the Project? O Yes @ No Component(s) Component Name Component Cost Review Legal and Regulatory Framework for Strengthening Pollution Mgt and Env. Compliance 91480.00 Assess Institutional Needs for Better Pollution Control, and Improved M&E 81960.00 Build Technical Capacity within DINAMA and to Disseminate to the Industrial Sector 138380.00 > Audits 10000.00 0 o Review Legal and Regulatory Framework for Strengthening Pollution Mgt and Env. Compliance 91480.00 Assess Institutional Needs for Better Pollution Control, and Improved M&E 81960.00 o Build Technical Capacity within DINAMA and to Disseminate to the Industrial Sector 138380.00 T) Audits 10000.00 C., 25 Overall Ratings 0- Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Unsatisfactory Page 1 of 3 The World Bank Report No: ISR15492 Previous Rating Current Rating Overall Implementation Progress (IP) Moderately Satisfactory Moderately Unsatisfactory Overall Risk Rating Low Moderate 0 0 Implementation Status Overview (D b Grant Agreement was signed in December 2012. Executing agency (DINAMA) prepared Procurement Plan and the Bank has provided no objection to the plan and the first 3 o consultants which represent key personnel for the project. DINAMA has completed the process for consultant identification (formal announcement, etc.) for all 3 consultants and is 8 pending their final selection and contracting which is anticipated for July. DINAMA and the Bank have been discussing the other work and consultants associated with the project. 0 has initiated process to select first 3 consultants but they have still not been contracted. The associated Bank efforts on industrial pollution under the UY PA have helped formulate L) ideas and actions that can be used to implement the project. Locations No Location data has been entered Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Institutional Capacity Yes/No Value No No Yes Date 17-Dec-2012 13-Feb-2013 31 -Dec-2014 Comments Data on Financial Performance (as of 05-Jul-2013) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P129749 TF-12379 Effective 12-Dec-2012 12-Dec-2012 12-Dec-2012 12-Dec-2015 12-Dec-2015 Disbursements Q. Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed 0 O P129749 TF-12379 Effective USD 0.32 0.32 0.00 0.10 0.22 31.00 0 U Disbursement Graph Page 2 of 3 The World Bank Report No: ISR15492 - Original ---- Formally Revised -- Actual 0.12 - 0 i 0.08- L8 % 3 0.04- nK CC 0.02- 0- rq M Tr Tr M M -O rN N N N N N N N N Key Decisions Regarding Implementation None Restructuring History There has been no restructuring to date. Related Projects There are no related projects. 0. C C r-) n o Pae3o0